Fidic law1

17
SUBMITTED BY: ANIL YADAV ASHOK PERSHAD DHIRAJ GAUR MANOJ MUKUL VERMA FIDIC

description

 

Transcript of Fidic law1

Page 1: Fidic law1

SUBMITTED BY:ANIL YADAV

ASHOK PERSHADDHIRAJ GAUR

MANOJMUKUL VERMA

FIDIC

Page 2: Fidic law1

Fédération Internationale Des Ingénieurs-Conseils - FIDIC

FIDIC is the French acronym for the International Federation of Consulting Engineers. FIDIC was founded in 1913 to promote the professional interests of the member associations and to disseminate information of interest to members of its component national associations Today FIDIC membership numbers more than 60 countries and represents most of the private practice consulting engineers in the world. Only associations of consulting engineers are eligible for FIDIC membership.

During the past half century, the International Federation of Consulting Engineers (FIDIC) has devoted itself to the compilation of management documents for all kinds of projects, among which the FIDIC Conditions of Contract are of the highest influence and are the most popular application.

Page 3: Fidic law1

New Edition FIDIC

The new models include :FIDIC Conditions of Contract for Construction, the

(New Red Book)FIDIC Conditions of Contract for Plant and

Design/Build, the (New Yellow Book)FIDIC Conditions of Contract for EPC Turnkey

Projects, the (Silver Book)FIDIC Short Form of Contract, the (Green Book)FIDIC Conditions of Contract (new edition) raised a

higher requirement to the Parties concerned in the area of contract management 12

Page 4: Fidic law1

APPLICATION

Applicability under Various Project Delivery and Contracting System: 1. The “New Red Book” can be used in any kind of Engineering

Construction Contract. 2. The “New Yellow Book” applies to the lump sum contract

project where the Contractor takes participation in the design work.

3. The “Silver Book” applies to the turnkey projects of infrastructures or large-scale factories, where the Contractor takes on more work and risk while the Employer’s participation is small (private financing or government financing), but it is strictly defined upon the investment and construction period.

4. The “Green Book” can be used in all kinds of small-scale projects.

5. Altogether, these four Contract Conditions can be applied to nearly every kind of project, expect for that of managing contracting or simply consulting or designing

Page 5: Fidic law1

FIDIC

The first edition of FIDIC Conditions of Contract for Works of Civil Engineering Construction (use “Red Book” in the following) was compiled in 1957,and later its second, third, and fourth edition were issued in 1963, 1977, and 1987 respectively.

Page 6: Fidic law1

FIDIC

With the investigation of the governments, employers, contractors and consulting engineers all over the world about their application of the “Red Book”, 204 findings reports were returned.

According to the findings, the FIDIC Contract Committee organized a group of experts to compile the new Contract Condition models to be applied in the 21stcentury.

Page 7: Fidic law1

High-quality Provisions and Logical Clause Sequencing:

Compared with the original “Red Book”, the “New Red Book” has163 clauses, nearly 40% being freshly compiled. An additional 40% were modified and given supplements. Only 20% were kept intact. The old edition adopted ICE’s disorderly style bit in the clause sequence, while in the new edition, the related sub-clauses are put into one clause when possible, and convenient to the users.

Page 8: Fidic law1

Green Book -Low value,simple works

100%0%Amount of design by Contractor

• R

isk

tra

ns

fer

to C

on

tra

cto

r•

Ce

rta

inty

of

ou

ttu

rn p

ric

e

Red

Yellow

Silver

Page 9: Fidic law1

OLD NEW

Civil‘Red Book’4th Edition1987,1992

Construction(mainly)

Employer-Design1999

Page 10: Fidic law1

Typical Sequence of dispute Events Envisaged in Clause 20

20.2 Partiesappointthe DAB

20.4 A Partyrefers a disputeto the DAB

Parties presentsubmissions to the DAB

20.4 A Party mayissue a “notice ofdissatisfaction”

DAB gives its decision

< 28d < 84d < 28d < 56d

Amicable Settlement

Page 11: Fidic law1

The Parties in a FIDIC Contract

Page 12: Fidic law1

The Current (1999) Red Book – Basic Features

The Current (1999) Red Book – Basic Features

1. Suitable for all civil works projects where main responsibility for design lies with Employer (or his Engineer).

2. Some design may, of course, be carried out by Contractor.

3. Administration of Contract and supervision by Engineer.

4. Approval of work, payment and claims certified by Engineer.

5. Work done is measured, payment according to Bill of Quantities.

6. Option for payment on lump sum basis.

7. Balanced / fair risk-sharing.

Page 13: Fidic law1

More specific provisions concerning the rights & obligations of the contracting parties

Taking the clause of Employer’s default as an example, there are 3 points added to the new red book: two of them are concerned with payments. This shows the strict requirement for the employer. However the contractor should institute a quality assurance system and submit to the engineer to audit any aspect of the system before execution.

Monthly progress report shall be prepared by contractor to submit to engineer every month, otherwise, payment won’t be given.

Any kind of Bribe can result in contractors default.All of the above are high requirements from the

contractor.

Page 14: Fidic law1

To solve the problem of Back payment using world wide reference

Since the problem of Employers financial vacancy or contractor financing are originating world wide, the relative clause and regulations are added into FIDIC condition of contract

The employers shall submit within 28 days, after receiving any request from contractor reasonable agreement that financial agreement has been made.

If the employer intends to make any significant change to his financial agreement, he shall give notice to contractor with detailed particulars.

Page 15: Fidic law1

To Solve the Problem of Back Payment using World Wide Experience for Reference:

It is reported that the back payment and debt between the engineering units in China have added up to 280 billion (RMB), which is mostly Employer’s (government included) default to the Contractor. The problem has greatly influenced the construction corporations that their economic strength were weakened. The market needs a legal system to provide a guarantee for free and fair competition.

Page 16: Fidic law1

Since the problems of the Employer’s financial vacancy or Contractor financing are originating worldwide, the relative clauses and regulations are added into FIDIC Conditions of Contract:

Employer’s financial arrangement. The Employer shall submit within 28 days after receiving any request from the Contractor reasonable evidence that financial arrangement has been made. If the Employer intends to make any material change to his financial arrangement, he shall give notice to the Contractor with detailed particulars.

If the Employer fails to execute in accordance with this clause, the Contractor may, after giving a 21 days’ notice to the Employer, suspend the work or reduce production output as a kind of warning; if the Contractor does not receive any reasonable financial arrangement certificate within 42 days after giving the warning, he shall be entitled to terminate the Contract, for it is the Employer’s default. Also the Contractor can get all the compensation earned on the condition of Employer’s default.

Page 17: Fidic law1

Contractor Financed Project’s execution. It is specially set up in the Particular Conditions an Example Provisions for Contractor Finance, which defines that if it is Contractor financing and he has committed to the project, the Employer shall deliver a bank payment guarantee to the Contractor within 28 days after both parties have entered into the Contract Agreement. If the Contractor does not receive the guarantee, the Engineer shall not issue the notice to commence. It is defined in the guarantee that if the Employer fails to make payment in full by the date 14 days after the expiry of the period specified in the contract as that within which such payment should have been made, the Contractor shall been entitled to demand for payment from the bank with a certificate, Contractor’s signatures which must be authenticated by his bankers or by a notary public.