FLNG Training Module 1.1 Introduction to FLNG Rev 1

download FLNG Training Module 1.1 Introduction to FLNG Rev 1

of 34

Transcript of FLNG Training Module 1.1 Introduction to FLNG Rev 1

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    1/34

    FLNG FundamentalsModule 1.1: Introduction to FLNG

    LNG industry overview

    Development and history

    LNG properties and specifications

    Opportunities and advantages of FLNG

    Offshore considerations and challenges

    12/07/2015 1FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    2/34

    Most gas is transported by pipeline - Why LNG?

    Volume advantage for storage and transportation Transport over wide and deep oceans

    Economic advantage of LNG vs. pipeline gas dependent on distance

    World Bank estimates 140 billion standard cubic metres of gas was

    flared in 2011 (about 40% of the LNG traded), producing 360 million

    tonnes of CO2without any beneficial heat or power production

    Disadvantages of natural gas liquefaction:

    Energy intensive

    Capital intensive Requires specialised terminals and carriers

    Purity Requirements

    Cryogenic handling (materials, safety)

    12/07/2015 2FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    3/34

    Most gas is liquefied onshore -Why FLNG?

    FLNG is predicted to become an important sector of the LNG

    industry:

    While most of the easy onshore gas fields have been tapped, there areconsiderable stranded gas reserves offshore

    There is growing opposition to locating LNG plants onshore (e.g. JamesPrice Point in Australias Kimberley Region) for environmental or landuse zoning factors. Floating LNG import terminals are already gainingpopularity for this reason

    Environmental impacts may be reducedone example is reduction ofdredging in harbours for laying gas pipelines and for entry of LNGcarriers

    Possible cost and schedule advantages, though FLNG operatingexpense may be high

    As with any novel application of technology, some risk is associated withinitial application of FLNG. Teething problems can be expected withthe first FLNG applications, but subsequent FLNG projects can beexpected to become more straightforward

    Experience gained by first FLNG operators will provide a competitiveadvantage

    12/07/2015 3FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    4/34

    The cryogenic industry developed in the second half of the nineteenth

    century. Among others, Dr Carl von Linde developed and patented air and

    gas separation technologies in Munich, Germany. The LNG industry startedits early development in the USA by using LNG technology for natural gas

    peak shaving.

    1964: First base load LNG export plant begins operation in Arzew, Algeria

    using a cascade process designed and constructed by Technip/Air Liquid.

    Exports were initially to Canvey Island, UK and Le Havre, France.

    The first LNG cargo from Arzew was transported to Canvey Island on theRiver Thames in England on board the first purpose-built LNG carrier

    Methane Princess, which had a capacity of 27,000 m3.

    1968: The mixed refrigerant concept was presented in a paper at the LNG-1

    conference in Chicago

    1969: Kenai LNG plant comes on stream in Alaska USA, designed and

    constructed by Phillips Petroleum and Bechtel, exporting to Japan. The

    Kenai plant was mothballed for a while in 2012 but is currently back in

    production with licence to export until 2015

    1970: An LNG plant using an SMR process by APCI started up in Marsa El

    Brega, Libya, exporting to Italy and Spain

    Development History

    12/07/2015 4FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    5/34

    Development History

    Air Products developed the SMR process into the C3/MR process which

    was first applied in Brunei, starting up in 1972

    The C3/MR process enjoyed unprecedented success between 1972 and1999, with train sizes increasing from 1.4 MTPA (Brunei) to 3.2 MTPA

    (QatarGas). The only other technology built during this 27 year period

    was the Prico SMR process in Skikda Algeria by Pritchard-Rhodes (now

    Black & Veatch)

    In 1999, the first Optimised Cascade train (3 MTPA) started up in PortFontin Trinidad designed by ConocoPhillips and Engineered by Bechtel

    The Trinidad plant reintroduced competition into the industry and

    though APCI continued to dominate, both C3/MR and Optimised

    Cascade technologies were successfully developed reaching train sizes

    of 5 MTPA around 2005. In this period, there was a boom in

    construction of LNG plants and costs began to escalate significantly

    In 2004, Shell began to license its own version of the C3/MR process (a

    long-held ambition) starting with the Australian North West Shelf Train 4

    at 4.2 MTPA

    12/07/2015 5FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    6/34

    Development History

    Linde developed the Multifluid Cascade process which was implemented in

    the Norwegian Snohvit LNG plant, starting up in 2007 with a train size of

    4.3 MTPA. Initially, the Snohvit plant exhibited poor availability and wasfrequently shut down for cleaning, repair or modification

    Meanwhile Shell developed the Dual Mixed Refrigerant process and

    successfully applied it on Sakhalin Island in Russia with train sizes of 4.8

    MTPA, starting up in 2008

    At Gastech in 2002, APCI rolled out its large train APX process. After

    much development, the first 7.8 MTPA APX train was started up in Qatar in

    2009. Six APX trains were built in total, all in Qatar, for RasGas and

    QatarGas. The last, QatarGas IV, started up in 2011

    Other licensors, including ConocoPhillips and Shell, have designed large

    scale process, but at present there appear to be no plans to build any new

    trains of significantly larger capacity than 5 MTPA Construction of new liquefaction capacity slowed, with Pluto being the only

    new train added in 2012. Angola LNG joined the ranks of LNG exporters

    in 2013. PNG LNG started up in 2014, along with an Algerian expansion

    train and the first train using Queensland coal seam gas (QCLNG).

    12/07/2015 6FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    7/34

    Development History (FLNG)

    After years of research and development of several prototype FLNG

    facilities, Shell announced FID for a floating LNG facility, Prelude, offshore

    northwest Australia in 2011. Prelude will use the Shell DMR process for asingle train of 3.6 MTPA capacity. The FLNG facility is now under

    construction at Samsung shipyards in Korea and will be the largest

    floating structure ever constructed

    In 2013, Petronas achieved FID for its PFLNG1 floating LNG project.

    PFLNG1 will use a nitrogen expander process with a capacity of 1.2

    MTPA and will be positioned off Sarawak Also in 2013, Exmar and Pacific Rubiales announced that construction

    had started on an FLNG project for Columbia, consisting of a barge

    mounted liquefaction facility in near-shore, benign waters. Capacity is 0.5

    MTPA using an SMR process, but project was deferred in 2015

    In 2014, Petronas announced that FID had been reached for its PFLNG2

    facility to be positioned offshore Sabah with a capacity of 1.5 MTPA

    Golar also announced start on conversion of an LNG carrier for FLNG in

    2014. A number of other FLNG facilities are in FEED stage or undergoing

    concept development or preFEED

    12/07/2015 7FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    8/34

    Refrigerant

    Import

    12/07/2015 8FLNG Essentials

    Components of an LNG Plant

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    9/34

    Components Comments related to FLNG

    Gas Receiving, liquids

    separation and stabilisation

    Onshore LNG plants often have slug catchers

    with a large footprint. For FLNG, reducing deck

    space is paramount

    Gas TreatingRemoval of

    acid gases, water and mercury

    All required for FLNG. High sulphur

    concentrations present a problem for floating

    facilities

    Heavy hydrocarbon removal

    and fractionation

    Dependent on feed gas composition. For

    FLNG, less is better

    Liquefaction SMR and expander cycle plants are simpler

    with less equipment than larger plants with

    multiple refrigerant cycles, but train size islimited. They may be utilised in FLNG

    Hydrocarbon refrigerant cycles MRsame requirements as large scale LNG.

    N2Expander cyclesadvantage of no

    hydrocarbon refrigerants

    12/07/2015 9FLNG Essentials

    Components of an LNG Plant

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    10/34

    Components Comments related to FLNG

    LNG Storage and

    Loading

    For FLNG, LNG storage will be below deck

    Utilities FLNG needs to be self-contained for utility

    requirements

    Power Generation Power requirements need to be generated onboard for FLNG

    Gas and liquid

    disposal

    Same requirements as for large scale LNG plants.

    Location of flares on FLNG is a challenge

    Other infrastructure:

    buildings, drainage,

    security, emergency

    response, fire and gas

    systems

    Drainage and buildings require specific design to

    suit the FLNG structure. Fire & gas and

    emergency response systems require attention

    due to FLNG being more congested than onshore

    plants

    12/07/2015 10FLNG Essentials

    Components of an LNG Plant

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    11/34

    Equipment required for pre-treatment of feed gas is common to all

    LNG process technologies (depending on feed gas composition)

    Acid Gas RemovalPrevent freezing of CO2during liquefaction

    Typically amine processes are used

    DehydrationPrevent freezing of water during liquefactionTypically molecular sieve is used

    Mercury Removalprevent Aluminium corrosion

    A number of adsorbents are available

    Heavy Hydrocarbon removalPrevent freezing during liquefaction

    Typically distillation is used

    12/07/2015 11FLNG Essentials

    Gas Pre-Treatment

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    12/34

    LiquefactionQ: How is natural gas liquefied?

    A: By using refrigeration

    Q: How does refrigeration work?

    A: Carnot proposes the theory

    12/07/2015 12FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    13/34

    Carnot Cycle

    The Carnot cycle was proposed by Nicolas Carnot in 1823

    The Carnot cycle is a theoretical thermodynamic cycle to create a temperature

    difference (i.e. heat pump or, in reverse, refrigeration) by inputting work

    1. Reversible isothermal expansion

    2. Isentropic (reversible adiabatic) expansion

    3. Reversible isothermal compression

    4. Isentropic compression

    A real engine (left) compared to the Carnot cycle (right). The entropy of a real material changes

    with temperature.

    12/07/2015 13FLNG Essentials

    Refrigeration

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    14/34

    Reverse Carnot Cycle

    12/07/2015 14FLNG Essentials

    For liquefaction of natural gas, the

    warm air in the diagram is replacedby warm natural gas which is cooled

    and liquefied by the refrigerant

    Refrigeration

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    15/34

    LNG Properties and Specifications

    12/07/2015 15FLNG Essentials

    For large-scale projects, LNG is stored and transported at

    pressure slightly higher than atmospheric (50 to 200 mbar gauge) At these pressures, LNG is stored at its bubble point, and heat

    leakage into the storage container is balanced by boil-off

    LNG bubble point at these pressures is typically in the range -1650C to -160 0C, depending on composition

    Low pressure storage reduces cost of containment and reduces

    probability and severity of leaks

    Typical insulation specifications for boil-off are 0.05% per day for

    onshore storage, and 0.15 to 0.25% per day for LNG carriers (% of

    LNG boiled off per day, based on total storage volume) LNG boil-off may be compressed for use as fuel, or reliquefied

    Pressurised LNG storage and transport can be economic for

    smaller storage vessels and trucking operations

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    16/34

    LNG is :

    colourless odourless,

    non-corrosive,

    less dense than water ~ 450kg/m3

    non-toxic (may cause asphyxia by excluding oxygen)

    LNG vapour typically appears as a visible white cloud since its coldtemperature causes moisture in the air to condense. LNG (the liquid

    itself) is not flammable or explosive

    The vapours formed at an LNG liquid pool surface are always fuel rich.

    Because the LNG is boiling, the pool surface vapours contain near 100

    % hydrocarbons consisting primarily of methane, especially early onduring the spill

    The vapours need to mix with air in order to become flammable

    LNG vapours will become flammable once mixed with enough air to a

    concentration ranging from 5 to 15 % by volume

    LNG Properties and Specifications

    12/07/2015 16FLNG Essentials

    LNG Properties Video

    http://www.youtube.com/watch?feature=player_detailpage&v=18jB74GtZwghttp://www.youtube.com/watch?feature=player_detailpage&v=18jB74GtZwg
  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    17/34

    The ignition of LNG vapours, when in the flammable range, is relatively easy

    The minimum ignition energy of LNG vapours is approximately 0.29 mJ If LNG is spilled on land or on water, some of the LNG vaporises immediately. If

    ignition sources are present in locations where the vapour concentration is in the

    flammable range, the most likely outcome will be an immediate ignition. The

    resulting fire is sometimes termed a pool fire (even though it is the vapour which

    burns, not the liquid)

    LNG pool fire hazards are localized and as a result thermal radiation effects

    (burns) are typically confined to within one or two pool diameters from the edge

    of the flame

    Thermal radiation is absorbed by water moisture and carbon dioxide present in

    the air. In addition, thermal radiation intensity decays in proportion to the inverse

    square of the distance from the radiation source (1/distance2)

    Typically, a person exposed to a thermal radiation flux of 5 kW/m2will feel pain in

    20 seconds. Second degree burns are possible. 5 kW/m2is often used as an

    injury threshold

    12/07/2015 17FLNG Essentials

    LNG Properties and Specifications

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    18/34

    If ignition is not immediate, the LNG vapours will continue to evolve and will

    disperse in the prevailing direction of wind If the wind speed is low and the atmosphere is stable, the vapours, being cold

    and heavy, will remain close to the spill surface, and will persist for some time

    until dispersed by wind. As heat is absorbed from the environment, the vapour

    warms and becomes lighter than air

    Cold LNG vapours drift in the direction of wind and become diluted as they mix

    with more air If the vapours continue to disperse without ignition, they will ultimately become

    diluted to below the lower flammability limits of 5 % and will not burn or present a

    hazard anymore

    Typically, 2.5 % is used as a concentration threshold (1/2 the lower flammability

    limit) when estimating flammable dispersion hazard zones in order to account for

    the possibility of pocketing Dilution therefore is one of the main methods used to control spills resulting

    from a loss of containment of LNG

    Water curtains and jets can be used to draw in air and dilute the cloud that is

    generated (putting water directly onto liquid pools should be avoided)

    12/07/2015 18FLNG Essentials

    LNG Properties and Specifications

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    19/34

    LNG Vapour leak showing water condensation

    12/07/2015 19FLNG Essentials

    LNG Properties and Specifications

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    20/34

    If the LNG vapours encounter an ignition source and ignition occurs

    without the presence of confinement, a slow-burning flash fire will occur Thermal radiation hazards are confined to the boundaries of the

    flammable cloud and no appreciable overpressure is generated

    provided the vapour cloud is not in a confined or congested area.

    The flash fire outcome can change drastically in the presence of

    significant confinement (3 walls or more), or congestion (equipment andpipe work).

    This is further exacerbated by flammable gas concentration close to

    stoichiometry (~9.5% of methane in air) and the presence of higher

    hydrocarbon in the LNG vapour (e.g. ethane and propane).

    Though it is possible to have a transition from a deflagration to adetonation, this has not been observed in practice in industrial

    accidents and in experiments that simulate explosions in industrial

    environment

    12/07/2015 20FLNG Essentials

    LNG Properties and Specifications

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    21/34

    LNG Properties and Specifications

    During actual spills of LNG on water, a phenomenon that is

    observed early on during liquid pool development is a Rapid PhaseTransition (RPT)

    A rapid phase transition is the very rapid (near spontaneous)

    formation of vapours as the cold LNG is vaporized from heat gained

    from the underlying spill surface

    Because the vapour is evolved very rapidly, localized overpressureis created. This is also sometimes described as a physical explosion

    The hazard potential of rapid phase transitions can be severe, but is

    highly localized within the spill area

    In one large scale field trial, a rapid phase transition may have

    ignited the evolved vapours

    12/07/2015 21FLNG Essentials

    An Example of Rapid Phase Transition

    http://www.youtube.com/watch?v=h-EY82cVKuAhttp://www.youtube.com/watch?v=h-EY82cVKuA
  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    22/34

    LNG Properties and Specifications

    Loss of containment leading to the formation of LNG liquid pools can also be

    caused by a phenomenon called rollover

    LNG rollover refers to the rapid release of LNG vapours from a storage tankcaused by stratification. The potential for rollover arises when two separate

    layers of different densities (due to different LNG compositions) exist in a tank

    In the top layer, the liquid becomes warmer due to heat leaking into the tank and

    rises up to the surface, where it evaporates

    Lighter gases are preferentially evaporated and the liquid in the upper layer

    becomes denser. In the bottom layer, the warmed liquid rises towards theinterface by free convection but does not evaporate due to the hydrostatic head

    exerted by the top layer

    The lower layer becomes warmer and less dense

    As the densities of two layers approach each other, the two layers mix rapidly,

    and the lower layer which has been superheated gives off large amounts of

    vapour as it rises to the surface of the tank Rollover is thought to be more likely if LNG nitrogen content is high

    For FLNG, rollover is unlikely to present a problem since sloshing due to sea

    state motions ensures mixing of tank contents

    12/07/2015 22FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    23/34

    LNG Tank Rollover

    12/07/2015 23FLNG Essentials

    LNG Properties and Specifications

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    24/34

    The main hazard arising out of a rollover accident is the rapidrelease of large amounts of vapour leading to potentially hazardous

    situations. It is also possible that the tank pressure relief system is

    not able to handle the rapid boil off rates, and as a result the storage

    tank will fail and lead to the rapid release of large amounts of liquid

    LNG forming a liquid pool.

    LNG operators avoid rollover by carefully monitoring the

    compositions, temperatures and densities and by keeping tank

    contents well-mixed using mechanical means such as pumps to

    circulate the liquid

    12/07/2015 24FLNG Essentials

    LNG Properties and Specifications

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    25/34

    LNG Properties and Specifications

    LNG specifications are applied for different reasons:

    Many of the specifications applied to LNG are relevant for the

    liquefaction/transportation/regasification processes and are commonthroughout the industry. Examples are specifications for mercury, nitrogen,

    water, CO2, C5+, aromatics

    Other specifications are concerned with the end use of regasified LNG and are

    related to pipeline specifications or the design of gas burners in the receiving

    country. Examples are heating value, wobbe number, NGL/LPG content,

    sulphur/H2S Receiving terminals may import LNG outside of the normal specifications (such

    as heating value) but then must modify the properties in the receiving terminal

    so that the gas will be suitable for in-country use. For instance to reduce

    heating value, LPG components may be extracted (before regasification) or

    nitrogen may be added (after regasification). To increase heating value, a

    terminal may be equipped to spike the LNG with LPG in order to raise heatingvalue

    Other specifications common for pipeline gas such as dewpoint are not of

    concern since the liquefaction process requirements are far more stringent

    than pipeline specifications

    12/07/2015 25FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    26/34

    LNG Properties and Specifications

    LNG Specification for facility design:

    An LNG specification is provided for design of the facilities, usually

    in the Basis of Design. The design contractor must guarantee that

    facilities, when built, can meet the specification

    The gas treating facilities must be designed to meet the

    specification for contaminants such as CO2, sulphur compounds,

    water and mercury, taking account of the feed gas composition

    envelope

    The process design for the liquefaction facilities must ensure that

    LNG can be produced to meet the specifications for properties

    such as heating value and compositions of hydrocarbon

    components and nitrogen

    The heat and material balances and high level process design tomeet the liquefaction process requirements are usually carried out

    by the liquefaction process licensor such as APCI or

    ConocoPhillips

    12/07/2015 26FLNG Essentials

    LNG P i d S ifi i

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    27/34

    LNG Properties and Specifications

    LNG Specifications for Sales Contracts:

    LNG specifications are also provided in LNG sales contracts,

    usually referred to as SPAs. These specifications are contractually

    binding and failure to meet them may result in refusal to accept an

    LNG cargo, or may incur a financial penalty.

    The LNG export facility may have separate SPAs with a number of

    different customers, so it is important that the specifications in

    each of these agreements should be compatible with thespecification provided for design of the plant.

    Since the marketing department of a company is often separate

    from the project design department, this is not always

    straightforward.

    In addition to specifying the allowable ranges for LNGcompositions and properties, the SPA will typically also specify

    calculation methods or international standards to determine exactly

    how the properties will be calculated

    12/07/2015 27FLNG Essentials

    LNG P ti d S ifi ti

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    28/34

    LNG Properties and Specifications

    Sample LNG specification for a typical liquefaction plant

    High Heating Value (ideal) 1050 - 1150 BTU/ Scf

    Composition

    Nitrogen 1.0 % mol maximum

    Methane 85.0 % mol minimumButanes and heavier 2.0 % mol maximum

    Pentanes and heavier 0.1 % mol maximum

    Impurities

    Hydrogen Sulphide 5.0 mg/Nm3 maximum

    Total Sulphur 30 mg/Nm3 maximum

    12/07/2015 28FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    29/34

    Examples of LNG Characteristics (from GIIGNL)

    12/07/2015 29FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    30/34

    Opportunities / Advantages of FLNG

    World Energy Outlook (International Energy Agency)

    The share of natural gas in the global energy mix increases from 21% to 25%

    in 2035, pushing the share of coal into decline and overtaking it by 2030

    Trade between the main world regions more than doubles, with the increase of

    around 629 bcm split evenly between pipeline gas and Liquefied Natural Gas

    An increase in production equal to about 3 times the current production of

    Russia will be required simply to meet the growth in gas demand by 2035

    All predictions are for natural gas usage and LNG trade to grow substantiallyover the coming decades. With recent developments, it seems increasingly

    likely that FLNG will become a major contributor to the predicted increases in

    LNG trade and production

    12/07/2015 30FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    31/34

    Opportunities / Advantages of FLNG

    Drivers for FLNG

    Proven technology is available (although building an LNG plant on a floating

    platform still involves novelties and challenges)

    A floating LNG vessel is potentially re-deployable (although modifications

    may be required when feed gas composition varies significantly - a fully

    flexible design to accommodate all feed gas compositions is not practical)and therefore may be viable for smaller gas reserves

    Cost effective way of monetising smaller and more remote gas reserves

    Cost savings can be realised e.g. by eliminating long subsea pipelines,

    offshore processing and compression

    Potential to avoid problems with land-based LNG plants such as land

    access, delays in obtaining permits, eliminating need for new infrastructure

    and influx of construction workers when the LNG plant is in a remote

    location

    12/07/2015 31FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    32/34

    Opportunities / Advantages of FLNG

    Some of the factors likely to be critical for success of the first FLNGventures are:

    Combination of LNG knowhow, FPSO experience and LNG shipbuilding

    expertise e.g. Shell/Technip/Samsung or Linde/SBM/Daewoo

    Recognition of novel aspects (risks); willingness, methodology and

    knowhow to address them

    Research and design development to address novel aspects such as

    effect of motion on LNG equipment, LNG offloading at sea

    Financefinancial backers are harder to find until the technology

    application is regarded as proven

    12/07/2015 32FLNG Essentials

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    33/34

    Offshore Considerations and Challenges

    LNG plants are relatively complex to operate and maintain, and doing this

    in a marine environment with less available space adds additional

    complexity Motion of the FLNG carrier due to sea state makes operation and

    maintenance operations more difficult, e.g. working on rotating equipment

    and other machinery with precise tolerances

    Emergency operations such as fire fighting become more difficult in a

    floating environment

    A marine atmosphere can be more corrosive for equipment and pipework

    (including stress corrosion cracking), though this is already well-known

    since many LNG plants are located in tropical coastal environments

    Compared with onshore LNG plants, staff live and work in a relatively

    confined space

    Escape and evacuation procedures and drills are more complex and

    assume more importance compared with onshore plants

    Major turnaround maintenance may require additional accommodation for

    maintenance personnel e.g. separate floating accommodation vessels

    12/07/2015 33FLNG Essentials

    Off h C id ti d Ch ll

  • 7/26/2019 FLNG Training Module 1.1 Introduction to FLNG Rev 1

    34/34

    Offshore Considerations and Challenges

    (according to TOTAL)

    The challenges of floating LNG (FLNG) derive mainly from the need to fit process

    operations that typically have a very extensive onshore footprint into a small space

    offshore. This raises numerous issues, especially with regard to:

    The size of the FPSO,which must have room to accommodate the gas production,

    processing and liquefaction facilities as well as living quarters for a crew of 200 to 300

    people. However, due to economic considerations as well as construction constraints,

    its dimensions must be as compact as possible

    Integration, because the space limitations of a floating plant dictate a specific process

    layout that requires some stacking of equipment. Installing the production facilities on

    deck and the LNG storage in the hull of the vessel creates some architectural

    challenges as well

    Marinisation of equipment,because process installations must be designed to

    withstand wave action. This is especially important to ensure proper processing of the

    gas prior to liquefaction, as the feed gas for the liquefaction process must comply with

    stringent specifications

    Safety, because the close proximity of process units - and above all the living quarters

    just adjacent to them - make safety issues even more acute than for an onshore plant.

    Safety is also a central focus when it comes to offloading the LNG onto methane

    carriers, and innovative transfer systems are being developed for this context

    12/07/2015 34FLNG Essentials