FF Design and project execution FPSO.ppt - · PDF filePIPA-II Petrobas 30,000 In commissioning...
-
Upload
truongduong -
Category
Documents
-
view
214 -
download
1
Transcript of FF Design and project execution FPSO.ppt - · PDF filePIPA-II Petrobas 30,000 In commissioning...
Fieldbus Design and Project Execution for FPSO Projects
Murali Krishnan Tand
K t bh D h dKaustubh DeshpandeEmerson Process Management, Asia Pacific
1
FPSO’s using Foundation Fieldbus
ProjectName
Owner/End User
CapacityBpd
Date Commissioned
Teekay SIRI PetroJarl 15,000 March 2008
PIPA-II Petrobas 30,000 In commissioning
Lord of the Sea
Pemex 200,000 May 2007
Greater Plutonio
BP 240,000 Oct 2007
Enfield Woodside 2007Enfield Woodside 2007
2Singapore FPSO Seminar - 21 August 2009
Agenda
• Typical project organization• Implementation Process• Modular concept• System hardware design, delivery and installation y g , y
flexibility• Software standards for FPSO automation• Use of bus technologiesUse of bus technologies
3Singapore FPSO Seminar - 21 August 2009
Proven project execution modelTypical project organisationTypical project organisation
Project Manager
Involving specialist in• Operational experience • Power and Automation Systems
Project Execution Model• Stages with defined objectives
• Key activities
How do you do it?Specialists HSE
• Key activities• Milestones
P j t t Asset y
Conceptual System and Power Safety and Automation Installation support & Operational
Project support Optimisation
pengineering
ydetail engineering Systems
ySystem
ppCommissioning
pSupport
Experienced personnel in • Project Management• Application knowledge
Asset Management
• Global Support• Engineering• Asset Management
• Safety and Automation System• Instrumentation / Valves• Power Systems• Fieldbus Technology
g g• Installation supervision• Commissioning• Service• Fieldbus Workshops
4Singapore FPSO Seminar - 21 August 2009
Project ExecutionFEED Phase
Integrated Engineering Team during FEED, follow-up engineering and site integration coordinationengineering and site integration coordination
• ( Customer / Contractor / Suppliers / End-user )• Customer/End-User/Contractor experts availability
Co design on solutions• Co-design on solutions• Prepare and train customer organization and yard-teams for
utilization of new designs/techniques and maximize the yieldf• Prepare and distribute project design specifications and
perform FEED• Empowered participation in the preparation of tender
documents and package procurement to enforce standards and improve data from package units
5Singapore FPSO Seminar - 21 August 2009
Project Execution
• Design phase• Implementation phase• FAT – Metering Skid• FAT – Top Sides• Site work on yard• Site work on yard• Site work on Offshore location
SFDS helps ensure agreement and
6Singapore FPSO Seminar - 21 August 2009
and consistency
Fieldbus Implementation Process
Fieldbus
FEED Phase Site Commissioning Phase
FieldbusDeployment Assessment
Fieldbus
Engineering Phase
Commissioning Workshop
Final Review
Loop Check &FieldbusTechnical Training Fieldbus
ApplicationWorkshop Design /
Segmentation
Loop Check & Commissioning
SegmentationSimulation
Test
7Singapore FPSO Seminar - 21 August 2009
FEED Phase
FieldbusDeployment Assessment
FEED PhaseExample of Physical Design: Hazardous Area•Easier live maintenance:-ExiAssessment- ExnL•What device and component hazardous area certification is required?-FISCO devices for FNICO-Entity Exi devices for Entity ExnL
8Singapore FPSO Seminar - 21 August 2009
Engineering Phases
FieldbusDeployment Assessment
FEED Phase
Assessment
FieldbusTechnical Training Fieldbus
Engineering Phase
Training e dbusApplicationWorkshop Design /
SegmentationSimulation
Test
9Singapore FPSO Seminar - 21 August 2009
Training for Success• Training is a critical success factor for any projects• For most projects the customer, EPC, and sub-contractors have not
undergone extensive Foundation fieldbus training• Standard training must be customized to the unique design and
requirements of each project
Day 1Day 11) Foundation Fieldbus Technical Overview 2) Project Fieldbus Component 3) Segment Design) g g4) Fieldbus Installation 5) Field-Check and Troubleshooting
Day 2Day 26) Transmitter - Fieldbus functionality 7) Valve Positioner - Fieldbus functionality 8) Fieldbus Systems Setup (Hands-on)
10Singapore FPSO Seminar - 21 August 2009
9) Roundup : Questions and Answers
Fieldbus Application Workshop
EPC defines philosophy (rules) by which Fieldbus devices are allocated to the bus to
Workshop topics for discussion:
• Control Loop / Valve Criticality Ranking
Fieldbus devices are allocated to the bus to achieve desired control availability
Consists of:- Definition of control loop criticality level
• Control Loop / Valve Criticality Ranking
• Application Scope of Foundation Fieldbus
• Cable Selection
A t f JB G di
- Restrictions for allocation for control criticality level- Analysis and ranking of control loops/valves
• Arrangement of JB, Grounding
• Redundant Philosophy
• Macro-cycle philosophy
Impacts:- Number of devices per bus- Number of loops per bus
• Function Block Requirement
• Controller Location (CIC/CIF)
• Zone Application
11Singapore FPSO Seminar - 21 August 2009
Functional Design Specification (FDS)
• Generated by the Project Team
• Common design philosophy document for all parties
• Appendix content:• Appendix content:– Hazardous area concept– Components
Wi i– Wiring– Design considerations– Control strategygy– Etc.
12Singapore FPSO Seminar - 21 August 2009 12
Fieldbus Implementation Methodology
(EPC)(EPC)
• EPC will load the segment based on process plot plan and results from Segment Design Tool, risk assessment, process criticality and equipmentSegment Design Tool, risk assessment, process criticality and equipment unit.
Segment Allocation = assigning devices to busSegment Loading = block and communication timingS t D i l l t t d lt
13Singapore FPSO Seminar - 21 August 2009
Segment Design = calculate current and voltage
Fieldbus Implementation Methodology
• EPC will load the segment based on process plot plan and results from Segment Design Tool risk assessment process criticality and plant unitSegment Design Tool, risk assessment, process criticality and plant unit.
• MIV will then validate for any software constraint and provide Fieldbus Segment Software Analysis to EPC.
15Singapore FPSO Seminar - 21 August 2009
Fieldbus Software Validation• Reportp
– Macrocycle– VCRs and other resources
16Singapore FPSO Seminar - 21 August 2009 16
Site Commissioning Phase
FieldbusDeployment Assessment
FEED Phase Site Commissioning Phase
Commissioning WorkshopAssessment
FieldbusTechnical Training Fieldbus
Engineering Phasep
Final Review
Loop Check & Commissioning
Training e dbusApplicationWorkshop Design /
SegmentationSimulation
Test
17Singapore FPSO Seminar - 21 August 2009
Installation & Pre-commissioningTest Equipmentq p
• Establish procedure and checklist• Hands-on training• Installation test tools are made available in required
quantity so as to not delay project– Fieldbus power and signal simulatorFieldbus power and signal simulator– Fieldbus tester– Oscilloscope
R and C meter– R and C meter• Pre-commissioning test tools are made available
– Fieldbus tester– Handheld field communicator
18Singapore FPSO Seminar - 21 August 2009
System modular in Zone
Topsides plug&play conceptBuilt & test as stand aloneBuilt & test as stand-aloneOnly electrical connections: power & network
M10
M31power & network
M45
20Singapore FPSO Seminar - 21 August 2009
M60
Technical solution for FPSO Cabinets with ‘late IO binding’ g
21Singapore FPSO Seminar - 21 August 2009
Software Configuration Flexibility
AI module FF
PID moduleFF
Pump moduleProfibus
Database-Area: M10 - Separation
FF FF Profibus
Modules in DCS Engineering Database
M10 – Separation skid M41 - MCC
H1
M10 Separation skid M41 MCC
Profibus
AI PID Pump
H1 Profibus
22Singapore FPSO Seminar - 21 August 2009
Classic & HART I/O Fieldbus I/O
Use of Bus Technology for FPSO
Safety Control & ElectricalDataMonitoringAcquisition
23
Digital system architecture that uses the power of field intelligence to improve FPSO performance
23Singapore FPSO Seminar - 21 August 2009
improve FPSO performance
Summary
Key success factors:F d ti Fi ldb l d d i l FPSO– Foundation Fieldbus already used in several FPSO projects
– Fieldbus architecture fits well with modular– Fieldbus architecture fits well with modular construction approach of FPSOs
– FDS discussion helps to optimize design and save p p gcost
– Tools and Documentation by Vendor
24– Training at all stages is vital for success
24Singapore FPSO Seminar - 21 August 2009