Full Mission Simulation Test Report UPR-R(river) P(rock) University of Puerto Rico Río Piedras...

34
Full Mission Simulation Test Report UPR-R(river) P(rock) University of Puerto Rico Río Piedras Campus May 14, 2010
  • date post

    19-Dec-2015
  • Category

    Documents

  • view

    217
  • download

    1

Transcript of Full Mission Simulation Test Report UPR-R(river) P(rock) University of Puerto Rico Río Piedras...

Full Mission Simulation Test Report

UPR-R(river) P(rock)

University of Puerto RicoRío Piedras Campus

May 14, 2010

Team Members

• Lauren Colón• Pedro J. Dávila• Luis García• Rafael Gavilanes• Laura Obén• Marilena Ortíz• Oscar Resto• Esteban Romero• Noel Sánchez• Verónica Zayas

Students: Faculty Support:

• Vladimir Makarov• Geraldo Morell• Gladys Muñoz• Rafael Velázquez• Benjamin Bolaño• Oscar Resto

Mission Overview• Compare our results with River Rock 2009 results and

findings.• Measurement of selected gases in near-space

conditions.• Inorganic and organic aerosols survey in near-space

conditions.• Also, measure pressure at the laminar air flow during

actual flight.

Changes Since Subsystem Integration

• There were no changes made since our last report, which was the Subsystem Integration and Testing Report.

• Data will be stored in the Flash memory of the AVR.

• Semiconductor sensors heaters should be activated at least 30 minutes before launching, so they can be calibrated for the first half of the flight.

• Our canister is already supplied up to 13,000mA at 12 volts. So, we do not need external power to operate.

• Under experimental conditions, temperature will be running from room temperature to flight temperature.

Subsystem Overview

Integration of Payload • Everything fits together as planned.

• One issue is if the batteries fit in the new canister.

• As known, the bottom plate of the existing canister is being used at the battery plate.

• When the new canister arrives we will be able to know if the batteries fit.

Semiconductor Sensors’ Board Subsystem (Layer #1)

First and Second Battery Filters’ Subsystem (Layer #2)

Third Battery Filter and Manifold’s Sensor Subsystem (Layer #3)

Interface and AVR Boards’ Subsystem (Layer #4)

Battery Plate Subsystem (Layer #5)

Integration of Payload’s Subsystems

Integration of Payload’s Subsystems

Subsystem OverviewSubsystems:

1) Power/Batteries2) AVR Flight computer and data storage3) Gas Semiconductor Sensors/Signal Boards4) Battery Filters5) Flow Regulator6) Selonoid Valves 7) Tubing8) Structure

Test Descriptions

We will asses the following tests:

• Check for any leaks in the tubing, fittings and valves.

• Inject different partial pressures of the gases of interest in order to calibrate the semiconductor sensors.

•Laminar air flow particles tests will not be conducted again this year.

Power/Batteries

Status: Completed

Test Completed: Voltage and current delivery.

Results: Successful. No shortage.

Power/Batteries

Status: In Progress– We have one fully operational system, but we want to

build a second AVR Computer. – We are still waiting for the boards.– We plan to do some modifications to the software.

AVR Flight computer and data storage

AVR Flight computer and data storage

Gas Semiconductor Sensors

Status: In Progress

– We want to refurbished the semiconductor sensor’s manifold.

Upcoming Tests: Test the sensitivity of each sensor to its respective gas.

Gas Sensores

Gas sensor Item No. Measuring Range

H2 701 50 - 1000 ppm

NH3 705 <25 – 10,000 ppm

NOx 706 0.5 – 10 ppm

H2S 714 1 – 100 ppm

NO2 718 0 - >200 ppm

• Synkera Technologies Inc.

Battery Filters

Status: In Progress– The main structure is already completed, but we still

need to clean it and assemble the filters to the main structure.

– We want to make sure that we work with the battery filters in a sterilized environment.

Upcoming Tests: Pressure and vacuum tight seal.

Battery Filters

Flow Regulator

Status: In Progress

– Still need to be cleaned and sterilized.

Upcoming Tests: Pressure and vacuum tight seal.

Pressure Regulator

Selonoid Valve

Status: In Progress

– Still need to be cleaned and tested with the AVR.

Upcoming Tests: Pressure and vacuum tight seal.

Selonoid Valve

Tubing

Status: In Progress

– Still need to be cleaned and sterilized

Upcoming Tests: Pressure and vacuum tight seal.

Tubing

Structure

Status: Completed

Upcoming Tests: Inspect for structure integrity, cracks, and loose parts.

Structure

Overall Analysis

• We are still working on the different test that are supposed to be done to each subsystem.

• We are confident that the tests will be successful and we will be ready for launch when the time comes.

Lessons Learned• We learned that no matter how small a problem may appear, it’s important to review and test every part of the payload to ensure proper function and safety during the flight.

• Next time, we will ensure that everything will be at 0V during pre-flight preparation and that every single subsystem works properly.

• We have learned to work as a team and to divide tasks and assignments with the help of our team leaders.

•We have also learned to cooperate and work together with other teams and universities.

Conclusions

•Our main concern right now involves our battery plate fitting on the new canister, as mentioned earlier. •We expect our subsystems to fit properly into the canister, while complying with Wallops requirements of maintaining a 20 pound payload weight.•We are working hard to complete every phase of this mission to ensure that we can launch our payload without any problem.