for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work...

233
Proposed at Shayampet (V), Geesugonda (M) & Chintalapalli (V) of Sangem (M), Warangal Rural Dist. Telangana State. Paryavaran Bhavan, A-3, I.E., Sanathnagar, Hyderabad -18 for (A Govt. of Telangana State undertaking) 6 th Floor, Parisrama Bhavan, Fateh Maidan Road, Basheerbagh, Hyderabad - 500 004 2 nd Floor, Ramky Grandiose, Gachibowli, Hyderabad - 32 NABET/EIA/1619/RA 0046 Submitted by Prepared by Submitted to

Transcript of for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work...

Page 1: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Proposed

at Shayampet (V), Geesugonda (M) & Chintalapalli (V) of Sangem (M),

Warangal Rural Dist. Telangana State.

Paryavaran Bhavan, A-3, I.E., Sanathnagar, Hyderabad -18

for

(A Govt. of Telangana State undertaking)

6th Floor, Parisrama Bhavan, Fateh Maidan Road,

Basheerbagh, Hyderabad - 500 004

2nd Floor, Ramky Grandiose, Gachibowli, Hyderabad - 32

NABET/EIA/1619/RA 0046

Submitted by

Prepared by

Submitted to

Page 2: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Table of contents

QCI/ NABET certificate 1

Declaration of experts i - iv

Terms of Reference (ToR) 4

ToR compliance i - viii

Executive summary ES1 - ES8

Sec. No. Contents Pg. No.

Chapter 1 - Introduction

1.1 Preamble 1.1

1.2 Purpose of report 1.1

1.3 Identification of project and project proponent 1.1

1.4 Brief description of nature, size, location of the project & its importance 1.2

1.5 Project Site 1.3

1.6 Salient features of Proposed Project site 1.4

1.7 Need/Justification for the Project 1.4

1.7.1 Demand Assessment 1.5

1.8 Project Development Plan 1.6

1.9 Scope of the study 1.6

1.10 Legal frame work for the implementation of EC conditions 1.7

Chapter 2 - Project Description

2.1 General 2.1

2.2 Location of the Project 2.1

2.3 Project land 2.1

2.4 Details of Industrial Estate Master Plan 2.1

2.4.1 Planning considerations 2.4

2.4.2 Overall project Site zoning 2.6

2.4.2.1 Proposed Product Mix 2.10

2.4.2.2 Proposed Production Process 2.11

2.4.3 Circulation and Road Hierarchy 2.16

2.4.4 Greenbelt 2.16

2.4.5 Common amenities/Industry related facilities 2.16

2.5 Infrastructure services and facilities 2.16

2.5.1 Water supply system 2.17

2.5.1.1 Water Demand 2.17

2.5.1.2 Reuse of Water 2.17

2.5.2 Sewage Treatment System 2.17

2.5.3 Effluent Collection and Treatment System 2.18

2.5.3.1 Design basis and treatment scheme – CETP with units and equipment 2.18

2.5.3.2 Major components of CETP 2.18

Ramky Enviro Services Pvt. Ltd. i

Page 3: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. ii

Sec. No. Contents Pg. No.

2.5.3.3 Collection & Conveyance System 2.19

2.6 Storm water management 2.20

2.6.1 Design Considerations 2.20

2.6.2 Design parameters 2.20

2.6.3 Proposed drainage system 2.20

2.7 Integrated waste Management 2.20

2.8 Power Supply 2.21

2.8.1 Power Demand 2.21

2.8.2 Transmission of Power 2.21

2.8.3 Primary Distribution 2.21

2.9 Manpower 2.22

2.10 Project Cost 2.22

2.11 Site Development 2.23

Chapter 3 - Description of the Environment

3.1 Introduction 3.1

3.2 Baseline environmental studies 3.1

3.2.1 Monitoring period 3.1

3.3 Meteorology 3.1

3.3.1 Climatic Conditions 3.3

3.3.2 Wind Pattern during study period (winter season) 3.4

3.4 Sampling Locations 3.6

3.4.1 Basis for Selection of the Monitoring Locations 3.6

3.5 Ambient air quality monitoring stations 3.6

3.5.1 Ambient Air Quality monitoring Techniques and frequency 3.6

3.5.2 Air quality scenario in the study area 3.8

3.5.3 Results and discussions 3.9

3.6 Ambient noise levels 3.9

3.6.1 Noise Levels in the Study Area 3.10

3.6.2 Results and discussions 3.12

3.7 Water environment 3.12

3.7.1 Water quality assessment 3.12

3.7.2 Results and discussion on Ground water quality 3.18

3.7.3 Results and discussion on Surface water quality 3.18

3.8 Soil 3.19

3.8.1 Soil quality 3.19

3.8.2 Criteria adopted for selection of sampling locations 3.19

3.8.3 Methodology and sampling 3.19

Page 4: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Sec. No. Contents Pg. No.

3.8.4 Results and discussions 3.23

3.9 Traffic study 3.23

3.9.1 Details of traffic study 3.23

3.10 Land use Land cover 3.26

3.10.1 Satellite Imagery 3.27

3.10.2 Land Use pattern 3.27

3.10.3 Land use pattern in and around project site (10 Km radius) 3.27

3.11 Biological Environment 3.31

3.11.1 General description of the study area 3.31

3.11.2 Objectives of Ecological Study 3.31

3.11.3 Methods for the study 3.31

3.11.3.1 Review of secondary data and environmental setting of the project site 3.32

3.11.3.2 Ecological Status 3.32

3.11.3.2.1 Terrestrial vegetation and flora of the core zone 3.32

3.11.3.2.2 Vegetation and Flora of the Buffer zone 3.32

3.11.3.2.3 Terrestrial fauna of the Core area and the Buffer zone 3.34

3.11.3.2.4 Aquatic flora and fauna 3.37

3.11.4 Identification of Environmentally sensitive places/ local protected species 3.38

3.11.5 Greenbelt development 3.40

3.12 Socio-economics 3.40

3.12.1 Demography and Socio-Economics (Secondary Data Description) 3.40

3.12.2 Methodology Adopted for the Study 3.40

3.12.3 Demographic Aspects 3.41

3.12.3.1 Distribution of Population 3.41

3.12.3.2 Average Household Size 3.41

3.12.3.3 Population Density 3.41

3.12.3.4 Sex Ratio 3.42

3.12.4 Social Structure 3.42

3.12.5 Literacy Levels 3.42

3.12.6 Occupational Structure 3.43

3.12.6.1 Dependency Ratio 3.44

3.12.6.2 Infrastructure and accessibility, Primary Observations in the Core Zone 3.44

3.12.7 CSR Works would Carry Out in Future 3.46

3.12.8 Suggestions for Improvement of Socio-Economic Status 3.46

Chapter 4 - Anticipated Environmental Impacts& Mitigation Measures

4.1 Introduction 4.1

4.2 Impact during construction phase 4.1

4.2.1 Impact on air quality 4.1

4.2.1.1 Proposed mitigation measures 4.2

Ramky Enviro Services Pvt. Ltd. iii

Page 5: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Sec. No. Contents Pg. No.

4.2.2 Impact on water quality 4.2

4.2.2.1 Mitigation measures 4.3

4.2.3 Impact on noise levels 4.3

4.2.3.1 Mitigation measures 4.3

4.2.4 Impacts due to solid waste generation 4.4

4.2.4.1 Mitigation measures 4.4

4.2.5 Impact on land use 4.5

4.2.6 Impact on demography and socio-economics 4.5

4.3 Impacts during operation 4.6

4.3.1 Impact on topography and climate 4.6

4.3.2 Impact on air quality 4.6

4.3.2.1 Emission details 4.6

4.3.2.2 Stimulation model for prediction 4.7

4.3.2.3 Model inputs and results 4.8

4.3.2.4 Mitigation measures 4.11

4.4 Impact on odour 4.11

4.4.1 Sources of odour 4.12

4.4.2 Odour mitigation measures 4.12

4.4.3 Impact on water quality 4.13

4.4.3.1 Wastewater generation 4.13

4.4.3.2 Reuse of water 4.14

4.4.3.3 Sewage Treatment System 4.14

4.4.3.4 Effluent Collection and Treatment System 4.14

4.4.3.5 Design Basis and Treatment Scheme – CETP with Units and Equipment 4.16

4.4.3.6 Major components of CETP 4.16

4.4.3.7 Collection & Conveyance System 4.16

4.4.3.8 CETP – Treatment system 4.17

4.4.3.9 CETP - Reverse Osmosis System 4.18

4.4.3.10 CETP Evaporator 4.19

4.5 Rainwater harvesting and storm water runoff 4.21

4.6 Solid waste management 4.21

4.6.1 Solid waste generation during operational phase 4.21

4.6.2 Mitigation measures 4.22

4.7 Impact on traffic 4.22

4.7.1 Mitigation measures 4.24

4.8 Positive and negative socio-economic impacts in study area 4.24

4.8.1 Positive impacts 4.24

4.8.2 Negative impacts 4.24

Ramky Enviro Services Pvt. Ltd. iv

Page 6: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Sec. No. Contents Pg. No.

4.9 Greenbelt development 4.25

4.9.1 Mitigation of impacts by greenbelt 4.25

4.10 Overall view of impacts due to proposed project 4.29

Chapter 5 – Analysis of Alternatives

5.1 Alternative site locations 5.1

5.2 Introduction 5.1

5.3 Siting criteria 5.2

5.4 Site selection 5.4

5.5 Mitigation measures 5.5

5.6 Alternative energy 5.8

5.7 Assessment of Various Treatment Technologies for Textile Dyeing

Effluent 5.8

5.8 Advanced Treatment Technology options for ZLD 5.12

5.8.1 Electro oxidation system for color removal 5.12

5.8.2 High Pressure Plate & Tube RO (HPPTRO) 5.12

5.8.3 Replacement of Solar pans with ATFD to avoid overflow of pans 5.13

5.8.4 Advanced technologies for textile effluent treatment 5.13

5.9 Resources recovery from the ZLD CETP 5.13

Chapter 6 – Environmental Monitoring Program

6.1 Introduction 6.1

6.1.1 Construction phase 6.2

6.1.2 Operational phase 6.4

6.2 Environmental laboratory equipment 6.5

6.3 Organizational setup of environmental management 6.6

6.4 Reporting schedules of the monitoring data 6.6

6.5 Wastewater Treatment and Disposal - Monitoring Mechanism 6.6

6.5.1 Real time Monitoring Mechanism at Industry level 6.6

6.5.2 Monitoring at CETP Level 6.7

6.5.3 Environmental Monitoring by Industry Member 6.7

6.6 Compliance reports 6.9

6.7 Plantation monitoring programme 6.9

6.8 On-site mock drills requirements 6.9

6.9 Budget estimates 6.10

Chapter 7 – Additional Studies

7.1 Safety management plan 7.1

7.1.1 Safety Policy 7.1

7.1.2 Safety plan 7.3

7.2 Safety in organization 7.4

7.2.1 Construction and erection phase 7.4

Ramky Enviro Services Pvt. Ltd. v

Page 7: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Sec. No. Contents Pg. No.

7.2.2 Operation and maintenance phase 7.4

7.3 Risk assessment plan 7.4

7.4 Inventory at site 7.4

7.5 Hazard identification and preliminary hazard analysis 7.5

7.5.1 Introduction to hazard identification 7.5

7.5.2 Identification of major hazardous units 7.5

7.5.3 Classification based on inventory rating 7.5

7.5.4 Identification of major hazard installations based on MSIHC Rules 1989,

amended rules 2000 7.5

7.6 Short listed hazards 7.7

7.7 Maximum credible accident analysis 7.7

7.8 Injuries resulting from flammable liquids 7.8

7.9 Pool fire analysis of HSD tanks 7.9

7.9.1 Pool fire of HSD storage tanks 7.9

7.9.2 Damage distance computations for Maximum Credible Accident analysis 7.12

7.10 Disaster management plan (DMP) 7.12

7.10.1 On-site disaster management Plan 7.13

7.10.1.1 Control centre 7.13

7.10.1.2 Fire prevention facilities 7.13

7.10.1.3 Assembly points 7.14

7.10.1.4 The key personnel for on-site emergency 7.14

7.10.1.5 Alarm system 7.16

7.10.1.6 Communication system 7.16

7.10.1.7 Siren for emergency 7.16

7.10.1.8 Escape route 7.16

7.10.1.9 Evacuation 7.16

7.10.1.10 Counting of personnel 7.16

7.10.1.11 All clear signal 7.16

7.10.1.12 Emergency facilities 7.17

7.10.2 Off-site disaster management plan 7.17

7.11 Occupational health and safety 7.19

7.11.1 Introduction 7.19

7.11.2 Occupational health 7.19

7.12 Geological and hydrogeology 7.21

7.12.1 Introduction 7.21

7.12.2 Topography 7.22

7.12.3 Soils 7.23

Ramky Enviro Services Pvt. Ltd. vi

Page 8: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Sec. No. Contents Pg. No.

7.12.4 Geology 7.23

7.12.5 Hydrogeology 7.23

7.12.5.1 Hydrological Assessment 7.24

7.12.5.2 Groundwater mode and occurrence 7.27

7.12.6 Groundwater classification as per the Central Ground Water Authority 7.27

7.12.7 Storm water drainage system and run off estimate 7.27

Chapter 8 - Project Benefits

8.1 Introduction 8.1

8.2 Infrastructure facilities 8.1

8.2.1 Physical and social infrastructure 8.1

8.3 Induced Development 8.1

8.4 Improved socio economic condition 8.2

8.4.1 Quality of life 8.2

8.4.2 Health facilities 8.2

8.4.3 Skill development activities 8.3

8.5 Employment opportunities 8.3

8.6 Revenue generation 8.3

8.7 Implementation and funding 8.4

Chapter 9 – Environmental Management Plan

9.1 Introduction 9.1

9.2 Environmental management during constructional stage 9.1

9.2.1 Air quality mitigation measures 9.1

9.2.2 Water quality mitigation measures 9.2

9.2.3 Noise mitigation measures 9.2

9.2.4 Solid waste mitigation measures 9.2

9.2.5 Ecological aspects 9.3

9.2.6 Site security 9.4

9.3 Management during operation stage 9.4

9.3.1 Air quality management 9.4

9.3.2 Water and wastewater quality management 9.5

9.3.3 Rain water harvesting and storm water management 9.5

9.4 Noise level management 9.5

9.5 Solid waste management 9.6

9.6 Greenbelt development 9.6

9.7 Fire protection services 9.7

Chapter 10 – Summary and Conclusion

10.1 Project objectives 10.1

10.2 Project background 10.2

Ramky Enviro Services Pvt. Ltd. vii

Page 9: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Sec. No. Contents Pg. No.

10.3 Proposed project 10.2

10.4 Description of Environment 10.3

10.5 Estimated project cost 10.5

10.6 Proposed means of finance 10.5

10.7 Conclusion 10.5

Chapter 11- Disclosure of Consultants

11.1 About the group 11.1

11.2 About the accredited consultant organization 11.2

11.2.1 Consultancy services 11.2

11.2.2 Laboratory services 11.3

11.2.3 Training services 11.3

11.2.4 Field services 11.3

11.2.5 Treatment plant service 11.4

11.2.6 Solid waste management services 11.4

11.3 Declaration by Accredited Consultant Organization 11.4

Ramky Enviro Services Pvt. Ltd. viii

Page 10: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

List of Tables

Table No. Contents Page No.

1.1 Categorization of the Project 1.2

1.2 Salient Features of project site 1.4

2.1 Project land use details 2.1

2.2 Proposed phasing plan 2.6

2.3 Summary of capacities & area requirement 2.10

2.4 Proposed product mix 2.10

2.5 Water balance ( MLD) 2.17

2.6 Manpower details 2.22

2.7 Estimated project cost for phased development 2.23

3.1 Meteorological Data – Statistics 3.2

3.2 Micro Meteorological Data 3.4

3.3 Frequency distribution Table – winter season (Dec’2016 to Feb’2017) 3.5

3.4 Details of AAQ monitoring locations 3.6

3.5 PM 10, 2.5, SO2, NOx, O3 & CO levels in the study area (µg/m3) 3.8

3.6 Details of Noise Monitoring Locations in the study area 3.10

3.7 Day and Night Equivalent Noise Levels 3.10

3.8 Water sampling locations 3.13

3.9 Groundwater sample analysis results 3.16

3.10 Surface water sample analysis results 3.17

3.11 Soil sampling locations 3.20

3.12 Soil analysis results 3.22

3.13 Traffic survey on Warangal - Narsampet road (To & Fro) 3.24

3.14 Traffic survey at Ookal Junction (Warangal – Narsampet road to Site 3.25

3.15 Traffic survey at Vanchanagiri Junction (Warangal - Narsampet road to

Site via Shayampet (To & Fro)

3.26

3.16 Details of satellite Imageries 3.27

3.17 Land use in the project area 3.27

3.18 Land use pattern in project influenced area 3.27

3.19 Land use pattern in Project core area 3.29

3.20 List of trees, shrubs & perennial climbers found in the buffer zone 3.33

3.21 List of vertebrates other than birds 3.34

3.22 List of Birds either spotted or reported from the areas in and around the

project site. WPA indicates Schedule number in the Indian WLP Act

3.35

3.23 List of aquatic / semi aquatic macrophytes found in the surface water

bodies of the buffer zone

3.37

3.24 List of fishes either caught by the fisherman/reported in the study area 3.38

Ramky Enviro Services Pvt. Ltd. ix

Page 11: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Table No. Contents Page No.

3.25 Greenbelt and landscaping details 3.40

3.26 Distribution of Population in Core and Buffer Zone 3.41

3.27 Population projections in the study area 3.42

3.28 Distribution of Population by Social Structure in Core& Buffer zone 3.42

3.29 Distribution of Literate and Literacy Rates in Core and Buffer Zone 3.43

3.30 Occupational Structure in Core and Buffer Zone 3.43

3.31 Socio economic details of the study area – Census 2011 3.48

3.32 Occupational Structure & employment scenario 3.50

4.1 24 hour mean meteorological data for winter season-Dec’2016 to Feb 17 4.8

4.2 Stack and emission details of proposed DG Sets & Boilers 4.9

4.3 Post project scenario 4.9

4.4 water requirement and wastewater generation 4.13

4.5 Industrial wastewater and CETP (post-treatment) characteristics 4.13

4.6 Domestic wastewater and CSTP (post-treatment) characteristics 4.13

4.7 Solid Waste Generation Details 4.22

4.8 Sludge Solid Waste Generation Details 4.22

4.9 Traffic details through Warangal – Sangem approach road 4.23

4.10 Traffic details through Warangal – Vanchanagiri approach road 4.23

4.11 Proposed level of service 4.24

4.12 Greenbelt and landscaping details 4.25

4.13 List of plant identified for greenbelt & avenue plantation 4.27

4.14 Overview of potential impacts due to proposed project 4.29

5.1 Site selection criteria – areas to be avoided 5.1

5.2 Site suitability based on the industrial siting guidelines/criteria 5.3

5.3 Assessment of various treatment technology options for ZLD CETP 5.10

5.4 Quality of recovery products 5.14

6.1 Environmental Monitoring during Constructional Phase 6.2

6.2 Environmental monitoring during operational phase 6.4

6.3 List of equipment proposed for environmental laboratory 6.5

7.1 Storage Capacity in project site 7.4

7.2 Summary table on the Inventories 7.5

7.3 Properties of fuel employed 7.5

7.4 Indicative criteria for identification of toxic, flammable and

explosive chemicals (MSIHC Rules 1989, amended 2000)

7.6

7.5 Applicability of MSIHC rules to storages 7.7

7.6 Short listed hazards 7.7

7.7 Mathematical models and analytical models for hazard analysis 7.8

Ramky Enviro Services Pvt. Ltd. x

Page 12: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Table No. Contents Page No.

7.8 Damage criteria 7.8

7.9 Radiation exposure and lethality 7.8

7.10 F&EI of fuels used for the proposed MTP 7.9

7.11 Onsite emergency key personnel – roles and responsibilities 7.14

7.12 Occupational health hazards with permissible limits and mitigation 7.20

7.13 Action plan for implementation of OHS standard 7.21

7.14 Runoff calculation for streams 7.28

7.15 Runoff estimation of project site 7.29

9.1 Air pollution control measures 9.4

10.1 Estimated project cost for phased development 10.5

List of Figures

Fig. No Contents Pg. No.

1.1 Photographs of the site and its surrounding areas 1.3

2.1 Location map of the proposed project site 2.2

2.2 Conceptual master plan for the Mega Textile Park 2.3

2.3 Proposed dedicated access road 2.5

2.4 Regional road connectivity 2.5

2.5 Zoning in project area 2.7

2.6 Proposed project concepts 2.8

2.7 Positioning of the Mega Textile Park 2.9

2.8 Basic Textile Manufacturing process flow chart 2.11

2.9 Process flow chart for cotton yarn ring spinning 2.12

2.10 Process flow for Cotton Yarn Open end spinning 2.12

2.11 Process flow chart for circular Knitting 2.13

2.12 Basic process flow chart of weaving 2.14

2.13 Yarn dying 2.14

2.14 Process for manufacturing woven garment 2.15

2.15 CETP schematic flow chart 2.18

2.16 Schematic collection and conveyance system of CETP 2.19

3.1 Average temperature graph (2010-2016) 3.3

3.2 Average rainfall graph (2010-2016) 3.3

3.3 Wind rose diagram for the winter season (Dec’2016 to Feb’2017) 3.5

3.4 Ambient Air Quality Monitoring Locations 3.7

3.5 Noise level monitoring locations 3.11

3.6 Ground water sampling locations 3.14

3.7 Surface water sampling locations 3.15

3.8 Soil monitoring locations 3.21

Ramky Enviro Services Pvt. Ltd. xi

Page 13: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Fig. No Contents Pg. No.

3.9 Land use land cover map 3.28

3.10 Land use pattern in project core area 3.29

3.11 Satellite imagery of the site & study area 3.30

3.12 Sensitivity map of the project site 3.39

4.1 Predicted 24-hourly average GLCs of PM (µg/m3) 4.10

4.2 Predicted 24-hourly average GLCs of SO2 (µg/m

3) 4.10

4.3 Predicted 24-hourly average GLCs of NOx (µg/m

3) 4.11

4.4 Schematic flow diagram of CSTP 4.15

4.5 Schematic flow diagram of CETP 4.16

4.6 Schematic collection and conveyance system of CETP 4.17

4.7 Colour and hardness removal system 4.18

4.8 Reverse Osmosis 4.19

4.9 Sodium Sulphates recovery rejects management system 4.19

4.10 Schematic flow chart of CETP 4.20

5.1 Location map of the alternate site 1 5.4

5.2 Location map of the selected site (Proposed Site-2) 5.5

5.3 Access from Gangadevipally and Dedicated RoB for the Project Site 5.6

5.4 Access from Gangadevipally and Proposed RoB over LC 67 (Including

two Alternatives within Project Site) 5.7

5.5 Access from Machapur, bypasssing Chintalapalli and RoB over LC 67 5.8

6.1 Organizational set-up for environmental management 6.6

6.2 Collection and Conveyance system of CETP 6.8

6.3 Web based on-line Monitoring system 6.8

7.1 Thermal Radiation Threat Zone 7.10

7.2 Aloha source point on the layout 7.11

7.3 Contour map 7.22

7.4 Drainage map 7.23

7.5 Surface profile of project site 7.24

7.6 Demarcated catchment area map for existing streams in the site 7.25

7.7 Lineament map 7.25

7.8 Map of micro watershed 7.26

7.9 Map showing buffer zone areas for existing stream protection 7.26

7.10 Rainfall trend graph 7.28

Ramky Enviro Services Pvt. Ltd. xii

Page 14: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General
Page 15: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Declaration by Experts contributing to the EIA – Proposed “Mega Textile Park” at Shayampet (V) of Geesugonda (M) and Chintalapalli (V) of Sangem (M) Warangal Rural (D), Telangana by

M/s. Telangana State Industrial Infrastructure Corporation Ltd.

I, hereby, certify that I was a part of the EIA team in the following capacity that developed this EIA report. EIA Coordinator: Name : Dr. B. Chakradhar Sign & Date : Period of involvement : November, 2016 – Till date Contact information : [email protected] Functional Area Experts:

S.No Functional

Area Name of the Expert

Involvement Sign & Date

Period Task

1 AP Mr. V. Vijay Kumar Nov, 2016 – Till

date

Selecting ambient air monitoring

sites based on IMD data, Review of

the meteorological data and AAQ

data, suggesting air pollution

control measures

2 WP Dr. Hemanth

Rajkumar

Nov, 2016 –

Till date

Identification of water monitoring

sites, estimating water

requirements & waste water

treatment methods

3 SHW Dr. B. Chakradhar Nov, 2016 –

Till date

Inventorization of wastes,

suggesting treatment measures

4 SE Mr. M. A Fasi Nov, 2016 –

Till date

Generating primary data &

estimating economic, infrastructure

& employment benefits

5 EB Mr. M. A Fasi Nov, 2016 –

Till date

Collected secondary data from

forest department, field studies for

generation of primary flora and

fauna data & suggested species for

greenbelt development

6 AQ Mr. M. Vishnu

Vardhan Reddy

Nov, 2016 –

Till date

Meteorological & Air Pollution

dispersion studies, suggesting

environmental management plan

for air pollution control

7 LU Dr. G.V.A.

Ramakrishna

Nov, 2016 –

Till date

Collection of GPS readings for

identification of topo sheets and

satellite imagery, preparation of

base map from topo sheets,

preparation of monitoring location

map

Page 16: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

S.No Functional

Area Name of the Expert

Involvement Sign & Date

Period Task

8 HG Mr. B. Mallikarjuna

Rao

Nov, 2016 –

Till date

Measurement of ground water

levels from the existing wells

present in and around project site,

observation of surface water

bodies, establishing groundwater

flow direction and its gradient and

evaluation of rainfall data and

identification of development of

monitoring wells. Identification of

natural drainage pattern.

Suggesting suitable storm water

management plan.

9 GEO Mr. B. Mallikarjuna

Rao

Nov, 2016 –

Till date

Observations made towards the

identification of country rock,

development of porosity, thickness

and extent of weathered formation

area seismicity and evaluation of

soil permeability for suggesting

suitable civil structures.

10 RH Mr. M. Santosh

Kumar

Feb, 2017 –

Till date

Estimating risks such as

construction failures, electrical or

civil accidents, fires etc., &

suggesting control measures

Declaration by the Head of the accredited consultant organization/ authorized person: I, Dr. B. Chakradhar, hereby, confirm that the above mentioned experts prepared the EIA Report for the

“Proposed Mega Textile Park at Shayampet (V) of Geesugonda (M) and Chintalapalli (V) of Sangem (M)

Warangal Rural (D), Telangana State” by M/s. Telangana State Industrial Infrastructure Corporation (TSIIC)

Ltd. I also confirm that the consultant organization shall be fully accountable for any misleading information

mentioned in this statement.

Signature :

Name : Dr. B. Chakradhar

Designation : Vice President

Name of the EIA Consultant Organization : Ramky Enviro Services Private Limited

NABET Certificate No. & Issue Date : NABET/EIA/1619/RA 0046

Page 17: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

QCI-NABET Scheme for Accreditation of EIA Consultant Organizations: Version 3

1 Format for information on Team Member -Version 3, Rev 1 Sep 2015

Annexure – IE

Format for information on Team Member

(Only for in-house employees)

Name of project: Proposed “Mega Textile Park” at Shayampet (V) of Geesugonda (M) and Chintalapalli (V) of Sangem (M) Warangal (D), Telangana State by M/s. Telangana State Industrial Infrastructure Corporation Ltd.

1. Name and address of EIA consultant organization

M/s. Ramky Enviro Services Private Limited

Ramky Grandiose, 2nd Floor,

Ramky Tower Complex, Gachibowli,

Hyderabad – 500 032

a. Head Office : b. Branch Office/s :

2. Name of the head of the organization with designation

Dr. B. Chakradhar

Vice President & Head

3. Contact details with name of the contact person

a. Name of Contact person Dr. B. Chakradhar Address M/s. Ramky Enviro Services Private Limited

Ramky Grandiose, 2nd Floor,

Ramky Tower Complex, Gachibowli,

Hyderabad – 500 032

b. Tel. No. 040 23015406 Mob. : +91-9000604455

c. Email: [email protected] Alt. Email : [email protected]

d. Website: www.ramky.com

Page 18: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

QCI-NABET Scheme for Accreditation of EIA Consultant Organizations: Version 3

2 Format for information on Team Member -Version 3, Rev 1 Sep 2015

4. Team Members proposed

Sl Name Qualification#

EC/

FAE

Sector/

FA

Approved

Sr. Expert Jobs to be assigned

With EIA Coordinator

1 Mr. M A Fasi M.Sc.- Environmental

Sciences (Year of

Passing – 2003)

M.Sc. – Psychology

(Year of Passing – 2013)

EC 31- 7(c) Dr. B. Chakradhar Survey of the site for

identifying the sensitive

issues related to land,

human resources etc.,

and also identify

baseline data

generation to evolve

adverse impacts due to

the project.

With Functional Area Expert

1 Mr. M A Fasi M.Sc.- Environmental

Sciences (Year of

Passing – 2003)

M.Sc. – Psychology

(Year of Passing – 2013)

FAE AP Mr. V. Vijay

Kumar

Identifying the air

pollution control

equipments to mitigate

air quality impacts due

to the textile process

operations. # Qualification – Bachelor degree in Technical subjects and Master’s degree in Science, Humanities

and other subjects, year of passing and name of university

Declaration by the employer

We have carefully read the provisions in respect of ‘Team Members’ in the NABET’s Scheme for

accreditation of EIA Consultants organizations and commit to abide by the same. The conformity of

eligibility of the candidates proposed as Team Member in respect of qualification and other

aspects has been verified by us at our end. We confirm that the information provided in the

application is correct to the best of our knowledge and belief.

We understand that in case the information provided is found wrong/mis-leading, it may result in

cancellation of accreditation granted to the organization.

Signature Name (authorized signatory) Designation

Organization Date

Dr. B. Chakradhar

Vice President & Head

M/s. Ramky Enviro Services Private Limited

15/04/2017

Page 19: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

State Level Environment Imnact Assessment Authori

Ministrv of Environment Forests & Climate ChangeA-3. Inclustrial Estate. Sanathnasar. Hyderabad-500 0 1 8.

Lr.No. SEIAA/TS/OLAilGL- 1 8/20 1 7- Dt:17.03 .2017 .

To

Sri A.'Laxmikantha Reddy, Chief Engineer,sth Floofo Parisrama Bhavanam,Fateh Maidan Road, Basheerbagh,Hyderabad - 500 004Ph;h{o. 040 23237625,040 23237626Email : [email protected]

'\S-nb: SEAC - "Proposed Mega Textile ParK' of M/s. TSIIC, at Shayampet (V)'..." Geesugond" (fvl) and =Chintalapalli (V) Sangem (M), Warangal- Dist.-, Enyironmental Clearance - TORs issued - Reg.

Ref: Your EC application received:on 04.02.2017.

With reference to your EC application received online for the above mentioned project, it is to informthat the proposal was examined by the State Expert Appraisal Committee (SEAC) in its meeting heldon21.02.2017. The SEAC observed as following:

The representative of the project proponent Sri K. Shyam Sunder; and Sri V. Vrjay Kumar ofI{/s. Ramlcy Enviro Engineers Ltd., Hyderabad attended and made a presentation before theSEAC. i

It is noted that homogenous type of inclustries (Spinning, Weaving, Knitting, Processing,Madeups, Apperal/ Readymade Garments,) are proposed in the Textile Park in an total area of481.85 Ha. It is also note that the proponent is also proposing a CETP in the Textile Park.The proponent informed that they have already started monitoring from December 2016 andrequested to consider the baseline datafor the periodfrom December 2016 to February 2017

After detailed discussions, the SEAC dbcided to consider the request of the proponent forusing the baseline datafor the periodfrom December 2016 to February 2017 for preparationof EIA report.

Hence, the proponent is directed n i)repare EIA report as per the Standard Terms ofReference (IOR) issued by the MoEF&CC, GoI available in their website viz.,v,wu,.moef.nic.in. under "7(C) Industrial estates/ parks/ complexes/ areas, export processingZones (EPZs), Special Economic Zones (SEZs), Biotech Parks, Leather Complexes"; undergothe process of public hearing in consultation with TSPCB and submit final EIA report alongwith minutes of public hearing & r,esponse of the proponent to the issues emerged in thepublic hearing to the SEACfor appraisal.

,In view of the above, you are directed to prepare EIA report as mentioned above, undergo the processof public hearing in consultation with TSPCB and submit final EIA report along with minutes ofpublic hearing & response of the proponent to the issues emerged in the public hearing to the SEACfor appraisal.

Yours faithfully,

SECRETARY, SEAC, TSllr.c.F.B.o//

Q*q1o.^SENIOR ENVIRONMENTAL ENGINEER

35 q3

(IJnit - ilD

Page 20: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

235

STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FORPROJECTS/ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE

7(c):STANDARD TERMS OF REFERENCE FOR CONDUCTINGENVIRONMENT IMPACT ASSESSMENT STUDY FOR INDUSTRIALESTATES/ PARKS/ COMPLEXES/ AREAS, EXPORT PROCESSINGZONES (EPZS), SPECIAL ECONOMIC ZONES (SEZS), BIOTECHPARKS, LEATHER COMPLEXES AND INFORMATION TO BEINCLUDED IN EIA/EMP REPORT

1) Reasons for selecting the site with details of alternate sites examined/rejected/selected on merit withcomparative statement and reason/basis for selection. The examination should justify site suitabilityin terms of environmental damage, resources sustainability associated with selected site as comparedto rejected sites. The analysis should include parameters considered along with weightage criteriafor short-listing selected site.

2) Submit the details of the land use break-up for the proposed project. Details of land use around 10km radius of the project site. Analysis should be made based on latest satellite imagery for land usewith raw images. Check on flood plain of any river.

3) Submit details of environmentally sensitive places, land acquisition status, rehabilitation of communities/villages and present status of such activities.

4) Examine the impact of proposed project on the nearest settlements.

5) Examine baseline environmental quality along with projected incremental load due to the projecttaking into account of the existing developments nearby.

6) Environmental data to be considered in relation to the project development would be (a) land, (b)groundwater, (c) surface water, (d) air, (e) bio-diversity, (f) noise and vibrations, (g) socio economicand health.

7) Submit a copy of the contour plan with slopes, drainage pattern of the site and surrounding area, andany obstruction of the sme by the project.

8) Details regarding project boundary passing through any eco- sensitive area and within 10 km fromeco- sensitive area.

9) Green buffer in the form of green belt to a width of 15 meters should be provided all along theperiphery of the industrial area. The individual units should keep 33% of the allotted area as a greenarea.

10) Submit the details of the trees to be felled for the project.

11) Submit the details of the infrastructure to be developed.

12) Submit the present land use and permission required for any conversion such as forest, agricultureetc.

13) Submit details regarding R&R involved in the project

Page 21: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

236

STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR PROJECTS/ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE

14) Zoning of the area in terms of 'type of industries' coming-up in the industrial area based on theresource requirement along with likely pollutants with quantity from the various industries.

15) The project boundary area and study area for which the base line data is generated should beindicated through a suitable map. Justification of the parameters, frequency and locations shall bediscussed in the EIA.

16) Submit Legal frame work for the implementation of Environmental Clearance conditions - to beclearly spelt out in the EIA report.

17) Submit Roles and responsibility of the developer etc for compliance of environmental regulationsunder the provisions of EP Act.

18) Site justification of the identified industry sectors from environmental angle and the details of thestudies conducted if any.

19) Ground water classification as per the Central Ground Water Authority.

20) Submit the source of water, requirement vis-à-vis waste water to be generated along with treatmentfacilities, use of treated waste water along with water balance chart taking into account all forms ofwater use and management.

21) Rain water harvesting proposals should be made with due safeguards for ground water quality.Maximize recycling of water and utilization of rain water. Examine details.

22) Examine soil characteristics and depth of ground water table for rainwater harvesting.

23) Examine details of solid waste generation treatment and its disposal.

24) Examine and submit details of use of solar energy and alternative source of energy to reduce thefossil energy consumption.

25) In case DG sets are likely to be used during construction and operational phase of the project,emissions from DG sets must be taken into consideration while estimating the impacts on airenvironment. Examine and submit details.

26) Examine road/rail connectivity to the project site and impact on the traffic due to the proposedproject. Present and future traffic and transport facilities for the region should be analysed withmeasures for preventing traffic congestion and providing faster trouble free system to reach differentdestinations in the city.

27) A detailed traffic and transportation study should be made for existing and projected passenger andcargo traffic.

28) Examine the details of transport of materials for construction which should include source andavailability.

29) Examine the details of National Highways/State Highways/ expressways falling along the corridorand the impact of the development on them.

30) Examine noise levels - present and future with noise abatement measures.

Page 22: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

237

STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FORPROJECTS/ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE

31) Identify, predict and assess the environmental and sociological impacts on account of the project. Adetailed description with costs estimates of CSR should be incorporated in the EIA / EMP report.

32) Examine separately the details for construction and operation phases both for EnvironmentalManagement Plan and Environmental Monitoring Plan with cost and parameters.

33) Submit details of a comprehensive Disaster Management Plan including emergency evacuationduring natural and man-made disaster.

34) The Public hearing should be conducted for the project in accordance with provisions of EnvironmentalImpact Assessment Notification, 2006 and the issues raised by the public should be addressed in theEnvironmental Management Plan. The Public Hearing should be conducted based on the TOR letterissued by the Ministry and not on the basis of Minutes of the Meeting available on the web-site.

35) A detailed draft EIA/EMP report should be prepared in accordance with the above additional TORand should be submitted to the Ministry in accordance with the Notification.

36) Details of litigation pending against the project, if any, with direction /order passed by any Court ofLaw against the Project should be given.

37) The cost of the Project (capital cost and recurring cost) as well as the cost towards implementationof EMP should be clearly spelt out.

38) Any further clarification on carrying out the above studies including anticipated impacts due to theproject and mitigative measure, project proponent can refer to the model ToR available on Ministrywebsite "http://moef.nic.in/Manual/Industrial Estate".

*****

Page 23: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. i

EIA Report for Proposed Mega Textile Park at Warangal

ToR Compliance

S.No ToR point Compliance

1 Reasons for selecting the site with details of

alternate sites examined/rejected/selected on merit

with comparative statement and reason/basis for

selection. The examination should justify site

suitability in terms of environmental damage,

resources sustainability associated with selected site

as compared to rejected sites. The analysis should

include parameters considered along with weightage

criteria for short-listing selected site.

Site selection was done keeping in view of

the following points.

- No Ecologically sensitive area is present

around 10 Km, the major water body is

Yelgur Lake which is 2.5 Km away from

the site boundary towards SE.

- Chintalapalli railway station is passing

along the boundary line. The major road

Warangal-Narsampet road is 3.5 Km

away from the site towards N. No high

tension line passing through the site.

- The nearest village of Shayampet 200 m

away from the site.

- No critically polluted area around the

project within 15 Km.

- No forest land involved for the project

development.

- The total land of the project is agricultural

private patta land.

- Well connected by road, rail and air

- The surrounding area is highly cotton

cultivated.

- Several cotton processing industries were

present the surrounding area.

- Availability of skilled man power.

- Government’s positive attitude towards

the industrialization.

2 Submit the details of the land use break-up for the

proposed project. Details of land use around 10 km

radius of the project site. Analysis should be made

based on latest satellite imagery for land use with

raw images. Check on flood plain of any river.

The Land use breakup details given in

Chapter-2 of Table 2.1. The land use around

10km radius of the study area occupies

agriculture land about 85.4%, Buildup area

3.18%, forest land 3%, waste lands 2% and

water bodies 6.42%. The details of land use

pattern given in Chapter-3; Table-3.18.

Analysis was made based on latest satellite

imagery for land use with raw images. There

is no river nearby for flood plain.

3 Submit details of environmentally sensitive places,

land acquisition status, rehabilitation of communities/

There are no environmentally sensitive

places within the 10 Km radius of the

Page 24: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

S.No ToR point Compliance

villages and present status of such activities. proposed project. The total land is under

possession of TSIIC. There is no

rehabilitation of communities/Villages.

4 Examine the impact of proposed project on the

nearest settlements.

Details of anticipated generic environmental

impacts due to this project during

construction and operational phase are given

Chapter-4 under section-4.2 & 4.3 and

mitigations were discussed under sub-

sections.

5 Examine baseline environmental quality along with

projected incremental load due to the project taking

into account of the existing developments nearby.

Baseline studies were conducted during

winter season (December 2016 to February

2017) is given in Chapter-3. And the

incremental loads and its impacts and

mitigations were discussed in Chapter-4.

6 Environmental data to be considered in relation to

the project development would be (a) land (b)

groundwater (c) surface water (d) air (e) bio-diversity

(f) noise and vibrations (g) socio economic and

health.

Environmental data is collected and in

discussed in detail with respect to land,

ground water, surface water, air, biodiversity,

noise & vibrations and socio-economics,

health & safety etc are given in Chapter-3

7 Submit a copy of the contour plan with slopes,

drainage pattern of the site and surrounding area,

and any obstruction of the same by the project.

The contour map of the proposed site and

surrounding area is shown in Chapter-7 in

Figure-7.2. Depicting the site area is mostly

a plain land. The drainage pattern of the

study area is given in Chapter-7 under sub-

section-7.12.2 indicating the flow pattern

from dendritic to sub-dendritic. Drainage map

is given in Figure-7.3.

8 Details regarding project boundary passing through

any eco-sensitive area and within 10 km from eco-

sensitive area.

The project area and the study area are

devoid of any eco sensitive area. The

sensitivity map of the study area is shown in

Chapter-3 in Figure-3.11.

9 Green buffer in the form of green belt to a width of 15

meters should be provided all along the periphery of

the industrial area. The Total Green belt of Industrial

estate should be 33% (which includes 15m along the

boundary, 2 to 5m along the roads, open spaces &

Setbacks in individual industries).

Green cover for the width of 15m will be

developed all along the periphery and 2m

along roads. Total 33%. Greenbelt will be

developed (i.e:10% at TSIIC park level &

23% Individual Industry level) green belt will

constitute avenue plantation taken by the

developer in the park and plantation by

member industries.

10 Submit the details of the trees to be felled for the

project.

No felling of trees in the project envisaged.

As the project site consists of agriculture

land & uncultivated waste land. The project

Ramky Enviro Services Pvt. Ltd. ii

Page 25: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

S.No ToR point Compliance

area is devoid of large trees and there are

few thorny bushes and with degraded

shrubs.

11 Submit the details of the infrastructure to be

developed.

TSIIC will be develop physical infrastructure

/common facilities like roads, power & water

supply, storm water drains, rain water

harvesting structures and 10% green belt at

park level. The details are given Chapter 2

under section 2.5.

12 Submit the present land use and permission required

for any conversion such as forest, agriculture etc.

The land is owned by TSIIC (A Govt.of

Telangana State undertaking). And at

present some parts of the land are fertile and

support vegetation some parts of the land

are devoid of any vegetation. No permission

required for conversion of forest and

agricultural departments.

13 Submit details regarding R&R involved in the project. No

14 Zoning of the area in terms of 'type of industries'

coming-up in the industrial area based on the

resource requirement along with likely pollutants with

quantity from the various industries.

The proposed textile park with homogenous

(Spinning, weaving, Knitting, Processing,

Made-ups, Apparel/readymade garments)

type of industries. Based on the availability of

land, production, type the total park is

divided into 7 zones. Zoning of the area is

given in Chapter-2. The likely pollutants and

its quantities (baseline status and predicted)

are given in Chapter- 4 during construction

and operation phages.

15 The project boundary area and study area for which

the base line data is generated should be indicated

through a suitable map. Justification of the

parameters, frequency and locations shall be

discussed in the EIA.

The project boundary and 10 Km radius

study area for which the baseline data

generated is clearly indicated in Chapter-3

Figure-3.4. Baseline study details are given

in Chapter-3 under sections 3.2 to 3.12.

Justification of the parameters and

frequencies in all locations in the study area

discussed in Chapter-3 in the EIA report.

16 Submit Legal frame work for the implementation of

Environmental Clearance conditions - to be clearly

spelt out in the EIA report.

Environmental Clearance legal frame work

for Implementation of EC conditions and

EMP were clearly mentioned in the EIA

report.

17 Submit Roles and responsibility of the developer etc.

for compliance of environmental regulations under

the provisions of EPA Act.

Obtaining EC, Creation and development of

basic infrastructure, allotment of land to the

industries, co-ordination with other dept. for

Ramky Enviro Services Pvt. Ltd. iii

Page 26: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. iv

EIA-EMP Report for Proposed Mega Textile Park at Warangal

S.No ToR point Compliance

external infrastructure, maintenance of civic

amenities after notification of IALA etc. and

compliance of environmental regulations

under the provision of EPA (under AIR &

Water) Act.

18 Site justification of the identified industry sectors

from environmental angle and the details of the

studies conducted if any.

After detailed survey for selection of suitable

site for the proposed project, site is selected

based on the siting guidelines/criteria. The

alternate site and technology options were

clearly discussed in the Chapter-5 of the EIA

report.

19 Ground water classification as per the Central

Ground Water Authority.

The project site comes under critical

category as per the groundwater

classification of CGWA. The details are given

in Chapter 7 under sub section 7.12.6.

20 Submit the source of water, requirement vis-à-vis

waste water to be generated along with treatment

facilities, use of treated waste water along with water

balance chart taking into account all forms of water

use and management.

The 40MLD of water is required for the

proposed Mega Textile Park will be sourced

from SRSP canal & ground water. The

details regarding the source of water and

requirement as well as wastewater

generation and treatment are given in

Chapter-2 under section-2.5.1 and

management of wastewater is discussed in

Chapter-4 under sub-section 4.3.5 were

wastewater is collected via. Separate drains

and treated in CETP and CSTP and reused

for greenbelt development. Zero liquid

discharge (ZLD) concept will be adopted.

21 Rain water harvesting proposals should be made

with due safeguards for ground water quality.

Maximize recycling of water and utilization of rain

water. Examine details.

Rainwater harvesting structures will be

suggested individual plots and the same will

be used for various industrial activities and

greenbelt development. The runoff water

from the roads will be diverted to the storm

water drains present all along the roads and

recharge pits will be maintained at regular

intervals. All the safeguard measures will be

taken to any contamination of the ground

water. Storm water drainage system and run

off estimate is given in Chapter 7 under

section 7.12.7.

22 Examine soil characteristics and depth of ground

water table for rainwater harvesting.

Details of soil characteristics are discussed

in Chapter-3 under section- 3.8. Basic soil

Page 27: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

S.No ToR point Compliance

parameter resultants fall in normal to

medium range. Level of available (NPK)

Nitrogen and Phosphorus in soil falls in low

range while Potassium ranges in high. The

details of groundwater depth are given in

Chapter 7 under section 7.12.5.2 and run off

estimate with rainwater harvesting are given

in Chapter 7 under section 7.12.7.

23 Examine details of solid waste generation treatment

and its disposal.

The total solid waste generated in the

proposed industrial park will be segregated

and disposed as per the norms. Details of

solid waste are given in Chapter-4 under

sub-section-4.2.4 and section-4.5.

24 Examine and submit details of use of solar energy

and alternative source of energy to reduce the fossil

energy consumption.

Solar energy is proposed as an alternative

energy for street lighting and the details are

given in Chapter-5; Section-5.5. Initiating

cleaner technology approach and helping in

saving electric energy.

25 In case DG sets are likely to be used during

construction and operational phase of the project,

emissions from DG sets must be taken into

consideration while estimating the impacts on air

environment. Examine and submit details.

The impact on the air environment is

estimated by considering the DG sets and

boilers to be used in the proposed industrial

park. The incremental ground level

concentrations (GLC’s) are given in Chapter-

4; Section-4.3.2 and in table 4.1 to 4.3 &

figure 4.1 to 4.3.

26 Examine road/rail connectivity to the project site and

impact on the traffic due to the proposed project.

Present and future traffic and transport facilities for

the region should be analyzed with measures for

preventing traffic congestion and providing faster

trouble free system to reach different destinations in

the city.

The Project site is about 21 km from

Warangal town. It can be accessed by road

via Mahbubabad - Warangal Road and

Narsampet Road - Warangal Road which

also leads to Khammam, Kothagudem and

Badrachalem. The access to the site from

Warangal has good road connectivity. This

road is a two lane highway with divided

carriageway at some portions and without a

divided carriageway at few stretches. The

industrial park is well connected with road

and rail network. Proposed industrial park

has direct access to the Warangal-

Narsampet (3Km, N) 2 lane road. Details of

road/rail network connectivity are given in

Chapter-2 under section-2.4.1. The traffic/

air quality impacts & mitigation, due to

additional traffic from the proposed project

Ramky Enviro Services Pvt. Ltd. v

Page 28: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

S.No ToR point Compliance

were discussed in Chapter-4 under section-

4.5 effective traffic management plan will be

implemented to prevent the traffic congestion

& for free movement.

27 A detailed traffic and transportation study should be

made for existing and projected passenger and

cargo traffic.

Detailed traffic study was carried out on both

village roads connecting to Warangal-

Narsampet highway at Ookal junction and

Vanchanagiri junction. The details are given

in Chapter-3; Section-3.9.1.The detailed

existing and proposed scenario of traffic and

level of services discussed.

28 Examine the details of transport of materials for

construction which should include source and

availability.

The construction materials required during

developmental stage of the proposed

industrial park will be transported from the

nearest town.

29 Examine the details of National Highways/State

Highways/ expressways falling along the corridor

and the impact of the development on them.

Proposed industrial park has direct access to

the Warangal-Narsampet highway (3Km, N)

2 lane road. Having access to NH-163, and

other village roads. The traffic impact on

Warangal-Narsampet road due to the

proposed project is given in Chapter-4

section-4.3.3.

30 Examine noise levels - present and future with noise

abatement measures.

The present day and night noise levels in

and around the project site are ranging

between 40.9 dB to 53.9 dB (A) details are

given in Chapter-3; Section-3.6. The noise

levels in the proposed industrial park will be

minimize by providing greenbelt around the

boundary and by maintaining the acoustic

enclosures around the DG sets. Abatement

measures is given in Chapter-4; Section-

4.2.3.1

31 Identify, predict and assess the environmental and

sociological impacts on account of the project. A

detailed description with costs estimates of CSR

should be incorporated in the EIA/EMP report.

The detailed impact analysis due to the

proposed industrial park has been carried

out and details are given in Chapter-4

Section 4.2.3 and 4.6. CSR activities will be

carried out by each individual industry.

32 Examine separately the details for construction and

operation phases both for Environmental

Management Plan and Environmental Monitoring

Plan with cost and parameters.

The environmental monitoring plan during

construction and operational phase is given

Chapter-6 under section-6.1.1 & 6.1.2 & in

table-6.1 and 6.2. The environmental

management plan during construction and

Ramky Enviro Services Pvt. Ltd. vi

Page 29: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

S.No ToR point Compliance

operational phase is given in Chapter-9

Section-9.1 & 9.2 respectively.

33 Submit details of a comprehensive Disaster

Management Plan including emergency evacuation

during natural and man-made disaster.

The detailed comprehensive disaster

management plan including emergency

evacuation during natural and man-made

disaster is given in Chapter-7; Section-7.10.

Suggestions were made according to latest

NDMA guidelines with preparedness against

any disastrous situation.

34 The Public hearing should be conducted for the

project in accordance with provisions of

Environmental Impact Assessment Notification, 2006

and the issues raised by the public should be

addressed in the Environmental Management Plan.

The Public Hearing should be conducted based on

the ToR letter issued by the Ministry and not on the

basis of Minutes of the Meeting available on the

web-site.

Noted. Followed and will be conducted as

per the EIA notification 2006.

35 A detailed draft EIA/EMP report should be prepared

in accordance with the above additional ToR and

should be submitted to the Ministry in accordance

with the Notification.

Noted and prepared the draft EIA/EMP and

will be submitted to MoEF&CC as per the

notification.

36 Details of litigation pending against the project, if

any, with direction /order passed by any Court of

Law against the Project should be given.

No litigation is pending against the project.

37 The cost of the Project (capital cost and recurring

cost) as well as the cost towards implementation of

EMP should be clearly spelt out.

The environmental monitoring plan during

construction and operation phase is given

Chapter-6; Section-6.1 & 6.2 & Table 6.1 and

6.2. The EMP during construction and

operational phase is given in Chapter 9

under section 9.1 & 9.2 respectively.

Ramky Enviro Services Pvt. Ltd. vii

Page 30: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. ES.1

Executive Summary

1. Project objectives

The State Government of Telangana through Telangana State Industrial Infrastructure Corporation

Limited (TSIIC) proposes to develop a Mega Textile Park (MTP) with state-of-the-art manufacturing

facilities for ginning, spinning, weaving, knitting and Textile processing at Shayampet village of

Geesugonda mandal and Chintalapalli village of Sangem mandal in Warangal district. The proposed

MTP will be implemented in five phases in 1190 acres of land.

TSIIC envisages establishing a world class integrated common infrastructure in the proposed Park

with plug and play built up infrastructure and common facilities to support the Textile and Apparel

Industry to move up in the value chain

Details of Project:

Details Description

Location Shayampet village of Geesugonda Mandal and Chintalapalli village of

Sangem Mandal, Warangal Rural Dist., Telangana State

Coordinates 170 54’ 29” N and 78

0 41’ 37” E

Land 1190 Acres (481.57 Ha)

Nearest habitation 0.6 km E of Chintalapalli villages; 0.7 km N of Shayampet villages; 0.5 km W

Road connectivity The Project site is about 21 km from Warangal town. It can be accessed by

road via Mahbubabad - Warangal Road and Narsampet Road - Warangal

Road which also leads to Khammam, Kothagudem and Bhadrachalam. The

access to the site from Warangal has good road connectivity. This road is a

two lane highway with divided carriageway at some portions and without a

divided carriageway at few stretches. From the Narsampet - Warangal Road,

a dedicated access road to the site is proposed from Gangadevipally; also

envisaging a dedicated RoB over the railway line.

Rail Connectivity Kazipet (26 km) & Warangal (14.1 km) are two major stations which provide

rail connectivity to the site. They are administered under the jurisdiction of

the Secunderabad railway division of South Central Railway zone. The

Warangal – Khammam railway line passes through the Project site; this line

connects to Vijayawada; the closest railway stations being Vanchanagiri and

Chintalapalli. About 6 passenger trains passes through this route and stops

Vanchanagiri and Chintalapalli at on daily basis

Airport Hyderabad International Airport 190 Km SW. There is also a proposal for an

Airport in Warangal at Mamnoor; about 9 km from Warangal City. Warangal

of Venkatapuram villages; and 0.6 km S of Sangem Taluk.

Present Land Use Partly barren land, partly double crop land

Page 31: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. ES.2

Airport is included in the Regional Connectivity Scheme.

Sea Port Machilipatnam (330 km); Kakinada (400 km); Visakhapatnam (530 km);

Chennai (665 Km). There is a proposal for a dry (Inland) port in Telangana.

Rivers/canals SRSP (Kakatiya) canal which is passing along the boundary from North to

south west side of the site.

Water bodies Sangem lake 3.0 km S, Yelgur lake 3.5 km SE, Gadepally lake 1.5 km W,

Bhadrakali lake 11.5 km NW

Seismicity Seismic Zone II (least active)

Hills/Valleys None

Archeologically

Important places

Warangal Fort 8.0 km NW; 1000 Pillars Temple 14.0 km NW; Bhadrakali

Temple 11.5 km NW

National Parks/

Wildlife sanctuaries

None

Reserved & Protected

forests

None

Defence Installations None

Resettlement &

Rehabilitation

None

2. Project background

Telangana is the twelfth largest State in India both in terms of area and population. Telangana is an

important Textile hub in India and has major locational advantages with international airport at

Hyderabad, extensive railway and road network, stable power situation, improved telecommunication

system and plenty of natural resources.

The major cities in Telangana are Hyderabad, Warangal, Mahabubnagar, Karimnagar, Nizamabad,

and Khammam. 15 National Highways of length 2,495 km cross Telangana and 24 State Highways of

length 1,815 km cover the State. South Central Railway headquartered at Secunderabad is the

second highest revenue earning zone in Indian Railways. The international airport at Hyderabad

connects domestic and international destinations and handles cargo to all over the world and major

cities in India.

Telangana is one of the largest producers of long staple cotton with production of around 50 lakh

bales per annum. The State stood at third position in the country in cotton production during the year

2014-15. The State is known for skilled Textile workers but due to absence of industry, they migrated

to other states for their livelihood.

There are 33 spinning mills with capacity of 10 lakh spindles, which consumes only about 20% of the

cotton grown in the State with the rest 80% going to other states for spinning. Capacity utilization of

Page 32: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. ES.3

weaving industry in the State is negligible and there is not much processing capacity available in the

State. There is no further downstream facility like processing and garmenting.

After bifurcation of the State, 75% of the pre-division cotton growing areas have remained in the State

while only 20% of the pre-division spinning capacity remains in the State. Thus, most of the cotton

goes to neighboring states for value addition, and so does the majority of the cotton yarn. The

availability of high cotton production and labour force presents an opportunity to create large

integrated Textile manufacturing capacities in the State. This will also support overall industrial

development in the State.

3. Proposed project

The MTP is proposed to be located in a district which is a major cotton producing district and trading

centre in the State. The region has a strong presence of Textile clusters (Warangal Durries) and

skilled manpower. The proposed Project envisages ploughing back economic benefits of the Park to

the local populace by catering to all activities in the Textile value chain.

TSIIC is a progressive Government organization responsible for planning and development of

industrial infrastructure in the State. TSIIC is known for creating landmark infrastructure projects in the

State, which are fueling economic growth. On 1190 acres of land with world class integrated

infrastructure which shall broadly include:

(i) Common Infrastructure

(ii) Built-Up Physical Infrastructure

(iii) Common Facilities

(iv) Social Infrastructure

The proposed MTP shall be implemented in a phased manner depending on the market demand. Due

to the large size of the Project, a long term strategy shall be adopted for the complete implementation

of MTP. The phasing approach shall not only help in ensuring sustainable development of the Park

but also in ensuring availability of fabric, accessories and man power for 75% of sales value of

garments.

4. Description of Environment

As described of baseline studies of the 10 km radius of surrounding of project site area. The data

collected has been used to understand the existing environment scenario around the proposed

project against which the potential impacts of the project can be assessed. The present activities will

not have any adverse impacts on the surrounding environment.

Environmental data has been collected for monitoring of:-

a) Air

b) Water

c) Noise

d) Soil

e) Socio-economic

f) Biological

Page 33: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. ES.4

a) Air Quality

Maximum value for PM10 was observed as 53.1 µg/m3

at Geesugonda (AAQ 8) and minimum

value is 41.3 µg/m3

at Kanaparti (AAQ6). NAAQ stipulated standard for PM10 for 24 hr

average is 100 µg/m3

.

Maximum value for PM2.5 was observed as 32.1 µg/m3

at Geesugonda (AAQ 8) and

minimum value is 19.7 µg/m3

at Kanaparti (AAQ6). NAAQ stipulated standard for PM2.5 for

24 hr average is 60 µg/m3

.

Maximum value for SO2 was observed as 12.2 µg/m

3

at Geesugonda (AAQ 8) and minimum

value is 6.6 µg/m3

at Kanaparti (AAQ6). NAAQ stipulated standard for SO2 for 24 hr average

is 80 µg/m3

.

Maximum value for NOx was observed as 21.0 µg/m3

at Geesugonda (AAQ 8) and minimum

value is 14.2 µg/m3

at Kanaparti (AAQ6). NAAQ stipulated standard for NOx for 24 hr average

is 80 µg/m3

.

Maximum value for O3 was observed as 19.8 µg/m

3

at Geesugonda (AAQ 8) and minimum

value is 10.1 µg/m3

at Kanaparti (AAQ6). NAAQ stipulated standard for O

3 for 8 hr average is

100 µg/m3

.

Maximum value for CO was observed as 580 µg/m3

at Geesugonda (AAQ 8) and minimum

value is 310 µg/m3

at Kanaparti (AAQ6) & Venkatapuram (AAQ5). NAAQ stipulated standard

for CO for 8 hr average is 2000 µg/m3

.

b) Water Quality

The analysis results indicate that the pH of the ground waters was to be in the range of 7.1 at

Katrapalli (GW4) and 7.8 at Shayampet (GW2). The Total Dissolved Solids (TDS) were found to be

in the range of 335 mg/l at Shayampet (GW2) and 1684mg/l at Sangem (GW5). Major samples were

above Acceptable limits and all are within the permissible limits. Other parameters like Chlorides and

Sulphates were observed to be well within the acceptable limits. It is seen that the physic chemical

analysis for all the parameters has within the standards as per IS: 10500:2012.

c) Noise Levels

It is observed that the day equivalent and night equivalent noise levels at all locations are within

prescribed CPCB standards.

Day equivalent noise levels (Ld) ranged between 51.8 to 53.9 dB (A) and Night equivalent

noise levels (Ln) ranged between 40.9 to 43.1 dB (A) for residential areas.

Sangem is the only residential cum commercial location where the Day equivalent noise

levels (Ld) is 52.9 dB (A) and Night equivalent noise levels (L

n) is 42.8 dB (A).

Page 34: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. ES.5

d) Soil Quality

The soil samples are analysed and results are obtained is compared with the standard soil

classification given Agriculture Soil Limits. It has been observed that the soils are sandy clay in

texture and neutral in nature. The nutrient and organic matter contents are medium and the soil is

normally fertile. The available Nitrogen is varies from 148 Kg/ha (Kanaparti) to 251 Kg/ha (Project

Site) is indicating low range. The available Phosphorous varies from 6.9 Kg/ha (Chintalapalli) to

11.4 Kg/ha (Venkatapuram) is indicating medium range and available Potassium is varies from 264

Kg/ha (Chintalapalli) to 372 Kg/ha (Mondrai) is indicating High range in the study area.

e) Socio-economic

The information on socio-economic aspects of the study area has been compiled from secondary

sources & Field work, which include various public offices, as indicated in the above section. The

sociological aspects of this study include human settlements, demography, social such as Scheduled

castes and Scheduled Tribes and literacy levels besides infrastructure facilities available in the study

area. The economic aspects include occupational structure of workers.

f) Biological

The area is devoid of vegetation and wildlife. The proposed project site is confined for Mega Textile

Park with an area of 1190 acres. Major scale of flora – fauna activities will be affected by the

proposed activity. There is no Wild Life Sanctuaries (WLS) within 10km from the project site. There is

no Reserve Forest (RF) or Protected Forest (PF).

5. Anticipated Environmental Impacts, Mitigation Measures EMP

The growth of any Industrial sectors and infrastructure developments in villages and towns is bound

to create its impact on socio-economic aspects of the local population. The impacts may be positive

and negative, large and small, long term and short term, reversible and irreversible impacts

depending upon the developmental activity.

Evidently, Economic, social and environmental change is inherent to development. Whilst

development aims to bring about positive change it can lead to conflicts. In the past, the promotion of

economic growth as the driver for increased well-being was the only focus, thus, with caving little

emphasis on adverse social or environmental impacts. The need to avoid adverse impacts and to

ensure long term benefits led to the concept of sustainability. Sustainability becomes also an

essential feature of development as it aims to increase well-being and greater equity in fulfilling basic

needs of present and future generations. Mankind, as developed today, cannot live without taking up

developmental activities for his food, security and other needs. Consequently, there is a need to

harmonize developmental activities with the environmental concerns.

Page 35: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. ES.6

6. Proposed Infrastructure

The facilities in the Park have been designed considering the activities and capacities of the proposed

units being set up in the Park. The list of facilities planned in the Park is given below:

S No. Infrastructure Components

1 Enabling Basic

Infrastructure

Road network including Footpaths & Utility Corridors

Storm Water Drainage System

Domestic & Industrial Water Supply System

Environmentally complaint Sewerage & Effluent Collection &

Treatment System

Waste Management facility

Electrical Distribution System and Street Lighting

Telecommunications

Truck parking & Weighbridge

2 Common

Facilities

Administrative Block including Product Display Centre

Skill Development Center

Convention & Exhibition Center

Warehouses

Market Place for Finished Goods & Product Display Centres

Testing Laboratory

3 Social

Infrastructure

Workers’ Hostel

Housing Zone

Crèche, Medical Facility

Commercial Centers / Recreational Center etc.

4 Built up

Infrastructure

Standard Plug n Play Factory sheds

Considering that the Project shall be implemented over five phases, the Project Cost mentioned

above has been further bifurcated for respective phases based on the total area to be developed in a

particular phase.

Phasing of Mega Textile Park development is essential in reducing financial uncertainty and boosting

potential investors’ confidence; through the minimization of initial capital outlay and risk, and

facilitation of development at manageable pace. Development will begin from a mini-estate and

Page 36: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. ES.7

gradually expand with changing rates of land occupancy. This will ensure practical expansion and

development with organized location of industries throughout Mega Textile Park (MTP).

The phasing plan provides a general guide for development of the MTP and shall be adopted with

flexibility depending on the market demand. The proposed Development Phasing needs to be

reviewed periodically in response to market demand; particularly in the development of new

units/sectors in the future.

7. Support Sought from Government of Telangana (GoT)

GoT has a vision for developing a strong Textile and Apparel Industry in the State which will facilitate

development of the entire value chain with added focus on creation of employment to local people.

The incentives have been suggested through estimation of operational risks and costs and

challenges inherent to the location. Warangal when compared to other Textile hubs in India may not

have a strong presence of complete value chain activities and value adds activities. The propose site

location being in a landlocked area may increase accessibility issues and transportation costs. The

non-availability of desired skill set, the Government may need to announce attractive fiscal and non-

fiscal incentives to lure investments.

As the MTP proposes to house units of various sizes engaged in wide range of Textile and Apparel

activities, the Project seeks additional fiscal and non-fiscal incentives apart from those available under

Telangana Industrial Policy and proposed Textile Policy of the State. Government incentives are

important to attract investments to relocate or expand to a certain identified location.

8. Conclusion

Warangal is the highest cotton growing district in Telangana and has one of the largest cotton market

yards in the region. Apart from cotton, presence of cotton ginning & pressing facilities, availability of

water and good railway & road connectivity make Warangal an attractive destination to establish the

MTP Project. In terms of availability of skilled manpower, it has been seen that majority of skilled

workers in Textile sector who migrated to other Textile hubs such as Andhra Pradesh, Tamil Nadu

and Maharashtra are originally from Warangal.

The MTP will establish state-of-the-art infrastructure, modern plug and play facility and world class

common facilities. The Park will be developed on a vertical integrated model to cover complete Textile

chain in one place. The Project shall meet the Industry standards and compliances and thereby

allowing the member units to complete globally. The Project will help in positioning Telangana as a

global sourcing hub for large scale buyers.

Page 37: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

ª«sLRiLigRiÍÞ ÍÜ[ úxms¼½Fyµj…»R½ ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä N]LRiNRPV BHFs ¬s®ªs[µj…NRP

ES.1 LSLiNUP Fs¬s*L][ xqsLki*|qs£qs \|ms#û®ªs[ÉÞ ÖÁ„sVÛÉÁ²`…

NSLRiù¬sLS*x¤¦¦¦NRP ryLSLiaRPLi

úFyÛÇÁNíRPV „sª«sLSÌÁV:

„sª«sLSÌÁV „sª«sLRißá

úxms®µ…[aRPª«sVV ¾»½ÌÁLigSßá LSxtísQûLi, ª«sLRiLigRiÍÞ ÑÁÍýØÍÜ[¬s xqsLilgiLi ª«sVLi²R…ÌÁLi ÀÁLi»R½ÌÁxmsÖýÁ

úgSª«sVLi ª«sVLji¸R…VV gkixqsVN]Li²R… ª«sVLi²R…ÌÁLiÍÜ[¬s aSùLi}msÈÁ úgSª«sVLiÍÜ[,

¬slLôi[aSLiNSÌÁV 170 54’ 29” N ª«sVLji¸R…VV 780 41’ 37” E

˳ÏÁW„sV 1190 FsNRPLSÌÁV (481.57 |¤¦¦¦NíSLýRiV)

xqs„dsVxms ¬sªyxqsLi ÀÁLi»R½ÌÁxmsÖýÁ úgSª«sW¬sNTP »R½WLRiVöÍÜ[ 0.6 NTP„dsV; aSùLi}msÈÁ úgSª«sW¬sNTP

D»R½òLRiLiÍÜ[ 0.7 NTP„dsV; ®ªsLiNRPÉØxmsoLRiLi úgSª«sW¬sNTP xmsbP誫sVLiÍÜ[ 0.5 NTP„dsV;

ª«sVLji¸R…VV xqsLigRiLi »yÌÁWNSNRPV 0.6 NTP„dsV.

úxmsxqsVò»R½ ˳ÏÁW„sV ª«sVLji¸R…VV

„s¬s¹¸…WgRiLi

LRix¤¦¦¦µyLji @ƒ«sVxqsLiµ³yƒ«sLi C úFyÇÁNíRPV \|qsÈÁV, ª«sLRiLigRiÍÞ xmsÈíÁßáLi ƒ«sVLi²T… xqsVª«sWLRiV 21NTP„dsV µR…WLRiLiÍÜ[

DLiµj…. BNRPä²T…NTP ª«sVx¤¦¦¦‡ÁWËØËص`… ª«sLRiLigRiÍÞ L][²ïR…V ª«sVLji¸R…VV ƒ«sLRixqsLi}msÉÞ

L][²ïR…V ª«sLRiLigRiÍÞ L][²ïR…V µy*LS ¿Á[LRiVN][ª«s¿RÁVè. C ª«sWLæRiLi ÅÁª«sVøLi,

1. úFyÛÇÁNíRPV ÌÁOSQQùÌÁV

¾»½ÌÁLigSßØ LSxtísQû úxms˳ÏÁV»R½*Li, ¾»½ÌÁLigSßØ LSxtísQû FyLjiúaS„sVNRP @ª«sróyxmsƒ«s NSL]ölLi[xtsQƒ±s ÖÁ„sVÛÉÁ²`…

(ÉÓÁFs£qsHHzqs) µy*LS, gjiLiÇÁÌÁV ¼d½¸R…V²R…Li, ª«s²R…NRP²R…Li, ®ƒs[¸R…V²R…Li, NRPVÈíÁ²R…Li ª«sVLji¸R…VV ÇÁª«so×dÁ úxmsúNTP¸R…V

N][xqsLi, ª«sLRiLigRiÍÞ ÑÁÍýØÍÜ[¬s xqsLilgiLi ª«sVLi²R…ÌÁLi ÀÁLi»R½ÌÁxmsÖýÁ úgSª«sVLi ª«sVLji¸R…VV gkixqsVN]Li²R… ª«sVLi²R…ÌÁLiÍÜ[¬s

aSùLi}msÈÁ úgSª«sVLiÍÜ[, @»yùµ³R…V¬sNRP »R½¸R…WLki úxmsª«sWßØÌÁ»][ INRP ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä (FsLiÉÓÁzms)¬s

@Õ³Áª«sXµôðj… ¿Á[¸R…V²y¬sNTP úxms¼½Fyµj…LiÀÁLiµj…. C úxms¼½Fyµj…»R½ FsLiÉÓÁzms @®ƒs[µj… 1190 FsNRPLSÌÁ xqósÌÁLiÍÜ[ HµR…V

µR…aRPÌÁÍÜ[ @ª«sVÌÁVxmsLRi¿RÁ‡Á²R…V»R½VLiµj….

úxms¼½Fyµj…»R½ FyLRiVäÍÜ[ úxmsxmsLi¿RÁúxmsÆØù¼½ gSLiÀÁƒ«s ryµ³yLRißá @ª«sróyxmsƒ«sƒ«sV GLSöÈÁV ¿Á[ R…V²y¬sNTP

ÉÓÁFs£qsHHzqs úxms¼½Fyµj…LiÀÁLiµj… ª«sVLji R…VV ªyùÌÁWù Q\¿Áƒ±sÍÜ[ xmsoL][gRi„sVLi¿RÁ²y¬sNTP „dsÌÁVgS ÇÁª«so×dÁ ª«sVLji R…VV

µR…VxqsVòÌÁ xmsLjiúaRPª«sVNRPV xqsx¤¦¦¦NRPLjiLi¿RÁµy¬sNTP @ª«sróyxmsƒ«s ª«sVLji R…VV ryµ³yLRißá xqsµR…VFy R…WÌÁƒ«sV xmýsg`i ª«sVLji R…VV }mýs

»][ GLSöÈÁV ¿Á[ R…V‡Á²T…Liµj…. C úFyÇÁNíRPVƒ«sV,¾»½ÌÁLigSßØÍÜ[ALójiNRP úxmsª«sWßØÌÁƒ«sV @LiµR…VN][ÛÍÁ[¬s

xmsLjiúaRPª«sVÌÁNRPV xqs¥¦¦¦ R…Vxms²R…V D®µô…[aRPLi»][ ª«sVLji R…VV ÇÁª«so×dÁ ªyùÌÁWù Q\¿Áƒ±s ÍÜ[ NSLSù¿RÁLRißáÌÁƒ«sV ƒ«s²R…Vxmso

D®µô…[aRPLi»][ zqsµôðR…Li¿Á[ R…V‡Á²T…Liµj….

µyµyxmsogS xmsLiÈÁ F~ÌÁLi

Page 38: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

ª«sLRiLigRiÍÞ ÍÜ[ úxms¼½Fyµj…»R½ ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä N]LRiNRPV BHFs ¬s®ªs[µj…NRP

ES.2 LSLiNUP Fs¬s*L][ xqsLki*|qs£qs \|ms#û®ªs[ÉÞ ÖÁ„sVÛÉÁ²`…

\lLiÌÁV @ƒ«sVxqsLiµ³yƒ«sLi ÆØÒÁ}msÈÁ (26 NTP„dsV), ª«

„sª«sWƒyúaRP¸R…Vª«sVV \|¤¦¦¦µR…LSËصR…V @Li»R½LêS¼d½¸R…V „sª«sWƒyúaRP¸R…VLi, \®ƒs‡ÁVV¼½ µj…NRPVäÍÜ[ 190 NTP„dsV

µR…WLRiLiÍÜ[ DLiµj….

J²R… lLi[ª«so ª«sVÀÁÖd xmsÈÁõLi (330 NTP„dsV); NSNTPƒy²R… (400 NTP„dsV); „saSÅÁxmsÈÁõLi (530 NTP„dsV);

¿Á\®ƒsQõ (665 NTP„dsV). ¾»½ÌÁLigSßØÍÜ[ INRP \®²…Qû (BƒýyLi²`…) lLi[ª«so N][xqsLi

úxms¼½FyµR…ƒ«s DLiµj….

ƒ«sµR…VÌÁV/NSÌÁVª«sÌÁV Fs£qsAL`iFs£qszms (NSNRP¼d½¸R…V) NSÌÁVª«s, C \|qsÈÁVNRPV D»R½òLRiLi ƒ«sVLi²T… \®ƒs‡ÁVV¼½

µj…NRPVäNRPV xqsLjix¤¦¦¦µôR…V gRiVLi²y úxmsª«sz¤¦¦¦r¡òLiµj….

¬dsÉÓÁ gRiVLiÈÁÌÁV xqsLilgiLi xqsLRixqsV= 3NTP„dsV µR…OTPQßáLi, FsÌæÁWL`i xqsLRixqsV= 3.5NTP„dsV Algi[õ¸R…VLi,

gS®µ…xmsÖýÁ xqsLRixqsV= 1.5 NTP„dsV xmsbP誫sVLi, ˳ÏÁúµR…NS×Á xqsLRixqsV= 11.5NTP„dsV

ªy¸R…Vª«sùLi

˳ÏÁWNRPLixms xqsLi‡ÁLiµ³j…»R½Li ˳ÏÁWNRPLixms xqsLi‡ÁLiµ³j…»R½ ÇÜ[ƒ±s II (@»R½ùÌÁö úNTP¸R…WbdPÌÁNRPLi)

xmsLRi*»yÌÁV/ÍÜ[¸R…VÌÁV G„dsÛÍÁ[ª«so

xmsoLSª«sxqsVò xqsLi‡ÁLiµ³j…»R½

úxmsª«sVVÅÁ úFyLi»yÌÁV

ª«sLRiLigRiÍÞ N][ÈÁ 8.0NTP„dsV \®ƒs‡ÁVV¼½; 1000 xqsòLi˳ØÌÁ ®µ…[ªyÌÁ¸R…VLi 14.0NTP„dsV

ªy¸R…Vª«sùLi; ˳ÏÁúµR…NS×Á ®µ…[ªyÌÁ¸R…VLi 11.5NTP„dsV ªy¸R…Vª«sùLi

Çؼd½¸R…V FyLRiVäÌÁV/

ª«sƒ«sùúFyßáVÌÁ

@˳ÏÁ¸R…WLRißØùÌÁV

G„dsÛÍÁ[ª«so

sLRiLigRiÍÞ (14.1 NTP„dsV), C \|qsÈÁVNRPV \lLiÌÁV

@ƒ«sVxqsLiµ³yƒ«sLi @Liµj…Li¿Á[ lLiLi²R…V @¼½|msµôR… }qísxtsQƒý«sV. B„s µR…OTPQßá ª«sVµ³R…ù

Q\lLiÛÍÁ[* ÇÜ[ƒ±s ¹¸…VVNRPä zqsNTPLiµR…LSËصR…V \lLiÛÍÁ[* ²T…„sÇÁƒ±s xmsLjiµ³j… úNTPLiµR…

¬sLRi*z¤¦¦¦Li¿RÁ‡Á²R…V»R½VƒyõLiVV. ª«sLRiLigRiÍÞ µy*LS ÅÁª«sVøLi Q\lLiÛÍÁ[* Q\ÛÍÁƒ«sV C

úFyÛÇÁN`íP Q\|qsÈÁV gRiVLi²y ®ªsÎÏÁ§»R½VLiµj…; C \ÛÍÁƒ«sV „sÇÁ¸R…Vªy²R…NRPV ®ªsÎÏÁ§»R½VLiµj…;

@¼½ xqs„dsVxmsLigS Dƒ«sõ QQ\lLiÛÍÁ[* }qísxtsQƒý«sV, ª«sLi¿RÁƒ«sgjiLji ª«sVLji¸R…VV ÀÁLi»R½ÌÁxmsÖýÁ.

xqsVª«sWLRiV 6 úxms¸R…WßÔáNRPVÌÁ \lLiÎÏÁ§þ C ª«sWLæRiLigRiVLi²y úxms¸R…WßÓáryòLiVV

ª«sVLji¸R…VV úxms¼½L][ÇÁÙ ª«sLi¿RÁƒ«sgjiLji ª«sVLji¸R…VV ÀÁLi»R½ÌÁxmsÖýÁ ª«sµôR… AgRiV»yLiVV.

N]»R½ògRiW®²…Li ª«sVLji¸R…VV ˳ÏÁúµy¿RÁÌÁLiNRPV NRPW²y ®ªsÎÏÁ§»R½VLiµj…. ª«sLRiLigRiÍÞ ƒ«sVLi²T…

C \|qsÈÁVNRPV ª«sVLiÀÁ LRix¤¦¦¦µyLji @ƒ«sVxqsLiµ³yƒ«s»R½ DLiµj…. C LRix¤¦¦¦µyLji,

lLiLi²R…V\ÛÍÁƒý«s \|¤¦¦¦®ªs[ NRPÖÁgji DLi²T… N]¬sõ Qúxms®µ…[aSÌÁÍÜ[ NSùlLi[ÇÞ ª«sWLæSÌÁ»][

ª«sVLji¸R…VV N]¬sõ ¿][ÈýÁ NSùlLi[ÇÞ ª«sWLæSÌÁV ÛÍÁ[NRPVLi²y „s˳ÏÁÑÁLixms‡Á²T… DLiµj…

Page 39: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

ª«sLRiLigRiÍÞ ÍÜ[ úxms¼½Fyµj…»R½ ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä N]LRiNRPV BHFs ¬s®ªs[µj…NRP

ES.3 LSLiNUP Fs¬s*L][ xqsLki*|qs£qs \|ms#û®ªs[ÉÞ ÖÁ„sVÛÉÁ²`…

úxms¾»½[ùNTP»R½ ª«sVLji¸R…VV

LRiOTPQ»R½ @LRißØùÌÁV G„dsÛÍÁ[ª«so

LRiOTPQ»R½ @ª«sróyxmsƒ«sÌÁV G„dsÛÍÁ[ª«so

xmsoƒ«sLRiVµôðR…LRißá ª«sVLji¸R…VV

xmsoƒ«sLSªyryÌÁV G„dsÛÍÁ[ª«so

2. úFyÇÁNíRPV ®ƒs[xms´R…ùLi

¾»½ÌÁLigSßØ LSxtísQLi, \®ªsaSùÌÁùLiÍÜ[ƒ«sW ª«sVLji¸R…VV ÇÁƒy˳ØÍÜ[ƒ«sW ˳ØLRi»R½®µ…[aRPLiÍÜ[ xms®ƒsõLi²R…ª«s @¼½|msµôR…

LSxtísQûLi. ¾»½ÌÁLigSßØ @®ƒs[µj… ˳ØLRi»R½®µ…[aRPLiÍÜ[ INRP úxmsª«sVVÅÁ ÇÁª«so×dÁ ZNP[LiúµR…Li ª«sVLji¸R…VV \|¤¦¦¦µR…LSËصR…VÍÜ[

„sª«sWƒyúaRP¸R…VLi NRPÖÁgji DLi²T… @¼½|msµôR… úFyLi¼d½¸R…V ÍØ˳جsõ NRPÖÁgjiDLiµj…. @Li¾»½[NSNRP úxms¾»½[ùNRP \lLiÛÍÁ[*

ª«sVLji¸R…VV L][²ïR…V ®ƒsÈÁ*LRiN`P, zqósLRi\®ªsVƒ«s xmsª«sL`i xmsLjizqós»R½VÌÁV, ®ªsVLRiV\lgiƒ«s ÛÉÁÖÁNRPª«sVWù¬sZNP[xtsQƒ±s ª«sùª«sxqós ª«sVLji¸R…VV

xqsª«sVXµôðj…\¹¸…Vƒ«s xqsx¤¦¦¦ÇÁ ª«sƒ«sLRiVÌÁƒ«sV NRPÖÁgji DLiµj….

¾»½ÌÁLigSßØÍÜ[¬s @¼½|msµôR… ƒ«sgRiLSÌÁV, \|¤¦¦¦µR…LSËص`…, ª«sLRiLigRiÍÞ, ª«sVx¤¦¦¦‡ÁWËÞƒ«sgRiL`i, NRPLkiLiƒ«sgRiL`i, ¬sÇت«sWËص`…

ª«sVLji¸R…VV ÅÁª«sVøLi. ¾»½ÌÁLigSßØ LSxtísQûQLiÍÜ[ 2,495NTP„dsV F~²R…ª«sogRiÌÁ 15 Çؼd½¸R…V LRix¤¦¦¦µyLRiVÌÁV ª«sVLji¸R…VV

1,815 NTP„dsV F~²R…ª«sogRiÌÁ LSxtísQû Q\|¤¦¦¦®ªs[ÌÁV DƒyõLiVV. \|¤¦¦¦µR…LSËص`… ÍÜ[ úxmsµ³yƒ«s NSLSùÌÁ¸R…VLi NRPÖÁgjiƒ«s

µR…OTPQßá ª«sVµ³R…ù Q\lLiÛÍÁ[*, ˳ØLRi¼d½¸R…V \lLiÛÍÁ[*£qs ÍÜ[ lLiLi²R…ª«s @¼½|msµôR… Aµy¸R…VLi NRPÖÁgjiƒ«sµj…. \|¤¦¦¦µR…LSËصR…VÍÜ[¬s

@Li»R½LêS¼d½¸R…V „sª«sWƒyúaRP¸R…VLi, úxmsxmsLi¿RÁLiÍÜ[¬s ª«sVLji¸R…VV ˳ØLRi»R½®µ…[aRPLiÍÜ[¬s @¼½|msµôR… ƒ«sgRiLSÌÁ¬sõLiÉÓÁÍÜ[¬s

®µ…[bdP¸R…V ª«sVLji¸R…VV @Li»R½LêS¼d½¸R…V gRiª«sWùÌÁNRPV @ƒ«sVxqsLiµ³yƒ«sLi NRPÖÁgji DLiµj….

xqsLiª«s»y=LS¬sNTP xqsVª«sWLRiVgS 50 ÌÁORPQÌÁ ‡ÁryòÌÁ úxms¼½ò D»R½ö¼½ò»][ F~²R…ªyÉÓÁ úxms¼½ò ¹¸…VVNRPä @¼½ |msµôR…

D»yöµR…ƒ«sµyLRiVÌÁÍÜ[ ¾»½ÌÁLigSßá LSxtísQûLi INRPÉÓÁgS DLiµj…. 2014c15 xqsLiª«s»R½=LRiLiÍÜ[ úxms¼½ò D»yöµR…ƒ«sÍÜ[

¾»½ÌÁLigSßØ LSxtísQûLi, ®µ…[aRPLiÍÜ[®ƒs[ ª«sVW²R…ª«s róyƒy¬sõ AúNRP„sVLiÀÁLiµj…. C LSxtísQûLi, \®ƒsxmsoßáùª«sLi»R½V\ÛÍÁƒ«s

ÇÁª«so×dÁ xms¬sªyLjiNTP |msÉíÓÁLiµj… }msLRiV, NS¬ds BNRPä²R… xmsLjiúaRPª«sV ÛÍÁ[NRPF¡ª«s²R…Li ª«sÌÁƒ«s xms¬sªyLRiLiµR…LRiW »R½ª«sV

ÒÁª«sƒ¯[Fyµ³j… N][xqsLi B»R½LRi LSuíyûÌÁNRPV ª«sÌÁxqs ®ªsÎØþLRiV.

LSxtísQûQLiÍÜ[ 10 ÌÁORPQÌÁ NRPµR…VLýRi ryª«sVLóRiQùLi»][ 33 zqsö¬sõLig`i „sVÍÞ= DƒyõLiVV, BLiµR…VÍÜ[ ZNP[ª«sÌÁLi LSxtísQûLiÍÜ[

|msLjigjiƒ«s úxms¼½òÍÜ[ ZNP[ª«sÌÁLi 20% ª«sWú»R½®ªs[V „s¬s¹¸…WgjiLi¿RÁ‡Á²R…V»R½VLiµj… ª«sVLji¸R…VV „sVgjiÖÁƒ«s 80% úxms¼½ò

ª«s²R…NRP‡Á²R…²y¬sNTP B»R½LRi LSuíyûÌÁNRPV ®ªsÎÏÁ§»][Liµj…. LSxtísQûLiÍÜ[ ®ƒs[»R½ xmsLjiúaRPª«sV ¹¸…VVNRPä ryª«sVLóRiQù „s¬s¹¸…WgRiLi

¿yÍØ »R½NRPV䪫sgS DLiµj… ª«sVLji¸R…VV LSxtísQûLiÍÜ[ @Li»R½ FsNRPV䪫s úFy|qszqsLig`i ryª«sVLóRiQùLi @LiµR…VËØÈÁVÍÜ[ ÛÍÁ[µR…V.

úFy|qszqsLig`i ª«sVLji¸R…VV gSlLiøLiÉÓÁLig`i ª«sLiÉÓÁ xqsµR…VFy¸R…WÌÁV @LiµR…VËØÈÁVÍÜ[ ÛÍÁ[ª«so.

Page 40: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

ª«sLRiLigRiÍÞ ÍÜ[ úxms¼½Fyµj…»R½ ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä N]LRiNRPV BHFs ¬s®ªs[µj…NRP

ES.4 LSLiNUP Fs¬s*L][ xqsLki*|qs£qs \|ms#û®ªs[ÉÞ ÖÁ„sVÛÉÁ²`…

3. úxms¼½Fyµj…»R½ úFyÇÁNíRPV

ÉÓÁFs£qsHHzqs @®ƒs[µj… 1190 FsNRPLSÌÁÍÜ[ úxmsxmsLi¿RÁ úxmsÆØù¼½ ¿ÁLiµj…ƒ«s xqsª«sVúgRi\®ªsVƒ«s @ª«sróyxmsNRP»R½»][ FsLiÉÓÁzms¬s

GLRiöLRi¿RÁ²y¬sNTP úxms¼½Fyµj…LiÀÁLiµj… ª«sVLji¸R…VV ªyÉÓÁÍÜ[ CúNTPLiµj…„s DƒyõLiVV

(i) ryµ³yLRißá @ª«sróyxmsƒ«s

(ii) ˳ݼ½NRP @ª«sróyxmsƒ«s ¬sLjiøLi¿RÁ²R…Li

(iii) ryµ³yLRißá xqsµR…VFy¸R…WÌÁV

(iv) ryª«sWÑÁNRP @ª«sróyxmsƒ«s

75% ª«sLRiNRPV ¬sLôðSLjiLi¿RÁVN][gRiÌÁVgRiV»R½VLiµj….

LSxtísQû„s˳ÏÁÇÁƒ«s »R½LRiVªy»R½, xmspLRi*c„s˳ØgRi úxms¼½ò |msLRiVgRiV úFyLi»R½LiÍÜ[ 75% LSxtísQûLiÍÜ[®ƒs[ DLi²T…F¡LiVVLiµj…

ª«sVLji¸R…VV ZNP[ª«sÌÁLi 20% xmspLRi*c„s˳ØgRiLiÍÜ[¬s ª«s²R…NRPV ryª«sVLóRiQùLi ª«sWú»R½®ªs[V LSxtísQûLiÍÜ[ „sVgjiÖÁLiµj…. @ÍØ

¿yÍت«sLRiNRPV úxms¼½ò, úxmsNRPäLSuíyûÌÁNRPV @µR…ƒ«sxmso ÇÜ[²T…Lixmso „sÌÁVª«sgS ®ªs×ÁþF¡LiVVLiµj… ª«sVLji¸R…VV úxms¼½ò

ƒ«sWÌÁVÍÜ[ ¿yÍØ˳ØgRiLi @ÍØ ®ªs×ÁþF¡LiVVLiµj…. @µ³j…NRP úxms¼½ò D»yöµR…ƒ«s ª«sVLji¸R…VV NSLjiøNRP aRPNTPò ¹¸…VVNRPä

ÌÁ˳ÏÁù»R½ @®ƒs[µj… LSxtísQûLiÍÜ[®ƒs[ @¼½|msµôR… xqsª«sVúgRi\®ªsVƒ«s ÇÁª«so×dÁ »R½¸R…WLki ryª«sVLóSQùÌÁƒ«sV xqsXztísQLi¿RÁVÈÁNRPV

@ª«sNSaRPLi NRPÖÁöLiÀÁLiµj…. Bµj… LSxtísQûLiÍÜ[¬s xqsLixmspLñRi FyLjiúaS„sVNRP @Õ³Áª«sXµôðj…NTP NRPW²y »][²R…ö²R…V»R½VLiµj….

LSxtísQûLiÍÜ[®ƒs[ @¼½|msµôR… úxms¼½ò D»yöµR…ƒy ÑÁÍýØ ª«sVLji¸R…VV ªyßÓáÇÁù ZNP[LiúµR…LiÍÜ[ C FsLiÉÓÁzms

úxms¼½Fyµj…Li¿RÁ‡Á²T…Liµj…. C úFyLi»R½LiÍÜ[ ÇÁª«so×dÁ ZNP[LiúµyÌÁV (ª«sLRiLigRiÍÞ ²R…WùLki£qs) ª«sVLji¸R…VV \®ƒsxmsoßáùª«sLi»R½V\ÛÍÁ

NSLjiøNRPaRPNTPò ‡ÁÖdÁ¸R…VLigS DLiµj…. úxms¼½Fyµj…»R½ úFyÛÇÁN`íP ÍÜ[, ÇÁª«so×dÁ ªyùÌÁWùQ\¿Áƒ±s ÍÜ[¬s @¬sõ NSLSù¿RÁLRißáÌÁNRPV

FyLRiVä ¹¸…VVNRPä ALójiNRP úxms¹¸…WÇÁƒyÌÁƒ«sV róy¬sNRP úxmsÇÁÌÁV ¼½Ljigji F~LiµR…²y¬sNTP „dsÌÁVNRPÖÁöxqsVòLiµj….

ÉÓÁFs£qsHHzqs @®ƒs[µj… LSxtísQûLiÍÜ[ FyLjiúaS„sVNRP @ª«sróyxmsƒ«s ¹¸…VVNRPä úxmsßØ×ÁNRP ª«sVLji¸R…VV @Õ³Áª«sXµôðj… N]LRiNRPV

Ëص³R…ù»R½ ª«sz¤¦¦¦xqsVòƒ«sõ INRP xmsoL][gRiª«sVƒ«s úxms˳ÏÁV»R½* xqsLixqós. ÉÓÁFs£qsHHzqs @®ƒs[µj… LSxtísQûLiÍÜ[ ÍØùLi²`… ª«sWL`iä

@ª«sróyxmsƒy úFyÇÁN`íPQ= xqsXztísQLi¿RÁ²y¬sNTP }mslLi¬sõNRPgRiƒ«sõµj…. ÉÓÁFs£qsHHzqs @®ƒs[µj… ª«sLRiLigRiÍÞ ÍÜ[FsLiÉÓÁzms¬s ª«sXµôðj…

xmsLRi¿RÁ²y¬sNTP úxms¼½Fyµj…LiÀÁLiµj…

úxms¼½Fyµj…»R½ FsLiÉÓÁzms @®ƒs[µj… ª«sWlLiäÉÞ ²T…ª«sWLi²R…Vƒ«sV ‡ÁÉíÓÁ µR…aRPÌÁªyLkigS @ª«sVÌÁVxmsLRi¿RÁ‡Á²R…V»R½VLiµj…. C

úFyÛÇÁN`íP @¼½|msµôR… úFyÛÇÁN`íP NSª«s²R…Li ª«sÌÁƒ«s, FsLiÉÓÁzms ¹¸…VVNRPä xqsLixmspLñRi @ª«sVÌÁVNRPV INRP µk…LçRiNSÖÁNRP ª«spùx¤¦¦¦Li

GLSöÈÁV ¿Á[¸R…V‡Á²T…Liµj…. µR…aRPÌÁªyLkigS ¿Á[¸R…V²R…Li @®ƒs[µj… FyL`iä ¹¸…VVNRPä zqósLRi\®ªsVƒ«s @Õ³Áª«sXµôðj…¬s

¬sLôðSLjiLi¿RÁVN][ª«s²R…®ªs[V NSNRPVLi²y, FnyúÕÁN`P, DxmsNRPLRißØÌÁV ª«sVLji¸R…VV NSLjiøNRPaRPNTPò¬s, µR…VxqsVòÌÁ „súNRP¸R…V„sÌÁVª«sÍÜ[

Page 41: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

ª«sLRiLigRiÍÞ ÍÜ[ úxms¼½Fyµj…»R½ ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä N]LRiNRPV BHFs ¬s®ªs[µj…NRP

ES.5 LSLiNUP Fs¬s*L][ xqsLki*|qs£qs \|ms#û®ªs[ÉÞ ÖÁ„sVÛÉÁ²`…

4. xmsLSùª«sLRißá „sª«sLRißá

xmsLSùª«sLRißá xqsª«sW¿yLRiLi, C úNTPLiµj… ªyÉÓÁ¬s xmsLRiù®ªs[OTPQLi¿RÁ²y¬sNTP }qsNRPLjiLi¿RÁ‡Á²T…Liµj…:c

a) ªy¸R…VVª«so

b) ¬dsLRiV

c) aRP‡ôÁLi

d) ª«sVÉíÓÁ

e) ryª«sWÑÁNRPcALójiNRPxmsLRi\®ªsVƒ«s

f) ÒÁª«sxqsLi‡ÁLiµ³R…\®ªsVƒ«s

a) ªy¸R…VVª«so ƒyßáù»R½

• SO2

N]LRiNRPV

24gRiLi xqsLSxqsLji N]LRiNRPV ¬slLôi[bPLi¿RÁ‡Á²T…ƒ«s Fsƒ±sFsFsNRPVù úxmsª«sWßáLi 80 µg/m3.

ÛËÁ[£qs\ÛÍÁƒ±s @µ³R…ù¸R…VƒyÌÁÍÜ[ „sª«sLjiLi¿RÁ‡Á²T…ƒ«sÈýÁVgS úFyÛÇÁN`íP Q\|qsÈÁV úFyLi»R½Li 10 NTP„dsV ªyùryLóRi xmsLjiµ³j…¬s NRPÖÁgji

DLiÈÁVLiµj…. }qsNRPLjiLi¿RÁ‡Á²T…ƒ«s xqsª«sW¿yLRiLi, úxms¼½Fyµj…»R½ \®ªsV¬sLig`i úFyÛÇÁN`íP ÍÜ[ BxmsöÉÓÁZNP[ Dƒ«sõ xmsLSùª«sLRißá

ryµR…XaSù¬sõ xmsLjigRißძsÍÜ[ ¼d½xqsVNRPV¬s „s¬s¹¸…WgjiLi¿RÁ‡Á²T…, úFyÇÁN`íP ¹¸…VVNRPä xqsLi˳ت«sù úxms˳تyÌÁV @Li¿RÁƒy

®ªs[¸R…V‡Á²R…»yLiVV. úxmsxqsVò»R½ NSLSù¿RÁLRißáÌÁV, úgS„dsVßá xqsLixmnsWÌÁ ¹¸…VVNRPä xqsLixmsµR… ª«sƒ«sLRiVÌÁ\|ms FsÍØLiÉÓÁ

úxms¼½NRPWÌÁ úxms˳تyÌÁƒ«sV NRPÖÁgji DLi²R…ª«so, FsLiµR…VNRPLiÛÉÁ[ C úFyLi»R½LiÍÜ[ xqsª«sWÇÁLi ¹¸…VVNRPä G „s˳ØgRiLi

µy*LS\®ƒsƒy C úFyÛÇÁN`íP QúFyLi»R½Li „s¬s¹¸…WgjiLi¿RÁVN][‡Á²R…µR…V.

úxmsxqsVò»R½ NSLSù¿RÁLRißáÌÁV, úgS„dsVßá xqsª«sWÇØÌÁ ryµ³yLRißá xqsLixmsµR… ª«sƒ«sLRiVÌÁÍÜ[ ®µ…[¬s\|ms\®ƒsƒy NRPW²y FsÍØLiÉÓÁ

úxms¼½NRPWÌÁ úxms˳تyÌÁƒ«sV NRPÖÁgjiDLi²R…ª«so, FsLiµR…VNRPLiÛÉÁ[ C úFyLi»R½LiÍÜ[ xqsª«sWÇÁLi ¹¸…VVNRPä G „s˳ØgRiLi

µy*LS\®ƒsƒy C úFyÛÇÁN`íP QúFyLi»R½Li FsÍØLiÉÓÁ D®µô…[aS¬s\ZNPƒy „s¬s¹¸…WgjiLi¿RÁ‡Á²R…µR…V..

• zmsFsLi10 N]LRiNRPV gRiLjixtísQ „sÌÁVª«s, gkixqsVg]Li²R… (FsFsNRPVù 8) ª«sµôR… 53.1 µg/m3 gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…

ª«sVLji¸R…VV NRP¬sxtísQ „sÌÁVª«s, NRPƒ«sxmsLjiò (FsFsNRPVù6) ª«sµôR… 41.3 µg/m3gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…. zmsFsLi10

N]LRiNRPV 24gRiLi xqsLSxqsLji N]LRiNRPV ¬slLôi[bPLi¿RÁ‡Á²T…ƒ«s Fsƒ±sFsFsNRPVù úxmsª«sWßáLi 100 µg/m3.

• zmsFsLi2.5 N]LRiNRPV gRiLjixtísQ „sÌÁVª«s, gkixqsVg]Li²R… (FsFsNRPVù 8) ª«sµôR… 32.1 µg/m3gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…

ª«sVLji¸R…VV NRP¬sxtísQ „sÌÁVª«s, NRPƒ«sxmsLjiò (FsFsNRPVù6) ª«sµôR… 19.7 µg/m3gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…. zmsFsLi 2.5

N]LRiNRPV 24gRiLi xqsLSxqsLji N]LRiNRPV ¬slLôi[bPLi¿RÁ‡Á²T…ƒ«s Fsƒ±sFsFsNRPVù úxmsª«sWßáLi 60 µg/m3.

N]LRiNRPV gRiLjixtísQ „sÌÁVª«s, gkixqsVg]Li²R… (FsFsNRPVù 8) ª«sµôR… 12.2 µg/m3gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…

ª«sVLji¸R…VV NRP¬sxtísQ „sÌÁVª«s, NRPƒ«sxmsLjiò (FsFsNRPVù6) ª«sµôR… 6.6 µg/m3gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…. SO2

Page 42: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

ª«sLRiLigRiÍÞ ÍÜ[ úxms¼½Fyµj…»R½ ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä N]LRiNRPV BHFs ¬s®ªs[µj…NRP

ES.6 LSLiNUP Fs¬s*L][ xqsLki*|qs£qs \|ms#û®ªs[ÉÞ ÖÁ„sVÛÉÁ²`…

N]LRiNRPV 24gRiLi xqsLSxqsLji N]LRiNRPV ¬slLôi[bPLi¿RÁ‡Á²T…ƒ«s Fsƒ±sFsFsNRPVù úxmsª«sWßáLi 80 µg/m3.

• O3 N]LRiNRPV gRiLjixtísQ „sÌÁVª«s, gkixqsVg]Li²R… (FsFsNRPVù 8) ª«sµôR… 19.80 µg/m3gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…

ª«sVLji¸R…VV NRP¬sxtísQ „sÌÁVª«s, NRPƒ«sxmsLjiò (FsFsNRPVù6) ª«sµôR… 10.1 µg/m3gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…. O3 N]LRiNRPV

24gRiLi xqsLSxqsLji N]LRiNRPV ¬slLôi[bPLi¿RÁ‡Á²T…ƒ«s Fsƒ±sFsFsNRPVù úxmsª«sWßáLi 100 µg/m3

b) ¬dsÉÓÁ ƒyßáù»R½

c) aRP‡ôÁ róyLiVVÌÁV

• ¬sªyxqs úFyLi»yÌÁ N]LRiNRPV, xmsgRiÉÓÁxmspÈÁ xqsª«sV»R½VÌÁù aRP‡ôÁ róyLiVVÌÁV (Ld) 51.8 ƒ«sVLi²T… 53.9 dB (A)

• NOx N]LRiNRPV gRiLjixtísQ „sÌÁVª«s, gkixqsVg]Li²R… (FsFsNRPVù 8) ª«sµôR… 21.0µg/m3 gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…

ª«sVLji¸R…VV NRP¬sxtísQ „sÌÁVª«s, NRPƒ«sxmsLjiò (FsFsNRPVù6) ª«sµôR… 14.2 µg/m3 gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…. NOx

• CO N]LRiNRPV gRiLjixtísQ „sÌÁVª«s, gkixqsVg]Li²R… (FsFsNRPVù 8) ª«sµôR… 580 µg/m3gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…

ª«sVLji¸R…VV NRP¬sxtísQ „sÌÁVª«s, NRPƒ«sxmsLjiò (FsFsNRPVù6) ª«sVLji¸R…VV ®ªsLiNRPÉØxmsoLRiLi (FsFsNRPVù5) ª«sµôR… 310

µg/m3gS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…. CO N]LRiNRPV 8gRiLi xqsLSxqsLji N]LRiNRPV ¬slLôi[bPLi¿RÁ‡Á²T…ƒ«s Fsƒ±sFsFsNRPVù

úxmsª«sWßáLi 2000 µg/m3.

˳ÏÁWgRiLRi÷é ÇÁÍØÌÁ ¹¸…VVNRPä DµR…ÇÁ¬s xqsWÀÁNRP, NSúÈÁxmsÖýÁ (ÑÁ²R…‡ýÁVù4) ª«sµôR… 7.1 úZaP[ßÓáÍÜ[ƒ«sW ª«sVLji¸R…VV

xtsQ¸R…WLi}msÉÞ (ÑÁ²R…‡ýÁVù2) ª«sµôR… 7.8 úZaP[ßÓáÍÜ[ƒ«sW DLi²yÌÁ¬s „sZaýP[xtsQßá xmnsÖÁ»yÌÁV xqsWÀÁxqsVòƒyõLiVV. ÉÓÁ²T…Fs£qs

@®ƒs[µj… xtsQ¸R…WLi}msÉÞ (ÑÁ²R…ËÞýù2) ª«sµôR… 335 mg/l úZaP[ßÓáÍÜ[ƒ«sW ª«sVLji¸R…VV xqsLilgiª±sV (ÑÁ²R…‡ýÁVù5) ª«sµôR…

1684mg/l úZaP[ßÓáÍÜ[ƒ«sW DƒyõLiVV. @¼½|msµôR… ƒ«sª«sVWƒyÌÁV, A®ªsWµR…¹¸…WgRiù xmsLji„sV»R½VÌÁNRPLiÛÉÁ[ FsNRPV䪫sgS

DƒyõLiVV ª«sVLji¸R…VV @ƒ«sVª«sV¼½Li¿RÁ‡Á²R…V xmsLji„sV»R½VÌÁNRPV ÍÜ[‡Á²T… DƒyõLiVV. Ný][Q\lLi²R…VÌÁV ª«sVLji¸R…VV xqsÛÍÁ[öéÈÁVÌÁ

ª«sLiÉÓÁ B»R½LRi FyLS„sV»R½VÌÁV A®ªsWµR…¹¸…WgRiùQ\®ªsVƒ«s xmsLji„sV»R½VÌÁNRPV ÍÜ[‡Á²T… Dƒ«sõÈýÁVgS gRiª«sV¬sLi¿RÁ‡Á²ïyLiVV.

@¬sõ FyLS„sV»R½VÌÁNRPV ˳ݼ½NRP LRiry¸R…V¬sNRP „sZaýP[xtsQßá (ÛÉÁ[‡ÁVÍÞ ƒ«sLi.3.9), HFs£qs: 10500:2012 úxmsNSLRiLi

úxmsª«sWßØÌÁNRPV ÍÜ[‡Á²T… Dƒ«sõÈýÁVgS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj….

@¬sõ QúFyLi»yÌÁÍÜ[ xmsgRiÉÓÁ xmspÈÁ xqsª«sV»R½VÌÁùQ\®ªsVƒ«s ª«sVLji¸R…VV LSú¼½ xmspÈÁ xqsª«sV»R½VÌÁù\®ªsVƒ«s aRP‡ôÁ róyLiVVÌÁ¬dsõ

NRPW²y xqsWÀÁLi¿RÁ‡Á²T…ƒ«s zqszmszqsÕÁ úxmsª«sWßØÌÁNRPV ÍÜ[‡Á²T… Dƒyõ¸R…V¬s gRiª«sV¬sLi¿RÁ‡Á²T…Liµj….

ª«sVµ³R…ù úZaP[ßÓáÍÜ[ƒ«sW ª«sVLji¸R…VV LSú¼½ xmspÈÁ xqsª«sV»R½VÌÁù aRP‡ôÁ róyLiVVÌÁV (Ln) 40.9 ƒ«sVLi²T… 43.1 dB

(A) ª«sVµ³R…ùÍÜ[ƒ«sW DƒyõLiVV.

Page 43: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

ª«sLRiLigRiÍÞ ÍÜ[ úxms¼½Fyµj…»R½ ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä N]LRiNRPV BHFs ¬s®ªs[µj…NRP

ES.7 LSLiNUP Fs¬s*L][ xqsLki*|qs£qs \|ms#û®ªs[ÉÞ ÖÁ„sVÛÉÁ²`…

• xmsgRiÉÓÁxmspÈÁ xqsª«sV»R½VÌÁù aRP‡ôÁ róyLiVVÌÁV (Ld), 52.9 dB (A) gSƒ«sW ª«sVLji¸R…VV LSú¼½ xmspÈÁ xqsª«sV»R½VÌÁù

aRP‡ôÁ róyLiVVÌÁV (Ln), 42.8 dB (A) gSƒ«sV Dƒ«sõ G\ZNPNRP ¬sªyxqs ª«sVLji¸R…VV ªyßÓáÇÁù úFyLi»R½Li xqsLilgiLi.

d) ª«sVÉíÓÁ ƒyßáù»R½

e) ryª«sWÑÁNRPcALójiNRPxmsLRi\®ªsVƒ«sµj…

f) ÒÁª«sxqsLi‡ÁLiµ³R…\®ªsVƒ«sµj…

5. Ez¤¦¦¦Li¿RÁµR…gjiƒ«s xmsLSùª«sLRißá úxms˳تyÌÁV, DxmsaSLi¼½ úxmsª«sWßØÌÁV BFsLizms

ª«sVÉíÓÁ „sZaýP[xtsQßØ xmnsÖÁ»yÌÁV BHFs ¬s®ªs[µj…NRP ¹¸…VVNRPä ¿³yxmísL`ic3 ÍÜ[ úxmsµR…Lji+Li¿RÁ‡Á²ïyLiVV. F~Liµj…ƒ«s xmnsÖÁ»yÌÁV,

ª«sùª«sry¸R…V ®ƒs[ÌÁ xmsLji„sV»R½VÌÁÍÜ[ Bª«s*‡Á²T…ƒ«s úFyª«sWßÓáNRP ª«sVÉíÓÁ ª«sLækiNRPLRißá»][ F¡ÌÁè‡Á²ïyLiVV. ª«sVÉíÓÁ®ƒs[ÌÁÌÁV

BxqsVNRP»][ NRPW²T… ‡ÁLiNRPgSƒ«sW ª«sVLji¸R…VV »R½ÈÁxqós xqs*˳ت«sLi NRPÖÁgji Dƒ«sõÈýÁVgS gRiª«sV¬sLi¿RÁ‡Á²T…Liµj…. F¡xtsQNRP

ª«sVLji¸R…VV }qsLiúµk…¸R…V xmsµyLóSLiaSÌÁV ª«sVµ³R…ùxqósLigSƒ«sW ª«sVLji¸R…VV ª«sVÉíÓÁ ryµ³yLRißáLigS ryLRiª«sLi»R½LigSƒ«sW

DƒyõLiVV. „sª«sLRi\®ªsVƒ«s ª«sVÉíÓÁ „sZaýP[xtsQßá xmnsÖÁ»yÌÁV BHFs ¬s®ªs[µj…NRP ¿³yxmísL`ic3 ÍÜ[ ¿RÁLjièLi¿RÁ‡Á²T…Liµj….

@µ³R…ù¸R…Vƒ«s úFyLi»R½LiÍÜ[¬s ryª«sWÑÁNRPcALójiNRP @LiaSÌÁ\|ms xqsª«sW¿yLRiLi, ª«sWµ³R…ù„sVNRP ª«sVWÍØÌÁV ª«sVLji¸R…VV

ZOP[QQú»R½ xms¬s»R½ƒ«sLi ƒ«sVLi²T… úN][²U…NRPLjiLi¿RÁ‡Á²T…Liµj…, BLiµR…VÍÜ[, \|ms „s˳ØgRiLiÍÜ[ xqsWÀÁLi¿RÁ‡Á²T…ƒ«sÈýÁVgS „s„sµ³R…

LRiNSÌÁ úxmsÇØ NSLSùÌÁ¸R…WÌÁV DƒyõLiVV. C @µ³R…ù¸R…Vƒ«sLi ¹¸…VVNRPä ryª«sWÑÁNRP @LiaSÌÁÍÜ[, ª«sWƒ«sª«s

|qsÉÓÁÛÍÁøLiÈýÁV, ÇÁƒyË³Ø xqsLi‡ÁLiµ³j…»R½\®ªsVƒ«s„s, |tsQ²R…WùÍÞï NRPVÍØÌÁV ª«sVLji¸R…VV |tsQ²R…WùÍÞï ¾»½gRiÌÁ ª«sLiÉÓÁ

ryª«sWÑÁNRP\®ªsVƒ«s„s ª«sVLji¸R…VV @µ³R…ù¸R…Vƒ«s úFyLi»R½LiÍÜ[ @LiµR…VËØÈÁVÍÜ[ Dƒ«sõ @ª«sróyxmsNRP xqsµR…VFy¸R…WÌÁ»][

FyÈÁV @ORPQLSxqsù»y róyLiVVÌÁV NRPW²y DƒyõLiVV. ALójiNRP @LiaSÌÁÍÜ[ NSLjiøNRPVÌÁ ¹¸…VVNRPä ª«sX¼½ò ¬sLSøßáLi

¿Á[LRiè‡Á²T…Liµj….

C úFyLi»R½Li, ®ªsVVNRPäÌÁV ª«sVLji¸R…VV ª«sƒ«sùúFyßÓá LRiz¤¦¦¦»R½LigS DLiµj…. úxms¼½Fyµj…»R½ úFyÛÇÁÉÞä Q\|qsÈÁV, 1190

FsNRPLSÌÁ \®ªsaSÌÁùLi»][ ®ªsVgS ÛÉÁN`P=\ÛÉÁÍÞ FyL`iä Q\ZNP xmsLji„sV»R½\®ªsVƒ«sµj…. ª«sXORPQ ÇÁLi»R½VÇØÌÁ NSLSù¿RÁLRißáÌÁÍÜ[

FsNRPV䪫s ˳ØgRiLi, úxms¼½Fyµj…»R½ NSLSù¿RÁLRißá µy*LS úxms˳؄s»R½Li @ª«so»R½VLiµj…. úFyÛÇÁN`íP Q\|qsÈÁV xmsLji„sV¼½ÍÜ[ 10

NTP„dsV ÍÜ[xmsÌÁ ²R…‡ýÁVùFsÍÞFs£qs ÛÍÁ[µR…V. AL`iFs£mns NRPW²y ÛÍÁ[µR…V. „sª«sLRi\®ªsVƒ«s ÒÁª«sxqsLi‡ÁLiµ³j…»R½ xmsLSùª«sLRißáLi, BHFs

¬s®ªs[µj…NRP ¹¸…VVNRPä ¿³yxmísL`i - 3 ÍÜ[ „sª«sLjiLi¿RÁ‡Á²T…Liµj….

úgSª«sWÌÁV ª«sVLji¸R…VV xmsÈíÁßØÌÁÍÜ[¬s G\®ªsƒy FyLjiúaS„sVNRP „s˳ØgSÌÁV ª«sVLji¸R…VV @ª«sróyxmsƒ«s @Õ³Áª«sXµôðR…VÌÁV,

róy¬sNRP ÇÁƒyË³Ø ¹¸…VVNRPä ryª«sWÑÁNRPcALójiNRP @LiaSÌÁ\|ms úxms˳ت«sLi ¿RÁWxmso»yLiVV. A úxms˳تyÌÁV, @Õ³Áª«sXµôðj…

NSLSù¿RÁLRißáÌÁƒ«sV ‡ÁÉíÓÁ, @ƒ«sVNRPWÌÁ\®ªsVƒ«s„sgSƒ«sW ª«sVLji¸R…VV úxms¼½NRPWÌÁ\®ªsVƒ«s„sgSƒ«sW, |msµôR…„s ª«sVLji¸R…VV

ÀÁƒ«sõ„sgSƒ«sW, µk…LçRiNSÖÁNRPLigS ÛÍÁ[µy xqs*ÌÁö NSÖÁNRPLigSƒ«sW, xmsLjiª«sLRiò¬ds¸R…VLigS ÛÍÁ[µy @xmsLjiª«sLRiò¬ds¸R…VLigSƒ«sW

DLi²R…ª«s¿RÁVè.

Page 44: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

ª«sLRiLigRiÍÞ ÍÜ[ úxms¼½Fyµj…»R½ ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä N]LRiNRPV BHFs ¬s®ªs[µj…NRP

ES.8 LSLiNUP Fs¬s*L][ xqsLki*|qs£qs \|ms#û®ªs[ÉÞ ÖÁ„sVÛÉÁ²`…

6. úxms¼½Fyµj…»R½ @ª«sróyxmsƒ«s

úNRP.xqsLi. @ª«sróyxmsƒ«s „s˳ØgRiª«sVVÌÁV

1 ryµ³yLRiß á@ª«sróyxmsƒ«s

»yLRiV L][²ïR…V ®ƒsÈÁ*L`iä, „dsµ³j… µk…xmsLi»][ xqs¥¦¦¦

úxms¸R…WßÔáNRPVÌÁ ª«sVLji¸R…VV ªyßÓáÇÁù ªyx¤¦¦¦ƒyÌÁ N]LRiNRPV FyLjiäLig`i

¬dsÉÓÁ xqsLRixmnsLS ª«sùª«sxqós

ª«sLRiµR… ¬dsÉÓÁ \®²…Qû®ƒs[ÑÁ ª«sùª«sxqós

ª«sVVLRiVgRiV¬dsLRiV xmsLji¿RÁLSù FýyLiÉÞ

xqsªyLki ª«sVLji¸R…VV FyLRi®ªs[¸R…VV ª«sùª«sxqós»][ BÉÓÁzms

ÛÉÁÖÁNRPª«sVWù¬sZNP[xtsQƒ±s=

2 ryµ³yLRißá xqsµR…VFy¸R…WÌÁVs

D»yöµR…ƒ«s úxmsµR…LRi+ƒy ZNP[LiúµR…Li»][ xqs¥¦¦¦ NSLRiù¬sLS*x¤¦¦¦NRP

„s˳ØgRiLi

\®ƒsxmsoßáù @Õ³Áª«sXµôðj… ª«sùª«sxqós

xqs˳ÏÁ ª«sVLji¸R…VV úxmsµR…LRi+ƒ«s ZNP[LiúµR…ª«sVV

ALójiNRP, ryª«sWÑÁNRP ª«sVLji¸R…VV xmsLSùª«sLRißá ª«sWLRiVö @®ƒs[µj… @Õ³Áª«sXµôðj… N]LRiZNP[ @¬s ¬sxqs=Li®µ…[x¤¦¦¦LigS ¾»½ÌÁVxqsV.

@Õ³Áª«sXµôðj… @®ƒs[µj… @ƒ«sVNRPWÌÁ ª«sWLRiVö N]LRiNRPV D®µô…[bPLi¿RÁ‡Á²T…ƒ«s\®µ…ƒy, @µj… xqsLiNýTPQxtísQ»R½ÌÁNRPV µyLji¼d½¸R…Vª«s¿RÁVè.

gRi»R½LiÍÜ[, |msLRiVgRiV»R½Vƒ«sõ xqs*xqós»R½ N][xqsLi ALójiNRP @Õ³Áª«sXµôðj… @®ƒs[µj… ª«sWú»R½®ªs[V µR…XztísQ ryLjiLi¿RÁ‡Á²T… DLi®²…[µj…,

µy¬s»][ ryª«sWÑÁNRP ÛÍÁ[µy xmsLSùª«sLRißØÌÁ\|ms úxms¼½NRPWÌÁ úxms˳تyÌÁ\|ms ¿yÍØ xqs*ÌÁö µR…XztísQ DLi®²…[µj….

úxms¼½NRPWÌÁ úxms˳تyÌÁƒ«sV ¬sªyLjiLi¿RÁ²y¬sNTP Aª«saRPùNRP»R½ ª«sVLji¸R…VV µk…LçRiNSÖÁNRP úxms¹¸…WÇÁƒyÌÁƒ«sV F~LiµR…²y¬sNTP

gRiÌÁ Aª«saRPùNRP»R½ @®ƒs[µj… zqósLRi»R½*Li @®ƒs[ @LiaS¬sNTP µyLji¼d½zqsLiµj…. zqósLRi»R½*Li @®ƒs[µj… @Õ³Áª«sXµôðj… N]LRiNRPV INRP

Aª«saRPùNRP @LiaRPLigS DLiµj… FsLiµR…VNRPLiÛÉÁ[, @µj… úZaP[¸R…VxqsV=ƒ«sV |msLiF~Liµj…Li¿RÁ²y¬sNTP ª«sVLji¸R…VV úxmsxqsVò»R½

ª«sVLji¸R…VV ˳ÏÁ„sxtsQù »R½LSÌÁ ª«sVWÌÁ Aª«saRPùNRP»R½ÌÁƒ«sV xmspLjiLi¿RÁVÈÁÍÜ[ ª«sVLjiLi»R½ xqsª«sWƒ«s»R½ƒ«sV NRPÖÁgjiLi¿RÁ²y¬sõ

ÌÁORPQQùLigS NRPÖÁgji DLiµj…. ª«sWƒ«sª«sÇؼ½, ®ƒs[²R…V @Õ³Áª«sXµôðj… ¿ÁLiµj…ƒ«sÈýÁVgS, »R½ƒ«s A¥¦¦¦LRiLi, LRiORPQßá ª«sVLji¸R…VV

B»R½LRi Aª«saRPùNRP»R½ÌÁ N]LRiNRPV @Õ³Áª«sXµôðj… @LiaSÌÁƒ«sV xmsLjigRißÓáLi¿RÁNRPVLi²y ÒÁ„sLi¿RÁÛÍÁ[NRPVƒ«sõµj…. »R½µR…ƒ«sVgRiVßáLigS,

xmsLSùª«sLRißá @LiaSÌÁ»][ @Õ³Áª«sXµôðj… NSLSù¿RÁLRißáÌÁƒ«sV F~xqsgRiVƒ«sÈýÁV ¿Á[¸R…VVÈÁ Aª«saRPùNRPLigS DLiµj….

FyLRiVäÍÜ[¬s xqsµR…VFy¸R…WÌÁV, FyLRiVäÍÜ[ @ª«sVLRiè‡Á²R…ƒ«sVƒ«sõ Qúxms¼½Fyµj…»R½ ¸R…VW¬sÈýÁ ¹¸…VVNRPä NSLSù¿RÁLRißáÌÁV

ª«sVLji¸R…VV ryª«sVLóSQùÌÁƒ«sV xmsLjigRißÓáLiÀÁ LRiWF~Liµj…Li¿RÁ‡Á²T…ƒ«s„s. FyLRiVäÍÜ[ úxmsßØ×dÁNRPLjiLi¿RÁ‡Á²T…ƒ«s xqsµR…VFy¸R…WÌÁ

xmsÉíÓÁNRP C úNTPLiµj…„sµ³R…LigS DLiµj….

Page 45: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

ª«sLRiLigRiÍÞ ÍÜ[ úxms¼½Fyµj…»R½ ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä N]LRiNRPV BHFs ¬s®ªs[µj…NRP

ES.9 LSLiNUP Fs¬s*L][ xqsLki*|qs£qs \|ms#û®ªs[ÉÞ ÖÁ„sVÛÉÁ²`…

ƒ«sWÌÁV ª«sVLji¸R…VV B»R½LRi »R½¸R…W\lLiƒ«s D»R½ö»R½VòÌÁ g][µyª«sVVÌÁV

»R½¸R…W\lLiƒ«s ª«sxqsVòª«soÌÁ N]LRiNRPV ª«sWlLiäÉÞ xqósÌÁLi ª«sVLji¸R…VV

D»R½ö¼½ò úxmsµR…LRi+ƒ«s ZNP[LiúµR…ª«sVV

xmsLkiOSQ úxms¹¸…WgRiaSÌÁ

3 ryª«sWÑÁNRP @ª«sróyxmsƒ«s

NSLjiøNRPVÌÁ ¥¦¦¦xqísÍÞ xqsµR…VFy¸R…VLi

úZNP¿`Á, \®ªsµR…ù xqsµR…VFy¸R…VLi

ªyßÓáÇÁù ZNP[LiúµyÌÁV/„sƒ¯[µR… ZNP[LiúµyÌÁV ®ªsVVµR…\ÛÍÁƒ«s„s

úFyÛÇÁNíRPV HµR…V µR…aRPÌÁªyLkigS @ª«sVÌÁVxmsLRi¿RÁ‡Á²R…V»R½VLiµR…¬s xmsLjigRißÓáxqsWò, \|msƒ«s ¾»½ÌÁVxms‡Á²T…ƒ«s úFyÛÇÁNíRPV ª«sù¸R…VLi,

INRP ¬slLôi[bP»R½ µR…aRPÍÜ[ @Õ³Áª«sXµôðj… xmsLRi¿yÖÁ=ƒ«s ®ªsVV»R½òLi Q\®ªsaSÌÁùLiQ\|ms xqsLi‡ÁLiµ³j…»R½ µR…aRPÌÁ N]LRiNRPV ª«sVLjiLi»R½

„s˳ÏÁÑÁLi¿RÁ‡Á²T…Liµj….

7. ¾»½ÌÁLigSßá úxms˳ÏÁV»R½*Li ƒ«sVLi²T… AbPLi¿RÁ‡Á²T…ƒ«s xqsx¤¦¦¦NSLRiLi (ÑÁJÉÓÁ)

®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä ¹¸…VVNRPä @Õ³Áª«sXµôðj…¬s µR…aRPÌÁªyLkigS „s˳ÏÁÑÁLi¿RÁ²R…Li @®ƒs[µj… ALójiNRP @xqsLi‡ÁµôðR…»R½ƒ«sV

»R½gæjiLi¿RÁ²y¬sNTP ª«sVLji¸R…VV ª«sVµR…VxmsoµyLRiVÌÁ „saS*ry¬sõ |msLiF~Liµj…Li¿RÁ²y¬sNTP @ª«sxqsLRiLi; úFyLRiLi˳ÏÁNRP |msÈíÁV‡Á²T…

ª«sVLji¸R…VV Lji£qsä »R½gæjiLi¿RÁ²R…Li µy*LS, ª«sVLji¸R…VV ¬sLRi*z¤¦¦¦Li¿RÁgRiÌÁ ®ªs[gRiLi»][ @Õ³Áª«sXµôðj…NTP „dsÌÁVNRPÖÁöLi¿RÁ²R…Li

µy*LS. @Õ³Áª«sXµôðj… @®ƒs[µj… INRP xqs*ÌÁöcFs}qísÉÞ ƒ«sVLi²T… úFyLRiLi˳ÏÁª«sVª«so»R½VLiµj… ª«sVLji¸R…VV ˳ÏÁW„sV ry*µ³k…ƒ«s»R½

¹¸…VVNRPä ª«sWLRiV»R½Vƒ«sõ lLi[ÈýÁ»][ ®ƒsª«sVøµj…gS „sxqsòLjixqsVòLiµj…. Bµj…, FsLiÉÓÁzms @Li»R½ÉØ xmsLjiúaRPª«sVÌÁ róy¬sNRP»R½

¬sLRi*x¤¦¦¦ßá»][ A¿RÁLRißáxmspLRi*NRP „sxqsòLRißá ª«sVLji¸R…VV @Õ³Áª«sXµôðj…¬s ¬sLôðSLjixqsVòLiµj….

µR…aRPÌÁªyLki úxmsßØ×ÁNRP @®ƒs[µj… FsLiÉÓÁzms ¹¸…VVNRPä @Õ³Áª«sXµôðj… N]LRiNRPV INRP ryµ³yLRißá ª«sWLæRiµR…Lji+¬s @Liµj…xqsVòLiµj…

ª«sVLji¸R…VV ª«sWlLiäÉÞ ²T…ª«sWLi²`…ƒ«sV ‡ÁÉíÓÁ, @ƒ«sVNRPWÌÁ»R½»][ {qs*NRPLjiLi¿RÁ‡Á²R…V»R½VLiµj…. úxms¼½Fyµj…»R½ @Õ³Áª«sXµôðj…

µR…aRPÌÁV, ª«sWlLiäÉÞ ²T…ª«sWLi²`…NRPV @ƒ«sVgRiVßáLigS NSÍ؃«sVgRiVßáLigS xqs„dsVOTPQLi¿RÁ‡Á²yÖÁ; úxms¾»½[ùNRPLigS

˳ÏÁ„sxtsQù»R½VòÍÜ[¬s N]»R½ò ¸R…VW¬sÈýÁV/„s˳ØgSÌÁ @Õ³Áª«sXµôðj… „sxtsQ¸R…VLiÍÜ[.

LSxtísQûLiÍÜ[ INRP aRPNTPòª« Li»RQ\®ªsVƒ«s ÇÁª«so×dÁ ª«sVLji¸R…VV µR…VxqsVòÌÁ xmsLjiúaRPª«sV @Õ³Áª«sXµôðj… ¿ÁLiµyÌÁ®ƒs[ INRP µR…XN][äßجsõ

ÑÁJÉÓÁ NRPÖÁgji DLiµj…, µk…¬s»][ Dµ][ùgSÌÁ GLSöÈÁV\|ms µR…XztísQ ryLjiLi¿RÁgRiÌÁ xqsLixmspLñRi ªyùÌÁWù Q\¿Áƒ±s

@Õ³Áª«sXµôðj…NTP LSxtísQûLiÍÜ[ „dsÌÁVNRPÖÁöLi¿RÁ‡Á²R…V»R½VLiµj…. C ¬s®ªs[µj…NRPÍÜ[¬s ¿³yxmísL`i 6 ÍÜ[, C úFyÛÇÁNíRPV ¹¸…VVNR ä

xqsxmnsÖdÁNRPX»R½\®ªsVƒ«s @ª«sVÌÁV N]LRiNRPV ÑÁJÉÓÁ ƒ«sVLi²T… @ª«sxqsLRi\®ªsVƒ«s NUPÌÁNRP\®ªsVƒ«s úF¡»y=x¤¦¦¦NSÌÁV „sª«sLRiLigS

Bª«s*‡Á²ïyLiVV. C úF¡»y=x¤¦¦¦NSÌÁV, A¸R…W úxms®µ…[aSÌÁÍÜ[¬s NSLRiù¬sLRi*x¤¦¦¦ßØ Lji£qsä ª«sVLji¸R…VV ÅÁLRiVèÌÁ

@Li¿RÁƒy µy*LS xqsWÀÁLi¿RÁ‡Á²ïyLiVV. ˳ØLRi»R½®µ…[aRPLiÍÜ[ B»R½LRi ÇÁª«so×dÁ ZNP[LiúµyÌÁ»][ F¡ÖÁ胫sxmsöV²R…V, ª«sLRiLigRiÍÞ

ÍÜ[ xqsLixmspLñRi ªyùÌÁWù Q\¿Áƒ«s%`Á NSLSù¿RÁLRiƒ«sÌÁV ª«sVLji¸R…VV ªyùÌÁWù A²`…= NSLSù¿RÁLRißáÌÁ ¹¸…VVNRPä INRP

Page 46: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

ª«sLRiLigRiÍÞ ÍÜ[ úxms¼½Fyµj…»R½ ®ªsVgS ÛÉÁN`P=Q\ÛÉÁÍÞ FyL`iä N]LRiNRPV BHFs ¬s®ªs[µj…NRP

ES.10 LSLiNUP Fs¬s*L][ xqsLki*|qs£qs \|ms#û®ªs[ÉÞ ÖÁ„sVÛÉÁ²`…

8. ryLSLiaRPLi

aRPNTPòª«sLi»R½\®ªsVƒ«s D¬sNTP ÛÍÁ[NRPF¡ª«s¿RÁVè. úxms¼½Fyµj…»R½ \|qsÈÁV úFyLi»R½Li @®ƒs[µj… INRP ÍØùLi²`… ÍØN`ïP QúFyLi»R½LiÍÜ[

DLi²R…²R…Li ª«sVWÍ؃«s, BLiµR…VÍÜ[ úFyxmsù»y xqsª«sVxqsùÌÁV ª«sVLji¸R…VV LRiªyßØ ÅÁLRiVèÌÁƒ«sV |msLi¿RÁª«s¿RÁVè.

Aª«saRPùNRP \®ƒsxmsoßØùÌÁV ÌÁÕ³ÁLi¿RÁNRPF¡ª«s²R…Li ª«sÌÁƒ«s, |msÈíÁV‡Á²R…VÌÁƒ«sV ANRPL<jiLi¿RÁ²y¬sNTP, úxms˳ÏÁV»R½*LiªyLRiV

ANRPL<RißÔá¸R…VNRP ALójiNRP ª«sVLji¸R…VV ALójiZNP[»R½LRi úF¡»y=x¤¦¦¦NSÌÁƒ«sV úxmsNRPÉÓÁLi¿yÖÁ=ƒ«s Aª«saRPùNRP»R½ DLiµj….

„sxqsòQX»R½ úZaP[ßÓá ÇÁª«so×dÁ ª«sVLji R…VV µR…VxqsVòÌÁ NSLSù¿RÁLRiƒ«sÌÁ ¹¸…VVNRPä gRiXx¤¦¦¦ ¸R…VW¬sÈýÁƒ«sV FyLRiVä

úxms¼½Fyµj…xqsVòƒ«sõLiµR…Vƒ«s, úFyÛÇÁNíRPVNRPV ¾»½ÌÁLigSßØ FyLjiúaS„sVNRP „sµ³yƒ«sLi ª«sVLji¸R…VV LSxtísQûLi ¹¸…VVNRPäúxms¼½Fyµj…»R½

ÇÁª«so×dÁ „sµ³yƒ«sLi úNTPLiµR… @LiµR…VËØÈÁVÍÜ[ Dƒ«sõ„s NSNRPVLi²y @µR…ƒ«sxmso ALójiNRP ª«sVLji¸R…VV ALójiZNP[»R½LRi

úF¡»y=x¤¦¦¦NSÌÁV NSªyÖÁ= DLiµj…. INRP ¬slLôi[bP»R½ gRiVLjiòLi¿RÁ‡Á²T…ƒ«s úFyLi»y¬sõ ¼½Ljigji gRiVLjiòLi¿RÁ²y¬sNTP ÛÍÁ[µy

„sxqsòLjiLi¿RÁ²y¬sNTP |msÈíÁV‡Á²R…VÌÁƒ«sV ANRPL<jiLi¿RÁ²y¬sNTP úxms˳ÏÁV»R½* úF¡»y=x¤¦¦¦NSÌÁV ª«sVVÅÁùQ\®ªsVƒ«s„s.

¾»½ÌÁLigSßØÍÜ[ @»R½ùµ³j…NRP úxms¼½ò @Õ³Áª«sXµôðj… ¿ÁLiµR…V¿RÁVƒ«sõ ÑÁÍýØgS ª«sLRiLigRiÍÞ DLiµj… ª«sVLji¸R…VV A úFyLi»R½LiÍÜ[

@¼½|msµôR… úxms¼½ò ª«sWlLiäÉÞ ¸R…WLïRiVÌÁƒ«sV NRPÖÁgji DLiµj…. úxms¼½ò NSNRPVLi²y, úxms¼½ò gji¬sõLig`i ª«sVLji¸R…VV ú|mszqs=Lig`i

xqsµR…VFy¸R…WÌÁ D¬sNTP»][, ÇÁÌÁ ÌÁ˳ÏÁù»R½ ª«sVLji¸R…VV LRix¤¦¦¦µyLji @ƒ«sVxqsLiµ³yƒ«s»R½ ª«sÌÁƒ«s FsLiÉÓÁzms úFyÛÇÁNíRPV

GLSöÈÁV ¿Á[¸R…VVÈÁNRPV ª«sLRiLigRiÍÞ INRP ANRPL<Ri¬ds¸R…V\®ªsVƒ«s gRiª«sVùLigS DLiµj…. \®ƒsxmsoßáùª«sLi»R½\®ªsVƒ«s NSLjiøNRP aRPNTPò

ÌÁ˳ÏÁù»R½ „sxtsQ¸R…VLiÍÜ[, ALiúµ³R…úxms®µ…[a`P, »R½„sVÎÏÁƒy²R…V ª«sVLji¸R…VV ª«sV¥¦¦¦LSxtísQûNRPV ª«sÌÁxqs ®ªs×Áþƒ«s ªyLjiÍÜ[

FsNRPV䪫s˳ØgRiLi ª«sLRiLigRiÍÞ ƒ«sVLi®²…[ @¬s gRiª«sV¬sLi¿RÁ‡Á²T…Liµj….

FsLiÉÓÁzms ÍÜ[ @»yùµ³R…V¬sNRP @ª«sróyxmsNRP»R½, Aµ³R…V¬sNRP xmýsg`i ª«sVLji¸R…VV }mýs xqsµR…VFy¸R…VLi ª«sVLji¸R…VV úxmsxmsLi¿RÁ

úxmsÆØù»R½ ryµ³yLRißá xqsµR…VFy¸R…WÌÁV GLSöÈÁV ¿Á[¸R…V‡Á²R…»yLiVV. C FyL`iä, IZNP[ úxms®µ…[aRPLiÍÜ[ ÇÁª«so×dÁ xqsLRi×Á¬s

xmspLjiò ¿Á[¸R…VVÈÁNRPV ¬sªyLjiLi¿RÁµR…gæRi xqsª«sVúgRi\®ªsVƒ«s ª«sWµj…Lji Aµ³yLRiLigS @Õ³Áª«sXµôðj… xmsLRi¿RÁ‡Á²R…V»R½VLiµj…. úFyÛÇÁN`íPÍÜ[

úFyLjiúaS„sVNRP úxmsª«sWßØÌÁV ª«sVLji¸R…VV ¬s‡ÁµôðR…»R½ÌÁV FyÉÓÁLi¿RÁ‡Á²R…»yLiVV ª«sVLji¸R…VV »R½µy*LS, xqs˳ÏÁù ¸R…VW¬sÈýÁV

úxmsxmsLi¿RÁªyùxmsòLigS ªyùzmsLi¿RÁVÈÁNRPV „dsÌÁVNRPÖÁöLi¿RÁ‡Á²R…»yLiVV. C úFyÇÁNíRPV ª«sÌÁƒ«s @µj…|msµôR… úZaP[ßÓá

N]ƒ«sVg][ÌÁVµyLRiVÌÁNRPV, INRP úxmsxmsLi¿RÁªyùxmsò ª«sVWÌÁª«sƒ«sLRiVÌÁ ZNP[LiúµR…LigS ¾»½ÌÁLigSßØ LSxtísQûLi A„sLRi÷é„sLi¿RÁVÈÁNRPV

xqs¥¦¦¦¸R…VNRPª«sVª«so»R½VLiµj….

Page 47: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 1.1

Chapter – 1 Introduction

1.1 Preamble

Telangana State Industrial Infrastructure Corporation (TSIIC) is a Telangana State Government

initiative for development of industrial areas. TSIIC was incorporated on 4th September 2014, vested

with the objective of providing industrial infrastructure through the development of industrial

Estates/Parks/Areas.

TSIIC has developed mega infrastructure projects including SEZs, biotech parks, MSME clusters,

NIMZ, etc. and also developed other infrastructure projects apart from Industrial Parks on its own.

TSIIC has so far developed over 150 Industrial Parks with areas ranging from 15 acres to 2500 acres.

TSIIC has presence in each and every District.

TSIIC proposes to develop Mega Textile Park (MTP) with state of art manufacturing facilities in

Warangal District, Telangana. TSIIC has identified required land at Shayampet Village of Geesugonda

Mandal and Chintalapalli village of Sangem Mandal; Warangal Rural District. The land acquisition is

almost completed.

1.2 Purpose of the report

TSIIC, a Government of Telangana State undertaking, proposes to setup a Mega Textile Park at

Warangal Rural district, which is a major cotton producing district and trading centre in the state.

The setting up of the park is expected to provide a major boost to the state’s textile sector by

ensuring a fair share of export revenues and also by enabling increased value addition to the cotton

production and employment generation raising the living standard of workers.

The setting up of the park is also expected to bring about a marked improvement in the operational

efficiency of the textile units in the state and reduce the monopoly of merchant exporters. The

proposed Mega Textile Park will be developed with all amenities required for environmental friendly

operation of Textile units, and other units which can be occupied by the industrialists without any

administrative hassles associated with setting up of an industry.

As per the Environmental Impact Assessment (EIA) Notification dated 14th September’2006 and its

subsequent amendments, the proposed developmental activity of establishing Mega Textile Park

which is less 500 Ha of the area falls under the category ‘B’ of Project Activity 7(c).

In line with the said Notification, a meeting was held in SEAC, Telangana on 21st February’2017 for

finalization of Terms of Reference (ToR). SEAC, Telangana has issued ToR for preparing EIA report

vide letter No: SEIAA/TS/OL/WGL/-18/2017-3543 Dated: 17th March, 2017.

1.3 Identification of project and Project proponent

The proposed MTP is being planned as per global standards to boost productivity, augment

efficiencies, enhance quality and increase competitiveness of the textile industry. The project will

offer an ecosystem for complete textile value chain and set up eco-friendly integrated facility for all

Page 48: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 1.2

textile related activities. The development strategy of the proposed project is based on the Fibre to

Fashion concept. Categorization of the project as per EIA notification is given in Table 1.1.

Table 1.1 Categorization of the Project

EIA Notification – 14.09.2006 No.S.O.1533 & Subsequent Amendments

Project Activity Project/Activity 7 (c) – Industrial Estate

Category Category ‘B’ (The proposed project is Industrial Textile Park with an area of less than 500 ha).

Location Shayampet (V) of Geesugonda (M) & Chintalapalli (V) of Sangem (M), Warangal Rural Dist.

Project Details

Project Name Mega Textile Park (Spinning, Weaving, Knitting processing, Made-ups, Apparel / Readymade Garments)

Project Area 1190.67 Acres – (481.85 Ha.); Number of units approximately 224

The project proponent for developing the MTP is TSIIC having their head office at Hyderabad and

Zonal office in Warangal. The contact details of the concerned officers are given below.

Head Office Zonal Office (Site Office) O/o. Chief Engineer “Parisrama Bhavanam” 5th Floor, 5-9-58/B, Fateh Maidan Road, Baseerbagh, Hyderabad – 500 004 Ph: 040-23237625, 23237626 Fax: 040-23240205, 23241385 E-mail: [email protected]

Rathod Rathan Zonal Manager (FAC) Near TATA Motors, Mulugu Road, Warangal Ph: 0870-2623217, E-mail: [email protected]

1.4 Brief description of nature, size, location of the project & its importance to the country, region The Government’s role in Textile sector extends to a range of activities such as price support to

cotton and jute, incentives for investments in technology up-gradation and modernization, setting

up of world class Integrated Textile Parks, implementation of Technology Mission on cotton, jute and

textiles, development of mega clusters for power looms, handlooms and handicrafts, development

of sericulture and wool sub-sectors by implementing a number of schemes, implementation of

welfare schemes for handloom weavers and handicrafts artisans and promoting skill development of

textile workers in collaboration with the industry. The Government is also providing a number of

incentives for export of textile products.

Telangana is one of the largest producers of long staple cotton with production of around 43 lakh

bales per annum. The state stood at third position in the country in cotton production during the

year 2014-15. The state is known for skilled textile workers but due to absence of industry, they

migrated to other states for their livelihood. The proposed MTP shall be planned as an integrated

textile park covering all the trades of textile viz. from yarn to finished product with all requisite

infrastructure facilities to provide a conducive working environment to the units in the Park and also

to the workforce. The Park shall be an environment friendly eco-system comprising of physical and

common infrastructure components interwoven with green spaces.

The proposed MTP shall be implemented in a phased manner depending on the market demand.

Due to large size of the project, a long term strategy shall be adopted for the complete

Page 49: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 1.3

implementation of the project. The phasing approach will help in ensuring sustainable development

of the park and also in ensuring availability of fabric, accessories and man power.

1.5 Project Site

The project site is located in Warangal Rural district of Telangana State at a distance of 0.6 Km E of

Chintalapalli village and 0.7 Km N of Shayampet village, 0.5 Km W of Venkatapuram village and

0.6Km of Sangem (Taluk headquarter). The major city nearer to the proposed project is Warangal

(District headquarter) at a distance of 8.0 Km (SW). Geographical co-ordinates of the site are 170 54’

29” North Latitude and 780 41’ 37” East longitude. Photographs of the site and its surrounding areas

are given in Figure 1.1.

Figure 1.1 Photographs of the site and its surrounding areas

Proposed Project site Road Connectivity

Site road connecting to Warangal-Narsampet Road

Proposed Project site

Proposed Project site Railway Crossing

Page 50: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 1.4

1.6 Salient features of Proposed Project site

The project site is relatively flat with minimum undulations. The site slopes from north to north east

with ground contour levels varying from minimum 250m MSL to maximum of 264m MSL. The salient

features of project site are given in Table 1.2.

Table 1.2 Salient features of project site

Details Description

Location Shayampet village of Geesugonda Mandal and Chintalapalli village of

Sangem Mandal, Warangal Rural Dist., Telangana State

Coordinates 170 54’ 29” N and 780 41’ 37” E

Land 1190 Acres (481.57 ha)

Nearest habitation 0.6 Km E of Chintalapalli villages; 0.7 Km N of Shayampet villages; 0.5 Km W of Venkatapuram villages; and 0.6Km of Sangem Taluk.

Present Land Use Partly barren land, partly double crop land

Road connectivity Warangal-Narsampet (3Km) N. The NH-163 is underway.

Rail Connectivity Kazipet & Warangal are two major stations. South Central Railway zone.

The Warangal-Khammam railway line is passing through the project site.

The closest railway stations being Vanchanagiri and Chintalapalli.

Airport Hyderabad International Airport 190 Km SW.

Sea Port Machilipatnam (330 Km); Kakinada (400 Km); Visakhapatnam (530 Km);

Chennai (665 Km). There is a proposal for a dry (Inland) port in Telangana.

Rivers/canals SRSP (Kakatiya) canal which is passing along the boundary from North to

south west side of the site.

Water bodies Sangem lake 3km S, Yelgur lake 3.5km SE, Gadepally lake 1.5kmW, Bhadrakali lake 11.5km NW

Seismicity Seismic Zone II (least active)

Hills/Valleys None

Archeologically Important

places

Warangal Fort 8.0km NW; 1000 Pillars Temple 14.0km NW; Bhadrakali

Temple 11.5km NW

National Parks/ Wildlife

sanctuaries

None

Reserved & Protected

forests

None

Defence Installations None

1.7 Need/Justification for the Project

Telangana is one of the largest cotton producing states in India but only 20% of the cotton produced

in the State is used by Industry present in the State. The remaining 80% of the cotton produced by

Telangana goes to other states for spinning and thereby losing the opportunities for value addition,

employment creation and socio-economic up-liftment of the local population. Looking at the

potential for value addition in the State, an integrated MTP shall not only help in strengthening the

economy but also help in stemming the migration of skilled textile workers to other states with

Textile industries. It has been found that more than 5 lakh workers in Textile centers such as Surat,

Bhiwandi, Sholapur are originally from Telangana and migrated for jobs.

Page 51: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 1.5

With an objective to address the gap in present Textile Industry in Telangana, TSIIC envisages setting

up of a MTP in Warangal Rural District. The Park will house common infrastructure, plug and play

facilities, common facilities and social infrastructure to support all activities in textile value chain.

The Project will be developed with the objectives to help the Indian Industry and particularly the

units in Telangana to become globally competitive and to help the State in creating employment and

thereby addressing the issue of labour migration.

In order to provide the Textile Industry with world-class infrastructure facilities for setting up their

Textile units at potential growth centers; Scheme for Integrated Textile Park (SITP) was approved in

July 2005. The Government of India (GoI) has decided to continue SITP in the 12th Five Year Plan. All

the units related to the entire supply chain of Textile Industry are eligible, Government of Telangana

(GoT) proposes to develop a Greenfield “Mega Textile Park” at Warangal, leveraging the inherent

strengths in the sector visà-vis industry presence and high cotton production. GoT has appointed

TSIIC as the nodal agency for the Project. The Project is proposed to be funded by TSIIC with financial

support from GoI under SITP. Some of the support facilities like CETP etc.; will be developed in a

Public Private Partnership (PPP) model.

TSIIC now intends to undertake a comprehensive programme for development of MTP and thereby

facilitate the economic development in the State. TSIIC envisages that developing Textiles parks in

the backdrop of successful implementation will facilitate additional investment, employment

generation and increase in Textiles production. TSIIC has engaged IL&FS Clusters Development

Initiative Limited (IL&FS Clusters) to facilitate the programme development and implantation of the

Project.

1.7.1 Demand Assessment

Warangal is the highest cotton growing district in Telangana and has one of the largest cotton

market yards in the region. Apart from cotton, presence of cotton ginning & pressing facilities,

availability of water and good railway & road connectivity make Warangal an attractive destination

to establish the MTP Project. In terms of availability of skilled manpower, it has been seen that

majority of skilled workers in Textile sector who migrated to other Textile hubs such as Andhra

Pradesh, Tamil Nadu and Maharashtra are originally from Warangal.

The annual cotton production in Telangana is 43 lakh bales per annum, equivalent to 85 lakh quintals

of lint. Though, spinning is already in excess capacity nationally, Warangal has a unique advantage of

availability of cotton and is one of the prominent hubs for cotton trade in the country. Presently,

cotton after sizing is transported to far of places like Tamil Nadu, Andhra Pradesh and Gujarat

majorly for spinning and value added services. In this context, there is a natural demand for spinning

and value added services which could be explored in the Textile Park.

The MTP will establish state-of-the-art infrastructure, modern plug and play facility and world class

common facilities. The Park will be developed on a vertical integrated model to cover complete

Textile chain in one place. The Project shall meet the Industry standards and compliances and

thereby allow the member units to complete globally. The Project will also help in positioning

Telangana as a global sourcing hub for large scale buyers.

Page 52: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 1.6

1.8 Project Development Plan

The development of the MTP is a long term strategy and it is important to phase the Project to

ensure sustained development of the Park. The phasing will ensure availability of fabric, accessories

and manpower for 75% of sales value of garment. The Project marketability shall also be focused and

it will be important to identify entrepreneurs with experience in the manufacturing and willing to

establish new units or reallocate part of existing units. The region proposed for MTP is well suited for

export to Japan and other Eastern countries.

Phasing of mega textile park development is essential in reducing financial uncertainty and boosting

potential investors’ confidence; through the minimization of initial capital outlay and risk, and

facilitation of development at manageable pace. Development will begin from a mini-estate and

gradually expand with changing rates of land occupancy. This will ensure practical expansion and

development with organized location of industries throughout MTP.

1.9 Scope of the study

The primary objective of the EIA studies is to internalize and integrate the environmental concerns /

aspects, and mitigation measures into the project planning stages like basic design, detailed design,

and construction and operation phases of the project. Monitoring and feedback on Health, Safety

and Environment (HSE) and training activities can be planned thoroughly and effectively with the

help of these studies. To achieve the above objectives the following strategy is recommended.

1. EIA is to be prepared with baseline data collection and making use of preliminary design

specifications/data of the proposed operations.

2. The findings and recommendations of the study are to be incorporated into the project

planning, design, construction and operation stages of the project.

3. The EIA will cover one season baseline environmental data, as per ToR issued by SEAC. The

scope includes collection of baseline data with respect to major Valued Environmental

Components (VECs); defined as fundamental elements of the physical, biological or socio-

economic environment, including the air, water, soil, terrain, vegetation, wildlife, birds and

land use that may be affected by a proposed project along with the parameters of human

interest and prediction and evaluation of environmental impacts to delineate Environmental

Management Plan (EMP).

In order to assess the likely impacts arising out of the proposed project on the surrounding

environment and recommending environmental safeguards to alleviating the likely negative

impacts, TSIIC has engaged M/s. Ramky Enviro Services Pvt. Ltd. (RESPL) as their environmental

consultant. RESPL had carried out the Rapid Environmental Impact Assessment (REIA) studies for

various environmental components and submitting REIA, which are likely to be affected and

suggested EMP.

The scope of study includes detailed characterization of existing status of environment in an area of

10 km from the proposed project as its centre for various environmental components.

Any developmental activity in general is expected to cause impacts on surrounding environment of

the project site during its implementation and operation phases, which can be both positive and

Page 53: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 1.7

negative. The nature and intensity of impacts on different components of environment depend on

the type of project activities and geographical conditions of the study area. The impacts of the

project activities on environmental components can be quantified through EIA Studies within the

impact zone of the project activities. The results of EIA Studies form the basis for the preparation of

a viable EMP for mitigation of the impacts.

1.10 Legal Frame work for the implementation of Environmental Clearance conditions

Form-1, PFR Project report with Proposed

ToR to SEAC

Treated as category A- if

general condition apply

EC rejected by SEIAA on the

recommendation of SEAC

Category B1-EIA required Category B2-EIA not required

ToR approved by SEAC

Draft EIA report to SPCB

by PP

Display at Panchayat, ZP, DM/DC

/Dy. Com& on the SPCB website

Summary EIA & Form-1-display

on the website by SPCB

Public consultation

processed by SPCB

Proceedings of Public

consultation

Scoping by SEAC

site visit by sub

group of SEAC, if

necessary

Appraisal &

recommendation by

SEAC

To PP for submission of Final

EIA/supplementary report to

draft EIA

Referred back to SEAC under

communication to the PP

Display on the

SEIAA website

Decision by

SEIAA Reject

ed

Approved

Post EC Monitoring

Display on the SPCB website &

PP website

Display on the SPCB website &

PP website

Display of Compliance

report on SEIAA website

Page 54: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.1

Chapter – 2 Project Description

2.1 General

This chapter describes the development plan of proposed MTP covering project land, details of layout

/plant technical features, project size, raw material requirement, production capacity, supply &

demand, source and storage, utilities & services, estimated cost of project, and project implementation

schedule, etc.

2.2 Location of the Project

The Proposed Mega Textile Park site is located at Shayampet Village of Geesugonda Mandal and

Chintalapalli Village of Sangem Mandal in Warangal Rural district. The encompass areas falling under

two villages namely Shayampet & Chintalapalli. The proposed site has good road connectivity. The

location map of the proposed project is given in Figure 2.1.

2.3 Project Land

The proposed project is planned in an area of 1190 acres acquired from land owners and the breakup

details of the same are provided in Table 2.1.

Table 2.1 Project land use details

S.No Acquired Land Acres Percentage Remarks

1 Land for Industrial Purpose 750 63% Greenbelt 33% (393 Acres); Green areas in industries 188 acres; along roads 45 acres; in common amenities 10 acres; common infrastructure 20 acres; along the boundary and open spaces 130 acres

2 Roads 179 15%

3 Common Amenities 48 5%

4 Common Infrastructure 83 7%

5 Green/Open space 130 10%

Total 1190 100

2.4 Details of Industrial Estate Master Plan

A state-of-the-art site Master Planning incorporating holistic & sustainable development concepts and

eco industrial development concepts is prepared and presented as Figure 2.2 covering following:

- Long term vision with focus on international competence

- Create new industrial employment opportunities

- Focus on integrated infrastructure

- Optimal utilisation of available land and flexibility in plot division owing to the irregular

shape of the project site.

- Optimal use of natural resources including energy conservation measures

- Traffic management, Disaster management

- Inclusion of social infrastructure – housing and allied requirements

- Integration of operation and management aspects

Page 55: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.2

Figure 2.1 Location map of the proposed project site

Page 56: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.3

Figure 2.2 Conceptual Master Plan for the Mega Textile Park

Page 57: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.4

The master plan has been conceptualized considering the opportunities and constraints of the site. To

summarize, the design philosophy revolves around prioritizing various aspects viz., circulation, land

suitability, environmental sustainability and topography to optimize various land uses. Such an approach

shall ensure that various stakeholders of the project as well as the environment are benefited.

2.4.1 Planning considerations

Planning for the proposed project is carried out based on the concept of zoning. Zoning of area for

industrial use, common utilities, entrance and exit, access roads, utility corridors, etc. is done based

on the following.

a) Site topography: The site is predominantly plain sloping towards the north east. The maximum

difference in levels in the site is 14m. These topographical aspects were considered for water,

wastewater and storm water management.

The terrain of the Project site is generally flat. The land area of the Project site is mostly vacant land

with grass, open scrub other mixed vegetation. Agricultural land of corn, maize, cotton and paddy

cultivation is available in and around the Project site. There are also mango groves in the area. Some

parts of the Project site are rocky in nature. There is no forest area in the Project site. There are no

national parks, marine parks, sanctuaries, wild life habitats, biosphere reserves, within 15 km of the

proposed Project boundary. The Warangal Fort and other structures of archaeological importance

and heritage sites located in Warangal are at a distance of about 8 km (aerial distance) from the

boundary of the project site.

Canal from the Sri Rama Sagar Project (SRSP) adjoins the Project site on the west and south. The

SRSP is an Indian flood-flow Project on the Godavari River. SRSP is an irrigation Project across river

Godavari in Telangana to serve irrigational needs in Karimnagar, Warangal, Adilabad, Nalgonda, and

Khammam districts.

b) Existing and Proposed Road Network: The project site is about 21 Km from Warangal city. It can

be accessed by road via Warangal – Narsampet road which also leads to Khammam, Kothagudem &

Bhadrachalam. This road is a two lane highway with divided carriageway at some portions and

without a divided carriageway at few stretches. The already existing roads were taken into

consideration while proposing to expand the road network.

There is also an alternative road connectivity that goes through Shayampet & Vanchanagiri villages.

This road is longer in distance and narrow in width for RoW.

A dedicated corridor will be developed for the project originating at Gangadevipally; a village on the

Warangal Narsampet Road. This requires a new alignment to be developed from the main road up

till reaching the existing road after bypassing Parvathagiri, Mariyapuram and Ookal Villages which is

beneficial as social issues will be minimised and also the corridor will be more or less straight in

alignment without many kink/bends. Approximately 2.4 km length of land will need to be acquired

for the access road from Gangadevipally till the existing road. The alignment mostly traverses

through fields;

Page 58: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.5

The new alignment also envisages a RoB over the railway line through the project site and onto the

other side into existing project lands, thereby enabling direct access and connectivity into the

project site.

Figure 2.3 Proposed Dedicated Access Road

Figure 2.4 Regional Road connectivity

Page 59: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.6

2.4.2 Overall Project Site zoning

The proposed project area of 1190 acres is proposed to be divided into following 5 zones. Based on

the zoning concept, land use is prepared incorporating the current plot divisions and possible future

sub divisions. The industrial plots, common utilities, infrastructure services are conveniently located

based on the site boundary, contour and other factors. In the land designated for industrial

activities, industrial clusters are preferred to individual industries which results in synergy and co-

existence and optimal sharing of industry related facilities.

Table 2.2 Proposed Phasing plan

Value chain/Phase Phase

Total 1 2 3 4 5

Spinning 3 3 3 3 3 15

Texturing 2 2 2 2 2 10

Weaving 4 5 7 9 12 37

Knitting with processing 1 2 2 4 6 15

Process house – Woven fabric 2 2 2 6 8 20

Yarn dying 1 1 1 2 2 07

Towel & Sheeting 2 2 2 2 2 10

Printing units (Flat bed, Digital printing) 2 2 2 3 3 12

Ready-made garments 6 6 8 12 14 46

Total No. of units 23 25 29 43 52 172

Land Area (acres) 265 235 220 230 240 1190

Page 60: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.7

Figure 2.5 Zoning in Project Area

Page 61: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.8

Figure 2.6 Proposed Project Concepts

Page 62: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.9

2.7 Positioning of the Mega Textile Park

Page 63: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.10

Table 2.3 Summary of capacities & Area requirement

Trade/Fabric Woven cotton

Non-woven cotton

Knits cotton

Knits non-cotton

Apparel/RMG

No. of sewing machines 30,000 12,000 30,000 12,000

Production pieces/day 1,065,020 240,000 675,000 270,000

Fabric requirement in Kg/day 94,500 42,000 168,750 216,000

No.of units 45 25 45 25

land required/unit (acres) 44 20 44 25

Employment 60,000 24,000 60,000 24,000

Weaving/Knitting & Processing

No. of looms (Airjet/waterjet/Knitting machines)

1,575 1,120 422 180

Fabric for weaving (Sq. m/day) 945,000 504,000 168,750 54,000

Fabric for processing (Kg) 96,000 42,000 192,000 54,000

No.of units 8 6 8 4

Land required/unit (acres) 105 69 60 28

Employment 2,100 1,152 2,450 1,169

Spinning

No. of spindles 100,000 150,000

Production based avg. Ne 30 s in Kgs/day

50,500 60,000

No.of units 3 2

Land required/unit (acres) 50 75

Employment 950 1200

Madeups

Total no.of looms 1,225

No.of units 6

Land required/unit (acres) 84

Employment 7518

2.4.2.1 Proposed Product Mix

The proposed Textile Park by TSIIC will house a mix of various Textile processing units ranging

from ginning, spinning, knitting, weaving to apparel manufacturing. The capacities of the units

proposed to be set up in the Park are presented in the below table.

Table 2.4 Proposed Product mix

S.No Activity No.of Units Total Production Capacity/Annum

1 Spinning 27 6.38 Lakh-kg

2 Weaving 28

10.68 Lakh – mt 3 Knitting 142

4 Processing 21

5 Apparel 112 0.52Lakh bed sheets + 1.32 lakh garments

Total 330

Page 64: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.11

2.4.2.2 Proposed Production Process

Textile manufacturing process involves long and complicated processes. Textile fibers are converted

to yarn and grey fabrics. The grey fabric is then converted into finished fabrics to finally manufacture

garments.

1. The basic manufacturing process flow chart is given below.

Figure 2.8 Basic Textile Manufacturing process flow chart

a. Textile Fibers Fibre is any substance that has high length to width ration. However apart from having high

length to width ration, Textile fibers have suitable characteristics for being processed into

fabric.

b. Yarn Yarn is a continuous strand which is made by natural or synthetic Fibre or material twisted or

laid together that can be made into a textile fabric. Yarn may be divided into two groups

depending on their use – weaving yarn and knitting yarn.

c. Grey Fabric

A cloth of flexible planar substance constructed from solutions, fibers, yarns in any

combination. Grey fabric is the fabric before finishing such as dyeing, printing or any other

finishing activities. Generally grey fabric is not ready for making garments.

d. Finished Fabrics

The fabric that is comes as a result of dyeing, printing or any other finishing process is called finished.

e. Garments

Garments are final step of Textile processing.

Textile Fibers

Yarn

Grey Fabric

Finished Fabric

Garments

Yarn Manufacturing –Spinning Mills

Fabric Manufacturing –Weaving Knitting, Industry

Wet Processing – Dyeing, Printing, Finishing Industry

Garment Manufacturing –Garment Industry

Page 65: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.12

2. The main processes involved in manufacturing of Textile products are given below.

a. Spinning

Spinning is the first step in Textile processing. The process of making yarns from Textile

fibers is called spinning. Spinning from fiber to yarn is a very complex process. The

process flows involved in spinning process given in below Figures.

Figure 2.9 Process flow chart for cotton yarn ring spinning

Figure 2.10 Process flow for Cotton Yarn Open end spinning

b. Knitting

The process by which fabric is produced by set of connected loops from a series of yarn in weft or

wraps direction is called knitting. Knitted fabrics are produced by knitting technology. The process

flow chart for circular knitting shown below Figure 2.11.

Page 66: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Tublar Inspection Tublar Heat Setting

Slitting

Stenter

Grey Yarn

Precesion Soft Winding

Yarn Dyeing

Hydro Extraction

Dryer

Back Winding

Circular Knitting

Inspection

Packing

Bagging

Compactor Tublar Compactor Open Width

Soft Flow

Squeezing

Relax Dryer

Figure 2.11 Process Flow Chart for Circular Knitting

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.13

Page 67: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.14

c. Weaving

The process of producing a fabric by interlacing warp and weft threads is known as weaving. The

machine used for weaving is known as weaving machine or loom. Weaving is an art that has been

practiced for thousands of years. Weaving machines are classified according to their filling insertion

mechanism. They are mainly classified into two categories – shuttle and shuttle-less. The basic

process flow chart of weaving shown in Figure 2.12.

d. Yarn dying

Yarn dyeing is slightly difference from woven or knit dyeing. Dyed yarns are used for making stripe

knit or woven fabrics or solid dyed yarn fabric or in sweater manufacturing. Yarns are dyed in

package form or hank form by yarn dyeing process. The process flow chart for yarn dyeing is shown

below Figure 2.13.

Figure 2.12 Basic process flow chart of weaving

Figure 2.13 Yarn dying

e. Garmenting

Various units would sew different parts of the garment, such as the sleeves, hand sewing or

trimming, as required. The product would thereafter pass through quality control, ironed and hand

tagged before being put into the inventory for shipment. The process of embroidery involves putting

patterns/designs on the garment. The process for manufacturing of woven garment process flow

chart is shown in Figure 2.14.

Page 68: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Alter Spotting

Pressing

Inspection

Tagging & Final Inspection

Packing

Inspection

Rectification of Defects

Thread Cutting

Washing

Button Holing

Marking for Button Placement

Button Attachment

Assembly of Parts

Checking for Specs

Marking for Button Hole

Numbering of Parts in Sequence of Layers

Fabric & Garment Accessories Store

Inspection

CAD/CAM Pattern Development

Spreading & Cutting

Fabric Development

Sampling

Fit and IT & Specks Approval

Bundling of Parts

Distribution to Assembly Line

Shipping

Hydro

Tumble Drying

Ramky Enviro Services Pvt. Ltd. 2.15

EIA Report for Proposed Mega Textile Park at Warangal

Figure 2.14 Process Flow Chart for Woven Garments

Page 69: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.16

2.4.3 Circulation and Road Hierarchy The entire area will have different hierarchy of roads, with the primary road of 45 m &30 m RoW.

The secondary road is 18 m RoW.

Types of Internal Roads:

a. Type I: 45 m wide with median & 3 lane (10.5m) carriage on both sides.

b. Type II. 30 m wide roads with/without median & 3-lane (10.5m) carriageway on both sides.

c. Type III. 18 m wide roads with 7.5m carriageway.

The utility corridor would run parallel to either side of the road links and would require a minimum

width of 2-3m on either side to accommodate water supply lines, sewage conveyance lines, storm

water drains etc.

2.4.4 Greenbelt

Greenbelt/green areas proposed within the project and a total area of ~130 acres is earmarked for

greenbelt/green areas development which is about (10%) of the project area at park level.

2.4.5 Common amenities/Industry Related Facilities

Following amenities are proposed in the proposed park.

Customs & security check facilities at entry/exit location. Administrative building along with Emergency Control Room (ECR) Fire station at prominent locations near the entrances Community hall, recreational spaces, commercial areas, banks and ATMs, Post Office,

cafeterias, fuel filling station, hotel/canteen, convention center etc.at convenient locations distributed along the processing area for easy access.

Wastewater treatment plant (CETPs and STP)

Storm water recycling unit Solid waste management and disposal Hospital/clinic at convenient locations Child care

Apart from the above common amenities, textile processing area will also include industry related facilities like R&D centers, material testing centers, Quality Control (QC) laboratories, raw material banks, training centers; weigh bridge, exhibition cum business center etc. 2.5 Infrastructure Services and Facilities

The preliminary engineering aspects of the infrastructure facilities proposed in the facility described

and the following:

Water supply network including proposal for RO plant

Fire protection services

Wastewater management

Storm water management

Site grading

Solid waste management

Power supply system

Page 70: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.17

2.5.1 Water supply system

2.5.1.1 Water demand

Water resources for the proposed Project are of two fold. There is the SRSP canal which runs close to

the Project site. The SRSP canal is a perennial source of water mainly used for irrigation purposes.

The other source of water at the Project site is the Bhagiratha project, which is a drinking water

project for every household in Telangana. Bore water, will also be used to sustain the Project needs.

The proposed park comprises units in textile value chain, common facilities, social infrastructure and

fire safety. The water requirement is calculated based on the requirement for the processing and

domestic usage. The calculated aggregate ultimate water requirement for the MTP is about 40 MLD.

The total water balance as follows:

Table 2.5 Water balance (MLD)

Water supply Fresh Treated Water

Demand Wastewater Generation

Remarks

Domestic water 3.0 5.8 8.8 8.0 Treated in CSTP & reused

Industrial

Textile Processing 2.6 18.0 20.6 14.4

Treated in CETP and reused Other units 6.7 0 6.7 4.6

Greenbelt, fire water makeup, etc.

2.1 1.8 3.9 0

Total 14.4 25.6 40.0 27.0

Domestic water assumptions: Employees 190000 @45LPD; Workers in quarters 1500 @ 135 LPD; Greenbelt @ 10KLD/acre Source of water: SRSP Canal & Ground water

The industrial water demand within the park is estimated at 31.20 MLD, out of which about 20.6

MLD shall be for textile processing units. Though the total water requirement is 40 MLD, the treated

effluent from the CETP and CSTP to the tune of about 18 MLD shall also be topped up in the system

for textile processing units and rest of the treated water will be used greenbelt, flushing, dust

suppression, etc. Domestic water requirement is estimated at 8.80 MLD which includes the potable

and non-potable needs of industrial workers. Firefighting demand in the Park is estimated at 0.11

MLD.

2.5.1.2 Reuse of Water

An underground sewerage network has been designed to collect sewage from each building and

convey it to a sewage treatment plant. At the STP, the sewage would be treated to acceptable

standards and the treated sewage could be used for irrigation purpose within the proposed park, for

greenbelt development.

2.5.2 Sewage Treatment System

a. A sewage treatment plant of 15 MLD (2.5MLD x 4 units) capacities using attached growth activated sludge process has been proposed for the MTP.

b. When the CSTP reached the about 70% of the capacity, the next phase of CETP shall be proposed.

Page 71: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.18

c. The STP shall have a screen and grit removal mechanism followed by an equalization tank, aeration tanks with extended aeration and sludge recycling facility, secondary clarifier with sludge removal mechanism, sand and activated carbon filters and a treated sewage tank.

d. Bleaching powder doses will be used for chlorination before disposal of the treated sewage. It is proposed that treated sewage will be used to the extent possible for landscaping and flushing of toilets.

2.5.3 Effluent Collection and Treatment System

The core textile processing facilities and the other textile units in the park are expected to generate

about 20.6 MLD. The waste water so generated will be conveyed through pipes and discharged into

the effluent treatment plant. The effluent collection network would be of about 22607m in and

would be separated from the domestic sewage collection system. The proposed CETP shall be

phased out as 5 MLD x 4 units. When the CETP reached the about 70% of the capacity, the next

phase of CETP shall be proposed.

The treatment process proposed is a biological treatment. Effluent shall be processed using

extended aeration technology with aeration tanks and secondary clarifiers with sludge handling and

processing units. The treated effluents shall be used for mass foresting in that area.

2.5.3.1 Design Basis and Treatment Scheme – CETP with Units and Equipment

After studying the topographic survey, collection and conveyance points’ survey, geotechnical

investigation reports and pollution load after sampling and analysis, the subsequent step is to work

out the treatment scheme and the design basis and specification of equipments of the proposed 20

MLD CETP.

2.5.3.2 Major components of CETP

The Major components in a ZLD based CETP includes, Collection and conveyance system, Pre-

treatment section, RO section and Evaporator section. The schematic flow chart of CETP is given in

Figure 2.15.

Figure 2.15 CETP schematic flow chart

Page 72: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.19

2.5.3.3 Collection & Conveyance System

Collection and conveyance system would comprise DI/HDPE/Cement pipe line to transport the raw

effluent from member units, manholes for cleaning, collection sump to receive effluent and effluent

transfer pumps to pump the untreated effluent to the CETP. The choice of pipeline material depends

on the nature (acidic/alkaline/ corrosive) of the effluent and costs. In some clusters, tankers are used

for transportation of effluents. Transportation with tankers may be viable where it is difficult to lay

pipelines and the volume of effluents to be transported is low, along with close monitoring (with GPS

tracking) & licensing, to avoid illegal discharges. In this Project, no transportation of effluent through

tankers are envisaged. The conveyance system for the Project would be through the following

pipeline networks:

a. Untreated or raw effluent collection and discharge network from the individual units to the CETP

b. Recovered water conveyance systems for return of recovered water from CETP to individual units

c. Recovered brine solution from CETP to member units

This consists of sewer network with gravity pipeline, Collection wells, intermediate pumping stations

& Online monitoring instruments including Electro Magnetic Flow Metering system (EMFM). DI pipes

with cement mortar coating have been used for Raw Effluent system and recovered water and HDPE

pipes have been used for Brine solution. The raw effluent from ember units is collected and

transferred to the Storage and Homogenization tank followed by Pretreatment, Reverse Osmosis

and Thermal Evaporation process. The entire systems are monitored through PLC/SCADA which is

connected with the website. The above collection and conveyance system is presented in the

schematic diagram Figure 2.16.

Figure 2.16 Schematic collections and conveyance system of CETP

Collection and Conveyance System of a typical ZLD based Textile CETP

Member Dyeing Units

Common

Effluent Treatment

Plant

SCADA / GPRSSYSYTEM

M

M

MBrine Solution

Recovered Water

DI with cement mortar coating

DI with cement mortar coating

HDPE

Electromagnetic Flow Meters

Raw effluent

Page 73: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.20

2.6 Storm water management

2.6.1 Design Considerations

Designing of the storm water disposal system would be a key design aspect of the proposed Park.

Considering the topographic features and the levels at the site with the corresponding off-site

drainage network, a network of storm water drains parallel to the proposed road network has been

planned to drain the storm water.

2.6.2 Design parameters

The following factors are taken into consideration for planning of the storm water drainage system:

The pattern of natural slope of the site, its extent and direction.

Strom water drained towards the ponds, thus natural drainage system in the downstream area.

The road network system envisaged and level of the roads.

The rain fall run off from plots/units, and other covered areas into catch basin connected to branch drain lay along the road adjacent property line. The branch drain carries the water into lateral, which in turn carries it to the trunk drain.

The rainwater from open spaces and from isolated places, flow over the ground following the natural slope and get into the nearest drain through the vertical grating.

As a camber of 2.5% on the pavement is provided, the runoff from the ROW shall flow towards the drains provided at either side of road.

For design of storm water drainage system for the park, following design parameters are considered:

- Rainfall Intensity: 45mm / hr for a return period of 2 years

- Runoff factor: 60% runoff factor from the total area

- Minimum gradient: 1 in 300

- Minimum velocity: 0.6 m /sec

2.6.3 Proposed drainage system

The network shall be designed to drain away the runoff from the plots and the roads would

comprise of open rectangular RCC drains with PCC floor. The storm water flow will finally drain into a

lead off storm water drainage system connected to the road system.

2.7 Integrated waste Management The main goal of Integrated Waste Management (IWM) planning in the Park is to optimise waste

management by maximizing efficiency, and minimizing associated environmental impacts and

financial costs. The waste hierarchy in IWM starts with waste prevention and minimization followed

by recycling/reuse, finally treatment and disposal. The system should be planned considering the

safety of workers and safeguard public health by preventing the spread of disease.

The Environmental Management Plan (EMP) proposed for the park envisages a comprehensive

waste management system comprising collection & segregation, reuse/ recycling, temporary storage

Page 74: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.21

and disposal. To accomplish this adequate numbers of bins, pickup vans, dumpers, compacters,

manpower, etc. will be employed. A primary collection system shall be put in place wherein

dedicated staff will be provided with tri-cycles and engaged in street sweeping activities Collection

bins would be located at convenient locations and such waste shall be transferred by the staff to the

nearest bin which would be collected by the tractor-cum-trailer.

The solid waste generated from street sweepings, packaging and other commercial activities in the

industrial units which is dry in nature and does not include the process wastes from the industries

shall also be collected and stored in segregation.

The overall collection activity itself would also involve segregation and as suggested in the table

above, the waste collected would be stored in a temporary storage facility which shall be designed

as per the CPCB/ MoEF guidelines and would have storage capacity of up to 90 days. Organic waste

segregated during collection itself will be sent to nearest composting facility and industrial dry waste

to any waste recycling facility. The rest will be sent for final disposal to a secured landfill facility.

2.8 Power supply

The following are the feasible options for drawing from grid.

2.8.1 Power Demand

The aggregate power demand of the Park is estimated to be approximately in the order of 210 MW

for the textile units, common amenities, social infrastructure, street lighting etc. including common

infrastructure. For the purpose of estimation the internal distribution of the complete park is

considered, including the cost of distribution transformers.

2.8.2 Transmission of Power

Northern Power Distribution Company of Telangana Limited (TSNPDCL) shall be responsible for

distribution and bulk supply of power in this area. There are three existing substations close to the

Project site;

a. 33/11 kV substation at Geesugonda at approximately 4 km (aerial distance from closest

project boundary).

b. 33/11 kV substation at Vanchanagiri at approximately 2.5 km (aerial distance from closest

Project boundary).

c. 132 kV substations at Geesugonda at approximately 4 km (aerial distance from closest

Project boundary).

TSNPDCL will be requested to setup the proposed sub-station as part of external infrastructure

assistance under the Industrial Development Policy.

2.8.3 Primary Distribution

a. 33 KV/ 11 Receiving stations: These stations are to be located in the load centres for sourcing of power to each utility area. 11 KV level as transformed from 33 KV level would be reticulated as ‘HV (11 KV) distribution system’ within the entire project area.

Page 75: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.22

b. Maximum Capacity of each 33/ 11 kV station is 15 MVA as per norms and nos. of stations would thus depend upon the anticipated load demand as projected.

c. 11/ 0.415 KV Plinth/ Pole mounted Stations: These 11 KV stations would be located for sourcing of power to all residential units/ plots and commercial/ public amenities with load demand less than 75 KW (each). These numbers will be considered on approximate basis.

d. 132/ 33/ 11 KV Transmission link to large/ medium and small Industrial units from Grid Station. Substation of these industrial units will be located within each industrial unit. However, route of each capacity/ voltage rating transmission link would be along the road and this aspect would be considered at Master Planning stage.

e. Route of 33 KV Transmission link whether underground or overhead would be along internal roads and this aspect would be considered at planning stage of all type of roads.

2.9 Manpower

The manpower requirement during operations basically depends on the industries proposed to be

located in the park. The estimated total manpower requirement on completion of the project work

during operation of all the industrial units in the park is projected in Table 2.6

Table 2.6 Manpower

Details Total

Direct & Indirect Employment in industries 184539

Direct and Indirect employment Amenities (common services) 3000

Total 187539

2.10 Project Cost

Phasing of mega textile park development is essential in reducing financial uncertainty and boosting

potential investors’ confidence; through the minimization of initial capital outlay and risk, and

facilitation of development at manageable pace. Development will begin from a mini-estate and

gradually expand with changing rates of land occupancy. This will ensure practical expansion

and development with organized location of industries throughout the MTP.

The phasing plan provides a general guide for development of the MTP and shall be adopted with

flexibility depending on the market demand. The proposed Development Phasing needs to be

reviewed periodically in response to market demand; particularly in the development of new

units/sectors in the future. The component like CETP will be taken up on Public Private Partnership

(PPP) mode.

Page 76: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 2.23

Table 2.7 Estimated Project cost for phased development

S.No Project Cost Amount (Rs. in crores)

1 Roads 91.68

2 Storm water drain 27.16

3 Water supply 78.07

4 Sewage system 39.41

5 Electrical Infrastructure 71.83

6 Landscaping 8.00

7 Common Infrastructure 55.80

Total Project Cost 371.95

2.11 Site Development

Ground development is required before commencement of any construction activity at site. This

activity would consist of cutting, removing and disposing of all materials such as bushes, shrubs,

stumps, roots, grass, weeds, top organic soil, rubbish, etc. from the area of work.

Ground development would also include necessary excavation, backfilling of pits resulting from

uprooting of trees and stumps to required compaction, handling, salvaging, and disposal of cleared

materials, etc. All excavations below the general ground level arising out of the removal of trees,

stumps, etc., shall be filled with suitable material and compacted thoroughly so as to make the

surface at these points conform to the surrounding area.

The site shall be accessible by a Gate House structure with entry/exits and a security office.

Page 77: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.1

Chapter – 3

Description of the Baseline Environment 3.1 Introduction

Baseline environmental status in and around the proposed project depicts the existing conditions of

air, water, noise, soil, ecological studies, land utilization and socio-economic environment. The

baseline data was collected for various environmental components to compute the impacts that are

likely to be arising out of the industrial activities covering an area of 10 km radially, from the

proposed Mega Textile Park at Warangal.

3.2 Baseline environmental studies

The main aim of the impact assessment study is to find out the impact of the project on the

environment. This study is carried out during the project planning stage itself, so that the proponent

can implement the project in a technically, financially and environmentally viable way.

The success of any impact assessment study depends mainly on two factors. One is assessment of

the environmental condition and the second one is estimation of impact from proposed project on

the environment. Both are key factors to arrive at the post project scenario. The estimated impact

due to the project can be superimposed over the existing conditions to arrive at the post project

scenario. The scope of the baseline studies includes detailed characterization of following

environmental components which are most likely to be influenced by setting up an industry:

Meteorological conditions Ambient air quality Noise levels Water quality (surface + ground)

Soil quality Ecological studies Socio economic studies Land utilization

3.2.1 Monitoring period

Meteorological data was collected for the study area during the months of winter season (December

2016 to February 2017). Wind speed, wind direction, temperature, and relative humidity were

recorded on hourly basis during the study period. Secondary meteorological data has been collected

from the nearest IMD station of Hanamkonda.

3.3 Meteorology

Regional meteorological scenario helps to understand the trends of the climatic factors. It also helps

in determining the sampling stations in predicting the post project environmental scenario.

Meteorological scenario exerts a critical influence on air quality as the pollution arises from the

interaction of atmospheric contaminants with adverse meteorological conditions such as

temperature inversions. Atmospheric stability and topographical features like hills, canyons and

valleys.

Page 78: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.2

The climate in the project area is generally dry, humid and hot. During the winter season, the

predominant wind direction recorded was south to north closely follow by South East. The calm

percentage recorded is 12.5% and the average wind speed for the season i.e. winter season is 2.41

m/s. The maximum temperature recorded is 12.8°C and minimum is 36.2°C with a maximum

humidity level of 88%.

The study of meteorological conditions forms an intrinsic part of the environment impact

assessment study. The meteorological conditions of an area have a definite influence over the other.

Summary of the climatological data (Station at Hanamkonda) is taken from India Meteorological

Department (IMD), Climatological data (from 1981 to 2010) given in Table 3.1. An average

temperature and rainfall details of Warangal from 2010-2016 are shown in Figure 3.1 and 3.2.

Table 3.1 Meteorological Data – Statistics

IMD Station Hanamkonda

Lat:17 58 8 & Lon:79 35 39 MSL 270m, Distance from proposed site 11 Km NW.

Month Temperature °C Humidity % Rainfall Mean

Wind

speed

(m/s)

Pre-

dominant

direction Mean

Max

Mean

Min

High

est

Lowe

st Max Min

Monthl

y mm

No of

rainy

days 1st

Jan 30.0 17.2 32.8 12.6 74 59 10.2 0.5 1.7 S

Feb 32.7 19.5 35.3 15.4 70 55 7.5 0.5 2.0 S

Mar 36.3 22.5 39.3 29.1 70 52 11.4 0.9 2.1 S

Apr 39.4 25.3 42.5 22.0 67 48 9.9 0.7 2.2 SE

May 41.2 27.4 44.4 23.1 61 44 22.1 1.5 2.4 SE

Jun 36.5 26.4 42.5 22.8 70 59 105.2 6.0 2.6 S

Jul 32.5 24.8 36.8 22.5 78 71 217.1 10.6 2.1 NW

Aug 31.0 24.4 34.0 22.2 80 75 154.9 7.9 2.2 NW

Sep 32.4 24.5 35.1 22.1 79 74 116.3 6.0 1.7 NW

Oct 32.4 22.8 34.7 19.1 76 69 65.2 3.8 1.4 S

Nov 31.0 19.3 33.5 15.1 73 67 19.0 1.1 1.4 N

Dec 29.8 16.2 31.7 12.9 72 62 6.1 0.3 1.3 S

Source: GOI, Ministry of Earth Sciences, IMD, Climatological Table 1981-2010

Page 79: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.3

Figure 3.1 Average temperature graphs (2010-2016)

Source: Worldweatheronline weather API (application programming interface)

Figure 3.2 Average rainfall graphs (2010-2016)

Source: Worldweatheronline weather API (application programming interface)

3.3.1 Climatic Conditions

The climate in the study region is generally dry, humid and hot and is characterized with seasonal

variations as follows:

Summer March to May Post monsoon September to November

Monsoon June to August Winter December to February

Page 80: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.4

Project area falls under the hot temperate climate zone and hence it experiences very hot and dry

climate. Summer season start from March stays till May. Rainy season due to the monsoon starts

from June to August and Post monsoon is from September to November. The critical weather

elements that influence air pollution are wind speed, wind direction, temperature, which together

determines atmosphere stability. Hence it is an indispensable part of any air pollution studies and

required for interpretation of baseline information. The details of the temperature, relative humidity

and rainfall observed during study period as micro meteorological data is given in Table 3.2.

Table 3.2 Micro Meteorological Data

Period

Temperature

(oC) R. Humidity (%) Rainfall

(mm) Predominant wind

direction blowing from Min Max Min Max

December - 2016 13.4 31.3 56 82 2.8

South to North January - 2017 12.8 32.1 59 88 0

February - 2017 15.1 36.2 52 84 0

3.3.2 Wind Pattern during study period (winter season)

Dispersion of different air pollutants released into the atmosphere has significant impacts on

neighborhood air environment. The dispersion/dilution of the released pollutant over a large area

will result in considerable reduction of the concentration of a pollutant. The dispersion in turn

depends on the weather conditions like the wind speed, direction, temperature, relative humidity,

mixing height, cloud cover and also the rainfall in the area. Normally the impacts surrounding the

project site are studied in detail.

Site-specific meteorological data was generated during the study period winter season, 2016-17

(December 2016 to February 2017). Automatic weather station was installed at Shayampet village

(near project site) to record the meteorological parameters during the study period. Meteorological

parameters recorded include temperature, wind speed, wind direction, relative humidity and rainfall

to understand the prevailing surface and upper air conditions for Air Quality modelling. The

parameters like wind speed, wind direction, relative humidity, station pressure, cloud cover, ceiling

height, precipitation and temperature, etc. have been considered as a meteorological input to the

model.

Wind speed and direction data recorded during the study period is useful in identifying the influence

of meteorology on the air quality of the area. Based on the IMD meteorological data, wind roses that

is the diagrammatic representation of wind speed and wind direction along with their persistence

for a fractional period of occurrence at a given location is constructed. Wind roses on sixteen sector

basis have been drawn. Wind directions and wind speed frequency observed during study period for

winter season is given in Table 3.3 wind rose diagram is given in Figure 3.3.

Page 81: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.5

Table 3.3 Frequency distribution Table – winter season (December-2016 to February-2017)

Wind Directions Wind Classes (m/s) Total (%)

0.5-2.0 2.0-3.5 3.5- 5.0 > 5.0

N 3.47 1.62 0.97 0.60 6.67

NNE 1.85 1.81 0.65 0.93 5.23

NE 1.76 2.13 0.83 0.42 5.14

ENE 1.16 1.34 0.74 0.42 3.66

E 1.48 1.30 0.56 0.46 3.80

ESE 1.34 1.39 0.97 0.46 4.17

SE 4.31 1.99 1.76 2.45 10.51

SSE 3.19 1.25 1.62 1.76 7.82

S 7.96 3.33 2.31 2.78 16.39

SSW 1.44 0.28 0.60 0.46 2.78

SW 1.62 1.20 0.56 0.69 4.07

WSW 2.13 1.06 0.65 0.46 4.31

W 1.20 0.74 0.60 0.65 3.19

WNW 1.48 0.51 0.51 0.46 2.96

NW 1.02 1.02 0.51 0.37 2.92

NNW 1.90 0.83 0.32 0.83 3.89

Sub-Total 37.31 21.81 14.17 14.21 87.50

Calms (< 0.5 m/s) 12.50

Total 100

Note: 1.Average wind speed – 2.41 m/s

2.All Values are in percentage

Figure 3.3 Wind rose diagram for the winter season (December-2016 to February-2017)

Page 82: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.6

3.4 Sampling Locations

In order to identify the baseline quality of Air, Noise, Water (Surface and Groundwater) and Soil in

surroundings of the project area, sampling locations are identified.

3.4.1 Basis for Selection of the Monitoring Locations

The selection criteria for monitoring locations are based on the following:

- Topography/Terrain

- Meteorological conditions

- Residential and sensitive areas within the study area

- Representatives of regional background air quality/pollution levels and

- Representation of likely impacted areas.

3.5 Ambient air quality monitoring stations

To evaluate the baseline air quality of the study area, Ten (10) monitoring locations have been

identified as per MoEF&CC guidelines. A map showing the monitoring locations and the details of

the locations are given below.

3.5.1 Ambient Air Quality monitoring Techniques and frequency

Ambient air quality was monitored twice in a week for One (01) season (shall cover 12 weeks), i.e.

during winter season (December, 2016 – February, 2017). PM10, PM2.5, SO2 and NOx were

monitored on 24 hourly bases. O3 and CO were monitored on 8 hr basis. Sampling was carried out as

per Central Pollution Control Board (CPCB) monitoring guidelines at each location. The air quality

locations and details are given in Table 3.4 and the sampling locations selected for studying the

environmental quality of the study area are shown in the Figure 3.4.

Table 3.4 Details of AAQ monitoring locations

Station Code

Location Distance (Km) from

site boundary Azimuth Direction Environmental Setting

AAQ1 Shayampet 1.5 N

Residential AAQ2 Chintalapalli 2.2 E

AAQ3 Katrapalli 2.6 SW

AAQ4 Sangem 3.2 SE Residential/Commercial

AAQ5 Venkatapuram 3.4 W

Residential

AAQ6 Kanaparti 5.4 W

AAQ7 Gavicherla 5.8 S

AAQ8 Geesugonda 6.5 N

AAQ9 Dharmaram 6.7 NW

AAQ10 Mondrai 6.8 E

Page 83: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.7

Figure 3.4 Ambient Air Quality Monitoring Locations

Page 84: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.8

3.5.2 Air quality scenario in the study area

The existing concentration levels of air pollutants of concern, as mentioned above, are presented in

Table 3.5. Statistical parameters like minimum, maximum and 98th percentiles have been computed

from the observed raw data for all sampling locations. The observed values were compared with the

standards as prescribed by Central Pollution Control Board (CPCB) for Industrial, Residential and

Rural zone.

Table 3.5 PM10, 2.5, SO2, NOx, O3 & CO levels in the study area (µg/m3)

Code Location PM10 PM2.5

Min Max 98th

%tile Min Max 98th

%tile

AAQ1 Shayampet 44.5 49.6 49.6 20.3 29.3 28.1

AAQ2 Chintalapalli 42.4 48.6 48.6 21.7 28.8 28.8

AAQ3 Katrapalli 43.9 50.8 50.7 20.7 27.6 27.4

AAQ4 Sangem 45.8 52.1 51.7 21.7 30.8 29.2

AAQ5 Venkatapuram 43.7 46.9 46.9 22.5 28.9 28.9

AAQ6 Kanaparti 41.3 45.6 45.6 19.7 27.1 27.0

AAQ7 Gavicherla 45.8 51.7 51.7 22.6 29.7 29.7

AAQ8 Geesugonda 48.5 53.1 52.9 25.6 32.1 32.1

AAQ9 Dharmaram 43.6 48.9 48.8 21.5 31.3 30.4

AAQ10 Mondrai 47.4 50.8 50.7 22.9 29.2 28.5

98th

Percentile range 45.6 to 52.9 27.0 to 32.1

NAAQ Standards 2009 100 (24 hr) 60 (24 hr)

60 (Annual) 40 (Annual)

Code Location SO2 NOx

Min Max 98th

%tile Min Max 98th

%tile

AAQ1 Shayampet 7.3 9.9 9.8 14.8 17.7 17.7

AAQ2 Chintalapalli 8.7 10.9 10.9 15.1 18.7 18.6

AAQ3 Katrapalli 7.5 9.2 9.1 16.8 19.4 19.4

AAQ4 Sangem 8.5 12.1 11.9 17.4 20.5 20.3

AAQ5 Venkatapuram 8.2 11.8 11.8 16.1 18.3 18.3

AAQ6 Kanaparti 6.6 8.4 8.4 14.2 16.8 16.8

AAQ7 Gavicherla 7.8 11.5 11.4 17.1 19.7 19.4

AAQ8 Geesugonda 10.1 12.2 12.0 18.1 21.0 20.8

AAQ9 Dharmaram 8.2 10.9 10.9 17.6 19.8 19.8

AAQ10 Mondrai 9.8 11.9 11.9 17.3 20.1 20.0

98th

Percentile range 8.4 to 12.0 16.8 to 20.8

NAAQ Standards 2009 80 (24 hr) 80 (24 hr)

50 (Annual) 40 (Annual)

Code Location O3 CO

Min Max 98th

%tile Min Max 98th

%tile

AAQ1 Shayampet 11.6 14.8 14.6 320 360 354

AAQ2 Chintalapalli 13.8 17.1 17.1 445 550 549

AAQ3 Katrapalli 12.9 16.0 15.9 330 410 406

AAQ4 Sangem 14.3 17.8 17.8 450 560 551

AAQ5 Venkatapuram 12.6 17.5 17.3 310 420 413

AAQ6 Kanaparti 10.1 14.1 14.1 310 350 349

AAQ7 Gavicherla 13.1 17.1 17.0 450 520 514

AAQ8 Geesugonda 16.6 19.8 19.8 480 580 564

AAQ9 Dharmaram 14.9 18.2 18.2 410 460 459

AAQ10 Mondrai 14.1 17.3 17.2 420 480 474

98th

Percentile range 14.1 to 19.8 349 to 564

NAAQ Standards 2009 100 (8 hr) 2000 (8 hr)

Page 85: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.9

3.5.3 Results and discussions

The maximum, minimum and mean values of PM10, PM2.5, SO2, NOx, O3 & CO are given in above

table and the variations of results were compared with National Ambient Air Quality Standards

(NAAQ), MoEF Notification in November-2009. Maximum concentrations of PM10, PM2.5, SO2 and

NOx are well within the ambient air quality standards for Commercial and residential areas at all

monitoring locations during the study period.

Maximum value for PM10 was observed as 53.1 µg/m3 at Geesugonda (AAQ 8) and minimum

value is 41.3 µg/m3 at Kanaparti (AAQ6). NAAQ stipulated standard for PM10 for 24 hr

average is 100 µg/m3.

Maximum value for PM2.5 was observed as 32.1 µg/m3 at Geesugonda (AAQ 8) and

minimum value is 19.7 µg/m3 at Kanaparti (AAQ6). NAAQ stipulated standard for PM2.5 for

24 hr average is 60 µg/m3.

Maximum value for SO2 was observed as 12.2 µg/m3 at Geesugonda (AAQ 8) and minimum

value is 6.6 µg/m3 at Kanaparti (AAQ6). NAAQ stipulated standard for SO2 for 24 hr average

is 80 µg/m3.

Maximum value for NOx was observed as 21.0 µg/m3 at Geesugonda (AAQ 8) and minimum

value is 14.2 µg/m3 at Kanaparti (AAQ6). NAAQ stipulated standard for NOx for 24 hr average

is 80 µg/m3.

Maximum value for O3 was observed as 19.8 µg/m3 at Geesugonda (AAQ 8) and minimum

value is 10.1 µg/m3 at Kanaparti (AAQ6). NAAQ stipulated standard for O3 for 8 hr average is

100 µg/m3.

Maximum value for CO was observed as 580 µg/m3 at Geesugonda (AAQ 8) and minimum

value is 310 µg/m3 at Kanaparti (AAQ6) & Venkatapuram (AAQ5). NAAQ stipulated standard

for CO for 8 hr average is 2000 µg/m3.

3.6 Ambient noise levels

Ambient noise levels have been established by monitoring noise levels at Ten (10) locations. The

noise monitoring locations in the study area was selected after giving due consideration to the

various land use categories. The land use categories include commercial, residential and rural areas.

Noise levels were recorded on an hourly basis for one complete day at each location using pre-

calibrated noise levels. A map is showing the monitoring locations and the details of the same are

given in Table 3.6.

Page 86: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.10

Table 3.6 Details of Noise Monitoring Locations in the study area

Location Code

Location Name

Distance (Km) from site boundary

Azimuth Direction Environmental Setting

N1 Shayampet 1.5 N

Residential N2 Chintalapalli 2.2 E

N3 Katrapalli 2.6 SW

N4 Sangem 3.2 SE Residential/Commercial

N5 Venkatapuram 3.4 W

Residential

N6 Kanaparti 5.4 W

N7 Gavicherla 5.8 S

N8 Geesugonda 6.5 N

N9 Dharmaram 6.7 NW

N10 Mondrai 6.8 E

3.6.1 Noise Levels in the Study Area

Based on the recorded hourly noise levels at each monitoring location, the day equivalent (Ld) and

night equivalent (Ln) were calculated.

Ld: Average noise levels between 6:00 am hours to 10:00 pm hours

Ln: Average noise levels between 10:00 pm hours to 6:00 am hours

The Day-Night (Ldn) equivalent noise levels were calculated using the US Environmental Protection

Agency Formula.

Ldn = 10 Log [0.0416 {16(10Ld/10) + 8 (10Ln+10/10)}]

The comparison of day equivalent (Ld) and night equivalent noise levels (Ln) with the respective CPCB

stipulated noise standards for various categories and results are shown Table 3.7 and monitoring

locations map is shown in Figure 3. 5.

Table 3.7 Day and Night Equivalent Noise Levels

Code Location Name Lday (Ld) CPCB Standards LNight (Ln) CPCB Standards

N1 Shayampet 52.7

55

41.3

45

N2 Chintalapalli 51.8 40.9

N3 Katrapalli 53.5 42.7

N4 Sangem 52.9 42.8

N5 Venkatapuram 52.8 42.6

N6 Kanaparti 52.9 42.5

N7 Gavicherla 52.6 42.2

N8 Geesugonda 53.9 43.1

N9 Dharmaram 52.9 41.8

N10 Mondrai 53.7 42.5

Page 87: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.11

Figure 3.5 Noise level monitoring locations

Page 88: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.12

3.6.2 Results and discussions

It is observed that the day equivalent and night equivalent noise levels at all locations are within

prescribed CPCB standards.

Day equivalent noise levels (Ld) ranged between 51.8 to 53.9 dB (A) and Night equivalent

noise levels (Ln) ranged between 40.9 to 43.1 dB (A) for residential areas.

Sangem is the only residential cum commercial location where the Day equivalent noise

levels (Ld) is 52.9 dB (A) and Night equivalent noise levels (Ln) is 42.8 dB (A).

3.7 Water Environment

Surface and groundwater samples were collected from different sources within the study area and some important physical and chemical parameters including heavy metals were considered for depicting the baseline status of the study area.

3.7.1 Water quality assessment

Selected water quality parameters for water resources of the study area have been used for

describing the water environment and assessing the quality of it. To assess the water quality, water

resources in the area have been grouped into 2 classes.

a. Ground water resources in the deeper strata of the ground b. Surface water resources

About 10 no. of ground water and 07 no. of surface water samples were collected from the study

area to assess the water quality during the study period. The ground water samples were drawn

from the hand pumps and tube wells/ bore wells being used by the villagers for their domestic needs

not drinking purpose.

Surface water sampling was carried out from major tanks/ponds/lakes within 10 km of the proposed

project site. The details of the locations are given in Table 3.8, results are given in Table 3.9, 3.10

and monitoring locations map is shown in Figure 3.6 & 3.7.

Page 89: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.13

Table 3.8 Water sampling locations

Code Location W.R.T site

Source Environmental settings Direction

Distance (Km)

Ground Water

GW1 Project Site -- -- Hand pump Drinking Purpose

GW2 Shayampet N 1.5 Well water Drinking Purpose

GW3 Chintalapalli E 2.2 Bore well Drinking water and Irrigation purpose

GW4 Katrapalli SW 2.6 Bore well Drinking Purpose

GW5 Sangem SE 3.2 Hand pump Inside the ST Hostel, drinking water

GW6 Venkatapuram W 3.4 Hand pump Not drinking water

GW7 Kanaparti W 5.4 Bore water Near school, drinking water

GW8 Gavicherla S 5.8 Hand pump Near village entrance drinking water

GW9 Geesugonda N 6.5 Hand pump Near Junction, drinking water

GW10 Dharmaram NW 6.7 Bore water Near water plant using for RO plant

GW11 Mondrai E 6.8 Hand pump Drinking water

Surface Water

SW1 Shayampet Lake N 1.6 Lake Using for Agriculture purpose

SW2 Venkatapuram Lake W 4.0 Lake Using for Agriculture purpose

SW3 Katrapalli Lake W 3.5 Lake Using for Agriculture purpose

SW4 SRSP Canal N 1.4 Lake Using for Agriculture purpose

SW5 Yelgur Lake SE 5.7 Lake Using for Agriculture purpose

SW6 Sangem Lake SE 4.0 Lake Using for Agriculture purpose

SW7 Gavicherla Lake S 5.5 Lake Using for Agriculture purpose

Page 90: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.14

Figure 3.6 Ground water sampling locations

Page 91: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.15

Figure 3.7 Surface water sampling locations

Page 92: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.16

Table 3.9 Groundwater sample analysis results

Sl. No

Parameter Unit

Analysis Results Standard as per IS -

10500:2012

GW-1 GW-2 GW-3 GW-4 GW-5 GW-6 GW-7 GW-8 GW-9 GW-10 GW-11 Acceptable Limit

Permissible Limit

1 Odour -- Agreeable Agreeable

2 pH Value -- 7.3 7.8 7.2 7.1 7.2 7.2 7.4 7.3 7.2 7.2 7.4 6.5-8.5 No Relaxation

3 Turbidity NTU 1.2 1.5 1.1 1.3 1.1 1.3 1.2 1.2 1.5 1.2 0.6 1 5

4 Electrical Conductivity µs/cm 1280 495 678 2254 2605 2562 810 931 1332 1132 613 -- --

5 Dissolved Solids mg/l 836 335 452 1423 1684 1644 526 604 890 740 416 500 2000

6 Alkalinity mg/l 285 98 180 403 423 445 208 246 297 261 166 200 600

7 Chloride (as Cl ) mg/l 122 58 70 302 345 352 77 86 142 127 62 250 1000

8 Sulphate (as SO4) mg/l 78 36 32 172 185 195 46 52 86 73 27 200 400

9 Nitrate (as NO3) mg/l 20.4 5.2 6.5 35.4 42.2 40.3 9.2 10.9 21.7 7.4 6.3 45 No Relaxation

10 Total Hardness (as CaCO3) mg/l 434 179 257 598 595 616 293 336 495 405 230 200 600

11 Calcium (as Ca ) mg/l 98 42 60 134 138 143 68 82 116 93 56 75 200

12 Magnesium (as Mg) mg/l 46 18 26 63 60 62 30 32 50 42 22 30 100

13 Sodium as Na mg/l 75 25 34 188 256 254 46 52 71 62 30 -- --

14 Potassium as K mg/l 8.6 5.6 5.8 14.8 22.3 16.6 7.1 7.2 9.2 7.2 5.5 -- --

15 Fluoride (as F) mg/l 0.52 0.50 0.51 0.54 0.56 0.57 <0.5 <0.5 0.53 0.51 <0.5 1.0 1.5

16 Iron (as Fe) mg/l 0.24 0.21 0.22 0.28 0.38 0.36 0.25 0.26 0.23 0.22 0.21 0.3

No Relaxation

17 Lead (as Pb) mg/l <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.01

18 Mercury (as Hg) mg/l <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 0.001

19 Cadmium (as Cd) mg/l <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 0.003

20 Chromium (as Cr) mg/l <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.05

21 Cyanide as CN mg/l <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.05

22 Copper (as Cu) mg/l <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.05 1.5

23 Arsenic as As mg/l <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.01 0.05

24 Boron as B mg/l <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 0.5 1.0

25 Zinc (as Zn) mg/l <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 5 15

Page 93: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.17

Table 3.10 Surface water sample analysis results

Parameter Units SW1 SW2 SW3 SW4 SW5 SW6 SW7 IS 2296 – 1992 Inland surface water standards

A B C D E

pH --- 6.7 7.1 7.0 7.1 7.7 7.6 7.6 6.5-8.5 6.5-8.5 6.0-9.0 6.5- 8.5 6.5- 8.5

EC µs/cm 314 292 379 488 262 385 290 - - - - 2250

Color Hazen 1.8 1.2 1.4 1.7 1.1 1.3 1.4 10 300 300 - -

Odor -- Unobjectionable Un-obj. - - - -

TDS mg/l 206 192 254 335 174 262 196 500 - 1500 - 2100

TSS mg/l <10 <10 <10 <10 <10 <10 <10 - - - - -

Turbidity NTU 1.2 1.0 1.1 1.3 1.1 1.3 1.3 - - - - -

Alkalinity as CaCO3 mg/l 74 70 82 102 62 85 69

Chloride as Cl- mg/l 32 30 42 56 26 42 30 250 - 600 - 600

Sulphate as SO4-2 mg/l 18 16 26 38 17 26 15 400 - 400 - 1000

Nitrates as NO3 mg/l 4.7 3.8 5.2 5.6 2.8 5.3 3.6 20 - 50 - -

Total Hardness mg/l 123 113 151 191 105 155 112 200 - - - -

Calcium as Ca mg/l 28 26 34 42 24 34 25 - - - - -

Magnesium as Mg mg/l 13 12 16 21 11 17 12 - - - - -

Sodium as Na mg/l 14 13 16 21 11 16 13 - - - - -

Potassium as K mg/l 5.2 5.0 5.5 5.2 5.9 5.6 5.9 - - - - -

Fluoride as F- mg/l <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 1.5 1.5 1.5 - -

Iron as Fe mg/l 0.21 0.22 0.31 0.35 0.25 0.30 0.28 0.3 - 0.5 - -

Lead as Pb mg/l <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.1 - 0.1 - _

Mercury as Hg mg/l <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 0.001 - _ _ _

Arsenic as As mg/l <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.05 0.2 0.2 - _

Cadmium as Cd mg/l <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 0.01 - 0.01 - _

Cyanide as CN mg/l <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.05 - 0.05 - _

Zinc as Zn mg/l < 1 < 1 < 1 < 1 < 1 < 1 < 1 15 - 15 - _

Copper as Cu mg/l <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 1.5 - 1.5 - _

Boron as B mg/l <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 - - - - 2

Phenolic compounds mg/l <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 0.002 0.005 0.005 - -

Cyanide as CN mg/l <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.05 0.05 0.05

DO mg/l 4.8 5.1 4.7 5.2 4.9 4.8 4.8 6 5 4 4 -

COD mg/l 16 12 18 12 15 17 17 - - - - -

BOD mg/l 4 3 4 3 4 4 4 2 3 3 - -

A - Drinking water without conventional treatment but after disinfection B - Outdoor bathing (organized)

C - Drinking water source with conventional treatment followed by disinfection D - Propagation of wild life, fisheries

E - Irrigation, industrial, cooling, controlled waste disposal

Page 94: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.18

3.7.2 Results and discussion on Ground water quality

pH ranged between 7.1 at Katrapalli (GW4) and 7.8 at Shayampet (GW2) all values are under acceptable limits.

Electrical conductivity (EC) varied between 495 µs/cm at Shayampet (GW2) and 2605 µs/cm at Sangem (GW5).

Total dissolved solids ranged between 335 mg/l at Shayampet (GW2) and 1684mg/l at Sangem (GW5). Major samples were above Acceptable limits and all are within the permissible limits.

Alkalinity ranged between 98 mg/l at Shayampet (GW2) and 445 mg/l at Venkatapuram (GW6). Only three samples are within the Acceptable limit and remaining was within the permissible limits.

Total Hardness ranged between 179 mg/l at Shayampet (GW2) and 616 mg/l at Venkatapuram (GW6). Only one sample is within the acceptable limit and remaining all was within the permissible limits.

Chlorides ranged between 58mg/l at Shayampet (GW2) and 352 mg/l at Venkatapuram (GW6). Only three samples were above the acceptable limits.

Sulphates ranged between 32 mg/l at Chintalapalli (GW3) and 195 mg/l at Venkatapuram (GW6). All samples were within the acceptable limits

Nitrates ranged between 5.2 mg/l at Shayampet (GW2) and 42.2 mg/l at Sangem (GW5). All the samples were within the acceptable limits.

Calcium ranged between 42 mg/l at Shayampet (GW2) and143 mg/l at Venkatapuram (GW6). Half of the samples were within the acceptable limits and half of the samples were within the permissible limits.

Magnesium ranged between 18mg/l at Shayampet (GW2) and 63 mg/l at Katrapalli (GW4).

Fluoride is within the acceptable limit at all the locations.

Heavy metals like Lead, Mercury, Cadmium, Chromium, Cyanide, Copper, Arsenic, Boron and Zinc were within the acceptable limit.

3.7.3 Results and discussion on Surface water quality

Surface waters are slightly alkaline in nature, pH ranged between 6.7 at Shayampet Lake

(SW1) and 7.7 at Yelgur Lake (SW5).

Total dissolved solids ranged between 174 mg/l at Yelgur Lake (SW5) and 335 mg/l at SRSP

canal (SW4).

Page 95: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.19

Biological Oxygen Demand (BOD) ranged between 3 mg/l at SW2 & SW4 to 4 mg/l at all

remaining locations.

Chemical Oxygen demand (COD) ranged between 12 mg/l at SW4 to 18 mg/l at SW3 & SW7.

DO range between 4.7 mg/l at SW3 to 5.2 mg/l at SW4.

Total Hardness ranged between 105 mg/l at SW5 and 191 mg/l at SW4.

Chlorides ranged between 26 mg/l at SW5 and 56 mg/l at SW4.

Calcium ranged between 24 mg/l at SW7 and 42 mg/l at SW4.

Magnesium ranged between 11 mg/l at SW4 and 21 mg/l at SW5.

Heavy metals like Lead, Mercury, Cadmium, Arsenic Cyanide, Copper, Arsenic, Boron and

Zinc were within the limits specified of class A, Drinking water without conventional

treatment but after disinfection as per Guidelines for Water Quality Management – CPCB

2008.

3.8 Soil

The topography of the district consists of isolated hills, rain fed tanks, lakes and shrubby forests. The

major soil types found in the district are red chalka (55%), black cotton soil (22%), loamy soil (14%,

and sandy loams (9%).

3.8.1 Soil quality

The present study on soil quality establishes the baseline characteristics in the study area surrounding the project site. The study has been addressed with the following objectives.

- To determine the base line characteristics

- To determine the soil characteristics of proposed project site

- To determine the impact of industrialization/urbanization on soil characteristics

- To determine the impacts on soils from agricultural productivity point of view

3.8.2 Criteria adopted for selection of sampling locations: For studying the soil types and soil characteristics, 10 no. of sampling locations were selected to

assess the existing soil conditions representing various land use conditions and geological features.

3.8.3 Methodology and sampling

The homogenized soil samples collected at different locations were packed in a polyethylene plastic

bag and sealed. The sealed samples were sent to laboratory for analysis. The important physical,

chemical parameter concentrations were determined from all samples. Details of the soil sampling

locations are given below.

Page 96: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.20

Table 3.11 Soil sampling locations

Code Location Name W.R.T site Source &

Environmental Settings Direction Distance

S1 Project Site -- -- Agriculture Land

S2 Shayampet N 1.5 Barren land

S3 Chintalapalli E 2.2 Agriculture Land

S4 Katrapalli SW 2.6 Agriculture Land

S5 Sangem SE 3.2 Barren land

S6 Venkatapuram W 3.4 Agriculture Land

S7 Kanaparti W 5.4 Agriculture Land

S8 Gavicherla S 5.8 Agriculture land

S9 Geesugonda N 6.5 Agriculture land

S10 Dharmaram NW 6.7 Agriculture land

S11 Mondrai E 6.8 Agriculture land

Page 97: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.21

Figure 3.8 Soil monitoring locations

Page 98: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.22

Table 3.12 Soil analysis results

Parameter Unit S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 Standard Soil Classification – ICAR, New Delhi

Texture - Sandy loam

Color - Grey Brown Black Grey Brown Grey Brown Grey

pH ( 1:5 extract) - 8.9 8.3 7.0 8.2 8.1 7.4 6.6 8.5 8.4 7.7 6.8

Acidic <6.0

Normal to saline 6.0 – 8.5

Tending to become alkaline 8.6-9.0

Alkaline > 9.0

EC ( 1:5 extract) µs/cm 199 174 164 142 159 163 122 187 145 178 108

Normal <1000

Critical for germination 1000 – 2000

Critical for growth 2000- 4000

Injurious to most crops > 4000

Bulk Density g/cc 0.89 0.87 1.20 1.48 1.27 1.35 1.13 1.20 1.01 1.30 1.13

Moisture content % 5.7 6.8 7.3 6.4 6.1 5.9 6.3 7.2 5.7 6.3 8.1

Total organic Carbon % 1.28 1.27 1.97 1.73 2.07 2.07 1.81 1.73 1.12 1.65 1.16 Low <0.5%, Medium 0.5-0.75%, High >0.75%

SAR - 15.0 12.9 13.6 3.0 20.7 33.6 28.2 27.9 35.8 30.5 53.5 -

Calcium as Ca mg/Kg 6964 6733 2770 5078 6925 4040 4852 5617 6117 9619 2924

Magnesium as Mg mg/Kg 3696 2446 692 3025 3682 2050 2539 2787 3668 3937 1528

Available Nitrogen as N Kg/Ha 251 175 152 188 231 161 148 206 175 206 193 Low below 280; Medium 280 to 560; High above 560

Available Phosphorus as P Kg/Ha 9.4 8.1 6.9 7.2 9.6 11.4 8.5 9.2 7.8 7.4 9.4 Low below 10; Medium 10 to 25; High above 25

Available Potassium as K Kg/Ha 309 287 264 289 323 298 289 345 282 367 372 Low below 110; Medium 110 to 280; High above 280

Chloride as Cl mg/Kg 306 95 124 114 124 134 105 114 115 134 105 -

Lead as Pb mg/Kg 2.4 2.9 3.2 2.6 3.1 2.2 3.5 2.9 2.1 3.0 2.6 -

Copper as Cu mg/Kg 5.7 9.3 5.4 6.2 4.6 4.7 5.3 4.1 3.9 4.8 5.5 -

Zinc as Zn mg/Kg 27.4 32.5 29.3 34.2 26.1 34.2 27.3 35.3 28.9 25.6 35.5 -

Boron as B mg/Kg <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 -

Page 99: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.23

3.8.4 Results and discussions

The soil analysis results are presented in Table 3.12. The result obtained is compared with the

standard soil classification given Agriculture Soil Limits. It has been observed that the soils are sandy

clay in texture and neutral in nature. The nutrient and organic matter contents are medium and the

soil is normally fertile.

3.9 Traffic Study

Anthropogenic emissions not only contribute to the greenhouse effect but also participate in the

reaction that results in photochemical oxidants. The effect of photochemical oxidants is well known

for forming smog particularly in the urban areas.

Among the anthropogenic sources of pollutants forming the greenhouse gases, burning of fossil fuels

constitute a major source. Highway mobile sources that contribute significantly to poor quality have

been regulated for the past two decades in countries like India. The absence of regulation in

developing countries has caused a global concern regarding potential environmental damage on a

larger scale.

In countries like India automobiles especially two-wheelers are a very popular mode of personal

transport for socio-economic reasons. They constitute to about 70-95% of the total passenger’s

vehicles. About the same percentage of two-wheeler vehicles are powered by two-stroke engines

because of low initial and maintenance costs. However these two stroke engines have high emission

levels which are of the major concern. Moreover, these emissions are concentrated in urban area,

further contributing to already polluted “heat islands”. Poor public transportation and high

transportation fares, increasing cost of living and greater demand for mobility may be attributed to a

surge in the number of personal vehicles during the last decade.

The objective of traffic study and emission quantification is to assess the magnitude of the emissions

resulting from two-wheelers, three wheelers, and four wheelers that are extensively used as a

means of common transport within the urban areas.

A detailed traffic survey was conducted in the study area and also to evaluate the impacts of the

increased traffic due to the proposed activity.

Vehicular emissions are the major source of air quality impacts in the study area. The principal cause

of air pollution during the construction phase is the diesel-powered vehicles used in haulage of

aggregates, earth and other construction material. Air quality could be affected by dust & particulate

matter arising due to site clearing, vehicular emissions etc. Gaseous emissions like SO2, NOx, and CO

might be released from the vehicular movement, which has a direct impact on the environment.

Increase in the traffic in the study area has a direct impact on the resources as a heavy release of

automobile exhaust is envisaged which has a direct impact on the air quality and the ambient noise

levels in the study area.

3.9.1 Details of traffic study

The methodology adopted for carrying out the traffic study was to select the major roads around the

project site and count the various categories of vehicles moving on these roads. The traffic survey

Page 100: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.24

was carried out at 3 locations. 1. On Warangal – Narsampet road (2lane 2way) road, 2. On site

approach road at Ookal junction (2lane 2way), 3. On site approach road at Vanchanagiri junction (2

lane 2 way) via Shayampet which were connecting to project site.

Vehicular movement observed & recorded on the roads as below:

i. On Warangal – Narsampet road -1199 PCU/hr. (in peak hour of 10 to 11 am).

ii. On site approach road at Ookal Junction (Warangal – Narsampet road to site via

Mariyapuram/ Chintalapalli) - 348 PCU/hr (in peak hour of 9 to 10 am)

iii. On site approach road at Vanchanagiri junction (Warangal – Narsampet road to site via

Shayampet) -262 PCU/hr (in peak hour of 9 to 10 am).

The details of traffic study on above mentioned locations are given in Table 3.13, Table 3.14 & Table

3.15 respectively.

Table 3.13 Traffic survey on Warangal -Narsampet road (To & Fro)

Hours

Two wheeler Three wheeler Passenger cars & pick-up vans

Heavy commercial

vehicles (HCV) Total vehicles

v/hr PCU/hr (0.75)

v/hr PCU/hr

(2) v/hr

PCU/hr (1)

v/hr PCU/hr

(3.7) Total

Total PCU/hr

06:00-07:00 132 99 87 174 56 56 45 167 320 496

07:00-08:00 186 140 115 230 87 87 92 340 480 797

08:00-09:00 265 199 123 32 96 96 112 414 596 741

09:00-10:00 387 290 162 324 113 113 119 440 781 1168

10:00-11:00 416 312 164 328 115 115 120 444 815 1199

11:00-12:00 412 309 154 308 117 117 118 437 801 1171

12:00-13:00 404 303 158 316 113 113 108 400 783 1132

13:00-14:00 397 298 156 312 102 102 97 359 752 1071

14:00-15:00 365 274 143 286 98 98 87 322 693 980

15:00-16:00 387 290 132 264 112 112 115 426 746 1092

16:00-17:00 412 309 123 246 128 128 103 381 766 1064

17:00-18:00 386 290 149 298 135 135 109 403 779 1126

18:00-19:00 403 302 136 272 105 105 121 448 765 1127

19:00-20:00 354 266 116 232 94 94 106 392 670 984

20:00-21:00 243 182 103 206 86 86 97 359 529 833

21:00-22:00 123 92 87 174 63 63 86 318 359 647

22:00-23:00 98 74 65 130 51 51 75 278 289 532

The highest peak observed is 1199 PCU/hr. during 10 am to 11 am.

Total width of the road in meters (arterial road with no frontage access, no standing vehicle little cross traffic

07

Carrying capacity of the road (the road is 2 lane 2 way road) As per IRC: 106-1990 (PCU’s per hr)

1500

Existing V/C ratio 0.8

LOS = Level of Service (Existing) “D”

V/C LOS Performance V/C

0.0 – 0.2 A Excellent 0.0 – 0.2

0.2 – 0.4 B Very Good 0.2 – 0.4

0.4 – 0.6 C Good 0.4 – 0.6

Page 101: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.25

Hours Two wheeler Three wheeler

Passenger cars & pick-up vans

Heavy commercial

vehicles (HCV) Total vehicles

v/hr PCU/hr (0.75)

v/hr PCU/hr

(2) v/hr

PCU/hr (1)

v/hr PCU/hr

(3.7) Total

Total PCU/hr

0.6 – 0.8 D Fair/Average 0.6 – 0.8

0.8 – 1.0 E Poor 0.8 – 1.0

1.0 and Above F Very Poor 1.0 and Above

Table 3.14 Traffic survey at Ookal Junction (Warangal - Narsampet road to Site via Mariyapuram &

Ookal (To & Fro)

Hours Two wheeler Three wheeler

Passenger cars &pick-up vans

Heavy commercial

vehicles (HCV) Total vehicles

v/hr PCU/hr (0.75)

v/hr PCU/hr

(2) v/hr

PCU/hr (1)

v/hr PCU/hr

(3.7) Total

Total PCU/hr

06:00-07:00 43 32 22 44 12 12 2 7 79 96

07:00-08:00 89 67 28 56 16 16 4 15 137 154

08:00-09:00 123 92 54 108 28 28 6 22 211 250

09:00-10:00 145 109 89 178 32 32 8 30 274 348

10:00-11:00 186 15 65 130 36 36 12 44 299 225

11:00-12:00 165 124 45 90 27 27 14 52 251 293

12:00-13:00 143 107 34 68 24 24 11 41 212 240

13:00-14:00 134 101 37 74 23 23 9 33 203 231

14:00-15:00 126 95 28 56 22 22 8 30 184 202

15:00-16:00 112 84 25 50 21 21 6 22 164 177

16:00-17:00 134 101 26 52 25 25 8 30 193 207

17:00-18:00 156 117 45 90 27 27 7 26 235 260

18:00-19:00 134 101 67 134 25 25 7 26 233 285

19:00-20:00 123 92 52 104 23 23 5 19 203 238

20:00-21:00 122 92 43 86 18 18 4 15 187 210

21:00-22:00 112 84 32 64 8 8 3 11 155 167

22:00-23:00 67 50 21 42 5 5 1 4 94 101

The highest peak observed is 348 PCU/hr. during 09 am to 10 am.

Total width of the road in meters (arterial road with no frontage access, no standing vehicle little cross traffic

07

Carrying capacity of the road (the road is 2 lane 2 way road) As per IRC: 106-1990 (PCU’s per hr)

1200

Existing V/C ratio 0.29

LOS = Level of Service (Existing) “B”

V/C LOS Performance V/C

0.0 – 0.2 A Excellent 0.0 – 0.2

0.2 – 0.4 B Very Good 0.2 – 0.4

0.4 – 0.6 C Good 0.4 – 0.6

0.6 – 0.8 D Fair/Average 0.6 – 0.8

0.8 – 1.0 E Poor 0.8 – 1.0

1.0 and Above F Very Poor 1.0 and Above

Page 102: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.26

Table 3.15 Traffic survey at Vanchanagiri Junction (Warangal - Narsampet road to Site via

Shayampet (To & Fro)

Hours Two wheeler Three wheeler

Passenger cars &pick-up vans

Heavy commercial

vehicles (HCV) Total vehicles

v/hr PCU/hr (0.75)

v/hr PCU/hr

(2) v/hr

PCU/hr (1)

v/hr PCU/hr

(3.7) Total

Total PCU/hr

06:00-07:00 32 24 18 36 9 9 0 0 59 69

07:00-08:00 54 41 25 50 13 13 2 7 94 111

08:00-09:00 86 65 47 94 24 24 3 11 160 194

09:00-10:00 112 84 68 136 27 27 4 15 211 262

10:00-11:00 103 15 54 108 25 25 5 19 187 167

11:00-12:00 94 71 34 68 22 22 6 22 156 183

12:00-13:00 86 65 28 56 18 18 7 26 139 164

13:00-14:00 62 47 22 44 16 16 5 19 105 125

14:00-15:00 54 41 19 38 14 14 3 11 90 104

15:00-16:00 46 35 16 32 17 17 2 7 81 91

16:00-17:00 57 43 23 46 21 21 4 15 105 125

17:00-18:00 76 57 36 72 23 23 5 19 140 171

18:00-19:00 84 63 42 84 15 15 6 22 147 184

19:00-20:00 63 47 46 92 12 12 4 15 125 166

20:00-21:00 44 33 32 64 9 9 2 7 87 113

21:00-22:00 32 24 28 56 6 6 0 0 66 86

22:00-23:00 21 16 14 28 4 4 0 0 39 48

The highest peak observed is 262 PCU/hr. during 09 am to 10 am.

Total width of the road in meters (arterial road with no frontage access, no standing vehicle little cross traffic

07

Carrying capacity of the road (the road is 2 lane 2 way road) As per IRC: 106-1990 (PCU’s per hr)

1200

Existing V/C ratio 0.22

LOS = Level of Service (Existing) “B”

V/C LOS Performance V/C

0.0 – 0.2 A Excellent 0.0 – 0.2

0.2 – 0.4 B Very Good 0.2 – 0.4

0.4 – 0.6 C Good 0.4 – 0.6

0.6 – 0.8 D Fair/Average 0.6 – 0.8

0.8 – 1.0 E Poor 0.8 – 1.0

1.0 and Above F Very Poor 1.0 and Above

3.10 Land use Land cover

The land use/land cover for the study area of 10 km radius is prepared in the form of a map by using

Satellite Imageries. The satellite data is processed using ERDAS Imagine software supported with

ground checks and ground truth verification. Area and distance calculations have been carried out

using Geographical Information System (GIS) software after georeferencing the interpreted data

with the help of Survey of India (SoI) Topo sheets (scale 1:50,000).

Page 103: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.27

3.10.1 Satellite Imagery

The Satellite Images (IRS - P6 LISS IV/ IVMX) of the study area are procured from National Remote

Sensing Agency (NRSA), Hyderabad. The details of satellite imageries are given below.

Table 3.16 Details of satellite Imageries

S.No Season Satellite Sensor

1 Khariff IRS P6 LISS IV

2 Rabi IRS P6 LISS IV

3.10.2 Land Use pattern

The land use pattern of the project site area is presented below.

Table 3.17 Land use in the Project area

S.No Land Use Area (ha) Area (acres) % of Area

1 Stream 3.27 8.09 0.68

2 Vegetation 12.70 31.37 2.64

3 Agricultural fallow 202.73 500.76 42.07

4 Agricultural (Crop Land) 263.14 649.96 54.61

Total area 481.84 1190.17 100.00

3.10.3 Land use pattern in and around project site (10 Km radius)

A map depicting major land use/land cover classes comprising built up lands, crop land, water bodies

and waste lands/others. Based upon output area statistics is calculated for different land use classes

given in below table.

Table 3.18 Land use pattern in Project influenced area

10 km Radius LULC Area

Level-1 (1:1000000 scale) Level-2 (1:250,000 scale)

Class Area (ha) % of Area Class Area (ha) % of Area

Built Up 1000.01 3.18 Built Up 1000.005 3.18

Agricultural Land

26730.73 85.48

Crop Land 17360.9975 55.27

Current Fallow 9263.685 29.49

Plantation 106.045 0.34

Low Dense Vegetation

940.55 3.01

Low Dense Vegetation\ Semi Green

481.83 1.53

Degraded Scrub Land 458.7175 1.46

Wastelands 590.76 1.89

Wet Land 334.745 1.07

Marshy\Swampy Land 28.0775 0.09

Barren Rocky Land 227.9375 0.73

Water Bodies

2008.50 6.42 Inland Water 1908.6875 6.08

Canal 87.195 0.28

Page 104: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.28

Figure 3.9 Land use Land cover Map

Page 105: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.29

Table 3.19 Land use pattern in Project core area

Core Area LULC

Level-1 (1:1000000 scale) Level-2 (1:250,000 scale)

Class Area (ha) % of Area Class Area (ha) % of Area

Built Up 0.04 0.01 Built Up 0.04 0.01

Agricultural Land 542.71 97.70 Crop Land 360.35 64.87

Current Fallow 182.36 32.83

Low Dense Vegetation

9.04 1.63 Low Dense Vegetation\ Semi Green

9.04 1.63

Wastelands 0.84 0.15 Wet Land 0.84 0.15

Water Bodies 2.89 0.52 Inland Water 0.26 0.05

River 2.62 0.47

Total area 555.51 100.00 Total area 555.51 100.00

Figure 3.10 Land use pattern in Project core area

Page 106: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.30

Figure 3.11 Satellite imagery of the site & study area

Page 107: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.31

3.11 Biological Environment

3.11.1 General description of the study area

The study area was divided in two major parts namely the Core area/Project area and buffer area.

Core Area: the core area is mostly comprised of project site and the area is flat with fallow

agriculture land with barren patches.

Buffer Area: The buffer area i.e. area around the project site is majorly occupied by the agriculture

fields. The board categories of the land use types in the buffer area include fallow agriculture fields,

waste land, water bodies and scrubs.

3.11.2 Objectives of Ecological Study

The objectives of the present study are intended to:

Generate baseline data from field observations from various terrestrial and aquatic

ecosystems

Compare the data so generated with authentic past records to understand changes a

Characterize the environmental components like land, water, flora and fauna.

3.11.3 Methods for the study

To accomplish the above objectives, a general ecological survey covering an area of 10 km radius

from the proposed project boundary was done as follows:

Reconnaissance survey for selection of sampling sites in and around the site on the basis of meteorological conditions

Generation of primary data to understand baseline ecological status, important floristic elements

Generation of primary data to understand baseline fauna structure and

Collection of secondary data from Forest Working Plan and Gazetteers.

Compilation of secondary data from published literature of Forest DivisionPrimary data generation through systematic studies which was done through:

Generation of primary data to understand baseline ecological status, fauna structure

and important floristic elements;

Preparing a checklist of plants observed at the site.

Determining the bird population by taking random readings at every location.

Observing mammals, reptiles, amphibians, insects through their calls, droppings,

burrows, pugmarks and other signs.

Interaction with local residents

Page 108: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.32

3.11.3.1 Review of secondary data and environmental setting of the project site

With reference to the vegetation of the district, dry deciduous type of forests is observed the study

area. Natural factors include factors such as the altitude, the soil conditions, the quantity and

regularity of the rainfall. All the acquired lands would be used for industrial purposes.

3.11.3.2 Ecological Status

3.11.3.2.1 Terrestrial vegetation and flora of the core zone: Environmental setting and flora of the area identified for the Industrial Park: The area identified for

the TSIIC Mega Textile Park is referred to hereafter as the core area while its surroundings extending

up to 10 Km radius is referred to as the buffer zone. Total area of the park is 1190 Ac (481.85 ha).

The core area comprises of non-forest wastelands and seasonal agriculture lands. It is sparsely

covered by a few shrubs, thorny bushes and some trees. There are no plantations or orchards. Major

part of the land was under dry rain-fed cultivation before it was acquired by the TSIIC for the Mega

Textile Park as evidenced by the existence of field bunds. There will be permanent change of land

use from agriculture/farming land to industrial use. Mesquite (Prosopis juliflora), Ber (Ziziphus

nummularia), Musti (Strychnos nux-vomica), Neem (Azadirachta indica), Babul (Acaia nilotica),

Lantana camara, Agave americana, Nirgundi (Vitex negundo) Anisomeles indica, Calotropis procera,

Cassia auriculata, Waltheria indica, Solanum xanthocarpum, were common wild plants found in the

core area and the maize (Zea mays) crop & cotton plantation (Gossypium arboreum) is observed in

the proposed site area.

3.11.3.2.2 Vegetation and Flora of the Buffer zone:

Land use and land cover of the buffer zone reveals the absence of any National Parks or Wildlife

Sanctuaries or Biosphere Reserves or Important Bird Areas (IBAs) or Protected Wetlands within 10

Km radius of the project site. The core area is surrounded mainly by croplands, fallow lands,

degraded vegetation and plantations, irrigation tanks and built-up area. Major Water bodies like

Sangem lake 3.0 Km (S), Yelgur lake 3.5 Km (SE), Gadepally lake 1.5 Km (W), Bhadrakali lake 11.5 Km

(NW) are present in the buffer zone are usually dry in summer, but due to heavy rains in monsoon

season 2016, and the “Mission Kakatiya” Programme of Telangana Government for revival and

restoration of Minor Irrigation Sources in Telangana State, results to collection of good amount of

water in the many of tanks in the district. There are no major streams existing within the site. But,

the SRSP Kakatiya canal is passing adjacent to the site boundary (West and South).

Paddy is the main crop, after paddy, cotton occupies next priority, other crops like sorghum,

sunflower and chilies, maize and pigeon pea, all vegetables, flowers, cereals especially Raagi, pulses

and oil seeds are grown in the buffer zone. But there are many non-cultivable wastelands sparsely

covered with thorny bushes of Maytenus emarginata, Prosopis juliflra, Acacia nilotica as well as

Lantana indica, Calotropis gigantea, Calotropis procera, Cassia auriculata and others. Tamarindus

indica, guava and pomegranate are the other major fruit trees. Eucalyptus and teak are the main

pulpwood and timber plantations respectively. All common avenue and agroforest species are grown

along the roadsides.

There are no rare, endangered and threatened (RET) species existing under wild conditions within

the buffer zone of the MTP. They range in plant cover from open to moderately closed. The major

trees observed are Tamarindus indica, Borassus flabellifer, Albizia procera, Species of Accacia,

Page 109: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.33

Holoptelea integrifolia, Strychnos nux-vomica, Lagerstroemia, Ficus species, Bamboo, Wrightia

tinctorea, Carissa spinarum, Cassia auriculata, Capparis decidua, etc. are common in these fallow

and barren areas. A list of trees, shrubs and perennial climbers found in the buffer zone is given

below.

Table 3. 20 List of trees, shrubs and perennial climbers found in the buffer zone

Scientific name Common or Local name Family

Acacia nilotica Nalla tumma Mimosaceae

Agave americana Kalabanda Agavaceae

Ailanthus excels Peddamaanu Simaroubaceae

Albizia procera Tella chinduga Fabaceae

Annona squamosa Custard apple Annonaceae

Azadirachta indica Vepa Meliaceae

Bauhinia racemosa Aare chettu Caesalpiniaceae

Brachiaria mutica Grass Poaceae

Breynia vitis-ideae Nalla purugudu Euphorbiaceae

Calotropis gigantea Tella Jilledu Asclepiadaceae

Calotropis procera Jilledu Asclepiadaceae

Cassia auriculata Tangedu Caesalpiniaceae

Cenchrus ciliaris Grass Poaceae

Cereus trigonodendron Cactus Cactaceae

Chrysopogon fulvus Grass Poaceae

Croton bonplandianum Bun Tulsi Euphorbiaceae

Cyperus rotundus Grass Cyperaceae

Eucalyptus teretocronis Eucalyptus Myrtaceae

Eucalyptus hybrid Eucalyptus Myrtaceae

Ficus benghalensis Marri Moraceae

Ficus racemosa Medi Moraceae

Ficus religiosa Raavi Moraceae

Heteropogon contortus Grass Poaceae

Holoptelia integrifolia Nemali naara Ulmaceae

Hyptis suaveolens Pignut Lamiaceae

Ipomoea carnea Rubber mokka Convolvulaceae

Jatropha glandulifera Wild castor Euphorbiaceae

Lantana camara Lantana Verbenaceae

Lantana indica Lantana Verbenaceae

Opuntia dillenii Bonta jemudu Cactaceae

Phoenix sylvestris Eetha Arecaceae

Pongamia pinnata Gaanuga Fabaceae

Prosopis juliflora English tumma Mimosaceae

Stylosanthes hamate Hamata grass Fabaceae

Tamarindus indica Chinta Caesalpiniaceae

Page 110: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.34

Scientific name Common or Local name Family

Tectona grandis Teak / Teku Verbenaceae

Tribulus terrestris Palledu Zygophyllaceae

Tylophora indica Kukkapala teega Asclepiadaceae

Vitex negundo Vaavili / Nirgundi Verbenaceae

Wattakaka volubilis Tummudu teega Asclepiadaceae

Withania somnifera Aswagandha Solanaceae

Wrightia tinctoria Pala –kordusha Apocynaceae

Ziziphus nummularia Nela Regu Rhamnaceae

Ziziphus mauritiana Regu Rhamnaceae

Source: The above data observed during primary survey

3.11.3.2.3 Terrestrial fauna of the Core area and the Buffer zone:

As the animals, especially vertebrates and the winged invertebrates move from place to place in

search of food, shelter, mate or other biological needs, separate lists for core and buffer areas are

not feasible. There are no forests or wildlife habitats within the core area. As such there are no

chances of occurrence of any rare or endangered or endemic or threatened (REET) species within

the core area.

There are no Sanctuaries, National Parks, Tiger Reserve or Biosphere Reserve or Elephant Corridor or

other protected areas within 10 Km buffer zone. It is evident from the available records, reports and

circumstantial evidence that the entire study area including the core and buffer areas were free

from any endangered animals. Among the mammals, only Squirrels, Mongoose, Rats, Bandicoots

and Rabbits were seen but rarely during the survey. Monkeys were also rare. Among the reptiles,

Lizards, Garden lizards were common. No snakes or Monitor lizard was seen during the survey.

The amphibians were seen frequently in and around the water bodies. A list of Mammals, Reptiles

and Amphibians either found or reported from the area is given in Table 3.21. A list of birds is given

in Table 3.22. There were no resident birds other than Crows, Parrots, Doves, and Weaver birds,

Swifts, Quails and Mynas. It is apparent from the list that none of the species either spotted or

reported is included in Schedule I of The Indian Wildlife (Protection) Act, 1972.

List of vertebrates other than birds in and around the project site are tabulated below. WPA

indicates Schedule number in The Indian Wildlife (Protection) Act, 1972.

Table 3.21 List of vertebrates other than birds

Scientific name Common name Local name WPA

Mammals

Bandicota indica Large bandicoot rat Pandikokku IV

Cynopterus sphinx Short-nosed fruit bat Gabbilam IV

Funambulus palmarum Three striped squirrel Udatha

IV

Golunda ellioti Indian bush rat Yeluka IV

Herpestes edwardsii Indian grey mongoose Mungeesa II

Page 111: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.35

Scientific name Common name Local name WPA

Hystrix indica Indian crested porcupine Mullapandi

IV

Macaca mulatta Rhesus Macaque Kothi II

Mus booduga Common Indian field mouse Yeluka IV

Mus musculus Home mouse Yeluka IV

Nosokia indica Bandicoot rat Pandikokku IV

Pipistrellus mimus Indian pygmy pipistrelle Gabbilam IV

Rattus rattus Common Indian rat Yeluka IV

Sus scrofa Wild boar Adavi Pandi III

Reptiles

Bungarus caeruleus Common Indian Krait Katla paamu IV

Calotes versicolor Garden lizard Thonda IV

Chameleon zeylanicus Chameleon Oosaravelli IV

Echis carinatus Saw scaled viper Pinjari IV

Geochelone elegans Indian star tortoise Nakshatra taabelu IV

Hemidactylus flaviviridis Indian wall lizard Balli IV

Naja naja Cobra Naagu paamu II

Ptyas mucosa Rat snake Jerri pothu II

Varanus bengalensis Common Indian Monitor Udumu I

Vipera russseli Russell’s viper Rakta pinjari II

Amphibians

Bufo melonosticatus Common Indian Toad Toad IV

Hoplobatrachus tigerinus Tiger Frog Kappa IV

Hyla arboria Tree Frog Chettu kappa IV

Rana hexadactyla Green Pond Frog Kappa IV

Sphaerotheca breviceps Indian Burrowing frog Burada kappa IV

Table 3.22 List of Birds either spotted or reported from the areas in and around the project site.

WPA indicates Schedule number in The Indian Wildlife (Protection) Act, 1972

Scientific Name Common Name Family WPA

Accipiter badius Shikra Accipitridae IV

Acridotheres tristis Common myna Sturnidae IV

Aegithinia tiphia Common Iora Irenidae IV

Alcedo atthis Common Kingfisher Alcedinidae IV

Alcedo atthis Smallblue kingfisher Alcedinidae IV

Anas poecilorhyncha Spotted billed duck Anatidae IV

Ardeola grayii India Pond Heron Ardeidae IV

Athene brama Spotted owlet Noctuidae IV

Bubulcus ibis Cattle Egret Ardeidae IV

Centropus sinasis Greater coucal Phasianidae IV

Ceryle rudis Lesser pied Kingfisher Alcedinidae IV

Columba livia Blue rock pigeon Columbidae IV

Coracias benghalensis Indian roller Coraciidae IV

Corvus splendens House crow Corvidae V

Coturnix coturnix Common Quail Phasianidae IV

Page 112: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.36

Scientific Name Common Name Family WPA

Dendrocitta vagabunda Indian tree pie Corvidae IV

Dendrocygna javanica Lesser whistling-duck Anatidae IV

Dicaeum erythrorhynchos Tickell’s flower pecker Dicaeidae IV

Dicrurus macrocercus Black drongo Dicruridae IV

Egretta garzetta Little egret Ardeidae IV

Elanus caeruleus Black-shouldered kite Accipitridae IV

Eudynamys scolopace Asian koel Cuculidae IV

Gallinula chloropus Common Moorhen Rallidae IV

Gallus gallus Red Jungle Fowl Fasianidae IV

Halcyon smyrnensis White-Breasted King fisher Alcedinidae IV

Hierococcyx varius Brain fever bird Ardeidae IV

Himantopus himantopus Black-winged stilt Recurvirostridae IV

Hydrophasianus chrugus Pheasant tailed Jacana Jacanidae IV

Lanius excubitor Great grey shrike Daniidae IV

lxobrychus cinnamomeus Chestnut bittern Ardeidae IV

Megalaima haemacephala Copper smith Barbet Capitonidae IV

Merops orientalis Small Bee eater Meropidae IV

Microcarbo niger Little cormorant Phalacrocoracidae IV

Milvus migrans Black kite Accipitridae IV

Motacilla alba White wagtail Motacillidae IV

Motacilla flava Yellow wagtail Motacillidae IV

Motacilla maderaspatensis Large pied wagtail Motacillidae IV

Nectarinia asiatica Purple sunbird Nectariniidae IV

Nectarinia zeylonica Purple-rumped sunbird Nectariniidae IV

Oriolus oriolus Eurasian golden oriole Oriolidae IV

Passer domesticus House sparrow Passeridae IV

Perirocotus cinnomomeus Small Minivet Phasianidae IV

Phalacrocorax carbo Large Cormorant Phalacrocoracidae IV

Phalacrocorax niger Little cormorant Phalacrocoracidae IV

Porphyrio porphyrio Purple moorhen Rallidae IV

Prinia inornata Plain prinia Cisticolidae IV

Prinia socialis Ashy prinia Cisticolidae IV

Psittacula cyanocephala Blossom headed Parakeet Psittacidae IV

Psittacula krameri Rose-Ringed Parakeet Psittacidae IV

Pycnonotus cafer Red-vented bulbul Pycnonotidae IV

Saxicolodies fulicata Indian robin Turdinae IV

Streptopelia chinensis Spotted dove Columbidae IV

Streptopelia decaocto Eurasian Collared-Dove Columbidae IV

Streptopelia Senegalensis Little brown dove Columbidae IV

Streptopelia tranquebarica Red Collared-Dove Columbidae IV

Sturnus pagodarum Brahminy starling Sturnidae IV

Page 113: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.37

Scientific Name Common Name Family WPA Turdoides caudatus Common babbler Timalinae IV

Upupa epops Common hoopoe Upupidae IV

Vanellus indicus Red-wattled lapwing Charadriidae IV

Vanellus malarbaricus Yellow -wattled lapwing Charadriidae IV

Source: Primary & secondary sources

3.11.3.2.4 Aquatic flora and fauna:

Normally during the winter all the surface water bodies in the study area remained full/some

amount of water. There were no rain water collection tanks within the core area. The Major Water

bodies like Sangem lake 3.0 Km (S), Yelgur lake 3.5 Km (SE), Gadepally lake 1.5 Km (W), Bhadrakali

Lake 11.5 Km (NW) are present in the buffer zone are usually dry in summer. A list of aquatic

macrophytes found in the water bodies is given in Table 3.23.

Table 3.23 List of aquatic/semi aquatic macrophytes found in surface water bodies of buffer zone

Latin name Local / Common name Family

Alternanthera philoxeroides Alligator weed Solanaceae

Alternanthera sessilis Ponnaganti kura Solanaceae

Ammania baccifera Ammania Lythraceae

Aponogeton natans Driftin sword plant Aponogetonaceae

Bacopa monnieri Brahmi Plantaginaceae

Brachiaria mutica Para grass Poaceae

Carex cruciata Carex Cyperaceae

Centella asiatica Saraswati aaku Apiaceae

Cyanotis axillaris Gorlagondi Commelinaceae

Cynodon dactylon Garika gaddi Poaceae

Cyperus rotundus Tunga gaddi Cyperaceae

Echinochloa colona Jungle rice Poaceae

Eclipta alba Guntagalgara Asteraceae

Eichhornia crassipes Gurrapu dekka Pontederiaceae

Limnophila indica Indian Marsh weed Scrophulariaceae

Ludwigia perennis Water Primrose Onagraceae

Marsilea quadrifolia Four leaf clover Marsiliaceae

Nelumbo nucifera Tamara Nelumbiaceae

Nymphaea alba Tella Tamara Nympheaceae

Nymphaea nouchali Lotus Lily Nympheaceae

Nymphoides indica Antara Menyanthaceae

Oxalis corniculata Indian Sorrel Oxalidaceae

Phragmites karka Tall Reed Poaceae

Pistia stratiotes Water Cabbage Araceae

Typha angustata Cattail Typhaceae

Source: The above data collected during primary survey

Almost all tanks were auctioned for aquaculture and the contractors told the survey team that all

commercial fishes were introduced. A list of fish either caught or reported is given in Table 3.24.

Page 114: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.38

Table 3.24 List of fishes either caught by the fisherman or reported from the study area.

S.No. Common name Latin name

1 Catla Catla catla

2 Rohu Labeo rohita

3 Murrel Channa punctatus

4 Prawn Macrobrachium rosenberghii

5 Gobids Glossogobius giuris

6 Mrigal Cirrhinus mrigala

7 Tilapia Oreochromis mossambicus

Source: Primary & secondary sources

3.11.4 Identification of Environmentally sensitive places/ local protected species

As per Botanical Survey of India records and available published literature pertaining to the study

area and current detailed study of project site, no threatened, endangered and rare plant species

were observed from the study area. There is no national park, wildlife sanctuary, biosphere reserve

within 10 Km of the study area. As per The Indian Wildlife (Protection) Act, 1972, no critically

endangered, threatened or rare species of wildlife are present within the buffer zone. The archeological

importance & heritage site of Warangal fort is located at a distance of about 8.0 Km (NW) from the

project site. The sensitivity map of the project site is shown in Figure 3.12.

Page 115: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.39

Figure 3.12 Sensitivity map of the project site

Page 116: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.40

3.11.5 Greenbelt development

Most of the human activities generate pollution of one or other types and of different magnitudes,

to which all the organisms are exposed. More often than not, exposures to some pollution types are

considered unavoidable. Resistance of organisms helps them to overcome the hazards caused by

such exposures. The air pollution emitted by various sources settles on the ground and vegetation of

surrounding area. The plants interact with both gaseous and particulate pollutants and to great

extent absorb them and thus, remove them from the atmosphere. This pollution removal property

of the plants has been known for a long time. For many years tree planting has been promoted by

city planners for the purpose of reducing ground level air pollution.

Out of the total project area of 1190 Acres, 33% of the land will be allotted for greenbelt

development all along the boundary, along the roads & block plantations. (10% at TSIIC park level &

23% Individual Industry level) All along the roads, on both sides avenue trees will be grown at the

rate of 400 per every Km of road at a distance of 5 m.

The Industrial plotted area represents 63.63% (757.67 Ac) of the total land. Besides the common

greenbelt, avenue plantations and block plantations, every industry is required to develop industrial

greenbelts of 5 to 15 m width on all sides in an area of at least 23% of the individual site of the

industry. Thus the total area under Green buffer / greenbelt shall reach 33%. But the trees grown

within the premises of the industries have the potential to make the area green. Once the area is

occupied, the Mega Textile Park under consideration will have more than the stipulated green cover

and industrial greenbelts.

The details of the land allotted for greenbelt and landscaping works are given in Table 3.25.

Table 3.25 Greenbelt and landscaping details

Particulars Area (acre) Remarks

Total land for greenbelt

Green belt area includes: Common greenbelt area at park level -10 % At individual industrial level -23%

3.12 Socio-economics

3.12.1 Demography and Socio-Economics (Secondary Data Description)

This section illustrates the prevailing socio-economic aspects of people inhabiting villages in the core

and buffer zone of the proposed Mega Textile Park boundary. It also attempts to understand these

realities so as to plan impactful developmental interventions for inhabitants of project area villages.

3.12.2 Methodology Adopted for the Study

The study area (both Core and Buffer Zone) covers a 10 km radial distance from the periphery of the

proposed Mega Textile Park in Geesugonda and Sangem taluka of Warangal Rural district. The study

area covers 42 villages including Census Towns (CTs), Out Growth (OG) of the urban municipal

corporations, in Warangal, Hanamkonda, Geesugonda, Sangem and Wardhannapet mandals of

392.9

@ 400 plants/acre will be planted in greenbelt. Identified

local species will be planted in 15 m along site boundary

and 2 m along the road.

Page 117: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.41

Warangal rural and urban Districts. The methodology adopted for data collection includes review of

published secondary data such as district census statistics of 2011, which includes: demography,

occupational structure, literacy profile and Social structure, etc.

Similarly, the primary data was collected through administering structured questionnaire, focused

group discussions, observation and key stakeholder interactions in the Core zone of project area

villages. The salient features of the demographic and socio-economic aspects in the Core and Buffer

Zone (hereafter referred as Study area) has been described in the following sections.

3.12.3 Demographic Aspects

3.12.3.1 Distribution of Population

As per 2011 census the study area consists of 143891 populations in 10 km radial distance from the

periphery of the project. The distribution of population in the study area is given in Table 3.26.

Table 3.26 Distribution of Population in Core and Buffer Zone

S. no. Particulars 0-2km 2-5km 5-10km Total

(0-10 km)

1 Number of households 2459 6654 28382 37495

2 Male population 4508 12443 55233 72184

3 Female population 4594 12277 54836 71707

4 Total population 9102 24720 110069 143891

5 SC population 1776 5594 25537 32907

6 ST population 494 610 10471 11575

7 Total population (0-6 years) 807 2140 10526 13473

8 Average household size 3.7 3.7 3.9 3.8

9 % of males to the total population 49.5 50.3 50.2 50.2

10 % of females to the total population 50.5 49.7 49.8 49.8

11 Sex ratio (no. of females per 1000 males) 1019.1 986.7 992.8 993.4

Source: District Primary Census Statistics of Andhra Pradesh -2011

As illustrated in the above table, the males and females constitute about 50.2% and 49.8% in the study area respectively.

3.12.3.2 Average Household Size

The study area had an average family size of 3.8 persons per household in 2011. This is moderate

family size reflecting single or nuclear type of families, which is also in comparison with the other

parts of the district.

3.12.3.3 Population Density

The density of population of the study area works out to about 273 persons per km2.

Page 118: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.42

Table3.27 Population projections in the study area

Decadal population projections in the project area

Percentage Decadal Variation in Geesugonda Mandal (2001-11)

Year Total population Male Female

8.14

2011 143891 72184 71707

2021 155603 78059 77543

2031 168269 84413 83855

2041 181966 91284 90680

2051 196778 98714 98061 Source: District Primary Census of Andhra Pradesh-2011

The population projections have been worked out based on available census data and the formula

used for this is Arithmetic mean.

3.12.3.4 Sex Ratio

The configuration of male and female indicates that the males constitute to about 50.2% and 49.8%

females of the total population. The sex ratio i.e. the number of females per 1000 males indirectly

reveals certain sociological aspects in relation with female births, infant mortality among female

children and single person family structure, a resultant of migration of industrial workers. The study

area on an average has 993 females per 1000 males.

3.12.4 Social Structure

In the study area about 8% of population belongs to Scheduled Tribes (ST) and 22.9% population

Scheduled Castes (SC) indicating that about 30.9% of the population in the study area belongs to

Scheduled category. The distribution of population in the study area by social structure is given in

Table 3.28.

Table 3.28 Distribution of Population by Social Structure in Core and Buffer zone

S. No. Particulars 0-2 km 2-5 km 5-10 km 0-10 km

1 SC population 1776 5594 25537 32907

2 ST population 494 610 10471 11575

3 % of SC to the total population 19.5 22.6 23.2 22.9

4 % of ST to the total population 5.4 2.5 9.5 8.0

5 Total SC & ST Population 2270 6204 36008 44482

6 Percentage to the total population 24.9 25.1 32.7 30.9

7 Total population 9102 24720 110069 143891

Source: District Primary Census statistics of Andhra Pradesh -2011

3.12.5 Literacy Levels

The analysis of the literacy levels in the study area reveals an average literacy rate of 60% as per 2011

census data. The distribution of literates and literacy rates in the study area is given in Table 3.29.

The male literacy i.e. the percentage of literate males to the total literates of the study area works out

to be 69.2%. The female literacy rate, which is an important indicator for social change, is observed to

be 42.7% in the study area.

Page 119: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.43

Table 3.29 Distribution of Literate and Literacy Rates in Core and Buffer Zone

S. No. Particulars 0-2 km 2-5 km 5-10 km 0-10 km

1 Male population 4508 12443 55233 72184

2 Female population 4594 12277 54836 71707

3 Total population 9102 24720 110069 143891

4 Male literates 3054 8706 38185 49945

5 Female literates 2247 5989 28145 36381

6 Total literates 5301 14695 66330 86326

7 Male literacy rate (%) 57.6 59.2 57.6 57.9

8 Female literacy rate (%) 42.4 40.8 42.4 42.1

9 % of Male literates to the male population 67.7 70.0 69.1 69.2

10 % of Female literates to the female population 48.9 48.8 43.1 42.7

11 Total literacy rate (%) 58.2 59.4 60.3 60.0

Source: District Primary Census Statistics of Andhra Pradesh -2011

3.12.6 Occupational Structure

The occupational structure of residents in the study area is studied with reference to main workers,

marginal workers and non-workers. The main workers include 4 categories of workers defined by the

census department consisting of cultivators, agricultural laborers, those engaged in manufacturing,

processing and repairs in household industry; and others including those engaged in household

industry, construction, trade and commerce, transport and communication and all other services.

The marginal workers are those workers engaged in some work for a period of less than six months

during the reference year prior to the census survey. The non-workers include those engaged in

unpaid household duties, students, retired persons, dependents, beggars, vagrant’s etc. institutional

inmates or all other non-workers who do not fall under the above categories.

As per 2011 census records, there is a total of 43% main workers in the study area. The marginal

workers and non-workers constitute to 7.4% and 49.6% of the total population respectively.

Therefore, non-workers are predominant in the total distribution of workers by occupation. The

work participation rate is estimated as 50.4% in the study area villages. The occupational structure of

the study area is given in Table 3.30.

Table 3.30 Occupational Structure in Core and Buffer Zone

S. No. Particulars 0-2 km 2-5 km 5-10 km 0-10 km

1 Total population 9102 24720 110069 143891

2 Total workers 4947 13288 54215 72450

3 Work participation rate (%) (Total workers/Total population)*100

54.4 53.8 49.3 50.4

4 Main workers 3856 11452 46566 61874

5 Percentage of main workers to total 42.4 46.3 42.3 43.0

Page 120: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.44

population

6 Marginal workers 1091 1836 7649 10576

7

Percentage of marginal workers to total population

12.0 7.4 6.9 7.4

8 Non-workers 4155 11432 55854 71441

9 Percentage of non-workers to total population

45.6 46.2 50.7 49.6

10 Dependency ratio 0.8 0.9 1.0 1.0

Source: District Primary Census Statistics of Andhra Pradesh -2011

3.12.6.1 Dependency Ratio

Based on the occupational structure of the study area the dependency rate of non-workers on the

workers category has been estimated at 1. Hence some economic generating activities should be

developed so that most of the pupils can engage in employment opportunities.

3.12.6.2 Infrastructure and accessibility, Primary Observations in the Core Zone

The following sections ascertains the current existing infrastructural details in surveyed villages in

the core zone, which includes educational institutions, working profile, housing typology and social

composition.

Demographic aspects

As it is illustrated in the table 3.25, the sex ratio in the core zone observed as decent as 1019 women

for 1000 men, and the total socially weaker sections amounts to 24.9 in the core zone.

Occupational Structure

It is also observed that 42% main worker in the total population, whereas marginal workers and non-

workers constitute to 12% and 45.6% of the total population respectively. The distribution of

workers by occupation in the core zone indicates that the non-workers are the predominant

population.

It is also observed that majority of population is dependent on Agriculture and allied activities in the

core area villages. The study also observed the presence of salaried employees in these villages who

has been working as Teachers, employees in the revenue, police departments and road Transport

Corporation.

There are no industries in the core zone, baring few rice mills in the core project area villages. A lot

of un-employed youth travel to Warangal or Hanamkonda to work as daily labour, carpenters,

tailors, construction workers etc.

Literacy Profile:

The male literacy rate is observed as 57.6 and female literacy rate is observed as 42.4 and hence the

total literacy rate is 58.2 has been recorded.

Page 121: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.45

Health Care Facilities and Accessibility:

It 80% of the population are accessed to govt. hospitals and else 20% are accessed to Private

hospitals in the core zone. Majority of the villages has Primary Health Centres as well as

private/registered medical practitioners.

Accessibility to Educational Institutions:

It was observed, that 80% of villages have primary schools, secondary schools and some even have

junior collages which provides education up to Intermediate level. In short, the educational

infrastructure is developed due to closer proximity to major municipal corporations, and district

headquarters. Many students travel to Hanamkonda and Warangal for higher studies.

Water Resources:

Major water sources in our surveyed villages are Water Tanks, Hand pumps, Bore wells, and wells

which have been observed in the core zone. It is observed that few villages also have taps in the core

zone.

Housing Typology:

The 70% of typology of housing is observed as pucca and other 30% is kutcha in the core zone.

Communication Facilities:

The transport and communication facilities are both public and private owned. People travel by

personal vehicles.

Post offices:

80% of villages surveyed are accessed with postal services, while other 20% of villages have to access

nearby town to get postal benefits in the core zone.

Electricity:

All villages are accessed with electricity supply for both phases in the core zone.

Bank facilities:

No village is accessed with bank facilities within the villages.

Heritage/pilgrim interests:

Some of the villagers have accessed with temples

Awareness about Government Schemes and Programs:

Most of the villages surveyed in the core zone are benefitted by government schemes such as old

age pension schemes, widow pensions, MGNREGA (Mahatma Gandhi National Rural Employment

Guarantee Act), housing schemes, mobile health service-104 services etc. The villagers are also

aware of the developments so far as the welfare schemes and measures of the government is

concerned.

Page 122: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.46

Other Observations in the Core Zone

The primary study revealed that 80% of households generate income through cattle rearing and goat

farming. These villages are also connected with existing milk value chain. The local dairy act as a

facilitating channel to enable additional incomes for the village community. Some village Punchayats

also set up veterinary hospitals, which are funded by NABARD. The Gopala Mitra/Para Vet services

are provided all over the cluster of villages.

The socio-Economic study revealed that the youth in the core zone are devoid of employment

opportunities. The employment scenario has been observed as a critical issue in these villages.

Although there are many educated youth in the village, they do not get gainful employment

throughout the year. Many of them work in local companies as casual labour/contract employees for

a period of 2 to 4 months.

During the FGD, it is also observed that many are educated youth in the village of core zone. Some of

them have studied till ITI. As the job scenario is not promising, many of them are migrating to nearby

towns and cities. These youth can be a potential source of workers with minimum handholding and

vocational education skills. The youth have expressed their willingness to setting up of industries in

the area as it provides them gainful employment opportunities. Similarly, this would also trigger

many direct and indirect benefits for economic advancement and social up liftment of project area.

The study also noted an active presence of self-help-groups in the villages. Many of these groups are

acting as micro-finance entities, rotating small amount of loans among the group members.

3.12.7 CSR Works would Carry Out in Future

There has been a possibility of development through CSR and community service in and around the

villages of industrial park. This would develop health, education, skill development, environmental

management of villages in the project area.

3.12.8 Suggestions for Improvement of Socio-Economic Status

The socio-economics status of the population in the project area shall be improved through CSR and

focused community development interventions. Some of the salient activities are illustrated below:

Periodical health checkup camps need to be conducted along with regularization of 104 services which are currently meeting the health care needs of the villages.

The social investment on providing capacity building trainings and strengthening of SHG activities.

Distribution of vitamin and de worming tablets to anganwadi and school going children, distribution of iron tablets to women will bring a tremendous change in the health of women and children.

Fruit distribution to anganwadi children on certain days in a week, construction of child friendly toilet with water facility in the anganwadi etc. will have positive impact.

Page 123: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.47

Providing skill trainings for rural women in tailoring, manufacturing household items like: detergents, soap, toilet cleaners and room fresheners etc. would enhance their income; thereby create better livelihood opportunities for the rural women. These products can be purchased by company will provide additional employment opportunity of the rural women & adolescent girls.

Veterinary camps and para-vet services to enhance the milk production of existing milk producing households.

Abbreviations

No_HH: No. of House Holds

TOT_P: Total Population

TOT_M: Total Male

TOT_F: Total Female

P_06: Population below 6 years

P_SC: Population belongs to SC

P_ST: Population belongs to ST

P_LIT: Population Literate

P_ILL: Population Illiterate

TOT_WORK_P: Total Working Population

MAINWORK_P: Main working population

MAIN_CL_P: Main Cultivator Population

MAIN_AL_P: Main Agriculture Labour Population

MAIN_HH_P: Main Household Population

MAIN_OT_P: Main Other Population

NON_WORK_P: Number of Non-Working population

Page 124: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.48

Table 3.31 Socio economic details of the study area – Census 2011

S.No Name No_HH TOT_P TOT_M TOT_F P_06 P_SC M_SC F_SC P_ST M_ST F_ST P_LIT M_LIT F_LIT P_ILL

0-2 km

1 Venkatapuram (Haveli) 375 1368 667 701 141 263 128 135 56 34 22 826 464 362 542

2 Katrapalli (Haveli) 786 2766 1351 1415 218 580 284 296 17 6 11 1548 880 668 1218

3 Chintalapalli 737 2858 1445 1413 249 366 192 174 381 196 185 1603 953 650 1255

4 Shayampet 561 2110 1045 1065 199 567 290 277 40 21 19 1324 757 567 786

Total 2459 9102 4508 4594 807 1776 894 882 494 257 237 5301 3054 2247 3801

2-5 km

5 Gadepally 811 2968 1488 1480 320 973 492 481 8 3 5 1735 1010 725 1233

6 Kanaparti 976 3711 1863 1848 302 885 439 446 40 19 21 2261 1327 934 1450

7 Gavicherla 1169 4182 2075 2107 346 823 389 434 85 43 42 2473 1442 1031 1709

8 Sangem 1780 6939 3629 3310 554 1459 734 725 304 200 104 4191 2617 1574 2748

9 Vanchanagiri 953 3427 1662 1765 343 641 305 336 62 25 37 1861 1064 797 1566

10 Ookal (H) 665 2330 1152 1178 162 478 236 242 87 41 46 1489 847 642 841

11 Vasanthapur 300 1163 574 589 113 335 160 175 24 12 12 685 399 286 478

Total 6654 24720 12443 12277 2140 5594 2755 2839 610 343 267 14695 8706 5989 10025

5-10 km

12 Ammavaripet 98 412 212 200 34 405 209 196 0 0 0 266 145 121 146

13 Allipur 357 1329 662 667 131 166 86 80 7 4 3 767 447 320 562

14 Thimmapur 1784 7513 3828 3685 780 2372 1195 1177 74 37 37 5140 2875 2265 2373

15 Nakkalapalle 229 928 476 452 89 836 435 401 1 0 1 643 370 273 285

16 Mamnoor (CT) 1651 6319 3156 3163 653 2087 1044 1043 494 247 247 4644 2513 2131 1675

17 Punnole 1258 4900 2471 2429 478 1147 586 561 58 27 31 2806 1635 1171 2094

18 Panthini 1110 4165 2085 2080 431 904 471 433 112 57 55 2285 1294 991 1880

19 Chennaram 742 2745 1366 1379 274 481 234 247 6 2 4 1465 864 601 1280

20 Bollikunta 1038 4116 2097 2019 314 1402 718 684 81 42 39 2588 1521 1067 1528

21 Ramachandrapur 589 2146 1067 1079 186 427 226 201 18 8 10 1221 717 504 925

22 Lohitha 591 2235 1121 1114 212 408 214 194 537 252 285 1185 706 479 1050

23 Shapur 352 1391 706 685 145 235 125 110 4 3 1 850 498 352 541

24 Theegarajupalle 618 2450 1237 1213 238 227 114 113 725 376 349 1261 727 534 1189

25 Thimmapur 308 1039 530 509 92 206 108 98 7 5 2 562 342 220 477

26 Pallaruguda 989 3682 1834 1848 334 522 265 257 1817 914 903 1758 1049 709 1924

27 Mondrai 960 3614 1807 1807 361 428 209 219 0 0 0 1970 1135 835 1644

28 Narlavai 308 1090 537 553 82 299 150 149 0 0 0 592 359 233 498

Page 125: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.49

S.No Name No_HH TOT_P TOT_M TOT_F P_06 P_SC M_SC F_SC P_ST M_ST F_ST P_LIT M_LIT F_LIT P_ILL

29 Mummadivaram 98 340 169 171 46 121 58 63 18 10 8 185 111 74 155

30 Elugur( Rangampet) 1040 4053 2009 2044 429 534 260 274 1639 821 818 2062 1239 823 1991

31 Nallabelle 524 2212 1101 1111 243 339 165 174 820 401 419 992 579 413 1220

32 Bodduchintalapalle 310 1197 604 593 100 495 256 239 25 14 11 767 428 339 430

33 Manugonda 800 2823 1425 1398 244 785 397 388 0 0 0 1530 934 596 1293

34 Anantharam 254 852 436 416 76 206 106 100 76 31 45 540 307 233 312

35 Geesugonda 1262 4850 2476 2374 435 1398 719 679 71 34 37 2954 1752 1202 1896

36 Potharajpalle 384 1542 742 800 148 316 143 173 31 15 16 859 499 360 683

37 Machapur 989 3778 1878 1900 283 326 161 165 454 223 231 2276 1324 952 1502

38 Viswanathpur 880 3450 1732 1718 380 196 91 105 2554 1280 1274 1560 971 589 1890

39 Warangal (M.Corp. + OG) (Part) 2935 11451 5725 5726 1078 2269 1122 1147 298 148 150 7158 4124 3034 4293

40 Dharmaram 1577 6091 3036 3055 543 789 391 398 68 36 32 3813 2210 1603 2278

41 Stambampalle 1058 4197 2115 2082 422 1145 571 574 206 100 106 2660 1515 1145 1537

42 Gorrekunta (CT) 3289 13159 6593 6566 1265 4066 2010 2056 270 146 124 8971 4995 3976 4188

Total 28382 110069 55233 54836 10526 25537 12839 12698 10471 5233 5238 66330 38185 28145 43739

Grand Total 37495 143891 72184 71707 13473 32907 16488 16419 11575 5833 5742 86326 49945 36381 57565

Source: District Primary Census Statistics of Andhra Pradesh -2011

Table 3.32 Occupational Structure and Employment Scenario in the project area Villages

S.No Name No_HH TOT_P TOT_WORK

MAIN WORK_P MAIN_CL MAIN_AL MAIN_HH MAIN_OT

MARG WORK_P NON_WORK_P P M F Population Population Population Population

0-2 km

1 Venkatapur (Haveli) 375 1368 699 355 344 696 111 413 0 172 3 669

2 Katrepale(Haveli) 786 2766 1508 785 723 1169 348 517 5 299 339 1258

3 Chintalapalle 737 2858 1560 785 775 1196 426 516 47 207 364 1298

4 Shayampet 561 2110 1180 597 583 795 252 150 24 369 385 930

Total 2459 9102 4947 2522 2425 3856 1137 1596 76 1047 1091 4155

2-5 km

5 Gadepalle 811 2968 1690 876 814 1602 439 808 14 341 88 1278

6 Kapulakanaparthy 976 3711 2258 1164 1094 2143 650 937 64 492 115 1453

7 Gavicherla 1169 4182 2208 1197 1011 1313 502 531 15 265 895 1974

8 Sangam 1780 6939 3616 1899 1717 3038 1014 1295 66 663 578 3323

9 Vanchangiri 953 3427 1716 841 875 1647 463 841 17 326 69 1711

10 Ookal (H) 665 2330 1268 683 585 1226 233 552 174 267 42 1062

11 Vasanthapur 300 1163 532 316 216 483 76 252 26 129 49 631

Total 6654 24720 13288 6976 6312 11452 3377 5216 376 2483 1836 11432

Page 126: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 3.50

S.No Name No_HH TOT_P TOT_WORK

MAIN WORK_P MAIN_CL MAIN_AL MAIN_HH MAIN_OT

MARG WORK_P NON_WORK_P P M F Population Population Population Population

5-10 km

12 Ammavaripet 98 412 236 127 109 234 2 200 2 30 2 176

13 Allipur 357 1329 726 388 338 513 138 105 4 266 213 603

14 Thimmapur 1784 7513 3073 2015 1058 2595 21 881 38 1655 478 4440

15 Nakkalapalle 229 928 484 265 219 204 17 133 0 54 280 444

16 Mamnoor (CT) 1651 6319 2141 1620 521 1850 62 421 14 1353 291 4178

17 Punnole 1258 4900 2516 1355 1161 2500 427 1926 6 141 16 2384

18 Panthini 1110 4165 1986 1147 839 1299 455 392 15 437 687 2179

19 Chennaram 742 2745 1375 756 619 1075 343 405 6 321 300 1370

20 Bollikunta 1038 4116 2112 1108 1004 1916 322 1058 34 502 196 2004

21 Ramachandrapur 589 2146 1154 587 567 1041 423 503 14 101 113 992

22 Lohitha 591 2235 1171 610 561 955 230 558 24 143 216 1064

23 Shapur 352 1391 820 411 409 466 228 122 1 115 354 571

24 Theegarajupalle 618 2450 1326 681 645 1041 548 270 23 200 285 1124

25 Thimmapur 308 1039 643 326 317 593 189 359 5 40 50 396

26 Pallaruguda 989 3682 2086 1023 1063 1764 264 1254 29 217 322 1596

27 Mondrai 960 3614 1905 1000 905 1689 724 686 20 259 216 1709

28 Narlavai 308 1090 621 295 326 583 254 305 0 24 38 469

29 Mummadivaram 98 340 180 100 80 180 21 97 9 53 0 160

30 Elugur( Rangampet) 1040 4053 2332 1151 1181 1801 446 1144 29 182 531 1721

31 Nallabelle 524 2212 1237 602 635 885 618 196 2 69 352 975

32 Bodduchintalapalle 310 1197 593 342 251 591 113 447 7 24 2 604

33 Manugonda 800 2823 1624 848 776 1270 200 778 28 264 354 1199

34 Anantharam 254 852 530 266 264 529 219 261 0 49 1 322

35 Geesugonda 1262 4850 2616 1335 1281 2490 304 1788 49 349 126 2234

36 Potharajpalle 384 1542 908 464 444 895 291 308 30 266 13 634

37 Machapur 989 3778 2121 1093 1028 1865 259 1297 71 238 256 1657

38 Viswanathpur 880 3450 1981 974 1007 1788 932 634 6 216 193 1469

39 Warangal (M.Corp. + OG) (Part) 2935 11451 5329 3168 2161 4644 587 1431 59 2567 685 6122

40 Dharmaram 1577 6091 2835 1644 1191 2583 340 821 14 1408 252 3256

41 Stambampalle 1058 4197 1962 1208 754 1578 171 358 19 1030 384 2235

42 Gorrekunta (CT) 3289 13159 5592 3641 1951 5149 116 930 138 3965 443 7567

Total 28382 110069 54215 30550 23665 46566 9264 20068 696 16538 7649 55854

Grand Total 37495 143891 72450 40048 32402 61874 13778 26880 1148 20068 10576 71441

Page 127: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.1

Chapter – 4

Anticipated Environmental Impacts &

Mitigation Measures

4.1 Introduction

In this chapter the environmental impacts associated with the proposed set-up of Mega Textile Park

(MTP) are identified, characterized, and evaluated systematically. The extent of impact on air, water,

soil, flora and fauna will be evaluated in relation to the environmental pollution. The impacts will be

distinctly direct and indirect, positive and negative, reversible and irreversible. The prediction of

impacts on various environmental parameters during preoperational, operational, and post-

operational activities assists in effective identification of mitigation measures to minimize the

adverse impacts on environmental quality. The prediction of impacts on different sectors has been

studied using scientific tools and the results are anticipated. Such predictions are superimposed over

the baseline (pre-project) status of environmental quality to develop the ultimate (post-project)

scenario of the environmental conditions. The successful environmental impact assessment process

requires proper identification, prediction, assessment, and also communication of the significant

environmental impacts to the public. The details on impact of the project activity on each of the

disciplines mentioned above are discussed below.

The environmental impacts associated due to the proposed MTP are classified into two phases and

the possible impacts are assessed.

1. Impacts during construction phase

2. Impacts during operation phase

4.2 Impact during construction phase

Activities during constructional phase include site clearance, site formation, building works,

infrastructure provision, and any other infrastructure activities.

4.2.1 Impact on air quality

Up gradation of existing roads and construction of new roads approaching the proposed MTP

involves leveling of the earth work, within the proposed MTP, cutting and leveling activity would be

required for providing roads, sewage network, storm water system and administrative buildings for

proposed project.

The potential source of air quality impact arising from the establishment/construction of the

proposed project is fugitive dust generation. The dust, measurable as particulate matter (PM<2.5

µm, PM<10 µm), Sulphur dioxide (SO2), oxides of nitrogen (NOx) would be generated as a result of

construction activities. During construction, the existing houses nearby may be subjected to the

potential dust impacts.

Page 128: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.2

The potential dust sources associated with the constructional activities are loading and unloading of

the materials, top soil removal, vehicular movement over unpaved roads, and wind erosion, etc. The

possible constructional activities that contribute to the environmental impacts broadly given below:

Dust generation during leveling of earth

Dust generation due to the movement of vehicles on unpaved roads

Emission of pollutants from vehicular exhaust

Unloading of raw materials and removal of unwanted waste material

Accumulation of excavated earth material

4.2.1.1 Proposed mitigation measures

The impact of the above mentioned activities would be temporary and will be restricted to the

constructional phase. However, the impact is generally confined to the proposed project and is

expected to be negligible outside the boundary of the MTP. Nevertheless, the following mitigation

measures will be adopted to limit the environmental impact during constructional phase:

Regular water sprinkling will be done to avoid the dust materials entering into the atmosphere. Furthermore, during windy days, the frequency of the water sprinkling will be increased.

The vehicular movement will be minimized, with a planned scheduling, to reduce the emission of pollutants.

Temporary tin sheets of sufficient height (3m) will be erected around the proposed site as a barrier for dust control.

The excavated material shall be reused within the boundary and the movement of cut and fill material will be limited.

Plantation of trees around the proposed boundary and it will be initiated at the early stages by plantation of 2 to 3 years old saplings using drip irrigation so that the area will be moist for most part of the day.

All the vehicles carrying raw materials will be covered with tarpaulin or plastic sheet and the unloading and loading activity will be stopped during windy period.

4.2.2 Impact on water quality

The proposed project involves various construction activities and the impact on water quality

associated with each of these construction activities are described below:

Site formation

The preparation of land required for the subsequent development activities generates a significant

amount of construction waste. The site formation may produce large quantities of runoff with high

suspended solids in the absence of appropriate mitigation measures. This potential problem will be

intensified during rainy season.

Page 129: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.3

Construction of buildings

During rainy season, due to the construction of various civil structures, the site runoff results in

significant pollution in the receiving water bodies and washing of different construction equipment

will also result in water pollution.

Site workshop

The storage of used engine oil and lubricants as waste materials has a potential to create impacts if

spillage occurs. Waste oil may infiltrate into the surface soil layers or in the form of runoff into local

watercourses which increases the hydrocarbon levels.

Presence of workers

Wastewater will be generated from eating areas and the sewage will be generated from temporary

sanitary facilities. Significant impact on water quality is envisaged if the sewage is discharged directly

into the receiving waters without any prior treatment.

4.2.2.1 Mitigation measures

During site development necessary precautions will be taken, so that the runoff water from the site

gets collected in a working pit. If any over flow occurs, the excess water will be diverted to nearby

greenbelt or plantation area.

The domestic wastewater generated from cleaning of equipment and from eating areas will be

collected and diverted to the working pit in which the suspended solids, if any, will be separated. The

settled water will be reused for constructional purposes and for sprinkling on roads to control the

dust emissions.

The wastewater generated from temporary toilets used by the workforce will be diverted to septic

tank followed by soak pit. If the wastewater generation is high, a mobile STP will be hired from the

local suppliers. Therefore, impact on water quality due to proposed MTP would be insignificant.

The waste generated from the site workshop like used oil and lubricants etc., will be segregated and

disposed to authorized recyclers. The waste like soiled cotton and/or paper will be disposed to

municipal bins.

4.2.3 Impact on noise levels

The major activities which produce periodic noise during construction phase are as follows:

Foundation works

Fabrication of structures

Plant erection

Operation of construction equipment

Movement of vehicles

4.2.3.1 Mitigation measures

The impact on noise environment can be made insignificant by adopting the following mitigation

measures:

Page 130: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.4

Noise generating equipment will be used during daytime for a brief period as per requirements.

Wherever possible the noise generating equipment will be kept away from the human habituation.

Temporary tin sheets of sufficient height (3 m) will be erected around the proposed site as barrier for minimizing the noise travel to surrounding area.

All the vehicles entering into the proposed site will be informed to maintain speed limits and not to blow horns unless it is required.

The workers involved in operating major noise generating equipment will be provided with ear plugs or ear muffs.

4.2.4 Impacts due to solid waste generation

During the constructional stage, the solid waste generated is required to be disposed in an

appropriate and environmentally acceptable manner. The wastes generated from different activities

of constructional phase include the following:

Vegetation and demolition waste from site clearance

Excavated materials from earthworks like cuttings, grading, and foundation works

General construction waste like wood, scrap metal and concrete debris

Domestic waste generated by site workers

Bricks, tiles, etc.

Cement plaster

Steel (from RCC, door, window frames, roofing support, railings of staircase etc.)

Rubble and sand

Stone (marble, granite and sandstone)

Timber and/or wood

Paints and/or varnishes

Besides above there are some major and minor components namely conduits, pipes, electrical

fixtures, panels, etc., also constitutes the solid waste.

4.2.4.1 Mitigation measures

The solid waste generated during this period being predominantly inert in nature, construction and

demolition waste does not create chemical or biochemical pollution. Hence, maximum effort will be

made to reuse and recycle them. The most of the solid waste material can be used for filing and/or

leveling of low-lying areas. All attempts should be made to stick to the following measures:

All construction waste shall be stored within the proposed site itself. A proper screen will be provided so that the waste does not get scattered.

Attempts will be made to keep the waste segregated into different heaps as far as possible so that their further gradation and reuse is facilitated.

Page 131: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.5

Materials which can be reused for purpose of construction, leveling, making roads and/or pavement will also be kept in separate heaps from those which are to be sold or land filled.

The local body or a private company may be arranged to provide appropriate number of skip containers/ trolleys on hire.

The use of the construction material basically depends on their separation and conditions of the

separated material. A majority of these materials are durable and therefore, have a high potential

for reuse. It would, however, be desirable to have quality standards for the recycled materials.

Construction waste can be used in the following manner.

Reuse of bricks, tiles, stone slabs, timber, piping railings etc., to the extent possible and depending upon their conditions.

Sale or auction of materials which cannot be used at the site due to design constraint.

Plastics, broken glass, scrap metal etc., can be sent for recycling in the industries.

Rubble or brick bats can be used for building activity, such as leveling, under coat of lanes where the traffic does not constitute heavy moving loads.

Larger unusable pieces can be sent for filing up low lying areas.

Fine material such as sand, dust, etc., can be used as cover material.

The unearthed soil can be used for leveling as well as for lawn development.

The broken pieces of the flooring material can be used for leveling in the building or can be disposed of.

The unused or remaining paints/varnishes/wood can either be reused or can be disposed of by authorized PCB verndors.

4.2.5 Impact on land use

The Present land use is covered with open scrubs, agricultural, barren land, current follow land etc.

The existing vegetation in the proposed industrial park is predominantly bushes and ground level

shrubs/grasses. There are no matured trees within the site and therefore, no major loss of biomass

is envisaged during the construction phase. The land use pattern of the site will be converted to

industrial activities. Furthermore, the impact on surrounding land use during the constructional

activity is negligible, as all the raw materials required will be stored in the designated area within the

boundary of the proposed MTP.

4.2.6 Impact on demography and socio-economics

The impact due to the proposed MTP on demography and socio economic conditions of the study

area will be as follows.

Increase of floating population

Page 132: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.6

Additional strain on civic amenities like road, transport, communication, drinking water, sanitation and other facilities to meet the work force requirement.

Increase in demand for services like hotels, lodges, public transport, and so on

Employment opportunities for construction laborers; skilled and unskilled workers.

Economic up-liftment of the area.

Raising of home rents and land prices and increase in labour rates

Rapid growth of service sector will result in increase of incomes in the area.

More work to civil construction and transportation companies

Expanding of services like retail shops, banks, automobile workshop, schools, hospitals, and so on.

Increase in literacy rates

4.3 Impacts during operation

The major areas identified to assess the environmental impact due to the proposed MTP are:

Topography and climate

Ambient air quality

Water quality

Soil quality

Noise quality

Solid waste generation

Ecology

Demography and socio-economics

Impact on health

4.3.1 Impact on topography and climate

The major topographical changes envisaged would be the manmade structures like erection of plant

sheds, raw material storage space, civil structures, water reservoirs, etc. However, it will also invite

some positive benefits in the form of up gradation of existing roads, land leveling, tree plantations,

greenbelt development, and so on in the proposed MTP vicinity. Being an industrial park, the impact

on the climate due to the exhaust gas could be envisaged. However, the impact on the climatic

conditions from the proposed MTP will be marginal which can be nullified and/or reduced by

developing greenbelt and by adopting pollution prevention equipment like bag filters and mix of

others.

4.3.2 Impact on air quality

The main raw materials required for the proposed MTP are water and power. PM, SO2 and NOx are

major air pollutant generated from the proposed development of MTP. However PM, SO2 and NOx

emissions are anticipated during the usage of DG sets and boilers.

4.3.2.1 Emission details

Emissions generated during process activities will be properly managed by the member industries.

However, the PM, SO2 and NOx emissions are generated from proposed industrial park are from

Page 133: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.7

diesel generator sets and boilers are properly dispersed into the atmosphere by providing the stack

at sufficient height.

4.3.2.2 Simulation model for prediction

AERMOD version 7.0.3 Gaussian plume dispersion models for prediction of ground level

concentrations (GLC’s) of Sulphur dioxide (SO2), and oxides of nitrogen (NOx) from point source

emissions of proposed MTP.

Where C = Plume contaminant concentration (µg/m3)

Q = Pollutant emission rate (g/s)

u = Average wind speed (m/s)

y = y direction plume standard deviation (m)

z = z direction plume standard deviation (m)

y = y position (m)

z = z position (m)

H = Effective stack height (m)

It should be noted that the vertical term includes the effects of source elevation, receptor elevation,

plume rise, limited mixing in the vertical, and the gravitational settling and dry deposition of

particulates (with diameters greater than about 0.1 microns).

AERMOD is used extensively to assess pollution concentration and deposition from a wide variety of

sources. It is a regulatory steady-state plume modeling system with three separate components:

AERMOD View (AERMOD dispersion model), AERMAP (AERMOD terrain preprocessor), and AERMET

(AERMOD meteorological pre-processor). The AERMOD model includes a wide range of options for

modeling air quality impacts of pollution sources.

Some of the modeling capabilities of AERMOD include the following:

1. The model is used to analyze primary pollutants.

2. Source emission rates can be treated as constant or may be varied by month, season, hour-of-day, or other optional periods of variation. These variable emission rate factors may be specified for a single source or for a group of sources. For this, project all emission rates were treated as constant. The model can account for the effects of aerodynamic downwash due to buildings that are nearby point source emissions.

3. Receptor locations are specified as gridded and/or discrete receptors in a Cartesian or polar coordinate system.

4. Site location involving elevated terrain, the AERMAP terrain pre-processing program is incorporated into the model to generate hill height scales as well as terrain elevations for all receptor locations.

Page 134: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.8

5. The model contains algorithms for modeling the effects of settling and removal (through dry and wet deposition) of large particulates and for modeling the effects of precipitation scavenging for gases or particulates.

AERMOD requires two types of meteorological data files, a file containing surface scalar parameters

and a file containing vertical profiles. These two files are provided by AERMET meteorological pre-

processor program.

4.3.2.3 Model inputs and results

The inputs used to run the model are stack details, emission details, and twenty-four hours mean

meteorological data. The meteorological data is given in Table 4.1; stack emission details and

predictions are given in the Table 4.2, 4.3 and isopleths are shown in Figures 4.1 to 4.3.

The predicted maximum ground level concentration of 24-hour average of PM, SO2 and NOx

concentrations considering 24-hour mean meteorological data of study season are superimposed on

the maximum baseline concentrations obtained during the study period to estimate the post-project

scenario, which would prevail at the post-operational phase.

Table 4.1 24 –hour mean meteorological data for winter season (Dec, 2016 to Feb, 2017)

Hour Temperature (0C) Relative Humidity (%) Wind Direction Avg. Wind speed (m/s) Stability Class

1 20.4 72 180 2.61 6

2 18.5 76 180 2.42 6

3 16.6 78 180 2.15 6

4 14.6 85 180 2.17 6

5 13.2 87 180 2.32 6

6 12.8 88 135 1.88 6

7 15.9 85 180 2.05 5

8 22.8 79 180 2.34 4

9 25.6 77 160 2.19 4

10 28.8 74 180 2.54 3

11 30.3 68 160 2.66 2

12 33.8 59 180 3.04 1

13 35.4 56 180 3.22 1

14 36.2 52 180 3.12 1

15 35.4 54 180 2.45 2

16 32.4 57 180 2.34 3

17 31.6 58 160 2.45 4

18 29.5 60 180 2.41 5

19 28.3 62 180 1.99 5

20 26.4 64 180 2.03 6

21 25.4 65 180 2.22 6

22 24.2 67 180 1.88 6

23 23.2 68 180 2.22 6

24 21.7 70 180 2.28 6

Page 135: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.9

Table 4.2 Stack and emission details of proposed DG Sets & Boilers

(A). Details of emissions from proposed DG sets

Stack Type

of fuel Qty. of fuel

(l/hr)

Height

Dia. Exit Gas tem. (°C)

Exit Gas velocity

(m/s)

Volumetric Flow rate

(m3/s)

SO2 NOx

(m) (g/s)

1000 kVA HSD 206 30 0.5 410 22 4.32 0.04 0.88

Note: No of DG Sets 1000 kVA=27 no’s;

Source: Emissions Regulations: Part IV: COINDS/26/1986-87

- DG set Stack Height (H)=h+0.2 √kVA. - H= Total height of the Stack, h= height of the building (m) where DG set is installed, - kVA Generator capacity, height of the building assumed 3 m - Sulphur content 350 mg/kg as per BS-III HSD standards

- NOx limit 4 g/kW-h as per Gazette of India - G.S.R .771(E) Environmental (Protection)Third Amended Rules dated 11

th December 2013

Table 4.3 Post project scenario

24 – Hourly Concentrations Concentrations (µg/m3)

PM SO2 NOx

Baseline scenario (Max) 52.9 12.0 20.8

Predicted ground level concentration 0.8 5.8 8.4

Overall scenario (Worst Case) 53.7 17.8 29.2

Distance (km) 1.5 1.5 1.5

Direction North North North

NAAQ Standards 2009 Industrial, Residential, Rural & Others 100 80 80

(B). Details of emissions from proposed stacks – Boilers

Stack

Type of

Fuel

Qty. of fuel (kg/hr)

Height Dia. Exit Gas tem. (°C)

Exit Gas velocity

(m/s)

PM SO2 NOx

(m) (g/s)

1 TPH

Boiler

Coal 104 30 0.5 130 15

0.05 0.29 0.19

Note: 54 No. of boilers with - 1 TPH capacity

54-Boilers requirement units (Knitting with processing 15 no’s, Process house- Woven fabric 20 no’s, Yarn

dying 7 no’s & Printing units 12 no’s).

Source: EPA notification GSR 176 (E), April 2, 1996

- Stack height (H)= 14 Q0.3, H- total stack height (m), Q- SO2 emission rate in kg/hr - In no case the stack height shall be less than 11 m - As per Indian coal standards,: Ash content 40 %, : Sulphur content 0.5%.: ESP Efficiency 99.5% - *NOx Considered as 260 g/GJ from pollution prevention and abatement handbook (World Bank group-industry

sector guidelines) - *NOx emission calculation for 1 TPH Boiler: 1TPH = 745 kW = 0.745 MW: We know,

- GJ/h =MW/0.2778 , Therefore GJ/h =0.745/0.2778= 2.682: From world bank guideline ,NOx content in coal is 260 g/GJ, Therefore ,NOx emission =260 g/GJ * 2.682 GJ/h=697 g/h = 0.19 g/s

Page 136: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.10

Figure 4.1 Predicted 24 hourly average GLCs of PM (µg/m3)

In put values (g/s) Predicted GLC ( µg/m3) Distance (km) Direction

2.7 0.8 1.5 North

Figure 4.2 Predicted 24 hourly average GLCs of SO2 (µg/m3)

In put values (g/s) Predicted GLC ( µg/m3) Distance (km) Direction

16.8 5.8 1.5 North

Page 137: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.11

Figure 4.3 Predicted 24 hourly average GLCs of NOx (µg/m3)

In put values (g/s) Predicted GLC (µg/m3) Distance (km) Direction

34.1 8.4 1.5 North

4.3.2.4 Mitigation measures

The major air pollutants generated from the proposed industrial park are given below:

Particulate matter (PM), Sulphur dioxide (SO2) and nitrogen oxides (NOx) from DG set and boiler

stack emissions. To control PM, SO2 and NOx emissions from DG set and Boiler stacks sufficient

height will be proposed according to MoEF&CC guidelines and proper pollution control equipment’s

such as electrostatic precipitator (ESP), bag filter, wet scrubber and so on will be installed at each

industry level.

The air pollution in the proposed MTP arises mainly from the vehicles used for transportation of men

and materials. The main air pollutants like PM, NOx and CO will be released from the transportation

operations.

4.4 Impact on odour

The different types of industries that are coming in the proposed MTP will have an impact on the

odour either by means of its process or product of manufacturing such as different product mix units

of textile & apparels units like spinning, weaving, Knitting, processing & Apparel etc., are among

contributors to odour pollution. Improper sewage treatment practices will produce unpleasant

odour. Vehicular sector also has its share in odour pollution. Rapidly growing vehicular population as

well as pollutants emitted by them generate harmful and pungent odour that have marked effects

on pedestrians as well as near-by residents.

Page 138: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.12

4.4.1 Sources of odour

Odour-producing compounds are hydrogen sulfide, ammonia, carbon disulfide, mercaptans, phenols

and some petroleum hydrocarbons. Most offensive odour is created by the anaerobic decay of wet

organic matter. Warm temperature enhances anaerobic decay and foul odour production. Odour

sources can be classified as:

• Point sources: Point sources are confined emissions from vents, stacks and exhausts.

• Area sources: Area sources may be unconfined like sewage treatment plant, waste water

treatment plant, solid waste landfill, composting, household manure spreading, settling lagoons,

and so on.

• Fugitive sources: In this source of odour, emissions are of fugitive nature like odour emissions

from soil bed or bio-filter surface.

Though foul odour may not cause direct damage to health, toxic stimulants of odour may cause ill

health or respiratory symptoms. Secondary effects, in some, may be nausea, insomnia and

discomfort. Very strong odour can result in nasal irritation; trigger symptoms in individuals with

breathing problems or asthma.

1. Developing green buffer around source

2. Nozzles and sprayers containing chemicals (eg. chlorine dioxide)

3. Rotary water atomizers

In case of point sources such as that of industries, the odour-causing gas stream can be treated after

collecting through piping and ventilation system. Different treatment technologies are available for

control of odour from gas streams collected through process ventilation systems etc.

These include:

1. Dispersion method—Release odorous gases from tall stack is the simplest of the methods that

can be adopted for odour abatement. It results in normal dispersion in the atmosphere and

consequent decrease in ground-level concentration below the threshold value.

2. Mist filtration—while gases cause most odors, problem may also result from aerosols in the

fumes. Odorous air streams frequently contain high concentration of moisture. If the vapor

discharge can be cooled below 40°C, a substantial quantity of the water vapor will condense

thereby reducing the volume of gases to be incinerated. Mist filters can be used for this purpose.

3. Greenbelt development— Greenbelts are used to form a surface capable of sorbing and forming

sinks for odorous gases. Leaves with their vast area in a tree crown, sorbs pollutants on their

surface, thus effectively reduce their concentrations in the ambient air and source emissions.

4.4.2 Odour mitigation measures

Mitigation measure for odour related impacts depends on type of sources – area source or point

source. Some of the control measures from odour emitting from area source such as holding ponds,

lagoons and effluent treatment plants are:

Page 139: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.13

Weightage is to be given for native species while developing greenbelt. Few plants which

counteract odour are:

Eucalyptus can be used as green belt and also as per odour source

Tulasi, Turmeric can also be used for counteracting odour

Water Demand

Wastewater Generation

Remarks

Domestic water 3.0 5.8 8.8 8.0 Treated in CSTP & reused

Industrial

Textile Processing 2.6 18.0 20.6 14.4

Treated in CETP & reused Other units 6.7 0 6.7 4.6

Greenbelt, fire water makeup, etc.

2.1 1.8 3.9 0

Total 14.4 25.6 40.0 27.0 Domestic water assumption

- Employees 190000 @45LPD; Workers in quarters 1500 @ 135 LPD; Greenbelt @ 10KLD/acre - Source of water: SRSP Canal & Ground water

Parameter Units Industrial

wastewater CETP

(post treatment) Standards *

pH - 5.5 – 9.0 6.5 – 8.5 6-9

Oil & Grease mg/l 20 <10 10

TSS mg/l 100 <100 100

FDS (TDS) mg/l 4000 - 4500 <2100 2100

COD mg/l 3000 - 3500 <120 250

BOD at 27C mg/l 2000 - 2500 <100 100

Note: * MoEF&CC Notification – S.O.4 (E) dated 01.01.2016- Into Inland Surface water

Domestic

wastewater

CSTP

(post treatment) Standards **

pH - 6.5 – 9.0 6.5 – 8.5 5.5-9

Oil & Grease mg/l 15 <10 <10

TSS mg/l 250-400 <20 20

COD mg/l 400-500 <50 50

BOD at 27C mg/l 250-350 <10 10

Note: ** MoEF&CC draft Notification dated 24.11.2015

4.4.3 Impact on water quality

4.4.3.1 Wastewater generation

The water demand includes all forms of water use such as water required for production units,

workers, commercial use and landscape irrigation and also firefighting. The details of total water

required and wastewater generated details are given in Table 4.4 and the characteristics of treated

water are given in Table 4.5 and 4.6.

Table 4.4 water requirement and wastewater generation

Water supply Fresh Treated

Table 4.5 Industrial wastewater and CETP (Post-treatment) characteristics

Table 4.6 Domestic wastewater and CSTP (post-treatment) characteristics

Parameter Units

Page 140: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.14

4.4.3.2 Reuse of water An underground sewerage network has been designed to collect sewage from each building and

convey it to a sewage treatment plant. At the STP, the sewage would be treated to acceptable

standards and the treated sewage could be used for irrigation purpose within the proposed park, for

greenbelt development.

4.4.3.3 Sewage Treatment System

a. A sewage treatment plant of 15 MLD capacity using attached growth activated sludge process has been proposed for the MTP.

b. When the CSTP reached the about 70% of the capacity, the next phase of CETP shall be proposed.

c. The STP shall have a screen and grit removal mechanism followed by an equalization tank, aeration tanks with extended aeration and sludge recycling facility, secondary clarifier with sludge removal mechanism, sand and activated carbon filters and a treated sewage tank.

d. Bleaching powder doses will be used for chlorination before disposal of the treated sewage. It is proposed that treated sewage will be used to the extent possible for landscaping and flushing of toilets.

4.4.3.4 Effluent Collection and Treatment System

The core textile processing facilities and the other textile units in the park are expected to generate

about 20.6. The waste water so generated will be conveyed through pipes and discharged into the

effluent treatment plant. The effluent collection network would be of about 22607m in and would

be separated from the domestic sewage collection system. The proposed CETP shall be phased out

as 5 MLD x 4 units. When the CETP reached the about 70% of the capacity, the next phase of CETP

shall be proposed.

The treatment process proposed is a biological treatment. Effluent shall be processed using

extended aeration technology with aeration tanks and secondary clarifiers with sludge handling and

processing units. The treated effluents shall be used for mass foresting in that area.

e. The schematic diagram of the sewage treatment system is presented in Figure 4.4.

Page 141: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.15

SEWAGE

BAR SCREEN

CHAMBER

EQUALISATION

TANKCOLLECTION WELL

SECONDARY

CLARIFICATION

SLUDGE

DRYING BEDSTREATED WATER

SUMP

EXCESS SLU

DGE

RECYCLE

PSF

GARDENS

ON LINE

CHLORINATION

FIL

TR

AT

E

SP

FFP

SP

PUMP

PUMPING

TRICKLINGFILTER

PUMPING

UASB

EFFLUENT

UASB PLANT

EFF

LUE

NT

LAU

ND

ER

EFF

LUEN

T LA

UN

DER

SETTLER

PLATES

GAS

COLLECTORS

TO S

LUD

GE

DR

YING

BED

S

TO T

RIC

KLIN

G

FILT

ERS

SC

UM

MOISTURE

TRAP

GAS

HOLDER

FLARE

STACK

UNIT

FFP FILTER FEED PUMP

PSF PRESSURE SAND FILTER

SP SLUDGE

FFP

Figure 4.4 Schematic flow diagram of CSTP

Page 142: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.16

4.4.3.5 Design Basis and Treatment Scheme – CETP with Units and Equipment

After studying the topographic survey, collection and conveyance points’ survey, geotechnical

investigation reports and pollution load after sampling and analysis, the subsequent step is to work

out the treatment scheme and the design basis and specification of equipment’s of the proposed 20

MLD CETP. This section would further look into this aspect.

4.4.3.7 Collection & Conveyance System

Collection and conveyance system would comprise DI/HDPE/Cement pipe line to transport the raw

effluent from member units, manholes for cleaning, collection sump to receive effluent and effluent

transfer pumps to pump the untreated effluent to the CETP. The choice of pipeline material depends

on the nature (acidic/alkaline/ corrosive) of the effluent and costs. In some clusters, tankers are used

for transportation of effluents. Transportation with tankers may be viable where it is difficult to lay

pipelines and the volume of effluents to be transported is low, along with close monitoring (with GPS

tracking) & licensing, to avoid illegal discharges. In this Project, no transportation of effluent through

tankers are envisaged. The conveyance system for the Project would be through the following

pipeline networks:

a. Untreated or raw effluent collection and discharge network from the individual units to the CETP b. Recovered water conveyance systems for return of recovered water from CETP to individual units c. Recovered brine solution from CETP to member units

This consists of sewer network with gravity pipeline, Collection wells, intermediate pumping stations

& Online monitoring instruments including Electro Magnetic Flow Metering system (EMFM). DI pipes

with cement mortar coating have been used for Raw Effluent system and recovered water and HDPE

pipes have been used for Brine solution. The raw effluent from ember units is collected and

transferred to the Storage and Homogenization tank followed by Pretreatment, Reverse Osmosis

4.4.3.6 Major components of CETP

The Major components in a ZLD based CETP includes, Collection and conveyance system, Pre-

treatment section, RO section and Evaporator section. The schematic flow chart of CETP is given in

Figure 4.5.

Figure 4.5 Schematic flow diagram of CETP

Page 143: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.17

4.4.3.8 CETP – Treatment system

The pre-treatment system would include all the treatment processes before the Reverse Osmosis

System, and comprises of the following processes and components:

i. Storage & Homogenization Tank

ii. Biological Treatment

iii. Tertiary Filtration system comprises Quartz filter, UF, Colour removal resin filter & Softener

filters.

iv. Side stream Lime-Soda Softening Brine Solution

Pre-treatment system involves screening of the effluent for removal of trash & floating solids

followed by a storage and homogenization tank to reduce the temperature of dye bath effluents to

ambient temperature and is subsequently passed through a neutralization tank for pH adjustment.

The next step is the physio-chemical process involving physical separation of suspended solids from

textile dyeing effluent. This process enhances the reduction of Total Suspended Solids (TSS) and

associated Biochemical Oxygen Demand (BOD) levels and prepares the waste for the next

downstream treatment processes. The prime objective is to remove settleable solids by plain

sedimentation and by addition of coagulants and removal of materials that float (scum) by

skimming. Approximately 25 to 50% of the insoluble BOD, 50 to 70% of the total suspended solids

Collection and Conveyance System of a typical ZLD based Textile CETP

Brine Solution

Member Dyeing Units

Common

Effluent Treatment

Plant

SCADA / GPRSSYSYTEM

Electromagnetic Flow Meters

M

M

MHDPE

Recovered Water

DI with cement mortar coating

Raw effluent

DI with cement mortar coating

and Thermal Evaporation process. The entire systems are monitored through PLC/SCADA which is

connected with the website. The above collection and conveyance system is presented in the

schematic diagram Figure 4.6.

Figure 4.6 Schematic collection and conveyance system of CETP

Page 144: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.18

(TSS), and 65% of the oil and grease are removed during this treatment. In addition to this, organic

nitrogen, phosphorous and heavy metals are also removed and settled as sludge.

Next to physio-chemical process, biological treatment, which involves decomposition of suspended

and dissolved organic matter in waste water using microbes. The mainly used biological treatment

processes are suspended culture type activated sludge process or attached culture methods.

Microbes use the organic compounds as both a source of carbon and as a source of energy.

Biological treatment can be either aerobic where microbes require oxygen to grow or anaerobic

phase where microbes grow in absence of oxygen or facultative where microbes can grow with or

without oxygen. In this case, aerobic biological treatment has been considered and a Biological

Oxidation Tank would be used.

We next have the tertiary filtration system which plays a significant role in the final polishing of the

secondary treated effluent. This comprises of Quartz filter, Ultrafiltration, Colour removal resin filter

and Softener filters.

Ion exchange is a process of exchange of ions between solid and liquid interface. Ion Exchange is

widely used to remove colour and calcium and magnesium ions present in the textile effluent. There

are two types of ion exchange systems, the anion exchange resins and the cation exchange resins.

The primary objective of using these resin is to produce high quality treated water and for

safeguarding the RO membranes.

4.4.3.9 CETP - Reverse Osmosis System

The pre-treatment system is followed by a 4-stage Reverse Osmosis System with a permeate

recovery of 78-80%. There are two streams of water generated out of the RO process, one is low TDS

permeate water which would be reused in the dyeing process and the other is high TDS reject water.

This reject stream contains high concentration of salt, colour and organics. The RO reject further

passes through an Additional Stage RO recovery between 28-35% followed by a High Pressure RO.

Figure 4.7 Colour and hardness removal system

Page 145: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.19

High Pressure RO (HPRO) system is an alternative and sustainable technology option to avoid

thermal based Evaporators such as MVR-E/reducing the dependency on conventional evaporators by

reducing the brine volume.

4.4.3.10 CETP Evaporator

The RO reject after High Pressure RO is concentrated in the MEE type Evaporators for recovering of

sodium Sulphates through adiabatic chiller. Multiple Effect Evaporator (MEE) with Falling Film

Evaporators (FFE) and Forced Circulation Evaporators (FCE) and crystallizers are applied for brine

concentrations of up to 350 to 400 gpl for crystallization of salt. Adiabatic chiller is used for recovery

of sodium Sulphates salt at low temperature. Push type centrifuge is used for dewatering of salts

and recovery of chloride and Sulphate salts. An Agitated Thin Film Dryer (ATFD) is used for dry salt

recovery through evaporation of highly concentrated mother liquor (from chillers & centrifuges).

Figure 4.8 Reverse Osmosis

Figure 4.9 Sodium Sulphates recovery rejects management system

Page 146: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Excess Sludge

Sludge Cake for Disposal

Filtrate

Major Quantity

Brine for Reuse at Member dyeing Units

(150-170 gpl)

Condensate

250-350 gpl Mother liquor

Mother Liquor

Recirculation

Waste salt for Disposal

Regenerate/Reject/Brine solution

Legend: HPRO- High Pressure RO, MEE- Multiple Effect Evaporator, FFE- Falling Film Evaporator, FCE- Forced Circulation Evaporator, ATFD- Agitated Thin Film Dryer

Proposed Modifications

Condensate

Existing Components

Untreated effluent

Recovered water

Sludge / Filtrate Recovered Glauber Salt

(Na2SO4.10H2O)

for Reuse

at Member Dyeing Units

Minor Quantity

RO Permeate

Raw Effluent from Member Dyeing Units

Biomass

Recirculation

Filtrate

(Bio Sludge)

Storage and

Homogenisation Tank

Biological Oxidation

Tank

Secondary

Clarifier

Quartz Filter

Ultra Filtration System

(Proposed)

Sludge

Thickener

Filter Press

Softener Filter

Reverse Osmosis

System (4 Stages)

High Pressure RO

Resin Regenerate

Liquor to RC

Reactor

Clarifier

(Lime-Soda

Softening )Sludge

Thickener

Recovered Water for

Reuse at Member Dyeing

Units (RO Permeate &

Evaporator condensate)

MEE

FFE FCE

Brine Treatment System

Adiabatic Chiller

Pusher Centrifuge

Agitated Thin Film

Dryer (ATFD)

Electo-oxidation

/Chlorine Contact Tank

(Colour Removal )

Decolourant Resin

Filter / Electro-

oxidation

Neutralisation Tank

Additional Stage RO

(Proposed)

Filter Press

Sludge Cake (Lime

Sludge to Cement

Industries)

Chlorine Gas Dosing

System

Sulphuric Acid Dosing

System

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.20

Figure 4.10 Schematic flow chart of CETP

Page 147: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.21

4.5 Rainwater harvesting and storm water runoff

All along the road network of the proposed site, storm water drains would be provided to collect

water during rains. They will be adequately sized to prevent flooding of the site. It is proposed to

have rainwater harvesting structures for recharge of roof top rainwater and rainwater of paved

surface at respective buildings. Treatment for silt, oil and grease removal will be provided to

rainwater harvesting recharging pit.

The storm water drains will be acting as recharge trench as the bottom will not be lined and

intermittent check dams will be provided in the storm water drains, so that maximum amount of

rainwater infiltrate into the ground. The excess water will be diverted into the common storm water

drain. The width and depth of the storm water drains will be maintained depending on the slope or

contour of land.

4.6 Solid waste management

The present section presents an assessment of solid waste impacts associated with the operational

phase of the proposed MTP. The sources of solid waste generation at the different phases of the

development are categorized as follows.

Pre-construction/construction phase: Construction and demolition waste is generated during

the constructional activity. Activities such as site clearance, site formation, building works,

infrastructure provision and any other infrastructure. It consists mostly of inert and non-

biodegradable materials such as concrete, plaster, metal, plastics etc.

Occupational phase: The most common solid waste generated in the proposed project is used

batteries, waste oil, and municipal solid waste containing biodegradable and non-

biodegradable waste.

4.6.1 Solid waste generation during operational phase

Solid waste management involves activities associated with generation, storage, collection,

transport, processing and disposal of waste. Information on nature of waste, its composition, and

the quantities generated are essential for effective waste management.

Solid wastes are principally waste clothes, yarn, waste cotton, chemical waste domestic waste,

waste oil, used batteries which originate in the textile units proposed in the Textile Park. No impact

on Land environment is envisaged. The following table gives the anticipated Wastes generated from

the proposed MTP.

The solid waste generated would be from two key sources:

1. Industrial waste, and

2. Municipal solid waste

Industrial waste is classified as hazardous and non-hazardous. The Hazardous wastes will be treated

as per the Hazardous waste (Management, Handling and Tran’s boundary Movement) Rules, 2008

and its subsequent amendments. Electronic waste will be processed as per E-waste (management

Page 148: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.22

S.No Details Units Quantity Remarks Disposal

1 Waste cloths, yarn, etc. kg/day 750 2kg/acre TSDF/Sale

2 Waste Cotton kg/day 375 1 kg/acre TSDF/Sale

3 Chemical waste kg/day 750 2 kg/acre TSDF

4 Waste oil kg/month 17200 (17.2Ton) 100 kg/unit TSDF

5 Used Batteries No’s/annum 344 2 per unit Buy back

6 CETP kg/day 13680 (13.6Ton) TSDF

Assumptions: Industrial land 750 acres; waste generation is assumed for 50% of the Industrial land(i.e:375 acres); Man power assumed:190000(80% of population i.e:1,52,000); For s.no:5 &6 calculated with 172 Units

S.No Details Units Quantity Disposal

1 Domestic Waste & canteen

kg/day 38000 (38 Ton) Disposed to Local Municipalities/compost pit

2 CSTP Sludge Kg/day 868 (0.8Ton) Used as manure for greenbelt

Note: As per CPHHEO manual the per capita MSW generation in developed countries is 0.2-0.6kg/per capita/day.(considered 0.25 kg/person/d)

and handling) Rules 2016, the batteries (management and handling) Rules 2010, Bio medical waste

will be processed as per the Bio medical Waste (Management & handling) Rules, 2016.

The hazardous wastes will be sent to the nearby approved TSDF facility where the hazardous waste

is treated to the standards and disposed of in landfill facility. The breakup of industrial waste and

solid waste is given in Table 4.7 and the Non-hazardous waste is given in Table 4.8.

Table: 4.7 Solid Waste Generation Details

Table: 4.8 Solid Waste Generation Details

Recyclable wastes like paper, cartons, plastics, scrap materials etc., will be sold for further reuse and

recycle.

4.6.2 Mitigation measures

The domestic waste will be segregated at source, recyclable (metal, paper, glass, plastic, etc.) will be

sold to local vendors, biodegradable will be sent to vermicomposting and inert (non-biodegradable)

will be disposed of to the nearest municipal bin by the selected local contractor.

4.7 Impact on traffic

The impact on traffic during operation phase of the proposed MTP depends upon the type of

activities and industries that are coming up in the park. The proposed MTP is adjacent to the

Warangal-Narsampet road. The impact of the traffic is assessed on the basis of the following:

Page 149: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.23

1. Incremental traffic due to the proposed project

2. Impact on air quality

3. Adequacy of the existing highway road network

4. Adequacy of the existing internal road network

5. Adequacy of parking facilities

The transport demand is a function of land use. The land use will be developed in phases and it has

been taken from the approved plan of the MTP and it will be used for traffic demand projections.

Some broad assumptions have also been made about trip generating potential of the various land

uses in different horizon years. The attraction to the study area from surrounding areas is based on

assumptions.

Type of Shift Type of Vehicle Persons

Per Vehicle No.of

employees No.of

Vehicles PCUs

General Shift

Two wheeler 2 998 499 374

Auto 4 333 111 222

Car 4 665 166 166

Bus 50 4655 93 344

Total 6651 869 1106

Note:

Type of Shift Type of Vehicle Persons

Per Vehicle No.of

employees No.of

Vehicles PCUs

General Shift

Two wheeler 2 1995 998 748

Auto 4 665 166 333

Car 4 1330 333 333

Bus 50 9310 186 689

Total 13300 1682 2102

Note: Total estimated manpower is 190000. Total manpower will be considered as 3 shifts + 1 General Shifts =47500/shift Out of the total 30%b of the employees will use train i.e. 14250 employees, remaining 33250 employees 20% (6650) of the employees are use Warangal to Sangem road, 40% (13300) are use Vanchanagiri road and 40% (13300) Ookal road. As considered in general shift the 33250 employees are share 3 approach roads; each road 15% are come by two wheelers, 5% are by 3 wheelers, 10% are by cars and 70% by public transportation (Bus).

Table 4.9 Traffic details through Warangal – Sangem approach road

Total estimated manpower is 190000. Total manpower will be considered as 3 shifts + 1 General Shifts =47500/shift Out of the total 30%b of the employees will use train i.e. 14250 employees, remaining 33250 employees 20% (6650) of the employees are use Warangal to Sangem road, 40% (13300) are use Vanchanagiri road and 40% (13300) Ookal road. As considered in general shift the 33250 employees are share 3 approach roads; each road 15% are come by two wheelers, 5% are by 3 wheelers, 10% are by cars and 70% by public transportation (Bus).

Table 4.10 Traffic details through Warangal – Vanchanagiri approach road

naveenkumar.b
Line
naveenkumar.b
Line
Page 150: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.24

Approach Towards Volume (V) PCU’s/ hr

(Worst case) Capacity (C)

PCU’s/ hr Existing

V/C Level of service

Through Vanchanagiri Road

Existing 262

1200 0.22 “B” (Very Good)

Proposed 262 + 2102 = 2364

1200 1.97 “F” (Very Poor)

rates and Labour prices

Improvement in socio cultural environment of the study area

Improvement in transport, communication, health and educational services

Increase in employment due to increased business, trade and commerce and service sector

Negative impacts would be minimized by allocating the funds for environmental

management plan and CSR

Annually, a minimum of 1% profit from the MTP will be used for taking up CSR activities

From the project capital cost, around 1% will be allocated to environmental budget for

environmental management/environmental mitigation measures

The overall impact on the socio-economic environment will be beneficial.

Table 4.11 Proposed level of service

4.7.1 Mitigation measures

There is an addition of 2102 PCUs (Passenger Car Units) (worst case) in a day during general shift to

the existing traffic (348 PCU/hr) on site approach through Vanchanagiri road. The total PCUs in

future will be projected to 2364 PCUs in peak hour of the day and which is above the IRC-106-1990

Standards for 2 way 2 lane (Roads with no frontage access, no standing vehicles very little cross

traffic). The level of service of the proposed MTP as seen in Table 4.10, the level of service of the

existing road is deteriorating from ‘B’ to ‘F’. The access to the proposed MTP is through two roads

i.e. 7 m wide Ookal road and another 7 m wide road from Dharmaram ; both of which are connected

to Warangal- Narsampet road.

Hence, the existing level of service roads are very poor, it is recommended to development of the

road from 2 way/2 lane to 2 way/4 lane road for better movement of vehicles in the future. Then the

level of service will change from ‘F’ (very poor) to ‘C’ (Good).

4.8 Positive and negative socio-economic impacts in study area

The impacts of the proposed MTP, during operation on demography and socio economic conditions

would be both positive and negative some of them are as follows.

4.8.1 Positive impacts

Increase in employment opportunities and reduction in migrants to outside for employment

Growth in industrial sector of local area

Increase in consumer prices of indigenous produce and services, land prices, house rent

4.8.2 Negative impacts

Page 151: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.25

Out of the total project area of 1190.97 Ac. Out of which 33% of the land will be allotted for

greenbelt development all along the boundary, along the roads & block plantations (10% at TSIIC

MTP level & 23% Individual Industry level). All along the roads, on both sides, avenue trees will be

grown at the rate of 400 per every Km of road at a distance of 5 m.

The Industrial plotted area represents 63.63% (757.67 Ac) of the total land. Besides the common

greenbelt, avenue plantations and block plantations, every industry is required to develop industrial

greenbelts of 5 to 15 m width on all sides in an area of at least 33% of the individual site of the

industry. Thus the total area under Green buffer / greenbelt shall reach 33%. But the trees grown

within the premises of the industries have the potential to make the area green. Once the area is

occupied, the Mega Textile Park under consideration will have more than the stipulated green cover

and industrial greenbelts.

Total land for greenbelt

392.9

@400plants/acre will be planted in greenbelt.

Identified local species will be planted in 15 m along

site boundary and 2 m along the road.

Green belt area includes: - Common greenbelt area at park level-10 %( 119 ac.)

- At individual industrial level-23% [(273 acres)i.e:36% of the allotted land)]

In the proposed MTP, the natural vegetation of the construction site is going to be severely

damaged, however, in the present case only small portion of the land will be used for providing civil

infrastructure. None of the plants or animals of the proposed site (core area) belong to rare or

endangered or endemic or threatened (REET) categories or occur in the buffer zone. Hence, there

are no chances of losing any valuable biodiversity. When the project is fully operational, over a

period of time, lots of greenery will come up in the form of avenue trees, ornamentals, fruit trees

and lawns.

The details of the land allotted for greenbelt and landscaping works are given in Table 4.12.

Table 4.12 Greenbelt and landscaping details

Particulars Area (acre) Remarks

4.9 Greenbelt development

Most of the human activities generate pollution of one or other types and of different magnitudes,

to which all the organisms are exposed. More often than not, exposures to some pollution types are

considered unavoidable. Resistance of organisms helps them to overcome the hazards caused by

such exposures. The air pollution emitted by various sources settles on the ground and vegetation of

surrounding area. The plants interact with both gaseous and particulate pollutants and to great

extent absorb them and thus, remove them from the atmosphere. This pollution removal property

of the plants has been known for a long time. For many years tree planting has been promoted by

city planners for the purpose of reducing ground level air pollution.

4.9.1 Mitigation of impacts by greenbelt

Page 152: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.26

As a result, the loss of carbon sequestration capacity due to the loss of few plants could be

compensated. There is no plan to introduce new exotic species except those that have become

naturalized. Preference will be given to native and local trees. A list of trees proposed to be included

for the development of greenbelt and avenue plantation as per CPCB guidelines are given in Table

4.13.

Planting stocks are readily available from the forest department as well as from the local private

nurseries. All plants are locally adapted and the present site can support their growth with suitable

horticultural practices. Sufficient space, resources and manpower for development and maintenance

are provided in the plan.

Page 153: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.27

S.No Botanical Name Family Telugu English /common Habit Height

1 Acacia auriculiformis A.cunn Mimoseae

Australian Wattle Tree 16m

2 Adenanthera pavonina Linn Mimoseae Bandiguruvenda Red wood or Coral Tree 20m

3 Ailanthus excela Roxb Simarubaceae Peddamaanu Tree of Heaven Tree 20m

4 Albizia lebbeck Benth Mimoseae Dirisana,Sirisha The Siris tree Tree 20m

5 Albizia odoratissima Benth Mimoseae Chinduga Black siris Tree 18m

6 Albizia procera Benth Mimoseae Tellachinduga White siris Tree 20m

7 Alstona scholaris (Linn.) R.Br. Apocynaceae Marri chettu Devil tree Tree 15m

8 Anona squamosa Linn Anonaceae Seetaphalam Custard apple Small Tree 10m

9 Anona reticulata Linn Anonaceae Raamaphalamu Bullock's Heart Tree 10m

10 Anogeissus latifolia Wall Combretaceae Chirumaanu Axle wood, Button Tree Tree 11 Azadirachta indica A Juss Meliaceae Veepachettu Indian Lilac, Neem tree, Tree 20m

12 Balanties roxburghii Planch Balanitaceae Gara Desrt- Date Tree 9m

13 Barringtonia acutangula (L) Gaetn Barringtoniaceae Kanapachettu Indian Oak Tree 9-12m

14 Bauhinia varigata Linn Caesalpinaceae Devakanchanamu Budhist bauhinia, Mountain Ebony Tree 5m

15 Buchanania lanzan Spreng Anacarsdiceae Martichettu or Saara Almondette tree Tree 13m

16 Butea monosperma Lamk Fabaceae Mooduga Flame of the forest Tree 10m

17 Caesalpinia pulcherrima (L) Swartz. Cesalpinaceae Sankesula White gold mohur Tree 4m

18 Calophyllum inophyllum Linn Clusiaceae Ponnachettu Alexandrian laurel Tree 18m

19 Cassia fistula Linn Caesalpinaceae Reelachettu Golden showers, Indian laburnum Tree 12m

20 Cocos nucifera Linn Arecaceae Narikelamu Coconut tree Tree 10-15m

21 Cardia dichotoma Forst Cordiaceae Chinn - anakkeru Seb estan fruit tree Tree 10m

22 Dalbergia sisoo Roxb. Fabaceae Errasissoo Sissoo Tree 10m

23 Delonix regia (Boijer) Rafin. Caesalpinaceae Seemasantkesula Flame tree Tree 15m

24 Derris Indica (Lann.) Bennett. Fabaceae Gaanugachettu Pomgam- Oil tree, Indian Beech Tree 10m

25 Emblica officinalis Gaertn. Euphorbiaceae Amalakama, raatausirika Gooseberry, Emblic myrobalan Tree 5m

26 Erythrina variegata Linn Fabaceae Baadita, Maduga Indian coral tree Tree 10m

27 Ficus benghalensis Linn Moraceae Peddamarri Banyan tree Tree 20m

28 Ficus hispida (L.) F. Moraceae Vettiyati Kala- umbar Tree 10m

29 Ficus religosa Linn Moraceae Ashavathamu,Raavichettu Peepal tree Tree 20m

30 Holoptelia integrifolia Ulmaceae Thapass Indian Elm. Kanju Tree 31 Lagerstroemia speciosa Lythraceae Varagoogu Queen crape Myrtle Tree 10m

Table 4.13 List of plant identified for greenbelt & avenue plantation

Page 154: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.28

S.No Botanical Name Family Telugu English /common Habit Height

32 Mangifera indica Linn Anacardiaceae Mammidichettu, Maavi Mango tree Tree 15m

33 Mimusops elengi Sapotaceae Vakulamu Bakuli Tree 10m

34 Moringa oleifera Lamk. Moringaceae Mulaga Drumstick Tree, Horse Radish Tree Tree 10m

35 Phoenix sylvestris Arecaceae Peddaetta The Wild datepalm Tree 10m

36 Phyllanthus acidus Euphorbiaceae Sanagalu Country gooseberry Tree 8m

37 Pithecellobium ducle Mimosaceae Seema chinta Manila tamarind Tree 8m

38 Sesbania grandiflora Fabaceae Arise - Chetta. Swamp- pea Tree 10m

39 Soymida febrifuga Meliaceae Sumi, Sonidamaanu. Indian redwood Tree 15m

40 Syzygium cumini Myrtaceae Neereedu Black plum Tree 20m

41 Tamarinduss indica Caesapinaceae Chintachettu The Tamarind tree Tree 20m

42 Tectona grandis Verbenaceae Adaviteeku Teak Tree 20m

43 Terminalia arjuna Combretaceae Yerramaddi Arjun, Arjhan Tree 15m

44 Terminalia chebula Combretaceae Krarakkaaya Chebulic myrobalan Tree 15m

45 Zizyphus mauritiana Rhamnaceae Reegu Indian jujube Tree 10m

Odour controlling species

S.No Name Family Habit Height Growth Rate Suggested roles/areas

1 Eucalyptus citriodora hook Myrtaceae Tree 20m Quick growing Landscape and odour control

2 Ocimum sanctum Lamiaceae Shrub 0.6m Quick growing Landscape and odour control

3 Curcuma longa Zingiberaceae Shrub 1m Quick growing Landscape and odour control

4 Cymbopogon martini Poaceae Grass 1.5m Quick growing Soil stabilization and odour control

Page 155: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.29

S. No. Impacts

Phase Scope of impact F = Frequency L = Likelihood E = Extent D = Duration M = Magnitude

Effect & action

Mitigation suggested Construction Operation

1 Air quality & meteorology

a Dust generation during transportation of raw material

F = Regular L = Likely E = Local D = Short term M = Medium

Negative Direct

Covering of raw materials with Tarpaulin during transportation Water sprinkling for dust suppression Develop a transport management system for industries Surface access roads and on-site roads cover with aggregate materials, wherever appropriate Keep soil loads below the freeboard of the truck to minimize fugitive dust Minimize drop heights when loaders dump soil into trucks

b Moment of vehicles on unpaved roads

F =Regular L = Likely E = Local D = Short term M = Medium

Negative Direct

Water sprinkling for dust suppression Greenbelt development Inventory of vehicles and establishing pollution loads Establish and enforce speed limits to reduce airborne fugitive dust Cover dump trucks before traveling on public roads

C

Emissions from process plant/ industry operation

F =Regular L = Likely E = Local D = Long term M = Medium

Negative Direct

Determination of ventilation coefficient as a measure of assimilative potential Studying the industries for the pollutant control systems including its efficiency and reliability Establishment of pollution load from each point source Listing of all air pollution industries

Table 4.14 Overview of potential impacts due to proposed project

4.10 Overall view of impacts due to proposed project

Any developmental activity will have an impact on the surrounding environment. The possible impacts and the proposed mitigation measures during the

construction and operational phases of the proposed MTP are given in Table 4.14.

Page 156: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.30

S. No. Impacts

Phase Scope of impact F = Frequency L = Likelihood E = Extent D = Duration M = Magnitude

Effect & action

Mitigation suggested Construction Operation

2 Odour

A Emissions from specific process plant/ industry operation

F =Regular L = Likely E = Local D = Short term

Negative Indirect

Adopting odor controlling methods for specific process Development of Green belt with odor counteracts species

3 Noise

A Operation of construction equipment

F =Regular L = Likely E = Local D = Short term M = Medium

Negative Direct

Providing ear muffs to the constructing labors Development of wind breakers. All equipment should have sound-control devices no less effective than those provided on the original equipment. Motorized equipment used should be adequately muffled and maintained. Notify nearby residents in advance if blasting or other noisy activities are required during the construction period

B Transportation of equipment and raw materials

F =Regular L = Likely E = Local D = Short term M = Medium

Negative Direct

Sound proofing of admin buildings and sensitive areas. Development of Wind breakers. Restricting the movement of vehicles to specific time.

C Noise generation from process plant/ industry operation

F =Regular L = Likely E = Local D = Short term M = Medium

Negative Direct

Providing ear muffs to the workers Using less noise generating machines Development of wind breakers The noise levels in the workspace environment will be monitored periodically and if necessary corrective action will be taken. All necessary modern noise reducing gadgets will be attached like silencers, anti-vibration pads; closed room enclosures will be arranged.

Page 157: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.31

S. No. Impacts

Phase Scope of impact F = Frequency L = Likelihood E = Extent D = Duration M = Magnitude

Effect & action

Mitigation suggested Construction Operation

4 Water

A Turbidity and suspended solids levels will increase in near water bodies

F =Regular L = Likely E = Local D = Short term M = Medium

Negative Indirect

Fencing with proper material will be done around the site area to avoid movement of dust or soil to the surrounding areas.

B Wastewater generation

F =Regular L = Likely E = Local D = Short term M = Medium

Negative Direct

Wastewater generated during construction will be treated in mobile STP. During operational phase industrial and domestic effluents will be treated separately. Treated water will be reused either for green belt development or for industrial activities like floor washing. Homogenization of wastewater. Recycling of treated waters for beneficial uses or disposal through marine outfalls.

c Decrease in ground water levels

F =Regular L = Likely E = Local D = Short term M = Medium

Negative Direct

Ground water will be used as per the requirement Proper rain water harvesting structures will be proposed in the industrial park to recharge the ground water levels Treated water from the treatment facilities will be reused in the industrial park

6 Solid waste

A Waste generation during land clearing, construction and from workers activities

F =Regular L = Likely E = Local D = Short term M = Medium

Negative Direct

A possible reuse of treated waste for horticultural purposes will also explored and attempted. Construction waste will be reused within the site. Waste from the workers residence will be send to municipal bins or handover to authorized dealer.

B Waste generation from process F =Regular Negative Industries proposed in the site will generate only small

Page 158: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.32

S. No. Impacts

Phase Scope of impact F = Frequency L = Likelihood E = Extent D = Duration M = Magnitude

Effect & action

Mitigation suggested Construction Operation

specific industries, admin buildings and from residential colony

L = Likely E = Local D = Short term M = Medium

Direct quantity of hazardous waste which will be disposed as per the hazardous waste collection, handling and disposal rules at common facility. Solid waste generated from the admin buildings and residential colony will be segregated and handover to authorized disposal facility. The system should entail basic segregation (organic / inorganic in colored coded bins) of waste at source at different levels, collection and conveyance of segregated waste to nearest municipal bins or transfer stations or possibly to land fill Develop a waste management plan identifying anticipated solid and liquid waste streams and addressing determination, inspection and waste minimization procedures, storage locations, and waste-specific management and disposal requirements. Include a recycling strategy to be practiced by workers during all project phases

7 Traffic

A Increase in vehicular moment during material transport and workers/employees movement

F =Regular L = Likely E = Local D = Short term M = Medium

Negative Direct

Level of service of existing road will be improved by proposing service road adjacent to the existing road

8 Ecology & Biodiversity

A Habitat development

F =Regular L = Likely E = Local D = Short term

Positive Direct

No reserve forest is present in the study area Aesthetic value of the project area will be increased by developing parks with native species Instruct all survey and monitoring personnel on the

Page 159: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.33

S. No. Impacts

Phase Scope of impact F = Frequency L = Likelihood E = Extent D = Duration M = Magnitude

Effect & action

Mitigation suggested Construction Operation

M = Medium protection of ecological resources, laws pertaining to the collection and removal of these resources, and the purpose and necessity of protecting them Develop a habitat restoration management plan that identifies vegetation, soil stabilization, and erosion reduction measures, and requires that reclamation activities be implemented as soon as possible following facility construction activities Monitor the right-of-way (RoW), access roads, and ancillary facilities regularly for invasive nonnative plant species establishment, and initiate weed control measures immediately upon evidence of invasive species introduction or spread.

9 Socio-economics

a Employment

F =Regular L = Likely E = Local D = Short term M = Medium

Positive Direct

Preference will be given to the locals during construction and operational phases Necessary training will be given to the unemployed youth

B Infrastructure Development

F =Regular L = Likely E = Local D = Short term M = Medium

Positive Indirect

Infrastructure development will be expected in and around the proposed project which will increase the livelihood of people.

10 Land environment

A Site leveling and soil erosion

F =Regular L = Likely E = Local

Negative Direct

The excavated top soil during site leveling will be restored During site development necessary precautions will be taken, so that the runoff water from the site gets collected in

Page 160: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 4.34

S. No. Impacts

Phase Scope of impact F = Frequency L = Likelihood E = Extent D = Duration M = Magnitude

Effect & action

Mitigation suggested Construction Operation

D = Short term M = Medium

a working pit. Save topsoil which is removed during construction and use it to reclaim disturbed areas upon completion of construction activities thus maintaining the constant slope. Design runoff control features to minimize soil erosion. Construct drainage ditches only where necessary. Use appropriate structures at culvert outlets to prevent erosion. Inspect and maintain project facilities regularly, including access roads, to ensure erosion levels remain the same or less than current conditions.

Page 161: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.1

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Chapter – 5

Analysis of Alternatives – Site & Technology

5.1 Analysis of Alternative site locations

Telangana is one of the largest producers of long staple cotton with production or around 50 lakh

bales per annum. The state stood at third position in the country in cotton production during the

year 2014-15. The state is known for skilled textile workers but due to absence of industries, they

migrated to other states for livelihood. There are few spinning mills in the state which consume

about 20% of the cotton grown rest 80% is going to other states for spinning. Capacity utilization of

weaving industry in the state is negligible and there is not much processing capacity available in the

state. There are no further downstream facilities like processing and garmenting. To overcome all

this issues Telangana state government through TSIIC has proposed to develop a MTP in Warangal

district.

The Warangal district is major cotton producing district and trading center of the state, the region

has strong presence of textile clusters (Warangal Durries) and skilled manpower. The proposed

project envisages ploughing back economic benefits of the park to the local population by catering

to all activities in the textile value chain.

Telangana state government through TSIIC has proposed to develop a MTP in Warangal district and

identified two locations. These two sites were analyzed for setting up of the proposed MTP in

Warangal; they are Mupparam & Devanoor and Shayampet & Chintalapalli.

5.2 Introduction

In order to help the concerned authorities and the entrepreneurs, Ministry of Environment Forests &

Climate Change (MoEF&CC), Government of India (GOI) has framed certain broad guidelines for

siting an industry/proposed projects. The broad environmental guidelines recommended for siting of

industries/proposed project to ensure optimum use of natural and man-made resources in

sustainable manner with minimal depletion, degradation and or destruction of environment are

given in Table 5.1.

Table 5.1 site selection criteria – areas to be avoided

Land Procurement Sufficient land to meet the demand of greenbelt development, reuse

of treated water, storing of solid waste before final disposal

Coastal areas At least 500 m from high tide line

Estuaries At least 200 m away from the estuary boundaries

Flood plains of the Riverine

system

At least 500 m from flood plain or modified flood plain, or by flood

control systems

Transport /

communications system

At least 500 m from highway and railway line

Major settlements At least 25 km from the project growth boundary of the settlement (3

lakh Population)

Page 162: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.2

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ecologically and or

otherwise sensitive area

At least 25 km (Archaeological monuments, National parks &

Sanctuaries, Biosphere reserves, Hill resorts, Scenic areas, etc

Ecologically and / or otherwise sensitive areas include: 1) Religious & historic places, 2)

Archaeological monuments, 3) scenic areas, 4) Hills resorts, 5) Beach resorts 6) Health resorts 7)

Coastal areas rich in coral, mangroves, breeding grounds of specific species, 8) Estuaries rich in

mangroves, breeding ground of specific species, 9) Gulf areas, 10) Biosphere reserves, 11) National

parks and sanctuaries, 12) Natural lakes, swamps, 13) seismic zones, 14) Tribal settlements, 15)

Areas of scientific and geological interest, 16) Defence installations, specifically those of security

importance and sensitive to pollution 17) Border areas (International), 18) Airports, 19) Tiger

reserves / elephant reserves / turtle nestling grounds 20) Habitat for migratory birds 21) Lakes

/reservoirs / dams

In siting of the proposed MTP, care would be taken to minimise the adverse impact of the proposed

project on the immediate neighbourhood as well as distant places. Some of the natural life

sustaining systems and some specific land uses are sensitive and vulnerable to the outputs. With a

view to protect such sensitive systems, shall maintain the above mentioned guidelines.

5.3 Siting criteria

The Site suitability based on the industrial siting guidelines/criteria of the two locations are given in

Table 5.2.

Though both the sites are meeting the major requirements of the guidelines suggested by MoEF&CC,

the first site is very near to Dharmasagar water reservoir, which is the main portable water source

for Warangal City, as the project site is in higher elevation compared to the reservoir, so during rainy

seasons there are chances of rain water from the project sites entering the reservoir, hence this site

was not considered.

The second site of Shayampet and Chintalapalli was considered and most of the land in the area has

been acquired by the TSIIC following the existing norms of state and central government.

Page 163: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.3

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Table 5.2 Site suitability based on the industrial siting guidelines/criteria

S.No Siting Guideline

Site Suitability

Alternate site Proposed Site

Mupparam & Devanoor Shayampet & Chintalapalli

1 Ecologically sensitive

areas more than 5 Km

(preferably)

Dharmasagar water reservoir

(drinking water source for

Warangal City) has to be

conserved is around 0.5 km S

Warangal Fort 8.0km NW; 1000

Pillars Temple 14.0km NW;

Bhadrakali Temple 11.5km NW

2 Transport/communicati

on system: at least ½ Km

from highway and

railway

No highway/railway is located

within 500m from the site. High

tension power line is passing

through the site which needs to

be shifted with due care.

Chintalapalli railway station is

passing along the boundary line.

The major road Warangal-

Narsampet is 3.5 Km away from

the site towards N direction. No

high tension line is passing

through the site.

3 Coastal areas:

preferably ½ Km away

from high tide line (HTL)

Project site is well away from

coastal area.

Project site is well away from

coastal area.

4 Major Settlements No major settlement near

project site.

Sangem Mandal is adjacent to the

site boundary. Shayampet village

is 200 meter away from the site

boundary.

5 Critically polluted areas

are identified by

MoEF&CC

No critically polluted areas in

and around project site within

15 km radius.

No critically polluted areas in and

around project site within 15 km

radius.

6 No forest land shall be

converted into non-

forest activity

No forest land is involved for

project development

No forest land is involved for

project development

7 No prime agricultural

land shall be converted

into industrial site.

Majority land for project

development is government

barren land and private lands

are of partly single crop and

partly follow land.

The total land of proposed project

is rain fed agriculture private Patta

land.

8 Land acquired shall be

sufficiently large to

provide space for

appropriate green

cover.

Greenbelt will be provided as

per MOEFCC guidelines, along

the boundary, along the roads,

and open spaces

Greenbelt will be provided as per

MOEFCC guidelines, along the

boundary, along the roads, and

open spaces

Page 164: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.4

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Figure 5.1 Location Map of the Alternate Site

5.4 Site Selection

Overlooking the Environmental Factors during site selection at the project initiation stage will

generally increase the project costs due to the increase in the compliance to environmental

regulations and also will make the project vulnerable to opposition from the public. The selected site

is best suited for the proposed project.

Page 165: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.5

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Figure 5.2 Location Map of the Selected Site (Proposed Site)

5.5 Mitigation Measures

Appropriate mitigation measures adopted such as CETP/CSTP, Municipal and Hazardous Waste

management, Storm water management and rainwater water harvesting system, green belt

development etc. will mitigate the impacts on air, water and land environment.

5.5.1 Analysis of Alternatives of Access to the Project Site (Connectivity)

Existing access to the Project site from the Warangal Road - Narsampet Road is through

Mariyapuram and Ookal villages. There is also another alternate road that passes through

Shayampet and Vanchanagiri Villages. These existing road network and connectivity to the project

site can be utilised during construction stage for movement of vehicles. However, on inception of

the Project for transportation of goods, materials, man-power and for movement of vehicles during

operations phase this existing road network will be inadequate not insufficient. The existing road

network will need to be widened and strengthened at several places. This entails land acquisition

through the villages of Parvathagiri, Mariyapuram and Ookal and/or Shayampet and Vanchanagiri

which may cause social related issues and acquisition of property within built-up areas.

Further, there will need to be a separate RoB for access into the project site to cross the railway line.

Therefore, three options were studied for a dedicated connectivity (expressway ~ 150 ft wide

corridors) to the project site. These are detailed here

Page 166: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.6

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Option 1: Access from Gangadevipally and Dedicated RoB for the Project Site

In this option, a dedicated corridor will be developed for the project originating at Gangadevipally; a

village on the Warangal Narsampet Road. This option requires a new alignment to be developed

from the main road up till reaching the existing road after passing Ookal. In this case, the access

bypasses the Parvathagiri, Mariyapuram and Ookal Villages which is beneficial as social issues will be

minimised and also the corridor will be more or less straight in alignment without many kink/bends.

Approximately 2.4 km length of land will need to be acquired for the access road from

Gangadevipally till the existing road. The alignment mostly traverses through fields; there is a high

tension power line that goes overhead and a poultry farm nearby, however, the alignment will not

be affected by either of these. Land acquisition will be taken up for the new alignment of road which

will have a width of about 150 ft wide. The total area of land required to be acquired will be around

27.25 acres which considering Rs. 12 Lakhs per acres will cost around Rupees 3.27 Crores.

Once the new proposed alignment meets the existing road (which is already a 7 m wide road), it will

need to be strengthened and widened (to a 45 m wide road) up till the point where the project lands

start (approximately 850 m) and from there on the road will traverse within the project site.

The option also envisages a RoB over the railway line through the project site and onto the other

side into existing project lands. This will be very valuable and advantageous for the project as there

will be direct access and connectivity into the project site. This is the preferred option.

Figure 5.3: Option 1: Access from Gangadevipally and Dedicated RoB for the Project Site

Option 2: Access from Gangadevipally and RoB over LC 67

In this option, the possibility of an RoB within the project site is negated and the entry into the

project site on the other side of railway tracks will be through the RoB already proposed by the

railways at LC 67. In this case, also, the alignment from the main road remains the same and will

originate at Gangadevipally and traverse through the existing road as in Option 1, but the alignment

Page 167: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.7

EIA-EMP Report for Proposed Mega Textile Park at Warangal

within the project site will have two alternatives before exiting the and once again traversing

through existing roads to cross over the proposed RoB at LC 67 where there will be a request for the

RoB to turn into the project site.

Figure 5.4: Option 2: Access from Gangadevipally and Proposed RoB over LC 67 (Including two

Alternatives within Project Site)

Option 3: Access from Machapur, bypassing Chintalapalli and RoB over LC 67

In this option, the access to the project site will originate at a village called Machapur on the

Warangal – Narsampet Road. There is an existing 3.6 m road from Machapur to Chintalapalli which

will need to be strengthened and widened. The road connectivity will need to bypass Chintalapalli

town in order to reach the proposed RoB over LC 67 before turning into the project site. For this

bypass of approximately 1.7 km land acquisition will need to be carried out. The total area of land

required to be acquired will be around 19.30 acres which considering Rs. 12 Lakhs per acres will cost

around Rupees 2.32 Crores. This will be in addition to the strengthening and widening of

approximately 5.2 km of existing road from Machapur till the proposed new alignment.

This is not the preferred option as there are a few settlements on the road from Machapur till the

proposed new alignment which might entail acquiring of property. Also Machapur is an additional

distance of 1.7 km from Gangadevipally and 3.0 km from Ookal bus stop on the Warangal –

Narsampet Road. The entire length of connectivity from Machapur is also a whole additional km as

compared to the preferred option 1.

Page 168: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.8

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Figure 5.5: Option 3: Access from Machapur, Bypassing Chintalapalli and RoB over LC 67

5.6 Alternative Energy

Solar energy is proposed as an alternative energy. Solar street lights are proposed to be used and the

member industries would be asked to install solar water heaters to feed pre heat water to process.

Street lights (7m high) with a set of solar panels, battery backup (2 days) and 2x20 W bulbs will be

installed every 20m distance on both sides of 45m, 30m and 18m wide roads in the industrial area.

This will help in saving the electric energy. However, solar energy can be utilized only during sunny

days.

5.7 Assessment of Various Treatment Technologies for Textile Dyeing Effluent

An assessment and comparison of the types of treatment technologies for CETP – ZLD has been done

in terms of their capital and operating cost, energy efficiency, solid waste generation & management

and resource recovery and the same has been elaborated in Table 5.3 below.

From the assessment of the above technologies, “Treated Brine reuse based ZLD” stands out above

all due to its lower Capex and opex, specific energy consumption, sludge and waste salt generation.

In addition, the technology enables higher recovery of water and salt.

The basis of shortlisting the appropriate technology is given below:

Basis of selection and recommendation of technology (Brine Reuse Technology), based on the

detailed comparison made on various technology configuration which are being currently employed

in the CETPs for treatment of textile effluent to achieve the ZLD, Brine reuse technology has been

selected and recommended to implement in the 20.6 MLD CETP. The following are the reasons for

selection of this technology:

Page 169: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.9

EIA-EMP Report for Proposed Mega Textile Park at Warangal

i. Brine reuse technology is successfully operational in TWIC developed CETPs in Tirupur.

ii. Less dependency on thermal evaporation, resulting in significant reduction in the overall O&M cost of the CETP.

iii. Maximum recovery of water (96-97%) and salt (70%-80%).

iv. Low waste salt generation. Further research is on further salt recovery from the waste salt.

v. Purity of salt in the treated brine is far better that Nano Filtration (NF) based brine, where additional salt must be added for reuse in the dyeing process. Also, unlike NF, frequent replacement membranes are not required.

vi. Lower bio sludge generation (due to usage of low loaded extended aeration type reactor with low F/M ratio of 0.06) when compared to conventional biological treatment (Low HRT and F/M 0.15). Moreover, this bio sludge can be used as fuel in the boiler. Recently, field studies have been completed in the presence of IIT, Madras, who has also recommended this option in their report.

vii. Due to implementation of UF, Ion Exchange (IX) resins for colour and hardness removal, there has been a significant improvement in the quality of the liquid brine and this increases the life of RO membranes as well. These unit processes (UF, IX resins) are already in successful operation in the TWIC CETPs.

viii. Lime-Soda softening (LSS) will be used as a side stream treatment for removal of hardness from the regenerated waste, thereby resulting in lower sludge generation. This chemical /lime sludge will have significant concentration of lime and hence shall be utilized in the cement industries for co-processing. Most of the CETPs had implemented this LSS treatment as a main stream treatment. Due to this, enormous quantity of sludge is being generated, which requires sizable investment for disposal. Presently, most of the CETPs have entered into an agreement with local cement industries for co-processing of this sludge.

ix. High Pressure Plate & Tube RO (HPPTRO) has been considered in the proposed treatment scheme for concentrating the RO reject and reducing the volume of brine going to the downstream MEE section, thereby resulting in low Capex & Opex. Also, with this, dependency on thermal energy will be avoided considerably.

x. Agitated Thin Film Dryer (ATFD) has also been considered in the proposed scheme to evaporate the mother liquor instead of discharge the same in to the solar pans. Due to installation of ATFD, the dyeing units can continue operation during the rainy season as well or otherwise the overflowing solar pans would contaminate the surface / ground water. Hence solar pans are not considered in the proposed scheme.

xi. After considering the recovery cost of water & salt from the ZLD and savings from the CPP in terms of power and steam, 90% of O&M cost are recoverable.

xii. Fly ash and bottom ash generated from the CPP can be used for fly ash based brick manufacturing.

Page 170: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.10

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Table 5.3 Assessment of various treatment technology options for ZLD CETP

Description Segregation of High & Low

TDS waste stream based ZLD MBR based ZLD

Thermal Evaporation for salt crystallization based

ZLD

NF brine reuse based ZLD

Treated brine reuse based ZLD

Unit Operations

1. Separate Collection & Conveyance system for dye bath and wash water.

1. Collection & Conveyance system

1. Collection & Conveyance system

1. Collection & Conveyance system.

1. Collection & Conveyance system

2. Separate Equalisation Tank for dye bath & wash water

2. Equalisation Tank 2. Equalisation Tank 2. Equalisation Tank 2. Storage & Homogenization Tank

3. Chemical treatment

3. Biological Treatment - MBR

3. Biological Treatment 3. Biological Treatment.

3. Biological Treatment.

4. Biological Treatment for Wash water stream

4. Tertiary Filtration System comprises MGF& UF.

4. Tertiary Filtration system comprises MGF& UF.

4. Tertiary Filtration system comprises MGF & UF.

4. Tertiary Filtration system comprises Quartz filter, UF, Colour removal resin filter & Softener filters.

5. Tertiary Filtration system comprises MGF& UF.

5. Reverse Osmosis 5. Reverse Osmosis 5. Reverse Osmosis 5. Side stream Lime-Soda Softening

6. Reverse Osmosis 6. Reject Management System including MVR, Falling Film Evaporator, Chiller & Forced Circulation Evaporator

6. Reject Management System including MVR, Falling Film Evaporator, Chiller & Forced circulation Evaporator

6. Lime-Soda Softening system for RO Reject.

6. Reverse Osmosis

7. Reject Management System including for evaporation of RO reject from wash water stream and Dye bath stream including Falling Film Evaporator & Forced

7. Reject Management System including MVR, Falling Film Evaporator & Forced circulation

7. High Pressure Plate & Tube Reverse Osmosis (HPPTRO).

Page 171: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.11

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Description Segregation of High & Low

TDS waste stream based ZLD MBR based ZLD

Thermal Evaporation for salt crystallization based

ZLD

NF brine reuse based ZLD

Treated brine reuse based ZLD

circulation Evaporator Evaporator

8. Management System including Falling Film Evaporator, Adiabatic chiller, Forced circulation Evaporator and Agitated thin Film Dryer.

Capex High High High High Medium

Opex High Medium High High Low

Specific Energy

High Medium High Medium Low

Sludge generation

High Low High High Low

Waste salt generation

High High High High Low

Water recovery

Low High High High High

Recovery of salts

Nil Low Low Low High

Page 172: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.12

EIA-EMP Report for Proposed Mega Textile Park at Warangal

5.8 Advanced Treatment Technology options for ZLD

In the already implemented ZLD CETPs although it has state-of-art technologies to treat the effluent

and recovery of water & salt, there was some critical issues such as reduction of colour and COD,

High O & M Cost and waste salt & sludge generation. To overcome these issues, TWIC had been

conducting some pilots for advanced technologies such as Electro Oxidation for colour removal (EO),

High Pressure Plate and Tube RO (HPTTR) and Agitated Thin Film Dryer (ATFD). In the proposed

treatment scheme, in addition to the existing successfully operating technologies, the following

three advanced treatment technology options are proposed).

In the proposed treatment scheme, in addition to the existing successfully operating technologies,

the following three advanced treatment technology options are proposed.

5.8.1 Electro oxidation system for color removal

i. Gas chlorination system and colour removal resin are playing significant role in the removal

of colour and COD respectively. However handling of gas chlorination system is a tough task

to the operators, because of some safety issues. Similarly operation of colour removal resin

is expensive. To replace these technologies, An Electro oxidation system has been included

in the treatment scheme. COD and colour reduction shall be reduced up to 51% and 90%

respectively. Apart from this, there is side stream waste generation as in colour removal

resins.

ii. Key benefits of using this technology include:

- Reduction in recalcitrant COD

- No sludge generation

- No waste liquid generation as in colour removal resin

- No waste salt generation as in colour removal resin

- It can be easily operated & there is no safety issues as exist in operation gas chlorine

system.

- Due to reduction in COD, UF and RO feed quality will be increased and which resulting

increased membranes life by eliminating the frequent cleaning.

5.8.2 High Pressure Plate & Tube RO (HPPTRO) Due to several mechanical issues in the MVR system which is currently used in most of the CETPs, a

High Pressure RO system has been incorporated in the proposed scheme to reduce the brine volume

to MEE. In both the system, final reject TDS would be 100 - 110 gpl and feed TDS in range of 55 - 60

gpl. Proposed High Pressure System would comprises cartridge filter, Forwarding pump, 90 bar high

bride RO system and 120 bar Bolt on RO system. HPRO system will be installed as two modules.

HPPTRO system is designed to handle both RO reject stream. These two streams will be operated as

a batch mode to avoid mixing of Sulphate and chloride stream, because of chloride to Sulphate ratio

will be changed and it would affect the sodium Sulphate recovery and yield in the adiabatic chiller. A

field scale pilot trials had been carried to assess the performance and viability of the system and

found that pilot result was good in terms of performance and Capex & Opex.

Page 173: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.13

EIA-EMP Report for Proposed Mega Textile Park at Warangal

5.8.3 Replacement of Solar pans with ATFD to avoid overflow of pans

i. ATFD system plays a significant role in the concentration and recovery of mixed waste salt.

Most of the CETP had constructed solar pans as per TNCPB norms, but during rainy season

these solar pans are getting overflowing. To avoid this situation, a detailed pilot study had

been conducted in few CETPs and found that pilot results were good. Based on this ATFD

system has been considered in the proposed treatment scheme.

ii. Key benefits/advantages of Agitated Thin Film Dryer (ATFD)

- Reduced time for Evaporation when compared to solar evaporation pans

- Solar pans can be gradually eliminated after installation of ATFD.

- Condensate with reusable quality can be recovered from the ATFD system and the same can be reused in the dyeing process.

- Manual handling of waste salt can be totally eliminated and minimum manpower is sufficient to bag the salt, instead of engaging huge manpower for cleaning of waste salt from the solar pans.

- During rainy seasons overflowing of solar pans can be avoided by operating ATFD system and waste salt can be recovered as dry salt and shall be bagged & stored in yard. Hence, Dyeing units and CETPs shall be operated continuously without any stoppage during rainy seasons.

- Lower foot print area for installation as compared with solar pans.

- Ground water contamination by seepage/leakages from the solar can be avoided by elimination the solar pans.

5.8.4 Advanced technologies for textile effluent treatment

Conventional Multiple Effect Evaporator system is consuming high amount of thermal and electrical

energy to evaporate the RO brine. To reduce the operating cost, incurred in the reject management

system, some of advanced technologies such as Forward Osmosis (FO), Waste heat Evaporator

(WHE), VSEP shall be used. Detailed pilot studies needs to be done for the technologies such as FO &

VSEP to assess the process economics and suitability for textile effluent management. Waste Heat

Evaporator (WHE), pilot trials had been conducted with various feed streams and TDS and found that

the performance of WHE was good in terms of O&M cost and reduced dependency on thermal

energy.

5.9 Resources recovery from the ZLD CETP

RO system and MEE with salt recovery plays a significant role in recovering of low TDS water and

highly pure sodium Sulphate salt (98 - 99%) respectively from the dyeing effluent. Even though ZLD

operating cost is much higher than the conventional treatment (for discharge of treated effluents), it

is justified through efficient water & salt recovery & therefore 60-80% of the O&M cost is recovered.

The products recovered and their quality and quantity are provided in the below table.

Page 174: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 5.14

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Table 5.4 Quality of recovery products

Products Quality Quantity

Recovered Water Colourless, 150-300 mg/l TDS with Nil Hardness

90 -95% v/v

Treated Brine 150 -160 gpl 50-60% of the total salt load in the effluent

Glauber’s salt Na2SO4.10H2O. 98-98.5% Purity, Nil Hardness, white Crystalline salt

10-20% of salt load

Mixed salt Chloride - 50%, Sulphate – 25%, Bicarbonates – 15%, COD – 6%, Total hardness – 0.13%, others – 4.87%

20 – 25% of salt load

Page 175: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 6.1

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Chapter – 6

Environmental Monitoring Programme

6.1 Introduction

Environmental Monitoring Programme is an important component during construction and

operational stages of the project. The main objective of environmental monitoring program is to

check the efficacy of the Environmental Management Plan (EMP) and implementation and take

corrective actions. A well-defined environmental monitoring program would be followed for the

proposed development of MTP. It would be ensured that trained and qualified staff supervises the

monitoring and sampling of ambient air, DG set & Boiler stack gases, common sewage and

trade/Industrial effluents, noise, etc. to see that prescribed standards lay down are obtained.

The monitoring program will be done in two phases

Constructional phase

Operational phase

The project management should always go for a rational approach with regards to environmental

monitoring. This includes judicious decision making in consultation with institutional stakeholders

viz, state pollution control board, industrial units, public, etc.

The following are the main objectives of the environmental monitoring program

Provides information for documentation of monitoring of mitigation measures and impacts.

Tool for the statutory authority of unanticipated adverse impacts or sudden changes in the environmental condition due to the proposed project.

Provides information that could be used for evaluating the effectiveness of implemented

mitigation measures.

Provides information that could be used to verify predicted impacts and thus validate impact prediction techniques.

The efficacy of the mitigation measures being followed during construction and operational phases can be assessed and the measures can be revised, made more stringent and reinforced based on the monitoring results.

Environmental Monitoring can also serve a basic component of a periodic environmental regulatory auditing program for the proposed project.

The programme as detailed in the environmental monitoring programme for construction as well as

operation phases shall be implemented by the MTP officials / individual units. Besides the

monitoring, the compliances to all EC, CFE / CFO conditions shall be monitored and reported

periodically. The likely significant impacts and mitigation measures will be also be monitored.

Page 176: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 6.2

Table 6.1 Environmental Monitoring during Constructional Phase

Potential

Impact

Detailed actions to be

followed as per EMP

Parameters for

Monitoring

Frequency of

Monitoring

Air Emissions All equipments are operated

within specified design

parameters.

Random checks of

equipment logs/ manuals

Quarterly

Vehicle trips to be minimized

to the extent possible.

Vehicle logs Quarterly

Any dry, dusty materials stored

in sealed containers are

prevented from blowing.

Stockpiles or open

containers of dusty

materials.

Quarterly

Compaction of soil during

various construction activities

Construction logs Quarterly

Maintenance of DG set

emissions to meet stipulated

standards

Gaseous emissions (SO2,

HC, CO, NOx)

Quarterly

Ambient air quality within the

premises of the proposed

Industrial Area to be

monitored.

Gaseous emissions

Particulate matter, SO2,

NOx and CO

As per CPCB/ SPCB

requirement

Noise List of all noise generating

machinery onsite along with

age to be prepared.

Equipment logs, noise

reading

Regular Monitoring

Night working is to be

minimized.

Working hour records Quarterly

Generation of vehicular noise Maintenance of records

of vehicles

Quarterly

Implement good working

practices (equipment selection

and siting) to minimize noise

and also reduce its impacts on

human health (ear muffs, safe

distances, and enclosures).

Site working practices

records, noise reading

Quarterly

No machinery running when

6.1.1 Construction Phase

The proposed Industrial Area envisage the setting up of industries related to textile manufacturing

and its ancillary units along with common facilities for treatment of wastewater, solid waste,

common utilities. The constructional activities involve clearing of vegetation, mobilisation of

constructional material and equipment. However, mobilisation of constructional material &

equipment for excavation of earth etc. will be involved. The constructional activities are expected to

last for a short period. The generic environmental measures that need to be undertaken during

construction stage are given in the following Table 6.1.

Page 177: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 6.3

Potential

Impact

Detailed actions to be

followed as per EMP

Parameters for

Monitoring

Frequency of

Monitoring

not required.

Acoustic mufflers / enclosures

to be provided in large engines

Mufflers / enclosures

shall be in place.

Prior to use of

equipment.

Noise to be monitored within

the plant premises.

Instant Noise levels will

be recorded.

As per CPCB/SPCB

requirement

Noise level will not exceed the

permissible limit both during

day & night times.

All equipments operated within

specified design parameters.

Random checks of

equipment logs/ manuals

Quarterly

Vehicle trips to be minimized

to the extent possible

Vehicle logs Quarterly

Wastewater

Discharge

No direct discharge of

wastewater to be made to

surface water, groundwater or

soil.

No discharge hoses shall

be in vicinity of

watercourses.

Quarterly

The discharge point would be

selected properly and sampling

and analysis would be

undertaken prior to discharge

Discharge norms for

effluents as given in

Permits

Quarterly

Take care in disposal of

wastewater generated such

that soil and groundwater

resources are protected.

Discharge norms for

effluents as given in

permits

Soil Erosion Minimize area extent of site

clearance, by staying within the

defined boundaries

Site boundaries not

extended / breached as

per plan document.

Quarterly

Protect topsoil stockpile Effective cover in place. Quarterly

Drainage and

effluent

Management

Ensure drainage system and

specific design measures are

working effectively.

The design to incorporate

existing drainage pattern and

avoid disturbing the same.

Visual inspection of

drainage and records

thereof

Quarterly

Waste

Management

Implement waste management

plan that identifies and

characterizes every waste

arising associated with

proposed activities and which

identifies the procedures for

collection, handling & disposal

Comprehensive Waste

Management Plan should

be in place and available

for inspection on-site.

Compliance with MSW

Rules, 2000 and

Hazardous Wastes

Quarterly

Page 178: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 6.4

Potential

Impact

Detailed actions to be

followed as per EMP

Parameters for

Monitoring

Frequency of

Monitoring

of each waste arising. (Management, Handling

and Trans boundary

movement) Rules, 2008

& subsequent

amendments

Non-routine

events and

accidental

releases

Plan will be drawn, considering

likely emergencies and steps

required to prevent / limit

consequences.

Mock drills and records

of the same

Quarterly

Health Employees and migrant labour

health check ups

All relevant parameters Regular checkups

6.1.2 Operational Phase

During operational stage of proposed MTP, continuous air emissions from point source and non-

point sources (Particulate Matter, SO2, and NOX emissions), noise, solid waste generation and

wastewater generation are expected. The following attributes which merit regular monitoring based

on the environmental setting and nature of project activities are listed below:

Source emissions and ambient air quality

Groundwater Levels and ground water quality

Water and wastewater quality (water quality, effluent & sewage quality etc.)

Solid waste characterisation (HW/MSW/CETP/CSTP sludge)

Soil quality

Noise levels in and around the proposed Industrial Area (equipment and machinery noise

levels, occupational exposures and ambient noise levels)

Ecological preservation and afforestation.

The generic environmental measures that need to be undertaken during operational stage are given in

the following Table 6.2.

Table 6.2 Environmental Monitoring during Operational Phase

S. No Potential

Impact Action to be Followed

Parameters for Monitoring

Frequency of Monitoring

1. Air Emissions Air emissions from DG sets and Boilers

Gaseous emissions (Particulate Emissions)

As per CPCB/ SPCB requirement

AAQ within the project premises and nearby habitations to be monitored.

PM10, PM2.5, SO2 & NOx

All vehicles to be PUC certificate.

Vehicle logs to be maintained

Once in six months

Meteorological data Wind speed, direction, temp., relative humidity

As per CPCB/ SPCB requirement

Page 179: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 6.5

S. No Potential

Impact Action to be Followed

Parameters for Monitoring

Frequency of Monitoring

and rainfall.

2. Noise Noise generated from operation of common utility machinery to be monitored

Spot Noise Level recording;

Quarterly

3. Wastewater Discharge (CETP/CSTP)

Compliance to wastewater discharge standards

pH, TSS, TDS, BOD, COD, Oil& grease

Periodic or As per CPCB/ SPCB requirement

4. Solid waste/ Hazardous waste

Check compliance to HWM rules

Quality & quantity monitoring

Periodical

5. Ground Water Quality and Water Levels

Monitoring ground water quality, around the proposed project site and levels

Comprehensive monitoring as per IS 10500 Groundwater level BGL

Quarterly

6. Flora and fauna

Vegetation, greenbelt / green cover development

No. of plants, species Once in a year

7. Soil quality Checking & Maintenance of good soil quality around the proposed project

Physico-chemical parameters and metals.

Once in a year

8. Health Employees and migrant labour health check ups of individual industries

All relevant parameters including HIV

Regular checkups

6.2 Environmental laboratory equipment

The proposed MTP may maintain an in-house environmental laboratory or may use the services of

external (third party) laboratory for the routine monitoring/sampling of Air, Water, Soil,

Meteorology, and Noise. The industrial units present in MTP may utilize the Services of in-house

environmental laboratory and/or external laboratories as third party monitoring/sampling /analysis

for their compliance. For in house laboratory the minimum equipment’s required for monitoring /

sampling /analysis are listed in Table 6.3.

Table 6.3 List of Equipment Proposed for Environmental Laboratory

Name of the Equipment No of Instruments

Manual or Automatic Weather Station, which can record wind speed, wind

direction Temperature, Relative Humidity

2

Gaseous stack monitoring kit for SO2, NOx, Flue gas volume, Temperature and

conventional monitoring kit for particulates

3

Air samplers with PM<10µm & PM<2.5µm provision 10

Portable Flue gas Combustion Analyser 2

Portable Noise level meter (Dosimeter) 4

Portable Wastewater Analysis Kit 3

Electronic Micro Balance with minimum 0.01mg 2

Page 180: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 6.6

6.3 Organizational Setup of Environmental Management

To oversee the implementation of the environmental management plan within the MTP an

environmental management cell will be established, which will be headed by and EHS manager and

will be supported by other staff members. The organizational structure of the environmental

management cell is given in Figure 6.1.

6.4 Reporting Schedules of the Monitoring Data

The environmental management cell shall co-ordinate all monitoring programs at site and data thus

generated shall be regularly furnished to the State regulatory agencies. The frequency of reporting

shall be done on the basis of statutory requirements to Telangana State PCB officials and to Regional

office of MoEF&CC. The Environmental Audit reports shall be prepared for the entire year of

operations and shall be submitted to regulatory authorities.

6.5 Wastewater Treatment and Disposal - Monitoring Mechanism

The proposed CETP shall be developed in phased manner. Once first phase reaches about 70% of the

capacity, the next phase shall be proposed. The treatment process proposed consists of a biological

treatment. Effluent shall be processed using extended aeration technology with aeration tanks and

secondary clarifiers with sludge handling and processing units. The treated effluents shall be used for

developing greenbelt and reuse for industrial activities in MTP.

For treatment of domestic sewage from individual units a Common STP (Phased manner) shall be

provided at strategic location in MTP to collect, sort & recycling waste to make it convenient for

residents, workers & companies to support such green efforts. The schematic diagram of collection

and treatment of industrial wastewater is given as Figure 6.2.

6.5.1 Real time Monitoring Mechanism at Industry level

A real – time monitoring frame work (Centralized SCADA through GPRS/web connectivity) is

proposed to monitor the following.

Monitoring the raw effluent discharge from member units to CETP. Here the flow through

Electromagnetic Flow Meters (EMF) and the TDS are monitored on a real-time basis.

Recovered water from the CETP to the member units (Flow through EMF)

Chief Engineer

Manager

GM- EMP

Environmental Engineer

Environmental Engineer

Zonal Manager

Figure 6.1 Organizational Set-ups for Environmental Management Cell

Page 181: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 6.7

Treated brine solution conveyance from CETP to the member units

Stage-wise EMF in the CETP – after Pre-treatment, Reverse Osmosis and Evaporator system.

The schematic diagram of web based on-line Monitoring system for member units of CETP in MTP

are given in Figure 6.3.

6.5.2 Monitoring at CETP Level

At CETP level regular monitoring will be carried out at inlet and outlet points at strategic treatment

units for important parameters. The following are some of them.

Monitoring point at inlet of CETP is suggested to ensure the compliance of CETP inlet

characteristics.

CETP shall treat the wastewater to meet the recycle and reuse standard characteristics in the

system.

CETP will have a holding tank with 3 compartments for 3 days storage capacity of treated

wastewater.

Holding tank will be having online monitoring facility for parameters like pH, TDS, COD, TOC

and results will be displayed at respective CETP.

The parameters such as heavy metals shall be monitored by manual sampling and results shall

be recorded by EMP cell.

The lock and key operation of the valve at CETP holding tank will be totally controlled by EMP

Cell.

Each phase of CETP shall maintain a log sheet of inlet/outlet wastewater quality/quantity on

daily basis and same shall be maintained for future inspections by SPCB and IE/SEZ EMP cell.

6.5.3 Environmental Monitoring by Industry Member

The environmental monitoring shall be carried out by each unit industry as applicable within their

industry premises. The members units should not only limit the environmental monitoring as stated,

environmental monitoring programme in terms of parameters, location and frequency shall be

formulated as per the stipulations laid by TSPCB/MoEF&CC in their respective EC, CFE/CFO.

Page 182: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 6.8

Figure 6.2 Collection and Conveyance system of CETP

Figure 6.3 Web based on-line Monitoring system for member units of Textiles CETP

Collection and Conveyance System of a typical ZLD based Textile CETP

Raw effluent

Brine Solution

Member Dyeing Units

Common

Effluent Treatment

Plant

SCADA / GPRSSYSYTEM

HDPE

DI with cement mortar coatingM

Electromagnetic Flow Meters

M

MRecovered Water

DI with cement mortar coating

Treated Brine line

DI with cement mortar coating

Recovered Water

DI with cement mortar coating

Member Units

Common Effluent Treatment Plant

TDS: Conductivity meter

Common

Chrome

Recovery

System

NTU: Turbidity Meter Centralized

SCADA through

GPRS /Web connectivity for

online monitoring

EMF: Electromagnetic Flow Meters

HDPE pipe

ORP: Oxidation Reduction Potential / Chlorine Meter

LT: Tank Level Transmitter

PT: Pressure Transmitter

DO: Dissolved Oxygen Meter

TDS

EMF

EMF

EMF

Raw effluent

CETP MEMBER UNIT

TDS

NTU

ORP

DO

PT

LT

EMF

Electromagnetic flow meters in each stage of Pre treatment, Reverse Osmosis & Evaporator system

Page 183: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 6.9

6.6 Compliance reports

As a part of environmental monitoring programme, following compliance reports shall submitted to

TSPCB and regional office of MoEF&CC.

Half yearly compliance reports in respect of the stipulated prior environmental clearance terms and conditions on June 01 and December 01 of every calendar year.

Environmental statement for the financial year ending March 31 to TSPCB on or before September 30 every year.

Format for maintaining records of hazardous waste if any in Form-3 as per Hazardous Waste (Management, Handling and Transboundary movement) Rules, 2008 and subsequent amendments thereof.

Format for maintaining hazardous waste imported and exported in Form-10 as per Hazardous Waste (Management, Handling and Transboundary movement) Rules, 2008 and subsequent amendments thereof.

Safety data sheet for hazardous chemicals shall be maintained as per schedule 9 of MSIHC rules, 1989 (subsequent amendments thereof).

Format for maintaining notification of major accident in schedule 6 as per MISHC rules, 1989 (subsequent amendments thereof).

Water Cess returns in Form 1 as per Rule 4 (1) of Water (Prevention & Control of Pollution) Cess Rules 1978 on or before the 5th of every calendar month.

6.7 Plantation monitoring programme

Environmental Management cell will monitor the following activities of greenbelt and landscape

development:

Development of nursery

Treatment and sowing of seeds

Watering

Transport of seedlings

Planting of seedlings

Fencing of plantation area

Weeding and soil working

Pruning (trimming of plant)

Replacement/ Inter planting

Watch and ward of plantation

During operation phase periodic monitoring of plantation growth, manuring, watering, pruning, and

replacement will be performed in order to properly maintain vegetation, greenbelt, landscape and

green cover. It is suggested to plant shrubs or plants with 1 or 2 m height in utility corridor to avoid

bird nesting/resting on the plants.

6.8 On-site mock drills requirements On-site mock drills are very important as it helps employees to be aware of the safety procedures

and how to react during the time of crisis. Conducting mock drills at regular intervals enhances

preparedness and checks the viability of environmental/ disaster management plan. Mock drills are

essential for the following reasons:

Page 184: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 6.10

Helps in revising/improving the environmental/disaster management plan

Helps to evaluate whether the responsible officials are trained efficiently for the unforeseen

event.

Helps in evaluating whether the emergency equipment are being maintained at project

premises.

To ensure efficient environmental / disaster management, EHS department/ EMP cell shall conduct

periodic on-site mock drills in case of occurrence of the following activities:

Fire; Natural calamities (cyclones, floods, earthquakes)

Power break down

Oil spill

Bomb threats; War alerts/terrorist attacks

Mock drills should also involve fire department, police, municipal authorities, hospitals and other

department/ agencies that are mandated to provide emergency support. Documenting the outcome

of mock drills is an important aspect as this helps in revising the existing plan more efficiently.

6.9 Budget estimates

In order to comply with the environmental protection measures as suggested in the above sections,

the management has made a budgetary provision for Environmental Protection and Safety measures

in capital cost of the proposed MTP.

S.No Project Cost Amount (Rs. in crores)

1 Roads 91.68

2 Storm water drain 27.16

3 Water supply 78.07

4 Sewage system 39.41

5 Electrical Infrastructure 71.83

6 Landscaping 8.00

7 Common Infrastructure 55.80

Total Project Cost 371.95

EMP budget: The cost for EMP budget would be 5% of the Total Project Cost.

Page 185: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.1

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Chapter 7 Additional Studies

7.1 Safety Management Plan

During construction, erection, testing, commissioning, operation and maintenance of Mega Textile Park

the important basic requirement are the manpower, materials and machines. The textiles sector

generally has issues related to occupational health and safety. Hence management proposes to take

steps to minimize the impacts from the proposed development of MTP to ensure appropriate

occupational health and safety including fire plans by adapting occupational health & safety measures

as per standard procedures & local guidelines.

Over-exertion, ergonomic injuries and illnesses caused due to repetitive motion and manual

handling are among the most common during construction. The proper steps for their prevention

and control include:

Training workers regarding the lifting of materials & handling, placement of weight limits, planning of work, selection of tools and implementation of administrative controls in the site for the development.

Implementation of good house-keeping practices, such placing loose construction materials or demolition debris in identified areas away from foot paths.

A fall protection plan will be implemented for the persons who will work in heights and also depending on the nature and aspects of the fall hazard.

Appropriate techniques and measures will be taken for the prevention and control of hazards caused by the objects and moving machinery.

Suitable dust suppression techniques will be implemented like water spraying to minimize dust from vehicle movements and also proper Personal Protective Equipment (PPE) used at excessive levels.

7.1.1 Safety Policy

The employee’s safety policy includes the following:

Contact their immediate supervisors according to individual department policies. What happened will be sorted out through the accident reporting and investigation process.

The supervisor or employee should be responsible for the following to be completed:

Obtain names, addresses and phone numbers (work and home) of any witnesses. Interview the witnesses and prepare a report; including statements from the witnesses. The report should include any suggestions to prevent a similar accident or incident from occurring in the future.

Page 186: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.2

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Take photographs of the property damage or defect. A sufficient number of photos should be taken to fully describe the damage to a person who has not been at the scene.

Prepare a report of the incident with all necessary information. The reports should be prepared to reflect the seriousness of the incident.

Fill appropriate forms for future use.

If individual department procedures include all of the information required by this policy, that document can be utilized to fulfill these requirements.

This policy is in addition to a workers compensation reporting requirements.

Appropriate risk management strategies will be implemented to protect the community from

physical, chemical or other hazards associated with the site through a combination of Institutional

and administrative controls by adopting the community health and safety measures as per Standard

procedures & local guidelines provided for community health and safety.

To control communicable and vector-borne diseases attributable to the proposed site; which are not

a potentially serious health threat to project personnel and residents of local communities. The

investigation facilities are available to monitor all the employees for the occupational health

diseases expected in the MTP premises and also maintaining periodical check-up of all workers from

a certified industrial & occupational health physician. The MTP will maintain the first aid box with

sufficient medicines to face any emergency in the industrial premises.

The problem of occupational health in the operation and maintenance phase of member industries is

due to noise hearing losses. The personal protective equipment’s will be provided for workers which are

appropriate to their working environment given below:

Safety Helmet

Face shield with replacement acrylic vision

Zero power plain goggles with cut type filters on both ends

Welders equipment for eye and face protection

Ear muffs

Canister gas mask

Self-contained breathing apparatus

Leather apron

Full body Safety harness

Leather hand gloves

Acid/Alkali proof rubberized hand gloves

Electrically tested electrical resistance hand gloves and

Industrial safety shoes.

Emergency medical facilities will be made available round the clock for attending emergency arising out

of accidents by respective industries, if any. All working personnel are medically examined at least once

in every year and at the end of his term of employment.

Page 187: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.3

EIA-EMP Report for Proposed Mega Textile Park at Warangal

7.1.2 Safety plan

Safety of both humans and materials during construction and operational phases is of concern. The

preparedness in the proposed site for the occurrence of possible disasters is known as emergency plan.

A disaster in the proposed site may be possible due to leakage of hazardous fuels like HSD, collapse of

structures and fire/explosion etc.

Keeping in view the safety requirement during construction, operation and maintenance phases,

developer/common facilitator propose to formulate the safety policy and the same will be further

strengthening after establishment of the proposed MTP.

The safety policy is based on the following regulations:

To allocate sufficient resources to maintain safe and healthy conditions of work

To take steps to ensure that all known safety factors are taken into account in the design, construction, operation and maintenance of member industries, machinery and equipment.

To ensure that adequate safety instructions are given to all employees

To provide wherever necessary protective equipment, safety appliances and clothing and to ensure their proper use

To inform employees about materials, equipment or processes used in their work which are known to be potentially hazardous to health or safety

To keep all operations and methods of work under regular review for making necessary changes from the point of view of safety in the light of experience and up to date knowledge

To provide appropriate facilities for first aid and prompt treatment of injuries and illness at work

To provide appropriate instruction, training, retraining & supervision to employees in health & safety, first aid and to ensure that adequate publicity is given to these matters

To ensure proper implementation of fire prevention methods and an appropriate firefighting service together with training facilities for personnel involved in this service

To organize collection, analysis and presentation of data on accidents, sickness and incidents involving people with a view to taking corrective, remedial and preventive action

To promote through the established machinery, joint consultation in health and safety matters to ensure effective participation by all employees

Publish/notify regulations, instructions & notices in common language of employees

To prepare separate safety rules for each type of occupation/processes involved in a proposed activity and to ensure regular safety inspection by a competent person at suitable intervals of all buildings, equipment’s, work places and operations in all member industries.

Page 188: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.4

EIA-EMP Report for Proposed Mega Textile Park at Warangal

7.2 Safety in organization

7.2.1 Construction and erection phase

A qualified and experienced safety officer shall be appointed by the member industries and/or for the

entire MTP. The responsibilities of the safety officers include identification of the hazardous conditions

and unsafe acts of workers and advice on corrective actions, conduct safety audit, organize training

programs and provide professional expert advice on various issues related to occupational safety and

health. He is also responsible to ensure compliance of safety rules/ statutory provisions. In addition to

employment of safety officer by industry, every contractor who employs more than 250 workers in the

proposed site for the MTP/member industry shall also employ one safety officer to ensure safety of the

workers, in accordance with the conditions of contract.

7.2.2. Operation and maintenance phase

When the construction is completed the posting of safety officers shall be in accordance with the

requirement of Factories Act and their duties and responsibilities shall be as defined thereof.

A training center shall be set up at the proposed MTP or will utilize the services of external training

center of nearby area. Safety training shall be provided by the safety officer with the assistance of

external faculty members called from professional safety institutions and universities. In addition to

regular employees, contract labors shall also be provided safety training. To create safety awareness,

safety films shall be shown and leaflets containing safety information shall be distributed to workers.

7.3 Risk assessment plan

Risk involves the occurrence or potential occurrence of some accident consisting of an event or

sequence of events. Risk (R) can be mathematically expressed as R = fD where R is the risk (individual

or societal), f is the frequency of occurrence of an undesired event and D is the expected damage

distance due to likely occurrence of that unfortunate event. The main objectives of the study are as

follows:

i. Identification of hazard prone area and estimation of damage distance for the Maximum

Credible Accident (MCA) scenarios visualized for storages. ii. Computation of frequency of occurrence of hazards and evaluation of risk. iii. Based on the studies, suggest risk mitigation measures and arrive at guidelines for Disaster

Management and Emergency Preparedness Plan (DMP and EPP).

7.4 Inventory at site

The proposed project being a textile park, there are no major storage of solvents or hazardous

chemicals at site. In case if any individual unit uses any hazardous chemicals, solvents, etc., they will

be required to follow the guidelines of MSIHC Rules 1989 and amended 2000. The inventory at the

project site is given in the Table 7.1

Table 7.1 Storage Capacity in project site

S.No Name of Hazardous Materials & Location

Nature of Hazard

No. of Storage Units

Capacity of storage (Liters)

1 HSD (High Speed Diesel)

Stored at Utilities Department

Fire &

Explosion 2 no 2500

Page 189: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.5

EIA-EMP Report for Proposed Mega Textile Park at Warangal

7.5 Hazard identification and preliminary hazard analysis

7.5.1 Introduction to hazard identification

Identification of hazards in the MTP is of primary significance in the analysis, quantification and cost

effective control of accidents involving chemicals and process. A classical definition of hazard states

that hazard is in fact the characteristic of system/ plant/ process that presents potential for an

accident. Hence, all the components of a system/ plant/ process need to be thoroughly examined to

assess their potential for initiating or propagating an unplanned event/sequence of events, which

can be termed as an accident.

7.5.2 Identification of major hazardous units

Hazardous substances may be combustible/ flammable in nature. The HSD characteristics proposed

to be stored at the project site are given in Table 7.2

Table 7.2 Summary table on the Inventories

Chemical Codes/Label TLV FBP MP FP LEL UEL

%

HSD

(High Speed Diesel) Flammable 800 ppm 215 - 3760 C NA 320 C 0.6 6.0

TLV : Threshold Limit Value FBP : Final Boiling Point

MP : Melting Point FP : Flash Point

UEL : Upper Explosive Limit LEL : Lower Explosive Limit

7.5.3 Classification based on inventory rating

In order to ensure a steady supply of raw materials, process chemicals and fuels, adequate inventory

of all these materials is to be maintained at the project site (details will be provided by individual

units at the time of obtaining CFE from State PCB). The quantities of fuel required for running DG set

used for common facilities of MTP (CETP, CSTP, etc) stored and the degrees of hazard in terms of

National Fire Protection Agency, USA (NFPA) ratings are given below. The NFPA ratings, on scale 0 to

4 (least to worst), hazard rating is used as a tool to assess the preliminary hazard potential of a

material shown in the Table 7.3

Table 7.3 Properties of Fuel employed

S.No Raw Material Nh Nf Nr Remarks

1 HSD

(High Speed Diesel)

1 2 0 HSD falls under “moderate” category of

flammability index with Nf being 2

7.5.4 Identification of major hazard installations based on Manufacture, Storage and Import of

Hazardous Chemical (MSIHC) Rules 1989 and amended in 2000

Following accidents in the industry in India over the past few decades, a specific legislation covering

a major hazard activity has been enforced by Govt. of India in 1989 in conjunction with Environment

Protection Act, 1986. This is referred here as MSIHC Rules 1989. For the purpose of identifying major

hazard installations the rules employ certain criteria based on toxic, flammable and explosive

properties of chemicals.

Page 190: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.6

EIA-EMP Report for Proposed Mega Textile Park at Warangal

A list of hazardous substances with their threshold quantities are provided in Part II of Schedule I of the rules

Schedule II of the rules sets out the threshold quantities for isolated storage units

Schedule III gives a list of hazardous chemicals with their threshold quantities. In this schedule different chemicals are classified into distinct groups viz. Group 1 - Toxic substances, Group 2 -Toxic substances, Group 3 -Highly reactive substances, Group 4 -Explosive substances and Group 5-Flammable substances.

Schedule IV of the rules indicate various operations which are hazardous during production, processing or treatment of organic and inorganic chemicals.

Indicative criteria for identification of toxic, flammable and explosive chemicals (MSIHC Rules 1989,

Amended in 2000) is given in Table 7.4

Table 7.4 Indicative Criteria for Identification of Toxic, Flammable and

Explosive Chemicals (MSIHC Rules 1989, amended 2000)

a. Toxic chemicals

Chemicals having the following values of acute toxicity and which, owing to their physical and

chemical properties, are capable of producing major accident hazards

S.

No.

Degree of

Toxicity

Medium lethal dose by

the oral route (oral

toxicity) LD 50 (mg/Kg

body weight of test

animals)

Medium lethal dose by

the dermal route

(dermal toxicity) LD

50(mg/Kg body weight

of test animals)

Medium lethal

concentration by

inhalation route (four

hours) LC50 (mg/L

inhalation in test

animals)

1. Extremely toxic 1-50 1-200 0.1-0.5

2. Highly toxic 51-500 201-2000 0.5-2.0

b. Flammable Chemicals

i. Flammable gases: Chemicals which in the gaseous state at normal pressure and when mixed

with air become flammable and the boiling point of which at normal pressure is 20oC or

below;

ii. Highly flammable liquids: Chemicals, which have a flash point, lower than 23oC and the

boiling point of which at normal pressure is above 20oC.

iii. Flammable liquids : Chemicals which have a flash point lower than 650C and which remain

liquids under pressure, where particular processing conditions, such as high pressure and

high temperature, may create major accident hazards

c. Explosives

Chemicals which may explode under the effect of flame, heat or photo-chemical conditions or which

are more sensitive to shocks or friction than dinitrobenzene.

Based on the indicative criteria inventory (liquids/fuels) stored in proposed site has been analyzed

for applicability of MSIHC Rules 1989, amended 2000 and the results are summarized in Table 7.5

Page 191: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.7

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Table 7.5 Applicability of MSIHC rules to storages

S.

No.

Chemical/

Fuel

Listed in

Schedule

*Actual

Expected

Quantity

Threshold Quantity

for Application of Rules

5,7 – 9 and 13 – 15

for Application of

Rules 10 - 12

1 HSD 3 (2(e)(iii), 5 and

6(1)(a) /) 2.1 T 2500 T 20,000 T

*Expected quantity to be stored for a week

From the above table it can be inferred that HSD tanks does not (with capacity 2.1 T) attract rules

2(e)(iii), 5 and 6(1)(a) and 7-15, as the stored quantities are less than that of the stipulated threshold

quantities

7.6 Short listed hazards

Based on the preliminary hazard analysis, the following scenarios are short-listed for consequence

analysis to quantify the risks involved. The nature of hazards that could occur in proposed site is

presented in the Table 7.6 along with the sources.

Table 7.6 Short listed hazards

Nature of hazards sources & location

Fire hazards HSD storage area, storage & handling of HSD in DG power house

Accidents due to material

handling equipment

Connected with all material handling activities and equipment

Dust hazard Movement of vehicles, industrial activities, etc.

High voltage electrical

hazard

DG power house, switch yard, HT motors/ lines

Fall from height Civil construction works, welding and other hot jobs done at height.

7.7 Maximum credible accident analysis

Hazardous substances may be released as a result of failures or catastrophes, causing possible

damage to the surrounding area. This section deals with the question of how the consequences of

the release of such substances and the damage to the surrounding area can be determined by

means of models. A disastrous situation is generally due to outcome of fire, explosion or toxic

hazards in addition to other natural causes, which eventually lead to loss of life, property and

ecological imbalance.

Major hazards posed by hazardous chemical storages can be identified taking recourse to MCA

Analysis. MCA analysis encompasses certain techniques to identify the hazards and calculate the

consequent effects in terms of damage distances of heat radiation, toxic releases, vapor cloud

explosion, etc. A host of probable or potential accidents of the major units in the complex arising

due to use, storage and handling of the hazardous materials are examined to establish their

credibility. Depending upon the effective hazardous attributes and their impact on the event, the

maximum effect on the surrounding environment and the respective damage caused can be

assessed.

Page 192: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.8

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Various models for calculating the physical effects of the incidental release of hazardous substances

are detailed subsequently. First, attention is paid to the factors, which are decisive for the selection

of the models to be used in a particular situation, after which the various effect models are

discussed.

7.8 Injuries resulting from flammable liquids

In the case of flammable liquids such as HSD for immediate ignition of a pool fire will occur. The

injuries in this case are mainly caused by heat radiation. Serious injuries as the result of the shock

wave generally do not occur outside the fire ball zone. Fragmentation of the storage system can

cause damage up to distance of over 50m depending on the capacity of the affected storage tank. If

the gas is not ignited immediately, it will disperse into the atmosphere. If the gas cloud ignites it is

assumed that everyone present within the gas cloud will die as a result of burns or asphyxiation.

Outside the gas cloud the duration of the thermal load will be too brief to cause any injuries. In the

event of very rapid combustion of the gas cloud, the shock wave may cause damage outside the

limits of the cloud. Explosive combustion will only occur if the cloud is enclosed to some extent

between buildings and obstacles. The mathematical models and analytical models for hazard analysis

of the flammable liquids in the proposed site are as given in Table 7.7, damage criteria in Table 7.8,

radiation exposure and lethality in Table 7.9

Table 7.7 Mathematical models and analytical models for hazard analysis

S. No Explosions

1 Pool fire Fire ball and physical over pressure models

Table 7.8 Damage criteria

Heat Radiation

Incident Flux KW/m2 Damage

37.5 100% lethality, Heavy damage to equipment

25.0 50% lethality, non piloted ignition

12.5 1% lethality, piloted ignition

4.5 Not lethal, 1st degree burns

1.6 No discomfort even after long exposure

Table 7.9 Radiation exposure and lethality

Radiation Intensity

(KW/m2)

Exposure Time

(seconds) Lethality (%) Degree of Burns

1.6 -- 0 No Discomfort even after long exposure

4.5 20 0 1st

4.5 50 0 1st

8.0 20 0 1st

8.0 50 <1 3rd

8.0 60 <1 3rd

12.0 20 <1 2nd

12.0 50 8 3rd

12.5 -- 1 --

25.0 -- 50 --

37.5 -- 100 --

Page 193: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.9

EIA-EMP Report for Proposed Mega Textile Park at Warangal

7.9 Pool fire analysis of HSD tanks

The detailed computations of F&EI (Fire and Explosion Index) for HSD (High Speed Diesel) at

proposed site are given in Table 7.10.

The Health (Nh), Flammability (Nf), Reactivity (Nr), and MF (Material Factor) for HSD fuel under

consideration was derived from NFPA codes. The GPH (General Process Hazard Factor) and SPH

(Specific Process Hazard Factor) was calculated accordingly. Based on F & EI (Fire and Explosion

Index), the HSD fall under light degree of hazard category and nil toxicity. Thus, risk assessment and

hazard analysis has been carried out due to fire hazard for HSD storage tanks by carrying out MCA

(Maximum Credible Accident) analysis.

Table 7.10 F&EI of fuels used for the proposed MTP

Chemical/Fuel NFPA Classification

GPH SPH F&EI F&E Category Nh Nf Nr MF

HSD 1 2 0 10 1.8 2.83 50.89 Low

Note: *FEI = MF *(1+GPH) * (1+SPH)

F&EI 1 to 60 F&E Category Low;

F&EI 60 to 90 F&E Category Medium:

F&EI 60 and above F&E Category Severe

Two storage tanks of HSD with a capacity of 2500 liters are considered for the proposed MTP. Tank

fire would occur if the radiation intensity is high on the peripheral surface of tanks leading to

increase in internal tank pressure. Pool fire would occur when fuel oil collected in the dyke due to

leakage gets ignited. As the tanks are provided within the dyke the fire will be confined within the

dyke wall.

Site data:

Location: Warangal, India

Building air exchanges per hour: 0.57 (unsheltered single storied)

Time: March 30, 2017 15:09 hours ST (using computer's clock)

Chemical data:

Chemical Name: High Speed Diesel

CAS Number: 111-65-9 Molecular Weight: 114.23 g/mol

PAC-1: 230 ppm PAC-2: 385 ppm PAC-3: 5000 ppm

IDLH: 1000 ppm LEL: 9600 ppm UEL: 65000 ppm

Ambient Boiling Point: 124.6°C

Vapor Pressure at Ambient Temperature: 0.034 atm

Ambient Saturation Concentration: 34,770 ppm or 3.48%

Atmospheric data: (manual input of data)

Wind: 2.41 meters/second from S at 10 meters

Ground Roughness: open country Cloud Cover: 5 tenths

Air Temperature: 36.2°C

7.9.1 Pool fire of HSD storage tanks

Page 194: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.10

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Stability Class: D (user override)

No Inversion Height Relative Humidity: 88%

Source strength:

Leak from hole in horizontal cylindrical tank

Flammable chemical is burning as it escapes from tank

Tank Diameter: 0.80 meters Tank Length: 5 meters

Tank Volume: 2,500 liters

Tank contains liquid Internal Temperature: 36.2°C

Chemical Mass in Tank: 1,560 kilograms

Tank is 90% full

Circular Opening Diameter: 10 centimeters

Opening is 0.48 meters from tank bottom

Max Flame Length: 18 meters Burn Duration: 7 minutes

Max Burn Rate: 249 kilograms/min

Total Amount Burned: 478 kilograms

Note: The chemical escaped as a liquid and formed a burning puddle.

The puddle spread to a diameter of 7.7 meters.

Threat zone:

Threat Modeled: Thermal radiation from pool fire

Red : less than 10 meters--- (37.5 kW/ (sq m))

Orange: less than 10 meters--- (25 kW/ (sq m))

Red : 14 meters --- (12.5 kW/ (sq m))

Orange: 26 meters --- (4.5 kW/ (sq m))

Yellow: 46 meters --- (1.6 kW/ (sq m))

Figure 7.1 Thermal Radiation Threat Zone

Page 195: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.11

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Time: March 30, 2017 1509 hours ST

Chemical Name: High Speed Diesel

Wind: 2.41 meters/second from S at 10 meters

THREAT ZONE:

Red: 14 meters --- (12.5 kW/ (sq m))

Orange: 26 meters --- (4.5 kW/ (sq m))

Yellow: 46 meters --- (1.6 kW/ (sq m))

Model: ALOHA Thermal radiation from pool fire

Figure 7.2 ALOHA Source point on the

layout

Page 196: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.12

EIA-EMP Report for Proposed Mega Textile Park at Warangal

A perusal of the above table clearly indicates that 37.5 KW/m2 (100%) lethality occurs within the

radius of the pool which is computed at less than 10 m tank on pool fire. This vulnerable zone will

damage all fuel storage equipment falling within the pool radius.

Similarly the threshold limit for first degree burns is 1.6 KW/m2; this vulnerable zone in which the

thermal fluxes above the threshold limit for first degree is restricted to 88m in case fuel storage area

catches pool fire.

Disaster Management Plan (DMP)

A Disaster is called when following one or the other or more incidents occur:

Risk of loss of human lives-ten or more in one single situation

A situation which goes beyond the control of available resources

Loss of property as a consequence of the incident is over Rs. 1 Crore and/or bears a potential

to the above

A situation which may not have much loss but its long-term severity can affect loss of life,

production and property.

Disasters occur due to:

Emergencies on account of Fire, Explosion, Spillage of toxic chemicals, Electrocution

Natural calamity on account of Flood, Earthquake/Cyclone/Storm/Cloud burst/ Lightning

External factor on account of Food poisoning, Sabotage

The objective of the study is to assess the likely hazards and risk associated with process and

preparation of preliminary Disaster Management Plan (DMP).

These guidelines would be in addition to the guidelines issued by the NDMA which are available at

http://ndma.gov.in/ndma/guidelines.html. The main objectives of DMP are:-

To control and contain the incident/accident and if possible, eliminate it

To minimize the effects of the incident on persons, property and environment

If an accident/incident takes place within the MTP and its effects are confined to the premises,

involving only the persons working in the MTP and the property inside the MTP, it is called as on-site

disaster.

7.9.2 Damage distance computations for MCA (Maximum Credible Accident) analysis

The major hazard scenarios identified for the possibility of occurrence are mainly concerned with

HSD Storage tanks.

The most credible failure is the rupture of the largest pipe connecting to the storage tank. As worst

case, it is assumed that total quantity of HSD is leaked and the entire contents leak out into the dyke

forming a pool, which may catch fire on finding a source of ignition.

7.10

Page 197: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.13

EIA-EMP Report for Proposed Mega Textile Park at Warangal

If the accident is such that its affects are uncontrollable and it may spread outside the premises of

the MTP, it is called as off-site disaster.

7.10.1 On-Site disaster management plan

The important element of the onsite disaster management plan is it should have a designated

control center / room, assembly points, fire prevention facilities, key personnel, etc. The main

elements of On-site Emergency plans are given below:

Leadership and administration.

Role and responsibilities of key personnel.

Emergency action.

Light and power.

Source of energy control.

Protective and rescue equipment.

Communication.

Medical care.

Public relation.

Protection of vital records.

Training.

Periodical revision of plan.

7.10.1.1 Control center

This is the main center from where the operations to handle the emergency are directed and

coordinated. Facilities to be made available in the control center are:

Internal and external communication.

Computer and other essential records.

Daily attendance of workers employed.

Storage of hazardous material records and manufacturing records.

Pollution records.

Walky-talky.

Plan of the MTP showing:

Storage area of hazardous materials.

Storage of safety equipments.

Firefighting system and additional source of water.

Site entrance, roadway and emergency exist.

Assembly points.

Truck parking area.

Surrounding location.

Note Book, pad and pencil.

List of key personnel with addresses, telephone numbers, etc.

7.10.1.2 Fire prevention facilities

The individual units and / or MTP should provide appropriate firefighting equipment including

pumps for emergency requirement. Any one or combination of the following system is proposed.

Hydrant system

Page 198: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.14

EIA-EMP Report for Proposed Mega Textile Park at Warangal

High velocity and medium velocity sprinkler system.

Water spray

Foam system.

Chemical extinguishers.

Applicable codes and standards of NFPA would also be followed.

7.10.1.3 Assembly points

A safe place (main gate of individual units or any other safe area) should be pre-determined as

assembly point where in case of emergency personnel evacuated from the affected areas are to be

assembled. The workers, contract workers and visitors should assemble in assembly point in case of

emergency and the time office clerk should take their attendance so as to assess the missing persons

during emergency.

7.10.1.4 Key personnel for onsite emergency:-

The key personnel (individual units and or MTP) and their important roles for onsite emergency

handling are given in Table 7.11.

Table 7.11 of Onsite emergency key personnel – roles and responsibilities

Key personnel Roles and responsibilities

Works main

controller

General manager of the site should act as main controller

- Assess magnitude of the situation and decide whether the evacuation of staff

from the MTP / individual unit is needed.

- Exercise direct operational control over areas affected.

- Maintain a continuous review of possible development and assess in

consultation with work incident controller and other key personnel.

- Liaison with police, fire service, medical services, factory inspectorate and other

Govt. agencies.

- Direct and control rehabilitation of affected area after emergency.

- Intimate off-site emergency controller if emergency spreads beyond the MTP

/individual unit & likely to affect the surrounding area.

- Ensure that evidence is preserved for enquiries to be conducted by statutory

authorities.

- If required declare emergency and instruct gate office to operate the emergency

siren after assessing the gravity of the situation.

Works incident

controller

Next responsible officer after the works main controller.

- Generally the supervisor is designated as work incident controller.

- In case of emergency will rush to the place of occurrence and take overall

charge and report to the works main controller and inform about the

magnitude of emergency.

- Assess the situation considering the magnitude of emergency, take decision and

inform communication officer to communicate the news of emergency to

different agencies.

- Give direction to stop all operations within the affected area. Take charge of

main controller till the main controller arrives.

- If required order for shutdown and evacuation of workers and staffs from

affected area.

Page 199: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.15

EIA-EMP Report for Proposed Mega Textile Park at Warangal

- Inform all key personnel and all outside agencies for help.

- Inform security and fire officers and state fire services.

- Ensure that all non-essential workers/staff are evacuated to assembly point and

areas searched for casualties.

- Report all significant development to communication officer.

- Advise to preserve evidence of emergency into the cause of emergency.

Communication

officer

- On hearing the emergency siren/alarm he will proceed to the control center and

communicate to work incident controller.

- Collect information from the emergency affected area and send correct

message to work main controller for declaration of emergency.

- Maintain a log book of incident.

- Contact all essential departments.

- Take stock of the meteorological condition from local meteorological

department.

- Communicate all information as directed by works main controller.

Security and fire

officer

- Security/fire officer responsible for the firefighting.

- On hearing the emergency alarm/siren,

- Reach the incident area with fire and security staff.

- Immediately after arrival to the emergency area, inform to the work incident

controller about the situation and requirement of outside help like state fire

service and other members.

- At the site, the entire fire squad member will respond to the advice and

information given by the works incident controller.

- Control the visitors and the vehicle entry

Telephone

operators

In case of fire is discovered but no emergency siren is operated, he shall ensure the

information about the location of the fire/emergency incident from the persons

discovered/notices the above and communicate to different key personnel

immediately with clear message.

Medical officer - Medical Officer with his team will report to the works incident controller on

hearing the fire/emergency siren immediately.

- Organize ambulance nearest to the site of incident.

- Name of injured and other casualties carried to the hospital will be recorded

and handed over to works incident controller.

- Organize ambulance to carry injured to nearest hospital for treatment.

Personnel/

administrative

officer

- Work as a liaison officer lesioning with works main controller and other

essential departments such as police, press and statutory authorities.

- Ensure casualties receive adequate attention to arrange additional help if

required and inform relatives.

- Control traffic movement into the park and ensure that alternative transport is

available when needed.

- When emergency is prolonged, arrange for the relief of personnel and organize

refreshment and catering facilities.

- Arrange for finance for the expenditure to handle the emergency

Essential work

team leaders

Follow the instructions given by onsite emergency key personnel

Page 200: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.16

EIA-EMP Report for Proposed Mega Textile Park at Warangal

7.10.1.5 Alarm system

Alarm system varies and will depend on the size of the works area - simple fire bell, hand operated

siren – break open type, fire alarm, etc. Automatic alarm may be needed for highly hazardous nature

of industries in the IP.

7.10.1.6 Communication system

Communication is a key component to control an emergency. The following communication system

may be provided in the IP:

Walky-Talky.

Telephone (internal & external).

Cell phone.

Intercom/paging.

Runners (verbal or written messages).

7.10.1.7 Siren for emergency

Siren for emergency should be different from the normal siren. The emergency siren should be

audible to a distance of 5 km radius. The emergency siren should be used only in case of emergency.

7.10.1.8 Escape route

The escape route from each and every unit of the MTP should be clearly marked. The escape route is

the shortest route to reach out of the plant area to open area, which leads to assembly point. This

route should be indicated on the layout plan attached to the on-site management plan.

7.10.1.9 Evacuation

All non-essential staff should be evacuated from the emergency site. As soon as the emergency siren

rings the workers have to shut down the MTP and move to the assembly point. The shutdown

procedure in case of emergency should be prepared and kept ready and responsible persons should

be nominated for the purpose.

7.10.1.10 Counting of personnel

All personnel working in the MTP should be counted. Time office persons should collect the details

of personnel arriving at the assembly point. These should be checked with the attendances of

regular workers, contract workers present in the site on the day of emergency. The accident control

should be informed and arrangement should be made for searching missing persons in the

emergency affected area. The employees’ address, contact number of next to kin should be

maintained in the time office so that during emergency relatives of those affected due to emergency

may be informed accordingly. Information in respect of emergency should be given to the media and

other agency.

7.10.1.11 All clear signal

After control of emergency the work incident controller will communicate to the works main

controller about the cessation of emergency. The main controller can declare all clear by instructing

the time office to sound “All Clear Sirens”.

Page 201: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.17

EIA-EMP Report for Proposed Mega Textile Park at Warangal

7.10.1.12 Emergency facilities

The following facilities should be provided to tackle any emergency at any time.

Fire protection and firefighting facilities

Emergency lighting and standby power

Emergency equipment and rescue equipment

Breathing apparatus with compressed air cylinder

Fire proximity suit

Resuscitator

Water gel Blanket

Low temperature suit

First aid kit

Stretchers

Torches

Ladders

Safety Equipment (Respirators, Gum boots, Safety helmets, Asbestos rubber hand gloves,

Goggles and face shield, Toxic gas measuring instruments, Explosive meter, Oxygen

measuring instruments, Toxic gas measuring instrument, Wind direction indicator)

The On-site Emergency Plan should contain following information

Site plan and topographic plan

Plan showing the firefighting facilities

Plan showing hazardous material storage area

Material safety data sheets for hazardous chemicals

Facilities available in main control center

List of emergency equipment

List of Safety Equipment

List of important telephone numbers and addresses

Nearest hospitals and ambulance service center

Nearest fire station

Govt. Officials

Transport provider

Names and address & contact telephone number of key personnel

The on-site emergency plan so prepared shall be documented in a printed form in sufficient copies

to give all concerned for knowledge, study and easy follow up. The emergency plan shall be

rehearsed and practiced at regular intervals to test efficiency of personnel, equipment coordinated

efforts and to increase confidence and experience to operate such plan. The plan so prepared should

be updated annually and uploaded in the factory website for easy reference.

7.10.2 Off-site disaster management plan

The main objectives of the off-site emergency plan are save lives & prevent injuries, prevent or

reduce property losses and quick resumption of normal situation or operation.

Chemical Accidents (Emergency Planning, Preparedness and Response) Rules, 1996 prescribes for

the constitution of the state crisis group as apex body at the State Level to deal with major chemical

Page 202: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.18

EIA-EMP Report for Proposed Mega Textile Park at Warangal

accidents and to provide expert guidance for handling major chemical accidents. Schedule 7 and

Schedule 8 of the chemical accidents (Emergency Planning, Preparedness and Response) Rules, 1996

prescribes for the constitution of state, district and local crisis groups.

A. Functions of the state crisis group

Review all district off-site emergency plans in the State with a view to examine its adequacy

in accordance with the manufacture, storage and import of hazardous chemical, rules and

forward a report to the central crisis group once in three months

Assist the state government in managing chemical accidents at a site

Assist the state government in the planning, preparedness and mitigation of major chemical

accidents at a site in the State

Continuously monitor the post-accident situation arising out of a major chemical accident in

the State and forward a report to the central crisis group

Review the progress report submitted by the district crisis group

Respond to queries addressed to it by the district crisis group

Publish a list of experts and officials in the State who are concerned with the management of

chemical accidents.

B. Functions of the district crisis group

Assist the preparation of the district off-site emergency plan

Review all the on-site emergency plans prepared by the occupier of major accident hazards

installation for the preparation of the district off-site emergency plan

Assist the district administration in the management of chemical accidents at a site lying

within the district

Continuously monitor every chemical accident

Ensure continuous information flow from the district to the centre and state crisis group

regarding accident situation and mitigation efforts

Forward a report of the chemical accident within fifteen days to the state crisis group

Conduct at least one full scale mock-drill of a chemical accident at a site each year and

forward a report of the strength and the weakness of the plan to the state crisis group.

C) Functions of the local crisis group

Prepare local emergency plan for the industrial pocket

Ensure dove tailing of local emergency plan with the district off-site emergency plan

Train personnel involved in chemical accident management

Educate the population likely to be affected in a chemical accident about the remedies and

existing preparedness in the area

Conduct at least one full scale mock-drill of a chemical accident at a site every six months

and forward a report to the district crisis group and

Respond to all public inquiries on the subject.

Central control committee

As the offsite plan is to be prepared by the government, a central control committee shall be formed

under the chairmanship of the district collector. Other officers from police, fire service, factory

inspectorate, medical department shall be incorporated as members of the central control

Page 203: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.19

EIA-EMP Report for Proposed Mega Textile Park at Warangal

committee. Under the central control committee the following committees shall be constituted

under the control of the district collector.

Incident and environment control committee

Fire control committee

Traffic control, law and order, evacuation and rehabilitation committee

Medical help, Ambulance and Hospital Committee

Welfare, restoration and resumption committee

Utility and engineering services committee

Press, publicity and public relations committee

The off-site emergency plan shall be prepared by the district magistrate in consultation with the

factory management and Govt. agencies. The plan contains up-to-date details of outside emergency

services and resources such as fire services, hospitals, police etc. with telephone number. The

district authorities are to be included in the plan area.

a. Police department

b. Revenue department

c. Fire brigade

d. Medical department

e. Municipality

f. Gram panchayat

g. Railway department

h. Telephone department

i. Factory department

j. Electricity department

k. Pollution control department

l. Explosive department

m. Press and media

Mock exercises on off-site plan should be carried out at least once in a year to train the employees,

up to date the plan, observe and rectify deficiencies. Each industrial unit or group of units should

prepare separate emergency preparedness and DMP which will be in sync with the main DMP of

MTP incorporating details of action to be taken in case of any major accident/disaster occurring

within the unit. The plan should cover all types of major accident/occurrences and identify the risk

involved in the industry. Mock drills on the plan should be carried out periodically to make the plan

foolproof and persons are made fully prepared to fight against any incident in the industry. The plan

will vary according to the type of industry and emergency.

Occupational health and safety

7.11.1 Introduction

Maintaining a high degree of physical, mental and social wellbeing of employees ensures high

productivity and overall sustainability of the proposed project.

7.11.2 Occupational health

There would be first aid stations and an industrial health laboratory within the MTP to take care of

the comprehensive health management system of the individual unit personnel which are to be

developed in the proposed MTP. Regular health education programs and other health care initiatives

would be taken up to uphold workers general health conditions.

7.11

Page 204: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.20

EIA-EMP Report for Proposed Mega Textile Park at Warangal

The health education program includes the topics like occupational health, noise hazards, exposure

to toxic chemicals and heavy metals, cardiac risks reduction, life style management, wellness

management, stress management, ergonomics, early diagnosis & treatment, burn safety & eye care,

gas & heat hazards, occupational lung diseases, physical fitness, nutrition etc. The occupational

health hazards with permissible limits and mitigation is presented in Table 7.12. The action plan for

implementation of OHS standard is presented in Table 7.13.

Table 7.12 Occupational health hazards with permissible limits and mitigation

S. No Occupational &

safety hazards

Permissible Exposure Level

(PEL)

Measures adopted at site

1 Dust Level 2 mg/m3 in closed work zone,

500 µg/m3 in open work zone

Dry fogging, preventing leakages, conducting environmental audits and strict adherence to pollution control measures

2 Noise 85 db(A)/ 8 hours duration Ear plugs & ear muffs

3 Vibrations Exposure action value (EAV) -

2.5 m/s2 A(8)

Reducing the time spent holding vibrating equipment or work pieces. Hand gloves, fibre handles

4 Kerosene Recommended Exposure Limit

(REL) : 100 mg/m3 TWA

PEL : None

Ansel nitrile chemical resistant gloves, chemical resistance gloves, 3M Disposable respirators

5 LDO/HSD Threshold Limit Value (TLV) :

800 ppm, TWA (vapors/

aerosol)

Proper ventilation, use of PVC gloves, safety glasses, air purifying respirators for uncontrolled release

6 working at

height

2 m above ground level Double lanyard full body safety harness. Life line support. Proper IITS (information, instructions, training, and supervision) provided.

7 Excavation 1.5 m depth Gum boot, ramp, shoring, benching etc. Proper IITS implemented. SOP & standards implemented.

8 Scaffolding 2 m above ground level Railings in access, work platform, hand rail, mid rail, toe guard. System scaffold standard implemented

9 Welding/ Gas-

Cutting

- Apron, leather hand gloves, face-shield, black goggles, SOP implemented

10 Manual

Material

Handling

Max. 50 kg/ Adult Male, 30 kg/

Adult Female

Cotton gloves, safety shoe (steel toe), safety helmet. Head & shoulder load carrying is strictly prohibited

Page 205: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.21

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Table 7.13 Action plan for implementation of OHS standard

S. No Type of possible health

hazards

Preventive action plan

1 Fall from Height All workers working at height to be examined specially for vertigo & certified.

Workers to be supplied with personal protective equipment (PPE) like belt, harness, helmet, gloves use has been ensured

2 Slip, Trip or Fall on the Level All workers to use non slip safety shoes

3 Injury Caused by Falling

Objects

Use of helmet by all workers

4 Exposure to Extreme Temp. In summer working hours to be rescheduled as per government guideline

5 Electrical Injury Positive isolation.

Barricading installation.

Use of PPE, like gloves, shoes, helmet, goggles

6 Eye Injury Use of goggles.

Supply of water tab at strategic locations.

Providing first aid available within 10 minutes ambulance service for major injury

7 Risk of Road Traffic Accident Entry of only authorized vehicle.

Speed limit regulation and display of speed limit area.

Mandatory use of seat belt.

Regular maintenance of road.

8 Noise Pollution Use of noise mask/ ear plugs at high decibel sound area

9 Exposure to Work Zone Dust Water sprinkling on services roads.

Use of mask.

Vacuum cleaning of shop floors.

Prevention of leakage from furnaces, conveying systems, DE/ FE systems and routine preventive maintenance

10 Exposure to Cement (During

Construction)

Use of nose mask, gloves and shoes by all workers

11 Exposure to Hazardous

Chemicals

Storage of chemicals in confined area as per regulations.

To be handled by authorized persons only.

Use of PPE

12 Periodic Health Check Up Pre-employment health check-up.

Health check up every 2 years

13 First Aid Back Up One first-aid centre to run in the factory premises.

Ambulance service to be available round the clock

7.12 Geological and hydrogeology

7.12.1 Introduction

Geological and hydro-geological studies were conducted within the proposed project site of the MTP

to evaluate the hydro-geological setting of the study area. The study is mainly oriented towards the

topographical conditions, existing natural drainage, planning of storm water drains, geological and

hydrogeological setting along with proposal of suitable artificial recharge structures for

improvement of groundwater in and around the proposed project area.

Page 206: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.22

EIA-EMP Report for Proposed Mega Textile Park at Warangal

7.12.2 Topography

Geographically, site is located in eastern part of Warangal district near Chintalapalli village, and from

Warangal city it is 20 km towards southeastern direction.

Topographically, the area consists of isolated rocky hills, plain lands, seasonal ponds and shrub

forests. The major portion is occupied plains with a moderate slope of 5-10 degrees. The maximum

elevation is 270 m and the minimum elevation contour values 250 m in 3 km radius area. The

contour map of study area for 3 km radius from site is shown in Figure 7.3. In this area, the land is

mostly agricultural land, scrub lands, barren lands and rain fed-waterbodies. The site area is mostly a

plain land with undulations at some places.

Hydrologically, there are no major rivers in the area and most of the minor rivers present are

ephemeral in nature. The drainage pattern is dendritic to sub-dendritic following straight courses.

Sriram Sagar Flood Flow Canal (SRSP Kakatiya Canal) is passing adjacent, and a Shayampet pond is in

northwestern direction and is outside the project site. Drainage map is shown in Figure 7.4.

Figure 7.3 Contour map

Page 207: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.23

EIA-EMP Report for Proposed Mega Textile Park at Warangal

7.12.3 Soils

The major soil type in the area is red soil; and also found black and lateritic soils. In the site area, the

soils are mostly red morrum. The red soils are strong brown to reddish-brown in colour and these

are sandy loams, sandy clay loam and clay loam in texture found most commonly. Also found are

sandy and gravelly textured soils. The alluvial soils are found at shallow depths covered in the flood

plains along the major streams only.

7.12.4 Geology

The area is mainly covered with crystalline rock of archaean age. These rocks mainly consisting of

granites and gneisses with several intrusions like quartz and pegmatite veins. Few dolerite dykes are

present in the north eastern part outside the textile park. Most of the granites are exhibiting

porpheritic texture. Grey granites are more common formations occurring within the industrial park.

The generalized stratigraphic succession is shown below:

Age Lithology

Recent etc. River alluvium, sands —less unconsolidated rock materials of sand, silt, clays

Archean Granites, gneisses, quartzite’s, laterites

7.12.5 Hydrogeology

The crystalline rocks like granite and gneisses lack primary porosity. They develop secondary porosity

through fracturing and weathering over ages and thus become water bearing. The movement of

ground water is controlled by the degree of inter-connection of secondary pores/voids. The depth to

Figure 7.4 Drainage map

Page 208: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.24

EIA-EMP Report for Proposed Mega Textile Park at Warangal

bed rock varies from few meters to 30 m bgl. Ground water occurs under unconfined conditions in

weathered zone and under semi confined conditions in the fractures and fissures. The deeper

fractured aquifer is developed through bore wells. The fractured aquifers are potential up to 100 m

depth in general, the occurrence of fractures decreases drastically beyond 100m depth. Potential

fractures are encountered only along the lineaments and at other favorable location. The deeper

water levels of more than 20 m bgl are observed in and around the Textile Park.

7.12.5.1 Hydrological Assessment:

In order to have detailed understanding about the surface topographical conditions and catchment

area assessment within the MTP and in an area of about 5km radius of the study area has been

generated. Based on the developed drawings the hydrological assessments including runoff

calculations and suggestive rainwater harvesting system were made for the textile park.

It is observed there are three secondary grade streams are passing across the Textile Park. These

streams are designated as Stream 1, Stream 2 and Stream 3 based on their presence from west to

east respectively. Topographically the area is basically a negative zone for development of deep cut

stream valleys. Most of the site area is located over a water divide. The existing streams are not

perennial and are only seasonally flowing streams. These streams are connected to the surface tanks

existing further south from the MTP area. In order to protect the existing streams it is suggested to

have 50 m buffer zone on either side of the streams by considering all protective measures. Only

clean water has to be released into the streams during rainy period. The map revealing the surface

profile within the MTP is shown in Figure 7.5. The demarcated catchments for existing streams in the

site are shown in Figure 7.6. The lineament map is shown in Figure 7.7. The map of micro watershed

is shown in Figure 7.8. Map showing buffer zone for existing streams for protection is shown in

Figure 7.9.

Figure 7.5 Surface profile of project site

Page 209: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.25

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Figure 7.6 Demarcated catchment area map for existing streams in the site

Figure 7.7 Lineament map

Page 210: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.26

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Figure 7.8 Map of micro watershed

Figure 7.9 Map showing buffer zone areas for existing stream protection

Page 211: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.27

EIA-EMP Report for Proposed Mega Textile Park at Warangal

7.12.5.2 Groundwater mode and occurrence

Groundwater occurs in open spaces of weathered fractures and fissures of gneisses and granites

which are below the soil horizon. There are found only limited aquifers. In weathered zone,

groundwater occurs under confined and in fractured and jointed formations, it occurs under semi-

confined to confined conditions. The mode of groundwater extraction is mainly through bore wells

with few only open wells existing. Due to over exploitation in many areas, groundwater in

weathered zone was dried-up, semi-confined to confined aquifer conditions are formed due to

fractures and fissures in hard rocks in greater depths. In hard rock areas, depth to water in wells

varying from 5 to 20 m bgl during summer, and below 2 to 5 m bgl during post monsoon. The yield

ranges from 20 to 60 cu. m/day. The deeper fractured aquifer developed through bore wells are

mostly potential upto 100 m depth, the occurrence of fractures decreases drastically beyond 100m

depth. Potential fractures are encountered only along lineaments and at other favorable locations.

Discharge of successful bore wells ranges from 0.5 lps to 4 lps. Transmissivity values range from 2.36

to 12.65 cu. m/day. In alluvial areas, yields of shallow wells varying from 30 to 60 cu.m/day, and of

dug wells and dug-cum-bore wells are upto 300 cu.m/day. The depth of alluvial sands varies from 5

to 20 mbgl. [CGWB studies, Sep. 2013]. Groundwater level fluctuations trend (2012 CGWB data) is

showing a rise of more than 4 m bgl.

7.12.6 Groundwater classification as per the Central Ground Water Authority

According to Groundwater Resource Estimation Studies (GEC 97) carried out by Central Ground

Water Board (CGWB), the net annual groundwater resources available in Warangal district is

1854.18 MCM with a groundwater draft of 1376.45 MCM (million cubic meter) and the ground water

balance is 511.39 MCM in command and non-command areas respectively. Based on this draft, the

stage of groundwater development in Hanamkonda mandal is categorized as 'critical' due to 95% of

resource overexploitation. (CGWB southern region, information booklet, Warangal district, Andhra

Pradesh, in September, 2013).

Total net groundwater availability (Hanamkonda mandal) 3387 ham

Existing gross groundwater draft for irrigation 2800 ham

Existing gross groundwater draft for domestic and industrial water supply 4333 ham

Existing gross groundwater draft for all uses 3233 ham

Provision for domestic and industrial requirement supply to 2025 546 ham

7.12.7 Storm water drainage system and run off estimate

Based on rainfall intensity of proposed site, storm water drainage system will be designed. The graph

of rainfall trend of Warangal is shown in Figure 7.10. The site is planned with well-designed

network of open surface drains and rainwater harvesting pits along the drains, so that all the storm

water is drained off without any water logging. It is planned to achieve proper utilization of

rainwater by using appropriate water harvesting mechanisms. Rainwater harvesting will be done by

construction of harvesting pits all along the storm water drainage network at a definite pitch.

Necessary expert advice will be taken in this regard. The collected storm water will be pre-treated

and diverted to raw water storage tanks for harvesting and, the excess if any will be used for

greenbelt/gardening purpose. The estimated surface runoffs for streams is shown in Table 7.14

and for project site the runoff estimate and rainwater harvesting shown in Table 7.15.

Page 212: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.28

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Rainfall Data of Warangal

Year Annual Rainfall (in mm)

2 Years Moving Average

1999 855 2000 1133 994

2001 808 970.5

2002 662 735

2003 903 782.5

2004 934 918.5

2005 1051 992.5

2006 1229 1140

2007 1030 1129.5

2008 1327 1178.5

2009 655 991

2010 1353 1004

2011 861 1107

Table 7.14 Runoff calculation for streams

Runoff Calculation for Stream 1

Area of influence within the watershed 1304999 sq. m

One hour continuous rainfall 22 mm (i.e. 0.022 m)

Runoff coefficient consider as 0.5

Estimated runoff load on stream 1 14355 cu. m

Nala carrying capacity

Length of nala 951 m

Base width of nala 2 m

Top width of nala 6 m

Channel side slope 1:2

Depth of nala 2 m

Volume of trapezoidal section ½ (A + B) X H X L

Cross sectional area of nala 8 sq. m

Capacity of the nala 7608 cu. m

Note:

There is an imbalance between runoff load and carrying capacity of stream 1. Under this circumstances in-fact the width of stream should be increased.

But the estimation is made under vacant condition of the site. After development of industrial park the runoff load will come down to more than 60% since each individual industry will hold their runoff for ground water recharge purpose. Under these circumstances the left out runoff will be accommodated within the existing stream hence, no improvement of stream is recommended.

Runoff Calculation for Stream 2

Area of influence within the watershed 893025 sq. m

One hour continuous rainfall 22 mm (i.e. 0.022m)

Runoff coefficient consider as 0.5

Estimated runoff load on stream 2 9823 cu. m

Nala carrying capacity

Length of nala 932 m

Base width of nala 2 m

Top width of nala 6 m

Channel side slope 1:2

Depth of nala 2 m

Volume of trapezoidal section ½ (A + B) X H X L

Figure 7.10 Rainfall trend graph

Page 213: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

Ramky Enviro Services Pvt. Ltd. 7.29

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Cross sectional area of nala 8 sq. m

Capacity of the nala 7456 cu. m

Note:

There is an imbalance between runoff load and carrying capacity of stream 2. Under this circumstances in-fact the width of stream should be increased.

But the estimation is made under vacant condition of the site. After development of industrial park the runoff load will come down to more than 60% since each individual industry will hold their runoff for ground water recharge purpose. Under these circumstances the left out runoff will be accommodated within the existing stream hence, no improvement of stream is recommended.

Runoff Calculation for Stream 3

Area of influence within the watershed 976586 sq. m

One hour continuous rainfall 22 mm (i.e. 0.022m)

Runoff coefficient consider as 0.5

Estimated runoff load on stream 3 10742 cu.m

Nala carrying capacity

Length of nala 1899 m

Base width of nala 3 m

Top width of nala 6 m

Channel side slope 1:2

Depth of nala 2 m

Volume of trapezoidal section ½ (A + B) X H X L

Cross sectional area of nala 9 sq. m

Capacity of the nala 17091 cu. m

Note:

The stream 3 is having more carrying capacity than the estimated runoff load. Hence, no improvement of stream is recommended.

Table 7.15 Runoff estimation of project site

Runoff Estimation for Textile Park and Rainwater Harvesting

Total land area 1191 acres

Average annual rainfall of the area (as per Indian Meteorological Dept.) 985 mm

Number of rainy days considered in the area 45 days

Rainfall in one rainy day 0.022 m Runoff coefficient taken as 0.5

Runoff generated within the industrial area in one rainy day 53028 cu. m

Annual total runoff within 45 rainy days 2386260 cu. m

60% of total runoff estimated for one rainy day is recommended for rainwater harvesting program by each individual industry within the mega textile park. The rest of 40% should be released into the nearby streams to cater the downstream areas.

60% from the total volume of one day runoff = 31817 cu. m

Note:

It is recommended to maintain about 160 recharge pits @ minimum 1 recharge pit in each industry area by accommodating about 200 cu. m of runoff or 60% of runoff generated within each individual industry

As per the Central Ground Water Board guidelines 60% of annual recharging water can be extracted through bore wells under this circumstances the industrial area can extract groundwater quantity of

1431895 cu. m/annum

Per day extraction limit of groundwater is 3923 cu. m/day

Page 214: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 8.1

Chapter – 8 Project Benefits

8.1 Introduction

The proposed Mega Textile Park (MTP) will be developed as a world class destination for attracting

investors from across the world. The Government of Telangana is keen to develop the MTP with

state-of-art site planning, incorporating appropriate concepts of eco-industrial Park and sustainable

development. By attracting investment from potential investors for the project, in addition, it is

bound to bring significant benefits to the local people and also to overall project region. The

proposed project will enhance economic growth and empower region development.

A comprehensive understanding of the project area evolved through socio-economic baseline and

social impact assessment studies carried out. Thus, a Comprehensive Intervention Plan for the

project area containing all the measures that need to be implemented in the different stages of

construction and operation of the project was formulated. This chapter addresses the Project

benefits due to implementation of the project to the local communities and to the country as a

whole.

8.2 Infrastructure facilities

There will be an increase in the infrastructure resources due to the project in the region by the way

of additional/improved transport, communication, health facilities and other basic facilities being

created. Creation of new infrastructure or up gradation of the existing infrastructure is likely to

create a boost to the local economy and enhance the quality of life of the people living in the project

region.

8.2.1 Physical and social infrastructure

The demand on the facilities in the surrounding villages due to the proposed project and the influx of

migrants can create a lot of pressure on existing infrastructure such as water, solid waste

management system and social infrastructures such as education facilities, health facilities, etc.

In order to meet the additional strain on existing infrastructure, a non-processing area is proposed in

project premises which will cater to the needs of employees of the industries such as schools, health

care facilities, commercial activities and recreational/entertainment facilities. Proposed facilities in

the non-processing zone shall be shared with the nearby settlements such as Shayampet,

Chintalapalli, Venkatapuram and Sangem, etc., in the region. The proposed social infrastructures like

Banks, ATM’s, Post Office & fire stations shall serve the region and other nearby towns. Hence strain

on existing water sources is minimised.

8.3 Induced development

Due to proposed Textile Park, surrounding villages and region would get maximum benefits. The development will be realised on several fronts.

Ensured and reliable supply of power to upcoming park and surrounding region.

Page 215: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 8.2

Benefits may be realized either as upcoming of industries and its allied ancillary units would be a boon for development of the region.

Implementation of the project will improve the existing connectivity and thus expected to benefit the locals.

Enhancement in the standard of living of the local people improving the income status.

Better quality of educational and medical facilities to the local people.

Improvement in the trading, marketing as well as value addition of local products.

Project development will also attract hotel business, banking sector, small eateries, construction, transport and other supply services.

Generation of varied direct and indirect employment catering to the available skilled and unskilled manpower in the surrounding region.

Provision of skill development activities to the employable youth in the region, thereby generating opportunities for fruitful income.

The proposed project will also cater to the growing demand-supply gap of physical and social infrastructure.

Thus, the proposed project is further acting as catalyst to industrialization and urbanization of the region.

8.4 Improved socio economic condition

Assessment of the potential socioeconomic impacts due to the proposed project focused primarily

on work force requirements, acquisition of supplies and increase in industrial activity, traffic,

increase in demand for services related to food, housing, communications, law enforcement,

medical care and local transportation, etc. The proposed project is likely to have a positive impact on

the socio-economic conditions of the region. The social structure in the region is likely to change due

to the creation of more job opportunities and avenues for income generation. People will have

higher incomes due to direct employment as well as indirect employment and will have higher

earning and buying capacities.

8.4.1 Quality of life

The quality of life in the region is likely to improve due to the creation of several job opportunities

for the local people so that the dependency changes and there will be more than one earning

member in the family, which will provide economic freedom. Higher income will provide better

opportunities for enjoying higher standard of living with better facilities. The employment

generation also reduces the migration of local people to other regions.

8.4.2 Health facilities

As a part of the Corporate Social Responsibility (CSR) initiatives, it is envisaged to create health

infrastructure in the form of Mobile Medical Unit and Community Outreach Centres, which will be

Page 216: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 8.3

beneficial to the employees and also to the local people living in the region as their dependency on

nearby towns and cities for quality medical treatment will be reduced. As part of CSR, it is also

proposed to conduct periodic health camps and carryout health and nutrition related programmes

which will create health awareness and lead to better health conditions of the people.

8.4.3 Skill development activities

The village educational status among the overall population has lower preference for higher

education which degrades the social development in the region and discourages the female

education. This is true the other way also; such that if the female education is lower, the parameters

of social upliftment of females and development of the region is affected negatively.

With globalization, Indian industries are now opening to the world, resulting in growing demand for

world-class quality workmanship and deployment of latest technologies to enhance technical skill

and productivity. Intense training to workforce and equipping them with required knowledge and

skill will ensure quality and higher level of productivity of men and machines.

Realizing this, as part of CSR, it is proposed to provide vocational training in professional manner and

to develop highly trained workforce that suits requirement of various industries. Structured training

programmes will be conducted to enable both new entrants and less experienced workers in order

to improve their skill levels, knowledge and competency.

8.5 Employment opportunities

The proposed project would have beneficial impacts through provision of direct and indirect

employment opportunities. At the time of construction and operational phases, there would be

requirement for large number of skilled, semi-skilled and un-skilled work force. Proposed project will

open up new avenues of development through creation of direct and indirect employment

opportunities. It is imperative that local people would be employed based on their skills and

educational qualifications.

Expected direct employment from proposed project, its ancillary units and common utilities is

around 1,90,000. In addition, there is wide variety of jobs that are generated in form of indirect

employment (e.g. businesses, hotels and eateries, construction work, transportation work, etc.). This

project may generate indirect employment up to 1.5 times of direct employment.

There would also be a significant number of spin-off opportunities created within the region in other

establishments catering to the needs of the project that will also employ a substantial number of

people. Furthermore, Capacity Building and Skill Development trainings will be imparted to the local

youth populace, thereby enabling them to be engaged in fruitful employment opportunities. This will

definitely bring a reduction in the existing unemployment level in the region. Thus, the proposed

project will have a positive impact on socio-economic condition of the overall region.

8.6 Revenue generation

The exposure of economies to trade and its related activities gave prominence to the development

of Industrial estate. Industrial Estates/Parks can be considered as the engines of growth for any

Page 217: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 8.4

country. The importance of Industrial estate/Parks and its related infrastructure plays a vital role in

the growth of a nation and its economy.

The project construction and operation will generate revenue for the State and Central Government

by way of payment of royalty, tax etc. In addition to the above, Industrial estate/park development

will attract investments into the region and thereby contribute to economic growth of Warangal

District and the State of Telangana and the country as a whole.

8.7 Implementation and funding

After the establishment of industries the based on the qualification of the individuals and the

requirement of the industries recruitment shall be done by the upcoming industries.

Financial help will be provided to local youth (tuition fees, hostel charges, books, examination fees,

etc.) of the study area in getting them trained in industrial training institutes/centers, polytechnics in

various trades like electricians, plumbers, fitters, drivers, etc. An approximate amount of 1% of the

total project cost (around Rs.25 lakhs for first year) is earmarked towards CSR activities.

TSIIC shall develop the park by providing the required infrastructure while the Upcoming industries

shall comply with the CSR activities.

Page 218: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 9.1

Chapter 9

Environmental Management Plan

9.1 Introduction

The development of the proposed Mega Textile Park (MTP) needs to be intertwined with utilization

of natural resources within the limits of permissible assimilative capacity. The Environmental

Management Plan (EMP) is required to ensure sustainable development of the proposed MTP to

meet these objectives.

The EMP is an action plan aiming to control pollution at the source level to the maximum possible

extent with the available and affordable technology followed by treatment measures before they

are discharged. It encompasses the mitigation measures that are proposed in order to synchronize

the economic development of the study area with the environmental protection of the region.

9.2 Environmental management during constructional stage

The impacts during the constructional stage of the proposed MTP on the environment would be

basically of temporary in nature and are expected to reduce gradually on completion of the

constructional activities.

9.2.1 Air quality mitigation measures

For the proposed MTP, levelling and grading will be carried out, wherever possible to maintain the

natural elevations they will not be disturbed, only levelling activity will be carried out for providing

roads, sewage network, storm water system, and places required for providing buildings for

administration, production/manufacturing plant and other utility erections. According to the

engineering assessment; most of the excavated material shall be reused within the proposed MTP.

Most of the construction dust will be generated by the movement of carrying vehicles on unpaved

roads. Unloading and loading of constructional materials shall also act as a potential source for dust

nuisance. The control measures proposed to be taken up are given below:

Water sprinkling on main haul roads in the proposed MTP will be done; this activity will be carried out at least twice a day. If need arises (such as on windy days), the frequency will be increased; in this way around 50% reduction on the dust contribution from the exposed surface will be achieved.

The duration of stockpiling of excavated material will be as short as possible; as most of the material will be used as backfill material for road development.

Temporary tin sheets of sufficient height (3 m) will be erected around the proposed construction site as barrier for dust control.

Tree plantations around the boundary, along the roads will be initiated at the early stages by plantation of 2 to 3 years old samplings using drip irrigation / watering at regular intervals so that the area will be moist for most part of the day.

Page 219: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 9.2

All the vehicles carrying raw materials will be covered with tarpaulin/plastic sheet and the unloading and loading activity will be stopped during windy period.

To reduce the dust movement from civil construction site to the neighbourhood the external part of the building under construction will be covered by plastic sheets.

Given the implementation of proper control measures for dust suppression, no adverse impacts are

expected and compliance with the Ambient Air Quality is achieved at ASR’s (Air Pollution Sensitive

Receivers) at all time.

9.2.2 Water quality mitigation measures

During the development of proposed MTP necessary precautions will be taken, so that the runoff

water from the proposed site gets collected in working pit and if any over flow, it will be diverted to

nearby greenbelt/plantation area.

At the time of construction in the proposed MTP, all the equipment washed water will be diverted to

working pit to arrest the suspended solids if any and the settled water will be reused for

constructional purposes, and for sprinkling on roads to control the dust emission.

The waste generated from the proposed project site, will be segregated like used oil, lubricants, etc.,

and disposed to authorized recyclers. The waste like soiled cotton, paper, etc., will be disposed to

municipal bins or sold-out to the authorised agencies. The domestic wastewater generated from

temporary toilets used by the work force will be treated through sewage treatment plant and

reused. Therefore, impact on water quality due to the proposed MTP would be insignificant.

9.2.3 Noise mitigation measures

Noise generating equipment will be used during daytime for brief period of its requirement. Proper

enclosures will be used for reduction in noise levels, wherever possible the noise generating

equipment will be kept away from the human habituation. Temporary tin sheets of sufficient height

(3 m) will be erected around the noise generating activity or all around the proposed site as barrier

for minimizing the noise travel to surrounding areas. Therefore, impact on noise environment due to

proposed MTP would be insignificant.

All vehicles entering into the proposed site will be informed to maintain speed limits, and not blow

horns unless it is required. Personal protective equipment like ear-muffs, helmets covering ears

would be provided to the workers working near noise generating equipment and will see that

workers use the protective gadgets regularly.

9.2.4 Solid waste mitigation measures

The solid waste generated during constructional period being predominantly inert in nature,

construction and demolition waste does not create any chemical or biochemical pollution. However,

maximum effort would be made to reduce, reuse and recycle them. The most of the solid waste

material will be used for filling/levelling of low-lying areas. All attempts will be made to stick to the

following measures.

Page 220: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 9.3

All construction waste shall be stored within the proposed site itself. A proper screen will be provided so that the waste does not get scattered

Attempts will be made to keep the waste segregated into different heaps as far as possible so that their further gradation and reuse is facilitated

Materials, which can be reused for purpose of construction, levelling, making roads/pavement will also be kept in separate heaps from those which are to be sold or land filled.

The local body or a private company may be arranged to provide appropriate number of skip containers/trolleys on hire

The use of the construction material basically depends on their separation and conditions of the

separated material. A majority of these materials are durable and therefore, have a high potential

for reuse. It would, however, be desirable to have quality standards for the recycled materials.

Construction waste can be used in the following manner.

Reuse of bricks, tiles, stone slabs, timber, piping railings, and so on, to the extent possible and depending upon their conditions.

Sale/auction of materials which cannot be used at the proposed site due to design constraint.

Plastics, broken glass, scrap metal, used cement bags, etc., can be sold-out to the authorised agencies.

Rubble/brick bats can be used for building activity, such as levelling and under coat of lanes, where the traffic does not constitute heavy moving loads.

Larger unusable pieces can be sent for filling-up of low lying areas.

Fine material, such as sand and dust, can be used as cover material

Unearthed soil can be used for levelling as well as for lawn development

Broken pieces of the flooring material can be used for levelling in the building or can be disposed off

Unused or remaining paints/varnishes/wood can either be reused or can be disposed of to the authorised agencies

9.2.5 Ecological aspects

In the proposed project site, no major vegetation is present and hence there will not be any negative

impact on the existing plantation. However, the proponent is going for plantation along the boundary,

along the roads during construction activity. A comprehensive greenbelt program will improve the

ecological condition of the region.

Page 221: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 9.4

9.2.6 Site security

Adequate security arrangement would be made to ensure that the local inhabitants and the stray cattle

are not exposed to the potential hazards of construction activities.

9.3 Management during operational stage

Necessary control measures will be undertaken at the design stage to meet the statutory

requirements towards minimizing environmental impacts.

The design basis for all member industries will lay special emphasis on measures to minimize the

effluent generation and emission control at source. The specific control measures related to gaseous

emissions, liquid effluent discharges, noise generation, solid waste disposal etc., are described

below:

9.3.1 Air quality management

a) Reduction of emissions at source

To control the dust particulates from the stacks to meet the MoEF&CC standards through

appropriate air pollution control equipment’s are proposed. To control SO2 and NOx emissions from

DG set stack of member industries, stack of sufficient height is proposed to meet the MoEF&CC

guidelines.

b) Air pollution control

The main sources of air pollution from the proposed MTP are diesel generator (DG) and Boiler

emissions. The DG and Boilers are being proposed and operated by the member industries in the

MTP. The DG sets will be used by respective individual units and common utilities during power

failure for emergency requirement, whereas the boilers are used for steam requirement of

individual units and common utilities. The air pollution control measures to be adopted are

summarized in Table 9.1.

Table 9.1: Air pollution control measures

S. No. Air pollutant Source Control

As common facilities

1. PM10/PM2.5/SO2/NOx and CO DG Sets & boiler Stack height and air pollution control equipment meeting MoEF&CC regulations.

At individual industry

2. Process emissions of member industries

Fugitive in nature during material flow

Standardization of equipment and accessories (engineering standards)

3. PM10/PM2.5/SO2/NOx and CO

DG sets and boilers of member

industries

Stack height and air pollution control equipment meeting MoEF&CC regulations.

c) Particulate emissions

The Permissible AAQ standard as per ministry of environment, forests and climate change for

industrial, residential and other areas are 60 µg/m3 for PM - (<2.5 µm ) and 100 µg/m3 for PM - (<10

µm ) using respirable/fine dust sampler (RDS) by gravimetric method.

Page 222: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 9.5

The DG Sets and Boilers used by member industries and common utilities operating in the proposed

MTP, as part of an agreement - must include the provision air pollution control equipment’s to attain

the prescribed limits of NAAQ Standards, 2009—industrial, residential, rural and others for

particulate matter (<2.5µm and <10µm).

d) Control of gaseous emissions

To minimize the Sulphur dioxide emission on ambient air, the stack height for letting of flue gases at

safe dispersion height has to meet the standards laid down by MoEF&CC. The majority source of SO2

emission will be due to DG set and boiler operations by the member industries. Advanced

combustion technology with low NOx burners will be provided to limit NOx emissions to 200 g/GJ.

9.3.2 Water and waste water quality management

a) Water management

The primary source of water for the proposed MTP is industrial water supply by Government of

Telangana. The major part of this water will be supplied to the member industries used for industrial

needs and the minor part of this water will be used for domestic requirement.

b) Wastewater generation

It is proposed to install full-fledged treatment plant for treating the industrial effluents and sewage

generated by the member industries and from common utilities in the proposed MTP. All the

upcoming member industries have to treat their wastewater in their respective industrial units up to

meeting inlet standards of the proposed CETP.

Common Effluent Treatment Plant (CETP) and Common Sewage Treatment Plant (CSTP) for treating

the industrial effluents and sewage generated from member industries is proposed so as to meet the

statutory requirements for disposal and reuse of the wastewater.

9.3.3 Rain water harvesting and storm water management

Based on the rainfall intensity of the proposed site, storm water drainage system will be designed. It

consists of well-designed network of open surface drains and rainwater harvesting pits along the

drains so that all the storm water is drained of without any water logging. It is planned to achieve

proper utilization of rainwater by using appropriate water harvesting mechanism. Rainwater

harvesting will be done by the construction of harvesting pits all along the storm water drainage

network at a definite pitch. Necessary expert advice will be taken in this regard.

Under Corporate Social Responsibility (CSR) activity, to improve the recharging capacity of the

aquifer, greenbelt development will be taken up by individual industries

9.4 Noise level management

All the noise generating equipment in the MTP will be designed not to exceed the noise levels 85-90

dB (A) as per the OSHA (occupational safety & health administration) standards. The equipment shall

be provided with acoustic shields/enclosures to minimize the sound level inside the member

industries of the proposed MTP. Greenbelt will be developed along the boundary, along the roads,

within setback areas of industrial units to prevent noise generation beyond the MTP boundary.

Page 223: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 9.6

The following measures are suggested to keep the noise levels within the permissible standards in

member industries:

Noise barriers will be placed around the stationary noise generating equipment of the

proposed MTP and also along the side of moving objects

All noise generating machines like pumps, compressors, etc., shall be properly serviced and

mounted on anti-vibration pads to reduce the noise generation

The DG sets shall be provided by acoustic enclosure

Proper maintenance of transportation vehicles will be done

In addition to this, the open areas in the proposed MTP shall be provided with adequate greenbelt to

minimize the noise levels. The proponent of member industries during operation of their plants

would monitor the noise levels within and outside the plant on a regular basis to attain national

standards for noise quality are strictly adhered to. Corrective action would be initiated immediately

in case of any deviations are found during the course of monitoring.

9.5 Solid waste management

The waste generated by the member industries/manufacturing units can be classified as:

Manufacturing process waste—may fall under the hazardous and non-hazardous waste

category

Waste from utilities such as ash, paper and plastic and other packing waste

Pollution control facilities—primary STP/ETP sludge

All the member industries coming up in the proposed MTP, with respect to the category and type of

waste, will segregate and store the waste temporarily in an earmarked area. If required, the services

of the common hazardous waste management facility (CHWMF) which already exists in Dundigal,

Hyderabad will be utilized. All the hazardous waste from member industries will be transported to

CHWMF facility for treatment and for further safe disposal as per the statutory requirement and

procedures. Safe storage and transportation of the produced solid and hazardous waste is the total

responsibility of the member industry.

Municipal solid waste would be collected and stored in an earmarked storage yard and further hand

over to the authorized facility for treatment and disposal by the member industries and by the

developer.

9.6 Greenbelt development

In order to comply with the MoEF&CC guidelines for greenbelt development within the proposed

MTP, management will develop thick greenbelt of tall and evergreen plants 15 m along the

periphery, 2m along the roads and within setback areas of the individual industrial units.

MTP official will also instruct and make an agreement (MoU) with member industries to develop

greenbelt and along the periphery of the member industries. Sufficient space, resources and man

power for development and maintenance of greenbelt are provided in the plan. Greenbelt

development is one of the most effective environmental pollution control measure. Trees play vital

role in the environment in preventing the horizontal dispersion of the pollutants to the surrounding

areas. They are very effective in trapping the pollution causing agents viz., dust and gaseous

Page 224: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA-EMP Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 9.7

pollutants. They are also considered to be excellent indicators of excessive ground level

concentrations. The greenbelt is being proposed for the following objectives.

Mitigation of fugitive dust emissions

Noise pollution control

Prevention of soil erosion

Balancing eco-environment

Aesthetics

Apart from the bulk plantation in vacant areas, roadside avenue plantations, parks will also be taken

up. The placement of the plants would be designed as follows:

Trees growing up to 10 m or more in height with thick canopy cover and perennial foliage would be planted around the proposed MTP

Planting of trees would be done in rows with minimum three rows encircling perimeter of the installation. While planting the trees care would be taken that the installation structure would be difficult to see through foliage when seen from a point outside the green envelope. For preventing the horizontal dispersion of pollutants, if any, the trees planted in alternate rows would fall in straight line.

Trees would be planted on roadside for containment of vehicular traffic emissions and fugitive emissions due to the movement of vehicles.

Tree trunks being free foliage up to a height of 2 to 3 m, it is also proposed to grow shrubs in front of trees so as to give coverage to the open portion.

Sensitive species like Mangifera indica will be planted in patches along the entire greenbelt to work as an indicator of pollution potential.

9.7 Fire protection services

Fire protection is one of the most essential services in the proposed MTP and overhead water

storage tanks with a required storage capacity shall be constructed at park level, individual member

industries will also should maintain sufficient water within their premises in overhead tanks for

emergency needs.

All the member industries within the proposed MTP are expected to have their own unit or site

specific fire protection system and the common fire protection system as additional backup and

support required combating any eventualities due to fire accidents. In addition to this, a fire station

is recommended with adequate fire protection personnel and other standard fire protection devices

to attend the fire calls from the industries within the MTP or strengthen the services of the common

fire station available nearby appropriately to the requirement of the MTP and use their services as

and when required.

The firefighting facilities listed above are planned for combating the fire emergencies in the MTP.

However, during the allotment of lands/approvals for setting up of the units, the MTP management

shall inform respective industry to comply with the guidelines laid down in the safety policy of the

proposed MTP.

Page 225: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 10.1

Chapter – 10 Summary & Conclusion

10.1 Project objectives

The State Government of Telangana through Telangana State Industrial Infrastructure Corporation

Limited (TSIIC) proposes to develop a Mega Textile Park (MTP) with state-of-the-art manufacturing

facilities for ginning, spinning, weaving, knitting and Textile processing at Shayampet village of

Geesugonda mandal and Chintalapalli village of Sangem mandal in Warangal district. The proposed

MTP will be implemented in five phases in 1190 acres of land.

TSIIC envisages establishing world class integrated common infrastructure in the proposed Park with

plug and play built up infrastructure and common facilities to support the Textile and Apparel

Industry to move up in the value chain. The Master Plan for the Project is prepared with an objective

to cover all activities in the Textiles value chain and help the Industry in Telangana in achieving

economies of scale.

Details of Project:

Details Description

Location Shayampet village of Geesugonda Mandal and Chintalapalli village of Sangem Mandal, Warangal Rural Dist., Telangana State

Coordinates 170 54’ 29” N and 780 41’ 37” E

Land 1190 Acres (481.57 ha)

Nearest habitation 0.6 Km E of Chintalapalli villages; 0.7 Km N of Shayampet villages; 0.5

The Warangal-Khammam railway line is passing through the project site. The closest railway stations being Vanchanagiri and Chintalapalli.

Airport Hyderabad International Airport 190 Km SW.

Sea Port Machilipatnam (330 Km); Kakinada (400 Km); Visakhapatnam (530 Km); Chennai (665 Km). There is a proposal for a dry (Inland) port in Telangana.

Rivers/canals SRSP (Kakatiya) canal which is passing along the boundary from North to south west side of the site.

Water bodies Sangem lake 3km S, Yelgur lake 3.5km SE, Gadepally lake 1.5kmW, Bhadrakali lake 11.5km NW

Seismicity Seismic Zone II (least active)

Hills/Valleys None

Archeologically Important places

Warangal Fort 8.0km NW; 1000 Pillars Temple 14.0km NW; Bhadrakali Temple 11.5km NW

National Parks/ Wildlife sanctuaries

None

Reserved & Protected forests

None

Defence Installations None

Km W of Venkatapuram villages; and 0.6Km of Sangem Taluk.

Present Land Use Partly barren land, partly double crop land

Road connectivity Warangal-Narsampet (3Km) N. The NH-163 is underway.

Rail Connectivity Kazipet & Warangal are two major stations. South Central Railway zone.

Page 226: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 10.2

10.2 Project background

Telangana is the twelfth largest State in India both in terms of area and population. Telangana is an

important Textile hub in India and has major locational advantages with international airport at

Hyderabad, extensive railway & road network, stable power situation, improved telecommunication

system and plenty of natural resources.

The major cities in Telangana are Hyderabad, Warangal, Mahabubnagar, Karimnagar, Nizamabad,

and Khammam. 15 National Highways of length 2,495 km cross Telangana and 24 State Highways of

length 1,815 km cover the State. South Central Railway (SCR) headquartered at Secunderabad is the

second highest revenue earning zone in Indian Railways. The international airport at Hyderabad

connects domestic and international destinations and handles cargo to all over the world and major

cities in India.

Telangana is one of the largest producers of long staple cotton with production of around 43 lakh

bales per annum. The State stood at third position in the country in cotton production during the

year 2014-15. The State is known for skilled Textile workers but due to absence of industry, they

migrated to other states for their livelihood.

There are 33 spinning mills with capacity of 10 lakh spindles, which consumes only about 20% of the

cotton grown in the State with the rest 80% going to other states for spinning. Capacity utilization of

weaving industry in the State is negligible and there is not much processing capacity available in the

State. There is no further downstream facility like processing and garmenting.

After bifurcation of the State, 75% of the pre-division cotton growing areas have remained in the

State while only 20% of the pre-division spinning capacity remains in the State. Thus most of the

cotton goes to neighboring states for value addition, and so does the majority of the cotton yarn.

The availability of high cotton production and labour force presents an opportunity to create large

integrated Textile manufacturing capacities in the State. This will also support overall industrial

development in the State.

10.3 Proposed project

The MTP is proposed to be located in a district which is a major cotton producing district and trading

centre in the State. The region has a strong presence of Textile clusters (Warangal Durries) and

skilled manpower. The proposed Project envisages ploughing back economic benefits of the Park to

the local populace by catering to all activities in the Textile value chain.

TSIIC is a progressive Government organization responsible for planning and development of

industrial infrastructure in the State. TSIIC is known for creating landmark infrastructure projects in

the State, which are fueling economic growth. TSIIC proposes to develop the MTP in Warangal.

TSIIC proposes to establish the MTP on 1190 acres of land with world class integrated infrastructure

which shall broadly include

(i) Common Infrastructure

(ii) Built-Up Physical Infrastructure

(iii) Common Facilities

(iv) Social Infrastructure

Page 227: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 10.3

The proposed MTP shall be implemented in a phased manner depending on the market demand.

Due to the large size of the Project, a long term strategy shall be adopted for the complete

implantation of MTP. The phasing approach shall not only help in ensuring sustainable development

of the Park but also in ensuring availability of fabric, accessories and man power for 75% of sales

value of garments.

10.4 Description of Environment

As described of baseline studies of the 10 km radius of surrounding of project site area. The data

collected has been used to understand the existing environment scenario around the proposed MTP

project against which the potential impacts of the project can be assessed. The present activities will

not have any adverse impacts on any of the common property resources of the village communities,

as the project area is not being used for any purpose by any section of the society in this region.

Environmental data has been collected by monitoring for:-

a) Air b) Water c) Noise

Maximum value for PM10 was observed as 53.1 µg/m3 at Geesugonda (AAQ 8) and minimum

value is 41.3 µg/m3 at Kanaparti (AAQ6). NAAQ stipulated standard for PM10 for 24 hr

average is 100 µg/m3.

Maximum value for PM2.5 was observed as 32.1 µg/m3 at Geesugonda (AAQ 8) and

minimum value is 19.7 µg/m3 at Kanaparti (AAQ6). NAAQ stipulated standard for PM2.5 for

24 hr average is 60 µg/m3.

Maximum value for SO2 was observed as 12.2 µg/m3 at Geesugonda (AAQ 8) and minimum

value is 6.6 µg/m3 at Kanaparti (AAQ6). NAAQ stipulated standard for SO2 for 24 hr average

is 80 µg/m3.

Maximum value for NOx was observed as 21.0 µg/m3 at Geesugonda (AAQ 8) and minimum

value is 14.2 µg/m3 at Kanaparti (AAQ6). NAAQ stipulated standard for NOx for 24 hr average

is 80 µg/m3.

Maximum value for O3 was observed as 19.8 µg/m3 at Geesugonda (AAQ 8) and minimum

value is 10.1 µg/m3 at Kanaparti (AAQ6). NAAQ stipulated standard for O3 for 8 hr average is

100 µg/m3.

Maximum value for CO was observed as 580 µg/m3 at Geesugonda (AAQ 8) and minimum

value is 310 µg/m3 at Kanaparti (AAQ6) & Venkatapuram (AAQ5). NAAQ stipulated standard

for CO for 8 hr average is 2000 µg/m3.

d) Soil e) Socio-economic f)Biological

a) Air Quality

The present activities will not have any adverse impacts on any of the common property resources

of the village communities, as the project area is not being used for any purpose by any section of

the society in this region.

Page 228: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 10.4

b) Water Quality

The analysis results indicate that the pH of the ground waters was to be in the range of 7.1 at

Katrapalli (GW4) and 7.8 at Shayampet (GW2). The TDS were found to be in the range of 335 mg/l at

Shayampet (GW2) and 1684mg/l at Sangem (GW5). Out of the 11 samples only 3 samples

Shayampet (GW2), Chintalapalli (GW3) and Mondrai (GW11) were within the acceptable limits and

remaining was within the permissible limits. Other parameters like Chlorides and Sulphates were

observed to be well within the acceptable limits. It is seen that the physico-chemical analysis for all

the parameters are within the standards as per IS: 10500:2012.

c) Noise Levels

It is observed that the day equivalent and night equivalent noise levels at all locations are within

prescribed CPCB standards.

Day equivalent noise levels (Ld) ranged between 51.8 to 53.9 dB (A) and Night equivalent noise levels (Ln) ranged between 40.9 to 43.1 dB (A) for residential areas.

Sangem is the only residential cum commercial location where the Day equivalent noise levels (Ld) is 52.9 dB (A) and Night equivalent noise levels (Ln) is 42.8 dB (A).

d) Soil Quality The soil samples are analysed and results are obtained is compared with the standard soil

classification given Agriculture Soil Limits. It has been observed that the soils are sandy clay in

texture and neutral in nature. The nutrient and organic matter contents are medium and the soil is

normally fertile. The available Nitrogen is varies from 148 Kg/ha (Kanaparti) to 251 Kg/ha (Project

Site) is indicating low range. The available Phosphorous varies from 6.9 Kg/ha (Chintalapalli) to 11.4

Kg/ha (Venkatapuram) is indicating medium range and available Potassium is varies from 264 Kg/ha

(Chintalapalli) to 372 Kg/ha (Mondrai) is indicating High range in the study area.

e) Socio-economic

The information on socio-economic aspects of the study area has been compiled from secondary

sources & Field work, which include various public offices, as indicated in the above section. The

sociological aspects of this study include human settlements, demography, social such as Scheduled

castes and Scheduled Tribes and literacy levels besides infrastructure facilities available in the study

area. The economic aspects include occupational structure of workers.

f) Biological

The area is devoid of vegetation and wild life. The proposed project site is confined for Mega Textile

Park with an area of 1190 acres. Major scale of flora – fauna activities will be affected by the

proposed activity. There is no Wild Life Sanctuary within 10km from the project site. There is no RF.

The detailed biological environment described in Chapter-3 of Section 3.11.

The study area was divided in two major parts namely the Core area and buffer area.

Core Area: the core area is mostly comprised of project site and the area is flat with fallow

agriculture land with barren patches.

Buffer Area: The buffer area i.e. area surrounding the project site is majorly occupied by the

agriculture fields. The board categories of the land use types in the buffer area include fallow

agriculture fields, waste land, water bodies and scrubs.

Page 229: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 10.5

10.5 Estimated project cost

Based on the block estimates for the various facilities proposed in MTP, the aggregate cost of the

Project was presented the Table below.

Considering that the Project shall be implemented over five phases, the Project Cost mentioned

above has been further bifurcated for respective phases based on the total area to be developed in a

particular phase. The component like CETP will be taken up on Public Private Partnership (PPP)

mode.

S.No Project Cost Amount (Rs. in crores)

1 Roads 91.68

2 Storm water drain 27.16

3 Water supply 78.07

4 Sewage system 39.41

5 Electrical Infrastructure 71.83

6 Landscaping 8.00

7 Common Infrastructure 55.80

Total Project Cost 371.95

EMP budget: The cost for EMP budget would be 5% of the Total Project Cost.

10.6 Proposed means of finance

The Promoters of the Project proposes to place the MTP for approval of grant/funding from

Government of India and Government of Telangana under suitable schemes.

10.7 Conclusion

Warangal is the highest cotton growing district in Telangana and has one of the largest cotton

market yards in the region. Apart from cotton, presence of cotton ginning & pressing facilities,

availability of water and good railway & road connectivity make Warangal an attractive destination

to establish the MTP Project. In terms of availability of skilled manpower, it has been seen that

majority of skilled workers in Textile sector who migrated to other Textile hubs such as Andhra

Pradesh, Tamil Nadu and Maharashtra are originally from Warangal.

The MTP will establish state-of-the-art infrastructure, modern plug and play facility and world class

common facilities. The Park will be developed on a vertical integrated model to cover complete

Textile chain in one place. The Project shall meet the Industry standards and compliances and

thereby allowing the member units to complete globally. The Project will help in positioning

Telangana as a global sourcing hub for large scale buyers.

By considering the entire baseline data collected during December, 2016 - February, 2017 as part of

the EIA study conducted in the study area and by evaluating all the possible environment impacts of

the project, it can be concluded that project activities during construction and operation phase of

this proposed Project will not have any significant negative impact on environment. If all the

environment management plans, Disaster management plan given is strictly followed. More over

this project will have a positive impact on the socio economy of this region as source of

employment.

Table 10.1 Estimated Project cost for phased development

Page 230: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 11.1

Chapter – 11

Diclosure of Consultants

11.1 About the Group

Since inception in 1994 in Hyderabad, India, Ramky has been focusing on developing projects that

positively impact both the environment and the economy as a whole. Ramky has progressed at a

consistent pace to become one of India’s leading players in the infrastructure development and

environment management sectors.

As part of the blueprint to be an active participant in global economic progress, Ramky Group has

augmented potential in key growth sectors including Water & Waste Water, Transportation,

Industrial Infrastructure, Commercial, Residential, Social, Institutional and Irrigation Infrastructure,

Environment Management , Waste & Water Management, Energy Generation, transmission and

distribution and many others.

Our focus areas are Infrastructure Development, Environment Management, Real Estate and

Consultancy; as an engineering, procurement and contracting partner; as well as developing and

managing the assets for long term. We have successfully executed projects for design, engineering

and construction on BOT and BOOT basis, while handling more than 80 Public Private Partnership

projects in the Country – one of the largest being handled by any Group, for developing

infrastructure in the Country. We’re the preferred partner to government and private players alike

because all our companies have implemented ISO 9000, ISO 14000, ISO 17025 and OHSAS 18000

quality systems at work, with a clear commitment to quality.

In the field of Environment and Waste Management, the group has pioneered bio-medical waste

and hazardous waste management facilities in India. We are now the market leaders with over

50% market share in Solid Waste Management (SWM) with 60 projects on ground/under setup

including medical waste management, hazardous waste management and municipal waste

management.

Ramky’s global outlook has picked up momentum… so much so that we have a considerable

workforce operating from outside India. The Group has a pan-India presence with more than 500

project locations across 23 States (including Union Territories). Internationally, the Group’s

footprints can be seen in U.S.A, Singapore, Saudi Arabia, UAE, Vietnam, China, West Africa, and

Peru.

The major companies of the group are: 1) Ramky Infrastructure Ltd (RIL).

2) Ramky Enviro Engineers Ltd (REEL)

3) Ramky Enviro Services Pvt. Ltd (RESPL)

4) Ramky Estates & Farms Pvt. Ltd. (REFL)

5) Ramky Life Sciences Ltd (RLSL)

6) Ramky Foundation (RF)

Page 231: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 11.2

11.2 About the Accredited Consultant Organisation

Ramky Enviro Engineers Limited (REEL) is the consulting arm of the group provides vital function of

effectively providing the backward linkage to the project implementation function in the form of

concepts, strategies, structuring, planning and designing infrastructure projects. A multi and cross

disciplinary team of professionals, offering solution at each stage of the life cycle of a project.

It is one of the well-established and leading Environmental Engineering concern in this country

having under taken Ten Industrial Estate projects which involves the duties of project scheduling and

budgeting, Topographical surveying and soil investigation, Environmental and social impact

assessment, market viability, Master Planning, land use Planning, design of Roads, Water supply

system, CETP, Storm Water Drainage, Electrical System, Cost Planning, Financial Feasibility, Project

Structuring and Draft Concession Agreement, Bid Process Management etc.

Our Company also designs, manufactures and supplies almost the entire range of equipments

required for ETPs, STPs and WTPs. Consultancy Division is one of the departments of REEL. The

services offered by the consultancy division are given below.

11.2.1 Consultancy Services

Facilitating Environmental Clearances from MOEF, New Delhi.

Obtaining Consent for Establishment and consent for Operation from state pollution Control Boards Preparing of Environmental Impact Assessment Reports.

Environmental Audits to help industries to recycle and reuse resources and plan for low polluting technologies.

Risk Assessment Studies for hazardous chemical storage & Process in order to devise viable onsite and offsite emergency plans.

Identification and evaluation of hazardous Waste disposal sites.

Environmental management systems, training, documentation and implementation as per ISO 14001:1996 Standards.

Characterization and quantification of biomedical waste, municipal solid waste and design of disposal facilities.

Environmental management strategies to mitigate adverse impacts arising out of developmental activities.

Effluent treatment plant design after thorough review of process, reaction mass balance and treatability studies of effluents.

Post project Monitoring network design

Consultancy Services for setting up environmental laboratories

Design of Sewage treatment plants

Page 232: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 11.3

Design of Waste treatment plants

Health and socio- economic surveys

Resettlement and rehabilitation plans

Systems development for ISO 9000, OSHAS 18000, NABL, ISO 17025 Standards

11.2.2 Laboratory services

Analysis of air samples for ambient air quality and those collected from industrial sources for both routine and industry specific pollutants

Water and waste water analysis for all parameters as for standard methods, including pesticides and poly hydro carbons

Solid and hazardous waste analysis including TCPL tests

Monitoring of noise levels at source and in ambient air

Development of new methods and quality assurances of results obtained

Design and settings of laboratories

11.2.3 Training services

Monitoring of environmental parameters –air, water, noise, soil etc.

Environmental impact assessments

Effluent treatment plant operations and maintenance

Sewage treatment plant operations and maintenance

ISO 9000 & 14000, OHSAS 18000 Awareness, documentations, internal auditors

Establishment environmental laboratories

Pollution control in industries

Biomedical waste management

11.2.4 Field Services

Site selection and suitability studies for settling up of Industries

Ambient Air Quality monitoring for all pollutants

Noise Level Monitoring

Meteorological data collection as per CPCB norms

Stack Emission monitoring for all pollutants & assessment of efficiency of control equipment

Page 233: for Proposed · 1.8 Project Development Plan 1.6 1.9 Scope of the study 1.6 1.10 Legal frame work for the implementation of EC conditions 1.7 Chapter 2 - Project Description 2.1 General

EIA Report for Proposed Mega Textile Park at Warangal

Ramky Enviro Services Pvt. Ltd. 11.4

Water, Wastewater and Soil Sample Collection

Assessment of efficiency of ETP and analyzing critical parameters of field.

Flora and Fauna assessment through sectorial studies and damage assessment due to development projects

Damage Assessment studies in case of oil well blowouts, major industrial accidents. 11.2.5 Treatment Plant Services

Water Treatment Plants-design, construction, operation and maintenance

Efficiency studies of Effluent Treatment plants

Design, construction, operation and maintenance of ETP

Upgradation/modification of ETP

Sewage Treatment Plants-design, construction, operation and maintenance along with mechanical equipment erection

Supply of mechanical equipment

11.2.6 Solid Waste Management Services

Industrial Waste Management

Hazardous Waste Management

Municipal Solid Waste Management

Biomedical Solid Waste Management

E-waste Management

11.3 Declaration by Accredited Consultant Organization

The Company has over 2000 employees in various sectors of which over 600 employees are post

graduates and about 15 employees are having Ph.D’s. The Analysis was carried out in the Laboratory

of Hyderabad Waste Management Project, a subsidiary company under Ramky Enviro Engineers Ltd.

which is NABL accredited and recognized as Environmental Laboratory by Ministry of Environment

and Forests under the Environment (Protection) Act 1986 vide notification dated: 9th Jan, 2008.