Free PMP® Exam Sample Questions

19
Free PMP® Exam Sample Questions pm-exam-simulator.com

description

Free sample questions that will help and guide you in studying for the PMP exam.

Transcript of Free PMP® Exam Sample Questions

Page 2: Free PMP® Exam Sample Questions

PMP® Exam Sample Question

Presented by Cornelius Fichtner, PMP

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Page 3: Free PMP® Exam Sample Questions

Provided by

www.pm-exam-simulator.com

This presentation showcases free sample

questions to help you study for the PMP exam

Page 4: Free PMP® Exam Sample Questions

The critical path in a project can be

determined by which of the following

techniques?

Page 5: Free PMP® Exam Sample Questions

A. Parametric Estimating

B. Pareto Chart

C. Sensitivity Analysis

D. Precedence Diagramming Method

Page 6: Free PMP® Exam Sample Questions

PDM is used for this purpose.

Page 7: Free PMP® Exam Sample Questions

D. Precedence Diagramming Method

Page 8: Free PMP® Exam Sample Questions

AOA (Activity on Arrow), AON (Activity on Node) and

PDM (Precedence Diagramming Method) are all valid

methods to use when determining a project's critical

path. PDM is also referred to as AON.

Page 9: Free PMP® Exam Sample Questions

The risk shared between the buyer

and the seller is determined by which

of the following?

Page 10: Free PMP® Exam Sample Questions

A. The Scope of Work

B. The Teaming Agreement

C. The Contract Type

D. The Project Charter

Page 11: Free PMP® Exam Sample Questions

How can you control the project risk

while negotiating the scope

of work with a seller?

Page 12: Free PMP® Exam Sample Questions

C. The Contract Type

Page 13: Free PMP® Exam Sample Questions

The risk shared between the buyer and seller is

determined by the contract type. For example,

fixed-price contracts have a higher risk for the

seller while cost-reimbursable contracts have a

higher risk for the buyer.

Page 14: Free PMP® Exam Sample Questions

You planned for contingency reserves for

your office building construction project

and used contingency plans to control

risks. However, your attempts to control

project risks were not effective. What is the

next step you should take?

Page 15: Free PMP® Exam Sample Questions

A. Use a fallback plan

B. Escalate to the project team

C. Perform the Plan Risk Responses

process again

D. Escalate to the sponsor

Page 16: Free PMP® Exam Sample Questions

If the primary risk response plan fails,

there should be one more plan to use

as a reaction to a risk.

Page 17: Free PMP® Exam Sample Questions

A. Use a fallback plan

Page 18: Free PMP® Exam Sample Questions

A fallback plan is used when a

contingency plan is not effective.