PMP Exam Sample Questions Set 4

12
PMP® Sample Questions PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Transcript of PMP Exam Sample Questions Set 4

Page 1: PMP Exam Sample Questions Set 4

PMP® Sample

Questions

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Page 2: PMP Exam Sample Questions Set 4

This presentation will showcase free sample PMP® questions

that will help and guide you in studying for your PMP® exam

Find more free sample questions when you visit

www.free-pm-exam-questions.com and free.pm-

exam-simulator.com

Page 3: PMP Exam Sample Questions Set 4

Cost of Quality refers to the total cost of all efforts related to quality throughout the Product Life Cycle. Organizations should invest in product quality improvement to reduce which of the following?

a.Internal Cost of Quality b.Prevention Costs c.Appraisal Costs d.External Cost of Quality

Sample PMP® Exam Question

HINT: If organizations don’t invest in product quality improvements, the cost of product returns, warranty claims, and recall campaigns increases.

Page 4: PMP Exam Sample Questions Set 4

The correct answer is D

Organizations should invest in reducing the External Cost of Quality by improving product quality. This will result in reduced product returns and warranty claims.

Answer and Explanation

Page 5: PMP Exam Sample Questions Set 4

Joe is working as a project manager in a highway construction project. He wants to use a fixed price contract instead of cost-plus contract. The risk response strategy he is using in this case is an example of?

a.Risk Avoidance b.Risk Transference c.Risk Mitigation d.Risk Acceptance

Sample PMP® Exam Question

HINT: The project manager in this example is currently performing the Conduct Procurements process but the answer is in the Plan Risk Responses process.

Page 6: PMP Exam Sample Questions Set 4

The correct answer is B

Risk Transference requires shifting some or all of the negative impact of a threat, along with the ownership of the response. A fixed price contract may transfer risk to the seller, whereas a cost-plus contract may transfer cost risk to the buyer.

Answer and Explanation

Page 7: PMP Exam Sample Questions Set 4

Maintaining a realistic project schedule is very important for the successful execution of a project. When you develop a schedule, which of the following items from the Project Scope Statement will impact the schedule?

a.Work Packages b.Activity List c.Assumptions and Constraints d.Activity Attributes

Sample PMP® Exam Question

HINT: Think about different parts of the Project Scope Statement.

Page 8: PMP Exam Sample Questions Set 4

The correct answer is C

Assumptions and constraints are very important items that impact the schedule. The Project Scope Statement contains this information.

Answer and Explanation

Page 9: PMP Exam Sample Questions Set 4

The Six Sigma process uses which of the following quality cycles?

a.Plan-Do-Check-Actb.Plan-Perform-Verify-Actc.Plan-Execute-Monitor-Rund.Plan-Do-Control-Act

Sample PMP® Exam Question

HINT: Deming proposed this quality cycle.

Page 10: PMP Exam Sample Questions Set 4

The correct answer is A

The Plan-Do-Check-Act cycle was proposed by Deming, which uses Six Sigma processes.

Answer and Explanation

Page 11: PMP Exam Sample Questions Set 4

Which of the following relates to a quality excellence award and also to a quality improvement model?

a.Philip Crosbyb.Joseph Juranc.Malcolm Baldridged.Edwards Deming

Sample PMP® Exam Question

HINT: This is the only formal recognition of the quality performance excellence of U.S. organizations given by the President of the United States.

Page 12: PMP Exam Sample Questions Set 4

The correct answer is C

Process improvement models include Malcolm Baldridge, Organizational Project Management Maturity Model (OPM3®), and the Capability Maturity Model Integrated (CMMI®). Crosby, Juran, and Deming are quality champions, not process improvement models. Malcolm Baldridge is the only formal recognition of the quality performance excellence of U.S. organizations given by the President of the United States.

Answer and Explanation