FINAL - tzdpg.or.tzANNUAL PROGRESS REPORT FOR FY 2012/13 FINAL CONTACT: Permanent Secretary Ministry...
Transcript of FINAL - tzdpg.or.tzANNUAL PROGRESS REPORT FOR FY 2012/13 FINAL CONTACT: Permanent Secretary Ministry...
1
THE UNITED REPUBLIC OF TANZANIA
MINISTRY OF FINANCE
PUBLIC FINANCIAL MANAGEMENT REFORM PROGRAMME
(PFMRP PHASE IV)
ANNUAL PROGRESS REPORT FOR FY 2012/13
FINAL
CONTACT:
Permanent Secretary
Ministry of Finance
P.O. Box 9111
Dar es Salaam
September, 2013
2
TABLE OF CONTENTS
LIST OF ABBREVIATIONS ................................................................................................................................. 3
Executive Summary ................................................................................................................................................ 5
Chapter 1.0 BACKGROUND AND INTRODUCTION ........................................................................................ 7
Chapter 2.0 PROGRESS ON IMPLEMENTATION OF PLANNED ACTIVITIES IN FY 2012/13 ................. 11
Chapter 3.0 BUDGET EXECUTION ................................................................................................................... 25
Chapter 4.0 CHALLENGES AND RECOMMENDATIONS FOR NEXT PERIOD .......................................... 32
Annexes:
- Annex 1: Detailed assessment of milestone status as at Dec 2012 based on M&E Framework
for 2012 – 2017 ............................................................................................... 33
- Annex 2: Fund use by milestone for the year 2012/2013 ........................................ 64
- Annex 3: Procurement progress report for the year 2012/2013 .......................... 86
3
LIST OF ABBREVIATION
AG Attorney General
CAG Controller and Auditor General
ICT Information & Communication Technology
IPSAs International Public Sector Accounting Standards
LAAC Local Authority Accounts Committee
LGAs Local Government Authorities
JSC Joint Steering Committee
KRA Key Result Area
MCA – T Millennium Challenge Account - Tanzania
MCC Millennium Challenge Cooperation
MDAs Ministries, Departments and Agencies
M&E Monitoring and Evaluation
MIS Management Information System
MKUKUTA Mkakati wa Kukuza Uchumi na Kupunguza Umaskini Tanzania
MoF Ministry of Finance
MTEF Medium Term Expenditure Framework
PAC Public Accounts Committee
PEFA Public Expenditure Framework for Assessment
PFMRP Public Financial Management Reform Program
PMU Procurement Management Unit
PO-PC President’s Office – Planning Commission
PO- PSM President’s Office – Public Service Management
RSs Regional Secretariat’s
SMTB Secretary for Ministerial Tender Board
4
TRA Tanzania Revenue Authority
TRMIS Treasury Registrar Management Information System
TWG Technical Working Group
5
EXECUTIVE SUMMARY
PFMRP Phase IV was officially launched in June, 2012 and its implementation started on 1st
July, 2012. The Programme is designed to consolidate and build on achievements of the previous
phases in line with National policy objectives stated in the Tanzania Development Vision 2025,
the Five Year Development Plan (FYDP) 2011/12 - 2015/16 and the MKUKUTA/MKUZA II
aimed at fostering economic growth and the reduction of poverty in the country. PFMRP IV aims
at strengthening and improving public financial management in a more coordinated manner in
order to meet the current fiscal policy challenges.
PFMRP Phase IV implementation is organized in five Key Result Areas (KRAs) of the PFM
system; namely 1) Revenue management, 2) Budget and Planning, 3) Budget execution,
Transparency and Accountability, 4) Budget Control and Oversight, 5) Change management,
Program Monitoring and Communication. The KRAs are structured to ensure that all the
different aspects and dependencies of a sound PFM are managed during the program
implementation. The strategic actions are facilitated through the results-based management,
program based budgets, accountability and performance audits, transparency and
communication.
The approved budget for FY 2012/13 is Tshs 33,597,704,853 of which Tshs 3,996,904,853 are
Project funds1, Tshs. 16,250,000,000 Government funds and Tshs. 13,350,800,000 Basket
Funds2. During the year 2012/13 a total of Tshs. 24,129,665,331 was released of which Tshs.
8,478,922,060 from GoT; Tshs. 2,911,442,271 from Project fund and Tshs. 12,739,295,000 from
Basket Fund. Actual expenditure and commitment as at 30th
June, 2013 amounted to Tshs.
19,456,556,160 being 81% of the fund released. Expenditure by source was GoT Tshs.
7,755,244,698 being 91% of the released funds; Project Tshs. 2,300,718,540 being 79% of the
released funds and Basket Fund Tshs. 9,400,592,922 being 74% of the released funds.
1 Bilateral project fund include AfDB and World Bank
2 DFID, CIDA, Denmark, Ireland and KFW have signed a Memorandum of Understanding with the GoT establishing a pooled
funding mechanism.
6
In procurement, activities which had been completed or in contracting stage by 30th
June, 2013
amounted to Tshs. 12,230,903,613 which represented 62.2% of the total planned procurements.
This amount includes costs of Tshs. 749,220,000 activities which the method of procurement
was changed by doing internally instead of initially planned option of engaging consultants. Two
works project implemented by NAO and ACGEN amounted to Tshs. 7,698,204,848 representing
39.1 % of the total planned procurement cost (72.6% of planned works cost). A total amount of
Tshs. 377,000,000 representing 2% of the estimated total procurements was at various
procurement stages. Detailed procurement progress report is displayed under Annex 3.
The programme recorded fairly satisfactory progress whereby 25 milestones were achieved and
82 milestones were on track. Notable achievements are: chart of accounts have been modified
to accommodate program based budgeting; EPICOR system was upgraded from version 7.3.5 to
9.05; Approved National Budget and Citizens Budget were published on MoF website; and Joint
Supervision Mission was conducted and report approved. However, the low absorption of funds
during the period under review was due to late release of funds.
During the period under review, component managers were committed to fast track the
implementation of activities and utilized the TWGs to discuss and resolve emerging issues. It
was envisaged that through enhanced information sharing there was smooth coordination to
achieve milestone targets. The PEFA Central exercise for central government was conducted,
while for Local government will be conducted in the Financial Year, 2013/2014.
7
CHAPTER ONE
BACKGROUND AND INTRODUCTION
1.0 Background
The Government of Tanzania has been implementing Public Financial Management Reform
Programme (PFMRP) for the past two decades in different phases aiming at improving Public
financial management systems across all levels. Phase I was implemented from 1998-2004 with
an objective of controlling expenditure, introducing aggregate fiscal discipline and contributing
to stable macro-economic growth. Phase II was implemented from 2004 to 2008 with an
objective of progressively modernizing the processes, procedures and systems involved in PFM
through the implementation and use of ‘best practice’ tools, techniques and methodologies to
improve revenue forecasting and resource allocation for strategic priorities. Phase III was
implemented from 2008 to 2011 with the objective of ensuring greater predictability and
availability of medium term resources to executing agencies.
1.1 Introduction
PFMRP IV was launched in June 2012 and its implementation started on 1st July 2012. PFMRP
Phase IV is designed and implemented to complement efforts to achieve national policy
objectives stated in Tanzania Development Vision 2025, Five Year Development Plan (FYDP)
2011/12-2015/16 and MKUKUTA/MKUZA II so as to achieve economic growth. The
overarching goal of attaining sound financial management and discipline in public service
delivery for sustainable development will be achieved through implementation of PFMRP IV
five Key Results Areas which are: Revenue management; Budget and Planning; Budget
execution, Transparency and Accountability; Budget Control and Oversight; and Change
management, Program Monitoring and Communication. Table 1.1 gives a summary of KRA
overview.
The Public Financial Management Reform Program is implemented in line with the on-going
reforms in the Public Sector which aim at improved performance, efficiency and effectiveness in
service delivery for sustainable economic growth. In doing so, PFMRP IV will address
interventions which will be:
8
i. Comprehensive to include the various key reform activities in the PFM systems as well as
the cross-cutting issues related to capacity building, improving infrastructure for service
delivery, and reviewing the institutional policy and regulatory frameworks;
ii. Captured in a well defined Monitoring and Evaluation framework, sequenced to manage
priorities and ensure a more accurate cash forecasting and achievement of results;
iii. Linked and inter-dependent with clear demarcation of responsibilities and accountability;
iv. Better standardized and automated systems to ensure attainment of desired results in
financial recording and reporting;
v. Well managed, with effective institutional arrangement to support implementation of the
programme;
vi. Focused, aiming at supporting agencies and initiatives which are likely to have a great
cross cutting impact on the PFM system.
Table 1.1 KRA and components overview
Key Result Area (KRA) Major Component,
Department and KRA-
TWG
KRA 1: Revenue Management
Leader: CPAD
Focus: improving revenue forecasting and resources mobilization and
reviewing & streamlining existing revenue policies, laws and regulations.
The intervention aims at developing appropriate model for revenue
forecasting to improve cash flow forecasting to spending units. Also the
KRA will continue to improve external resource management, review
retention schemes and enhance capacity for managing public investments.
1. CPAD – MoF
2. TR - MoF
3. PMO-RALG
4. External Finance -
MoF
5. MDAs
KRA 2:Planning and Budgeting
Leader: BC
Focus: improving macro-fiscal policy, planning, MTEF credibility,
enhancing budget classification by adopting GFS 2001 and CoFoG
standards, facilitate program based budgeting, broadening the scope of the
chart of accounts, enhancing monitoring, reporting and accountability and
review of the Medium Term Strategic Planning & Budgeting Manual
1. CB – MoF
2. CPAD – MoF
3. PMO-RALG
9
(MTSPBM) to enable the national development planning and budgeting
system to articulate national policy priority targets with the desired
institutional results.
KRA 3: Budget Execution, Transparency and Accountability
Leader: ACCGEN
Focus: achieving greater predictability of resources to spending units;
strengthening capacity on procurement, cash and debt management; and
improving the scope and quality of financial recording and reporting
1. PPRA
2. PPPD
3. ACCGEN - MoF
4. CPAD - MoF
5. DGAM - MoF
KRA 4: Budget Control and Oversight
Leader: IAG
Focus: strengthening capacity on audit functions (internal and external) as
well as oversight function of the Parliament. The interventions involves
providing technical guidance and capacity building to MDAs and LGAs in
the areas of internal audit and to facilitate timely independent external
examination of financial and performance auditing and report to the public
1. IAG - MoF
2. NAO (and
Parliament PACs)
3. TR
KRA 5:Change Management Programme Monitoring and
Communication
Leader: DPD
Focus: cross cutting issues including capacity building on change
management, Monitoring and Evaluation, stakeholders’ communication,
coordination and leadership for efficient and effective programme
implementation.
1. DFMIS - MoF
2. GCU - MoF
3. DPD – MoF
4. PMO – RALG
5. ACGEN - MoF
6. DAHRM - MoF
7. Zanzibar
Layout of the report
This report comprises of four chapters: Chapter one provides background information and
introduction; Chapter two covers progress on implementation of the planned activities; Chapter
three reports the budget execution and Chapter four highlights on challenges and
recommendations for next period. Annexes 1 give detailed assessment of milestone status as at
10
the end of June, 2013 based on M&E Framework for 2012 – 2017; and 2: Procurement Progress
report for the period ended June, 2013.
11
CHAPTER TWO
PROGRESS ON IMPLEMENTATION OF PLANNED ACTIVITIES IN FY
2012/13
The Fiscal Year 2012/13 being the first year of PFMRP phase IV implementation focused on
activities that lay foundation for the attainment of milestones as outlined in the M&E Framework
as well as Performance Assessment Framework (PAF) 2012 key policy actions.
2.1 Highlights on Targets/Outputs and Implementation Status of Milestones as Per M&E
Result Framework
167 milestones are included in the work plan and budget for FY 2012/13. Out of 167 milestones,
achievement was realized in 25 (15%) milestones. Satisfactory progress was recorded on track in
82 (49%) milestones while Pending and Delayed milestones were 18 (11%) and 37(22)
respectively. Pending and delayed milestones involve activities that could not be initiated before
getting specific inputs from stakeholders. 5 (3%) milestones were at risk of implementation.
Milestones on track include those in areas of consultancy for various studies, works, training and
review of legal instruments. Status of milestones per KRA as at 31st June, 2013 is in table 2.1
while detailed information on each milestone is outlined in Annex 1. Progress toward achieving
the output under each KRA is presented in the next part.
Table 2.1: Cumulative Milestone Status for FY 2012/13
KRA Achieved On Track Pending Delayed At Risk Total
KRA 1 - 12 3 7 2 24
KRA 2 2 8 5 5 - 20
KRA 3 10 30 3 7 2 52
KRA 4 9 13 2 1 - 25
KRA 5 4 19 5 17 1 46
TOTAL 25 82 18 37 5 167
Percentage 15 49 11 22 3 100
12
KRA 1 Revenue Management:
Objective: Strengthened systems, processes and procedures for improving the operational
capability of the revenue collection by June 2016.
Output 1.2: The Government improves efficiency in domestic revenue mobilization both at the
policy and the administration levels by updating legal instruments towards international best
practices:
i. Non-tax revenue study on Integration and harmonization of revenue collection is in
progress. A consultant is continuing with a study.
ii. A draft of Tax Administration Bill has been submitted to the cabinet for approval. It is
expected that Cabinet approval and Attorney General Verification will be done in time
for the draft Act to be submitted to parliament.
iii. The first draft of new TR Bill has been submitted to Cabinet Secretariat for an initial
review. The bill is expected to be sent to parliament by June, 2013
Implementation Status of Milestones as Per M&E Result Framework
The implementation status on the 24 milestones was fair satisfactory of which 12 (50%) were on
track, 3 (13%) pending, 7(29%) delayed and 2(8%) at risk. Figure 1 below depicts schematic
presentation of KRA 1 status as at June, 2013.
13
A milestone at risk concerns the review of M & E systems for Parastatals which was proposed to
be changed.
Among of the delayed milestones include revision of the JAST (DCF) and AMP user guidelines.
Concerted efforts may change status on pending milestones once a way forward is agreed to
address factors that are hindering the implementation process. Summary of KRA 1 Financial
Performance is shown in the table 2.2 below.
Table 2.2: KRA1 Financial performance for the year 2012/13
S/
N COMPONENT
SOURCE
OF FUND
APPROVED
BUDGET FY
2012/13 RELEASE
EXPENDITURE
AND
COMMITMENT
% ON
RELEASE
TSHS TSHS TSHS
1
POLICY
ANALYSIS
GOT 500,000,000 252,000,000 204,614,260 81%
P 55,713,406 - -
BF 228,000,000 228,000,000 135,891,850 60%
SUB TOTAL 783,713,406 480,000,000 340,506,110 71%
2 MNRT BF 127,000,000 - - -
SUB TOTAL 127,000,000 - -
3
TREASURY
REGISTRAR
GOT 300,000,000 200,000,000 198,593,103 99%
P -
BF 372,800,000 372,800,000 320,345,000 86%
SUB TOTAL 672,800,000 572,800,000 518,938,103 91%
4 PMO-RALG
GOT 210,000,000 - -
P - - -
BF 340,300,000 317,800,000 317,800,000 100%
SUB TOTAL 550,300,000 317,800,000 317,800,000
5
EXTERNAL
FINANCE
GOT 150,000,000 12,500,000 12,500,000 100%
P 95,530,473 95,530,473 95,530,473 100%
BF 115,000,000 115,000,000 - 0%
SUB TOTAL 360,530,473 223,030,473 108,030,473 48%
GOT 1,160,000,000 464,500,000 415,707,363 89%
P 151,243,879 95,530,473 95,530,473 100%
BF 1,183,100,000 1,033,600,000 774,036,850 75%
KRA 2 Budgeting and planning
Objective: Strengthened capacity of planning and budget management, including results and
program based budgeting, within MoF, MDAs and LGAs by June 2016.
Output 2.1: Strengthened capacity of MDAs, RSs and LGAs in implementing program based
budgeting by June 2016.
14
i. Programs and sub-programs have been (tentatively) defined and objectives, outputs and
performance indicators were developed from MKUKUTA II and FYDP. Six ministries
were involved in training as a part of pilot phase in fiscal year 2012/13.; these ministries
are Community Gender and Children, Ministry of Finance, Ministry of Education and
Vocational Training, Ministry of Health and Social Welfare, Ministry of Agriculture,
Food Security and Cooperatives and Ministry of Water.
ii. The chart of account has been modified to accommodate Program Based Budgeting.
iii. Continued to implement Program Based Budgeting (PBB) action plan.
Output 2.2: Increased effective utilization of Planning and budgeting tools by 2016
i. PER meetings were conducted and PER Champion Group Team was established for
coordinating PER Agenda
ii. Training for MDAs on Prioritization and Planning and on the new budget cycle for their
comments and implementation were carried out.
Implementation Status of Milestones as Per M&E Result Framework
During the period under review 2 milestones (10%) were achieved, 8 milestones (40%) were on
track, 5 milestones (25%) were pending and 5 milestones (25%) were delayed in this KRA.
Figure 2 below depicts the schematic presentation for KRA 2 status as at June, 2013.
15
The milestones delayed include those relate to agreement on the improvement of LGAs
allocation formula.
Summary of KRA 2 Financial Performance is shown in the table 2.3 below.
Table 2.3: KRA 2 financial performance for the year 2012/13
S/
N COMPONENT
SOURCE
OF FUND
APPROVED
BUDGET FY
2012/13 RELEASE
EXPENDITURE
AND
COMMITMENT
% ON
RELEASE
TSHS TSHS TSHS
1
GOT 1,500,000,000 98,800,000 62,870,000 64%
P
BF 470,000,000 470,000,000 34,540,000 7%
SUB TOTAL 1,970,000,000 568,800,000 97,410,000 17%
2 POLICY
ANALYSIS
GOT - - - -
P - - - -
BF 40,000,000 40,000,000 - 0%
SUB TOTAL 40,000,000 40,000,000
3 PMO-RALG
GOT 90,000,000 - - -
P - - - -
BF 67,000,000 90,419,000 90,419,000 100%
157,000,000 90,419,000 90,419,000 100%
GOT
1,590,000,000 98,800,000 62,870,000 64%
P
- - -
BF
577,000,000 600,419,000 124,959,000 21%
16
KRA 3: Budget Execution, Accountability and Transparency
Objective: Improved utilization of public resources in a more effective, efficient and transparent
manner by June 2016
Output 3.1: Improved public procurement performance by PEs by 2015
i. Annual audit conducted and preliminary results indicated positive trend based on
compliance and Value for Money (VfM) audits in 30 PEs.
ii. PPA,2011 has been disseminated to 85 Board of Directors and 189 Accounting officers
of Public Entities
iii. 610 Users from 299 PEs are now registered and use PMIS
Output 3.2: Strengthened public sector procurement by June 2015
i. A draft of the public procurement regulations has been prepared and submitted to the
Attorney General’s office for verification. Following the minister’s finalization, the
regulation will be submitted to responsible parliamentary committee.
ii. Data base information for 1,022 Public Procurement and Supplies Staff have been
verified and updated.
iii. National procurement policy draft in place.
Output 3.3: Strengthened capacity of MDAs, RSs and LGAs in Cash management by 2015
Each LGA is now operating with six bank accounts
Output 3.5: Improved integrity and content of government financial statements and the
migration from IPSAS cash to IPSAS accrual accounting for all government accounts is
progressing in accordance with plans.
i. Action plan for migration towards IPSAS Accrual accounting has been prepared.
ii. Opening balances for the financial year 2012/2013 for all MDAs were established in order
to facilitate the implementation of IPAS Accrual;
17
iii. A draft of revised PFA has been circulated to stakeholders’ for comments. This revised
PFA provides for migration to IPSAS accrual among others.
iv. 250 accountants from MDAs, Regions were trained on migration to IPSAS Accrual;
Output 3.6: Improved accountability in management of Government Assets for supporting
migration to IPSAS Accrual
i. Contract has been awarded and implementation is underway scheduled for completion by
February 2014.
ii. The contract for formulation of the asset policy management has been awarded.
Implementation Status of Milestones as Per M&E Result Framework
Out of 52 milestones achievement was realized in 10 (19%) milestones, which include
Procurement Plans being a mandatory requirement for strategic and budget plans for MDAs,
LGAs and Parastatal Institutions as well as each LGA now operates only six bank accounts.
Satisfactory progress (on track) was recorded in 30 (58%) milestones. These are in areas related
to compliance to 2004 PPA; review of procurement regulations to achieve Value for Money in
public procurement; capacity building to PPRA; preparation for e-procurement; development of
National Public Procurement Policy; capacity building on Cash Management; updating IPSAS
guidelines from Cash to Accrual accounting; and improvement on accountability in Government
Asset Management.
About 3 (6%) milestones were pending and 7(13%) were delayed due to a number of factors
including the action plan for implementing the 2011 PPA, training strategy and plan for public
procurement cadre as well as approval of TORs for the uploading 16 MDAs in EPICOR.
Establishment of Debt Management Department was awaiting approval of PO -PSM. Only
2(4%) milestones were at risk. Figure 3 below depicts the schematic presentation for KRA 3
status as at June, 2013.
18
Summary of KRA 3 Financial Performance is shown in the table 2.4 below.
Table 2.4: KRA 3 financial performance for the year 2012/13
S/N COMPONENT SOURCE
OF FUND
APPROVED
BUDGET FY
2012/13 RELEASE
EXPENDITURE
AND
COMMITMENT
COMMITED
FUNDS
TOTAL
EXPENDITURE
AND
COMMITMENT
% ON
RELEASE
TSHS TSHS TSHS TSHS TSHS
1
PUBLIC
PROCUREMENT
REGULATORY
AUTHORITY
GOT 100,000,000 50,000,000 50,000,000 - 50,000,000 100%
P 2,032,520,000 2,319,673,975 1,708,944,244 - 1,708,944,244 74%
BF 1,317,188,000 1,317,188,000 1,317,188,000 - 1,317,188,000 100%
SUB TOTAL 3,449,708,000 3,686,861,975 3,076,132,244 - 3,076,132,244 83%
2
ACCOUNTANT
GENERAL
GOT 3,500,000,000 1,375,000,000 1,023,116,808 - 1,023,116,808 74%
P - - -
BF 1,084,320,000 1,050,138,800 699,515,153 - 699,515,153 67%
SUB TOTAL 4,584,320,000 2,425,138,800 1,722,631,961 - 1,722,631,961 71%
3
POLICY
ANALYSIS
GOT - - - - -
P 1,316,897,151 - - - -
BF - - - - -
SUB TOTAL 1,316,897,151 - - - -
4
PUBLIC
PROCUREMENT
POLICY
GOT 62,500,000 62,500,000 27,785,430 - 27,785,430 44%
P - -
BF 482,000,000 482,000,000 170,101,550 166,734,000 336,835,550 70%
SUB TOTAL 544,500,000 544,500,000 197,886,980 166,734,000 364,620,980 67%
5
GOVERNMENT
ASSET
MANAGEMENT
GOT 200,000,000 50,000,000 44,296,796 - 44,296,796 89%
P - -
BF 1,378,572,000 1,378,572,000 204,836,950 591,102,665 795,939,615 58%
SUB TOTAL 1,578,572,000 1,428,572,000 249,133,746 591,102,665 840,236,411 59%
GOT 3,862,500,000 1,537,500,000 1,145,199,034 - 1,145,199,034 74%
P 3,349,417,151 2,319,673,975 1,708,944,244 - 1,708,944,244 74%
BF 4,262,080,000 4,227,898,800 2,391,641,653 757,836,665 3,149,478,318 74%
19
KRA 4: Budget Control and Oversight
Objective: Improved adherence and enforcing of MDAs and LGAs to financial internal controls,
rules, laws, regulations and audit recommendations by June 2016
Output 4.1: Increased coverage and quality of the internal audit functions by 2016
i. Operation Plan for 5 year (2013 – 2017) approved and disseminated.
ii. Survey to identify weaknesses of MDAs audit committees was conducted.
iii. Training on roles of internal auditors for 226 stakeholders (Mayors, Council Chairpersons
and Internal Audit) was conducted.
iv. Training on roles of internal auditors to 114 audit committees’ chairpersons was
conducted.
Output 4.2: Strengthened External audit functions by 2016
i. Report on Laws and Policies was submitted to the Attorney General’s Office for action,
however with the ongoing Constitutional review, the amendment of various laws will
follow after the new Constitution. NAOT submitted to the Constitutional Review
committee NAOT views on Articles related to NAOT meanwhile addressing
Independence of the CAG. An AFROSAI-E team undertook an assessment of NAO`s
performance in September 2012, focusing on institutional assessment, performance audits
and regularity audit. The result was positive as NAOT has been elevated to level 3 of
AFROSAI-E capability model.
ii. 200 auditors have been trained on Risk Based Audit and 100 auditors have been trained
on IT audit. The Risk Based audit approach will be applied during the coming audit
(October 2013), at the same time the office has created a group of IT auditors who
eventually will form IT audit unit.
iii. Construction of Dodoma and Rukwa offices are on-going, Dodoma (80%), Rukwa
(50%). Procurement process for a Consultant to supervise construction of office buildings
in Iringa and Mara regions is in final stage.
iv. 200 auditors have been trained on International Standards of auditing and 100 senior
officers have been trained on quality assurance. The NAOT Regularity Audit Manual has
been up dated to comply with International Standards.
20
v. The Citizen Audit report for 5 General Audit Reports in Kiswahili language has been
prepared internally and printed
Output 4.5: Strengthened Capacity of oversight functions of Parliamentary Accounts
Committees by 2016
Training to members of Parliamentary Accounts Committees (PAC and LAAC) on
interrogation skills, understanding of CAG reports and elementary understanding of financial
statements was conducted. Tracking of implementation of projects was facilitated and MPs
visited a good number of projects.
Implementation Status of Milestones as per M&E Result Framework
During the period, 9 milestones (36%) were achieved, 13 milestones (52%) were on track, 2
(8%) were pending and 1 milestone was delayed. Milestones achievement was recorded in area
of production of Value for Money audit reports annually. Milestones on track status included
areas of internal audit functions, development of Internal Audit Manual, capacity building in
computerized auditing, enhancing accountability on parastatals performance and production of
citizen audit reports. Figure 4 below depict milestone status for KRA 4 by June, 2013.
21
Summary of KRA 4 Financial Performance is shown in the table 2.5 below.
Table 2.5: KRA 4 financial performance for the year 2012/13
S/
N
COMPONENT
SOURCE
OF FUND
APPROVED
BUDGET FY
2012/13 RELEASE
EXPENDITU
RE
COMMITE
D FUNDS
TOTAL
EXPENDITU
RE AND
COMMITME
NT
% ON
RELEAS
E
TSHS TSHS TSHS TSHS TSHS
1
INTERNAL
AUDITOR
GENERAL
GOT 300,000,000 - -
P - - -
BF 1,323,050,000 1,323,050,000 373,957,935 881,300,000 1,255,257,935 95%
SUB TOTAL 1,623,050,000 1,323,050,000 373,957,935 881,300,000 1,255,257,935 95%
2
NATIONAL
AUDIT OFFICE
GOT 7,500,000,000 5,700,000,000 5,700,000,000 - 5,700,000,000 100%
P 469,097,486 469,097,486 469,097,486 - 469,097,486 100%
BF 1,654,850,000 1,654,800,000 1,654,800,000 - 1,654,800,000 100%
SUB TOTAL 9,623,947,486 7,823,897,486 7,823,897,486 - 7,823,897,486
100%
GOT 7,800,000,000 5,700,000,000 5,700,000,000 - 5,700,000,000 100%
P 469,097,486 469,097,486 469,097,486 - 469,097,486 100%
BF 2,977,900,000 2,977,850,000 2,028,757,935 881,300,000 2,910,057,935 98%
KRA 5 – Change Management, Programme Monitoring and Communication
Objective: Improved management practices with increased accountability and leadership to
better manage performance of PFMRP.
Output 5.1: Coordinate Integration, interfacing and rationalization of Government financial
systems.
ICT mapping study has started.
Output 5.2: Utilization of EPICOR modules increased from seven to ten
i. EPICOR system has been upgraded from version 7.3.5 to version 9.05 with 7 modules
installed of which 6 are activated
ii. Training to 40 ACCGEN staff and 381 end users was undertaken on the new version of
EPICOR.
Output 5.3: All software development and module upgrades are coordinated with the
overarching plans for ICT integration
7 staffs have been trained on Data Center Infrastructure Specialists, ICT Security, Database
Management and Data Center Operations Specialists
22
Output 5.4: Improved communication and public access to key fiscal information to
stakeholders
i. The approved National Budget was published on Ministry of Finance website by
September 2012 and Citizens budget October, 2012
ii. The final draft of communication strategy has been submitted to the Ministry’s
Communication Committee for proof reading;
Output 5.5: Coordination and Standardization of PFM Training Achieved.
A PFM training mapping exercise was conducted. The final report will be ready in FY
2013/2014.
Output 5.6: PFMRP Component Managers are being guided by detailed multi-year
operating plans
A five year operating work plan has been developed and is intended to be updated when
preparing the next financial years plans.
Output 5.7: PFM activities are effectively planned and implemented
The Change Management Training was conducted at ESAMI HQ to 150 staff from
various MDAs. Meanwhile, 30 Top Management staff from various ministries were
trained on the same by ESAMI in Dodoma during Bunge Session in June, 2013.
Output 5.12: National systems and processes for intergovernmental transfers to LGAs
Streamlined and rationalized
Two mapping systems namely ICT systems and processes for intergovernmental transfers
exercise were at various stage of implementation. The final reports were expected during
the first quarter of FY 2013/2014.
23
Summary of KRA 5 Financial Performance is shown in the table 2.5 below.
Table 2.5: KRA 4 financial performance for the year 2012/13
S/N COMPONENT
SOURCE
OF
FUND
APPROVED
BUDGET FY
2012/13 RELEASE
EXPENDIT
URE
COMMITE
D FUNDS
TOTAL
EXPENDITU
RE AND
COMMITM
ENT
% ON
RELEASE
TSHS TSHS TSHS TSHS TSHS
1
FINANCIAL INFORMATION
SYSTEM
MANAGEMENT
GOT 600,000,000 206,750,000 192,206,211 - 192,206,211 93%
P - -
BF 243,000,000 243,000,000 128,315,352 69,888,096 198,203,448 82%
SUB TOTAL 843,000,000 449,750,000 320,521,563 69,888,096 390,409,659
87%
2 PMO-RALG
GOT - - -
P - - -
BF 337,700,000 336,781,000 336,781,000 - 336,781,000 100%
SUB TOTAL 337,700,000 336,781,000 336,781,000 - 336,781,000 100%
3
ACCOUNTANT
GENERAL
GOT - - - - -
P - -
BF 1,538,520,000 1,088,246,200 797,963,274 - 797,963,274 73%
SUB TOTAL 1,538,520,000 1,088,246,200 797,963,274 - 797,963,274
73%
4
GOVERNEMNT
COMMUNICATION UNIT
GOT 200,000,000 88,500,000 88,403,440 - 88,403,440 100%
P - -
BF 276,000,000 276,000,000 100,231,430 - 100,231,430 36%
SUB TOTAL 476,000,000 364,500,000 188,634,870 - 188,634,870 52%
5
ADMINISTRATI
ON AND
GENERAL
GOT 173,500,000 3,500,000 - - 0%
P - - -
BF 107,000,000 107,000,000 72,100,000 - 72,100,000 67%
SUB TOTAL 280,500,000 110,500,000 72,100,000 - 72,100,000 65%
6
PLANNING
DIVISION
GOT 864,000,000 379,372,060 343,064,861 - 343,064,861 90%
P 27,146,337 27,146,337 27,146,337 - 27,146,337 100%
BF 1,348,500,000 1,348,500,000 841,831,942 86,623,800 928,455,742
69%
SUB TOTAL 2,239,646,337 1,755,018,397 1,212,043,140 86,623,800 1,298,666,940
74%
7 ZANZIBAR BF
500,000,000 500,000,000 8,325,925 - 8,325,925
2%
SUB TOTAL 500,000,000 500,000,000 8,325,925 - 8,325,925
2%
GOT
1,837,500,000 678,122,060 623,674,512 - 623,674,512
92%
P
27,146,337 27,146,337 27,146,337 - 27,146,337
100%
BF 4,350,720,000 3,899,527,200 2,285,548,923 156,511,896 2,442,060,819
63%
Implementation Status of Milestones as Per M&E Result Framework
Achievement was recorded in 4 milestones (9%) covering areas of upgrading EPICOR software,
transparency in budget management through publication on MoF website (National budget,
citizen budget, end-year budget out-turn report); coordination of plans for ICT integration;
24
timely update of MoF website and consultative PFM Reform management process through
annual supervision mission.
Satisfactory progress on milestones represented as on track were 19 (41%). These cover the
areas of capacity building and linking MoF IFMIS to PMO-RALG IFMS for immediate
capturing of budget and exchequer transfer to RSs and LGAs respectively; development of
MoF Communication Strategy; development of a comprehensive training programme on change
management and result based management and; timeliness of PFMRP dialogue structure.
5 milestones (11%) were pending and while 17 (37%) milestones were delayed. These included:
ICT mapping exercise; MoF training mapping exercise; prolonged secretariat recruitment
exercise; Development of Action Plan on transition to accrual accounting by IAG and ACGEN
and mapping of system and process for intergovernmental transfer of funds. Only 1 milestone
was at risk status. Figure 5 below depicts the schematic presentation for KRA 5 status as at
June, 2013.
25
CHAPTER THREE
BUDGET EXECUTION
3.1 Funds Disbursement and Release
The approved budget for FY 2012/13 is Tshs. 33,597,704,853 of which Tshs. 3,996,904,853 is
Project fund, Tshs. 16,250,000,000 is Government fund and Tshs. 13,350,800,000 is Basket
Fund. Source of Basket Fund and the status on disbursement is shown in table 3.1 below.
Table 3.1: Basket Funds Disbursement by Development Partners for FY 2012/13
DPs Commitment Actual Disbursement
DP
DPs Local
Currency
(Million)
Amount
in (US
Million) Amount in Tshs Date
Amount
USD Amount in TZS
DFID 2.00GBP 3.20 4,960,000,000 29.11.2012
1,601,601 2,530,273,324
DFID 07.03.2013
1,500,001 2,364,387,645
KFW 0.69EUR 0.92 1,426,000,000 24.12.2012
1,059,467 1,673,057,313
Canada 1.00CAD 1.00 1,550,000,000 27.02.2013
974,374 1,538,777,640
DANIDA 13.01DKK 2.19 3,394,500,000 11.10.2012
1,992,197 3,140,160,677
Ireland 1.00EUR 1.34 2,077,000,000 05.10.2012
1,292,300 2,036,949,106
Sub
Total 8.65 13,407,500,000
8,419,940 13,283,605,705
Note: Foreign currency transactions have been translated at TZS 1,550 per US $ during the 2012/13 budget period, actual disbursements
have been translated using prevailing rate at the date of disbursement
3.2 Fund flows
The available Basket Fund in the holding account was Tshs. 14,364,243,894/= of which Tshs.
886,496,043 was opening balance, Tshs. 194,142,145/= was unspent balance returned by
components and Tshs. 13,283,605,705/= was disbursement by DPs. The amount released to
components was Tshs. 12,739,295,000/= as detailed in table 3.2 below.
26
Table 3.2: PFMRP Basket Fund Flows for FY 2012/13
Date Description
Amount in
USD Amount in Tshs.
01.07.2012 (a) Opening Balance
568,482
886,496,043
Add Inflows
Returned Unspent Balances
20.07.2012 Natural Resources 7,850 12,237,667
25.07.2012 Accountant General's Department 116,680 181,904,479
(b) Unspent Balance Total 124,530 194,142,145
DP Releases
05.10.2012 Ireland 1,292,300 2,036,949,106
11.10.2012 Royal Danish 1,992,197 3,140,160,677
29.11.2012 DFID 1,601,601 2,530,273,324
24.12.2012 KFW 1,059,467 1,673,057,313
27.02.2013 CIDA 974,374 1,538,777,640
07.03.2013 DFID 1,500,001 2,364,387,645
(c) DP Release Total 8,419,940 13,283,605,705
Funds Available (a+b+c) 9,112,952 14,364,243,894
Less Outflows
31.08.2012 Ministry of Finance-Vote 50 349,452 545,000,000
31.08.2012 Ministry of Finance-Vote 21 64,127 100,000,000
31.10.2012 PMO-RALG 63,932 100,000,000
09.11.2012 Ministry of Finance-Vote 21 47,310 74,000,000
14.11.2012 PMO-RALG 37,624 58,865,250
14.11.2012 Ministry of Finance-Vote 50 684,939 1,071,625,000
19.11.2012 Ministry of Finance-Vote 50 228,312 357,555,000
29.11.2012 National Audit Office 319,653 500,000,000
13.02.2013 Ministry of Finance-Vote 50 1,623,183 2,556,063,000
13.02.2013 Ministry of Finance-Vote 21 334,027 526,000,000
20.02.2013 Ministry of Finance-Vote 21 84,436 134,000,000
25.02.2013 Accountant General 1,122,493 1,780,830,000
25.02.2013 Ministry of Finance-Vote 50 1,308,606 2,076,097,000
28.02.2013 PMO-RALG 46,836 73,965,250
13.03.2013 National Audit Office 626,732 987,600,000
16.05.2013 National Audit Office 105,339 167,200,000
29.05.2013 PMO-RALG 322,079 512,169,500
27
18.06.2013 Ministry of Finance-Vote 50 689,866 1,099,325,000
19.06.2013 Ministry of Finance-Vote 21 11,923 19,000,000
Amount Transferred to Exchequer 8,070,870 12,739,295,000
Balance in The Holding Account as at 30 June,2013 1,042,082 1,661,787,850
Note: Holding Account Balance have been translated at Tshs 1,594.68 per US $ at 30 June 2013
During the period a total sum of Tshs 24,129,665,331 was released to components from
Government Fund, Basket Fund as well as Bilateral Projects. The release by sources was GoT
Tshs. 8,478,922,060/=, Bilateral Projects Tshs. 2,911,448,271/= and Basket Fund Tshs.
12,739,295,000/=
3.3 Actual Expenditure and Commitment
During the period actual expenditure and commitment amounted to Tshs. 19,456,556,160/=
being 81% of the total funds released. Actual expenditure and commitment by source was GoT
Tshs. 7,755,244,698/= being 91% of the released funds; Project Tshs. 2,300,718,540/= (79%)
and Basket Funds Tshs. 9,400,592,922/= being 74% of the released funds. Table 3.3 below
summarizes the overall funds release against actual expenditure for July 2012 to June 2013 while
table 3.4 shows the summary breakdown by component recipients.
Table 3.3: PFMRP IV Summary of Fund Release and Actual Expenditure and commitment
FY 2012/13
SOURCE OF
FUNDS
APPROVED
BUDGET
CUMMULATIVE
RELEASE
CUMMULATIVE
EXPENDITURE
AND
COMMITMENT
% ON
RELEASE
GOT 16,250,000,000 8,478,922,060 7,755,244,698 91%
P 3,996,904,853 2,911,448,271 2,300,718,540 79%
BF 13,350,800,000 12,739,295,000 9,400,592,922 74%
GRAND
TOTAL 33,597,704,853 24,129,665,331 19,456,556,160 81%
28
Table 3.4: PFMRP IV Fund Release against Expenditure and Commitment by component for FY 2012/13
S/N COMPONENT
SOURCE
OF FUND
APPROVED
BUDGET FY
2012/13 RELEASE
EXPENDITUR
E
COMMITED
FUNDS
TOTAL
EXPENDITUR
E AND
COMMITMEN
T
% ON
RELEASE
COMMENT
S ON
COMMITED
FUND
TSHS TSHS TSHS TSHS TSHS
1
POLICY
ANALYSIS
DIVISION
GOT 500,000,000 252,000,000 204,614,260 - 204,614,260 81%
P 1,372,610,557 - - - -
BF 268,000,000 268,000,000 135,891,850 - 135,891,850 51%
SUB TOTAL 2,140,610,557 520,000,000 340,506,110 - 340,506,110 65%
2
PRIME
MINISTER'S OFFICE
REGIONAL
ADMINISTRATION AND
LOCAL
GOVERNMENT
GOT 300,000,000 - - - -
BF
745,000,000 745,000,000 745,000,000 - 745,000,000 100%
SUB TOTAL 1,045,000,000 745,000,000 745,000,000 - 745,000,000
100%
3
EXTERNAL
FINANCE
DIVISION
GOT 150,000,000 12,500,000 12,500,000 - 12,500,000 100%
P 95,530,473 95,530,473 95,530,473 - 95,530,473 100%
BF 115,000,000 115,000,000 - - - 0%
SUB TOTAL 360,530,473 223,030,473 108,030,473 - 108,030,473
48%
4
GOVERNMENT BUDGET
DIVISION
GOT 1,500,000,000 98,800,000 62,870,000 - 62,870,000 64%
- - - - -
BF 470,000,000 470,000,000 34,540,000 - 34,540,000 7%
SUB TOTAL 1,970,000,000 568,800,000 97,410,000 - 97,410,000 17%
5
MINISTRY OF
NATURAL RESOURCES
AND TOURISM BF 127,000,000 - - - -
SUB TOTAL 127,000,000 - - - -
29
S/N COMPONENT
SOURCE
OF FUND
APPROVED
BUDGET FY
2012/13 RELEASE
EXPENDITUR
E
COMMITED
FUNDS
TOTAL
EXPENDITUR
E AND
COMMITMEN
T
% ON
RELEASE
COMMENT
S ON
COMMITED
FUND
6
ACCOUNTANT GENERAL
DEPARTMENT
GOT 3,500,000,000 1,375,000,000 1,023,116,808 1,023,116,808 74%
BF 2,622,840,000 2,138,385,000 1,497,478,427 - 1,497,478,427 70%
SUB TOTAL 6,122,840,000 3,513,385,000 2,520,595,235 - 2,520,595,235
72%
7
PUBLIC
PROCUREMENT
REGULATORY
AUTHORITY
GOT 100,000,000 50,000,000 50,000,000 - 50,000,000 100%
P 2,032,520,000 2,319,673,975 1,708,944,244 - 1,708,944,244 74%
BF 1,317,188,000 1,317,188,000 1,317,188,000 - 1,317,188,000 100%
SUB TOTAL 3,449,708,000 3,686,861,975 3,076,132,244 - 3,076,132,244 83%
8
GOVERNMENT
ASSET
MANAGEMENT
GOT 200,000,000 50,000,000 44,296,796 44,296,796 89%
BF 1,378,572,000 1,378,572,000 204,836,950
591,102,665 795,939,615 58%
Signed
Contracts
SUB TOTAL 1,578,572,000 1,428,572,000 249,133,746
591,102,665 840,236,411 59%
9
INTERNAL
AUDITOR
GENERAL
DIVISION
GOT 300,000,000 - - - - TZS
485,364,980 Signed
Contracts and
TZS 395,935,020 Associated
costs
BF 1,323,050,000 1,323,050,000 373,957,935
881,300,000 1,255,257,935 95%
SUB TOTAL 1,623,050,000 1,323,050,000 373,957,935
881,300,000 1,255,257,935 95%
10
NATIONAL
AUDIT OFFICE
GOT 7,500,000,000 5,700,000,000 5,700,000,000 - 5,700,000,000 100%
P 469,097,486 469,097,486 469,097,486 - 469,097,486 100%
BF 1,654,850,000 1,654,800,000 1,654,800,000 - 1,654,800,000 100%
SUB TOTAL 9,623,947,486 7,823,897,486 7,823,897,486 - 7,823,897,486 100%
11
FINANCIAL
INFORMATION SYSTEMS
MANAGEMENT
GOT 600,000,000 206,750,000 192,206,211 - 0%
BF 243,000,000 243,000,000 128,315,352
69,888,096 198,203,448 82%
On-going
contract
SUB TOTAL 843,000,000 449,750,000 320,521,563
69,888,096 198,203,448 44%
30
S/N COMPONENT
SOURCE
OF FUND
APPROVED
BUDGET FY
2012/13 RELEASE
EXPENDITUR
E
COMMITED
FUNDS
TOTAL
EXPENDITUR
E AND
COMMITMEN
T
% ON
RELEASE
COMMENT
S ON
COMMITED
FUND
12
GOVERNMENT COMMUNICAT
ION UNIT
GOT 200,000,000 88,500,000 88,403,440 - 88,403,440 100%
BF 276,000,000 276,000,000 100,231,430 - 100,231,430 36%
SUB TOTAL 476,000,000 364,500,000 188,634,870 - 188,634,870 52%
13
ADMINISTRATI
ON AND
GENERAL
GOT 173,500,000 3,500,000 - - - 0%
BF 107,000,000 107,000,000 72,100,000 - 72,100,000 67%
SUB TOTAL 280,500,000 110,500,000 72,100,000 - 72,100,000 65%
14
PLANNING
DIVISION
GOT 864,000,000 379,372,060 343,064,861 - 343,064,861 90%
P 27,146,337 27,146,337 27,146,337 - 27,146,337 100%
BF 1,348,500,000 1,348,500,000 841,831,942
86,623,800 928,455,742 69%
On-going
contract
SUB TOTAL 2,239,646,337 1,755,018,397 1,212,043,140
86,623,800 1,298,666,940 74%
15
TREASURY REGISTRAR
GOT 300,000,000 200,000,000 198,593,103 - 198,593,103 99%
BF 372,800,000 372,800,000 320,345,000 - 320,345,000 86%
SUB TOTAL 672,800,000 572,800,000 518,938,103 - 518,938,103 91%
16
PUBLIC PROCUREMEN
T POLICY
DIVISION
GOT 62,500,000 62,500,000 27,785,430 - 27,785,430 44%
BF 482,000,000 482,000,000 170,101,550
166,734,000 336,835,550 70%
Signed
Contract
SUB TOTAL 544,500,000 544,500,000 197,886,980
166,734,000 364,620,980 67%
17 ZANZIBAR BF 500,000,000 500,000,000 8,325,925 - 8,325,925 2%
SUB TOTAL 500,000,000 500,000,000 8,325,925 - 8,325,925 2%
GRAND
TOTAL 33,597,704,853 24,129,665,331 17,853,113,810
1,795,648,561 19,456,556,160 81%
BY SOURCE
GOT 16,250,000,000 8,478,922,060 7,947,450,909 - 7,755,244,698 91%
31
S/N COMPONENT
SOURCE
OF FUND
APPROVED
BUDGET FY
2012/13 RELEASE
EXPENDITUR
E
COMMITED
FUNDS
TOTAL
EXPENDITUR
E AND
COMMITMEN
T
% ON
RELEASE
COMMENT
S ON
COMMITED
FUND
P 3,996,904,853 2,911,448,271 2,300,718,540 - 2,300,718,540 79%
BF 13,350,800,000 12,739,295,000 7,604,944,361
1,795,648,561 9,400,592,922 74%
32
CHAPTER FOUR
CHALLENGES AND RECOMMENDATIONS FOR NEXT PERIOD
Challenges
1. Late release of funds delayed the start of some critical activities. The DP disbursements were
received between October and late December, 2012. However, implementation of some
activities went on and the programme was in full swing by the end of December, 2012. As
such, actual expenditure will be captured in the next report. The challenges on delays of
operational funds release to components at the beginning of the fiscal year is anticipated to
be resolved under the new government budget cycle whereby, by end of June, the
Government Budget and Appropriation Bill will be approved by the Parliament for execution
from July 1st of each financial year.
2. The absence of the PFMRP GoT Secretariat to Support coordination. Given the absence, the
component managers showed dedication to ensuring activities were undertaken, challenges
addressed and information shared in TWGs and ad-hoc meetings.
Recommendations for next Financial Year (2013/14)
1. To build on the pace of PFMRP implementation, TWGs will continue to meet on a regular
basis to review emerging implementation constraints. Information sharing is to be enhanced
for smooth coordination to streamline Action Plan and Cash Flows.
2. Components are encouraged to undertake comprehensive capacity assessment in terms of
working tools and technical skills for the work load and nature of activities as per milestone
targets.
3. Linked to above, all stakeholders will begin to prepare the ground work (agreements) on the
possible revision of targets in the M&E framework so as to ensure that the process is
completed in time.
33
4. Given that a number of reform areas are dependent on legislative amendments, the TWGs
will endeavor to list their pending respective legislative so that top management can be
informed to take appropriate action.
It is anticipated that flow of operational funds to components will improve in the third quarter
and thus implementation pace will have fully picked up. Government is committed to strengthen
and improve coordination of PFM reform agenda and stakeholders are encouraged to take an
active role to support and embrace results-oriented reforms interventions. The DPs, basket fund
and project contributors, share a common interest in ensuring synergy of efforts and resources in
a view to facilitate a smooth implementation of the programme.
An important development and exercise for the next period will be the repeat (third) assessments
of the PFM system at both central and local government through the PEFA assessments. The
GoT, jointly with the DPs, is committed to applying PEFA as a means of monitoring
improvements in Public Finance Management (PFM) in the country. The assessment process and
the PEFA report will be monitored and endorsed by the PFMRP through the Joint Steering
Committee (JSC) with PEFA secretariat verification checks along the process.
34
Annex 1
PFMRP ANNUAL REPORT FOR FY 2012/13
PFMRP IV M&E RESULT FRAMEWORK 2012 – 2017
STATUS AS AT 30TH
JUNE 2013
CODE: MILE STONE DESCRIPTIONS STATUS
(State
whether
Achieved,
On track,
Delayed
Pending,
At Risk)
COMMENTS ON THE STATUS RESPONSIBLE
COMPONENT
KRA 1: Revenue Management
Output 1.1: Improved quality of forecasting of fiscal aggregates for three years on a rolling basis
1.1.1 Study on forecasting targets and actual
revenue collection by June 2013
Delayed It was agreed that the milestone was vague. As such; it
was to be discussed during the 2013 supervision mission
TWG and rephrased to capture the core subject and
objective of the milestone. Given the reports from the
CAG and and PFM do not help to show the extent of
problem (model or use of the model), the intention of the
study is to help to have a more realistic revenue
projection. TRA has indicated that it is ready to conduct
the study.
PAD
35
1.1.2 Recommendations from study on forecasting
targets and actual revenue collection informs
budget preparations for budget 2014/15.
Pending This milestone needs to be rephrased in right of the
above milestone.
PAD
1.1.3 A team of trainers in revenue forecasting
developed by June 2014 (The milestone to be
reviewed in line with recommendation from
the study)
On track The implementation of this activity was planned to be
done between April and June 2013. However, it was
postponed to July, 2013 due to other pressing activities in
regards to Budget preparation. 2 TRA and 1 external
consultant are on board to the 5 trainees selected. The
study still remains an important output in terms of
improving the training.
PAD
Output 1.2:The Government improves efficiency in domestic revenue mobilization both at the policy and the administration levels by
updating legal instruments towards international best practices
1.2.1 The study on Non Tax Revenue (NTR) -
“Integration and Harmonization of Revenue
Collection Systems” completed by November
2013.
On track The study is on progress. The consultant is in the field
collecting data.
PAD
1.2.2 Submission of a bill to Parliament to enact Tax
Administration Act for the purpose of
establishing a common tax procedure among
different taxes collected by Tanzania revenue
authority (TRA) by November 2013
At risk A draft of Tax Administration Bill has been submitted to
the cabinet for approval. It is expected that Cabinet
approval and Attorney General Verification will be done
in time for the Bill to be submitted to parliament
depending on parliamentary calendar.
PAD
1.2.3 Review laws, rules and regulations for local
government revenue system to improve LGA
own sources in line with best practice by June,
2016
Pending Progress on Local Government Finance Act revision as
per milestone 1.3.6. As the LGAs are governed by
different laws (such as The Local Government (District
Authority) Act CAP 287, The Local Government (Urban)
Act CAP 288 and the Urban Authority (Rating) Act CAP
289) and other rules and regulations such as the Local
PMO-RALG
36
Government Financial Memorandum, these may also
need to be amended/reviewed to accommodate the
changes made under Local Government Finances Act
No. 9.
1.2.4 Take policy action to improve revenue
mobilization from natural resource sectors by
June, 2014
On track ToRs for consultancy to recommend policy action have
been developed and await availability of funds. However,
MNRT has some made progress: review of different fees
and charges chargeable for different services (antiquities,
royalty fee for forest products) to reflect the market
price; introduction of Tourism Development Levy (TDL)
with first collection started this year expecting to
contribute the increase of revenue by about 10 billion
TZ; grading of hotels in Dar es Salaam, Arusha and
Manyara regions which facilitates correct charge of
TALA License as well as improving tourism facilities
database; follow - up visits to revenue collection areas
and training to about 230 revenue collectors on the
regulations governing revenue collection in natural
resources sector, rules and regulations of revenue
collection as per Public Finance Act 2001 (Revised 2004)
MNRT
1.2.5 The action plan to implement the
recommendations from review of non tax
collection developed and implemented by June
2016
On track The action plan will be developed once the study is
finalized. Revised milestone and an interim (new)
milestone have been developed and renumbered next to
non-tax study: “1.2.2 Action plan to implement the
recommendations from review of non-tax collection
developed by June 2014” and “1.2.3 Costed action plan
incorporated in FY2015/16 for implementation.
PAD
37
1.2.6 Computerized revenue collection to at least
50% of participating MDAs and LGAs by
2016
On track Almost 50% reached mainly in Wildlife and Tourism.
Computerization of revenue collection is as a result of
recommendations of non-tax studies done over the years.
The Ministry has established two Computerized Revenue
Collection Systems which are now in use in Photographic
Tourism and Hunting Tourism using its recurrent budget.
Hunting Tourism system was operationalised in July,
2012 while Photographic Tourism System came into use
in July, 2013. Also the Ministry is in last stages of
completion of Logs Tracking System which will be used
by Tanzania Forest Services. In the year 2013/2014 the
Ministry is expecting to establish Tourism Operators
Licensing System. This system is expected to start in
January, 2014. (Milestone to be changed following
forestry moving to separate agency: link to LGA revenue
collection was with forestry dept)
MNRT
1.2.7 New TR's Bill presented to the Parliament by
June 2013
Delayed The first draft of new TR Bill has been submitted to
Cabinet Secretariat for an initial review. The bill is
expected to be sent to parliament by June, 2013
TR
1.2.8 150 Parastatals' Act Reviewed to be in line
with the New TR Act by June 2014
On Track The review of the individuals’ Parastatals acts will begin
after the bill is passed. However areas of conflicts have
been identified and incorporate in the new TR act
TR
1.2.9 TR's Office Capacities enhanced by June 2015 On track 33 TR Staff attended short courses in 2012/13 TR
1.2.10 M& E system for Parastatals reviewed and
implemented by June 2015
On track
Establishment of monitoring framework is reliant on the
enactment on the new TR Bill. Given the timeframe for
the Bill there is optimism that the framework will be set
up by June 2014. Further, TR undertook review of 31
TR
38
financial regulations, 31 staff regulations, 32 schemes of
service, 3 voluntary agreements and 12 strategic plans.
The mission was informed that the TR Act will be more
stringent on compliance. It is recommended that the
TWG during the Supervision Mission reviews this
milestone together with 4.4.3 and 4.4.4 as these three
milestones seem to refer the same monitoring
framework/M&E system.
1.2.11 Review the current system of tax exemptions
with the value-added Tax (VAT) regime and
amend the VAT Act with a view to be in line
with international best practices by November
2014
On track The Cabinet paper for the VAT Act is being prepared
with support from IMF consultant. The draft bill will
shared to internal stakeholders for comments.
CPAD
Output 1.3: Strengthened capacity of local government authorities to collect revenue by 2015
1.3.1 Completed assessment and evaluation of
revenue potential for major sources of
revenue to all LGAs by June 2013
Delayed Survey conducted to identify major revenue potentials in
30 LGAs including Shinyanga MC, Tabora MC, Magu
DC, Urambo DC, Kahama/Ushetu DC, Bunda DC,
Mtwara MC, Lindi MC, Mtwara DC, Newala DC,
Nachingwea DC, Ruagwa DC, Songea MC, Mbeya CC,
Iringa MC, Mbinga DC, Mbarali DC, Mufindi DC, Ilala
MC, Morogoro MC, Mpwapwa DC, Mvomero DC,
Kibaha TC, Bagamoyo DC, Arusha CC, Moshi MC,
Monduli DC, Siha DC, Korogwe TC and Muheza DC.
The process of collecting field data and the preparation
of initial draft report was completed. The report is
expected to be completed before the end of August,
2013.
PMO-RALG
39
1.3.2 PMO - RALG staff and Finance Management
Officers at RS are trained in tax revenue plans
and budgets to spearhead LGAs tax reviews
and reforms, June 2013
Delayed Training has not been undertaken yet. The TORs for the
consultant to conduct the training are yet to be shared and
training is expected to be completed before Dec 2014. A
total of 8 personnel will be trained: 8 staff from
PMORALG and 4 staff from RAS.
PMO-RALG
1.3.3 Local Authorities Tax administration teaching
and practice modules established and TOT
completed for all finance management staff at
the regional levels by June 2014
On track The training modules and TOT are yet to be developed
as part of 1.3.2.
PMO-RALG
1.3.4 Four (4) revenue accountants, 3 Council
management team members and 1 FMO from
each LGA and RS are trained on own source
revenue management in every two years.
On Track The ToT will facilitate the training of LGA staff as a
Step-by-step approach: Study Develop training
modules Train the ToT team (PMORALG and RS)
Train LGA.
PMO-RALG
1.3.5 Establishment of known and clear revenue
data base by each source of revenue, presence
of trained personnel and a clear follow up
arrangement at PMORALG and RS levels by
June, 2014
Pending The database is supposed to be developed based on the
study and encompass sources, rates, potentials, budget,
and collection methods. There is need to agree on the
intermediate steps to be taken for establishment of a
revenue database and for PMORALG to unpack this
milestone to reflect the work that needs to be covered on
the ground.
PMO-RALG
1.3.6 Completed study on the effectiveness,
relevancy and sufficiency of the provisions of
the Local Government Finances Act No. 9 by
June, 2013
Delayed . PMORALG to provide more details on status of the
study (i.e., TORs development, etc). However, no funds
were released for this activity.
PMO-RALG
1.3.7 A bill for an act to amend the Local
Government Finances Act No.9 of 1982 is
finalized and submitted to the Cabinet by
February 2014
At risk This activity is dependent on the study (milestone above)
completion. However, no funds were released for this
activity.
PMO-RALG
40
Output 1.4: Increase of Donor funding that flows through the exchequer system by 2016
1.4.1 National framework for managing
development cooperation (JAST) be reviewed
and put in operation by December 2012
Delayed Following the change in the budget cycle, the responsible
authorities for formulation of DCF were pre-occupied by
the budget activities and so were compelled to postpone
finalization of new DCF to the year 2013. Final version
of DCF is expected in October, 2013.
EFD
1.4.2 Revised JAST and AMP user guideline clearly
communicated to both parties by December
2012
Delayed JAST user guidelines to be shared as soon as it is
completed. Training on updated AMP was conducted to
obtain feedback from users. This feedback will be used to
improve the user guidelines which are been revised.
Further, the milestone needs to be revised to relate only
to AMP user guidelines and not revised JAST (DCF)
guidelines
EFD
1.4.3 Analysis of the trends of the direct project
fund portfolio disbursed via exchequer system
published and shared annually by June 2015
On Track The annual report of trends was published. The PEFA
2013 report positively highlights that the use of country
PFM systems by donors has improved. However, both
the PEFA and the EFD emphasised that there is more that
needs to be done particularly in creating a clear
understanding to both DPs and Sector Ministries/Project
implementing agencies on the importance of having
project funds on government budget
EFD
41
KRA 2: Planning and Budgeting:
Output 2.1: Strengthened capacity of MDAs, RSs and LGAs in implementing program based budgeting by June 2016.
2.1.1 All Sub programs, program objectives and
performance indicators defined by December
2012
On track Programs and sub-programs have been (tentatively)
defined and objectives, outputs and performance
indicators were developed from MKUKUTA II and
FYDP. Eight ministries were involved in training as a
part of pilot phase in fiscal year 2012/13. These
ministries are Community Gender and Children, Ministry
of Finance, Ministry of Education and Vocational
Training, Ministry of Health and Social Welfare,
Ministry of Agriculture, Food Security, Cooperatives,
Ministry of Water and Ministry of Infrastructure.
GBD
2.1.2 Chart of Accounts modified to accommodate
program based budgeting by Aug 2013
Achieved Chart of accounts has been modified to accommodate
PBB.
GBD
2.1.3 MTEF reviewed to make program based
budget compatible by September 2014
On track Pilot MDAs reviewed their MTEF Plans GBD
2.1.4 Progress on the PBB Action plan
implementation annually
On track Continued to implement the Action Plan though it was
affected by the change of the budget cycle. The activities
lagging behind will be dealt with in the FY 2013/14
GBD
2.1.5 Completed phased training for all MDAs and
RSs by June 2014
On track Pilot MDAs were trained on the basic concepts of PBB
and reviewed their MTEF Plans based on PBB setting
GBD
2.1.6 Completed phased training for all LGAs by
June 2014
Pending The pilot for MDAs is still ongoing. The training for
LGAs will be decided at a later stage.
GBD
Output 2.2:Increased effective utilization of Planning and budgeting tools by 2016
2.2.1 MTSPBM reviewed by June 2013 Delayed Implementation of this activity was affected by the
implementation of the New budget Cycle; the division
GBD
42
intends to implement this activity in the FY 2013/14
2.2.2 Sixty MDAs, 21 RSs and 133 LGAs trained in
MTSPBM by June 2014
On track However, completion may be delayed as MoF is only at
the stage of developing a Training Budget Manual.
GBD
2.2.3 Reviewed MTSPBM to be applied during FY
2013/14
Pending To be applied in FY 2014/15 GBD
2.2.4 Annexes to budget book volume II for
Executive Agencies completed by June 2014
On track This milestone will be partially achieved by timeline, as
only some of the 133 public agencies will be covered by
June 2014. It will be included in the PBB Action Plan,
the level of detail required for these annexes is still under
discussion. MoF plans to organize training on MTEF to
public agencies
GBD
2.2.5 Action plan on implementation of
recommendations on budget legal framework
completed by June 2013
Delayed Mainly due to external constraints. Review of the Public
Finance Act is under process but the new Constitution is
likely to further delay it. The Local Government Finance
Act will also need to be changed, as it currently doesn’t
include IFMS. The PPP Act will also be changed. In
parallel, the Parliamentary Budget Committee is pushing
to have a separate Budget Act. Budget to advise on new
timeline.
GBD
2.2.6 At least 10 PER Main Dialogue meetings held
by June 2016
On track The PER process has been strongly revitalised since June
2012. The PER Champion Group has had regular
meetings on the on-going 5 studies and an annual
dissemination workshop is planned for beginning of
October 2014.
GBD
43
2.2.7 Phased training to MDAs, RSs and LGAs
Budget Committees on resources prioritization
and planning
On track Training for MDAs on Prioritization and Planning was
carried out and also MDAs were oriented to the New
budget cycle for their comments and implementation
GBD
2.2.8 Mechanism for quality assurance of Quarterly
Budget Performance Reports (level of detail,
timeliness, accuracy, consistency and
usefulness to decision makers, as well as for
budget transparency to citizens) established by
June 2013
Delayed GBD
Output 2.3: Strengthened capacity of LGAs for MTEF preparation by 2015
2.3.1 Proposal for budget information to be included
in the Budget guideline to be submitted to
National Budget Guideline committee by
October annually.
Achieved The process of collecting, scrutinizing and submitting all
LGAs own source budget information to National Budget
guideline Committee has successful been done.
PMO-RALG
2.3.2 Recommendations of various studies on LGAs
budget allocation formula reviewed by
December, 2012
Delayed There are significant delays in the review of the LGAs
budget allocation formulas. Analytical review has not
started yet, which puts at risk the whole sequence of
milestones.
PMO-RALG
2.3.3 Agreement on improvement of LGAs budget
allocation formulas among the sector Ministry
(PMORALG, MOF, PO-PSM and Sectors)
completed by June 2013
Delayed Pending achievement of 2.3.2. PMO-RALG
2.3.4 All LGAs budget allocation formulae reviewed
by June, 2014
Pending Pending achievement of 2.3.3 PMO-RALG
2.3.5 All reviewed LGAs budget allocation formulae
applied in the budget preparation during
2014/15 for the FY 2015/16 budget.
Pending Pending achievement of 2.3.4 PMO-RALG
44
2.3.6 Monitoring arrangements are in place for
measuring deviations in actual releases against
all formula-based allocations to LGAs by June
2015.
Pending Pending achievement of above milestones PMO-RALG
KRA 3: Budget Execution, Transparency and Accountability
Output 3.1 Improved public procurement performance by PEs by June 2015
3.1.1 Annual PPRA audit results confirm positive
trend on a yearly basis
On track Annual audit conducted and a preliminary result
indicates positive trend based on compliance and Value
for Money (VfM) audits in 30 PEs.
PPRA
3.1.2 Revised Procurement Implementation and
monitoring tools issued by December 2013
On Track A consultant has been hired to develop the Procurement
Implementation tools in line with the PPA,2011 and new
regulations which awaits approval of the Minister
PPRA
3.1.3 New Public Procurement Act, 2011,
Regulations and Tools disseminated to major
PE's and other stakeholders by December 2015
On track PPA, 2011 has been disseminated to 85 Board of
Directors and 189 Accounting officers of Public Entities.
PPA has been disseminated in in June and July 2013.
However, there are delays in the regulations given other
consideration to be incorporated in the PPA (e.g PPP
issues)
PPRA
3.1.4 Procurement Plans aligned with MDAs, LGAs
and Parastatals Institutional Strategic Plans by
June 2015
Achieved It has been mandatory that Public Procurement lan to be
part of the strategic plana and budget in the new PPA. A
3 days workshop was conducted for chairpersons of
LGAs council committees for Finance and planning do
deliberate on various procurement issues. 150
participants attended the workshop.
PPRA
3.1.5 Value for money procurement enhanced by
Framework contracts for common use items
and services by June 2017
On track A survey to update database on average prices of goods
and services in collaboration with GPSA is underway.
PPRA
45
3.1.6 PPRA operational and outreach capacity
strengthened by June 2014
On track A feasibility study for developing a permanent office in
Dar es Salaam has been done. Also procurement of
contractors for developing DSM and Arusha zonal
offices is on final stages. The Authority has requested
Municipal Councils, Ministry of Finance and GPSA for
allocation of office spaces in Mwanza, Dodoma and
Mbeya Regions for opening other offices.
There is a need to recruit 89/90 new staff to top the
current 52 staff. PPRA has requested a budget for new
staff and awaiting PO-PSM approval.
PPRA
3.1.7 All (393) PEs will have a fully functional
PMIS as a reporting tool for procuring entities
to report back to PPRA by Nov 2014
On track 610 Users from 299 PEs are now registered and use
PMIS
PPRA
3.1.8 e-procurement will start functioning as pilot
stage by Nov. 2016
On track Terms of reference for a consultancy has been developed
but will be finalized after approval of the new regulations
of PPA, 2011. A study tour will also be done by the
Board to learn from experiences of other countries.
PPRA
3.1.9 393 PEs audited by June 2013 Achieved 434 PEs were audited PPRA
3.1.10 Follow up audit of 100 PEs to be done
annually by 2016
On track This procurement audit for 2012/13 started in April 2013
and it is ongoing until end of August 2013.
PPRA
3.1.11 Annual Procurement Performance Evaluation
Report prepared and published annually
Achieved Annual Performance Evaluation Report for FY 2011/12
was prepared and submitted to the Minister in October,
2012.This report was submitted to the Parliament, PEs
and published PPRA website.
PPRA
Output 3.2: Strengthening public sector procurement by June 2015
3.2.1 Action Plan for implementing Public
Procurement Act is developed by December
Delayed The intention is for MoU with PPPD and PPRA to spell
out the cooperation so as to facilitate the PPA Action
PPRA
46
2012 (Milestone to be revised after finalization
of action plan)
Plan, harmonize and remove gaps.
3.2.2 New public procurement regulations prepared
and issued by June 2013
Delayed Parliament passed the PPA in 2011 and the draft of the
public procurement regulations has been prepared and
submitted to the Attorney General’s office for
verification. Following the minister’s finalization, the
regulation will be submitted to responsible parliamentary
committee.
PPD
3.2.3 Procurement training needs assessment
exercise completed by June, 2013
Delayed The consultant to carry out the exercise for LGAs (phase
I) has been hired and the inception report is under
preparation. The TOR for` MDAs (phase II) has been
submitted.
PPD
3.2.4 [300] procurement staff trained on public
procurement by June 2017 as per TNA.
Pending Pending. Will be done after completion of TNA exercise.
It was agreed that the number and type of training will be
revisited depending on the findings and
recommendations of the TNA. There may be need to
prepare for training modules given the TNA
recommendations.
PPD
3.2.5 Strategy on public procurement human
resource management developed and
disseminated by June, 2015
On track Zero draft for proposed PMU structure in the Public
Sector has been prepared using internal means instead of
using consultants.
PPD
3.2.6 Procurement and supplies staff database
maintained and updated by December, 2015
On track Data base information for 1,022 Public Procurement and
Supplies Staff have been verified (in Tanga and
Morogoro regions) and updated.
PPD
3.2.7 National procurement policy draft is finalized
by June 2013
Delayed The national procurement policy draft has been prepared
pending the accompanying implementation plan. The
national procurement policy draft will explain the PPA
and covers central and local government. A consultant
PPD
47
has been hired from University of Dar salaam and has
submitted a framework paper.
3.2.8 Stakeholders’ comments incorporated by June,
2013
Achieved Stakeholders’ meeting conducted and comments
incorporated in the draft National Procurement Policy.
PPD
3.2.9 PPDs' office and staff capacity enhanced by
June, 2013
On Track Eight PPD staff capacity enhanced with skills on public
policy formulation, implementation and evaluation.PPD
will offer training on public procurement policies for
those with relevant responsibilities. There are currently
17 staff in PPD.
PPD
3.2.10 -
3.2.17
The following milestones are related to the
final national procurement policy:
20 members of PPD staff equipped with
skills on public policy formulation,
implementation and evaluation by June,
2013
National procurement policy developed and
shared by December, 2014
National procurement policy (NPP) strategy
developed and implemented by June 2015
Printing and uploading the NPP on the
website by June, 2015
National procurement policy and
procurement law synchronized by June, 2015
Monitoring the implementation of the
National procurement policy by June, 2015
Evaluation and feedback of the
implementation of the National procurement
policy by June, 2016
On track On track. Will be done after completion of the National
Public Procurement Policy. The 2014 onwards targets for
the national procurement policy are all on track – targets
within reach.
PPD
48
1000 Stakeholders acquainted with the
National procurement Policy by June, 2016
Output 3.3:Strengthened capacity of MDAs Rs and LGAs in Cash Management by 2015
3.3.1 600 staff of MDAs and LGAs Trained on cash
Management using standardized materials by
June 30 2014( Milestones to be reviewed and
aligned after the East AFRITAC
recommendations on Cash and Banking
Arrangement Mission)
On track 271 staff from MDAs were trained on cash Management. ACGEN
3.3.2 Six bank accounts operated by each LGA by
December, 2013
Achieved Each LGA is now operating with six bank accounts ACGEN
Output 3.4: Strengthened Public Debt Management Capacity by 2015
3.4.1 The agreed actions arising from the Feb. 2012
World Bank debt management report shared
with key stakeholders by July 31, 2012
Achieved The report has been shared and it is available in the
Ministry of Finance website
PAD
3.4.2 Debt management policy developed and
shared by June 2013
Delayed
With technical support from the World Bank and the East
African MEFMI, MOF intends to conduct a debt
sustainability analysis (DSA), which covers both
domestic and external debt. The DSA output is expected
to serve as key inputs for the country’s new Public Debt
Management (PDM) Strategy that will guide the
government borrowing policy going forward.
PAD
3.4.3 Capacity of 50 Public Debt management staff
enhanced by June 2014
Pending
Despite funds not being available, capacity continues
adhoc basis (such as secondment of GoT to MEFIM on
risk management and another to WB HQ) while waiting
for PO PSM approval of new structure of DMO when a
PAD, ACCGEN
49
capacity building assessment will inform the capacity
needs. The new structure would include a middle office -
MO (PAD), front office -FO (BoT) and Back Office- BO
(ACGEN)
3.4.4 Reviewed Government Loans, Guarantees and
Grants Act by June 2014
On track
Review in progress. Team is drafting the revised Act
(combined with work on strategy). The draft will
incorporate provisions that will insure a greater control of
public indebtedness growth, and limit fiscal risks
stemming from contingent liabilities and also consider
possible conflicting legal frameworks under PPP Act and
Loans and Guarantees Act among others.
PAD
3.4.5 Debt Management department established by
June 2016.
On track
Despite funds not been released from basket funds,
waiting for presidential approval to operationalize and
provide the effective date for new DMO.
PAD
Output 3.5: Improved Integrity and content of government financial statements and migration from IPSAS cash Basis to
IPSAS accrual is progressing in accordance with the plans.
3.5.1 Completed review of the IPSAS guideline
issued by PMORALG in 2008/09 to
accommodate the recent IPSAS updates by
June 2013
At risk It will be reviewed next FY. The TWG ACGEN was not
clear on if the review is related to the financial statement
as there is no IPSAS guideline issued by PMORALG.
Does this milestone relate to the need for the accounting
manual or template? Or should this milestone be
transferred to PMORALG?
ACGEN
3.5.2 Training to MDAs, RSs and LGAs accounting
officers to develop awareness on IPSAS
Accrual by 2013
On track 320 people (chief accountants from MDAs, Public
Accounts Committee (PAC) members and staff from
foreign embassies) have been trained.
ACGEN
50
3.5.3 Capacity building to 250 staffs from MDAs,
RSs and embassies to enhance skills in IPSAS
Accrual by 2014.
Achieved 250 staff from MDAs and Embassies were trained e on
IPSAS accrual.
ACCGEN
3.5.4 Public Finance Act. of 2001 and regulations
reviewed to address migration to IPSAS
accrual by 2016
On track The work is in progress. The committee is still collecting
opinions from various stakeholders. A draft of the
revised PFA is ready and currently is being circulated for
Stakeholders ‘comments since August 2012. It includes
provisions for migration to IPSAS Accrual and other
considerations including CAG and others
ACGEN
3.5.5 Consolidated template of financial statements
to include MDAs, Rs, LGAs, Controlled
entities and GBEs developed by June 2016
On track Currently the template of financial statement of MDAs
and RS has been completed. The rest of entities will be
taken on board as per the road map.
ACGEN
3.5.6 250 government accountants in MDAs /LGAs
trained in IPSAS accrual and accrual modules
for Epicor by September 2013
Achieved Training was conducted on IPSAS Accrual basis to
MDAs, RS & Embassies accountants.
ACGEN
3.5.7 Plan for migration towards IPSAS Accrual
accounting is completed by December 2013.
Achieved The 5 year road map is in place and often upgraded to be
fully compliant to IPSAS.
ACGEN
3.5.8 Plan is approved for execution and stakeholder
information sessions have been completed by
January 2014
Achieved The plan has been approved and is in use. Awareness
been done to some of the stakeholders (e.g. PAC
members). Other groups will follow
ACGEN
3.5.9 All legislative and policy supports have been
identified by 31st Dec.2014
On track Some of the legislative and policy supports have been
identified such as accounting policy, PFA, Accounting
manual, LGF act and TR act. The committee is still
collecting opinions from various stakeholders
ACGEN
3.5.10 Milestones for the transition have been On track Pending the completion of milestone 3.4.5 (Review of ACGEN
51
identified and approved (E.g. Public Finance
Act of 2001 and Regulations) amendments by
October 2014
PFA and its Regulations) Some milestones have been
identified
3.5.11 Plan to integrate all Rs and LGAs operation
into centralized IPSAS accrual architecture is
completed and PMO-RALG is fully engaged
as stakeholder by 31st Dec.2014
Pending Currently the Government (Central) is migrating to
accrual basis of accounting before considering moving in
centralized IPSAS Accrual architecture with all
stakeholders.
ACGEN
Output 3.6: Improve accountability in management of Government asset management for supporting migration to IPSAS
Accrual
3.6.1 Uploading of 16 additional MDAs in EPICOR
by December 2012
Delayed Before establishment of GAMD, 20 MDAs were
intergraded in EPICOR, as such; an additional 16 MDAs
were uploaded (using in house expertise) in EPICOR
making to total 36. The task of verifying assets
importation documents after testing and final uploading
is scheduled to be completed by August, 2013
GAMD
3.6.2 Asset Management (tracking) software
acquired by March 2013
Delayed The consultant was hired to undertake installation of
asset management software before June, 2013. The
installation is foreseen to be completed before
September, 2013.
GAMD
3.6.3 40 staff(25) regional heads(RSVs) and 15 from
HQ) trained on asset management function by
December 2013
On Track 4 staff scheduled to attend training on asset management.
Training programme is available
GAMD
3.6.4 Asset Management Policy prepared and
submitted by June 2015
On Track Contract has been awarded and ongoing. Draft policy is
scheduled to be received by February 2014
GAMD
3.6.5 Valuation of Government assets in 34 MDAs
and Rs completed by June 2016
On Track With support of the consultant, drafted and waiting for
the fund release to embark on tender.
GAMD
3.6.6 Progress against target reported annually At risk Milestone to be redefined GAMD
52
KRA 4: Budget Control and Oversight
Output 4.1: Increased coverage and quality of the internal audit functions by 2016
4.1.1 Operational plan developed and approved by
June, 2013
Achieved Operation Plan for 5 year 2013 – 2017 approved and
disseminated to all Internal Audit Units.
IAG
4.1.2 Internal Audit manual/guidelines, standards
and quality assurance improvement
programme in line with International
Standards will be in place by June, 2013
Achieved a) The manual was prepared. Consultant is
incorporating comments from stakeholders.
b) Quality assurance and improvement program
procedures (QAIP) manual was prepared, approved
and disseminated.
c) Consultant for preparing Audit Committees
guidelines selected.
d) Manuals for LGAs and MDAs have been reviewed
by consultants (August 2012) to ensure consistency
with the International Practice Framework (IPPF),
training has been provided on IPPF and inception
report was produced for guidelines on quality
assurance. Stakeholders’ consultation conducted.
IAG
4.1.3 Effective internal audit units and audit
committees established to all MDAs and
LGAs by June, 2016
On Track a) Training on business processes of EPICOR for 38
internal auditors in MDAs was conducted.
b) Consultant for training of IPSAS selected to allow for
understanding of how financial statements are
prepared.
c) Data of Audit committees and internal auditors
from193 MDAs and RSs were collected.
d) Quarterly Audit Committees minutes for FY 2012/13
and Annual Audit Committees reports for FY
2011/12 were reviewed.
e) Awareness workshop on roles of internal auditors for
IAG
53
226 stakeholders (Mayors, Council Chairpersons and
Internal Audit) was conducted.
f) Training on roles of internal auditors to 114 audit
committees’ chairpersons was conducted.
4.1.4 The Pilot stage of Computerized Audit will be
finalized by June 2014
On track -Procurement of audit software is at tendering stage.
-Training will be conducted after procurement of audit
software
IAG
4.1.5 Computerized Audit in place by June 2016. Pending IAG
4.1.6 550 internal auditors and other stakeholders
trained in risk management process and risk
based audit by June, 2017.
On track a) The contract for consultancy service to train 150
Head of departments and Audit committee Members
from MDAs and LGAs on risk management process
has been signed and training preparation is on
process.
b) The contract for consultancy service to train 160
internal auditors from MDAS and LGAs on risks
based audit, Governance and Controls has been
signed and training preparation is on process.
c) Technical team for review and streamline Risk
Management process in PFA has been selected.
d) Preparation for monitoring the implementation of the
Institutional Risk Management Framework in 20
MDAs and 30 LGAs is on process
IAG
4.1.7 Technical Audits are conducted for 70 Projects
by 2016
On track The baseline survey has been done, Training on technical
audits to Internal auditor to be conducted from July 2013
and consultant already engaged.
IAG
Output 4.2: Strengthened External audit functions by 2016
4.2.1 The committee report on needs of legal
amendments (existing laws) to contribute
Achieved An AFROSAI-E team elevated NAOT to level 3 of
AFROSAI-E capability model in early 2013. The
NAOT
54
towards reaching level 3 submitted to the
attorney General and awareness programs
conducted by December 2012
ambition is now to move towards level 4. As such, a
report on need to revise the Laws and Policies was
submitted to the Attorney General’s Office for action,
however with the ongoing Constitutional review, the
amendment of various laws will follow after the new
Constitution. NAOT submitted to the Constitutional
Review committee NAOT views on Articles related to
NAOT meanwhile addressing Independence of the CAG.
4.2.2 50% of auditors to be accommodated in NAO
own offices by 2014
On track Construction of Dodoma and Rukwa on going, Dodoma
(80%), Rukwa (50%). Procurement process for
identification a Consultant to supervise construction of
two office buildings in Iringa and Mara regions is in final
stage. Meanwhile CAG is renting offices in 5 regions
(Tabora, Mwanza, Iringa, Tanga and Dar es Salaam) and
there are 11 own offices in Dar es Salaam, Morogoro,
Dodoma, Singida, Shinyanga, Kilimanjaro, Arusha,
Manyara, Ruvuma, Mbeya and Lindi regions.
NAOT
4.2.3 300 Auditors trained on Risk Based Audit
and 200 in IT audit by 2014
On track 200 auditors have been trained on Risk Based Audit and
100 auditors have been trained on IT audit. The Risk
Based audit approach will be applied during the coming
audit (October 2013), at the same time the office has
created a group of IT auditors who eventually will form
IT audit unit.
NAOT
4.2.4 Two Value for Money audit reports to be
produced each year by NAO staff without
technical assistance from external consultant
by 2014.
Achieved More than 5 performance audits p.a. are being carried out
using internal coaching, providing a base to build on.
NAOT
55
4.2.5 300 Auditors trained on international
standards of auditing and full adoption of
International Audit Standards by 2014
Achieved 200 auditors have been trained on International Standards
of auditing and 100 senior officers have been trained on
quality assurance. The NAOT Regularity Audit Manual
has been up dated to comply with International
Standards. There is fully adoption of International
standards
NAOT
4.2.6 Closing of books of accounts for Parastatals
harmonized and audit modalities agreed by
2014.
On track Forum with 176 CEOs of Public bodies to discuss on
harmonization of closing of books of accounts and round
table with Board of Directors of Parastatals was
conducted. Decision to harmonize closing of books of
accounts needs time and more discussion at technical
level
NAOT
4.2.7 Audit methodology in line with ISSAIs
guidelines adopted by June 2013
Achieved Alignment of audit methodology is progressing well,
with guidelines already in place.
NAOT
4.2.8 Scoping study to ascertain the parameters of
the outstanding matters Database is completed
by November 2012
Delayed The scoping study has been completed. Data for the
outstanding audit recommendations has been collected,
analysis is on going
NAOT
4.2.9 Establish a database that will separate findings
(monetary and non monetary) and
recommendations including by age, and record
follow up actions by December 2013.
On track Creation of data base for tracking outstanding audit
recommendations is ongoing. Data has been collected
analysis including preparations of software requirements
is ongoing
NAOT
4.2.10 200 Auditors trained on audit commanding
language (ACL) and other audit based
software by 2014
Achieved 200 Auditors has been trained on ACL. The office has
created a group of IT auditors who eventually will form
IT audit unit.
NAOT
4.2.11 NAO Headquarter is connected to 10
Regional offices using WAN by 2014
Achieved 12 NAOT offices have been connected with WAN fiber
optics, the office is currently using intranet for internal
communication with the help of WAN
NAOT
56
4.2.12 Two of five Team mate modules applied in
auditing by October 2014
On track Application of Team Mate modules on track. Action plan
in place to activate four modules with support from NAO
Development project and PFMRP.
NAOT
Output 4.3: Improved transparency on audit report (Central, Local and Parastatals levels) to strengthen scrutiny and accountability)
4.3.1 Citizen audit reports available for the 4
General audit reports by June 2013 and
onward and on annual basis
On track The citizen audit report for 5 General audit reports in
Kiswahili language has been prepared internally and
printed. Dissemination is expected in Mid July 2013.
NAOT
Output 4.4:Improved Performance of Parastatals by June 2016
4.4.1 Ten (10) Parastatals signed Performance
Contracts with TR by June 2014
Pending
The templates are yet to be agreed with the 10
parastatals.
TR
4.4.2 Database on Parastatals set up and functioning
by December 2014
Achieved The TR’s database (TRIMS) developed need to be
transferred to the New TR Office at Samora and updated.
TR
4.4.3 Monitoring framework for Parastatals set up
by June 2014
On track Establishment of monitoring framework is reliant on the
enactment on the new TR Bill. Given the timeframe for
the Bill there is optimism that the framework will be set
up by June 2014. The Milestone has been proposed to be
changed/ merged with others (1.2.10 and 4.4.4).
TR
4.4.4 Mechanism for measuring Parastatals’
compliance rate developed by June 2014
On track Establishment of monitoring framework is reliant on the
enactment on the new TR Bill. Given the timeframe for
the Bill there is optimism that the framework will be set
up by June 2014. The Milestone has been proposed to be
changed/ merged with others (1.2.10 and 4.4.3).
TR
Output 4.5: Strengthened Capacity of oversight functions of Parliamentary Accounts Committees by 2016
4.5.1 Capacity building interventions to PACs
conducted
On track Training to members of Parliamentary Accounts
Committees (PAC and LAAC) on interrogation skills,
understanding of CAG reports and elementary
NAOT
57
understanding of Financial statements was conducted.
Tracking of implementation of projects was facilitated
and MPs visited a good number of projects.
KRA 5: Cross-Cutting Issues (Change Management and Programme Monitoring),
Output 5.1: Coordinate Integration, interfacing and rationalization of Government financial systems.
5.1.1 ICT mapping exercise showing location and
owners of all and peri-financial software
commenced with inception report published by
December 2012
Delayed ICT mapping exercise in progress. Draft report expected
in July, 2013.
FISM
5.1.2 Stakeholder coordination meetings held to
gather input and agree on cross functional
responsibilities for financial systems Planning
held on by December, 2012
Delayed A stakeholder workshop will be held to discuss the report
and recommendations arising from mapping exercise in
view of paving the way for a comprehensive action plan
towards integration option. Workshop to take place as
early as possible.
FISM
5.1.3 Sequenced, prioritized and costed action plan
to bring all GoT financial and peri-financial
software under one common Government
financial systems architecture with supporting
technical, infrastructure and management
structures completed and approved by the GoT
by June, 2013
Delayed It awaits a feasibility study report on ICT mapping on all
GoT financial and peri-financial software from the
consultant
FISM
5.1.4 Integration/Interfacing plan is engaged and
series of planned actions are being executed
and completed by October, 2015
On track. Target within reach. Awaits the process of action plan. FISM
5.1.5 IFMS infrastructure installed to new 34
LGAs, RSs and PMORALG institutions and
connected to central server at Dodoma and
MoF by June 2013
Delayed The process of selecting supplier and the signing of
contract terms for supplying IFMS infrastructure was
completed. The assignment is expected to be completed
at the end of August 2013.
PMO-RALG
58
5.1.6 MoF IFMS linked to PMO-RALG IFMS to the
immediate capture of the Approved Budget
and all Exchequer transfers to RSs and LGAs
respectively by June 2013.
Delayed There is need to recruit a consultant to create an
interface between the two EPICOR systems.
FISM/PMO-
RALG
5.1.7 Completed capacity building to key users of
IFMS from all LGAs, RS and PMORALG
institutions by June 2013.
On Track The initial stages with respect to this activity are in place.
The completeness of the whole processes is expected to
be on or before the end of 30th
September, 2013 as
promised.
PMO-RALG
5.1.8 Audit of IFMIs in LGAs conducted by June
2015
On track Target within reach PMO-RALG
Output 5.2: Utilization of EPICOR modules increased from seven to ten
5.2.1 EPICOR system upgrade complete by
December 2014
Achieved EPICOR system has been upgraded from version 7.3.5
to version 9.05 with 10 modules installed of which 6 are
activated
ACGEN
5.2.2 ACGEN Staff capacity enhanced by Dec.2014 On track Training to 40 ACCGEN staff. ACGEN
5.2.3 Training for IFMS end users on the upgraded
modules conducted by Dec 2014
On track Training in progress as 381 end users were trained on the
new version of EPICOR.
ACGEN
5.2.4 EPICOR is able to provide real-time
information to all LGAs on flow of funds by
July 2015
At risk Milestone to re-formulated PMO-RALG
Output 5.3: All software development and module upgrades are coordinated with the overarching plans for ICT
integration
5.3.1 FISM is operationalized and controls are put
in place to manage software acquisition and
development by December, 2012.
Delayed Server room has been modified to manage acquisition of
software and development, however FISM is still
working on the development of the strategy to control
stand alone software
FISM
59
5.3.2 FISM staff capacity enhanced by June, 2015. On Track 7 staffs have been trained on Data Center Infrastructure
Specialists, ICT Security, Database Management and
Data Center Operations Specialists
FISM
Output 5.4: Improved communication and public access to key fiscal information to stakeholders by 2016.
5.4.1 The Approved National Budget is published
on MOF website by September each year
On track Approved National Budget for 2012/13 published in the
website by September
GCU
5.4.2 Publish Citizens Budget by November each
year
Pending Late start of project implementation and late release of
fund for 2012/13 as such the citizen budget was not
published.
GCU
5.4.3 A Year-End Report (budget out turn)
comparing the actual budget execution to the
enacted budget is published on Ministry of
Finance website by October each year
Pending Budget out turn report for 2012/13 to be published in
November
GCU
5.4.4 MoF Communication Strategy developed and
implemented by June 2013
Delayed The final draft of communication strategy has been
submitted to the ministry communication committee for
proof reading.
GCU
5.4.5 Fiscal Information and Budget Transparency
Publication Cycle developed and implemented
by June 2014
Pending Information is yet to be provided GCU
5.4.6 MoF website timely updated by June 2017 On track Website is regularly updated GCU
Output 5.5: Coordination and Standardization of PFM Training Achieved
5.5.1 Training mapping exercise completed by Dec
2012
Delayed Using In-house expertise, ToRs were developed for the
mapping exercise and finalized by Dec 2012. The
mapping was conducted and it covered 29 ministries, 14
regions and 28 district councils from selected regions.
The final report will be ready during the first quarter of
FY 2013/2014
DAHRM
60
5.5.2 Capacity building Plan developed and shared
with key Stakeholders by June 2013.
Delayed This milestone will be worked out in 2013/14 DAHRM
5.5.3 Two tracer studies conducted to measure the
impact of training and documented by June
2014 and 2016
Pending This milestone will be worked out in 2013/14 DAHRM
Output 5.6: PFMRP Component Managers are being guided by detailed multi-year operating plans
5.6.1 All activities are presented for inclusion in
PFMRP annual work plan are presented within
the context of a detailed multi-year operating
plans by June 2013
Achieved The 2012/13 PFMRP Annual Work plan (as well as five
year provisional work plan) includes activities that are
continually verified to be aligned with component
operational plans.
PD
Output 5.7: PFM activities are effectively planned and implemented
5.7.1 Capacity building Plan developed and shared
with key Stakeholders by Dec. 31, 2012
Delayed This milestone is been reported under milestone 5.5.2 PD/DAHRM
5.7.2 Training on Change Management and Strategic
Planning completed by December 2013
On track The Change Management Training was conducted at
ESAMI HQ to 150 staff from various MDAs.
Meanwhile, 30 Top Management staff from various
ministries was trained on the same by ESAMI in
Dodoma during Bunge Session in June, 2013.
PD
5.7.3 Results Based Management training has been
delivered to 60 PFMRP Component managers
by June 30, 2013.
Delayed Training will be conducted in 2013/14 PD
Output 5.8: Effective coordination of activities and support provided to the programme implementers
5.8.1 Secretariat procurement process completed by
July 2012
Delayed Half of the required Secretariat staff (procurement
specialist, Financial Expert and Communication
Specialist) had been recruited and already working. The
Program Coordinator, M & E Specialist and PFM
PD
61
Specialist are yet to be recruited.
5.8.2 Secretariat work plan is completed and
approved by JSC by December 2012
Delayed Waiting for other members of secretariat to be recruited PD
5.8.3 PFMRP Co-ordination secretariat facilitated
annually.
On track The PFMRP Secretariat was facilitated through provision
of office equipment, consumables, salaries, computers
and office.
ACGEN, PD
Out Put 5.9: PFM programme oversight and review is being guided by clearly defined milestones derived from an agreed M&E framework
5.9.1 Annual review and amendment of the M&E
framework to ensure ongoing congruence and
relevance annually by Nov 2012
On track The 2012 supervision mission recommended that a
thorough review of M& E framework would be more
suitable to be done following the 2013 PEFA results and
as part of 2013 Joint Supervision Mission. .
PD
Output 5.10 All major PFM reforms have been coordinated with and informed by relevant government and DP stakeholders groups
5.10.1 PFM information session completed to
disseminate results of: ICT mapping exercise,
ICT Harmonization Integration Plan by March
2013
Delayed The Information session for the ICT mapping exercise
and ICT Harmonization Integration Plan were not carried
out as planned.
PD
5.10.2 IAG action plan, ACGEN’s Plan to transition
to Accrual Accounting
On track The TWGs agreed to hold to hold awareness/information
sessions on various PFM themes (migration to IPSAS
accrual and creation of DMO) The information sessions
were not performed as planned
IAG , ACGEN’s
5.10.3 Minimum of one PFM reform information day
conducted for CSOs , DPs and GoT during
Public Service day annually by Dec.31st each
year
On track The PFM information session is planned to take place
with effect from 2013 December.
PD
62
Output 5.11: PFMRP implemented efficiently and effectively through result based management approach.
5.11.1 PFMRP implemented according to annual
work plan and milestones are being met
On track The PFMRP Annual work plan was implemented as per
the plan.
PD
5.11.2 Annual supervision mission are conducted by
Sept 30 of each year commencing 2012.
On track The 2012 Supervision Mission was carried out
successfully and the program rated as Satisfactory.
PD
5.11.3 Independent program evaluations are
completed in 2014
On track The evaluation is planned to take place in 2014. PD
5.11.4 Dialogue structures are working as evidenced
by combined DP/GoT Survey results (Survey
1-March 2013, Survey 2-March 2015 for
effective program implementation improved)
On track The dialogue has been on-going and working as required
within the PFMRP structure.
PD
5.11.5 Surveys to ensure that teams (KRA Teams
and JSC members) are actually working
completed, March 2013, March 2015 and
results informed to JSC for action.
On track The survey is planned to take place in the FY 2013/2014 PD
Output 5.12: National systems and process for intergovernmental transfer to LGAs streamlined and rationalized
5.12.1 TORs (for Streamlining and rationalizing
National systems and processes for
intergovernmental transfers to LGAs)
completed by July 2012.
Achieved The ToR was completed and the consultant procured. PD
5.12.2 Mapping commences September, 2012 Achieved The inception report for Mapping exercise was submitted
on February, 2013. The consultant is the field collecting
data
PD
5.12.3 Review and mapping of the systems and
processes for intergovernmental transfers
initiated with inception report finalized by
October 2012,
On track The exercise is on progress and the draft report is
expected in July, 2013.
PD
63
5.12.4 Comprehensive and sequenced action plan on a
recommendation of the mapping exercises on
the intergovernmental transfers finalized by
June 2013.
Delayed The activity was delayed due to delay of the report from
the consultant.
PD
5.12.5 Reports to be produced annually by end
September
Pending Reports to be produced after implementation of the
action plan.
PD
Output 5.13: Strengthened Public Financial Management Reforms in Zanzibar by 2017
5.13.1 Milestones developed and agreed after
discussion with Zanzibar and thereafter decide
on the support by September 2012
Delayed It is waiting development of the strategy ZANZIBAR
5.13.2 Zanzibar PFMRP Strategy developed by June
2013
Delayed Selection process for a consultant to support Zanzibar to
work on its strategic plan for PFM drawing on the
comprehensive PFM evaluation undertaken.
ZANZIBAR
64
Annex 2
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
KRA 1: REVENUE MANAGEMENT
Output 1.1:
Improved
quality of
forecasting of
fiscal
aggregates for
three years on a
rolling basis by
2015
Milestone 1.1.1. Study on forecasting targets and actual revenue
collection by June 2013
-
- CPAD
Milestone 1.1.2. Recommendations from study on forecasting
targets and actual revenue collection informs budget preparations for
budget 2014/15.
-
- CPAD
Milestone 1.1.3 A team of trainers in revenue forecasting developed
by June 2014 (milestone to be reviewed in line with
recommendations from the study)
112,000,000
59,500,000 CPAD
Sub Total 112,000,000 59,500,000
Output 1.2: The
Government
improves
efficiency in
domestic
revenue
mobilization
both at the
policy and the
administration
Milestone 1.2.1. The study on Non Tax Revenue (NTR)-“Integration
and Harmonization of Revenue Collection Systems” completed by
November 2013.
252,000,000
204,614,260 CPAD
Milestone 1.2.2. Submission of a bill to Parliament to enact Tax
Administration Act for the purpose of establishing a common tax
procedure among different taxes collected by Tanzania revenue
authority (TRA) by November 2013
63,000,000
52,000,000 CPAD
Milestone 1.2.3. Review Laws, rules and Regulations for Local
Government revenue system to improve LGA’s own sources in line
with best practices by June, 2016.
-
- PMORALG
65
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
levels by
updating legal
instruments
towards
international
best practices
Milestone 1.2.4.Take policy action to improve revenue mobilisation
from natural resource sectors by June 2014
-
- MNRT
Milestone 1.2.5 The action plan to implement the recommendations
from review of non tax collection developed and implemented by
2016
-
- CPAD
Milestone 1.2.6. Computerised revenue collection to at least 50% of
participating MDAs and LGAs by June 2016
-
- MNRT
Milestone 1.2.7: New TR's Bill presented to the Parliament by June
2013 230,000,000 189,290,000 TR
Milestone 1.2.8: 150 Parastatals’ Acts Reviewed to be in line with
the New TR Act by June 2016
-
- TR
Milestone1.2.9: TR’s Office Capacities enhanced by June 2014 342,800,000 329,648,103 TR
Milestone 1.2.10:M& E system for Parastatals reviewed and
implemented by June 2015
-
- TR
Milestone 1.2.11: Review the current system of tax exemptions with
the value-added Tax (VAT) regime and amend the VAT Act with a
view to be in line with international best practices by November
2014
53,000,000
24,391,850 CPAD
940,800,000 799,944,213
Output 1.3:
Strengthened
capacity of local
Milestone 1.3.1 Completed assessment and evaluation of revenue
potential for all major own sources of revenue to all LGAs by June
2013
150,000,000
150,000,000 PMORALG
66
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
government
authorities to
collect revenue
by 2015
Milestone 1.3.2: PMO - RALG staff and Finance Management
Officers at RS to be trained in tax revenue plans and budgets to
spearhead LGAs tax reviews and reforms. June 2013
100,000,000
100,000,000 PMORALG
Milestone 1.3.3: Local Authorities Tax administration teaching and
practice modules established and TOT completed for all finance
management staff at the regional levels.
-
- PMORALG
Milestone 1.3.4 Four (4) revenue staff, 3 Council management
team members and 1 FMO from each LGA and RS are trained on
own source revenue management in every two years.
-
- PMORALG
Milestone 1.3.5 Establishment of known and clear revenue data base
for each source of revenue, presence of trained personnel and a clear
follow up arrangement at PMORALG and RS levels by June, 2014
-
- PMORALG
Milestone 1.3.6: Completed study on the effectiveness, relevancy
and sufficiency of the provisions of the Local Government Finances
Act No. 9 by June, 2013
31,500,000
31,500,000 PMORALG
Milestone 1.3.7: A bill for an act to amend the Local Government
Finances Act No.9 of 1982 is finalized and submitted to the Cabinet
by February 2014
36,300,000
36,300,000 PMORALG
317,800,000 317,800,000
Output 1.4:
Increase of
donor funding
Milestone 1.4.1: National framework for managing development co-
operation (JAST) be reviewed and put in operation by December
2012
108,030,473
108,030,473 CEF
67
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
that flows
through the
exchequer
system by 2016
Milestone 1.4.2: Revised JAST and AMP user guideline clearly
communicated to both parties by December 2012
115,000,000
- CEF
Milestone 1.4.3: Analysis of trends of direct project fund portfolio
disbursed via the exchequer published and shared annually by June
2015.
-
- CEF
223,030,473 108,030,473
KRA 2: BUDGETING AND PLANNING
Output 2.1
Strengthened
capacity of
MDAs, RSs and
LGAs in
implementing
program based
budgeting by
June 2016.
Milestone 2.1.1: All sub programs, program objectives and
performance indicators defined by December 2012
125,000,000
62,870,000 CB
Milestone 2.1.2: Chart of accounts Modified to accommodate
program based budgeting by August 2013
74,000,000
16,170,000 CB
Milestone 2.1.3: MTEF reviewed to make program compatible by
September 2014
28,800,000
- CB
Milestone 2.1.4: Progress on the PB Action Plan implementation - - CB
Milestone 2.1.5: Completed phased training for all MDAs and RSs
by 2014
39,000,000
18,370,000 CB
Milestone 2.1.6: Completed phased training for all LGAs by 2014 39,000,000 - CB
305,800,000 97,410,000
Output 2.2:
Increased
effective
utilization of
Milestone 2.2.1: MTSPBM reviewed by June 2013 57,000,000 - CB
Milestone 2.2.2: Sixty MDAs, 21 RSs and 133 LGA trained in
MTSPBM by June 2014 CB
Milestone 2.2.3: Reviewed MTSPBM to be applied during FY CB
68
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Planning and
budgeting tools
by 2016
2013/14
Milestone 2.2.4: Annexes to budget book volume II for Executive
Agencies completed by June 2014
61,000,000 CB
Milestone 2.2.5: Action plan on implementation of
recommendations on budget legal framework completed by June
2013
CB
Milestone 2.2.6: At least 10 PER Man Dialogue meetings held by
June 2016
125,000,000 CB
Milestone 2.2.7: Phased training to MDAs, RSs and LGAs Budget
Committees on resource prioritization and planning
20,000,000 CB
Milestone 2.2.8 Mechanism for Quality assurance (timeliness,
accuracy, consistency and usefulness to decision makers) established
by June 2013
40,000,000
- CPAD
303,000,000 -
Output 2.3:
Strengthened
capacity of
LGAs for
MTEF
preparation by
2015
Milestone 2.3.1: Proposal for budget information to be included in
the Budget guideline to be submitted to National Budget Guideline
committee by October annually.
42,575,000
42,575,000 PMORALG
Milestone 2.3.2 Recommendations of various studies on allocation
formula reviewed by December, 2012
47,844,000
47,844,000 PMORALG
Milestone 2.3.3 Agreement on improvement of budget allocation
formula among the Sector Ministries (PMO-RALG, MOF, PO-PSM
and Sectors) completed by June,2013
-
- PMORALG
69
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Milestone 2.3.4 All LGAs budget allocation formulae reviewed by
June, 2014
-
- PMORALG
Milestone 2.3.5 All reviewed LGAs budget allocation formulae
applied in the budget preparation during 2014/15 for the FY 15/16
budget.
-
- PMORALG
Milestone 2.3.6 Monitoring arrangements are in place for measuring
deviations in actual releases against all formula-based allocations to
LGAs by June 2015.
-
- PMORALG
90,419,000 90,419,000
KRA 3: BUDGET EXCUTION, ACCOUNTABILITY AND TRANSPARENCY
Output 3.1:
Improved public
procurement
performance by
Pes by 2015
Milestone 3.1.1: Annual PPRA audit results confirm positive trend
on a yearly basis
66,200,000
66,200,000 PPRA
Milestone 3.1.2: Revised procurement implementation and
monitoring tools issued by December 2013
88,100,000
88,100,000 PPRA
Milestone 3.1.3: New Public Procurement Act, 2011, Regulations
and Tools disseminated to major PEs and other key stakeholders by
December 2015
78,800,000
78,800,000 PPRA
Milestone 3.1.4: Procurement Plans aligned with MDAs, LGAs and
Parastatal Institutional Strategic Plans by June 2015
-
- PPRA
Milestone 3.1.5: Value for money procurement enhanced through
Framework contract in procurement of common use items and
services by June 2017
55,900,000
55,900,000 PPRA
70
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Milestone 3.1.6: PPRA operational and outreach capacity
strengthened by June 2014
1,819,091,921
1,819,091,921 PPRA
Milestone 3.1.7: All (393) PEs will have a fully functional PMIS as
a reporting tool for procuring entities to report back to PPRA by
Nov 2014
644,020,054
33,290,322 PPRA
Milestone 3.1.8: E- Procurement will start functioning as pilot stage
by Nov. 2016 -
- PPRA
Milestone 3.1.9: 393 PEs audited by June 2012
934,750,000
934,750,000 PPRA
Milestone:3.2.10: Follow up audit of 100 PEs to be done annually
by 2016
-
- PPRA
Milestone 3.1.11: Annual Procurement Performance Evaluation
Report prepared and published Annually
-
- PPRA
3,686,861,975 3,076,132,244
Output 3.2
Strengthened
public sector
procurement by
June, 2017
Milestone 3.2.1: Action plan for implementing PPA is developed by
December 2012 (Milestones to be revised after finalization of the
action plan)
-
- PPD
Milestone 3.2.2: New public procurement regulations prepared and
issued by June 2013
-
- PPD
Milestone 3.2.3: Procurement training needs assessment exercise
completed by June, 2013 178,000,000 21,711,800.00 PPD
71
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Milestone 3.2.4: [300] procurement staff trained on public
procurement by June, 2017 as per TNA
-
- PPD
Milestone 3.2.5: Strategy on public procurement human resource
developed and disseminated by June, 2015 73,000,000 64,525,230 PPD
Milestone 3.2.6:Procurement and supplies staff database maintained
and updated by December, 2015
25,500,000
3,176,200 PPD
Milestone 3.2.7: National procurement policy draft finalized by
June, 2013
-
- PPD
Milestone 3.2.8: Stakeholders’ comments incorporated by June,
2013
-
- PPD
Milestone 3.2.9: PPDs’ office and staff capacity enhanced by June,
2013
100,000,000
89,702,700 PPD
Milestone 3.2.10: 20 members of PPD staff equipped with skills on
public policy formulation, implementation and evaluation by June,
2013
-
- PPD
Milestone3.2.11: National procurement policy developed and
shared by December, 2014
64,000,000
18,771,050 PPD
Milestone3.2.12: National procurement policy (NPP) strategy
developed and implemented by June 2015
104,000,000
- PPD
Milestone3.2.13: Printing and uploading the NPP on the website by
June, 2015
-
- PPD
72
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Milestone3.2.14: National procurement policy and procurement law
synchronised by June, 2015
-
- PPD
Milestone3.2.15: Monitoring the implementation of the National
procurement policy by June, 2015
-
- PPD
Milestone 3.2.16: Evaluation and feedback of the implementation of
the National procurement policy by June, 2016
-
- PPD
Milestone 3.2.17: 1000 Stakeholders acquainted with the National
procurement Policy by June, 2016
-
- PPD
544,500,000 197,886,980
Output 3.3:
Strengthened
capacity of
MDAs, RSs and
LGAs in Cash
management by
2015
Milestone 3.3.1: 600 staff of MDAs and LGAs Trained on cash
Management using standardized materials by June 30 2014(
Milestones to be reviewed and aligned after the East AFRITAC
recommendations on Cash and Banking Arrangement Mission)
233,000,000
199,183,303 ACGEN
Milestone 3.3.2: Six bank accounts operated by each LGAs by
December 2013
-
- ACGEN
233,000,000 199,183,303
Output 3.4:
Strengthened
public debt
Milestone 3.4.1: The agreed actions arising from the Feb. 2012
World Bank debt management report shared with key stakeholders
by July 31, 2012
-
- CPAD
73
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
management
capacity by
2015
Milestone 3.4.2: Debt management policy developed and shared by
June 2013
-
- CPAD
Milestone 3.4.3: Capacity of 50 Public Debt staffs enhanced by
June 2014
-
- CPAD
Milestone 3.4.4: Reviewed Government Loans, Guarantees and
Grants Act by June 2014
-
- CPAD
Milestone 3.4.5: Debt Management department established by
June 2016
-
- CPAD
Output 3.5
Improved
contents and
quality of
financial
statements
through
migrating from
IPSAS Cash
basis to IPSAS
Accrual basis by
June 2016
Milestone 3.5.1 Completed review of the IPSAS guideline issued
by PMORALG in 2008/09 to accommodate the recent IPSAS
updates by June 2013
-
- ACGEN
Milestone 3.5.2 Training to the MDAs, RSs and LGAs accounting
officers to develop awareness on IPSAS Accrual by 2013
103,205,000
39,920,000 ACGEN
Milestone 3.5.3 Capacity building to 250 staffs from MDAS and
RSs and Embassies to enhance skills in IPSAS accrual by 2014
153,000,000
152,973,050 ACGEN
Milestone 3.5.4 Public Finance Act No.2001 and Regulations
reviewed to address migration to IPSAS accrual by 2016
30,000,000
- ACGEN
Milestone:3.5.5 Consolidated template of financial statements to
include MDAs,Rs,LGAs, Controlled entities &GBEs developed by
2016
29,000,000
- ACGEN
Milestone 3.5.6: 250 government accountants in MDAs /LGAs
trained in IPSAS accrual and accrual modules for Epicor by
September 2013
ACGEN
74
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Milestone 3.5.7 Plan for migration towards IPSAS Accrual
accounting is completed by December 2013.
31,633,800
7,813,800 ACGEN
Milestone 3.5.8 Plan is approved for execution and stakeholder
information sessions have been completed by January 2014
70,900,000
65,800,000 ACGEN
Milestone 3.5.9 All legislative and policy supports decisions have
been identified by December 2014
54,000,000
14,000,000 ACGEN
Milestone 3.5.10 Milestones for the transition have been identified
and approved Eg Public Finance Act No.2001 and Regulations
amendments by October 2014
-
- PMORALG
Milestone 3.5.11 Plan to integrate all RSs and LGAs operations
into the centralized IPSAS accrual architecture is completed and
PMO RALG is fully engaged as a stakeholder by 31 December 2014
-
- ACGEN
471,738,800 280,506,850
Output 3.6:
Improved
accountability
in management
of Government
Assets for
supporting
migration to
IPSAS Accrual
Milestone 3.6.1. Uploading of 16 additional MDAs in EPICOR by
December 2012
66,000,000
58,292,500 DGAM
Milestone 3.6.2. Asset Management(tracking) Software
installed and operational by March 2013
122,000,000
- DGAM
Milestone 3.6.3. 40 staff(25 regional heads(RSVs) and 15 from
HQ) trained on asset management function by December 2013
130,000,000
44,296,796 DGAM
Milestone 3.6.4. Asset Management Policy prepared and
submitted by June 2015
165,700,000
- DGAM
Milestone 3.6.5. Valuation of Govermnet assets in 34 MDAs and Rs
completed by June 2016
944,872,000
- DGAM
75
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Milestone 3.6.6.Progress against target reported annually. - - DGAM
1,428,572,000 102,589,296
KRA 4: BUDGET CONTROL AND OVERSIGHT
Output 4.1:
Increased
coverage and
quality of the
internal audit
functions by
2016
Milestone 4.1.1: Operational plan developed and approved by
December, 2013
-
- IAG
Milestone 4.1.2: Internal audit manual, guidelines, standards and
quality assurance as per international standards in operation by
June, 2013
369,000,000
174,427,435 IAG
Milestone 4.1.3: Effective internal audit units and audit committees
established to all MDAs and LGAs by June, 2016
153,800,000
51,300,000 IAG
Milestone 4.1.4: The pilot stage of Computerised Audit will be
finalized by June, 2014.
319,000,000
33,000,000 IAG
4.1.5 Computerised Audit in place by June 2016. - - IAG
Milestone 4.1.6: 550 internal auditors trained in risk management
process and risk based audit by June, 20167
364,500,000
99,693,000 IAG
4.1.7 Technical Audits are conducted for 70 Projects by June, 2016 116,750,000 15,537,500 IAG
1,323,050,000 373,957,935
Output 4.2:
Strengthened
External audit
functions by
Milestone 4.2.1: The committee report on needs of legal
amendments (existing laws) to contribute towards reaching level 3
submitted to the attorney General and awareness programmes
conducted by December 2012
150,000,000
150,000,000 CAG
76
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
2016 Milestone 4.2.2. 50% of Auditors to be accommodated in NAO
own offices by 2014
5,700,000,000
5,700,000,000 CAG
Milestone 4.2.3 300 Auditors trained on Risk Based Audit and
200 in IT audit by 2014
306,190,000
306,190,000 CAG
Milestone 4.2.4 Two Value for Money audit reports to be produced
each year by NAO staff without technical assistance from external
consultant by 2014.
29,939,020
29,939,020 CAG
Milestone 4.2.5 300 Auditors trained on international standards of
auditing and full adoption of International Audit Standards by
2014
293,339,402
293,339,402 CAG
Milestone 4.2.6. Closing of books of accounts for Parastatals
harmonized and audit modalities agreed by 2014.
50,000,000
50,000,000 CAG
Milestone 4.2.7 Audit methodology in line with ISSAIs guidelines
adopted by June 2013
322,675,741
322,675,741 CAG
Milestone 4.2.8 Scoping study to ascertain the parameters of the
outstanding matters Database is completed by November 2012
150,000,000
150,000,000 CAG
Milestone 4.2.9 Establish a database that will separate findings
(monetary and non monetary) and recommendations including by
age, and record follow up actions by December 2013.
-
- CAG
Milestone 4.2.10: 200 Auditors trained on audit commanding
language (ACL) and other audit based software by 2014
-
- CAG
Milestone 4.2.11: NAO Headquarter is connected to 10 Regional
offices using WAN by 2014
183,190,000
183,190,000 CAG
77
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Milestone 4.2.12: Two of five TeamMate modules applied in
auditing by October 2014
-
- CAG
7,185,334,163 7,185,334,163
Output 4.3:
Improved
transparency on
audit reports
(central, local
and parastatal
levels) to
strengthen
scrutiny and
accountability.
Milestone 4.3.1 Citizen audit reports available for the 4 General
audit reports by June 2013
204,190,000
204,190,000 CAG
Sub Total 204,190,000 204,190,000
Output 4.4:
Improved
Performance of
Parastatals by
June 2016
Milestone 4.4.1: Ten (10) Parastatals signed Performance Contracts
with TR by June 2014
- TR
Milestone 4.4.2: Database on Parastatals set up and functioning by
December 2014
-
- TR
Milestone 4.4.3: Monitoring framework for Parastatals set up by
June 2014
-
- TR
Milestone 4.4.4:Mechanism for measuring Parastatals’ compliance
rate developed by June 2014
-
- TR
78
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Sub Total
-
-
Output 4.5:
Strengthened
Capacity of
oversight
functions of
Parliamentary
Accounts
Committees by
2016
Milestone 4.5.1 Capacity building interventions to PACs conducted
434,373,323
434,373,323 CAG
434,373,323 434,373,323
KRA 5: CHANGE MANAGEMENT AND PROGRAMME MANAGEMENT
Output 5.1:
Coordinate
Integration,
interfacing and
rationalization of
Government
Milestone 5.1.1 ICT mapping exercise showing location and
owners of all and peri-financial software commenced with
inception report published by December 2012.
210,686,755
130,698,189 DFMIS
Milestone 5.1.2 Stakeholder coordination meetings held to gather
input and agree on cross functional responsibilities for financial
systems Planning held on by December, 2012
4,000,000
3,959,344 DFMIS
79
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
financial systems. Milestone 5.1.3: Sequenced, prioritized and costed action plan to
bring all GoT financial and peri-financial software under one
common ICT architecture with supporting technical, infrastructure
and management structures completed and approved by the GoT
by June, 2013
5,000,000
2,835,476 DFMIS
Milestone 5.1.4: Integration/Interfacing plan is engaged and series
of planned actions are being executed and completed by October,
2015
-
- DFMIS
Milestone 5.1.5: IFMS infrastructure installed to new 34 LGAs,
RSs and PMORALG institutions and connected to central server at
Dodoma and MoF by June 2013
253,960,000
253,960,000 PMORALG
Milestone 5.1.6: MoF IFMS linked to PMO-RALG IFMS to the
immediate capture of the Approved Budget and all Exchequer
transfers to RSs and LGAs respectively by June 2013.
-
- PMORALG
Milestone 5.1.7 Completed capacity building to key users of
IFMS from all LGAs, RS and PMORALG institutions by June
2013.
82,821,000
82,821,000 PMORALG
Milestone 5.1.8 Audit of IFMIs in LGAs conducted by June 2017 - - PMORALG
556,467,755 474,274,009
Output 5.2:
Utilization of
EPICOR Modules
increased from
Milestone 5.2.1: EPICOR system upgrade completed by
December 2014
350,000,000
350,000,000 ACGEN
Milestone 5.2.2 ACGEN staff capacity enhanced by Dec 2014.
119,000,000
112,000,000 ACGEN
80
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
four two to six
modules
Milestone 5.2.3 Training for IFMS end users on the upgraded
modules conducted by December 2014
98,021,200
96,806,300 ACGEN
Milestone 5.2.4 EPICOR is able to provide real-time information
to all LGAs on flow of funds by July 2015
59,700,000
- ACGEN
626,721,200 558,806,300 -
Output 5.3: All
software
development and
module upgrades
are coordinated
with the
overarching plans
for ICT
integration.
Milestone 5.3.1: DFISM is operationalized and controls are put in
place to manage software acquisition and development by
December, 2012.
81,000,000
48,417,742 DFISM
Milestone 5.3.2: DFISM staff capacity enhanced by June, 2015.
149,063,245
134,610,812 DFISM
230,063,245 183,028,554
Output 5.4:
Improved
communication
and public access
to key fiscal
information to
stakeholders by
2016
Milestone 5.4.1: The Approved National Budget is published
on Ministry of Finance website by September each year
10,000,000 GCU
Milestone 5.4.2: Publish Citizens Budget by November each year. 100,000,000 GCU
Milestone 5.4.3:A Year-End Report (budget out turn) comparing
the actual budget execution to the enacted budget is published on
Ministry of Finance website by October each year
12,000,000 GCU
Milestone 5.4.4:MoF Communication Strategy developed and
implemented by June 2014
154,500,000
188,634,870 GCU
81
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Milestone 5.4.5: Fiscal Information and Budget Transparency
Publication Cycle developed and implemented by June 2014
72,000,000 GCU
Milestone 5.4.6: MoF website timely updated by June 2017
16,000,000 GCU
364,500,000 188,634,870
Output 5.5:
Coordination and
Standardization of
PFM Trainning
Achieved.
Milestone 5.5.1: Training mapping exercise completed by Dec
2012
107,000,000
72,100,000 DAHRM
Milestone 5.5.2: Capacity building Plan developed and result
measurement framework shared with key Stakeholders by June
2013
3,500,000
- DAHRM
Milestone 5.5.3: Two tracer studies conducted to measure impact
of training and documented by June 2014 and June 2016
-
- DAHRM
110,500,000 72,100,000
Output 5.6:
PFMRP
component
Managers are
being guided by
detailed multi-
year operating
plans.
Milestone 5.6.1: . All activities presented for inclusion in PFM RP
annual work plan are presented within the context of a detailed,
multi year operating plans by June 2013
61,000,000 54,089,000 DPD
61,000,000 54,089,000
82
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Output 5.7:PFM
activities are
effectively
planned and
implemented.
Milestone 5.7.1: Capacity building Plan developed and shared
with key Stakeholders by Dec. 31, 2012 - - DPD
Milestone 5.7.2: Training on Change Management and Strategic
Planning completed by Dec.31/13 230,372,060 230,372,260 DPD
Milestone 5.7.3: Results Based Management training has been
delivered to 60 PFM RP Component managers by June 30,2013 202,146,337 201,201,267 DPD
432,518,397 431,573,527
Output 5.8
Effective
coordination of
activities and
support provided
to the program
implementers
Milestone 5.8.1: Secretariat procurement process completed by
June 31/12 120,000,000 102,832,000 DPD
Milestone 5.8.2: Secretariat workplan is completed and approved
by JSC by December 2012 - - DPD
Milestone 5.8.3 PFMRP coordinate secretariat facilitated annually 494,545,000 277,390,672
DPD/ACGE
N
Improved Financial Management in LGA by June, 2015 491,380,000 334,981,974 ACGEN
Office Accomodation constructed/rehabilitated in all zones by june
2013 1,375,000,000 1,023,116,808 ACGEN
2,480,925,000 1,738,321,454
83
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Output 5.9 PFM
Program oversight
and review is
being guided by
clearly defined
Milestones
derived from an
agreed M&E
framework
Milestone 5.9.1: Annual review and amendment of the M&E
framework to ensure ongoing congruence and relevance annually
byNovember 2012.
50,000,000 - DPD
50,000,000 - DPD
Output 5.10 All
major PFM
reforms have
been coordinated
with and informed
by the relevant
government and
DP stakeholder
groups
Milestone 5.10.1: PFM information session completed to
disseminate results of: ICT mapping exercise, ICT Harmonization
Integration Plan
IAG action plan, AccGen’s Plan to transition to Accrual
Accounting conducted by March 31/13
130,000,000 - DPD
Milestone 5.10.2: IAG action plan, ACGEN's Plan to transition to
Accrual Accounting - -
IAG/ACGE
N
Milestone 5.10.2: Dec.31st each year Minimum of one PFM
reform information day conducted for CSOs , DPs and GoT during
Public Service day annually by Dec. 31st each year
94,000,000 59,073,370 DPD
224,000,000 59,073,370
84
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
Output
5.11:PFMRP
implemented
efficiently and
effectively
through result
based
management
approach.
Milestone 5.11.1: PFMRP im plemented according to annual
workplan and milestones are being met
96,000,000
96,000,000 DPD
Milestone 5.11.2: Annual supervision mission are conducted by
Sept 30 of each year commencing 2012. Independent program
evaluations are completed in 2014
74,000,000
74,000,000 DPD
Milestone 5.11.3: Independent program evaluations are completed
in 2014
95,000,000
50,000,000
Milestone 5.11.4: Dialogue structures are working as evidenced
by combined DP/GoT Survey results (Survey 1-March 2013,
Survey 2-March 2015 fr effective program implemetation
improved)
81,500,000
79,335,371 DPD
Milestone 5.11.5:Surveys to ensure that teams ( KRA Teams and
JSC members)nare actually working completed, March 2013,
March 2015 and results informed to JSC for action.
88,000,000
- DPD
434,500,000 299,335,371
Output 5.12:
National systems
and processes for
intergovernmental
transfers to LGAs
Streamlined and
Milestone 5.12.1: TORs completed by July 2012. 30,000,000 30,000,000 DPD
Milestone 5.12.2: Mapping commences September 2012. - - DPD
Milestone 5.12.3: Mapping commences September 2012. - - DPD
Milestone 5.12.3: Review and mapping of the systems and
processes for intergovernmental transfers initiated with inception
report finalised by October 2012
224,000,000
81,749,200 DPD
85
FUND USE BY MILESTONE FOR THE YEAR 2012/2013
PFM
OUTPUT MILESTONE
Amount in Tsh
RESP. RECEIVED
AMOUNT
ACTUAL
EXPENDIT
URE
rationalized Milestone 5.12.4: Comprehensive and sequenced action plan on a
recommendation of the mapping exercises on the
intergovernmental transfers finalized by June 2013.
-
- DPD
Milestone 5.12.5: Reports to be produced annually by end
September. DPD
254,000,000 111,749,200
Output 5.13
Strenthen Public
Financial
Management
Reforms in
Zanzibar by June
2016
Milestone 5.13.1 Milestones developed and agreed after
discussion with Zanzibar and thereafter decide on the support by
September 2012
-
-
Milestone 5.13.2 Zanzibar PFMRP Strategy Developed by June
2013
500,000,000
8,325,925
ACGEN-Z
/OCAG
500,000,000 8,325,925
24,129,665,331 17,706,569,360
86
Annex 3
ANNUAL PROCUREMENT PROGRESS REPORT
FOR THE PERIOD 2012/13
1 2 3 4 5 6 7 8 9
Procurement
Reference
No.
Tender No. Description Local (Tshs.) Foreign (Tshs) Total amount
(Tshs)
Contract
Price (Tshs)
Selection
Method
Implementation
status as on 30th
June, 2013
1.01 Development, installation and
operationzalize of a non taxed revenue
collection system -
58,000,000
58,000,000
IC Draft ToR done but
was postponed until
next FY
1.02 Undertake a study to identify major
revenue sources at LGAs -
150,000,000
150,000,000 N/A
QCBS Done internally
1.03 Undertake 10 PER thematic studies conducted
-
80,000,000
80,000,000
CQ Not initiated
1.04 AE/018/2012-
13/HQ/C/08
Revise Standard Bidding documents and
other Procurement Implementation tools in
line with PPA, 2011 -
36,350,000
36,350,000
58,550,000
IC Contract signed and
implementation on
progress
1.05 AE/018/2012-13/HQ/C/07
Carry out procurement audits to determine the level of compliance to the PPA -
934,750,000
934,750,000 Various
IC Contract signed and
implementation on
progress
1.06 AE/018/2012-
13/HQ/C/011
Survey and update database on average
prices of goods and services in collaboration with GPSA
-
55,900,000
55,900,000 40,500,000
IC Negotiation in
progress
1.07 Prepare JAST II and AMP user guidelines
and disseminate 115,000,000 -
115,000,000
ISS Not initiated
1.08 Conduct Training Needs Assessment for TRs -
142,800,000
142,800,000
QCBS Not initiated
1.09 ME/004/2012-
13/HQ/C/26
Conduct capacity and training needs
assessment for Procurement and Supplies Staff in the Government Sector
19,000,000
159,000,000
178,000,000 166,734,000
QCBS Contract signed and
implementation on
progress
1.10 Develop human resource structure for
procurement and supplies staff in the
public sector 8,000,000
65,000,000
73,000,000
To be
undertaken
internally
CQ
1.11 ME/004/2010-
11/HQ/C/15
Preparation of Public Procurement Policy 10,000,000
33,000,000
43,000,000 66,715,000
On-going On-going
87
1 2 3 4 5 6 7 8 9
Procurement
Reference
No.
Tender No. Description Local (Tshs.) Foreign (Tshs) Total amount
(Tshs)
Contract
Price (Tshs)
Selection
Method
Implementation
status as on 30th
June, 2013
1.12 Review public procurement systems -
20,000,000
20,000,000
IC Postponed until when the new PPA is out.
1.13 Provide Consultation and training on debt
management legal framework -
278,000,000
278,000,000
QCBS Not initiated
1.14 ME/004/2012-13/HQ/C/03
Development of Assets Management Policy 15,700,000
150,000,000
165,700,000 83,625,000
QCBS Contract signed
1.15 ME/004/2012-13/HQ/C/02
Valuation of Government assets 15,700,000
866,000,000
881,700,000
(i) 205,830,940,
(ii) 238,727,275
QCBS On-going
1.16 ME/004/2012-
13/HQ/C/14
Uploading 16 MDAs in EPICOR 16,000,000
50,000,000
66,000,000
SS Done internally
1.17 ME/004/2012-
13/C/19
Review and streamline Risk Management
process in PFA -
71,000,000
71,000,000
CQ Done internally
1.18 ME/004/2012-
13/HQ/C/11
Conduct mapping exercise on software and
hardware infrastructure 155,000,000
157,000,000
312,000,000 116,480,160
QCBS Assignment on
progress. Draft report
expected in July, 2013
1.19 ME/004/2012-13/HQ/C/23
Develop MoF communication strategy 200,000,000
66,000,000
266,000,000
266,000,000 QCBS On-going
1.20 Conduct TNA and mapping exercise for
PFM training 15,000,000
80,000,000
95,000,000
CQ Done internally
1.21 Conduct annual financial Audit -
45,000,000
45,000,000
CQ Done by NAO
1.22 Conduct annual procurement Audit -
50,000,000
50,000,000
CQ Not done
1.23 ME/004/2012-
13/HQ/C/21
Conduct Surveys to ensure the KRA
teams and JSC Members are actually working
-
88,000,000
88,000,000
CQ Not initiated
1.24 ME/004/2012-
13/HQ/C/07
Undertake study and review the system
and process of fund transfers to MDAs, RSs and LGAs
-
224,000,000
224,000,000 144,373,000
QCBS Assignment is in
progress. Draft report expected in July, 2013
1.25 ME/004/2012-
13/HQ/C/17
Train internal auditors on how to audit
development projects -
20,000,000
20,000,000 132,000,000
IC Contract signed
1.26 Facilitate 3 stakeholders workshop on the new TR draft Bill
-
15,000,000
15,000,000
IC Not initiated
1.27 Facilitate consultative meeting with key
stakeholders to identify legislative and
policy supports
-
14,000,000
14,000,000
IC Not initiated
88
1 2 3 4 5 6 7 8 9
Procurement
Reference
No.
Tender No. Description Local (Tshs.) Foreign (Tshs) Total amount
(Tshs)
Contract
Price (Tshs)
Selection
Method
Implementation
status as on 30th
June, 2013
1.28 Facilitate PFMRP Co-ordination Unit -
700,000,000
700,000,000
IC Public Service Recruitment
Secretariat
1.29 Improvement of Financial reports in
LGAs -
200,220,000
200,220,000
QCBS Done internally
1.30 Set out systems to ensure proper
management and control of revenue
collections and reporting in the LGAs -
169,000,000
169,000,000
QCBS Not initiated
1.31 Development of Debt Management Policy -
263,200,000
263,200,000
QCBS Not initiated
1.32 Engage a consultant for the development
and implementation of the plan (to move
from IPSAS Cash Basis to IPSAS Accrual) -
50,000,000
50,000,000
IC Not initiated
1.33 IE/031/2009-10/HQ/C/01
Build capacity on development of business operations and support for the Government
IFMS -
202,520,000
202,520,000
392,400,000
QCBS Contract signed
1.34 Train IFMS end users on the upgraded
modules -
94,000,000
94,000,000
SS Undertaken internally
1.35 Construction of two office buildings 400,000,000 -
400,000,000 400,000,000
On-going On-going
1.36
(IE/001/NAO/HQ/C/2012-13/12)
Train 200 auditors on Risk based audit
-
154,000,000
154,000,000 *
CQ Done through PPRA
1.37 Train 100 auditors on IT audit -
146,000,000
146,000,000 *
IC Done through PPRA
1.38 IE/001/NAO/HQ/C/2012/2013/22
Conduct special audit of National budget -
123,000,000
123,000,000 *
CQ Evaluation stage
1.39 Establish system (electronic database) for
tracking ongoing and outstanding audit recommendations
-
150,000,000
150,000,000
QCBS Not initiated
2.01 Servers and computer software -
69,000,000
69,000,000
NCB Not initiated
2.02 ME/022/2012/20
13/NC/11
Information technology and office
equipment -
175,000,000
175,000,000 78,956,000*
NCB Negotiation stage
89
1 2 3 4 5 6 7 8 9
Procurement
Reference
No.
Tender No. Description Local (Tshs.) Foreign (Tshs) Total amount
(Tshs)
Contract
Price (Tshs)
Selection
Method
Implementation
status as on 30th
June, 2013
2.03 Information technology and office equipment - Computers, printers and
scanners, Photocopiers; Filing Cabinets;
Air Conditioner
-
26,500,000
26,500,000
NCB Done
2.04 Furniture -
6,000,000
6,000,000
NS Done
2.05 Information technology and office
equipment - Computers and scanner -
19,500,000
19,500,000
GPSA Done
2.06 Scientific Equipment -
9,000,000
9,000,000
NS Done
2.07 Information technology and office equipment - Computers, photocopier
45,000,000 -
45,000,000
GPSA Done
2.08 Office equipment and furniture and air conditioners 6,500,000 -
6,500,000 *
GPSA Done
2.09 ME/004/2012-13/HQ/G/9
Motor vehicles -
100,000,000
100,000,000
NCB Not initiated
2.10 Motor vehicles -
100,000,000
100,000,000
NBC Not initiated
3.01 ME/004/2012-
13/HQ/G/08
Acquisition of software and installation of
Assets Management(tracking) software-
ASSET AUDITOR 4,000,000
118,000,000
122,000,000 62,919,450
NCB Done*
3.02 Update SBAS tool to enhance resource
allocation -
20,000,000
20,000,000
On-going Not initiated
3.03 Acquisition of audit software tools and
license fees -
140,000,000
140,000,000
NCB Tender processed but
was later nullified for re tendering
3.04 Installation and connection of gadgets for
Wide Area Net work to regional Offices -
177,000,000
177,000,000 177,000,000*
NCB Done
3.05 ME/022/2012/2013/NC/11
Install and service set up and connection of the system -
79,000,000
79,000,000
75,000,000* NCB
3.06 IE/031/2013-
13/HQ/C/28
Upgrading of Epicor from version 7.3.5 to
version 9.05 with three additional modules -
350,000,000
350,000,000 199,939,200
SS On-going
4.01 Refurbishment of Zonal offices in Arusha,
Iringa and Mwanza 100,000,000 -
100,000,000
NCB Not initiated
90
1 2 3 4 5 6 7 8 9
Procurement
Reference
No.
Tender No. Description Local (Tshs.) Foreign (Tshs) Total amount
(Tshs)
Contract
Price (Tshs)
Selection
Method
Implementation
status as on 30th
June, 2013
4.02 Construction of two office buildings
7,000,000,000 -
7,000,000,000 *
NCB On-going. Sumbawanga 50%,
Dodoma 80% of works
accomplished
4.03 Construction of office accommodation in
Dodoma Sub-Treasury
3,500,000,000 -
3,500,000,000 *
NCB 95% of construction
completed.
Construction of worth Tshs. 698,204,848
done.
1.40 Develop and implement Zanzibar PFMRP
Strategy -
500,000,000
500,000,000
QCBS ToRs development on
progress
17 ME/004/2012-
13/HQ/C/12
Audit Committee Guidelines for Audit in
Public Sector 199,000,000 199,000,000 90,819,936 Contract signed
18 ME/004/2012-
13/HQ/C/15
Training to Audit Committees' members of
institutions in public sector 0 112,572,000 Contract signed
19 ME/004/2012-
13/HQ/C/18
Training on risk based audit, governance
and control of Internal Auditors from
MDAs and LGAs 137,000,000 137,000,000 68,340,000
Contract signed
20 ME/004/2012-
13/HQ/C/20
Training on risk management to head of
Departments and members of audit
committees of MDAs and LGAs 106,000,000 106,000,000
27,390,000
Contract signed
21 ME/004/2012-13/HQ/C/`16
To acquire and train internal auditors and the usage of Audit Software tools 319,000,000 319,000,000 140,000,000
Contract signed
21 ME/004/2012-13/HQ/C/14
To train internal auditors and the usage of Audit Software tools
69,000,000 69,000,000 50,634980 Contract signed