Transcript of Final Simulation
Presented to
Meet Our Team
Sharan Nav Tobias Tom Adam
Our Mandate
Review the project
Be positive in our attitude
Not looking to blame
The Project
SFU IT Project Review
AJ
Our Approach
02
Created Analysis
04
Just For You
01
Talked with Team Members
03
Spoke with External Vendors
AJ
Our Process
Broke Down Issues
We refined and consolidatedissues into categories
We ranked and ratedissues by severity
Identified key areas forimprovement on theseissues
> Tom
7 Key Problem Areas
Risk Assessment
Schedule
Cost
Resource Volatility and Allocation
Project Documentation
Collaboration and Interaction
Quality Management

Resource Volatility
• 4 Team Members Resigned or Retired
• Vendor Turn Over
• Lack of Engagement and Commitment

Resource Allocation
• Staff Underutilized
• Lack of Stakeholder Buy-in
TB
Project Documentation
• Documentation was not updated
• No Project Status
• Change Orders Not Approved Properly
Collaboration and Interaction
• DAPM in Toronto
• Collaboration with DAPM not Adequate
• SFU Failed to Provide Feedback
Additional Integration Necessary
Software Didn’t Meet Specifications In the End
Multiple Interfaces
Contact Updates to DAPM Software
No Testing Until the End
Quality ManagementNAV
No Documentation
Update at All 03
Risk Cycle
DAPM Purchased 01
Tool Change Necessary 02 2 Year Overrun 04
Schedule
No Task AllocationWork Plan Had Old Dates
No BaselineNo Resource Loading
Cost
• No Accountability
• Changed Not Properly Approved
• Many Billable Items Not Authorized
• No Work Plan Update = No Budget
• SFU Didn’t Claim Discount
SH

Recommendations

Resource Volatility Solution
• Implement Incentive based employment
• Better Identify Project Risks
• Succession Plans
• Team Building

Resource Allocation Recommendation
• Assign More Resources• Break Work Down Further• Require Resource Feedback• End-User on Project Steering
Committee
AJ
Project Documentation Recommendation
• Update Documentation within 48 Hours
• Central Repository for Documents
Collaboration and Interaction Recommendation
• Define Roles and Responsibilities• Define Communications Plan• Daily Meetings• Vendors on Site Once Per Month• Prefer Local Vendors
TO
Quality Recommendations
End-User Testing Before Completion
Engaged Project Sponsor
Engaged PM Who Developed Acceptance Criteria
Test Fully
Hire 3rd Party Tester
Assign Dedicated Testing Team
NAV
01 L
orem 02
Lorem
03 Lorem
Keep Vendors Accountable
Create and Update a Risk Management Plan
Stay True to Original Scope
Don’t be Afraid to Start Over
Risk Management Recommendation
Schedule
Use Online Tools
Use Timesheet Approval
Create, Enforce and Adjust the Schedule
Assign Responsibility
Have regular status meetings!
TB
Cost Recommendations
Have Legal Review Projects
Re-Review Contracts and Suggest Updates to Terms
Produce Cost Reports
Establish Cost Approval Policy
Finance to Review Bills with PM Staff
Reject Unauthorized Billing
Implement Checklists for Next Time
AJ
Starting Over
Financial Controls
Vendors
People
Schedule
Review
Wrap Up
Project Ran 2 Years Over Schedule
Little Effective Management
People Left the Project
All in a day’s workQuestions?