    The WindFloat Project

    Deep Offshore Wind an opportunity for

    Europe

    Conference Atlantic Forum

    Brest, 30th of October, 2012

    1

  • 7/28/2019 Forum Brest Maciel En

    2/37

    Are we creating sustainable value from our oceans? How can we do

    it? Energy as a sustainable value creation driver @ sea

    Ocean Energies can contribute to the development of a blue economy in Europe

    provide jobs and spur economic growth. Innovation and technology will drive this new

    economy.

    TECHNOLOGY AND INNOVATION

    JOBSVALUE CREATION

    OPPORTUNITY FOR EUROPE

  • 7/28/2019 Forum Brest Maciel En

    3/37

    Agenda

    EDP and its renewable energy positioning

    Deep offshore wind rationale

    3

    WindFloat Project

    Deep offshore wind - an opportunity for Europe

  • 7/28/2019 Forum Brest Maciel En

    4/37

    #3 wind energy player in the world with 7.500 MW of installed

    capacity in 11 countries

    Canada

    UK

    France

    Belgium Poland

    -

    -

    57 1901,448

    -

    -

    US

    215

    3,422

    100

    4

    FY2011 EBITDA MW + ENEOP

    Brazil

    Under construction

    -

    84

    Installed

    Pipeline

    1,614

    PortugalSpain

    Italy

    2 58

    -

    -

    20

    80

    -

    939 2,201

    306

    -

    285

    3,850390

    618

    43

    830

    1,365

    579

    375

    7,483

    21,028

    10,193

  • 7/28/2019 Forum Brest Maciel En

    5/37

    EDPR is leading the development of up to

    2.4 GW of wind offshore projects with a

    UK Offshore Wind Partnership

    EDP is partnering with Repsol for the development of Offshore Wind

    Projects in the UK

    Inch Cape

    Moray Firth1.5 GW

    5

    0.9 GW

    Partnering with Repsol, 1st class company in Energy Sector with strong commitment to wind

    offshore capacity development

    Sites to be developed in transitional waters (30-60m of depth) , 15-25 km shore distance

    Upon getting key consents, construction and operation could begin between 2015 and 2020

  • 7/28/2019 Forum Brest Maciel En

    6/37

    Why Offshore Wind and Why Floating Offshore Wind

    Why Offshore Wind?

    Higher wind resource and less turbulence

    Large ocean areas available Best spots in wind onshore are becoming scarce

    Offshore wind, including deep offshore, has the capacity

    to deliver high quantities of energy

    6

    Why Floating Offshore Wind?

    Limited spots with shallow waters (mostly in the North

    Sea)

    Most of the resource is in deep waters

    Huge scale ocean areas available Less restrictions for offshore deployments and reduced

    visual impacts

    Enormous potential around the world: PT, Spain, UK,

    France, Norway, Italy, USA, Canada

  • 7/28/2019 Forum Brest Maciel En

    7/37

    Deep offshore wind potential goes in line with the quality of the

    resource and the availability of areas to explore

    EU15 Potential

    Good offshore wind resource (load factor > 3.000h)

    Offshore wind potential is mostly in transitional and deep waters(1) (~65 %)

    Energy Potential >700 TWh (~220 GW)

    Ports and docks available along European coast

    Depth (m) 0 - 30 40 200 +

    Offshorepotential EU15

    77 GW >140 GW

    Mean Wind speed (50m)

    (1)Analysis limited to 100m water depths

    7Source: DTI

    0 105 km

    Portuguese & Spanish Potential

    Continental shelf ends near the coast

    Grid connection available near the coast

    Limited Potential for water depths < 40m

    250 km of PT Costal Line suitable to be explored Energy Potential in PT >40 TWh (~12 GW)

    Energy Potential in SP >290 TWh (~98 GW)

    European Bathymetry

    Depth (m) 0 - 30 40 200 +

    Offshore

    potential

    PT 2 GW >10 GW

    SP 18 GW >80 GW

    Source: Univ.de Zaragoza Evaluacin Potencial Energas Renovables (2007)

    Source: Greenpeace & Garrad Hassan 2004; IEA; Global insight;

  • 7/28/2019 Forum Brest Maciel En

    8/37

    Deep offshore wind carries the potential to deliver sustained

    long term growth to the Wind Energy industry

    Medium to Long Term

    Technology consolidation

    Cost reduction

    First large scale commercial deployments

    Short to Medium Term

    First outputs of demonstration

    projects

    First successful demonstration

    projects

    High growth rates mid

    Onshore Wind

    Shallow-water

    Offshore

    Deep-water

    Offshore

    High growth continues

    driven by emerging markets

    Adequate new sites become

    scarce in most markets

    Focus on repowering

    Adequate new sites become

    very scarce

    Deep Offshore

    Wind

    Technology

    development

    milstones

    G

    W

    Short Term Medium Term Long Term

    ~2012 ~2020

    2000s reaching close to 200

    GW in 2010

    First commercial projects,

    reaching around 3GW in

    2010

    First demonstration projects

    High growth period focused

    on North Sea and a fewother smaller shallow other

    areas

    Several demonstration and

    pre-commercial projects

    First commercial projects

    High growth stage

    (potentially sustainable for a

    very long period of time)

    8

  • 7/28/2019 Forum Brest Maciel En

    9/37

    WindFloat Project

    9

  • 7/28/2019 Forum Brest Maciel En

    10/37

    The WindFloat technology its main characteristics lead to

    High Stability even in rough seas

    Turbine Agnostic

    Conventional turbine (3-blade, upwind)

    Changes required in control system of the turbine

    High Stability Performance

    Static Stability - Water Ballast

    Dynamic Stability - Heave Plates and active ballast system

    - Move latform natural res onse above the wave excitation

    10

    (entrained water)- Viscous damping reduces platform motions

    Efficiency Closed-loop Active Ballast System

    Depth Flexibility (>40m)

    Assembly & Installation

    Port assembly Reduced risk and cost

    No specialized vessels required, conventional tugs

    Industry standard mooring equipment

  • 7/28/2019 Forum Brest Maciel En

    11/37

    We are still developing the 1st phase (demonstration phase) of apotentially larger project. Next step Pre-commercial phase

    Phase 1 Demonstration

    Capacity: 2MW WindFloat prototype

    Location: Aguadoura, grid connected

    ~6 km of coast, 40 - 50 m water depth

    Turbine: 2MW offshore wind turbine

    Test period: 24+ months

    11

    Phase 2 - Pre-commercialCapacity: ~27MW (~5 WindFloat units)

    Location: Portuguese Pilot Zone

    Turbine: Likely Vestas and other, Multi MW

    Phase 3 - Commercial

    Capacity: 150MW, gradual build-out

    Location: TBD

    Turbine: TBD

  • 7/28/2019 Forum Brest Maciel En

    12/37

    The WindFloat project was structured as a Joint Venture, WindPlus

    The Project is being developed by

    12

    in a joint venture

    with the support from

    WindPlus*

    * WindPlus shareholders are edp, repsol, inovcapital, principle

    power and a. silva matos

  • 7/28/2019 Forum Brest Maciel En

    13/37

    Workshop Fabrication of main components

    A. Silva Matos was the responsabilbe for thefabrication of the WindFloat

    13

  • 7/28/2019 Forum Brest Maciel En

    14/37

    Pre-assembly of the columns

    outside the Dry-dock in Setbal

    14

  • 7/28/2019 Forum Brest Maciel En

    15/37

    Columns moved to Dry-dock

    15

  • 7/28/2019 Forum Brest Maciel En

    16/37

    Dry-dock assembly

    16

  • 7/28/2019 Forum Brest Maciel En

    17/37

    Mooring Pre-Lay in parallel

    with the fabrication

    17

  • 7/28/2019 Forum Brest Maciel En

    18/37

    Turbine Installation in the Dry Dock using the

    shipyards gantry crane

    18

  • 7/28/2019 Forum Brest Maciel En

    19/37

    WindFloat being loaded out of the dock

    19

  • 7/28/2019 Forum Brest Maciel En

    20/37

    WindFloat at the Sado Estuary, just outside the

    shipyard

    20

  • 7/28/2019 Forum Brest Maciel En

    21/37

    Tow from Setbal to Aguadoura (~400 km) using the

    same vessel that was used for the mooring installation

    21

  • 7/28/2019 Forum Brest Maciel En

    22/37

    Hook-up at final location

    22

  • 7/28/2019 Forum Brest Maciel En

    23/37

    In Operation since December 2011!

    23

  • 7/28/2019 Forum Brest Maciel En

    24/37

    The WindFloat is monitored 24 hours a day remotely

    24

  • 7/28/2019 Forum Brest Maciel En

    25/37

    Survivability and performance proved in normal and extreme

    conditions

    22 Oct 2011Installation complete

    01 Nov 201115 meters wave

    20 Dec 2011First Electron produced

    03 Jan 2012

    Operation in Hs=6m andHmax=12,6m

    25

  • 7/28/2019 Forum Brest Maciel En

    26/37

    WindFloat is commissioned and producing at full power (when

    there is enough wind!). 3 GWh and counting!

    505,2 510,2

    2.335,2

    2.526,22.500,0

    3.000,0

    500,0

    600,0

    WindFloat Turbine Performance

    Energy Produced Cummulative

    26

    125,9

    285,9 287,5

    365,8

    254,7

    191,0

    125,9

    411,8

    699,3

    1.204,5

    1.570,3 1.825,1

    -

    500,0

    1.000,0

    1.500,0

    2.000,0

    -

    100,0

    200,0

    300,0

    400,0

    January February March April May June July August

    Cumulative(MWh)

    EnergyProduced(MWh)

  • 7/28/2019 Forum Brest Maciel En

    27/37

    WindFloat is behaving well in line with the models and turbine is

    following its original power curve no losses due to motions

    1200

    1400

    1600

    1800

    2000

    ]

    27

    0 5 10 15 20 25

    0

    200

    400

    600

    800

    1000

    WindSpeed [m/s]

    Pow

    er[k

  • 7/28/2019 Forum Brest Maciel En

    28/37

    WindFloat technology can lead to 70 to 110 /MWh

    Levelized Cost of Energy (*/MWh) evolution per

    number of built platformsMain Drivers of Improvement:

    1. Increase the Power of the

    turbine as:

    The size of the platform ismostly driven by the metocean

    conditions (1)

    Turbines of 7 MW 15 MW170/MWh

    190/MWh

    210/MWh

    230/MWh3 MW

    5 MW

    7 MW

    28

    are currently in development

    (Vestas 7MW announced) andin final testing phases

    2. Improve the installation

    procedure and O&M strategy

    3. Cheaper materials

    4. Synergetic commercial activities

    50/MWh

    70/MWh

    90/MWh

    110/MWh

    130/MWh

    1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39

    10 MW

    +

  • 7/28/2019 Forum Brest Maciel En

    29/37

    The WF technology revives traditional sectors with technologicalinnovation and without significant infrastructure investments

    Share of sectors involved in the development

    of the WindFloat Prototype (%)

    Total*=23 M

    Engineering

    30%Electrical

    Equipment

    18%

    Other

    9%

    Main sectors of activity directly involved in

    the project:

    1.Engineering Services

    2.Maritime Construction - Shipyards

    3.Metal-Working

    29

    Shipyards

    31%Maritime

    Transport

    6%

    Offshore

    Equipment

    5%

    4.Maritime Transport

    5.Electrical and Electronic Equipment

    6.Offshore Equipment

    7.Legal services

    8.Financial Services - Insurance

  • 7/28/2019 Forum Brest Maciel En

    30/37

    The WindFloat technology requires highly skilled labour in Europeantraditional sectors

    Unskilled

    5%

    FTEs involved in the WindFloat Prototype (%)

    Total*=210 WindFloat Prototype

    90% of highly skilled workers

    More than 70% of European

    Suppliers

    30

    39%

    PHD

    3%

    Other

    5%

    Qualified

    Technician

    48%

    * Not including other indirect participants also involved in engineering, investment and

    management activities from A. Silva Matos, EDP Innovation, EDP Renewables and InovCapital.

    WindFloat Pre-Commercial Project

    More than 450 highly skilled

    workers involved in a three year

    project

    More than 90% of European

    Suppliers

  • 7/28/2019 Forum Brest Maciel En

    31/37

    EC R&D (and other) support schemes can have a key role in fosteringsustainable value creation at sea: Upstream and Downstream

    Upstream

    Understand the SEA SustainableValue

    31

    Downstream

    Support Projects

    Creation

    @ Sea

    USTREAM EC f d d R&D h i l

  • 7/28/2019 Forum Brest Maciel En

    32/37

    Thinking strategically about the sea and its uses

    Studying the ocean in its various dimensions

    Fauna

    Flora

    mineral resources

    wave, tidal and offshore wind resources

    Studying and characterizing the potential activities to be developed in the ocean and its impacts

    USTREAM EC funded R&D can have an important role upstream

    to the development of projects, namely

    32

    s er es

    energy exploration

    mineral exploration

    Turism

    logistics and transportation

    Developing criteria (multi-variable / clustering methodologies) to identify what activities should be promoted / favored Sustainable Value Creation should be the moto

    Partnering with the Authorities and Industry to develop maritime spatial plans to accomodate the activities taking

    place at sea

    Partnering with the Authorities and Industry to develop simplified licensing processes

    DOWNSTREAM P t ti l f l ti d i ifi t

  • 7/28/2019 Forum Brest Maciel En

    33/37

    DOWNSTREAM Potential for value creation and significant

    opportunities for collaboration between Industry and Academia

    Potential to explore / fund:

    Deep Offshore wind project development methodologies (site and resource

    characterization, environmental evaluation)

    Adaptation of Multi MW offshore wind turbines (control systems, mechanical

    33

    Offshore wind structures / foundations design

    Offshore wind structures / foundations and integrated systems certification

    Offshore wind structures construction and assembly (industrial planning, industrial

    engineering, manufacturing optimization)

    DOWNSTREAM P t ti l f l ti d i ifi t

  • 7/28/2019 Forum Brest Maciel En

    34/37

    Ports and shipyards reconfiguration and adaptation towards offshore wind systems

    construction and assembly

    Docks

    Cranes

    Offshore wind structures / foundations and integrated systems transportation and

    installation

    DOWNSTREAM Potential for value creation and significant

    opportunities for collaboration between Industry and Academia (cont)

    34

    e o o og es es prac ces consu ancy

    Vessels

    Skilled labor (training)

    Offshore wind integrated systems comissioning, testing, monitoring and life cycle

    assessment Instrumentation and monitoring of the systems

    Data analysis

    Life cycle assessment

    DOWNSTREAM Potential for value creation and significant

  • 7/28/2019 Forum Brest Maciel En

    35/37

    DOWNSTREAM Potential for value creation and significant

    opportunities for collaboration between Industry and Academia (cont)

    Offshore wind systems operation and maintenance

    Methodologies / best practices / consultancy

    Vessels

    Access systems

    Skilled labor (training)

    Offshore wind systems decomissioning

    35

  • 7/28/2019 Forum Brest Maciel En

    36/37

    Final remarks

    WindFloat Project and deep offshore wind represent a significant industrial

    opportunity for Europe - highly skilled labor and value adding activities in traditionally

    strong European sectors

    The fabrication and assembly were successfully completed. Being able to construct the

    unit in Portugal (no offshore experience) indicates that it is possible to adapt naval

    36

    infrastructures successfully and without major investments

    Offshore installation strategy successful. Supply chain breakthrough?

    The technical results of the first 6-9 months of operation of the WindFloat are very

    promising. Need to evaluate long term performance and impacts

    Pre-commercial phase is the next meaningful step to bridge the gap between

    demonstration and market

  • 7/28/2019 Forum Brest Maciel En

    37/37

    Thank You

    [email protected]

    37

    Conference Atlantic Forum

    Brest, 30th of October 2012