FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT
Transcript of FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT
![Page 1: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/1.jpg)
FINAL PROJECT
PRELIMINARY DESIGN OF CHEMICAL PLANT
THE PRODUCTION OF LINEAR ALKYLBENZENE
FROM 1-DODECENE AND BENZENE
WITH CAPACITY 20,000 TONS PER YEAR
By
Mr.Mollakarn Kaewsareh
D 500 102 005
Supervisor
Dr.Ahmad M. fuadi
M. Mujiburohman, Ph.D.
Chemical Engineering Department
Universitas Muhammadiyah Surakarta
2015
![Page 2: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/2.jpg)
![Page 3: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/3.jpg)
TESTIMONY
I hereby asset that there is no plagiarism in this project paper, there is no
other work that has been submitted to obtain the bachelor degree and as far as I
am concerned there is no opinion that has been written or published before, except
the written references with referred in this paper and mentioned in the
bibliography.
If any incorrectness is proved in future dealing with my statement above, I
will be responsible.
Surakarta , January 2015
Mollakarn Kaewsareh
![Page 4: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/4.jpg)
iii
ABSTRACT
Linear alkyl benzene industry produces linear alkyl benzene from raw
material of 1-dodecene and benzene with production capacity 20,000 tons per
year. The industry is planned to be established at industrial estate in Cilegon,
Banten, East Jawa with land area of 10000 m2. The production process of linear
alkyl benzene is Detal process by using fixed bed reactor with solid acid catalyst.
The reaction condition is liquid-liquid phase at 80-193˚C temperature, 5 atm
pressure and mol ratio benzene to 1-dodecene is 2:1, the reaction is irreversible
and exothermal. All of materials do not cause any corrosive. Considering by the
reaction conditions the linear alkyl benzene industry is low risk chemical industry.
The linear alkyl benzene production produces 2,560 kilograms product per
hour. The raw materials needed are benzene 1,568 kilogram per hour and 1-
dodecene 1,689 kilograms per hour. To support the process, the linear alkyl
benzene production requires cooling water 39,709 kilograms per hour and steam
725 kilograms per hour, the water is obtained from seawater. The linear alkyl
benzene production requires fuel oil to generate steam and the diesel fuel uses 166
liters per day. The electricity required for all purposes in the industry is 743
kilowatt which is obtained from the state electricity company (PLN). Incase the
electricity is runs out, the electric generator is prepared for 4 days per month with
diesel fuel requirement 75 liters per hour.
The linear alkyl benzene is considered to operate for 330 days per year with
161 employees. The economic analysis result are as follows, the profit before tax
is IDR 35,872,735,199.40 per year and the profit after tax 30% is
IDR 25,110,914,639.58 per year. The return of investment before tax if 49.89%
and the return of investment after tax is 34.92% .The standard return of
investment before tax is between 40% to 60%. The payout time before tax is 1.670
years while the payout time after tax is 2.226 years, payout time before tax is
allowable for maximum 5 years with breakeven point is 48.20% while breakeven
point is expected between 40% -60% for standard chemical industry. Discounted
![Page 5: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/5.jpg)
iv
cash flow is 43.86%. Discount cash flow is allowable when it’s more than 15%
(bank credit interest). From the economic anlysis results above it can be
concluded that the establishment of the linear alkyl benzene industry is feasible.
Key words: Linear alkyl benzene , 1-dodecene , benzene , fixed bed reactor.
![Page 6: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/6.jpg)
v
PREFACE
Alhamdulillah, all praise and Thanksgiving that are uncountable I dedicate
to Allah SWT who has been giving mercy and extraordinary power so that I can
go through a period of the heavy long, tiring in the process of finishing the final
project. I always remember verse of the Qur'an, which inspire me in through all of
this namely "in difficulties there must be a easiness." Cheer and peace and not to
forget to say thank to the our Prophet Muhammad SAW that has brought us from
the Jahilliyah age to the best present age. The project was not free from direction
assistance and guidance from various people. For that, I thank greatness to
1. Rois Fatoni ST., MSc., PhD. As head of chemical engineering department,
University Muhammadiyah of Surakarta.
2. Dr.Ahmad M. Faudi and M. Mujiburohman, Ph.D. As supervisors I & II.
3. All of chemical engineering department lecturers and officers.
4. My family and friends.
Thanks ,January 2015
Mollakarn Kaewsareh
![Page 7: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/7.jpg)
vi
Contents
Chapter page
Title page…………………………………………………………..…. i
Authentication sheet…………………………………………………… ii
Abstract……………………………………………………………..… iii
Prefect………………………………………………………………… v
Contents…………………………………………………………….… vi
Figure contents………………………………………………………… viii
Table contents………………………………………………………… ix
Chapter I Introduction
1.1. Back ground…………………………………………… 1
1.2. Production capacity…………………………………..... 1
1.3. Plant location………………………………………….. 3
1.4. Literature review……………………………………… 3
Chapter II Process description
2.1. Specification of raw materials and product………….. 9
2.2. Process concept…….…………………………………. 11
2.3. Process flow diagram…………………………………. 13
2.4. Mass balances and heat balances…...………………… 15
2.5. Plant location and lay out……………………………... 19
Chapter III Inventory specifications
3.1. Accumulator………………………………………….. 22
3.2. Heat exchanger……………………………………….. 23
3.3. Pumps……...…………………………………………. 28
3.4. Reactor………………………………………………... 38
![Page 8: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/8.jpg)
vii
3.5. Separator………………………………………………. 39
3.6. Storage tank…..……………………………………....... 40
Chapter IV Supporting unit process (utility) and laboratory
4.1. Supporting unit process.…………………………….… 45
4.2. Laboratory…………………………………………..… 50
Chapter V Company management
5.1. Company entity….……………………………………. 53
5.2 Organization structure……………………………….… 54
5.3 Duties and authorities………………………………..… 56
5.4 The division of employee working hours……………… 62
5.5 Classification of position and Number of employees…. 65
5.6 Employee welfare and facilities……………………..… 69
Chapter VI Economic analysis
6.1 Cost factor specification..……………………………… 70
6.2 Cost estimation ………………….…………………….. 71
6.3 Total investment cost…………………………………… 72
6.4 Production cost………………………………………… 74
6.5 Economic estimation…………………………………… 75
Conclusion……………………………………………………………. 80
References…………………………………………………………..… xi
Attachments……………………………………………………………. xiii
![Page 9: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/9.jpg)
viii
Figure contents
Figure page
Figure 2.1 : Qualitative flow diagram …………………………….... 13
Figure 2.2 : Quantitative flow diagram ……………………………... 14
Figure 2.3 : Mass flow diagram…………………………………….… 14
Figure 2.4 : Building lay out ………………………………………… 22
Figure 4.1 : Demineralization Plant ……………………………….… 47
Figure 4.2 : Water treatment process diagram…………………….…. 52
Figure 5.1 : Chart of company organization …………………………. 68
Figure 6.1 : Graphic for CEPCI since 1990 until 2016………………. 72
Figure 6.2 : Graphic of economic analysis…...………………………. 79
![Page 10: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/10.jpg)
ix
Table contents
table page
Table 1.1 : Linear alkylbenzene needs in Indonesia
based on the import data ……………………………...… 2
Table 1.2 : LAB plants capacity that has been established …………. 2
Table 2.1 : Standard conditions ΔH f298 (kJ/mol) and
ΔG f298 (kJ/mol) of each component …………………... 11
Table 2.2 : Stream component…………………………………….… 15
Table 2.3 : Total mass balance ……..……………………………….. 15
Table 2.4 : Total Mass balance around reactor (R-01) …………….. 16
Table 2.5 : Total Mass balance around flash drum (FD-01) ……….. 16
Table 2.6 : Heat transfer around heater-01 (HE-01) …………….... 16
Table 2.7 : Heat transfer around heater-02 (HE-02) …………….... 17
Table 2.8 : Heat transfer around reactor (R-01) ……………........... 17
Table 2.9 : Heat transfer around flash drum-01 (FD-01) ………….... 18
Table 2.10 : Heat transfer around cooler-01 (Cl-01) ……………....... 18
Table 2.11 : Heat transfer around condenser-01 (Cd-01) ………....... 19
Table 2.12 : Heat transfer around cooler-02 (Cl-02) ……………....... 19
Table 2.13 : The details of building …………………………………. 21
Table 2.14 : Location description …………………………………. 22
Table 5.1 : Shift schedule ………………………………………... 64
![Page 11: FINAL PROJECT PRELIMINARY DESIGN OF CHEMICAL PLANT](https://reader030.fdocuments.in/reader030/viewer/2022012805/61bd343661276e740b106051/html5/thumbnails/11.jpg)
x
Table 5.2 : Classification of employee’s position …………………... 65
Table 5.3 : The number of employees…...…………………………... 67
Table 5.4 : Employee welfare and facilities ….……………………... 69
Table 6.1 : Total fixed capital investment ….……………………... 73
Table 6.2 : Manufacturing cost ……………..……………………... 74
Table 6.3 : Working capital ….……………………………………... 75
Table 6.4 : General expenses ….…………………………………….75
Table 6.5 : Total production cost ….……………………………….. 75
Table 6.6 : Total fixed manufacturing cost ….……………………... 77
Table 6.7 : Total variabel cost ….………………………………….. 77
Table 6.8 : Total regulated cost ….……………………………….... 77
Table 6.9 : The conclusion of economic estimation……………….. 79