Final Coursework
-
Upload
luiza-nunes -
Category
Documents
-
view
219 -
download
0
Transcript of Final Coursework
-
8/12/2019 Final Coursework
1/35
Design of a Wastewater Treatment
Plant in Leeds, UKProfessor: Dr. C. Tizaoui
EG-M09/EGA327
Water and Wastewater Engineering
Group D:
Frederico Halfeld Clark Gomes, 744484Luiza Pessoa Moreira, 744482Luiza Nunes Rocha, 744499Pedro Henrique Guerra Alves, 744486Thales Said Orichio, 744488
College of EngineeringSwansea University
SwanseaWales, UK
-
8/12/2019 Final Coursework
2/35
Contents
1. Introduction ..................................................................................................................... 4
2. Population ....................................................................................................................... 4
3. Flow rates Calculations ................................................................................................... 4
4. Domestic Wastewater ..................................................................................................... 5
4.1. Domestic Wastewater Characterization ...................................................................... 5
4.2. Designed Plant and Flow sheet ................................................................................... 6
4.2.1. Aerobic BioOxidation reactor ................................................................................. 8
4.2.1.1. Substrate (Dsticwaste) degradation...................................................................... 8
4.2.1.2. Nitrification .......................................................................................................... 8
4.2.1.3. Biomass decay ..................................................................................................... 8
4.2.2. Clarifier .................................................................................................................... 9
4.2.3. Granular media filter ............................................................................................... 9
4.2.4. Flow Splitting ........................................................................................................ 10
4.2.5. Belt Filter ............................................................................................................... 10
4.2.6. Sludge Drying ........................................................................................................ 10
4.2.7. Mixing unit ............................................................................................................ 11
5. Industrial Wastewater Treatment .................................................................................. 11
5.1. Industrial Wastewater Characterization .................................................................... 11
5.2. Designed Plant and Flow sheet ................................................................................. 12
5.2.1. Mixing Unit ........................................................................................................... 14
5.2.2. Aerobic BioOxidation reactors .............................................................................. 14
5.2.2.1. Glucose degradation........................................................................................... 14
5.2.2.2. Phenol degradation............................................................................................. 15
5.2.2.3. Biomass decay ................................................................................................... 15
5.2.3. Clarifier .................................................................................................................. 15
5.2.4. Granular media filter ............................................................................................. 15
5.2.5. Flow Splitting ........................................................................................................ 16
5.2.6. Belt Filter ............................................................................................................... 16
5.2.7. Sludge Drying ........................................................................................................ 16
6. Economic Evaluation .................................................................................................... 16
6.1. Domestic Wastewater Treatment Plant ..................................................................... 16
6.2. Industrial Wastewater Treatment Plant ..................................................................... 18
7. Environmental Impact Analysis .................................................................................... 20
7.1. Domestic WWT Plant Analysis ................................................................................ 20
7.2. Industrial WWT Plant Analysis ................................................................................ 207.3. Final Effluent Characteristics .................................................................................... 21
-
8/12/2019 Final Coursework
3/35
8. Alternatives for Sludge Disposal .................................................................................. 22
9. Conclusion .................................................................................................................... 23
10. References ................................................................................................................. 23
Appendix AUnits Mass Balances and Streams Composition .......................................... 25
Appendix B
Meetings Minutes ......................................................................................... 35
-
8/12/2019 Final Coursework
4/35
1. Introduction
This project aimed to design a new municipal wastewater treatment plant
using SuperPro Designer package for the city council of Leeds. The purpose of it isto replace the old WWT plant,which was not capable to achieve compliance withdischarge standards. The WWTP was designed to serve a current population of50,000 people and that after 50 years. The effluent to be treated is composed by adomestic wastewater stream and an industrial stream from a textile industry.
Leeds is a city situated in the West Riding, in the middle of the UnitedKingdom. It is a huge manufacturing centre for clothing, with many wool industries inparticular [1].
2. Population
It is known that population statistics are widely used to shape and planservices across the cities. Hence, understanding how the population is growing andchanging is critical for the effective planning of a Wastewater Treatment Plant.Analyses were made through the results of the Census conducted in Leeds andshowed that the population has increased by 5.1% from 2001 to 2011 [2]. This ratewas used in the calculation of population projections, thus considering that in everyten years the population would increase by 5,1%, in 50 years it would grow by(5,1%)5. The results are shown below:
Figure 1: Population Projections
By the end of 2063, the population would be 64119 but in order to make thecalculations easier, it was assumed a value of 65000 citizens for this year.
3. Flow rates Calculations
It is known that in the UK the current volume of water consumption is around
150 L/capita.day [3]. Using this value it was possible to calculate the flow rate, inlitters per day, defined by:
45000
50000
55000
60000
65000
70000
2013 2023 2033 2043 2053 2063
Population
Year
Population Projections
-
8/12/2019 Final Coursework
5/35
(Equation 1)
WhereQ = flow rate (L/day);
V = volume (L/capita.day);P = population.
The value was obtained in L/day. In order to obtain the flow rate in litters perhour, it was divided by 24. So, the flow rate was found in litters per hour. With thisvalue and the concentration of each component of the wastewater it was possible tocalculate the flow rate of all of it.
(Equation 2)Where
Q= flow rate of each component(kg/h);
C = concentration of each component (kg/L);
In order to determinate the quantity of water present in the effluent, thedifference between the total flow rate and the sum of all components flow rateswould be the amount of water input.
All of these calculations were used for the design of both, the domestic andindustrial wastewater plant.
4. Domestic Wastewater
4.1.Domestic Wastewater Characterization
Initially, the flow rate found for domestic wastewater was 406250 L/h. Usingthis value and the Equation 2, the values below were found.
Table 1: Components Information
ComponentConcentration
(mg/L)Flow rate
(kg/h)
Dsticwaste 250 101.5625
A_VSS 70 28.4375I_VSS 35 14.21875
N_VSS 6.2 2.51875
NonBio_SS 78 31.6875
NonBio_TDS 250 101.5625
NO2_NO3 2.5 1.015625
Ammonia 19 7.71875
Carbon dioxide 30 12.1875
-
8/12/2019 Final Coursework
6/35
The flow rate of the water was obtained as described before and it was foundto be 388103 kg/L. At this point, it was necessary to characterize each constituent foruse the SuperPro Designer software. All the componentsproperties were providedin the coursework paper task.
Table 2: Components Environmental Properties
Property\Component Dsticwaste A_VSS
biomass
I_VSS
biomass
N_VSS
biomass
NonBio_SS NonBio_TDS NO2_NO3
COD (g O2/g) 1.80 1.36 1.45 1.38 0.00 0.00 0.00
ThOD (g O2/g) 1.80 1.36 1.45 1.38 0.00 0.00 0.00
BODu/COD (g/g) 1.00 0.85 0.83 0.80 0.00 0.00 0.00
BOD5/BODu (g/g) 0.68 0.68 0.68 0.68 0.00 0.00 0.00
TOC (g C /g) 0.60 0.50 0.50 0.50 0.00 0.00 0.00
TP (g P /g) 0.00 0.05 0.05 0.05 0.00 0.00 0.00
TKN (g N /g) 0.07 0.12 0.12 0.12 0.00 0.00 0.00
NH3-N (g N /g) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
NO3-N (g N /g) 0.00 0.00 0.00 0.00 0.00 0.00 0.23
Kmaxo(mg substr/gbiomass.h)
76 0.00 0.00 0.00 0.00 0.00 0.00
Ks (mg/L) 0.4170 0.00 0.00 0.00 0.00 0.00 0.00
CaCO3 (g/g) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TS (g solids/g) 0.00 1.00 1.00 1.00 1.00 1.00 1.00
TSS/TS (g/g) 0.00 1.00 1.00 1.00 1.00 0.00 0.00
VSS/TSS (g/g) 0.00 0.90 0.90 0.90 0.00 0.00 0.00
DVSS/VSS (g/g) 0.00 0.80 0.80 0.80 0.00 0.00 0.00
VDS/TDS (g/g) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
DVDS/VDS (g/g) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
In the interest of achieving the UK wastewater discharge standards thefollowing unit operations were chosen to constitute the process.
4.2.Designed Plant and Flow sheet
The flow sheet of the domestic wastewater treatment plant is presented in.The unitsspecifications, dimensions and input and output streams are described inthe sub items as follow.
-
8/12/2019 Final Coursework
7/35
Figure 2 : Domestic WWT Plant Flowsheet
-
8/12/2019 Final Coursework
8/35
4.2.1.Aerobic BioOxidation reactor
It was needed to operate with two aeration biooxidation reactors in parallel.These bioreactors were used in order to digest the domestic waste, transforming theorganic matter and other compounds in a well-mixed basin under aerobic conditions.
In favour of the use of this process its necessary to define the reactions that willoccur in the reactor. Besides that, the kinetic constant and the stoichiometry also hadto be predetermined. The reactions are described below.
4.2.1.1. Substrate (Dsticwaste) degradation
gggggg
COOHVSSAONHDsticwaste
9.0
2
8.0
2
8.04.1
2
1.0
3
1
_
k = 2.4 mg BOD5/(mg vss.d). The above rate constant is assumed to apply for T =
20
o
C. The impact of temperature variations is accounted for by assuming a thetavalue of 1.08.
Ks = 8.1 mg BOD5/L
It was necessary to convert the kinetic constants from milligrams of BOD5 perlitter to milligrams of domestic waste (Dsticwaste) per litter. To accomplish this stepthe information in Table 2 were used.
4.2.1.2. Nitrification
gggggg
NONOOHVSSNCOONH2.257.7
2
0.18.1
2
6.24
2
5.7
3_2_3
k = 0.95 mg NH3-N/(mg N_VSS.d)
The above rate constant is assumed to apply for T = 20 oC. The impact oftemperature variations is accounted for by assuming a theta value of 1.023.
Ks = 1.5 mg NH3/L
4.2.1.3. Biomass decay
Reaction 1:
ggggggg
CONHOHSSNonBioVSSIOVSSA
45.1
2
1.035.0
2
1.02.015.1
2
05.1
3___
Reaction 2:
ggggggg
CONHOHSSNonBioVSSIOVSSN
45.1
2
1.035.0
2
1.02.015.1
2
05.1
3___
kd = 0.00325 1/h
-
8/12/2019 Final Coursework
9/35
The above rate constant is assumed to apply for T = 20 oC. The impact oftemperature variations is accounted by assuming a theta value of 1.089.
Both reactors have the same dimensions. The tank depth was 3.50 m, thelength of the tank was 56.07, and width was 22.43 m. The Hydraulic Residence Timeof determined as 18 h, and the dissolved oxygen was 2 mg/L, for one and the other.
On the first reactor there are four streams the S-126 is the one that feedsthe reactor. The S-108 is the input of air into the unit process. Those are the inputstreams. The output streams are the S-104, which is the nitrogen emission stream,and the S-127 that is the stream that carries on the effluent further to complete thetreatment (main branch). The second reactor follows the same standard of the firstone. Although the feed input is the S-125, the air input is the S-119. The nitrogenemission output is the S-124 and the last one is the S-128.In both reactors all thereactions above happened with the extend achieved present in the table below:
Table 3: Reactions efficiency
Reaction Extend Achieved
Biomass Decay 1 100%
Biomass Decay 2 7%
Nitrification 100%
DsticwasteDegradation
100%
4.2.2.Clarifier
This unit operation was used to remove solid particulates from liquids. The
outputs are clarified water and sludge. It was use two clarifier, one before the aerobicBioOxidation reactor and another after the reactor. The first one has the followingdimensions, a surface area of 306.24 m2, a tank depth of 3.00 m, the tank diameteris 19.75, and a volume of 918,711.48 L. This clarifier removed 10% of A_VSSbiomass, I_VSS biomass, N_VSS biomass and had a removal efficiency of 70% ofNonBio SS. The particles in sludge were 10 g/L. The stream Input feed this unitand there are three output streams accomplishing it. The stream S-102 is theoutput for emissions but for this unit none of the components were chosen to beemitted. The S-101 is the main line and the S-106is the sludge stream.
Beyond the point of the second clarifier the influent was divided in two parts,one was directed to recycling while the other was sent to a granular media filter. Thesurface area of the second clarifier is 372 m2, the tank depth is 3.00 m and the tankdiameter is 21.79m. The volume of tank is 1,118,984.57 L. The A_VSS biomass,I_VSS biomass, N_VSS biomass and NonBio SS had 90% of removal efficiency.Additionally, the particles in sludge were 10 g/L. The input of this unit is the streamS-103 and the outputs are the S-110 which represents an emission that followsthe same as S-102, the S-112 that is the main line and the Sludge stream.
4.2.3. Granular media filter
Granular media filter removes additional suspended solids and oils. It is also a
polishing step that lowers the levels of suspended solids and associatedcontaminants in treated wastes. The removal of particles takes place either on the
-
8/12/2019 Final Coursework
10/35
surface of the media (cake filtration) or throughout the depth of the media (depthfiltration). In the granular media filtration process, particles typically adsorb or attachto the grains of sand or anthracite in the filter [4].The bed depth is 2.13 m and thebed diameter is 1.50 m. As the volume that we are working with is huge, it would beneeded six units of granular media filters with the dimensions mentioned above. The
A_VSS biomass, N_VSS biomass and NonBio SS had 90% of removaleffectiveness. There are two input streams which are the S-112 carrying the feedand the S-116 that adds water to the process. The S-105 is the backwash flowthat contains A_VSS biomass, N_VSS biomass and NonBio SS, and the otherstream is the output of the domestic WWTP.
4.2.4.Flow Splitting
A procedure was used to split two bulk flow streams. It was used two flowssplitting. The first one was used to split the stream S-115, which comes out of thefirst clarifier, into the streams S-125 and the S-126. Those two streams are theones who feed both reactors. The S-115 was split in half. The second flow splittingwas used to separate the sludge stream that comes out of the second clarifier intothe S-114 and the sludge recycle stream. The flow was split in 25% to the topstream and the remaining to the down stream. The top stream, which is the sludgerecycle one, feed a mixer that sends this flow to the aerobic biooxidation reactor. TheS-114 stream was also linked to a mixer that later on would feed the Belt filtrationprocess.
4.2.5.Belt Filter
A Belt Filter Press is a sludge dewatering device that applies mechanicalpressure to a chemically conditioned slurry, which is sandwiched between twotensioned belts, by passing it through a serpentine of decreasing diameter rolls. Thematerial balances are based on the removal percentage of particulate componentsand the solids content of the cake. The belt width is 0.49 m. The A_VSS biomass,I_VSS biomass, N_VSS biomass and NonBio SS had 90% of removal efficiency.The specific sludge rate was 300 (kg/h)/m and the solids recovery were 90%. Also,the solids presents in the cake were 15 wt/wt cake. The sludge treatment line is thefeed stream of influent and the S-111 is the input of water.There are two outputstreams: the S-113 which takes the filtrate to the biooxidation reactor and the S-120 which carries the sludge to the sludge drying.
4.2.6.Sludge Drying
Sludge drying procedures are based on contact, convection or radiationprocesses. Large amounts of air are not necessary during the contact drying,because the warmth is supplied by the contact between the damp product and aheated wall. Only a minimum gas flow is often planned for the evacuation of steam[5].The evaporative capacity of the sludge drying is 531.92kg/h. The solids presentin dried sludge were 35%. The input of sludge is the S-120, while the S-121is theair input. The S-122 is the output for nitrogen, I_VSS biomass and oxygen whilst
the other output stream is the dried sludge.
-
8/12/2019 Final Coursework
11/35
4.2.7.Mixing unit
The mixing unit precedes the biological treatment aiming to mix the fourstreams, which constitute the total stream entering the biological treatment units. Themixing unit mixes the wastewater from the domestic process itself, the sludge
recycling stream, the waste stream from the Belt Filtration unit and the waste streamfrom the Granular Medium Filtration unit. The waste streams are added in intentionto reduce the liquid waste from the WWT plant. The second mixing unit was usedbefore the clarifier with the purposes to gather the streams, S-127 and S-128,which were getting out of both aerobic biooxidation reactor. The third mixer precededthe belt filtration with the intention to converge the streams S-106 and S-114 intothe sludge treatment line.
5. Industrial Wastewater Treatment
5.1.Industrial Wastewater Characterization
The industrial wastewater comes from a textile industry and thecharacteristics of the stream were determined with data from the literature, which willbe presented ahead.
The flow rate found for the sewage of a textile industry that processes 1000meters of textile fabric was 342700 L/h [6]. The characteristics of the industrialinfluent are given on Table 4.
Table 4: Components information
ComponentConcentration
(mg/L)Flow rate
(kg/h)
Glucose 806 276.216
NO2_NO3 2.4 0.822
Ammonia 1.18 0.404
Phenol 0.285 0.098
Carbondioxide
376 128.855
Heavy Metals 12.91 4.424
The COD and alkalinity data were taken from the average on the six textileindustries analysed by Paul et al. (2013). The COD average is 859.2 mg/L. Hence,considering that 1g of glucose gives 1.066 g of COD, we could find the concentrationof glucose in the stream. The alkalinity average is 376 mg/L, which representscarbon dioxide in its dissolved forms.
The value of 0.285 mg/L was selected for phenol as an average of the datafrom the mixed points of the textile effluent according to Nosheen et al. (2000).
From Khan et al. (2006) we have the parameters for nitrate and ammonia asan average of the wastewater parameters for different industries. The component
Heavy Metals was determined as a sum of concentration of the metals (Cd, Cr, Cu,
-
8/12/2019 Final Coursework
12/35
Fe, N, Mn and Zn) analysed by Imtiazuddin et al. (2012). The contribution of eachmetal is presented in Table 5.
Table 5: Heavy Metals Concentration
MetalsAverage
Composition (mg/L)
Cd 0.07
Cr 1.39
Cu 2.72
Fe 1.96
Ni 0.99
Mn 1.27
Zn 4.51
Total Heavy
Metals12.91
5.2.Designed Plant and Flow sheet
The flow sheet of the industrial wastewater treatment plant is presented in.The units specifications, dimensions and input and output streams are described inthe sub items as follow.
-
8/12/2019 Final Coursework
13/35
Figure 3: Industrial WWT Plant flowsheet
-
8/12/2019 Final Coursework
14/35
5.2.1.Mixing Unit
The mixing unit has the same function as described in 3.1 but it mixes otherfour streams, the input, the sludge recycling, S-117and S-105. The S-117 streamis the backwash flow from the granular medium filter and the S-105 stream is the
waste flow from the belt filter. The output stream of this unit is the S-102 stream.
5.2.2.Aerobic BioOxidation reactors
The bioreactors were used in order to digest the organic content of theindustrial waste under aerobic conditions and to remove heavy metals by sorption tothe biomass produced, which will be removed in the clarifier. The reactions occurringin this unit and their kinetic constants and stoichiometry are described below insections 4.2.2.1 to 4.2.2.3.
Two aerobic bio oxidation reactors in series were required to produce water in
accordance to United Kingdom standards for wastewater discharge.Both aeration basins have a total volume of 2,099,980.92 litres. The reactorshave a rectangular configuration, with length of 38.73 m and width of 15.49 m, anddepth of 3.5 meters. The hydraulic detention time is 6 hours, with a dissolved oxygenconcentration of 2 g/L. The reactors work with a surface aeration system. For thedesign, 90 % of the heavy metals are removed by sorption to the biomass.
The first aeration tank receives the S-102 stream and an air stream to supplyoxygen for the aerobic reactions (S-113). This reactor emission is represented as theS-103 stream, which is composed of carbon dioxide. The S-104 stream continues totreatment entering the second reactor.
The second reactor also has an input air stream (S-120) to provide oxygen.
The gas emission of this reactor is also composed of carbon dioxide and isrepresented by S-108 stream. The output stream of the reactor (S-106) goes to theclarifier to solids sedimentation.
The extend achieved for each reactions is presented in table 6.
Table 6: Reactions extend achieved
Reaction Aeration Basin 1 Aeration Basin 2Glucose
Degradation86.193% 100%
PhenolDegradation
99.057% 0.00%
Biomass decay 59.702% 19.870%
5.2.2.1. Glucose degradation
gggg
COOHVSSAeGlu
3.0
2
3.0
2
4.01
_cos
k = 0.08 1/h. The above rate constant is assumed to apply for T = 20 oC. The impactof temperature variations is accounted by assuming a theta value of 1.04.
Ks = 5 mg glucose/L.
-
8/12/2019 Final Coursework
15/35
5.2.2.2. Phenol degradation
gggg
COOHVSSAPhenol
3.0
2
4.0
2
3.00.1
_
k = 0.097 1/h.
The above rate constant is assumed to apply for T = 20 oC. The impact oftemperature variations is accounted by assuming a theta value of 1.0.
Ks = 7.462 mg Phenol/L
5.2.2.3. Biomass decay
ggggggg
CONHOHSSNonBioVSSIOVSSA45.1
2
1.035.0
2
1.02.015.1
2
05.1
3___
kd = 0.00325416 1/h.
The above rate constant is assumed to apply for T = 20 oC. The impact oftemperature variations is accounted by assuming a theta value of 1.089.
5.2.3.Clarifier
The Clarifier in question was set with a surface area of 355.80 m2, withdiameter of 21.28 meters, and a depth of 3m, resulting in a total volume of1,218,035.15 L. In this equipment 90% of the A_VSS and 90% of NonBio SS wereremoved.
The clarifier receives the S-106 stream from the second aeration tank. Noemissions were considered in this unit. The output streams are the S-121 thatcontinues to the treatment entering the granular media filter, and the sludge stream.The sludge stream is lead to the flow splitting unit.
5.2.4.Granular media filter
Generally used after gravity separation, Granular Media is a polishing stepthat lowers the levels of suspended solids and associated contaminants in treatedwastes. Particle removal takes place either on the surface of the media (cakefiltration) or throughout the depth of the media (depth filtration).
It was used a base unit with a bed depth of 2.02 m and a bed diameter of 1.5m. In order to achieve the total volume of wastewater that needs to be treated, 10granular media filters were used in this step. The overall removal efficiency was90%.
The S-121 stream from the clarifier is filtered and the main product of this unit,and also of the whole process, is represented by Output stream. The S-119 streamrepresents the backwash water input and the S-117 is the waste from this process,which is orientated to the mixing unit at the beginning of the plant.
-
8/12/2019 Final Coursework
16/35
5.2.5.Flow Splitting
The flow splitting unit of the plant splits the sludge stream that comes from theclarifier in two streams: 25% of the sludge stream is recycled to the first aeration tankand the left amount goes to the sludge treatment line, entering the Belt Filtration unit.
5.2.6.Belt Filter
A belt filter was selected to provide increase in solids concentration of thesludge with a low area requirement. The belt width is 0.34 m. The belt filter workswith 90% of sludge recovery and 15% of solids in cake. The unit works with 90% ofremoval of A_VSS biomass, I_VSS biomass and NonBio SS.
The unit receives the sludge treatment line and a water stream (S-112). TheS-105 stream is the waste stream of the unit process and is redirected to the mixingunit. The S-111 stream goes to the sludge drier with a higher solids concentration
then before.
5.2.7.Sludge Drying
The sludge drying process consists in a reduction of moisture throughevaporation of water, using energy to reach the evaporation rate desired.
In this case, the evaporative capacity used was 337.86 kg/h, reaching 35% ofsolids in dried sludge.
The S-111 stream enters the unit and is concentrated, resulting in the driedsludge stream. The S-114 stream is the air to the process and the S-116 stream iscomposed of the air and water evaporated in the process.
6. Economic Evaluation
6.1.Domestic Wastewater Treatment Plant
Analysing the data given and, adding to it, the knowledge obtained throughresearch, the simulations were performed in SuperPro Designer and an EconomicReport was generated.
In an executive summary, the Total Capital Investment obtained was101,178,000 $, with an Operating Cost of in 21,020,00 $/yr.
As part of an initial investment analysis, the Costs of Units were taken into
account and the results obtained are shown as in Table 7.Table 7: Equipment Costs
Quantity Name Unit Cost ($) Total Cost ($)
1 Aeration Basin [1] 4,944,000 4,944,000
1 Clarifier [1] 333,000 333,000
6 Granular Media Filter 500,000 3,000,000
1 Belt Filter 244,000 244,000
1 Sludge Dryer 31,000 31,000
1 Clarifier [2] 296,000 296,000
1 Aeration Basin [2] 4,944,000 4,944,000
-
8/12/2019 Final Coursework
17/35
The sum of all costs with the units results in a total cost of 13,792,000 $ forthe plant.
Along the Economic Evaluation a Fixed Capital Estimate Summary is made,based on the data of the software used, resulting in Table 8:
Table 8: Fixed capital estimate summary
Total Plant Direct Cost (TPDC)(physical cost)
Equipment Purchase Cost 17,240,000
Installation 2,587,000
Process Piping 6,034,000
Instrumentation 6,896,000
Insulation 517,000
Electrical 1,724,000
Buildings 7,758,000
Yard Improvement 2,586,000
Auxiliary Facilities 6,896,000
TPDC 52,239,000
Total Plant Indirect Cost (TPIC)
Engineering 13,060,000
Construction 18,283,000
TPIC 31,343,000
Total Plant Cost (TPC = TPDC+TPIC)TPC 83,582,000
Contractor's Fee & Contingency(CFC)
Contractor's Fee 4,179,000
Contingency 8,358,000
CFC 12,537,000
Direct Fixed Capital Cost (DFC =TPC+CFC)
DFC96,119,000
As a following step, the Labor Cost Analysis was made based on the selectedlabour type, such as Dryer Operator, and the rates of Unit Cost ($/h) combined withthe total of hours of usage. These calculations resulted in a total annual cost of2,709,275 $, with an annual amount of hours of 38,469 h.
Similarly to the Labor Cost Analysis, an Utilities Cost Evaluation is madetaking into account Std Power and Steam and its Unit Costs combined with theAnnual Amount, resulting in a total cost of 50,668 $.
As a final step in the Economic Evaluation, an Annual Operating Cost is made
compiling all the costs in the plant. Summing the costs from the plant, a Total AnnualOperating Cost obtained is equal to 21,020,000 $.
-
8/12/2019 Final Coursework
18/35
6.2.Industrial Wastewater Treatment Plant
Following the same steps as did with the Domestic Wastewater, an EconomicEvaluation of the Industrial Wastewater Plant is performed using the data from thesimulations in SuperPro Designer.
The Executive Summary generated for this plant gives a Total InvestmentCost of 86,041,000 $. Besides that, an Operating Cost rate is calculated, resulting in18,158,000 $/yr.
As did before in the previous Economic Evaluation, the equipment costs wereused to give an overall cost for the major units. The results can be seen as in Table9:
Table 9: Equipment Costs
Quantity Name Unit Cost ($) Total Cost ($)
1 Clarifier 324,000 324,000
10
Granular Media
Filter 485,000 4,850,000
1 Belt Filter 244,000 244,000
1 Sludge Dryer 31,000 31,000
1 Aeration Basin [1] 3,079,000 3,079,000
1 Aeration Basin [2] 3,079,000 3,079,000
The sum of the costs of all units results in a total equipment value of11,607,000 $.
As a part of consummating the evaluation, a fixed capital summary is madeand the values obtained are shown as in Table 10:
-
8/12/2019 Final Coursework
19/35
Table 10: Fixed capital estimate summary
Total Plant Direct Cost (TPDC)(physical cost)
Equipment Purchase Cost 14,509,000
Installation 2,623,000
Process Piping 5,078,000
Instrumentation 5,804,000
Insulation 435,000
Electrical 1,451,000
Buildings 6,529,000
Yard Improvement 2,176,000
Auxiliary Facilities 5,804,000
TPDC 44,408,000
Total Plant Indirect Cost (TPIC)
Engineering 11,102,000
Construction 15,543,000
TPIC 26,645,000
Total Plant Cost (TPC = TPDC+TPIC)
TPC 71,053,000
Contractor's Fee & Contingency(CFC)
Contractor's Fee3,553,000
Contingency 7,105,000
CFC 10,658,000
Direct Fixed Capital Cost (DFC =TPC+CFC)
DFC 81,711,000
Moving forward in the process of doing an Economic Evaluation, a Labor CostSummary is made using the same labor types as did before and the results obtained
culminated in a Total Annual Cost of 2,631,206 $, with an annual amount of hours of37,337h.Following the same steps as in the previous evaluation, the Utilities Cost
Evaluation uses again the Std Power and the Steam to obtain a total cost of 50,668$.
Finally, in order to accomplish a complete Economic Evaluation, a TotalAnnual Operating Cost is obtained, resulting in 18,158,000 $.
-
8/12/2019 Final Coursework
20/35
7. Environmental Impact Analysis
7.1.Domestic WWT Plant Analysis
The environmental properties of the input and output of the domesticwastewater treatment plant and the removal efficiency of the parameters are shownin Table 11.
Table 11: Environmental Parameters
ParameterDomesticInput (kg/h)
DomesticOutput (kg/h)
RemovalEfficiency
TOC (mgC/l) 204.56 10.334 95%
COD (mgO/l) 601.447 29.151 95%
ThOD (mgO/l) 601.447 29.151 95%
BODu (mgO/l) 576.953 24.591 96%
BOD5 (mgO/l) 392.328 16.722 96%
TKN (mgN/l) 30.688 2.44 92%
NH3 (mgN/l) 0 0 0
NO3/NO2 (mgN/l) 0.572 8.086 -1314%
TP (mgP/l) 5.532 1.001 82%
TS (mgSlds/l) 439.465 279.997 36%
TSS (mgSlds/l) 188.243 21.311 89%
VSS (mgSlds/l) 99.574 18.019 82%
DVSS (mgSlds/l) 79.659 14.415 82%
TDS (mgSlds/l) 251.222 258.686 -3%
VDS (mgSlds/l) 0 0 0
DVDS (mgSlds/l) 0 0 0
It can be seen in the table above that the domestic wastewater plant had asatisfying removal efficiency of COD and BOD5 as expected, once that the highorganic matter removal is a characteristic of the activated sludge process. Although,the removal efficiency of NO3/NO2 was negative but this was expected once that
these components are formed in the nitrification reaction (3.1.2.). Besides, the TDSrate was negative, which can be related to the increase of NO3/NO2.
7.2.Industrial WWT Plant Analysis
The environmental properties of the input and output of the domesticwastewater treatment plant and the removal efficiency of the parameters are shownin Table 12.
-
8/12/2019 Final Coursework
21/35
Table 12: Environmental Parameters
ParameterIndustrial Input(kg/h)
Industrial Output(kg/h)
RemovalEfficiency
TOC (mgC/l) 321.3 8.391 97%
COD (mgO/l) 856.36 23.456 97%ThOD (mgO/l) 856.07 23.276 97%
BODu (mgO/l) 626.361 19.393 97%
BOD5 (mgO/l) 563.725 13.188 98%
TKN (mgN/l) 0 1.981 -100%
NH3 (mgN/l) 0 0 0
NO3/NO2 (mgN/l) 0.55 0.436 21%
TP (mgP/l) 0 0.826 -100%
TS (mgSlds/l) 805.096 18.609 98%
TSS (mgSlds/l) 0 16.712 -100%
VSS (mgSlds/l) 0 14.86 -100%
DVSS (mgSlds/l) 0 11.888 -100%
TDS (mgSlds/l) 805.096 1.897 100%
VDS (mgSlds/l) 802.706 0 100%
DVDS (mgSlds/l) 802.706 0 100%
As observed, the plant had shown high removal rates of organic matter asexpected and these values were slightly higher than the domestic WWT plant since
the activator sludge reactors were set in series. The values obtained for TKN, TP,TSS, VSS and DVSS were -100% due to the fact that these parameters were onlyproduced during the process.
7.3.Final Effluent Characteristics
The output of both plants is going to be mixed before discharge in theenvironment. The final effluent characteristics are defined in Table 13.
-
8/12/2019 Final Coursework
22/35
Table 13: Final Effluent Environmental Parameters
ParameterFinal Effluent(kg/h)
TOC (mgC/l) 9.381
COD (mgO/l) 26.358
ThOD (mgO/l) 26.269
BODu (mgO/l) 22.042
BOD5 (mgO/l) 14.989
TKN (mgN/l) 2.215
NH3 (mgN/l) 0.000
NO3/NO2 (mgN/l) 4.334
TP (mgP/l) 0.915
TS (mgSlds/l) 151.794
TSS (mgSlds/l) 19.055
VSS (mgSlds/l) 16.470
DVSS (mgSlds/l) 13.176
TDS (mgSlds/l) 132.739
VDS (mgSlds/l) 0.000
DVDS (mgSlds/l) 0.000
The final effluent is in accordance to the United Kingdom standards forwastewater discharge, which are 20mg/L of BOD5 and 30mg/L of TSS. Additionally,the nutrients concentrations also met the standards for sensitive areas (P: 1-2 mg/Land N: 10-15 mg/L) [11, 12].
8. Alternatives for Sludge Disposal
After passing through the Dryer, the sludge in the end of the process couldhave different destinations, such as Landfill, Composting Plant or even Blending.
In case the option chosen as final destination is landfill, the sludge would betransported in special trucks to the landfills and in there the sludge would becorrectly disposed in areas with the proper equipment to receive and storage it.
As a second option, the sludge could be transported from the WastewaterPlant to a Composting Plant. Once it reaches the destination, the sludge would beproperly treated and its nutrient levels would be enhanced in order to be used indifferent agricultural areas, such as farms and plantations, working as a fertilizer.
One new alternative that is becoming more frequent in many differentcountries is the process of blending the sludge. This process involves mixingindustrial waste including sludge - with diverse physical characteristics, turningthem into a homogeneous product for energy use in the cement industry. Theprocess reduces the volume of waste for final disposal and extends their life cycle,
allowing their return to productive sector. In countries like Brazil this practice isbecoming very popular.
-
8/12/2019 Final Coursework
23/35
9. Conclusion
The objective of the coursework was accomplished, once that the wastewaterwas properly treated and the final effluent reached the UK standards required in
legislation. The SuperPro Designer package had a really important role ongenerating the environmental and economic reports, which aided achieving accurateresults. Besides that, the software also has a large amount of data available and afriendly interface simplifying the assembly of the project and its units.
As shown before, the volume of influent reaching the plant was large.Consequently, the size of the unit processes was relatively sizable which leaded tohigh costs associated to assembly and operating of both of the WWTP.
Finally, the project shown itself feasible considering all the parametersanalysed during the design of the plant.
10. References
[1] West Wind Yorkshire Teasroom (2010) Leeds From Industrial Centre to CallCentre I. Available at:http://www.westwindsinyorkshire.co.uk/attachments/LeedsI.pdf(Accessed at 2 November 2013).
[2] Leeds Population (no date). Available at:http://www.leeds.gov.uk/council/Pages/Leeds-population.aspxx (Accessed at 3November 2013).
[3] Downing, T.E, Butterfield, R.E., Edmonds, B., Knox, J.W., Moss, S., Piper, B.S.andWeatherhead, E.K.(and the CCDeW project team) (2003). Climate Change and theDemandfor Water, Research Report, Stockholm Environment Institute Oxford Office, Oxford.Available at: http://cfpm.org/ccdew/Climate_Change_and_Demand_for_Water-2003.pdf (Accessed at 3 November 2013).
[4] Granular Media Filter (no date). Available at:http://www.mcilvainecompany.com/brochures/liqfil%20brochure/liqfil%20charts/gran%20media%20filters.htm (Accessed at 13 November 2013).
[5] Lenntech Water Treatment Solution (no date). Available at:http://www.lenntech.com.pt/biblioteca/lamas/sludge-drying.htm#ixzz2mGZbIZuS(Accessed at 15 November 2013).
[6] BELTRAME, L. T. C. Caracterizao de Efluente Txtil e Proposta de Tratamento(Characterization of Textile Industry Effluent and Treatment Proposal). 2000. 179p.Masters Thesis (Chemical Engineering). Chemical Engineering Pos-GraduatedProgram, Federal University of Rio Grande do Norte, Natal/RN, Brazil. 2000.
[7] PAUL, S. A.; CHAVAN, S. K. and KHAMBE, S. D. (2012) Studies onCharacterization of Textile Industrial Waste Water in Solapur City, InternationalJournal of Chemical Science, 10(2), pp 635-642.
http://www.westwindsinyorkshire.co.uk/attachments/LeedsI.pdfhttp://www.westwindsinyorkshire.co.uk/attachments/LeedsI.pdfhttp://www.westwindsinyorkshire.co.uk/attachments/LeedsI.pdfhttp://www.leeds.gov.uk/council/Pages/Leeds-population.aspxxhttp://cfpm.org/ccdew/Climate_Change_and_Demand_for_Water-2003.pdfhttp://cfpm.org/ccdew/Climate_Change_and_Demand_for_Water-2003.pdfhttp://cfpm.org/ccdew/Climate_Change_and_Demand_for_Water-2003.pdfhttp://www.mcilvainecompany.com/brochures/liqfil%20brochure/liqfil%20charts/gran%20media%20filters.htmhttp://www.mcilvainecompany.com/brochures/liqfil%20brochure/liqfil%20charts/gran%20media%20filters.htmhttp://www.mcilvainecompany.com/brochures/liqfil%20brochure/liqfil%20charts/gran%20media%20filters.htmhttp://www.lenntech.com.pt/biblioteca/lamas/sludge-drying.htm#ixzz2mGZbIZuShttp://www.lenntech.com.pt/biblioteca/lamas/sludge-drying.htm#ixzz2mGZbIZuShttp://www.lenntech.com.pt/biblioteca/lamas/sludge-drying.htm#ixzz2mGZbIZuShttp://www.mcilvainecompany.com/brochures/liqfil%20brochure/liqfil%20charts/gran%20media%20filters.htmhttp://www.mcilvainecompany.com/brochures/liqfil%20brochure/liqfil%20charts/gran%20media%20filters.htmhttp://cfpm.org/ccdew/Climate_Change_and_Demand_for_Water-2003.pdfhttp://cfpm.org/ccdew/Climate_Change_and_Demand_for_Water-2003.pdfhttp://www.leeds.gov.uk/council/Pages/Leeds-population.aspxxhttp://www.westwindsinyorkshire.co.uk/attachments/LeedsI.pdf -
8/12/2019 Final Coursework
24/35
[8] NOSHEE, S.;NAWAZ, H. and KHALIL-UR-REHMAN. (2000). Physico-ChemicalCharacterization of Effluents of Local Textile Industries of FaisalabadPakistan,International Journal of Agriculture & Biology, Vol. 2, No 3, pp 232-233.
[9] Khan, M. S., Knapp, J., Clemett, A., and Chadwick, M. (2006). "Improving Effluent
Treatment and Management." Report, Key Document, R8161 - Section7, Researchfor Development, Department for International Development (DFID), UK.
[10] Imtiazuddin, S.M.; Mumtaz, M. and Mallick, K. A. (2012). Pollutants ofWastewater Characteristics in Textile Industries, Journal of Basic and AppliedScience, 8, pp 554-556.
[11] Environmental and Heritage Service. (2001). Regulation of Water ServiceDischarge. Available at:http://www.doeni.gov.uk/niea/reg_wsd.pdf(Accessed at 22November 2013).
[12] Council (91/271/EEC) 30 of May 1991, Council Directive concerning urbanwastewater treatment [1991]. No L 135/40.
http://www.doeni.gov.uk/niea/reg_wsd.pdfhttp://www.doeni.gov.uk/niea/reg_wsd.pdfhttp://www.doeni.gov.uk/niea/reg_wsd.pdfhttp://www.doeni.gov.uk/niea/reg_wsd.pdf -
8/12/2019 Final Coursework
25/35
Appendix A Units Mass Balances and Streams Composition
1. Domestic Wastewater Treatment Plant
Clarification P-6
Input Output
ComponentFlowrates (kg/h)
Input S-101 S-102 S-106
A_VSS biomass 28.438 25.594 0.000 2.844
Ammonia 7.719 7.719 0.000 0.000
Carb. Dioxide 12.188 12.188 0.000 0.000
dsticwaste 101.563 100.875 0.000 0.688
I_VSS biomass 14.219 12.797 0.000 1.422
N_VSS biomass 2.519 2.267 0.000 0.252
Nitrogen 0.000 0.000 0.000 0.000
NO2_NO3 1.016 1.009 0.000 0.007
NonBio SS 31.688 9.506 0.000 22.181
NonBio TDS 101.563 100.875 0.000 0.688
Oxygen 0.000 0.000 0.000 0.000
Water 388103.732 385476.077 0.000 2627.655
TOTAL (kg/h) 388404.641 385748.905 0.000 2655.736
TOTAL (L/h) 408316.213 405646.338 0.000 2669.875
Mixing P-4
Input Output
ComponentFlowrates (kg/h)
S-101 S-105 Sludge Recycle S-113 S-115
A_VSS biomass 25.594 37.189 278.916 9.582 351.280
Ammonia 7.719 0.000 0.000 0.000 7.719
Carb. Dioxide 12.188 0.000 0.000 0.000 12.188
dsticwaste 100.875 0.000 0.021 0.664 101.560
I_VSS biomass 12.797 0.000 32.294 1.219 46.310
N_VSS biomass 2.267 1.019 7.643 0.280 11.208
Nitrogen 0.000 0.000 0.000 0.000 0.000
NO2_NO3 1.009 0.000 1.317 0.426 2.752
NonBio SS 9.506 5.280 39.601 3.538 57.925
NonBio TDS 100.875 0.000 9.172 3.579 113.625
Oxygen 0.000 0.000 0.000 0.000 0.000
Water 385476.077 217.440 35286.575 16068.015 437048.106
TOTAL (kg/h) 385748.905 260.928 35655.538 16087.302 437752.673
TOTAL (L/h) 405646.338 262.317 35845.364 16172.949 457926.967
-
8/12/2019 Final Coursework
26/35
Flow Splitting P-10
Input Output
ComponentFlowrates (kg/h)
S-115 S-125 S-126
A_VSS biomass 351.280 175.640 175.640
Ammonia 7.719 3.859 3.859
Carb. Dioxide 12.188 6.094 6.094
dsticwaste 101.560 50.780 50.780
I_VSS biomass 46.310 23.155 23.155
N_VSS biomass 11.208 5.604 5.604
Nitrogen 0.000 0.000 0.000
NO2_NO3 2.752 1.376 1.376
NonBio SS 57.925 28.963 28.963
NonBio TDS 113.625 56.813 56.813
Oxygen 0.000 0.000 0.000
Water 437048.106 218524.053 218524.053
TOTAL (kg/h) 437752.673 218876.336 218876.336
TOTAL (L/h) 457926.967 228963.484 228963.484
Aerobic BioOxidation P-1
Input Output
ComponentFlowrates (kg/h)
S-125 S-119 S-128 S-124
A_VSS biomass 175.640 0.000 199.448 0.000
Ammonia 3.859 0.000 0.000 0.000Carb. Dioxide 6.094 0.000 41.489 0.000
dsticwaste 50.780 0.000 0.102 0.000
I_VSS biomass 23.155 0.000 23.817 0.000
N_VSS biomass 5.604 0.000 5.205 0.000
Nitrogen 0.000 76.712 1.117 75.592
NO2_NO3 1.376 0.000 1.472 0.000
NonBio SS 28.963 0.000 29.293 0.000
NonBio TDS 56.813 0.000 56.810 0.000
Oxygen 0.000 23.288 0.000 0.000
Water 218524.053 0.000 218541.993 0.000
TOTAL (kg/h) 218876.336 100.000 218900.745 75.592
TOTAL (L/h) 228963.484 84801.702 244062.539 66018.017
-
8/12/2019 Final Coursework
27/35
Aerobic BioOxidation P-2
Input Output
ComponentFlowrates (kg/h)
S-126 S-108 S-104 S-127
A_VSS biomass 175.640 0.000 0.000 199.448
Ammonia 3.859 0.000 0.000 0.000
Carb. Dioxide 6.094 0.000 0.000 41.489
dsticwaste 50.780 0.000 0.000 0.102
I_VSS biomass 23.155 0.000 0.000 23.817
N_VSS biomass 5.604 0.000 0.000 5.205
Nitrogen 0.000 76.712 75.592 1.117
NO2_NO3 1.376 0.000 0.000 1.472
NonBio SS 28.963 0.000 0.000 29.293
NonBio TDS 56.813 0.000 0.000 56.810
Oxygen 0.000 23.288 0.000 0.000
Water 218524.053 0.000 0.000 218541.993
TOTAL (kg/h) 218876.336 100.000 75.592 218900.745
TOTAL (L/h) 228963.484 84801.702 66018.017 244062.539
Mixing P-11
Input Output
ComponentFlowrates (kg/h)
S-127 S-128 S-103
A_VSS biomass 199.448 199.448 398.895
Ammonia 0.000 0.000 0.000Carb. Dioxide 41.489 41.489 82.979
dsticwaste 0.102 0.102 0.205
I_VSS biomass 23.817 23.817 47.634
N_VSS biomass 5.205 5.205 10.410
Nitrogen 1.117 1.117 2.233
NO2_NO3 1.472 1.472 2.943
NonBio SS 29.293 29.293 58.586
NonBio TDS 56.810 56.810 113.620
Oxygen 0.000 0.000 0.000
Water 218541.993 218541.993 437083.985
TOTAL (kg/h) 218900.745 218900.745 437801.490
TOTAL (L/h) 244062.539 244062.539 488125.078
-
8/12/2019 Final Coursework
28/35
Clarification P-3
Input Output
ComponentFlowrates (kg/h)
S-103S-
110S-112 Sludge
A_VSS biomass 398.895 0.000 41.321 371.888Ammonia 0.000 0.000 0.000 0.000
Carb. Dioxide 82.979 0.000 99.508 0.000
dsticwaste 0.205 0.000 0.237 0.029
I_VSS biomass 47.634 0.000 4.784 43.059
N_VSS biomass 10.410 0.000 1.132 10.190
Nitrogen 2.233 0.000 2.233 0.000
NO2_NO3 2.943 0.000 14.555 1.756
NonBio SS 58.586 0.000 5.867 52.801
NonBio TDS 113.620 0.000 101.374 12.229
Oxygen 0.000 0.000 0.000 0.000
Water 437083.985 0.000 390019.572 47048.766
TOTAL (kg/h) 437801.490 0.000 390290.582 47540.718
TOTAL (L/h) 488125.078 0.000 449532.655 47793.818
GM Filtration
Input Output
ComponentFlowrates (kg/h)
S-112 S-116 S-105 Output
A_VSS biomass 41.321 0.000 37.189 4.132Ammonia 0.000 0.000 0.000 0.000
Carb. Dioxide 99.508 0.000 0.000 99.508
dsticwaste 0.237 0.000 0.000 0.237
I_VSS biomass 4.784 0.000 0.000 4.784
N_VSS biomass 1.132 0.000 1.019 0.113
Nitrogen 2.233 0.000 0.000 2.233
NO2_NO3 14.555 0.000 0.000 14.555
NonBio SS 5.867 0.000 5.280 0.587
NonBio TDS 101.374 0.000 0.000 101.374
Oxygen 0.000 0.000 0.000 0.000
Water 390019.572 217.440 217.440 390019.572
TOTAL (kg/h) 390290.582 217.440 260.928 390247.094
TOTAL (L/h) 449532.655 218.597 262.317 449488.936
-
8/12/2019 Final Coursework
29/35
Flow Splitting P-5
Input Output
ComponentFlowrates (kg/h)
SludgeSludgeRecycle
S-114
A_VSS biomass 371.888 278.916 92.972Ammonia 0.000 0.000 0.000
Carb. Dioxide 0.000 0.000 0.000
dsticwaste 0.029 0.021 0.007
I_VSS biomass 43.059 32.294 10.765
N_VSS biomass 10.190 7.643 2.548
Nitrogen 0.000 0.000 0.000
NO2_NO3 1.756 1.317 0.439
NonBio SS 52.801 39.601 13.200
NonBio TDS 12.229 9.172 3.057
Oxygen 0.000 0.000 0.000
Water 47048.766 35286.575 11762.192
TOTAL (kg/h) 47540.718 35655.538 11885.179
TOTAL (L/h) 47793.818 35845.364 11948.455
Mixing P-12
Input Output
ComponentFlowrates (kg/h)
S-114 S-106Sludge Treatment
Line
A_VSS biomass 92.972 2.844 95.816Ammonia 0.000 0.000 0.000
Carb. Dioxide 0.000 0.000 0.000
dsticwaste 0.007 0.688 0.695
I_VSS biomass 10.765 1.422 12.187
N_VSS biomass 2.548 0.252 2.799
Nitrogen 0.000 0.000 0.000
NO2_NO3 0.439 0.007 0.446
NonBio SS 13.200 22.181 35.381
NonBio TDS 3.057 0.688 3.745
Oxygen 0.000 0.000 0.000
Water 11762.192 2627.655 14389.847
TOTAL (kg/h) 11885.179 2655.736 14540.916
TOTAL (L/h) 11948.455 2669.875 14618.330
-
8/12/2019 Final Coursework
30/35
Belt Filtration
Input Output
ComponentFlowrates (kg/h)
Sludge TreatmentLine
S-111 S-113 S-120
A_VSS biomass 95.816 0.000 9.582 86.234Ammonia 0.000 0.000 0.000 0.000
Carb. Dioxide 0.000 0.000 0.000 0.000
dsticwaste 0.695 0.000 0.664 0.031
I_VSS biomass 12.187 0.000 1.219 10.968
N_VSS biomass 2.799 0.000 0.280 2.519
Nitrogen 0.000 0.000 0.000 0.000
NO2_NO3 0.446 0.000 0.426 0.020
NonBio SS 35.381 0.000 3.538 31.843
NonBio TDS 3.745 0.000 3.579 0.166
Oxygen 0.000 0.000 0.000 0.000
Water 14389.847 2423.486 16068.015 745.318
TOTAL (kg/h) 14540.916 2423.486 16087.302 877.100
TOTAL (L/h) 14618.330 2436.388 16172.949 881.769
Sludge Drying
Input Output
ComponentFlowrates (kg/h)
S-120 S-121 S-122 Dried Sludge
A_VSS biomass 86.234 0.000 0.000 86.234Ammonia 0.000 0.000 0.000 0.000
Carb. Dioxide 0.000 0.000 0.000 0.000
dsticwaste 0.031 0.000 0.000 0.031
I_VSS biomass 10.968 0.000 7.714 3.254
N_VSS biomass 2.519 0.000 0.000 2.519
Nitrogen 0.000 3643.249 3643.249 0.000
NO2_NO3 0.020 0.000 0.000 0.020
NonBio SS 31.843 0.000 0.000 31.843
NonBio TDS 0.166 0.000 0.000 0.166
Oxygen 0.000 1106.020 1106.020 0.000
Water 745.318 0.000 524.204 221.114
TOTAL (kg/h) 877.100 4749.269 5281.187 345.182
TOTAL (L/h) 881.769 4027461.098 6183622.038 351.528
-
8/12/2019 Final Coursework
31/35
2. Industrial Wastewater Treatment Plant
Mixing P-9
Input Output
ComponentFlowrates (kg/h)
Input S-105Sludge
RecyclingS-117 S-102
A_VSS biomass 0.000 9.770 293.094 39.079 341.943
Ammonia 0.404 0.000 0.000 0.000 0.404
Carb. Dioxide 128.855 0.000 0.000 0.000 128.855
Glucose 276.216 0.000 0.000 0.000 276.216
Heavy Metals 4.424 0.517 13.650 3.520 22.111
I_VSS biomass 0.000 0.106 3.180 25.259 28.544
Nitrogen 0.000 0.000 0.000 0.000 0.000
NO2_NO3 0.822 0.030 0.093 0.000 0.945
NonBio SS 0.000 0.197 5.915 0.789 6.901
Oxygen 0.000 0.000 0.000 0.000 0.000
Phenol 0.098 0.003 0.009 0.000 0.109
Water 270219.100 11415.034 10258.816 271656.578 312753.811
TOTAL (kg/h) 270629.920 11425.656 31092.387 411.877 313559.840
TOTAL (L/h) 344106.222 11486.027 31245.842 410.956 387249.047
Aerobic BioOxidation P-7
Input Output
ComponentFlowrates (kg/h)
S-102 S-113 S-103 S-104
A_VSS biomass 341.943 0.000 0.000 424.512
Ammonia 0.404 0.000 0.000 1.613
Carb. Dioxide 128.855 0.000 196.058 21.784
Glucose 276.216 0.000 0.000 38.137
Heavy Metals 22.111 0.000 0.000 22.111
I_VSS biomass 28.544 0.000 0.000 30.962
Nitrogen 0.000 76.712 0.000 76.712
NO2_NO3 0.945 0.000 0.000 0.945NonBio SS 6.901 0.000 0.000 8.110
Oxygen 0.000 23.288 0.000 9.385
Phenol 0.109 0.000 0.000 0.001
Water 312753.811 0.000 0.000 312829.510
TOTAL (kg/h) 313559.840 100.000 196.058 313463.782
TOTAL (L/h) 387249.047 84801.702 108988.809 403596.310
-
8/12/2019 Final Coursework
32/35
Aerobic BioOxidation P-8
Input Output
ComponentFlowrates (kg/h)
S-104 S-120 S-108 S-106
A_VSS biomass 424.512 0.000 0.000 435.692
Ammonia 1.613 0.000 0.000 2.178
Carb. Dioxide 21.784 0.000 38.527 4.281
Glucose 38.137 0.000 0.000 0.000
Heavy Metals 22.111 0.000 0.000 22.111
I_VSS biomass 30.962 0.000 0.000 32.091
Nitrogen 76.712 76.712 0.000 153.421
NO2_NO3 0.945 0.000 0.000 0.945
NonBio SS 8.110 0.000 0.000 8.674
Oxygen 9.385 23.288 0.000 26.181Phenol 0.001 0.000 0.000 0.088
Water 312829.510 0.000 0.000 312839.594
TOTAL (kg/h) 313463.782 100.000 38.527 313525.255
TOTAL (L/h) 403596.310 84801.702 21417.236 474503.842
Clarification
Input Output
Component
Flowrates (kg/h)
S-106S-
107S-121 Sludge
A_VSS biomass 435.692 0.000 43.421 390.792
Ammonia 2.178 0.000 2.172 0.000
Carb. Dioxide 4.281 0.000 4.285 0.000
Glucose 0.000 0.000 0.000 0.000
Heavy Metals 22.111 0.000 3.911 18.200
I_VSS biomass 32.091 0.000 28.065 4.239
Nitrogen 153.421 0.000 153.421 0.000
NO2_NO3 0.945 0.000 0.821 0.124
NonBio SS 8.674 0.000 0.876 7.887
Oxygen 26.181 0.000 26.252 0.000Phenol 0.088 0.000 0.077 0.012
Water 312839.594 0.000 271656.578 41035.262
TOTAL (kg/h) 313525.255 0.000 271919.879 41456.516
TOTAL (L/h) 474503.842 0.000 432740.944 41661.123
-
8/12/2019 Final Coursework
33/35
GM Filtration
Input Output
ComponentFlowrates (kg/h)
S-121 S-119 S-117 Output
A_VSS biomass 43.421 0.000 39.079 4.342
Ammonia 2.172 0.000 0.000 2.172
Carb. Dioxide 4.285 0.000 0.000 4.285
Glucose 0.000 0.000 0.000 0.000
Heavy Metals 3.911 0.000 3.520 0.391
I_VSS biomass 28.065 0.000 25.259 2.807
Nitrogen 153.421 0.000 0.000 153.421
NO2_NO3 0.821 0.000 0.000 0.821
NonBio SS 0.876 0.000 0.789 0.088
Oxygen 26.252 0.000 0.000 26.252Phenol 0.077 0.000 0.000 0.077
Water 271656.578 343.231 271656.578 30776.447
TOTAL (kg/h) 271919.879 343.231 411.877 271851.233
TOTAL (L/h) 432740.944 345.058 410.956 432675.046
Flow Splitting P-9
Input Output
Component
Flowrates (kg/h)
SludgeSludge
RecyclingSludge Treatment
Line
A_VSS biomass 390.792 293.094 97.698
Ammonia 0.000 0.000 0.000
Carb. Dioxide 0.000 0.000 0.000
Glucose 0.000 0.000 0.000
Heavy Metals 18.200 13.650 4.550
I_VSS biomass 4.239 3.180 1.060
Nitrogen 0.000 0.000 0.000
NO2_NO3 0.124 0.093 0.031
NonBio SS 7.887 5.915 1.972
Oxygen 0.000 0.000 0.000Phenol 0.012 0.009 0.003
Water 41035.262 10258.816 0.000
TOTAL (kg/h) 41456.516 31092.387 10364.129
TOTAL (L/h) 41661.123 31245.842 10415.281
-
8/12/2019 Final Coursework
34/35
Belt Filtration
Input Output
ComponentFlowrates (kg/h)
SludgeTreatment Line
S-112 S-111 S-105
A_VSS biomass 97.698 0.000 87.928 9.770
Ammonia 0.000 0.000 0.000 0.000
Carb. Dioxide 0.000 0.000 0.000 0.000
Glucose 0.000 0.000 0.000 0.000
Heavy Metals 4.550 0.000 4.033 0.517
I_VSS biomass 1.060 0.000 0.954 0.106
Nitrogen 0.000 0.000 0.000 0.000
NO2_NO3 0.031 0.000 0.001 0.030
NonBio SS 1.972 0.000 1.774 0.197
Oxygen 0.000 0.000 0.000 0.000Phenol 0.003 0.000 0.000 0.003
Water 0.000 1669.934 513.716 11415.034
TOTAL (kg/h) 10364.129 1669.934 608.406 11425.656
TOTAL (L/h) 10415.281 1678.824 608.078 11486.027
Sludge Drying
Input Output
Component
Flowrates (kg/h)
S-111 S-114 S-116Dried
Sludge
A_VSS biomass 87.928 0.000 0.000 87.928
Ammonia 0.000 0.000 0.000 0.000
Carb. Dioxide 0.000 0.000 0.000 0.000
Glucose 0.000 0.000 0.000 0.000
Heavy Metals 4.033 0.000 0.000 4.033
I_VSS biomass 0.954 0.000 0.000 0.954
Nitrogen 0.000 2314.102 2314.102 0.000
NO2_NO3 0.001 0.000 0.000 0.001
NonBio SS 1.774 0.000 0.000 1.774
Oxygen 0.000 702.517 702.517 0.000Phenol 0.000 0.000 0.000 0.000
Water 513.716 0.000 337.861 175.854
TOTAL (kg/h) 608.406 3016.619 3354.480 270.545
TOTAL (L/h) 608.078 2558144.012 3927684.292 271.900
-
8/12/2019 Final Coursework
35/35
Appendix B Meetings Minutes
21/10: First group meeting, when we made the Project Plan in order to organize thetasks and next meetings. It was noticed the need of a population projection and thecomposition of the industrial wastewater. Everyone agreed to do some study on the
scope of the project until the next meeting.
28/10: The members of the group decided to do some research about the populationprojection in favour of choosing a good method for the estimates to be appropriate.In addition, the characteristics of the industrial wastewater required attention oncethat it is crucial for precise treatment. Another meeting was scheduled for 07/11. Theproject plan can be seen below:
07/11: The population projection was defined and calculated which also helped withthe definition of the design of the plant. The members of the group are supposed todo some research for the next days in order to find out the best way of treatment and
spend some time using SuperPro software to improve their abilities on it.
12/11: Meeting arranged for discussion about design of the Wastewater TreatmentPlant considering the wastewater composition. All the members had a discussionabout the domestic plant and started the design of it.
14/11: The group worked on the design of the domestic WWT plant, considering allthe information collected before.
18/11: Start of the design on the industrial WWT plant.
22/11: The design of both plants was finished, and the flow sheets were properlyorganized to facilitate viewing.
23/11: The group began to write the report, explaining all the calculations andinformation used on it.
27/11: Meeting arranged for final adjustments in the report, formatting and revisions.
28/11: The group started to prepare the presentation, discussing the main issues tobe addressed and the best way to do it, in order to meet the time set by the lecturer.
30/11: The presentation was finished and final revision was made to correct possible