Frank Kehlenbach Director of European International ... - FIDIC 2014 - Plenary... · In 2010, MDBs...
-
Upload
duongnguyet -
Category
Documents
-
view
239 -
download
0
Transcript of Frank Kehlenbach Director of European International ... - FIDIC 2014 - Plenary... · In 2010, MDBs...
Frank Kehlenbach
Director of European International Contractors
(EIC)
FIDIC standard forms as risk mitigation tool
FIDIC standard forms of contract have historically allocated the construction risk
fairly, i.e. on the basis of which party is best placed to assume individual risks
Provide the lowest outturn cost, as bidders do not have to price for potential risks
Avoid any possibility of arbitrary interpretations and actions by one of the parties
IMPACT OF FAIR CONDITIONS IMPACT OF UNFAIR CONDITIONS
Co-operation / Teamwork Claims, Disputes, Penalties
Quality works Poor quality works
Profitability Insolvencies / Bankruptcies
Professionalism & Integrity Corruption / Cartels
FIDIC standard forms have become more
risky for contractors over time
In the “good old times”, the first three
FIDIC “Red Book” editions were agreed and
published jointly by FIDIC and the world’s
regional contractors’ federations
Contractor was obliged to design (to the extent
provided for by the Contract), execute and
complete the Works with due care and
diligence (not fitness for purpose)
Existence of a trusted and independent
Engineer able to operate as experienced
contract administrator was welcomed as a
value added by both contractor and employer
FIDIC standard forms have become more
risky for contractors over time
In 1987, consensus between FIDIC and
international contractors – which had existed
for three decades – ended and
FIDIC became the sole publisher of the
4th edition of its “Red Book”
Reason was irreconcilable standpoints
with respect to the role of the impartial and
independent Engineer
In 1996 supplement, DABs were introduced
Collaboration between FIDIC and contractors
was remodeled (“friendly reviewer”)
FIDIC standard forms have become more
risky for contractors over time
In 1999, FIDIC published an unbalanced standard form
with enormous risk for contractors. EIC comment:
“Whilst it is not difficult to draft conditions that appeal to
employers, FIDIC has always endeavoured to explain
to prospective Employers the reason behind the
allocation of certain risks.
By leaving the traditional FIDIC philosophy behind and
instead in the Silver Book taking on-board the “all risks
on the contractor - philosophy”, FIDIC will contribute to
poor contract practices.
In the end, it does not serve employers generally that
unreasonable conditions are imposed on contractors.
Employers will have to pay the costs for construction
and it must be most fair that the cost to execute a
particular project is borne by the owner of the project.”
FIDIC standard forms have become more
risky for contractors over time
F A I R C O N T R A C T C O N D I T I O N S
Contractor’s contractual rights are unreasonably limited or duties expanded
Employer’s contractual rights are unreasonably expanded or duties reduced
Engineer’s or DAB’s powers are restricted or deleted
Event Time Cost Cost plus Profit
Delayed Drawings or Instructions X X X
Right of Access to the Site X X X
Fossils X X
Setting Out, Ground conditions X X X
Exceptionally adverse climatic conditions
X X
Consequences of Suspension by Employer
X X
Adjustment for Changesin Legislation
X X
Consequences of Employer’s Risks X X X
Typical re-allocation of risk in Particular Conditions of fair “FIDIC” forms
FIDIC standard forms have become more
risky for contractors over time
FIDIC standard forms have become more
risky for contractors over time
In 2010, MDBs adopted the FIDIC “Pink Book”
as the standard form of contract used by MDBs
for construction projects for which they provide
finance
Participating banks and FIDIC have amended
the General Conditions of the FIDIC 1999
Red Book and have also diminished the role of
the Engineer
WB Procurement Reform: FIDIC forms of
contract will probably no longer be imposed by
MDBs as exclusive set of general conditions but
will be one of several options available to
borrowers
Consequences of too risky contract conditions
If the risks to the Contractor become excessively high,
the following problems may occur:
Higher bid price
Bid failure & disruption of project implementation
Contract award to bidder who fails or not capable of estimating risks properly
Poor construction quality and delay of the work
Undermining the relationship of mutual trust and respect between parties
Groundless claims from the contractor
Frequent disputes between the employer and the contractor
In extreme cases eventual termination of the contract
JICA Checklist for One-Sided Contracts (March 2011)
EIC Contractor’s Guides flag FIDIC risk profile
International Construction Law Review, October 2011 (Introduction)
They [the EIC Contractor’s Guides] are valuable as they are the product of a
responsible and reputable international organisation. They also throw a light on the
approaches to be adopted in drafting international construction contracts... As in the
past, EIC’s comments are balanced. They indicate what it regards as improvements
and what it believes to be retrogressions.
Conclusions & Outlook
FIDIC standard forms of contract 1999 contain a greater deal of risk for
contractors when compared with earlier forms of the last century
FIDIC’s market core, the ”trusted and independent Engineer” who can
afford to make fair decisions, is often eliminated by ill-advised clients
Necessity for FIDIC (and its Member Federations) to raise awareness of the
negative effects connected with the uninhibited misuse of FIDIC forms
vis-à-vis clients and their financiers remains a daily concern
Given that the “Silver Book” goes to the extreme by allocating construction
risk to the contractor, FIDIC might consider to serve the international
contracting market by publishing a more collaborative and “innovative”
standard form of contract at the opposite end of the spectrum
EIC Contact
Address: EIC SecretariatKurfuerstenstrasse 129, D - 10785 Berlin, Germany
Phone: ++49 (0)30 /21286-244
Fax: ++49 (0)30 /21286-285
E-mail: [email protected]
Internet: www.eic-federation.eu