Federal AviationAdministration
Data Communications Program
DCL Trials DCIT Update
MEM ATCT
To: DCIT Plenary
From: Matt Maki
Date: 12.06.2012
Federal AviationAdministration
Agenda
• DTAP Development Status:- DTAP Development/Milestone Deliveries- Trials Schedule Update
• On-Going / Completed Trials Activities Status:
- DTAP Certification- MEM Training & Procedures- Trials Metrics Development
• Trials CSP Service Update
• EWR Trials – Schedule/Planning Discussion
Federal AviationAdministration
DTAP Milestone Deliveries
• SE2020 Deliverables / DTAP Development:- Limited Trials Build undergoing Functional Testing @ WJHTC
- Fixes previous HIGH/MED-HIGH level PTRs- Installed @ MEM ATCT 12/3 for continued Functional /FDX-UPS Testing- CAF, UM80, UM79 (Non INT), AOC DM (non SI Doc compliant)
- Full Trials Build scheduled estimated for delivery to the WJHTC on Jan 22
- Initial UM79 requirement included (ERAM FIR Boundary limits)- UM83 and discovered ‘out of scope’ minimum Trials requirements included- Additional requirements from testing included- Represents ‘full fleet’ Trials functionality
Federal AviationAdministration
MEM Limited Ops Trials (~ 3 Ops/Day - 2 Weeks) Nov 27:
- Limited Ops Build installed on WJHTC Data Comm lab DTAP- Limited Ops Build installed on designated Training DTAP3
• Dec 3-14 (WJHTC & MEM Functional/Pre-SAT Testing)- Limited Ops Build installed on MEM ATCT DTAP- Limited Ops Build Functional Testing @ MEM ATCT (Bench and FDX/UPS aircraft avionics planned)- Limited Ops Build WJHTC Functional Test summary review
• Dec 17-20 Boeing / Airbus Bench Testing Window
• Dec 24-Jan 1 (Holiday Break)
• Jan 2-7:
- OT2 @ MEM (Jan 2)- Limited MEM ATC Training (DTAP3 Training machine)- Formal MEM SAT (Jan 3-4)- Trials Start Checkpoint – Go/No Go (Jan 7)
• Jan 7-21: Buffer
• Jan 22 – TRIALS START (Jan 14 Target Start Option)
Federal AviationAdministration
MEM Limited Ops Trials Timeline
NOV DEC JAN
Holiday Break
12/24 – 1/2
OT2, ATC
Training, SAT @ MEM
1/2 – 1/7
BUFFER
1/7 – 1/21
FEB
Limited Ops Trials Window
(TBD Ops/Day – 2 Weeks)
1/22 – 2/10
Additional Functional
Testing BUFFER
12/14 – 12/24
Functional Testing @
WJHTC & MEM
11/27 – 12/14
Federal AviationAdministration
MEM Full Functionality Trials Ops• Dec 10-17:
- Final DTAP SE2020 Contract Build 6 Requirements/Delivery Date Implementation
• Jan 22-Feb 6: - Full Functionality Build installed on WJHTC DTAP – Functional Testing Window- FDX Pilot Training 30 Day Notice Given (FF Build Accepted for Trial Ops – 2/4)
• Jan 29-Feb 8:
- Conduct OT3 @ MEM (1/29)
- Conduct Formal ATC DTAP Training @ MEM
• Feb 10-Feb 15:
- END OF LIMITED OPS TRIALS (2/10)- Install Full Functionality Build on MEM DTAP (2/11)- Pre-SAT, Functional Testing Activities- FDX GOC Training 2 Week Notice Given
• Feb 18-22: - Formal Full Functionality Build SAT @ MEM- Full Trials Go/No-Go Checkpoint (2/22)
• March 4: FULL FUNCTIONALITY TRIALS START ~50 flights (2/25 Target Start Option)
- Trials Procedures Shake Out
Federal AviationAdministration
MEM Full Functionality 24x7 Ops Trials
• April 4 MEM Full Fleet Trials
• Starts 120 Day Trials Review Checkpoint Timer
Federal AviationAdministration
MEM Full Ops Trials Timeline
JAN FEB MAR
SAT @ MEM, Trials
FF GO Checkpoint
2/18 – 2/22
APR
Full Functionality 24x7 Trials Ops
4/4 + 120 Days
End of Limited
Ops Trials, MEM DTAP
Upgrade
2/10 – 2/15
Functional Testing @
WJHTC
1/22 – 2/6
OT3 & ATC
Training @ MEM
1/29 – 2/8
Full Functionality Trials Start, Procedures Shake Out (~50 DCL
Flights)
3/4 – 4/4
Buffer
FDX Pilot Training 30 Day Notice – 2/4
FDX GOC Training 14 Day Notice – 2/15
Federal AviationAdministration
Tech Ops DTAP Certification
• Certification on Track to enable Trials start:- Tech Ops reps completed draft DTAP Certification
procedures at the WJHTC lab on 10/10 & 11 - Procedures / FAM Training complete- AJW-13 to propagate Notice to field / trials sites
• FSEP office notified FTI that Cert / FAM procedures are satisfactory:
- Allows FSEP DTAP log entry & FTI check-off
• Train MEM Tech Ops Scheduled for December 17:- Trained MEM Tech Ops reps credentialed via District Mgr.
Federal AviationAdministration
MEM Training and Procedures
• MEM Training and SAT Procedures complete:- Limited MEM DTAP Training scheduled for Jan 2-7 2013- Full MEM DTAP Training planned for Jan 29 – Feb 8- MEM Trials SAT draft released for internal review 12/3
• FDX Training:- FDX AOC/Dispatch training (2 weeks advance notice req)- FDX Pilot training (30 day advance notice req)- FAA CMO LOA (2 weeks advance notice req)
Federal AviationAdministration
Trials Metrics Development
• DTAP log file analysis underway:- Thales to provide tools for decoding/presenting DTAP log file
data- Summary Trials data analysis planned- DCIT Plenary Update
• Independent Safety Assessment Office (AJI-321) planning Trials evaluation and analysis:
- Trials team to provide ISA with Trials procedures, metrics and test plans
Federal AviationAdministration
Trials CSP Service Update
• ARINC/SITA Current Agreements:- ARINC Trials service being extended from current 12/31
POP end - Additional ARINC extensions available if required- SITA service contract extended on month x month basis
Federal AviationAdministration
EWR Trials Schedule/Planning • Verify limited Trials start @ EWR can commence before the MEM
120 day review checkpoint
•EWR Trials Start in April is a challenge for DCP:- EWR ATC accepts final MEM DTAP functionality for initial Trials implementation
(Dec, DCIT Ops Mgt)- EWR CHI functionality updated utilizing a TBD DTAP release- EWR May-Sept Implementation Freeze Out
•EWR Trials Implementation Activities Underway:- Meeting at facility with ATC and Tech Ops Mgt (12/17)- FTI Telco/Network Connectivity Order Initiated- DTAP ZNY HADDS/OARS interface configuration Initiated- HADDS, FDIO Test NCP development Initiated- Equipment Implementation goal in March- Initial operators include UAL, FDX, UPS, LFT