Feasibility Review (EdF)

14
17 JJJJ 2003 J. J. JJJJJJ JJJJJ / JJ-JJ-JJ Feasibility Review (EdF) Prévessin Heating Plant & Compressed Air Production Electricity and Controls Renewal Object and proposal Object and proposal Planning and Planning and organization organization Cost estimate Cost estimate Conclusions Conclusions

description

Object and proposal Planning and organization Cost estimate Conclusions. Feasibility Review (EdF). Prévessin Heating Plant & Compressed Air Production Electricity and Controls Renewal. Object and proposal Planning and organization Cost estimate Conclusions. - PowerPoint PPT Presentation

Transcript of Feasibility Review (EdF)

Page 1: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Feasibility Review (EdF)

Prévessin Heating Plant & Compressed Air Production Electricity and Controls Renewal

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Page 2: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

A

B

C

D

E F G H I JK L M NO

P

Q

1

2

3

4

5 6 7 8 9 12 13

14

15

16

10 11

COMPRESSEUR 2

COMPRESSEUR 1

COMPRESSEUR 3

AC 216

AC 217

AC 218

AUTOCONTROLE

PUPITRECHAUDIERE 1

PUPITRECHAUDIERE 2

PUPITRECHAUDIERE 3

Inte

rrupt

eurs

géné

rale

s

Armoires BTcentrale thermique

Pupitrecentrale thermique

Armoires regulationcentrale thermique

Arm

oire

BT

com

pres

seur

s

Arm

oire

s re

gula

tion

com

pres

seur

s

5 – Heating plant self monitoring

1 – Electricity

2 – Compressed air

3 – Heating groups local control

4 – Heating plant control & supervision

Page 3: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Work packages

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Id.Id. Short descriptionShort description

1 Electricity

2 Compressed air – central control & remote monitoring

3 Heating groups (#1, #2, #3) – local control

4 Heating plant – central control & remote monitoring

5 Heating plant – self monitoring

Page 4: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Main objectives

Long-term maintainability Fulfillment of process operational needs

– Compressed air: ST-CV standard control architecture

– Heating plant: ST-FM compatibility with tertiary sector & reuse the Meyrin Heating Plant architecture, as far as possible

– Remote monitoring: Rationalization of the TCR data

Conformity to AFNOR NF E32-020-1 (1/12/96) Creation and/or upgrade of documentation

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Page 5: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Hardware redundant transmission of main alarms via APIMMD07

(existing, -EREM Project-)

Profibus DP Fieldbus

Compressed Air

Heating Plant (utilities)

Central supervision

Local controlHeating Group

# 3

Profibus DP Fieldbus

Heating Group # 2

Local control Local controlHeating Group

# 1

CERN Ethernet TCP/IP Technical Network

Wizcon

TCR

Compressor # 2

Compressor # 3

Compressor # 1

Controls architecture (except self monitoring)

Software redundancy

Software redundancy

Local controlLocal control Local control

Page 6: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Package # 1: Electricity

Two independent main feeds Cabling

– between the secondary of the transformer and the different cabinets & cubicles

Renewal of the LV cubicles Provisional feed for compressed air production during works

Proposed executionProposed execution

Material: November 2003

On-site installation: May 2004

Estimated duration: 4 weeks

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Page 7: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Package # 2: Compressed air

Central control for the 3 operational compressors (+1 backup) Supervision SCADA (Wizcon) TCR integration

Proposed executionProposed execution

Studies & factory implementation: 2003

On-site installation: June 2004

Estimated duration: 2 weeks

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Page 8: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Package # 3: Heating groups - local

Replacement of the PLC Integration of the local displays and regulators in the PLC Installation of an operation panel Replacement of the oxygen control’s servo by a VFD

Proposed executionProposed execution

On-site installation group #1: Aug 2003

Estimated duration: 2 weeks

On-site installation #2, #3: June 2004

Estimated duration: 4 weeks

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Page 9: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Package # 4: Heating plant - central

Central control for the utilities and monitoring of the three groups Control cabling and cubicles renewal Instrumentation inventory (and renewal if required) Local supervision and TCR integration

Proposed executionProposed execution

Studies : 2003

On-site installation: June 2004

Estimated duration: 4 weeks

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Page 10: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Package # 5: Self-monitoring

Replacement of the supervision platform and communications Upgrade of the self-monitoring controls and electricity NF E32-020 Décembre 1996 Equipements de chaufferie à

caractère industriel – Sécurité d’exploitation des générateurs de vapeur d’eau ou d’eau surchauffée avec ou sans présence humaine permanente

Proposed executionProposed execution

Installation of the supervision: Sept 2003

Estimated duration: 1 week

Self-monitoring upgrade: June-July 2004

Estimated duration: 8 weeks

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Page 11: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

AFNOR NF E32-020 Décembre 1996

Ce document a pour objet de définir quatre modes possibles d’exploitation des ensembles de production de vapeur d’eau ou d’eau surchauffée ainsi que les termes les plus couramment utilisés dans ce domaine, et de fixer les prescriptions générales de sécurité pour chacun de ces modes

– mode d’exploitation avec présence permanente– mode d’exploitation avec présence intermittente– mode d’exploitation en télécontrôle– mode d’exploitation en autocontrôle

Ces définitions et prescriptions concernent la surveillance, la conduite et les équipements de ces ensembles de production

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Page 12: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

Page 13: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions

PROJECT REQUESTER

Name Division/Group Telephone Mobile

Requester Mauro NONIS ST/FM 72701 164061

Requester’s deputy Paul PEPINSTER ST/FM 75326 160084

TSO Yvon BRU ST/CV 73933 160454

Budget code holder Mauro NONIS ST/FM 72701 164061

PROJECT TEAM

Name Division/Group Telephone Mobile

Project Leader Maria Carmen MORODO TESTA ST/CV 72333 164278

Correspondents

Yannic BODY (LV electricity) ST/CV/CE 72194 163977

Yvon BRU (Heating plant operation) ST/CV/OP 73933 160454

Serge DELEVAL, Michel KOLLY (Air compressed network operation) ST/CV/OP 72238 160382

François LEVRIER (Heating plant self monitoring expertise) ST/CV/TR 74812 160290

Maria Carmen MORODO TESTA (Controls and supervision) ST/CV/CE 72333 164278

Jerome PIERLOT ST/EL 72453 164053

Paul PEPINSTER ST/FM 75326 160084

Frederic HAVART ST/MA/IN 78291 164540

Frankie CARELLI ST/MA/TC 71807

Page 14: Feasibility Review (EdF)

17 2003June. . / - -M C Morodo Testa ST CV CE

Conclusions

Heating plant and compressed air are essential utilities– User and O&M requirements review– Safety requirements review (AFNOR NF E32-020)

Work planning must respect operational constraints

Hence, the splitting in 2 phases: 2003-2004, which allows the execution of in-house detailed studies while assuring the operational period engagements

Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions