Feasibility Review (EdF)
description
Transcript of Feasibility Review (EdF)
17 2003June. . / - -M C Morodo Testa ST CV CE
Feasibility Review (EdF)
Prévessin Heating Plant & Compressed Air Production Electricity and Controls Renewal
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
17 2003June. . / - -M C Morodo Testa ST CV CE
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
A
B
C
D
E F G H I JK L M NO
P
Q
1
2
3
4
5 6 7 8 9 12 13
14
15
16
10 11
COMPRESSEUR 2
COMPRESSEUR 1
COMPRESSEUR 3
AC 216
AC 217
AC 218
AUTOCONTROLE
PUPITRECHAUDIERE 1
PUPITRECHAUDIERE 2
PUPITRECHAUDIERE 3
Inte
rrupt
eurs
géné
rale
s
Armoires BTcentrale thermique
Pupitrecentrale thermique
Armoires regulationcentrale thermique
Arm
oire
BT
com
pres
seur
s
Arm
oire
s re
gula
tion
com
pres
seur
s
5 – Heating plant self monitoring
1 – Electricity
2 – Compressed air
3 – Heating groups local control
4 – Heating plant control & supervision
17 2003June. . / - -M C Morodo Testa ST CV CE
Work packages
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
Id.Id. Short descriptionShort description
1 Electricity
2 Compressed air – central control & remote monitoring
3 Heating groups (#1, #2, #3) – local control
4 Heating plant – central control & remote monitoring
5 Heating plant – self monitoring
17 2003June. . / - -M C Morodo Testa ST CV CE
Main objectives
Long-term maintainability Fulfillment of process operational needs
– Compressed air: ST-CV standard control architecture
– Heating plant: ST-FM compatibility with tertiary sector & reuse the Meyrin Heating Plant architecture, as far as possible
– Remote monitoring: Rationalization of the TCR data
Conformity to AFNOR NF E32-020-1 (1/12/96) Creation and/or upgrade of documentation
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
17 2003June. . / - -M C Morodo Testa ST CV CE
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
Hardware redundant transmission of main alarms via APIMMD07
(existing, -EREM Project-)
Profibus DP Fieldbus
Compressed Air
Heating Plant (utilities)
Central supervision
Local controlHeating Group
# 3
Profibus DP Fieldbus
Heating Group # 2
Local control Local controlHeating Group
# 1
CERN Ethernet TCP/IP Technical Network
Wizcon
TCR
Compressor # 2
Compressor # 3
Compressor # 1
Controls architecture (except self monitoring)
Software redundancy
Software redundancy
Local controlLocal control Local control
17 2003June. . / - -M C Morodo Testa ST CV CE
Package # 1: Electricity
Two independent main feeds Cabling
– between the secondary of the transformer and the different cabinets & cubicles
Renewal of the LV cubicles Provisional feed for compressed air production during works
Proposed executionProposed execution
Material: November 2003
On-site installation: May 2004
Estimated duration: 4 weeks
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
17 2003June. . / - -M C Morodo Testa ST CV CE
Package # 2: Compressed air
Central control for the 3 operational compressors (+1 backup) Supervision SCADA (Wizcon) TCR integration
Proposed executionProposed execution
Studies & factory implementation: 2003
On-site installation: June 2004
Estimated duration: 2 weeks
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
17 2003June. . / - -M C Morodo Testa ST CV CE
Package # 3: Heating groups - local
Replacement of the PLC Integration of the local displays and regulators in the PLC Installation of an operation panel Replacement of the oxygen control’s servo by a VFD
Proposed executionProposed execution
On-site installation group #1: Aug 2003
Estimated duration: 2 weeks
On-site installation #2, #3: June 2004
Estimated duration: 4 weeks
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
17 2003June. . / - -M C Morodo Testa ST CV CE
Package # 4: Heating plant - central
Central control for the utilities and monitoring of the three groups Control cabling and cubicles renewal Instrumentation inventory (and renewal if required) Local supervision and TCR integration
Proposed executionProposed execution
Studies : 2003
On-site installation: June 2004
Estimated duration: 4 weeks
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
17 2003June. . / - -M C Morodo Testa ST CV CE
Package # 5: Self-monitoring
Replacement of the supervision platform and communications Upgrade of the self-monitoring controls and electricity NF E32-020 Décembre 1996 Equipements de chaufferie à
caractère industriel – Sécurité d’exploitation des générateurs de vapeur d’eau ou d’eau surchauffée avec ou sans présence humaine permanente
Proposed executionProposed execution
Installation of the supervision: Sept 2003
Estimated duration: 1 week
Self-monitoring upgrade: June-July 2004
Estimated duration: 8 weeks
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
17 2003June. . / - -M C Morodo Testa ST CV CE
AFNOR NF E32-020 Décembre 1996
Ce document a pour objet de définir quatre modes possibles d’exploitation des ensembles de production de vapeur d’eau ou d’eau surchauffée ainsi que les termes les plus couramment utilisés dans ce domaine, et de fixer les prescriptions générales de sécurité pour chacun de ces modes
– mode d’exploitation avec présence permanente– mode d’exploitation avec présence intermittente– mode d’exploitation en télécontrôle– mode d’exploitation en autocontrôle
Ces définitions et prescriptions concernent la surveillance, la conduite et les équipements de ces ensembles de production
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
17 2003June. . / - -M C Morodo Testa ST CV CE
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
17 2003June. . / - -M C Morodo Testa ST CV CE
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions
PROJECT REQUESTER
Name Division/Group Telephone Mobile
Requester Mauro NONIS ST/FM 72701 164061
Requester’s deputy Paul PEPINSTER ST/FM 75326 160084
TSO Yvon BRU ST/CV 73933 160454
Budget code holder Mauro NONIS ST/FM 72701 164061
PROJECT TEAM
Name Division/Group Telephone Mobile
Project Leader Maria Carmen MORODO TESTA ST/CV 72333 164278
Correspondents
Yannic BODY (LV electricity) ST/CV/CE 72194 163977
Yvon BRU (Heating plant operation) ST/CV/OP 73933 160454
Serge DELEVAL, Michel KOLLY (Air compressed network operation) ST/CV/OP 72238 160382
François LEVRIER (Heating plant self monitoring expertise) ST/CV/TR 74812 160290
Maria Carmen MORODO TESTA (Controls and supervision) ST/CV/CE 72333 164278
Jerome PIERLOT ST/EL 72453 164053
Paul PEPINSTER ST/FM 75326 160084
Frederic HAVART ST/MA/IN 78291 164540
Frankie CARELLI ST/MA/TC 71807
17 2003June. . / - -M C Morodo Testa ST CV CE
Conclusions
Heating plant and compressed air are essential utilities– User and O&M requirements review– Safety requirements review (AFNOR NF E32-020)
Work planning must respect operational constraints
Hence, the splitting in 2 phases: 2003-2004, which allows the execution of in-house detailed studies while assuring the operational period engagements
Object and proposalObject and proposalPlanning and organizationPlanning and organizationCost estimateCost estimateConclusionsConclusions