Final Simulation

27
Presented to

Transcript of Final Simulation

Page 1: Final Simulation

Presented to

Page 2: Final Simulation

Meet Our Team

Sharan Nav Tobias Tom Adam

Page 3: Final Simulation

Our Mandate

Review the project

Be positive in our attitude

Not looking to blame

Page 4: Final Simulation

The Project

SFU IT Project Review

AJ

Page 5: Final Simulation

Our Approach

02

Created Analysis

04

Just For You

01

Talked with Team Members

03

Spoke with External Vendors

AJ

Page 6: Final Simulation

Our Process

Broke Down Issues

We refined and consolidatedissues into categories

We ranked and ratedissues by severity

Identified key areas forimprovement on theseissues

> Tom

Page 7: Final Simulation

7 Key Problem Areas

Risk Assessment

Schedule

Cost

Resource Volatility and Allocation

Project Documentation

Collaboration and Interaction

Quality Management

Page 8: Final Simulation

Resource Volatility

• 4 Team Members Resigned or Retired

• Vendor Turn Over

• Lack of Engagement and Commitment

Page 9: Final Simulation

Resource Allocation

• Staff Underutilized

• Lack of Stakeholder Buy-in

TB

Page 10: Final Simulation

Project Documentation

• Documentation was not updated

• No Project Status

• Change Orders Not Approved Properly

Page 11: Final Simulation

Collaboration and Interaction

• DAPM in Toronto

• Collaboration with DAPM not Adequate

• SFU Failed to Provide Feedback

Page 12: Final Simulation

Additional Integration Necessary

Software Didn’t Meet Specifications In the End

Multiple Interfaces

Contact Updates to DAPM Software

No Testing Until the End

Quality ManagementNAV

Page 13: Final Simulation

No Documentation

Update at All 03

Risk Cycle

DAPM Purchased 01

Tool Change Necessary 02 2 Year Overrun 04

Page 14: Final Simulation

Schedule

No Task AllocationWork Plan Had Old Dates

No BaselineNo Resource Loading

Page 15: Final Simulation

Cost

• No Accountability

• Changed Not Properly Approved

• Many Billable Items Not Authorized

• No Work Plan Update = No Budget

• SFU Didn’t Claim Discount

SH

Page 16: Final Simulation

Recommendations

Page 17: Final Simulation

Resource Volatility Solution

• Implement Incentive based employment

• Better Identify Project Risks

• Succession Plans

• Team Building

Page 18: Final Simulation

Resource Allocation Recommendation

• Assign More Resources• Break Work Down Further• Require Resource Feedback• End-User on Project Steering

Committee

AJ

Page 19: Final Simulation

Project Documentation Recommendation

• Update Documentation within 48 Hours

• Central Repository for Documents

Page 20: Final Simulation

Collaboration and Interaction Recommendation

• Define Roles and Responsibilities• Define Communications Plan• Daily Meetings• Vendors on Site Once Per Month• Prefer Local Vendors

TO

Page 21: Final Simulation

Quality Recommendations

End-User Testing Before Completion

Engaged Project Sponsor

Engaged PM Who Developed Acceptance Criteria

Test Fully

Hire 3rd Party Tester

Assign Dedicated Testing Team

NAV

Page 22: Final Simulation

01 L

orem 02

Lorem

03 Lorem

Keep Vendors Accountable

Create and Update a Risk Management Plan

Stay True to Original Scope

Don’t be Afraid to Start Over

Risk Management Recommendation

Page 23: Final Simulation

Schedule

Use Online Tools

Use Timesheet Approval

Create, Enforce and Adjust the Schedule

Assign Responsibility

Have regular status meetings!

TB

Page 24: Final Simulation

Cost Recommendations

Have Legal Review Projects

Re-Review Contracts and Suggest Updates to Terms

Produce Cost Reports

Establish Cost Approval Policy

Finance to Review Bills with PM Staff

Reject Unauthorized Billing

Implement Checklists for Next Time

AJ

Page 25: Final Simulation

Starting Over

Financial Controls

Vendors

People

Schedule

Review

Page 26: Final Simulation

Wrap Up

Project Ran 2 Years Over Schedule

Little Effective Management

People Left the Project

Page 27: Final Simulation

All in a day’s workQuestions?

Thanks