Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications...

9
Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials Update 3/13/2014 Matt Maki DCL Trials Lead

description

Federal Aviation Administration DTAP Build 7.2 Schedule Update Build 7.2 Full Climb Via SID Compliance: -Compliance with full CVS Changes -CVS, CVS Except Maintain, Maintain ALT Selections -Longer WJHTC lab testing period expected due to CVS scale Build 7.2 Estimated Schedule: -June 11-12:B7.2 FAT at Thales -June 13:Install at FAATC -June 16 - July 3:Testing at FAATC -July 7-10:Install and SAT at MEM and EWR (Parallel installs)

Transcript of Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications...

Page 1: Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials.

Federal AviationAdministrationData Communications

Implementation Team (DCIT)

Data CommunicationsImplementation Team (DCIT)

DCIT #31 PLENARYDCL Trials Update3/13/2014

Matt MakiDCL Trials Lead

Page 2: Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials.

Federal AviationAdministration

DTAP Build 7.1 Schedule Update• Build 7.1 Limited Climb Via SID Compliance:

- Interim Build with KEWR focus- UM169 CVS UL when MAINT ALT Set to NONE- National 7110.65 CVS ATC Implementation set for April 3- Trials will seek EWR/MEM CVS DTAP waiver thru May 15- EWR ATC FAT Input Planned

• Build 7.1 Estimated Schedule:- April 14-15: FAT at Thales- April 16: Install at FAATC- April 17-25: Testing at FAATC- April 28 - May1: Install and SAT at MEM and EWR (Parallel

installs)

Page 3: Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials.

Federal AviationAdministration

DTAP Build 7.2 Schedule Update

• Build 7.2 Full Climb Via SID Compliance:- Compliance with full 7110.65 CVS Changes- CVS, CVS Except Maintain, Maintain ALT Selections- Longer WJHTC lab testing period expected due to CVS scale

• Build 7.2 Estimated Schedule:- June 11-12: B7.2 FAT at Thales- June 13: Install at FAATC- June 16 - July 3: Testing at FAATC- July 7-10: Install and SAT at MEM and EWR (Parallel

installs)

Page 4: Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials.

Federal AviationAdministration

KEWR DCL Trials Status Update

• UAL, FDX MD11/B777 Daily Ops Ongoing:- Open OPR reports diminishing- UAL FRC DCL Filing Error Reductions- Resuming of UAL B767 ops expected next month+

• UPS Starts Daily MD11/B767 Ops March 15:- Approx. 24 Ops/week expected

• AFS-50/400/2P Approval letter to UK CAA pending:- BAW, SAS, DLH CAA Approval letters back to FAA pending- BAW approval expected first

Page 5: Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials.

Federal AviationAdministration

KEWR DCL Trials Status Update

• NetJets Trials Participation at KEWR:- NetJets confirmed interest in participating- Kick off Telcon set for March 19 with AOC and Pilot Reps- Bombardier Global Express 5000/6000 aircraft FANS equipped- Bombardier Challenger 350 FANS/VDL2 upgrades expected in

July- 1-2 DCL flights/week from KEWR expected

• March 1-4 ZNY 72 HR ERAM Testing Complete:- Test was successful- Next 72 HR ERAM run expected April 5-8

Page 6: Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials.

Federal AviationAdministration

Page 7: Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials.

Federal AviationAdministration

KMEM DCL Trials Update• DTAP Running Stable:

- Unplanned Recons minimized – 1 event since last DCIT- Server 1, 2 Re-starts On-going (Tues/Fri)- DTAP Processing 20-40 FDX DCL ops per push- Route Revisions remain minimal/none in #s

• MEM ATC confirms use of CVS phraseology:- Planned CVS waiver will include MEM

Page 8: Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials.

Federal AviationAdministration

DCL Ops Advantages During Upcoming SWAP Season

Page 9: Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials.

Federal AviationAdministration

Questions ?