Financial periods & periodic performance??? Im dealing with two projects that’s in almost similar timeframe , but having various data date. Project name Start date Finish date Data date Project A June 1,2013 June 20,2014 Saturday. Project B June 3,2013 August 21,2014 Monday. I need to store period performance for both the projects , weekly. How can I make financial period periods for both of the projects ,as the second project overlaps the other.??? 1 day ago Like CommentFollow Flag More 5 comments Follow Mimoune Mimoune Djouallah • Financial period is global data, you have to use the same cut off date, as a workaround you can always create a new database and load project B on it and have a different cut off date. it would have been nice, if P6 define period performance at the project level. 1 day ago• Like Follow Andrei Andrei Martemianov • Anas, As I understand, you update both projects on a weekly basis, but on different days of the week.

Transcript of Financial Periods

Page 1: Financial Periods

7/28/2019 Financial Periods

http://slidepdf.com/reader/full/financial-periods 1/3

Financial periods & periodic performance???

Im dealing with two projects that’s in almost similar timeframe , but having various data date.

Project name Start date Finish date Data date

Project A June 1,2013 June 20,2014 Saturday.

Project B June 3,2013 August 21,2014 Monday.

I need to store period performance for both the projects , weekly. How can I make financial period

periods for both of the projects ,as the second project overlaps the other.???

1 day ago

Like CommentFollow Flag More

5 comments

Follow Mimoune

Mimoune Djouallah • Financial period is global data, you have to use the same cut off date, as a

workaround you can always create a new database and load project B on it and have a different cut

off date.

it would have been nice, if P6 define period performance at the project level.

1 day ago• Like 

Follow Andrei

Andrei Martemianov • Anas,

As I understand, you update both projects on a weekly basis, but on different days of the week.

Page 2: Financial Periods

7/28/2019 Financial Periods

http://slidepdf.com/reader/full/financial-periods 2/3

Page 3: Financial Periods

7/28/2019 Financial Periods

http://slidepdf.com/reader/full/financial-periods 3/3

with actuals from past update, the progress doesnt match with the financial periods of the client

requirement. is there any solution to resolve this issue.

21 hours ago• Like• Reply privately• Flag as inappropriate 

Follow José

José Frade • Mohammed

You can delete the financial periods. But rebuild them and producing reports one year back it would

be a nightmare. I would advise to try to negociate some solution with cliente, otherwise you have to

re-enter every progresso update and freeze again every and sigle financial period.

Sorry, there are certain things that need to be right from begin and financial periods is one of those.