Full page fax print - Welcome to Western Regional Power ...wrpc.gov.in/wrpc/10wrpc_agenda.pdfmeeting...

51

Transcript of Full page fax print - Welcome to Western Regional Power ...wrpc.gov.in/wrpc/10wrpc_agenda.pdfmeeting...

Board Members1. Chairman, WRPC & GSECL, Vadodara.2. Member (GO&D), CEA, New Delhi3. Managing Director, CSPTCL, Raipur.4. Managing Director, CSPDCL, Raipur.5. Managing Director, CSPGCL, Raipur.6. Chief Engineer (LD), SLDC, Bhilai.7. Managing Director, GETCO, Vadodara.8. Managing Director, PGVCL, Rajkot.9. Chief Engineer (LD), SLDC, Vadodara.10. Chairman & Managing Director, MPPTCL, Jabalpur.11. Chairman & Managing Director, MPPGCL, Jabalpur.12. Chairman & Managing Director, MP PKVVCL, Indore.13. OSD(LD), SLDC, Jabalpur.14. Managing Director, MSETCL, Mumbai.15. Managing Director, MSEGCL, Mumbai.16. Managing Director, MSEDCL, Mumbai.17. Chief Engineer (LD), SLDC, Kalwa.18. Chief Electrical Engineer, Govt.of Goa, Goa19. Director (Comml.), NTPC Ltd., New Delhi.20. Director (Operation), PGCIL, Gurgaon.21. Director (Operation), NPCIL, Mumbai.22. Secretary(P), UT of Daman & Diu, Moti Daman.23. Secretary(P), UT of DNH, Silvassa.24. Executive Director, NLDC, New Delhi.25. Executive Director, WRLDC, Mumbai.26. Executive Director, Tata Power Company, Mumbai.27. Managing Director, RGPPL, Noida 28. Chief Executive Director, NHDC, Bhopal.29. Member (Power), NCA, Indore.30. Director, Essar Power Ltd, Surat31. Director, PTC India Ltd., New Delhi.32. General Manager, BEST, Mumbai.33. Member Secretary, WRPC, Mumbai

Special Invitees :1. Member (Power System), CEA, New Delhi.2. Managing Director, MSEBHCL, Mumbai3. Chairman & Managing Director, MP Tradeco, Jabalpur.4. Managing Director, CSPHCL, Raipur.5. Managing Director, GUVNL, Vadodara.

Copy to :1. Executive Director, CSPGCL, Raipur.2. Chief Engineer (Comml.), CSPDCL, Raipur.3. Managing Director, GSECL, Vadodara.4. Chief Engineer (R & C), GETCO, Vadodara.5. General Manager (Comml.), GUVNL, Vadodara.6. Executive Director (O&M-Gen), MPPGCL, Jabalpur.7. Executive Director (L & RA), MP TradCo, Jabalpur.8. Director (Operation), MSETCL, Mumbai.9. Director (Operation), MSEGCL, Mumbai.10. Director (Operation), MSEDCL, Mumbai.11. Chief Engineer (PP), MSEDCL, Mumbai.12. Chief Engineer (GM), CEA, New Delhi.13. Chief Engineer (Trans), NPCIL, Mumbai.14. Regional Executive Director, WRHQ, Mumbai.15. Executive Director (Comml.), NTPC Ltd., New Delhi.16. Executive Director (Comml), PGCIL, Gurgaon.17. Executive Director, WRTS-I, Nagpur.18. Executive Director, WRTS-II, Vadodara.19. Executive Engineer, DD, 20. Executive Engineer, DNH, 21. Executive Vice President, PTC India Ltd., New Delhi.22. General Manager (Power), RGPPL, Noida 23. Chief Engineer (Regulatory & Comml), BEST , Mumbai.24. General Manager, NHDC, 25. Sr. General Manager, Tata Power Company, Mumbai.26. Sr. Vice President, Essar Power Ltd, Surat27. Member Secretary, ERPC, Kolkata.28. Member Secretary, SRPC, Bangalore.29. Member Secretary, NERPC, Shillong.30. Member Secretary, NRPC, New Delhi.

Baart sarkar Government of India kond`Iya ivaVut p`aiQakrNa

Central Electricity Authority piScama xao~Iya ivaVut saimait

Western Regional Power Committee

œ¸®¸½¢¨¸¬¸ ˆÅú ¢™›¸¸¿ˆÅ 30 ma[- 2009 ˆÅ¸½ dIva Ÿ¸½¿ ‚¸¡¸¸½¢�¸÷¸ 10 ¨¸ì ¤¸¾“ˆÅ ˆÅú ˆÅ¸¡¸Ä¬¸»�¸ú

AGENDA NOTES OF 10TH MEETING OF WRPC

TO BE HELD ON 30TH MAY 2009 AT DIU

Ÿ¸º¿¤¸ƒÄ MUMBAI

Agenda Notes of 10th WRPC meeting to be held on 30th May 09

C O N T E N T S Item No. Particulars

Page No.

ITEMS FOR DISCUSSION

ITEM No.1 CONFIRMATION OF THE MINUTES OF THE 9th MEETING OF WRP COMMITTEE

1

ITEM No.2 LTSA ARRANGEMENT FOR SCADA/EMS UNDER WR ULDC SCHEME

1

ITEM No.3 TRANSMISSION SYSTEM ASSOCIATED WITH THE TILAIYA ULTRA MEGA POWER PROJECT (4000 MW), IN JHARKHAND, NABINAGAR (1000MW) OF RAILWAYS AND NTPC, BARH-II (1320 MW), RIHAND-III (1000MW), VINDHYACHAL-IV (1000MW) AND MAUDA (1000MW) OF NTPC, AND IPPS IN JHARKHAND, ORISSA, MP, CHATTISGARH, AND MAHARASHTRA

3

ITEM No.4 TRANSMISSION SYSTEM CONNECTED WITH VINDHYACHAL POOLLING STATION AND PHASING OF TRANSMISSION WORK

5

ITEM No.5 ALLOTMENT OF TRANSMISSION CAPACITY TO IPPs AGAINST THEIR APPLICATION FOR AVAILING LTOA

6

ITEM No.6 PERFORMANCE OF WR GRID DURING JAN. 09 TO APR. 09

9

ITEM No.7 WIDE AREA MANAGEMENT SYSTEM OF WR

11

ITEM No.8 BILLING OF TRANSMISSION CHARGES FOR WHEELING OF CENTRAL SECTOR POWER TO UT OF DD, DNH & GOA

12

ITEM No.9 RENOVATION AND MODERNISATION OF WRPC OFFICE BUILDING 13

ITEMS FOR INFORMATION

ITEM No.10 PAYMENT OF TRANSMISSION CHARGES FOR INTER-STATE TRANSMISSION

14

ITEM No.11 COMPUTATION OF PAYMENT OF CAPACITY CHARGES FOR THERMAL GENERATING STATION

14

ITEM No.12 IMPLEMENTATION OF REVISED UI CHARGES W.E.F. 01.04.09 15

ITEM No.13 SHIFTING OF SLDC BHILAI TO RAIPUR 17

ITEM No.14 COMMISSIONING OF TRANSMISSION LINES AND GENERATING UNITS

18

Agenda Notes of 10th WRPC meeting to be held on 30th May 09

ITEM No.15 ONGOING TRANSMISSION SCHEMES IN WESTERN REGION 19

ITEM No.16 ONGOING GENERATION SCHEMES IN WESTERN REGION 20

ITEM No.17 ANTICIPATED POWER SUPPLY POSITION IN WESTERN REGION FOR THE PERIOD FROM JUNE 09 TO AUG. 09.

20

ITEM No.18 PAYMENT OF UI AND REACTIVE ENERGY CHARGES 21

ITEM No.19 PROVISION OF 400 kV FEED TO UNION TERRITORY OF DAMAN & DIU.

22

ITEM No.20 CONTRIBUTION TOWARDS INCIDENTAL EXPENSES FOR VARIOUS MEETINGS ETC.

22

ITEM No.21 ANY OTHER ITEM WITH PERMISSION OF CHAIR 23

ITEM No.22 DATE AND VENUE OF NEXT WRPC MEETING 23

Agenda Notes of 10th WRPC meeting to be held on 30th May 09

ANNEXURES

Annexure

Particulars

Annexure-1 MPPTCL letter dated 17.02.09

Annexure-3 Transmission system associated with the Tilaiya UMPP (4000 MW), Nabinagar (1000MW), Barh-II (1320 MW), Rihand-III (1000MW), Vindhyachal-IV (1000MW) and Mauda (1000MW), and IPPs in Jharkhand, Orissa, M.P., Chattisgarh and Maharashtra

Annexure-6.1(a) Frequency particulars of Western Region for the period from January 2009 to April 2009

Annexure-6.1(b) Power supply position in WR for the period from January 2009 to April 2009

Annexure-6.2 Voltages at the important 400/765 kV substations during the period from January 2009 to April 2009

Annexure-7 WRLDC vide letter dated 7th May 2009

Annexure-15 Progress of transmission lines under construction in Western Region

Annexure-16 Ongoing generation schemes in WR both under State as well as Central Sector in Western Region

Annexure-17 Anticipated power scenario in WR for the period June 2009 to August 2009

Annexure-19 WRTS-II, PGCIL letter dated 14th May 2009 regarding provision of 400 kV feed to UT of Daman & Diu.

Annexure-20 Details of members of WRP Committee that will contribute Rs. 50,000/- each towards the Board Fund for the year 2009-10

AGENDA NOTES FOR 10th MEETING OF WESTERN REGIONAL POWER COMMITTEE TO

BE HELD ON 30TH MAY 2009 AT DIU

ITEMS FOR DISCUSSIONS

ITEM No.1: CONFIRMATION OF THE MINUTES OF THE 9th MEETING OF WRP

COMMITTEE Minutes of 9th meeting of WRP Committee held on 9th January 2009 at Lonavala

were sent to the members vide letter No. WRPC/Minutes/AS/2008-09-1218 dated 3rd

Feb. 2009.

Comments have been received from ED, MPPTCL (emclosed at Annexure-1) on

Item No. 4.5 “Transmission System for evacuation power from Krishnapattam UMPP

and requirement for additional transmission capacity between SR – WR”. MPPTCL

have proposed the following amendment in last 4 lines of Para 4.5, Page –15 :

“ WR Constituents agreed to share only 25% transmission charges” may be replaced

by “WR Constituents (except Madhya Pradesh & Chhattisgarh) agreed to share only

25% transmission charges”.

WRP Committee may like to discuss and confirm the minutes.

ITEM No. 2: LTSA ARRANGEMENT FOR SCADA/EMS UNDER WR ULDC SCHEME

2.1 In the 8th meeting of WRPC held on 12th September 2008, WRLDC had

intimated that ULDC project was under extended AMC period upto 31.05.2009 and

stressed the need for going in for a comprehensive Long term Service agreement

(LTSA). In this connection, it was informed to the Committee that M/s GE had

submitted their offer to take up AMC which broadly covered the scope of

SCADA/EMS/DTS software as well as hardware at ten control centers

commissioned under the ULDC project. The WRP Committee discussed the matter

and opined that ULDC/SCADA O&M committee may discuss and negotiate the cost

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 1

with M/s GE and also examine the alternative options and the outcome of the above

meeting should be placed before WRP Committee for consideration and approval.

2.2 Based on the feedback given by WRLDC the matter was further deliberated

by the TCC in the meeting held on 15th January 2009 and further deliberated during

the 9th meeting of WRPC held on 16th January 2009. The WRP Committee agreed to

the recommendation of the TCC that (i) Negotiation Committee being nominated by

PGCIL may negotiate the cost with M/s GE to a reasonable acceptable level and

(ii) alternatively, PGCIL may go for inviting quotation etc. on limited bidding and

formulate the specification. However, while formulating the specification by

WRLDC/PGCIL, views of SLDCs may also be taken care of. The WRP Committee

felt that it would be preferable to include five years support as a part of procurement,

considering the present scenario. After discussions, it was felt that latest features

like integration of PMUs, better GUI could be specified and the replacement system

should be evergreen with the vendor providing the latest updates. It was also

agreed that WR constituents would be associated while finalizing the technical

specifications.

2.3 In this context WRLDC vide letter dated 7th May 2009 intimated the following:

(i) As per the directive of WRPC Negotiation process with GE was initiated.

Three Negotiation Committees viz., one of WR constituents, other

POWERGRID Negotiation Committee followed by Senior level

POWERGRID Negotiation Committee held comprehensive negotiations

with M/s.GE, the original equipment manufacturer (OEM) of WR

SCADA/EMS systems. The initial price quoted by M/s.GE was Rs.46.14

crores which was brought down to Rs.32.5 crores after three

negotiations.

(ii) In respect of alternative arrangement suggested by WRPC a proposal

was received from M/s. OSI, however the same has many issues like

IPR, OSI not being the OEM and absence of competitive bidding. Based

on the experience of all other RLDCs, it is felt that OEM would be the

best option.

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 2

(iii) The extended AMC is to end on 31.05.2009, it is proposed that

maintenance be got done through M/s GE, the Original Equipment

Manufacturer in light of the above, considering all the related aspects to

ensure interrupt-free operation of the SCADA/EMS functionality at all the

Control Centers in WR.

WRP Committee may discuss and finalise further course of action.

ITEM No.3: TRANSMISSION SYSTEM ASSOCIATED WITH THE TILAIYA ULTRA MEGA POWER PROJECT (4000 MW) IN JHARKHAND, NABINAGAR (1000MW) OF RAILWAYS AND NTPC, BARH-II (1320 MW), RIHAND-III (1000MW), VINDHYACHAL-IV (1000MW) AND MAUDA (1000MW) OF NTPC, AND IPPS IN JHARKHAND, ORISSA, MP, CHATTISGARH AND MAHARASHTRA

3.1 The 28th meeting of the Standing Committee on Power System Planning in

WR was held at Aurangabad on 6th December 2008. In the meeting transmission

system associated with Tilaiya Ultra Mega Power Project (4000 MW) in Jharkhand,

Nabinagar (1000 MW) of Railways and NTPC, Barh-II (1320 MW), Rihand-III (1000

MW), Vindhyachal-IV (1000 MW) and Mauda (1000 MW) of NTPC, and IPPs in

Jharkhand, Orissa, MP, Chhattisgarh, and Maharashtra were discussed and

identified. The transmission scheme were identified in four groups, viz. (i) generation

specific, (ii) system strengthening common for WR and NR, (iii) system

strengthening for WR and (iv) pooling stations for IPPs in Orissa. Also, proposal for

sharing of transmission charges had been discussed and recommended in the

above Standing Committee Meeting.

Recommendations of the Standing Committee were discussed in detail during 9th

meeting of WRP Committee held on 16th January 2009. Some of the members

expressed that the minutes of Standing Committee Meeting were received only few

days earlier and they needed time to examine the same. After discussions, it was

decided that :

(i) The constituents will furnish their comments on the minutes of

28th Standing Committee Meeting on power system planning in WR to

CEA at the earliest.

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 3

(ii) The constituents if so desire may seek any clarification from CEA and

communicate their views to them.

(iii) CEA will convey a meeting to discuss and finalize the transmission

scheme and in case, the clearance is given, by the constituents of WR to

the same, the matter will not again put up to WRPC for its approval.

3.2 Subsequent to the decision taken in 9th WRPC meeting, comments were sent

to CEA by CSEB, MPTRANSCO and MAHATRANSCO. CEA accordingly clarified

the matter in a Special Meeting of the Standing Committee on Power System

Planning of WR was held on 18th April 2009. Member (PS), CEA in the meeting

stressed that the proposal circulated in the agenda for the 9th WRPC meeting

identifying the transmission scheme etc. was basically a sort of master plan for

evacuation of power from various IPPs and other projects anticipated in the same

time frame.

Further, as desired by MAHATRANSCO in their comments, PGCIL made a

presentation indicating how the transmission charges would vary with the

commissioning of System strengthening for WR and System strengthening common

for WR and NR and its impact on pooled transmission charges. Members desired

that the details of the calculations and the assumptions made should be circulated to

the various constituents of the WR along with the calculation of corresponding

transmission charges of NR which is likely to share the capacity of the project(s).

CSEB representative suggested that only one Rourkela-Raigarh 400 kV D/c line be

LILOed at Jharsurgada instead of all the 4 circuits, as proposed in the 28th SCM. It

was explained by Member(PS), CEA that LILO of all the 4 circuits is a temporary

arrangement, and once the Jharsurgada-Dharamjaygarh-Jabalpur link is available,

LILO of one D/c will be removed at Jharsurgada.

The detailed transmission scheme as decided in the 28th meeting of the Standing

Committee on Power System Planning in WR held at Aurangabad on 6th December

2008 and subsequent modification therein suggested by PGCIL in name of pooling

station etc. during Special Meeting of the Standing Committee on Power System

Planning of WR held on 18th April 2009 is enclosed at Annexure- 3. The actual

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 4

programme with each of the projects once finalized would be brought forth in the

SCM.

The matter was discussed in detail in the Special Meeting of the Standing Committee on Power System Planning of WR held on 18th April 2009 and all the constituents agreed with the proposal. WRP Committee may kindly note the same.

ITEM No.4: TRANSMISSION SYSTEM CONNECTED WITH VINDHYACHAL POOLLING STATION AND PHASING OF TRANSMISSION WORK

During the Special meeting of Standing Committee on Power system Planning of

WR held on 18th April 2009 at WRPC office, Mumbai, CEA stated that Vindhyachal-

IV, Rihand-III and Aryan Coal were presently proposed to be connected to 765/400

kV Vindhyachal pooling station. As the generators would be coming in different time

frame, the transmission system from Vindhyachal pool onwards up to Gwalior would

need to be initially operated at 400 kV to avoid reactive power management problem.

Therefore, CEA suggested the following phasing of transmission system

interconnected from Vindhyachal pool.

(i) When the initial unit at Vindhyachal stage-III and Rihand-III generation are

commissioned they could be connected to Vindhyachal Pooling point and

the Vindyachal Pooling-Satna-Gwalior 765 kV link is charged at 400 kV

level.

(ii) In this time frame few units at Sasan would only be commissioned and

there would not be any short circuit level problems at Vindhachal 400 kV

generating bus due to LILO of Vindhyachal- Jabalpur 400 kV D/C at

Sasan.

(iii) When the entire planned generating stations connected to Vindhyachal

pooling station are commissioned, at that stage the Vindyachal Pooling-

Satna-Gwalior link can be charged at 765 kV level along with

interconnection of Sasan-Vindyhachal 765 kV S/C.

(iv) After charging at 765 kV level the LILO of Vindhyachal – Jabalpur 400 kV

D/C line at Sasan could be disconnected with suitable switching

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 5

arrangements at Sasan 400 kV switchyard to meet its starting power

requirements in future.

The above was agreed to and it was also decided that for implementation the

following works could be taken up as a separate project associated with

Vindhyachal-IV and Rihand-III.

Transmission System associated with Vindhyachal-IV and Rihand-III A. Generation Specific Transmission System

Rihand-IV (1000MW)

• Rihand-Vindyachal pooling 2xS/C 765kV lines operated at 400kV (

under preview of NTPC)

Vindhyachal-IV (1000MW)

• Vindhyachal-IV – Vindhyachal pooling 400kV quad D/C line (under

preview of NTPC)

B. System strengthening common for WR and NR

• Vindhyacal pooling station with 2x1500MVA 765/400kV (initially to be

a switching station at 400 kV level)

• Vindhyachal pooling-Satna 2XS/C 765kV lines ( initially to be

operated at 400 kV)

• Satna-Gwalior 765kV 2XS/C ( initially to be operated at 400 kV)

• Vindhyachal-Sasan 765 kV S/C

WRP Committee may like to note. ITEM NO. 5: ALLOTMENT OF TRANSMISSION CAPACITY TO IPPs AGAINST

THEIR APPLICATION FOR AVAILING LTOA 5.1 In the context of Long Term Open Access meeting held at Aurangabad in

Dec.’08, CSEB vide letter No. CSEB/MIC/WRPC/ 3254 dated 16th Dec. 2008 had

raised certain issues concerning processing of applications in respect of Long Term

Open Access (LTOA) viz. (i) there seems to be no set criteria and qualification for

selection of IPPs from the lot for granting LTOA from the margin available with

existing transmission capacity of the transmission network in service, (ii) existing

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 6

margin in the transmission capacity is to accommodate the increased power flow of

the existing beneficiaries and is utilized by them for meeting the seasonal peak

demands and (iii) the IPPs who are allotted LTOA in the existing transmission

capacity would have to pay much less than IPPs who would avail LTOA in new

transmission system. CSEB therefore desired that the issue needs to be deliberated

by WRPC.

5.2 The matter was deliberated in the TCC meeting held on 15th January 2009

and recommended as under:

(i) CTU should circulate a paper to the constituents of WR on the criteria,

procedure etc. being followed by them in processing of application for

granting of Long Term Open Access.

(ii) A meeting should be convened by PGCIL by first week of Feb. 2009 to

discuss the above issues on LTOA.

(iii) It was suggested that LTOA meeting may be separately held well

before Standing Committee meeting on Power system Planning of WR.

After detailed deliberations, the WRP Committee in its 9th meeting held on 16th Jan.

2009 decided that PGCIL would circulate a base paper on procedure for granting of

LTOA to all the beneficiaries within a week. All constitutes will give their comments to

PGCIL within a month and thereafter PGCIL will arrange a meeting to discuss the

same and formulate the guidelines. PGCIL agreed to the same.

5.3 Accordingly, General Manager (Engg), PGCIL vide letter dated 23rd Feb. 2009

circulated a base paper on procedure for granting of LTOA to all the beneficiaries.

Subsequently, in a Special Meeting of the Standing Committee on Power System

Planning of WR held on 18th April 2009, PGCIL made presentation regarding the

methodology, procedure and the payment security mechanism being adopted by

them for grant of Long Term Open Access.

5.3.1 PGCIL clarified that grant of LTOA was being done in four stages. In the first

stage discussion were held with the IPPs regarding achieving of various milestones

viz. acquisition of land, allocation of coal and water, environment clearance,

placement of orders for equipment, payment of advance to manufacturers, EPC

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 7

contractors etc., and only after some progress was noted and after observing the

progress of project take off, further discussion were held with the IPPs and grant of

LTOA was considered. In the second stage discussions with IPPs and beneficiaries

were undertaken in the SCM and LTOA meetings. The third and fourth stage was

security mechanism like Bank Guarantee from IPPs along with signing of BPTA and

6 months advance transmission charges corresponding to the capacity for which

PPA had not been signed by the IPP with beneficiary states(s). Regarding time

frame for granting LTOA, PGCIL informed that as per draft open access regulations

the nodal agency was required to dispose of the application for connectivity within 60

days and norms for medium term open access were even stringent and suggested

holding of SCM meetings every two months.

5.3.2 Member (PS), CEA clarified that as per the Electricity Act 2003 and the

existing regulation non-discriminatory open access had to be granted in case

existing margins were available. In case the existing transmission margins were not

adequate for grant of LTOA, additional transmission lines were being planned and

built. The transmission capacity was for the beneficiaries and was not allocated to

the generators. As and when the allocation from the generator would get finalized

and the beneficiary signs BPTA with the CTU then the transmission capacity would

get allocated to the beneficiary. Many of the IPPs were indicating target beneficiaries

because the distribution/transmission licensees could procure their power

requirements only through competitive bidding process and this process was not

moving fast. To facilitate IPPs, the above methodology was being adopted. In case

of Merchant Power Plants if the actual sale of power was different from the one

indicated and for which open access had been granted then as per present

regulations, in addition to long term open access charges, short term open access

charges would also be applicable. Regarding planning of transmission system CEA

further clarified that planning of transmission was being done considering various

perspective load generation scenarios during different periods of the year and

transmission was being planned considering the worst case scenario.

CEA also clarified that any transmission capacity built and not allocated to any

agency on long term basis would be allocated to other agency on medium term or

short term basis. In the event there is a delay in commissioning of any IPP, the long

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 8

term transmission capacity granted to it would be made available to any other

generator coming up in the time frame and the additional transmission required for

the delayed IPP would be built to match with its commissioning so that unutilized

transmission capacity is not built up and the Transmission companies are not

unnecessary burdened with additional transmission charges. The transmission

system would be optimal to take care of the requirement meeting the planning

criteria.

WRP Committee may like to note. ITEM No.6: PERFORMANCE OF WR GRID DURING JAN. 09 TO APR. 09 6.1 SYSTEM PERFORMANCE During the period January 2009 to April 2009, the grid operated in the frequency

range of 49.0 Hz to 50.5 Hz for 96.67% of time. The percentage time when

frequency was within this range varied between 94.15% to 98.08%. During this

period, frequency remained below 49.0 Hz for 3.20% of time. From 1st April 2009,

CERC has amended the permissible frequency range for system operation to 49.2

Hz – 50.3 Hz. During the month of April 2009, grid frequency remained in the

revised frequency band for 80.93 % time and it remained below 49.2 Hz for 18.75%

of time. The frequency profile during the period was generally satisfactory except on

a few days in February,2009 and April,2009, when drawal by NR and ER increased

due to sudden weather changes / generating unit outages. The comfortable system

performance during most of the period was due to marginal drop in unrestricted

demand as compared to last year and improved availability due to synchronization of

new generating units at Sugen, NSPCL-Bhilai, Sipat and Trombay. The details of

frequency profile during the period from January 2009 to April 2009 are furnished at

Annexure 6.1(a).

The unrestricted demand of Western Region during the period varied between

35300MW to 37400 MW. The corresponding figures for the previous year were

between 38640MW to 39800 MW. The maximum demand met during the period

was 31608 MW and the region faced capacity shortage in the range of 5300 MW to

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 9

6400 MW. The details of Unrestricted Demand vs. Demand Met and Energy

Requirement vs. Availability are furnished at Annexure.6.1 (b).

WRP Committee may like to note.

6.2 Voltage Profile 6.2.1 The month wise detail of voltages at 400 kV and 765 kV sub-stations during

the month of January,2009 to April,2009 is placed at Annexure 6.2. During the

period low voltage was observed at Karad 400 kV touching to 320 kV on 12.01.2009

and at Sipat and Seoni 765 kV voltages touched 726 & 720 respectively on few

occasions.

High voltage was recorded at 400 kV throughout the period at Dhule, Itarsi and

Karad S/s in the order of 428 kV to 438 kV. To contain high voltages WRLDC had to

resort to opening of 5 to 6 lines on many days. In order to control incidences of high

voltages during low load periods, installation of reactors at following locations has

been planned by various utilities:-

Sl.No. 400 kV Substation

Size (MVAR)

Implementing Agency

Expected Commissioning date

1. Khandwa 1x125 PGCIL June,2010 2. Dhule 2x50 MSETCL Oct.,2009 / Dec.,2009 3. Dehgam 1x125 PGCIL June,2010 4. Kasor 1x125 GETCO November,2009 5. Karad 1x80 MSETCL May,2009 6. Nardipur 1x80 GETCO October,2009

All the concerned utilities may indicate further progress made and expected date of

installation and commissioning of reactors at the above locations. They are also

requested to ensure timely commissioning of these reactors as this would help in

smoothening of high voltage profile in Western Regional Grid.

6.2.2 The issue regarding high voltage in Dhule area was discussed in the 8th & 9th

meetings of WRPC. In the 8th meeting of WRPC held on 12th September,2008,

PGCIL was requested to conduct studies for installation of reactors at Nagda or

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 10

Rajgarh. During the 9th meeting of WRPC held on 16th January,2009, it was

intimated that the study carried out by PGCIL indicated that after commissioning of

all the reactors, that are under implementation, voltage at Rajgarh, Nagda and Dhule

remain at 410, 405 & 410 kV respectively. It was therefore suggested that to contain

high voltage, efforts might be made by the respective utilities to install the bus

reactors already planned at various 400 kV sub-stations expeditiously. It was

further suggested that at the same time other means of voltage control like switching

off shunt capacitors during lean hours, setting of transformer taps etc. should also be

explored.

6.2.3 The TCC in its meeting on 15th January,2009 observed that even after taking

all other actions, including opening of a number of lines, high voltage problem was

still persisting. PGCIL was therefore requested to carry out fresh studies to examine

the requirement of bus reactor around 400 kV Nagda / Rajgarh sub-station.

6.2.4 The matter was further discussed in the special meeting of the Standing

Committee on Power System Planning in Western Region held on 18th April,2009.

In this meeting, PGCIL intimated that according to studies carried out by them,

installation of 1 X 125 MVAR bus reactor at Nagda / Rajgarh would be beneficial to

control over voltages. After examining various options, installation of 1 x 125 MVAR

bus reactor at Rajgarh sub-station was agreed to.

WRP Committee may kindly note. ITEM No.7: WIDE AREA MANAGEMENT SYSTEM OF WR WRLDC vide letter dated 7th May 2009 (enclosed at Annexure- 7) stated that the

existing SCADA / EMS provides the data which are steady state in nature and not

suitable for dynamic monitoring and control of Grid due to high degree of latency of

telemeter data and also non-synchronization of sampling of data. Emerging

technologies like Wide Area Measurement System (WAMS) using Phasor

measurement Unit (PMU) provide more advanced measurement system that will

utilize synchronized measurements from geographically distant locations and

increase the situational awareness by monitoring a wide area of power system in

real time.

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 11

In this regard WRLDC intimated that TCS has approached PGCIL to join the

consortium team of TCS, IIT Bombay and Tata Power for executing a PMU based

project which has been approved by Council of Scientific and Industrial Research

(CSIR) of Department of Science & Technology, Government of India, under the

NMITLI (New Millennium India Technology Leadership Initiative) program. CSIR will

provide Loan for the project. The main features of the project are as follows:

(i) Installation of PMUs (Phasor Measurement Units) at around 25 to 30

locations in Western Region Grid. The data from PMUs shall be acquired

at Western Regional Load Despatch Centre (WRLDC)

(ii) Development of software functions using PMU data.

WRLDC intimated that the PGCIL share of total estimated cost of the project is Rs.

8.76 crores. The loan from CSIR is to be repaid over 10 years at an interest rate of

3% after completion of the project. The annual installments shall be ranging from Rs.

90.267 lakhs to Rs. 127.01 lakhs. WRLDC further informed that a Pilot Project for

implementation of PMUs in Northern Region has been agreed upon in Northern

Region during the last NRPC meeting held on 22.04.2009.

WRLDC have proposed that the PMU project in respect of Western Region could be

funded through UI CAP fund or Additional UI funds. Alternatively the constituent may

finance the project and make yearly advance payment to POWERGRID.

WRP Committee may discuss and decide. ITEM No. 8: BILLING OF TRANSMISSION CHARGES FOR WHEELING OF

CENTRAL SECTOR POWER TO UT OF DD, DNH & GOA WRTS-I, PGCIL during 52nd meeting of Commercial Committee held on 9th April

2009, intimated that Service Tax Cell of Central Board of Excise and Customs have

issued summons for furnishing data regarding Service Tax recovery. PGCIL

therefore felt that collection of wheeling charges by POWERGRID for

MSETCL/MSEDCL and GETCO/GUVNL may have to be discontinued from April

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 12

2009 and the concern transmission companies viz. GETCO and MSETCL can take

up the billing/collection from April 2009.

In the CCM, it was pointed out that the decision of pooling of wheeling charges in

PGCIL bill was taken in WRE board meeting. Further, the matter regarding fixation

of and adjudication of the transmission charges of GETCO system used for

transmission of Central Sector power to DD/DNH is under consideration of Hon’ble

CERC and is scheduled for hearing shortly. As such, constituents of WR stressed

that till such time any order is given by CERC, the present methodology of billing of

transmission charges for wheeling of central sector power to DD & DNH and Goa

should be continued. This would facilitate the adjustment/recovery of any

transmission charges, as the entire record and billing details are available with

PGCIL.

WRP Committee may like to discuss. ITEM No. 9:RENOVATION AND MODERNISATION OF WRPC OFFICE BUILDING WRPC office building is around 30 years old and is in urgent need of major repairs.

The building also need architectural renovation and improvement in facilities such as

conference Hall, guest house etc. It is proposed that cost of R&M be shared by the

Member of WRPC who are sharing the establishment expenditure of WRPC

Secretariat. Further, the agency for carrying out these works need to be decided. It

is proposed that assistance from one of the Members of WRPC may be availed to

get the R&M work done on deposit basis.

As per the preliminary estimate, the complete R&M of the building is estimated to

cost about 3.5 crores. The detailed estimate of R&M can be finalized after

finalisation of the executing agency.

It is requested that WRPC may accord in principle approval for sharing the cost of

R&M. The actual cost of R&M will be known after finalisation the executing agency.

As such, WRPC may authorize Member Secretary, WRPC to finalise the executing

agency and the cost of R&M with approval of Chairman, WRPC.

WRP Committee may please discuss and decide.

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 13

ITEMS FOR INFORMATION ITEM No. 10: PAYMENT OF TRANSMISSION CHARGES FOR INTER-STATE

TRANSMISSION In accordance with Central Electricity Regulatory Commission (Terms & Condition of

Tariff) Regulation, 2009, the monthly Energy account (REA) issued by RPC shall

also include a statement specifying the ratio in which transmission charges for

interstate transmission system for that month are to be shared by transmission users

in accordance with regulation 3.3. Also, the bill for transmission charges (inclusive of

incentive) for transmission charges for a month should be raised by the transmission

licensee based on its estimate of Transmission System Availability Factor (TAFM) for

the month and adjustment, if any, has to be made on the basis of TAFM to be

certified by the Member Secretary of WRPC within 30 days from the last day of the

relevant month.

This matter was discussed in 52nd meeting of Commercial Committee held on 9th

April 2009 and it was proposed that PGCIL would make available the details of

outages (certified by WRLDC) to all the beneficiaries by 10th of the following month.

Concerned beneficiaries, after examining these details, should furnish their

comments/observations, if any, to WRPC by the 20th of the following month. For

example, outage details for the month of April 2009 will be made available by PGCIL

to beneficiaries by 10th of May 2009. Comments of beneficiaries should be furnished

to WRPC 20th May 2009. In case of non-receipt of the same by this time period, it will

be taken, as no comments. Member Secretary, WRPC, will certify the TAFM

accordingly. All the members agreed to the same.

WRP Committee may like to note. ITEM No.11: COMPUTATION OF PAYMENT OF CAPACITY CHARGES FOR

THERMAL GENERATING STATION

Clause 21(4) Of Central Electricity Regulatory Commission (Terms And Conditions

Of Tariff) Regulation, 2009, which has come into force w.e.f. 1.04.2009 envisaged

that in case of fuel shortage in a thermal generating station, the generating company

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 14

might propose to deliver a higher MW during peak-load hours by saving fuel during

off-peak hours. The concerned Load Despatch Centre may then specify a pragmatic

day-ahead schedule for the generating station to optimally utilize its MW and energy

capability, in consultation with the beneficiaries. Average Declared Capacity i.e. DCi

in such an event shall be taken to be equal to the maximum peak-hour ex-power

plant MW schedule specified by the concerned Load Despatch Centre for that day.”

The matter was deliberated in 52nd meeting of Commercial Committee held on 9th

April 2009 and it was decided that the following methodology will be adopted in WR

for computation of DCi in case of fuel shortage:

(i) Peak Hours would generally be worked out by taking into regional load of

previous days or similar day of the previous week.

(ii) It would be of continuous 5 Hrs. (20 time blocks of 15 minutes)

(iii) The entire year will be divided in two seasons i.e. April to September as

summer and October to March as winter season.

(iv) Peak Hours during the month of April to September – 1800 Hrs to 2300

Hrs.

(v) Peal Hours during the month of October to March – 1700 Hrs to 2200 Hrs.

(vi) DCi will be taken equal to maximum ex-power plant MW schedule

specified by the WRLDC continuously during the above defined peak

hours for that day

WRP Committee may like to note. ITEM No.12 : IMPLEMENTATION OF REVISED UI CHARGES W.E.F. 01.04.09 Central Electricity Regulatory Commission (Unscheduled Interchange charges and

related matters) Regulation, 2009 has been notified by the Commission vide

Notification No.L-1(1)/2009-CERC dated 30th March 2009. These regulations have

come into force on 01.04.2009. Clause 7 of the above regulation “Limit on UI

volume and consequences of crossing limits envisages the following:

(a) The over-drawal of electricity from the schedule by any beneficiary or a buyer

during a time-block shall not exceed 12% of its scheduled drawal or 150 MW (whichever is lower) when frequency is below 49.5 Hz, and 3% on a daily aggregate basis.

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 15

(b) The under-injection of electricity from the schedule by a generating station or

by a seller during a time-block shall not exceed 12% of the scheduled injection of such generating station or seller when frequency is below 49.5 Hz, and 3% on daily aggregate basis.

(c) In addition to UI Rate corresponding to frequency of 49.2 Hz, as stipulated

under regulation 5, an Additional Unscheduled Interchange Charge at the rate equivalent to 40% of the UI Rate corresponding to frequency of 49.2 Hz shall be applicable for over-drawal or under-injection of electricity for each time-block when grid frequency is below 49.2 Hz. Provided that for under-injection of electricity during the time-block when grid frequency is below 49.2 Hz for the generating stations using coal or lignite or gas supplied under Administered Price Mechanism (APM) as the fuel, Additional Unscheduled Interchange Charge shall be equivalent to 40% of the UI Cap Rate.

(d) Payment of Unscheduled Interchange Charges under regulation 5 and the Additional Unscheduled Interchange Charge under (c) above, shall be without prejudice to any action that may be considered appropriate under section 142 and section 149 of the Act for contravention of the over-drawal and under-generation limit specified in these regulations, for a time block when frequency is below 49.5 Hz.

(e) The Commission may from time to time, if considered necessary, prescribe the Additional Unscheduled Interchange Charge for over-drawal or under-injection of electricity during the time-block when grid frequency is below 49.5 Hz and up to 49.2 Hz.

(f) Any over-drawal and under-injection of electricity shall be computed in

accordance with the methodology used for preparation of ‘Regional Energy Accounts’.

(g) Provided that the Regional Load Despatch Centre shall prepare and publish on its website the records, on monthly basis, of the UI Accounts, specifying the quantum of over-drawal/under-generation and corresponding amount of UI paid/received for each beneficiary or buyer and generating station or seller for the time-blocks when grid frequency was below 49.2 Hz and between 49.5-49.2 Hz separately.

Further, UI rate in a time block (15 minute) will be capped at 408 paise per kWh for

all generating stations using coal or lignite or gas supplied under Administered Price

Mechanism (APM) as fuel in case when actual generation is higher or lower than the

scheduled generation in the frequency range between 50.3 Hz and upto 49.2 Hz.

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 16

In view of the above, the procedure to be followed w.e.f. 1st April 2009 for

preparation of UI charges was discussed in 52nd meeting of Commercial Committee

held on 9th April 2009 and agreed.

So far as Application of fund collected through UI is concerned, Clause 11 of Central

Electricity Regulatory Commission (Unscheduled Interchange charges and related

matters) Regulation, 2009 envisages that the amount left after final settlement of

claims of Unscheduled Interchange charges of the generating station and the

beneficiaries shall be utilised, with the prior approval of the Commission, for either or

both of the activities viz. (a) Servicing of investment for transmission schemes of

strategic importance and (b) Providing ancillary services including but not limited to

‘load generation balancing’ during low grid frequency as identified by the Regional

Load Despatch Centre, in accordance with the procedure prepared by it, to ensure

grid security and safety. However, the amount of fund, allocable for the above

purposes shall be decided by the Commission from time to time.

WRP Committee may like to note.

ITEM No. 13: SHIFTING OF SLDC BHILAI TO RAIPUR 13.1 In order to improve the data reliability from SLDCs to RLDC and vice versa,

scheme for backup communication links from SLDCs and strategic locations in the

network of ULDC scheme of WR was discussed and approved in the 7th meeting of

WRP Committee held on 3rd May 2008. During this meeting, CSEB intimated that

SLDC, Bhilai is to be shifted to Raipur and as such the corresponding expenditure

for data communication link from Raipur to Bhilai shall required to be pooled in

regional system. The WRP committee had agreed to the same.

In the above context, WRTS-I, PGCIL during 9th meeting of WRP Committee held on

16th Jan. 2009, intimated that cost estimates (about Rs. 5.16 Crores) have been

worked by them based on inputs from CSEB and requested WRP Committee for its

approval. The WRP Committee members deliberated the matter and gave in

principle approval for the same. However, it was suggested by MPPTCL that the

SCADA Committee of WR may examine the cost estimates worked out by PGCIL.

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 17

13.2 In view of above, in the meeting of Regional SCADA/Communication Co-

ordination group (RSCG) held at WRLDC, Mumbai on 12th March 09, the details of

break up of cost estimates of Rs. 5.16 Crores was examined and discussed in detail.

The SCDA/ Communication Committee found the above estimates technically

justified. However, some of the constituent states of Western Region did not agree to

pool the expenditure. CSEB insisted that the issue of sharing the above expenditure

has been agreed in WRP Committee meeting and the decision already taken should

not be reviewed. In view of this, WRLDC, PGCIL requested to discuss the matter by

the member of Commercial Committee.

13.3 The matter was discussed in the 52nd meeting of Commercial Committee. It

was stressed that this Committee cannot review the decision taken by WRP

Committee for pooling the expenditure in the regional system. Further, it was

reiterated that the WRP Committee gave the mandate to the SCADA Committee to

the extent of examination of the cost estimate.

As such as decided by the WRP Committee in its 9th meeting held on 16th Jan. 2009, the corresponding expenditure for data communication link from Raipur to Bhilai shall be pooled in regional system. WRP Committee may like to note. ITEM No.14: COMMISSIONING OF TRANSMISSION LINES AND GENERATING

UNITS

14.1 Commissioning of transmission elements by PGCIL WRTS, PGCIL have reported commissioning and commercial operation of the

following elements of transmission system:

Sl. No.

Name of the transmission elements Date of commercial Operation

1 40% FSC of 400 kV Ranchi-Sipat D/c under Kahalgaon-II phase-II

1.03.2009

2 315 MVA ICT-II at Bhatapara S/s under Sipat-II 1.01.2009 3 Bur reactor at Damoh ICT-II at Damoh under WRSS-IV 1.01.2009 4 Agra-Gwalior 765 kV Ckt-II under N-W Inter connector 1.04.2009

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 18

5 400/220 kV, 315 MVA ICT-II at Rajgarh S/s along with associated bays under Sipat-I transmission system

01.04.2009

6 765 kV S/c Seoni-Wardha transmission line with associated bays (initially charged at 400 kV)

01.04.2009

7 400 kV D/c Wardha-Akola transmission line with associated bays

01.04.2009

8 400 kV D/C Zerda-Kankroli line (Associated with North-West Transmission Corridor Strengthening scheme)

Test charged in March 09

WRP Committee may like to note. 14.2 Commissioning of generating units

S.No State/Agency Name of Project Unit

No. Capacity in MW

Date of Synchronization

1 Maharashtra Trombay TPP (TPC)

8 250 Taken full load w.e.f. 26.3.2009

2 Torrent Power Co., Gujarat

Sugen CCPP- Torrent Power

Block-II 382.5 29.01.09

3 Torrent Power Co., Gujarat

Sugen CCPP- Torrent Power

Block-III 382.5 27.03.09

4 LANCO Pathadi TPP 1 300 Synchronised on 1.05.2009

5 Bhilai TPP (Joint venture with SAIL)

NSPCL 1 250 COD w.e.f 22.04.09

6 Bhilai TPP (Joint venture with SAIL)

NSPCL 2 250 Synd. On 28.03.09

WRP Committee may like to note.

ITEM No.15: ONGOING TRANSMISSION SCHEMES IN WESTERN REGION

The details of ongoing transmission schemes in WR is enclosed at Annexure- 15.

The important EHV lines, which are expected to be commissioned during the current

year, are as below:

S.No. Name of transmission element Expected date of commissioning

1 400 kV D/C Akola-Aurangabad June 2009

2 765 kV S/C Seoni - Bina line (to be charged at 400kV) Sep. 2009

3 400 kV D/c Ranchi - Rourkela Mar-2010

4 400 kV D/c Rourkela - Raigarh Mar-2010

5 400 kV D/c Raigarh – Raipur Mar-2010

6 400 kV Seoni – Wardha Jul-2010

7 LILO of Kankroli-Zerda at Bhinmal Oct-2009

WRP Committee may like to note.

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 19

ITEM No. 16: ONGOING GENERATION SCHEMES IN WESTERN REGION

The details of on going generation schemes in WR both under State as well as

Central Sector are enclosed at Annexure-16. The generating units expected to be

commissioned during the next one year are as follows:

Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

GUJARAT (i) Surat Llignite expansion-PH-I

GIPCL 1 125 Nov. 2009

2 125 Mar. 2010 (ii) Utran GPP GT+ST 374 Aug. 2009 (iii) Mundra TPP Ph-I, APL 1 330 May 2009 2 330 July 2009 3 330 Feb. 2010 4 330 May. 2010 (iv) Hazira CCPP (GSECL) GT+ST 350 Apr. 2010

CHHATTISGARH (i) Pathadi TPP (Lanco) 2 300 Dec. 2009

MAHARASHTRA (i) New Parli TPS Extn. 2 250 Nov. 2009 (ii) Paras TPS Extn. 2 250 Feb. 2010 (iii) JSW Energy, Ratnagiri (4x300) 1 300 Feb. 2010 CENTRAL SECTOR – NTPC (i) Sipat-I, TPP 1 660 Nov. 2009 2 660 Dec. 2009 3 660 Mar. 2010 (ii) Bhilai TPP (Joint venture with SAIL) 2 250 COD exp in May. 2009 (iii) Korba STPP Stage-III 7 500 May. 2010

WRP Committee may like to review. ITEM No.17 ANTICIPATED POWER SUPPLY POSITION IN WESTERN

REGION FOR THE PERIOD FROM JUNE 09 TO AUG. 09.

The anticipated power supply position in the region for the period from June,2009 to August,2009 is furnished at Annexure-17 for information of the members. The period under consideration is monsoon season and the regional demand is likely to

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 20

be low as compared to summer period. Aggregate unrestricted demand will vary from 33284 MW to 35249 MW and deficit will vary from 0.21% to 11.40%. In terms of energy, the unrestricted requirement is varying from 20769 MUs to 21375 MUs with regional deficit varying from 7.59% to 16.31%. The anticipated Peak demand shortages for Gujarat, Chhattisgarh, Maharashtra, Goa,DD and DNH is 910 to 1989 MW,223 to 396 MW,2816 to 3940 MW, 84 to 122 MW, 29 to 45 MW and 34 to 127 MW respectively.

Although deficit is comparatively less than other peak period due to monsoon season, Constituent states will have to be vigilant as regards to frequent tripping of lines and high voltages in certain pockets. Also, maintenance programme of generating units will have to be planned after taking into consideration regional demand and also diversity in demand of NR and ER in an integrated combined N-E-W grid. ITEM No.18: PAYMENTS OF UI AND REACTIVE ENERGY CHARGES

As per the information received from WRLDC, the status of payment to UI pool

account and Reactive Energy Pool account as on 8.05.2009 i.e. upto week

20.04.2009 to 26.04.2009 of the current financial year is given below: -

(All figures in Rupees)

UI Pool Account Reactive Energy Pool Account

Constituents Dues Constituents Dues GUJARAT (162,047,541) GUJARAT 3,937,144 MADHYA PRADESH (1,915,891) MADHYA 2,079,743 CHHATTISGARH (249,050,678) CHHATTISGARH (4,544,147)MAHARASHTRA (144,357,679) MAHARASHTRA (2,145,636)GOA (996,243) GOA (2,154,788)DD 138,404,833 DD 186,451 DNH (12,691,009) DNH 663,389 NTPC (117,739,452) NR Exchange 1,039,251,844 SR Exchange (793,201,144) ER Exchange 688,572,159 Jindal Power (10,163,740) HVDC Vindhyachal (428,141) HVDC Bhadravati (2,037,623) Diff. due to capping (1,786,551,289) Diff. due to Additional UI (42,796,067) Net Total (1,457,747,661) -1,977,844

*To be disbursed by WRLDC ; Figures in bracket ( ) are receivables from pool

WRP Committee may like to note.

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 21

ITEM No.19 PROVISION OF 400 kV FEED TO UNION TERRITORY OF DAMAN & DIU.

In the 9th Meeting of WRP Committee held on 16.01.2009, request of Union Territory

of Daman & Diu for providing 400 kV feed to the Union Territory by establishment of

400 kV substation in Daman was considered and the Committee gave in-principle

approval to the proposal. PGCIL were requested to carry out the survey and identify

a suitable location in the territory for the proposed 400/220 kV sub-station.

Executive Director (WR-II), PGCIL, vide his letter No.WRTS-II.VDR:Engg: dated

14.05.2009 intimated that joint exercise for identification of land in Daman was

carried out by them alongwith the Electricity Department of Daman & Diu. However,

no Government land could be located for the proposed substation. As such, they

have requested that Daman & Diu administration may provide 10-12 acres of land

(preferably Government owned) for construction of GIS substation at Daman. Copy

of the above referred letter of PGCIL is enclosed at Annexure-19.

Daman & Diu administration may kindly intimate the present status in this regard.

ITEM No.20: CONTRIBUTION TOWARDS INCIDENTAL EXPENSES FOR VARIOUS MEETINGS ETC.

20.1 The erstwhile WRE Board in its 120th meeting held on 20th December 2002

passed Resolution to create Board Fund for meeting the expenditure of Board viz.

periodic and special forum meetings, seminars, workshop, meetings with deferent

power sectors / advisors, management consultant of power sector of WR at WREB

head quarters etc. Subsequently, due to the formation of WRPC and change in the

membership of WRPC as per GoI Resolution, the WRP Committee in its 4th meeting

held on 29th June 2007 decided that the contribution towards the above fund be

made by the following :

(i) All State GENCOs (ii) All State TRANSCOs (iii) All State owned DISCOMs (by rotation, if more than one in a State) (iv) NTPC Ltd., PGCIL, NPCIL, IPPs having IC above 1,000 MW – contribution

to be made by each separately. (v) Representative of IPPs and (vi) Representative of Trading Company

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 22

Accordingly, the above members are making the contribution @ Rs. 50,000/- per

year to the Board Fund.

20.2 With the subsequent amendment to the Resolution regarding establishment of

Western Regional Power Committee made by MoP vide Resolution dated 9th May

2008, there is some change in the membership.

Accordingly the details of members of WRP Committee that will contribute Rs.

50,000/- each towards the Board Fund for the year 2009-10 and thereafter is

enclosed at Annexure-20.

WRP Committee members may like to note and send their contribution accordingly. ITEM No.21: ANY OTHER ITEM WITH THE PERMISSION OF THE CHAIR ITEM No.22: DATE AND VENUE OF NEXT WRPC MEETING

*****

Agenda Notes of 10th meeting of WRP Committee to be held on 30th May 2009at Diu 23

Agenda Notes of 10th WRPC meeting to be held on 30th May 09

ANNEXURE

Annexure - 3 Transmission System Associated with the Tilaiya Ultra Mega Power Project (4000 MW), in Jharkhand, Nabinagar (1000MW) of Railways and NTPC, Barh-II (1320 MW), Rihand-III (1000MW), Vindhyachal-IV(1000MW) and Mauda (1000MW) of NTPC, and IPPs in Jharkhand, Orissa, MP, Chattisgarh, and Maharashtra

The transmission system requirements were identified based on studies carried out by CEA and PGCIL. The evolve transmission scheme was deliberated during the 28th meeting of the Standing Committee on Power System Planning held on 6th December 2008 at Aurangabad and its Special meeting held on 18th April 09 at WRPC office Mumbai The transmission scheme agreed is in four parts, viz. (i) Generation specific transmission scheme, (ii) System strengthening common for WR and NR, (iii) System strengthening common for WR and (iv) Pooling Stations for IPPs in Orrissa A. Generation Specific Transmission System Tilaiya UMPP (4000MW)

1. Tilaiya UMPP – Sasaram, 765kV S/C line 2. Tilaiya UMPP – Gaya, 765kV S/C line. 3. Tilaiya UMPP – Balia 765kV S/C line

Nabinagar (1000MW)

1. Nabinagar-Sasaram 400kV D/C line Barh-II (1320MW)

1. Barh – Gorakhpur 400kV quad D/C line Rihand-IV (1000MW)

1. Rihand-Vindyachal pooling 2xS/C 765kV lines operated at 400kV (considering ageing of Rihand-Dadri HVDC system and possibility of decommission the HVDC system, a 765kV switchyard could be established at Rihand utilizing the space of HVDC terminal and considering this, 2XS/C 765kV lines operated at 400kV was suggested and agreed.

Vindhyachal-IV (1000MW)

1. Vindhyachal-IV – Vindhyachal pooling 400kV quad D/C line or 2x765kV S/C lines depending on feedback from NTPC

Mauda (1000MW)

1. Mauda-Nagpur South 400kV quad D/C 2. Mauda-Khaperkheda 400kV quad D/C

Essar(1800MW), Electrosteel(1200MW) and Corporate(800MW):

1

These three IPPs in Jharkhad would connect at 400kV to Ranchi 765/400kV substation through dedicated/common 400kV transmission lines

Adunik (1000MW) and DumkaCESC (1200MW) :

These two IPPs in Jharkhand would connect to ER grid at Jamshedpur/Maithon/Gaya

Sterlite(2400MW), GMR (1050MW), Monet (1005MW), Jindal (1200MW), Essar(1200MW) and Lanco (2640MW)

These IPPs in Orissa would connect to 765kV and 400kV system specifically proposed in ER for Orissa IPPs. Three 765/400kV pooling stations at Jharsuguda, Angul and Denkenal together with Jarsuguda-Angul-Denkenal-Jharsuguda 2xS/C 765kV lines would be connected to WR system through following provision: 1. LILO of all four circuits of Rourkela-Raigarh 2xD/C 400kV lines at

Jharsuguda. 2. Jharsuguda-Dharmjaygarh 2xD/C 765kV lines.

IPP of Sterlite would connect to 765/400 kV pooling station Jharsuguda IPPs of GMR, Monet, Jindal, Essar and LANCO would connect to Angul 765/400 kV pooling station WBPDCL projects To be connected to West Bengal and ER grid IPPs in MP Jaiprakash (1320MW)

1. Jaiprakash-Satna(or Vindhyachal pooling) 400kV quad D/C ShahdolRIL(1050MW)

1. Shahdol-Jabalpur pooling 400kV D/C Today Home(1000MW)

1. Today Home – Jabalpur pooling 400kV D/C IPPs in Maharashtra JSW Energy(1200MW) Connected through MSETCL’s STU system Maharashtra Egy(4000MW)

1. MahaEgy – Phadghe 2X S/C 765kV lines 2. MahaEgy – Pune S/C 765kV line

IPPs in Chattishgarh

2

Aryan Coal (270MW), Spectrum C&P (100MW), Maruti Coal (270MW) and Dheeru (1050MW)

1. All the above projects would be connected to Sipat pooling 2. Earlier open access to Aryan Coal was agreed with connectivity to Bhatpara. In

view of revised time frame for the generation project, the revised connectivity would be to Sipat pooling. PGCIL informed that Aryan and Sepctrum had planned to have a common dedicated 400kV line to Sipat pooling.

3. Maruti C Coal and Dheeru would have their own dedicated 400kV lines connecting to Sipat pooling.

4. Open access to Dheeru was already agreed for 600MW. Their revised application seeking open access of 682 MW (382 to NR and 300 to WR) was noted and approved.

B. System strengthening common for WR and NR:

1. Creation of 765kV Switching station at Daramjaygarh by LILO of Ranchi- Sipat 765kV S/C line

2. Ranchi-Daramjaygarh 765kV S/C line 3. Jarsuguda-Daramjaygarh 2xD/C 765kV lines 4. Dhramjaygarh-Jabalpur 765kV 2xD/C 765kV lines 5. Pooling station at Jabalpur with 2x1500MVA 765/400kV 6. Jabalpur pooling-Bina 765kV lines – one D/C line and one S/C line providing 3

nos. of 765kV circuits. 7. Bina-Gwalior S/C 765kV line (3rd ckt) 8. Gwalior-Jaipur 2XS/C 765kV lines 9. Vindhyacal pooling station with 2x1500MVA 765/400kV 10. Vindhyachal pooling-Satna 2XS/C 765kV lines 11. 2x S/c 765 kV Satna-Gwalior

C. System strengthening for WR:

1. Dharamjaigarh-Bilaspur (Sipat) pooling 765kV S/C line 2. Jabalpur pooling-Bhopal 765kV S/C line 3. Bhopal-Indore 765kV S/C line 4. Indore – Vadodara 765kV S/C line 5. 765/400kV substation at Vadodara, Bhopal, Dhule, Padghe, Aurangabad, Raigarh

pool, Champa pool, and Raipur pool each with 2x1500MVA 765/400kV and interconnecting 400kV lines/LILO

6. Raigarh Pool –Raipur Pool 765kV S/C 7. Raigarh Pool –Champa Pool 765kV S/C 8. Champa Pool – Bilaspur (Sipat) pooling 765kV S/C 9. Champa Pool -Raipur Pool 765kV S/C 10. Bilaspur (Sipat) pooling-Raipur Pool 765kV S/C 11. Raipur-Wardha 2XD/C 400kV lines upgradable to 2XS/C 1200kV lines with FSC

(40%) will be provided on 400 kV lines and will be removed once upgraded to 1200 kV.

12. Wardh-Aurangabad D/C 400kV line (2nd line) upgrdabale to 1200kV S/C line(2nd line) will be provided on 400 kV lines and will be removed once upgraded to 1200 k.V

13. Pune-Padghe 765kV S/C line

3

14. Aurangabad-Padghe 765kV S/C line 15. Aurangabad-Dhule 765kV S/C line 16. Dhule-Vadodara 765kV S/C line 17. Wardha-Nagpur South 400kV quad D/C with new 2x500MVA 400/220kV s/s at

Nagpur South (Butibori) ( with 220kV interconnectivity under preview of MSETCL)

18. 400 kV level interconnection from proposed new 765 kV S/s at vadodara, Bhopal, Dhule and Padghe

(i) Vadodara-Pirana (PG) 400 kV D/C quad. (ii) Vadodara-Asoj (GETCO) 400 kV D/C quad. (iii) Bhopal-Bhopal (MPPTCL) 400 kV D/C quad. (iv) Dhule – Dhule (MSETCL) 400 kV D/C quad. (v) Padghe – Padhge (MSETCL) 400 kV D/C quad

D. Pooling Stations for IPPs in Orissa

• Establishment of 765/400kV Pooling Station at Jharsuguda • Establishment of 765/400kV Pooling Station at Dhenkanal • Establishment of 765/400kV Pooling Station at Angul • Dhenkenal Pooling Station – Angul Pooling Station 765kV 2xS/c • Angul Pooling Station – Jharsuguda Pooling Station 765kV 2xS/c • Jharsuguda Pooling Station – Dhenkenal Pooling Station 765kV 2xS/c • LILO of Rourkela – Raigarh 400kV 2xD/c at Jharsuguda Pooling station • * LILO of Meramundali – Jeypore 400kV S/c line at Angul pooling station • * LILO of one ckt of Talcher - Meramundali 400kV D/c line at Angul pooling

station • * LILO of Meramundali-Chandaka 400kV D/c line at Dhenkenal Pooling station

[* These LILO would be later disconnected when Angul and Dhenkanal pooling stations are developed as 765kV as otherwise it would cause short circuit level problem.]

4

Sr.No. PARTICULARS Jan-09 Feb-09 Mar-09 Apr-091 MAXIMUM FREQUENCY (Hz)

1.1 Integrated over an hour 50.36 50.34 50.35 50.271.2 Instantaneous 50.86 50.72 50.55 50.53

2 MINIMUM FREQUENCY (Hz) 2.1 Integrated over an hour 48.97 48.97 49.02 48.942.2 Instantaneous 48.76 48.76 48.77 48.73

3 AVERAGE FREQUENCY (Hz) 49.58 49.45 49.60 49.45

4.1 48.6 Hz 0 0 0 04.2 48.8 Hz 23 76 10 1924.3 51.0 Hz 0 0 0 0

5.1 Above 50.2 Hz 4.10 1.26 2.43 0.645.2 Above 50.5 Hz 0.10 0.07 0.02 0.325.3 Between 50.2 Hz & 49.5 Hz 53.63 39.39 58.25 42.045.4 Between 50.2 Hz & 49.0 Hz 93.79 95.47 95.67 94.165.5 Below 49.0 Hz 2.11 3.27 1.90 5.535.6 Below 49.8 Hz 76.28 88.50 70.75 87.025.7 Between 49.0 Hz & 50.5 Hz 97.79 99.66 98.08 94.165.8 Between 50.5 Hz & 48.5 Hz 99.90 90.99 99.98 99.685.9 Between 49.2 Hz & 50.3 Hz - - - 80.93

5PERCENTAGE TIME WHEN FREQUENCY WAS

Annexure-6.1(a)

FREQUENCY PARTICULARS OF WESTERN REGION FOR THE PERIOD JANUARY 2009 TO APRIL 2009

4NUMBER OF TIMES FREQUENCY TOUCHED

Annexure - 6.1(b) (1/2)

Jan Feb Mar April Jan Feb Mar April Jan Feb Mar April Jan Feb Mar April

Demand met (MW) 2554 2996 2840 2880 8042 8502 8788 8271 5966 5754 5759 5468 13098 13617 14265 14801

Unrestricted demand (MW) 2625 3054 2907 2996 9127 8757 8733 8696 7168 7062 6957 6740 17699 18258 18426 19154

Deficit(-)/Surplus(+)

(i) MW -71 -58 -67 -116 -1085 -255 55 -425 -1202 -1308 -1198 -1272 -4601 -4641 -4161 -4353

( ii) % -2.70 -1.90 -2.30 -3.87 -11.89 -2.91 0.63 -4.89 -16.77 -18.52 -17.22 -18.87 -26.00 -25.42 -22.58 -22.73

Jan Feb Mar April Jan Feb Mar April Jan Feb Mar April Jan Feb Mar April

Demand met (MW) 401 400 401 400 197 207 215 255 423 443 434 441 30165 30585 31608 31509

Unrestricted demand (MW) 439 457 466 455 222 232 240 280 466 480 504 485 36577 36813 37392 36793

Deficit(-)/Surplus(+)

(i) MW -38 -57 -65 -55 -25 -25 -25 -25 -43 -37 -70 -44 -6412 -6228 -5784 -5284

(ii) % -8.66 -12.47 -13.95 -12.09 -11.26 -10.78 -10.42 -8.93 -9.23 -7.71 -13.89 -9.07 -17.53 -16.92 -15.47 -14.36

POWER SUPPLY POSITION IN WR FOR PERIOD FROM JANUARY 2009 TO APRIL 2009 (IN MW)

Details Chhatisgarh Gujarat Madhya Pradesh Maharashtra

Details Goa Daman & Diu Dadra & Nagar Haveli Western Region

Annexure - 6.1(b) (2/2)

Jan Feb Mar April Jan Feb Mar April Jan Feb Mar April Jan Feb Mar April

Availability (MUs) 1254 1235 1310 1334 5465 5036 5940 5888 3452 2955 3038 2926 8705 8110 9265 9196

Unrestricted Requirement (MUs) 1273 1264 1324 1376 5822 5147 5953 6072 4338 3801 3875 3551 11116 10515 11714 11650

Deficit(-)/Surplus(+)

(i) MUs -19 -28 -14 -42 -357 -111 -13 -184 -885 -845 -837 -625 -2411 -2405 -2449 -2454

(ii) % -1.509 -2.24 -1.063 -3.04 -6.13 -2.16 -0.216 -3.04 -20.41 -22.24 -21.60 -17.59 -21.69 -22.87 -20.905 -21.06

Jan Feb Mar April Jan Feb Mar April Jan Feb Mar April Jan Feb Mar April

Availability (MUs) 233.91 218.37 261.02 275.56 131.08 124.44 120.41 136.92 288.50 281.88 310.65 278.45 19529 17968 20271 20035

Unrestricted Requirement (MUs) 237.52 223.15 266.75 280.51 149.68 147.76 164.62 154.92 316.15 287.07 311.47 308.56 23252 21384 23609 23393

Deficit(-)/Surplus(+)

(i) MUs -3.61 -4.78 -5.73 -4.95 -18.60 -23.32 -44.21 -18.00 -27.65 -5.19 -0.82 -30.11 -3722 -3417 -3338 -3358

(ii) % -1.52 -2.142 -2.15 -1.76 -12.43 -15.78 -26.86 -11.62 -8.75 -1.808 -0.26 -9.76 -16.01 -15.98 -14.139 -14.35

POWER SUPPLY POSITION IN WR FOR PERIOD FROM JANUARY 2009 TO APRIL 2009 (IN MUs)

Details Chhatisgarh Gujarat Madhya Pradesh Maharashtra

Details Goa Daman & Diu Dadra & Nagar Haveli Western Region

400 kV S/SMonth Max Min Max Min Max Min Max Min Max Min Max Min

Jan-09 422 380 428 389 424 320 440 390 426 400 421 400

Feb-09 421 376 430 383 426 384 438 390 426 400 421 400

Mar-09 423 386 429 397 424 389 438 398 424 399 424 404

Apr-09 425 382 430 392 424 378 436 400 424 398 422 400

400 kV S/S

Month Max Min Max Min Max Min Max Min Max Min Max Min Max Min

Jan-09 418 388 419 389 422 389 424 383 431 385 762 724 774 723

Feb-09 415 389 420 394 428 385 424 389 430 383 755 727 776 720

Mar-09 417 390 424 384 433 399 430 393 429 393 761 726 775 713

Apr-09 420 394 415 382 429 396 437 389 430 392 773 725 777 721

Annexure-6.2Voltages at the important 400 and 765 kV substations during the period

January 2009 to April 2009

Indore Itarsi Karad Dhule Asoj Kasor

Nagda Sipat (765 kV) Seoni (765 kV)Bhilai Jetpur Bina Gwalior

1

Annexure -7

Agenda Item given by WRLDC vide letter dated 7th May 2009 WIDE AREA MANAGEMENT SYSTEM OF WR

Indian Grid is expanding exponentially with increased number of interconnections between Regions. There are further requirements imposed by Regulatory Regime, deregulated energy market & consumer aspiration for quality and reliable power supply. All these requirements with increasing complexity of Grid Operation manifold necessitates dynamic monitoring of parameters /conditions on real time basis.

The existing SCADA / EMS provides the data which are steady state in nature and not suitable for dynamic monitoring and control of Grid due to high degree of latency of telemetered data and also non-synchronization of sampling of data. Emerging technologies like Wide Area Measurement System (WAMS) using Phasor measurement Unit (PMU) provide more advanced measurement system that will utilize synchronized measurements from geographically distant locations and increase the situational awareness by monitoring a wide area of power system in real time. Technologies which are under various stages of development based upon WAMS facilitate real time visualization of power systems, real time congestion management, design of an advanced warning system, validation and fine tuning of system models and design of an adaptive protection system. Worldwide various utilities have started using / developing this new technology and pioneer utilities are from North America, Europe, China, Russia and Brazil etc.

It may be appreciated that the complexities of Indian Grids are as vast as in any other country. However, in India so far this technology has only been at the discussion / planning stage and taking into consideration the importance of the issue, it is necessary that the different transmission utilities take expeditious action in the matter. These technologies have been envisaged in the GoI report of Working Group on Pow4er for 11th Plan as well as National Electricity Plan – Transmission, wherein it is advised to take up Pilot Projects.

2

In this regard TCS has approached POWERGRID to join the consortium team of TCS, IIT Bombay and Tata Power for executing a PMU based project which has been approved by Council of Scientific and Industrial Research (CSIR) of Department of Science & Technology, Government of India. Under the NMITLI (New Millennium India Technology Leadership Initiative) program. CSIR will provide Loan for the project. The main features of the project are as follows:

• Installation of PMUs (Phasor Measurement Units) at around 25 to 30 locations in Western Region Grid. The data from PMUs shall be acquired at Western Regional Load Despatch Centre (WRLDC).

• Development of software functions using PMU data.

POWERGRID share of total estimated cost of the project

is Rs. 8.76 crores. The loan from CSIR is to be repaid over 10 years at an interest rate of 3% after completion of the project. The annual installments shall be ranging from Rs. 90.267 lakhs to Rs. 127.01 lakhs.

It may be mentioned that al Pilot Project for implementation of PMUs in Northern Region has been agreed upon in the last NRPC meeting held on 22.04.2009

The project can be funded through UI CAP fund or Additional UI funds. Alternatively the constituent may finance the project and make yearly advance payment to POWERGRID.

The Committee may discuss and finalized the funding of the WAMS project in WR.

*****

Annexure- 15 1/3 PROGRESS OF TRANSMISSION LINES UNDER CONSTRUCTION IN WESTERN REGIONSr.No.

Name of transmission line Length in Ckt. Km

Anticipated Completion

REMARKS

Target

A gaujarat GUJARAT (March 2009)

I. 400 kovaI laa[-na 400 kV Lines 1 LILO of 400 kV Asoj-Amreli line at 400 kV Chorania 39.10 Dec.08 Line is charged on 18.12.08

II. 220 kovaI laa[-na 220 kV Lines2 220 kV Bardoli-Chikhali D/C 96.00 Sept. 08 Ckt-I & II made parallel on 30.9.08

3 200 kV LILO at Mota (Bardoli) S/S from 2nd Ckt. of Ukai (T)-Vav 9.60 Sept. 08 Line work complted. Feeder bay work completed.LILO point jumper work pending.

4 200 kV D/C Utran-Kosambaat Kosamba S/S from Vav-Zagadia line 172.00 Oct-09 Check survey, foundation and Erection work under progress.

7 200 kV LILO Mangrol-Mobha D/C line 218.00 Jan-09 Foundation, erection & stringing work inprogress.

8 220 KV D/C Chorania - Bala 59.12 Feb-09 Foundation, erection & stringing workcompleted. Bay work completed on 14.04.09.

9 220 KV D/C Rajpur-Dudhrej 19.16 Dec-08 Work completed.10 200 kV LILO at Dinod S/S (Kosamba) from Vav-Zagadia line 10.20 Mar.09 Profiles under scrutiny

11 200 kV LILO at Chitrod from Deodar-Anjar 2.10 Line is ready but feeder bay panel work pending at Shiviakha S/s end.

12 200 kV LILO of Shivlakha-Nanikhakhar at Varsana one ckt at Kukma s/s 34.00 Mar.09 Work under progress.

13 220 KV D/C Mundra (Adani) - Varsana D/C line 166.00 Jun-09 Erection work under progress.14 220 KV Nanikhakhar-Adani Power ProjectD/C line 32.50 Oct. 08 Circuit No-2 charged on 22.11.08

B maGya p`doSa MADHYA PRADESH (March 2009)

I. 400 kovaI laa[-na 400 kV Lines 1 Extention of 400 kV Birsingpur-Katni-Damoh for PGCIL Damoh 26.04 2008-09 Line charged on 8.8.2008

2 Diversion of 400 kV Birsingpur-Katni-Damoh at Katni 1.94 2008-09 Line charged on 8.8.2008

3 Interconnector arrangement at 400 kV Birsingpur-Katni-Damoh at Birsingpur

0.66 2008-09 Line charged on 8.8.2008

II. 220 kovaI laa[-na 220 kV Lines4 LILO of 220 kV Birsinghpur-Rewa one Ckt. At Sidhi 117.56 2008-09 Line charged on 26.10.08

5 LILO of 1st Ckt. DCDS 200 kV Gwalior- Malanpur at 400KV Gwalior PGCIL S/S

16.90 2008-09 Work in Progress

6 200 kV Satna-Chhatarpur 140.00 2008-09 Work in Progress.

7 200 kV Amarkantak-Birsinghpur DCDS at 400kV s/s SUKHA(PGCIL) 300.00 2008-2009 In principle Forest approval for 4.366 Hactare received on 23.11.07. Final approval awaited. Work in progress.

8 220 kV Chhindwara-400 kV PGCIL Seoni D/C 140.00 2008-09 Work almost completed.9 LILO of first Ckts.of 200 kV Pithampura-Rajgarh for 400kV PGCIL

Rajgarh23.66 2008-09 Line Charged on 04.07.08

10 LILO of one Ckt of 200 kV Jabalpur-Itarsi at Piparia S/S 7.20 2008-09 Work almost completed.11 LILO of one Ckt of 200 kV Itarsi-Bhopal for 220kV Mandideep 12.38 2008-09 Line Charged on 25.5.0812 200 kV Shivpuri-Sabalgarh DCDS 200.56 2008-09 Line Charged on 11.02.0913 Second Ckt. Of 200 kV Pithampura-Rajgarh 68.65 2008-09 Line Charged on 25.5.0814 LILO of second Ckt of 220 kV Jabalpur-Itarsi for 220 kV Narsingpur 3.95 2008-09 Line Charged on 11.02.09

15 220 kV Bhopal (400 kV) -Ashta for Ashta S/S 194.00 2008-09 Work in Progress

25 LILO of 200 kV Birsingpur-Satna one Ckt. at ATPS Chachai 91.24 2008-09 Line Charged on 30.08.08

27 SujalpurPGCIL (400kV)-220kV Rajgarh Biaora line 134.40 2008-09 Work in progress.

28 Interconnector arrangement at 400kV Sujalpur-220kV Sujalpur 10.00 2008-0929 Jabalpur-Narsingpur part line for 400 kV PGCIL Sukha 158.00 2008-09 Work in Progress.

30 Chhindwara-Betul 270.00 2008-09 Work in Progress.134 kms survey completed

31 Chegoan-Nimrani 220.00 2008-09 Work in Progress.100.4 kms survey completed

32 LILO of one circuit of 220kV Satpura-Itarsi for 220kV Handia 220.00 2008-09 Work in Progress.

33 Rerouting of 220kV Makronia Traction Feeder through 220kV Sagar 10.18 2008-09 Work in Progress34 LILO of second circuit of 220kV Damoh-Bina line for proposed 220kV

Sager substations10.73 2008-09 Work completed. Line charged on 16.11.08

35 LILO of second circuit of 220kV Pithampur-Ratlam line for 220kV Badnagar

20.29 2008-09 Work completed exept termination of gantry

36 LILO of both circuit of 220kV Ujjain-Kota line for 220kV Badod 14.50 2008-09 Work completed.Line charged on 17.11.08

37 LILO of 1st Ckt. of 220 kV Itarsi-Bhopal for 220 kV Hosangabad 11.52 2008-09 Work completed. Line charged on 03.02.09.

38 LILO of 2nd Ckt. of 220 kV Itarsi-Bhopal for 220 kV Hosangabad 10.75 2008-09 Work in Progress39 LOLO of 1st Ckt. of 220 kV Damoh-Bina line for 220 kV sagar 15.22 2008-09 Work completed.Line charged on 07.03.09

Annexure- 15 2/3

Sr.No.

Name of transmission line Length in Km

Anticipated Completion

REMARKS

Target

C C%tIsa gaZ CHHATTISGARH (March 2009)I. 400 kovaI laa[-na 400 kV Lines

1 LILO of 400 kV Korba (West)-Bhilai to Raipur DCDS 25.00 2008-2009 PB bid opened on 21.01.092 400 kV Korba(West)- Khedamara DCDS 220.00 2008-2009 PB bid opened on 04.03.09

II. 220 kovaI laa[-na 220 kV Lines1 200 kV Korba -Bishrampur DCSS 153.00 2008-2009 1st phase approval received from AIG(FC)

Min. of Env & Forest, New Delhi 2

LILO of 220 kV line from PGCIL Kumhari to 220 kV Doma S/S DCDS 40.002008-2009 Work under Progress, Delayed due to ROW

3 220kV DCDS Suhela-PGCIL Bhatapara line 15.00 2008-2009 Work under Progress, Delayed due to ROW

4 I/C 220 kV Raigarh-PGCIL Raigarh DCDS 10.39 2008-2009 Work under Progress5 220 kV Raigarh-Ms Jindal Power Ltd. DCDS 52.00 2008-2009 line charged on 19.11.086 LILO of 200 kV Korba-Siltara at Mopka DCDS 12.14 2008-2009 Work held up by contractor7 220 KV DCSS lines between 400 KV S/S Bhilai& Rajnandgaon+ 1 No.

bay at Khedamara52.50 2008-2009 Work under Progress, Delayed due to ROW

8 220 kV DCSS Khedamara-220 KV s/s Bemetara+ 1 No. bay at Khedamara & 1 No. at Bemetara

55.00 2008-2009 Work under Progress, Delayed due to ROW

9 220 kV DCDS lines Chhuri-Mopka(Bilaspur) 90.00 2008-2009 PB opened on 09.01.0910 220 kV I/C between New Power House at Korba(E) to prposed 220 kV

Chhuri30.00 2008-2009 Land not decided hence work not started.

11 Diversion of 200 kV line from Korba(E)-Bhilai line emanating from 200 MW PH-II to Korba(E) and 200 kV I/C in between Korba(E) PH-II

30.00 2008-2009 Land not decided hence work not started.

12 Diversion of 200 kV line from Korba-Bhatpara and 200 kV I/C in between Korba(W) and proposed 200 kV Chhuri S/S using section of Korba-Amarkantak - I & II DCSS

14.00 2008-2009 Land not decided hence work not started.

13 Diversion of 200 kV Korba-Amarkantak Ckt.I&II to proposed 200/132KV Chhuri S/S DCSS

4.00 2008-2009 Land not decided hence work not started.

D maharaYT/ (MAHARASHTRA) (March 2009)I. 400 kovaI laa[-na 400 kV Lines

1 400 kV Dabhol- Nagothane Ckt II 135.56 Mar-09 Severe ROW Problems in Vadvali villageII. 220 kovaI laa[-na 220 kV Lines

2 LILO on 200 kV Tarapur-Borivali for 200 kV Boisar-II S/S 8.00 Mar-10 Forest proposal recommended by Dy. COF Dahanu to Chief Conservator Thane. Court case at Loc.No.11

3 200 kV line from PGCIL to 200 kV Wada S/S 57.00 Mar-10 Work held up due to Court cases & forest clearance approval requirement

4 220 kV Therur - Magarpatta D/C 12.00 Mar-09 Line commission on 12.03.094 Interconnection between 200 kV Kolhapur II-Kolhapur III S/S 18.40 Sep-09 Not required. Agency left site.

E pavarg`aID POWERGRID (March 2009)

765 kovaI & 400 kovaI laa[-na 765 kV & 400 kV Lines 1 SIPAT-I Trans. System 1.1 765 KV Sipat-Seoni line 2 354.0 Apr-08 Line commissioned in April 082 Western Region Strengthening Scheme-I 2.1 400 KV D/C Sipat - Raipur 298.0 Jul-08 Line commissioned in July 083 Sipat-II Supplimemtary Trans. System3.1 765 S/C Seoni-wardha (to be operated at 400kV) 269.0 Mar-093.2 400 kV D/C Wardha-Akola 324.0 Mar-093.3 400 kV D/C Akola-Aurangabad 482.0 Mar-09 Final checking under progress4 Western Region Strengthening Scheme-III 4.1 220 kV Vapi (PG)-Magarwada (DD) D/C line & 7 Kms.MultI-Ckt portion 31.0 Apr-08 Line commissioned in April 08

4.2 220 kV Vapi (PG)-Kharadpada(DNH) D/C line 34.0 Aug-08 Line commissioned in June 08

Annexure- 15 3/3

Sr.No.

Name of transmission line Length in Ckt. Km

Anticipated Completion

REMARKS

Target

5 Western Region Stregthening Scheme-II5.1 SET-A: For absorbing import in eastern&central part of WR5.1.1 765 KV 2nd S/C Seoni(PG)-Wardha(PG) (initially to be operated at

400kV)268 Award placed in Feb' 09

5.1.2 400 kV D/C Wardha (PG)-Parli (PG)(Quad.) 694 - Stringing commenced from Feb'09 end5.1.3 400 kV D/C Raipur(PG)-Wardha(PG) 734 - Stringing commenced from Feb'09 end5.1.4 400 kV D/C Bhadravati (PG)-Parli(PG) 776 - Stringing commenced from Feb'09 end5.1.5 400 kV D/C Parli(MSEB)-Parli(PG) 14 - Engg. & survey under progress.5.2 SET-B: For Regional strengthening in southern Maharashtra (to

be implemented through IPTC route)-

5.2.1 400 kV D/C Parli(PG)-Pune 616 -5.2.2 400 kV D/C Pune(PG)-Aurangabad(MSEB) 450 -5.2.3 400 kV D/C Parli(PG)-Pandharpur/Solapur 392 -5.2.4 400 kV D/C Pandharpur/Solapur(PG)-Kolhapur(MSEB) 378 -5.2.5 LILO of Lonikhand(MSEB)-Kalwa(MSEB)400 kV D/C at Pune(PG) 48 -5.2.6 LILO of Solapur(MSEB)-Karad(MSEB)400 kV D/C at

Pandharpur/Solapur(PG)52 -

5.3 SET-C: For Regional strengthening in Gujarat (to be implemented through IPTC route)

-

5.3.1 400 kV D/C Rajgarh(PG)-Karamsad(GEB) 480 -5.3.2 400 kV D/C Limbdi(Chorania)(GEB)-Ranchodpura(Vadavi)(GEB) 190 -5.3.3 400 kV D/C Ranchodpura(Vadavi)(GEB)-Zerda(Kansari)(GEB) 310 -5.4 SET-D: For Regional strengthening in Northern Madhaya Pradesh

5.4.1 Bina(PG)-Gwalior(PG) 765 kV 2nd Ckt.to be operated at 400kV 233 Jul-105.4.2 400 kV D/C Korba(NTPC)-Birsighpur(MPGENCO) 462 Jul-105.4.3 400 kV D/C Birsighpur(MPGENCO)-Damoh(PG) 457 Jul-105.4.4 400 kV D/C Damoh(PG)-Bhopal(MPSEB) 430 Jul-105.5 Trans. Sy. Associated with Gandhar-II (GBPP) -5.5.1 400 kV D/C Gandhar-Kawas 190 * 33 months from investment approval or from5.5.2 400 kV D/C Gandhar-Rajkot 600 * date of tying up of FSA by NTPC whichever 5.5.3 LILO of 400 kV D/C Bina-Nagda at Shujalpur 60 * is later6 Western Region Stregthening Scheme-V6.1 400 kV Vapi(PG)-Navi Mumbai D/C line 370 Sep-10 Row problem faced6.2 220 kV Vapi-Khadoli(UT of DNH) D/C line 56 Sep-106.3 LILO of Lonikhand(MSEB)-Kalwa(MSEB) 400 kV S/C line at Navi

Mumbai 9 Sep-10 Engg. & survey in progress

7 Western Region Stregthening Scheme-VI7.1 400 kV D/C Dehgam - Pirana line 106 Nov-108 Western Region Stregthening Scheme-IX8.1 LILO of 400 kV D/C Bina-Nagda line 60 Jan-11 Tendering under progress

8 Inter-regional lines

8.1 East-West Transmission corridor strengthening scheme8.1.1 400 kV D/C Ranchi - Rourkela 286 Mar-108.1.2 400 kV D/C Rourkela - Raigarh 440 Mar-10 Stringing commenced from Mar'' 098.1.3 400 kV D/C Raigarh - Raipur 440 Mar-108.2 Kahalgaon Stage-II Transmission System8.2.1 400 kV D/C Ranchi - Sipat Lines 816 Dec. 08 Line completed&ckt I commissioned on

31.12.08&ckt II ready for commissioning.8.3 Transmission System associated with Barh Generation Project8.3.1 765 kV S/C Seoni - Bina line (to be charged at 400kV) 293 Sep-098.4 Transmission System associated with North west Transmission

corridor strengthening scheme8.4.1 765 kV Agra - Gwalior 2nd S/C line (initially to be operated at 400kV) 128 Mar-09 Line commissioned in Mar'09.

8.4.2 400 kV D/C Zerda-Kankroli 470 Mar-09 Line commissioned in Mar'09.

GENERATION SCHEMES UNDER CONSTRUCTION DURING 11th PLAN IN WESTERN REGION

Sr. No. Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

A GUJARATGeneration Schemes included in 11th Plan

1 Kutch Lignite TPS 4 75 Commissioned on 22.10.20082 Sugen CCPP (Torrent Power Gen. Ltd.) Block -1 382.5 Commissioned on 20.11.2008

Block-2 382.5 Synchronised on 29.01.09Block-3 382.5 Synchronised on 27.03.09

3 Surat Lignite expansion- GIPCL 1 125 June. 20092 125 Aug. 2009

4 Utran GPP GT+ST 374 Aug. 20095 Sikka TPP Extn. 3 250 Jan. 2010

4 250 May. 20106 Ukkai TPS Extn. 6 490 Feb. 20117 Pipavav CCPP- GPCL & GSPC joint venture Block-1 350 Sep. 2010

Block-2 350 Mar. 20118 Mundra TPP Ph-1 (Adani Power Ltd.) 1 330 May. 2009

2 330 Jul. 20099 Mundra TPP Ph-2 (Adani Power Ltd.) 3 330 Jan. 2010

4 330 Apr. 201010 Mundra Ultra Mega TPP (Tata Power Ltd.) 1 800 Sep. 2011

2 800 Mar. 101211 Hazira CCPP Expansion GSEG GT+ST 350 Dec. 2010

Other Projects1 Gujarat Lignite-NLC & GPCL joint venture Stage-I 1500 2011-12

Stage-II 500 2012-132 Dhuvaran CCPP GSECL Stage-III 360 Mar. 20103 Pipavav TPP- Torrent Power 1000 2011-124 Bhavnagar Lignite TPP-joint venture 500 Apr. 20115 Mundra STPP (Adani Power Ltd.) 1 660 Jan. 2011

2 660 June. 2011

B MADHYA PRADESHGeneration Schemes included in 11th Plan

1 Amarkantak TPS 5 210 Commissioned on 15.06.20082 500 Apr. 2011

2 Satpura TPS Extn. 10 250 Nov. 201011 250 Mar.2011

Other Projects1 Maheshwar HEP - 400 2010-112 Malwa TPP 1 500 Dec. 2010

Annexure- 16 1/2

Sr. No. Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

C CHHATTISGARHGeneration Schemes included in 11th Plan

1 Jindal PL 1 250 Commissioned on 08.12.072 250 Commissioned on 16.04.083 250 Commissioned on 15.06.084 250 Commissioned on 17.06.08

2 LANCO Amarkantak PL 1 300 Synchronised on 01.05.20092 300 Sept. 2009

3 Marwa TPP 1 500 Jun. 20102 500 Dec. 2011

4 Korba West-III TPP 1 500 Jun. 2011Other Projects

1 Bhaiyathan TPP Phase-I 1 500 Apr. 20112 500 Oct. 2011

D MAHARASHTRAGeneration Schemes included in 11th Plan

1 New Parli TPS Extn. 2 250 Aug. 20092 Paras TPS Extn. 2 250 Aug. 20093 Khaperkheda TPP Extn. 1 500 Mar. 20104 Bhusawal Extn. TPP 1 500 May. 2010

2 500 Sep. 20105 Trombay TPS Extn. (Tata Power Co.) 8 250 Commissioned on 14.01.20096 Ghatghar HPS (Hydro) 1 125 Commissioned on 13.05.08

2 125 Commissioned on 01.07.087 JSW Ratnagiri TPP (JSW Energy (Ratnagiri) Ltd.) 1 300 Jun. 2010

2 300 Sep. 20103 300 Dec. 20104 300 Mar. 2011

Other Projects1 Koradi TPS Extn. 1 800 Oct. 20122 Dhopawe TPP 1 800 Nov. 2011

2 800 May 20123 Uran CCPP Block-1 700 Feb. 2010

Block-2 340 May. 20104 Koradi TPS Extn. (Replacemet of 4 x 120) 1 800 Apr 20125 Parli TPS (Replacement of 2x30) 1 250 May. 20106 Paras TPS (Replacement of 1x62.5) 1 250 May. 20107 Bhusawal TPS (Replacement of 1x62.5) 1 250 May. 20108 Chandrapur TPS Extn. 1 500 Dec. 2011

2 500 May. 2012

E CENTRAL SECTOR - NTPCGeneration Schemes included in 11th Plan

1 Sipat-II TPP 5 500 Commissioned on 27.12.08

2 Sipat-I TPP 1 660 Nov. 20092 660 Sept. 20093 660 Mar. 2010

3 Bhilai TPP (Joint venture with SAIL) 1 250 Declared commercial w.e.f 2 250 Synchronised on 28.03.09

4 Korba STPS-III 7 500 Feb. 20105 Mauda TPP 1 500 2011-12

2 500 2012-12

Annexure- 16 2/2

Annexure-17 (1/2)

Details Jun Jul Aug Jun Jul Aug Jun Jul Aug Jun Jul Aug

Availability (MW) 1993 2148 2056 7748 7209 7238 5144 5137 6536 13060 12660 13584Unrestricted demand (MW) 2389 2371 2329 9737 8745 8148 5000 4800 5200 16900 16600 16400Deficit(-)/Surplus(+)

(i) MW -396 -223 -273 -1989 -1536 -910 144 337 1336 -3840 -3940 -2816

( ii) % -16.58 -9.41 -11.72 -20.43 -17.56 -11.17 2.88 7.02 25.69 -22.72 -23.73 -17.17

Details Jun Jul Aug Jun Jul Aug Jun Jul Aug Jun Jul Aug

Availability (MW) 376 345 333 229 215 224 471 432 462 29941 29394 31843Unrestricted demand (MW) 460 455 455 258 260 262 505 495 490 33796 32335 31912Deficit(-)/Surplus(+)

(i) MW -84 -110 -122 -29 -45 -38 -34 -63 -28 -3855 -2941 -69

(ii) % -18.26 -24.18 -26.81 -11.24 -17.31 -14.50 -6.73 -12.73 -5.71 -11.41 -9.10 -0.22

Goa Daman & Diu Dadra & nagar Haveli Western Region

ANTICIPATED POWER SCENARIO IN WR FOR PERIOD FROM JUNE 2009 TO AUGUST 2009 (IN MW)

Chhatisgarh Gujarat Madhya Pradesh Maharashtra

Annexure-17 (2/2)

Jun Jul Aug Jun Jul Aug Jun Jul Aug Jun Jul Aug

Availability (MUs) 1343 1400 1340 5094 4878 5000 3014 3058 3960 7273 7058 7563Unrestricted Requirement (MUs) 1397 1509 1565 5398 5280 5009 2850 2790 2870 11000 10600 10600Deficit(-)/Surplus(+)

(i) MUs -54 -109 -225 -304 -402 -9 164 268 1090 -3727 -3542 -3037

(ii) % -3.87 -7.22 -14.38 -5.63 -7.61 -0.18 5.75 9.61 37.98 -33.88 -33.42 -28.65

Jun Jul Aug Jun Jul Aug Jun Jul Aug Jun Jul Aug

Availability (MUs) 244 231 215 112 102 103 253 228 241 17889 17610 19193Unrestricted Requirement (MUs) 270 260 255 148 163 165 312 305 305 21375 20907 20769Deficit(-)/Surplus(+)

(i) MUs -26.00 -29.00 -40.00 -36.00 -61.00 -62.00 -59.00 -77.00 -64.00 -3486 -3297 -1576

(ii) % -9.63 -11.15 -15.69 -24.32 -37.42 -37.58 -18.91 -25.25 -20.98 -16.31 -15.77 -7.59

Western RegionDetails

Goa Daman & Diu Dadra & nagar Haveli

ANTICIPATED POWER SCENARIO IN WR FOR PERIOD FROM JUNE 2009 TO AUGUST 2009 (IN MUs)

Details Chhatisgarh Gujarat Madhya Pradesh Maharashtra

Annexure -20 Details of members contributing towards “Board Fund”

S. No. Organisation / State Utilities

A State Generating Companies (i) Gujarat State Electricity Corp. Ltd.

(ii) Chhattisgarh State Power Generation Co. Ltd. (iii) Madhya Pradesh Power Generation Co. Ltd. (iv) Maharashtra State Power Generation Co. Ltd.

B State Transmission Companies (i) Gujarat Electricity Transmission Corp. Ltd.

(ii) Chhattisgarh State Power Transmission Co. Ltd. (iii) Madhya Pradesh Power Transmission Co. Ltd. (iv) Maharashtra State Electricity Transmission Co. Ltd.

C State Distribution Companies (by rotation in case of more than one DISCOMs)

(i) Paschim Gujarat Vij Company Ltd., Rajkot (by rotation)* (ii) Chhattisgarh State Power Distribution Company Ltd. (iii) M.P. Paschim Kshetra Vidyut Vitaran Co. Ltd., Indore (by

rotation)* (iv) Maharashtra State Electricity Distribution Co. Ltd.

E Central Generating Co. & CTU (i) NTPC Ltd.

(ii) Power Grid Corporation of India Ltd. (CTU) (iii) Nuclear Power Corporation of India Ltd.

F GENCO having Installed Capacity

more than1000 MW (other than State / Central GENCOs) (i) Tata Power Company Ltd.

(ii) Ratnagiri Gas & Power Private Ltd. (iii) Narmada Hydroelectric Development Corp. Ltd.

(Indirasagar & Omkareshwar HEP) (iv) Narmada Control Authority (SSP)

G One member representing GENCO having IC 1000 MW and less (by rotation)

(i) ESSAR Co. Ltd. (by rotation)

H One DICOM out of private DISCOs in WR (by rotation) (i) BEST Ltd., Mumbai (by rotation)

I One member representing Electricity Traders (by rotation) (i) PTC Ltd., New Delhi (by rotation)