Federal Grants and Airport Capital Improvement Programs

9
Presented to: By: Date: Federal Aviation Administration Federal Grants and Airport Capital Improvement Programs Western-Pacific Region Association of California Airports Brian Armstrong September 15, 2010

description

Federal Grants and Airport Capital Improvement Programs. Western-Pacific Region. Association of California Airports. Brian Armstrong. September 15, 2010. CA Best Practices on ACIP. The proposed project(s) should: Be prioritized and fully justified by the sponsor based on needs. - PowerPoint PPT Presentation

Transcript of Federal Grants and Airport Capital Improvement Programs

Presented to:

By:

Date:

Federal AviationAdministrationFederal Grants and

Airport Capital Improvement Programs

Western-Pacific Region

Association of California Airports

Brian Armstrong

September 15, 2010

2Federal AviationAdministration

FAA Update

CA Best Practices on ACIP

The proposed project(s) should: – Be prioritized and fully justified by the sponsor based on

needs.– Be consistent with the following documents:

• Airport Master Plan

• Airport Layout Plan (ALP)

• Airport’s Part 150 Noise Compatibility Program

• Runway Safety Action Team (RSAT) Report

• Airport’s FAA Pavement Maintenance Management Program (PMMP) and Caltrans Airport Pavement Management System (APMS)

• FAR Part 139 inspection report

• Caltrans 5010 inspection letters

3Federal AviationAdministration

FAA Update

CA Best Practices on ACIP (Cont)

The proposed project(s) should: – Meet eligibility requirements of FAA and Caltrans.– Be phased-in if the project is cost prohibitive based on

available State and Federal funding.– Be consistent with the national priority system found within

FAA Order 5100.39A “Airports Capital Improvement Plan”. A copy of FAA Order 5100.39A can be found in FAA website: www.faa.gov/airports under Airport Improvement Program (AIP).

– Be the subject of early communication with FAA and Caltrans to ensure proper analysis pursuant to the National Environmental Policy Act (NEPA) and California Environmental Quality Act (CEQA).

4Federal AviationAdministration

FAA Update

2012 – 2015 ACIP Planning

• October 18, 2010 - Expect letters requesting sponsor’s ACIPs to come out from FAA and State simultaneously.

• January 18, 2011 - Due Date for sponsor submittals

5Federal AviationAdministration

FAA Update

2012 – 2015 ACIP Planning• Be prepared. Expect us to fully consider the following in

considering your projects:

– AIP 4-year and older grant status

– AIP inactive grant status

– Part 139 compliance and corrective actions

– Consistency with Master Plan

– Reasonableness of forecasts (consistency with TAF)

– Airport Layout Plan (up to date and project depicted)

– Current and Accurate Exhibit A Property Map

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

To be expended 18% 60% 81% 91% 96%

Maximum to remain 82% 40% 19% 9% 4%

Year of Appropriation

1st Year after Appropriation

2nd Year after Appropriation

3rd Year after Appropriation

4th Year after Appropriation

6Federal AviationAdministration

FAA Update

2012 – 2015 ACIP Planning– Project Need and timing

• Special considerations for runway extension, supplemental runway, and land acquisition projects

– Airspace Review

– Status of Environmental Analysis• Presume 6-months for FAA to make Cat Ex determination• Presume 18-months for EA

– Status and Plan for Engineering and Design (do not exceed 30% design before NEPA is done)

– Overall funding strategy:• Use of entitlement funds on high priority projects• Project phasing• LOI or virtual LOI• Multiyear (carryover and reimbursement)• Use of PFC• Local Funding (Matching and in lue of AIP)

7Federal AviationAdministration

FAA Update

Fiscal Year 2011 Program • Level of funding and program is unclear

until the AIP is reauthorized. Anticipate funding levels similar to recent years.

• We are focusing more on proper planning before project is included in FAA’s AIP program and/or AIP provided.

Project Timing and Justification Established. Environmental Complete. Airspace is filed/complete (7460 or 7480). Airport Layout Plan Current and Depicts Project. Design complete or nearly complete. The advertisement and bid opening date established.

• Expect strict adherence to the May 1 application and AIP carryover declaration deadline.

8Federal AviationAdministration

FAA Update

2011 ACIP Related NEPA Workload• To fully implement our 2011 Program as

planned, there are:– 82 projects that may be Categorically

Excluded (CatEx) and no further action is required other than to document the Cat Ex in the project folder.

• 8 in HNL, 38 in SFO, 36 in LAX

– 335 projects that are normally CatEx but willrequire a review to determine if any Extraordinary Circumstances exist.

• 29 in HNL, 193 in SFO, 113 in LAX

– 15 projects that require at least an Environmental Assessment (EA).

• 1 in HNL, 7 in SFO, 7 in LAX

• In addition, there are 18 projects in 2012 and 13 projects in 2013 that are likely to require an EAs or EISs.

9Federal AviationAdministration

FAA Update

Questions?