FARM TO MARKET ROAD FOR THE PROVINCE OF PALAWAN · 2017. 9. 28. · 1.3.2. Araceli, Palawan Araceli...
Transcript of FARM TO MARKET ROAD FOR THE PROVINCE OF PALAWAN · 2017. 9. 28. · 1.3.2. Araceli, Palawan Araceli...
Republic of the Philippines COMMISSION ON AUDIT
Commonwealth Avenue, Quezon City
FARM TO MARKET ROAD FOR THE PROVINCE OF PALAWAN
A CITIZEN PARTICIPATORY AUDIT REPORT
Republic of the Philippines COMMISSION ON AUDIT Commonwealth Avenue, Quezon City Concreting of Barangay Kamuning Farm to Market Road Phase II of Puerto Princesa City A Citizen Participatory Audit Report April 2015
TABLE OF CONTENTS ACRONYMS ……………………………………………………………………………………………………i 1.0 BACKGROUND ………………………….……………………………………………………………1 2.0 AUDIT FOCUS ……………………..………………………………………………………..…..5 3.0 AUDIT OBJECTIVES ……………………….…………………………………………………..…...18 4.0 AUDIT CRITERIA …………………………………………………….……………………...…19 5.0 AUDIT METHODOLOGY ……………………………...……………………………………...21 6.0 AUDIT PERIOD ………………..…..………………………………………………….…...…23 7.0 AUDIT RESULTS ………..…………..………………………………………………………....23 8.0 AUDIT CONCLUSION ……………….………………………………………….…………..89 9.0 RECOMMENDATIONS FOR EXECUTIVE ACTION ……………...…………..……...91 10.0 AUDITEE’S COMMENTS …………………..………………………………………………...96 11.0 AUDIT TEAM’S EVALUATION AND REJOINDER ………………..……………………..100
APPENDIX 1: TECHNICAL AUDIT REPORT ……………………….……...……...……..21
APPENDIX 2: ACKNOWLEDGMENTS ……………………………..…………………...199
APPENDIX 3: AUDIT TEAM COMPOSITION ……………………………..…………………...200
APPENDIX 4: RESULTS OF INTERVIEW ……………………………..…………………...204
APPENDIX 5: COMPUTATION OF LIQUIDATED DAMAGES …………..…………………...207
APPENDIX 6: SCHEDULE OF FUEL, OIL AND LUBRICANTS …………..…………………...208
GLOSSARY ……………….……………………….……………………….…………..………………..209
i
ACRONYMS
ABC Approved Budget for the Contract
ANSA-AEP Affiliated Network for Social Accountability in East Asia and the Pacific
AUSAID Australian Agency for International Development
COA Commission on Audit
CPA Citizen Participatory Audit
CSO Civil Society Organizations
FMR Farm to Market Road
GPPB Government Procurement Policy Board
IRR Implementing Rules and Regulations
LGU Local Government Unit
NGO Non-Government Organization
PCCP Portland Cement Concrete Pavement
P.D. Presidential Decree
R.A. Republic Act
RCPC Reinforced Concrete Pipe Culvert
R-IRR Revised Implementing Rules and Regulations
UNESCO United Nations Educational, Scientific and Cultural Organization
1
1.1. Province of Palawan
Palawan’s economy is basically agricultural. The three major crops are palay, corn and coconut. Mineral resources include nickel, copper, manganese and chromite. The province has one of the richest fishing grounds in the country. About 45% of Manila’s fish supply comes from here. It is also the only oil-producing province in the country. Pearl diving used to be a significant economic activity for Palawan. The Province of Palawan is subdivided into twenty-three (23) municipalities, one (1) highly urbanized city and four hundred thirty-three (433) barangays.
1.2. Puerto Princesa City, Palawan
The City of Puerto Princesa is located 306 nautical miles southwest of Manila,
205 nautical miles from Panay and about 250 nautical miles from Zamboanga. It is
bounded on the north by the Municipality of San Vicente and Roxas, Palawan and on
the south by Municipality of Aborlan. A chain of mountains runs through the entire
length of the city, dividing it into two distinct areas-the East and West Coast. The
eastern side, which faces the Sulu Sea, is bordered by swamplands, following a series
of flat plains to hilly terrain. The West Coast has fewer plains with mountain ranges
close to the West Philippine Sea, thus giving the city a unique yet fragile ecology. It is
strategically situated in the center portion of the island province of Palawan.
A significant portion of the city retains its indigenous vegetation, rainforest,
mangroves, and coastal ecosystem, all of which support an array of wildlife. In terms
of species biodiversity and its wide range of ecosystems, Puerto Princesa is of national
and international significance. The famous Puerto Princesa Subterranean River
National Park (formerly known as Saint Paul’s Subterranean River National Park)
covering a protected area of 22,202 hectares is haven to endemic flora and fauna. The
United Nations Educational, Scientific and Cultural Organization (UNESCO) have
designated the park as a World Heritage Site on December 4, 1999.
The City’s economy largely depends on agriculture, fisheries, trade and commerce and tourism. Guided by its vision and in collaboration with the different sectors of society, the City Government of Puerto Princesa is committed to pursue inclusive sustainable development with agriculture and tourism as the primary engines of economic growth and development.
1.3. Municipalities of the Province of Palawan
1.3.1. El Nido, Palawan
El Nido is a first class municipality located in the northernmost tip of
mainland Palawan, about six (6) hours land travel or 238 kilometers from Puerto
1.0 BACKGROUND
2
Princesa City, Palawan’s capital. It covers a total land area of 465.1 square
kilometers and is politically subdivided into eighteen (18) barangays.
1.3.2. Araceli, Palawan
Araceli is a fourth class island municipality located in the northern part of
the Province of Palawan. It covers a total land area of 17,680 hectares and
occupies 1.19% of province’s total land area. It is politically subdivided into
thirteen (13) barangays.
1.3.3. Taytay, Palawan
The Municipality of Taytay, a 1st class municipality,is situated on the western
portion of the Philippines and is one of the northern towns of the Province of Palawan.
It is bounded on the north by the Municipality of El Nido, on the south by the
Municipalities of Roxas and Dumaran and on the southwest by the Municipality of San
Vicente.
As a thriving municipality, one of Taytay’s primary objectives in terms of economic
development is an increase of twenty percent (20%) in the income of its farmers and
fisher folks. The Municipality envisions that by the end of 2016, one hundred (100)
kilometers of Farm to Market Roads (FMRs) have been rehabilitated and maintained.
1.3.4. Roxas, Palawan
Roxas is a first class municipality geographically located 147 kilometers
north of Puerto Princesa City. It covers a total land area of 117,347 hectares and
is politically subdivided into thirty-one (31) barangays. Recent estimates indicate
that around 70 to 80 percent of the total households are engaged in farming
activities. Most of the arable land is being devoted in the production of vital
crops such as palay, corn and vegetables either for domestic consumption or for
trade to municipalities in the province. Other agricultural products include
permanent fruit crops such as coconut, cashew, mangoes, citrus and coffee.
1.3.5. Sofronio Española, Palawan
The Municipality of Sofronio Española is a first class municipality of the Province of Palawan, it is composed of nine (9) barangays and has a total land area of 47,391 hectares. The municipality has a total agricultural area of 11,367 hectares or 23.99% of the total land area, of which 7,292.865 hectares or 64.16% has been cultivated. The widest cultivated land is located in Barangay Panitian constituting 21% of the total agricultural land of the municipality. The major crops grown in the municipality are rice, coconut and corn.
3
1.3.6. Brooke’s Point, Palawan
The Municipality of Brooke’s Point is situated in the south-eastern section
of Palawan Island, approximately 215 kilometres (134 mi) from Puerto Princesa
City. It has a total land area of 85,064.90 hectares (210,199.9 acres) stretching
about 20 kilometres (12 mi) along the length of Palawan. Brooke's Point is one
of Palawan's main economic centers outside Puerto Princesa, along with Narra,
Coron and Cuyo.
The Municipality's economy is primarily based on agriculture. It produces
great quantity of rice, copra and corn. And many fruits and vegetables grow in
abundance in the area. The Municipality also caters to the palm oil industry
which is headquartered in Brgy. Mainit in the south. Unlike most of Palawans'
municipalities, Brooke's Point does not have white and pristine beaches that
draws local and foreign tourist. But because of the abundant freshwater
resources, the Municipality is one of the most productive in the province in
terms of agriculture.
1.3.7. Bataraza, Palawan
The Municipality of Bataraza is located on the southernmost part
of Palawan Island, with a total land area of 72,622 hectares and approximately
225 kilometres (140 mi) from Puerto Princesa City or about five to six hours
travel by land. The main industries of Bataraza include farming, fishing, and
nickel mining and processing.
The agriculture and fishery industry contributes to the economy of the
Municipality. But the existing roads linking the agriculture and fisheries
production sites and post-harvest facilities to the market and arterial roads and
highways are still the concern of the Municipality particularly those which are
located in remote areas.
1.4. Farm to Market Road
Farm to Market Roads (FMRs) play a significant role in the livelihood and food
security of farmers and the entire country's rural economy. FMRs improve the mobility
of people, goods, and services. They provide access to employment opportunities and
basic social services such as schools and health centers.
4
FMRs are the foundation of modern agriculture. FMRs provide market access to
farmers, which can then motivate the latter to plant more, ultimately increasing their
production and income. FMRs serve as catalysts in improving rural economy.
FMRs can increase local trade and productivity, reduce transportation costs of
farm input and output, and minimize post-harvest losses. They connect farms and
coastal areas to main roads, hence promoting agro-tourism.
Rural transport not only concerns the movement of farm produce, but also helps
in household tasks such as procuring food, water, and fuel wood. When deliveries are
delayed, the quality of crops drop, as well as their prices and sales – impacting the
income of farmers and the food security of their families.
Some farmers would just let their products rot than spend for transportation. This
impacts both producers and consumers.
Rural roads are also necessary for communication. In their absence, people
become isolated, less participative in information exchange, and more vulnerable to
deceptive market deals.
5
For audits which adopt the “Citizen Participatory Audit” (CPA) approach, the
Commission on Audit selects projects/services of the government that are close to the heart of the people, since the audit is conducted with direct involvement of citizens.
The focus of the Citizen Participatory Audit was the Farm to Market Roads that
are locally funded by the Local Government Units of the Province of Palawan.
2.0 AUDIT FOCUS
6
2.1. Concreting of Kamuning Road Phase II, Barangay Kamuning, Puerto Princesa
City, Palawan
The Barangay Kamuning Farm to Market road is 40 kilometers away from the City Proper and the last barangay at the southern portion of Puerto Princesa City. It is bounded on the north by the Sulu Sea, on the east by Barangay Inagawan, on the west by Barangay Isaub, Aborlan and on the south by Barangay Inagawan-Sub. Most of the areas are flat terrain suitable for rice, corn and coconut plantation.
Thus, the City Government recognized the need to improve the welfare of
its constituents by providing for the concreting of the farm to market roads that will help in the easy transport of their crops and products.
The Annual Investment Plan of the year 2012, the City Government started
the Kamuning Farm to Market Road Phase I through Appropriations Ordinance No. 430-2011 amounting to ₱11,908,803.06, which covered 1.28 kilometers in length representing the starting station of the project up to halfway of the total distance from the national highway. In General Appropriation Ordinance No. 1-2013 for 2014 Annual General Fund Budget of twenty percent development fund, another appropriation amounting to ₱7,895,000.00 was provided for the completion of the Kamuning Farm to Market Road Phase 2 of the same road which covered 739 meters in length, 5.0 meter width and 0.20 meter thick, reaching the national highway.
The Phase II of the FMR project was awarded to the contractor E.V. Villaos
Trading & Construction with contract cost amounting to ₱7,800,438.81. The contract time was 90 days effective March 16, 2014 and ending on June 14, 2014.
7
GROUND TRUTHING
Island: Luzon Province: Palawan City: Puerto Princesa
Barangay: Kamuning Contract Amount: ₱ 7,800,438.81
Geographic Coordinates (Starting Point)
Latitude : 9°31'44.11"N
Longitude : 118°37'19.71"E
Length: 739 meters
Source of Fund: 20% Development Fund for CY 2014
Travel Description and Landmarks:
8
2.2. Concreting of Inogbong Road, Bataraza, Palawan
The “Concreting of Ingobong Seashore Road, Bataraza, Palawan” is an
infrastructure project with an Approved Budget for the Contract (ABC) of
₱4,823,152.88 implemented by contract and funded under the 20%
Development Fund on CY 2013. The project was awarded to E.C. Timbancaya
Enterprise for its bid amount of ₱4,817,585.00. Although not specifically
identified as Farm-to-Market Road (FMR) in the Annual Investment Plan, the
project was determined and reported by the Municipal Engineer as FMR project.
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: Bataraza
Barangay: Inogbong Contract Amount: ₱ 4,817,585.00
Geographic Coordinates (Starting Point)
Latitude : 8°41'13.26"N
Longitude : 117°39'7.02"E
Length: 400 meters
Source of Fund: 20% Development Fund for CY 2013
Travel Description and Landmarks:
9
2.3. Rehabilitation of Malatgao-Culandanum-Panas-Linao Road, Bataraza, Palawan
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: Bataraza
Barangays: Malatgao, Culandanum, Panas,
Linao
Contract Amount:
₱9,897,661.97
Geographic Coordinates (Starting Point)
Latitude : 8°37'44.36"N
Longitude : 117°28'7.70"E
Length: 10.5 kilometers
Source of Fund: 20% Development Fund for CY 2013
Travel Description and Landmarks:
10
2.4. Graveling of Loblob - Calitang Road in Bgy. Bucana, El Nido, Palawan
This is a project funded from the 20% Development Fund of calendar year
2013 implemented “by administration”. Loblob-Calitang Road is a 4 kilometer
access road to Sitio Loblob of Barangay Pasadeña and Sitio Calitang of Barangay
Bucana from the national road. Sitio Loblob is an hour ride from the town
proper. Agricultural products in this area consist of rice, cashew, coconut and
mango.
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: El Nido
Barangay: Pasadeña and Bucana Project Cost: ₱170,479.82
Geographic Coordinates (Starting Point)
Latitude : 11°17'47.75"N
Longitude : 119°25'40.25"E
Length: 4 kilometers
Source of Fund: 20% Development Fund for CY 2013
Travel Description and Landmarks:
11
2.5. Construction/Rehabilitation and Maintenance of Local Roads, Barangay
Poblacion to Mauringen, Araceli, Palawan
This project was funded out of the 20% Development Fund of calendar year
2014 implemented “by administration”. The project covers the 33 kilometer
main road of the island from the town proper of Barangay Poblacion up to Sitio
Baing of Barangay Mauringen. Agricultural products in this area include rice,
cashew, coconut and vegetables.
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: Araceli
Barangay: Mauringen Project Cost: ₱898,539.56
Geographic Coordinates (Starting Point)
Latitude : 10°33'2.25"N
Longitude : 119°59'10.87"E
Length: 33 kilometers
Source of Fund: 20% Development Fund for CY 2014
Travel Description and Landmarks:
12
2.6. Construction of Nalbot-Old Guinlo Road Phase I and II, Bgy. Poblacion – Old
Guinlo, Taytay, Palawan
The FMR Sitio Nalbot to Barangay Old Guinlo Project was started in the
year 2010. It is the opening or piloting of roads from Palawan North Highway So.
Nalbot to Barangay Old Guinlo and is approximately sixteen (16) kilometers long.
The FMR project aims to shorten the route in transporting farm and marine
produce from Barangay Old Guinlo and its neighboring barangays to the
Poblacion. Barangay Old Guinlo is one of the barangays located in the
Malampaya, the Fishing Ground of the Philippines.
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: Taytay
Barangay: Poblacion – Old Guinlo
Project Cost:
Phase I : ₱ 2,000,000.00
Phase II: ₱ 1,000,000.00
Geographic Coordinates (Starting Point)
Latitude : 10°50'23.16"N
Longitude : 119°27'40.09"E
Length: 16 kilometers
Source of Fund: 20% Development Fund for CYs 2012 and 2013
Travel Description and Landmarks:
13
2.7. Development of Marirong to Cayasan FMR in Bgy. Nicanor Zabala, Roxas,
Palawan
The Marirong to Cayasan farm-to-market road was a project funded out of
the 20% Development Fund of calendar year 2012 and implemented “by
administration” on January 2015. Sitio Marirong of Bgy. Nicanor Zabala, about
thirty (30) minutes travel from town proper, is an access road that connects the
National Road to Cayasan Falls.
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: Roxas
Barangay: Nicanor Zabala Project Cost: ₱102,216.80
Geographic Coordinates (Starting Point)
Latitude : 10°8'11.25"N
Longitude : 119°11'54.50"E
Length: 1.24 kilometers
Source of Fund: 20% Development Fund for CY 2012
Travel Description and Landmarks:
14
2.8. Maintenance of Iniaran FMR, Bgy. Labog, Sofronio Española, Palawan
The municipality is also a good source of other marine products such as crabs and shrimps. It has 152 hectares of fishponds and 4 hectares of seaweed farms.
In CY 2002, The Asian Development Bank (ADB) assisted Agrarian Reform Community Program (ARCP) benefitted the Labog Iniaran Reform Community (Labog ARC) by granting the Iniaran Farm to Market Road project with the municipality providing its equity of P1,493,897.83 for its construction.
GROUND TRUTHING
Province: Palawan Municipality: Sofronio Española
Barangay: Labog Project Cost: ₱75,000.00
Geographic Coordinates (Starting Point)
Latitude : 9°3'43.44"N
Longitude : 118°3'38.86"E
Length: 4.8 kilometers
Source of Fund: 20% Development Fund for CY 2014
Travel Description and Landmarks:
15
2.9. Maintenance of Kanangkaan FMR, Bgy. Punang, Sofronio Espanola, Palawan
The Kanangkaan road at Barangay Punang was one of the projects of the
Department of Agrarian Reform under the Agrarian Reform Infrastructure
Support Project II (ARISP) wherein, as its share, the Municipality committed to
maintain the said road after its completion.
GROUND TRUTHING
Province: Palawan Municipality: Sofronio Española
Barangay: Punang Project Cost: ₱63,500.00
Geographic Coordinates (Starting Point)
Latitude : 9°0'56.80"N
Longitude : 118°3'17.72"E
Length: 3.7 kilometers
Source of Fund: 20% Development Fund for CY 2014
Travel Description and Landmarks:
16
2.10. Improvement and Rehabilitation of Bgy. Kalatagbak, Quezon, Palawan
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: Quezon
Barangay: Kalatagbak Project Cost: ₱ 953,390.37
Geographic Coordinates (Starting Point)
Latitude : 9°15'20.32"N
Longitude : 118°5'59.19"E
Length: 5 kilometers
Source of Fund: 20% Development Fund for CY 2014
Travel Description and Landmarks:
17
2.11. Regravelling of Sitio Mati and Paratungon roads, Barangay Pangobilian,
Brooke’s Point, Palawan
The project covers re-graveling of 3,240 meter-roads in two (2) separate
locations at Barangay Pangobilian namely Sitio Paratungon and Sito Mati, both of
which were implemented by Administration. Although not specifically identified
as Farm-to-Market Road (FMR) in the Annual Investment Plan, the project was
determined and reported by the Municipal Engineer as FMR project in the list
submitted for purposes of CPA.
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: Quezon
Barangay: Pangobilian Project Cost: ₱ 200,000.00
Geographic Coordinates (Starting Point)
Sitio Mati
Latitude : 8°48'24.93"N
Longitude : 117°48'7.74"E
Sitio Paratungon
Latitude : 8°47'41.83"N
Longitude : 117°49'59.28"E
Source of Fund: 20% Development Fund for CY 2013
Travel Description and Landmarks:
Sitio Mati
18
Sitio Paratungon
The citizen participatory audit was conducted to:
3.1. Validate the existence of the reported accomplishments;
3.2. Validate compliance of reported accomplishments with the approved plans and specifications; and
3.3. Validate if reported accomplishments are in accordance with the contract schedule.
3.4. Ascertain the existence of appropriations for the FMR projects and to determine whether the obligation did not exceed the allocations for the same.
3.5. Determine whether the LGU complied with the detailed engineering requirements of Annex A of the Revised IRR of RA No. 9184.
3.6. Determine whether the procurement of materials and labor is in accordance with the provisions of RA No. 9184 and its Revised IRR.
3.7. Determine the reasonableness of the expenditures for the FMR project.
3.8. Determine the existing condition of the project.
3.9. Determine whether the FMR project attained its main objective of providing a safe and convenient transport of agricultural and fishery products from production areas to the nearest existing roadway system that provides access to the nearest market center.
3.0 AUDIT OBJECTIVES
19
The standards/benchmarks used as basis for the validation were: 4.1. Section 62.2.2.1 of the Revised Implementing Rules and Regulations (R-IRR) of
Republic Act (R.A.) No. 9184 The contractor shall undertake the repair works, at his own expense,
of any damage to the infrastructure on account of the use of materials or inferior quality, within ninety (90) days from the time the Head of the Procuring Entity has issued an order to undertake repair. In case of failure or refusal to comply with this mandate, the procuring entity shall undertake such repair and shall be entitled to full reimbursement of expenses incurred upon demand.
4.2. Section 2 of the Presidential Decree (P.D.) No. 1445
It is the declared policy of the state that all resources of the
government shall be managed, expended or utilized in accordance with laws and regulations and safeguarded against loss or wastage through illegal or improper disposition for the purpose of ensuring efficiency, economy and effectiveness in the operations of the government.
4.3. DPWH Order No. 29 series of 2011 dated May 16, 2011
Revised guidelines on the Preparation of Approved Budget for the Contract
provides for laboratory tests, the cost of which, is part of the indirect cost component of the ABC.
4.4. Procurement Manual for Local Government Units, Volume III, Infrastructure
Projects issued by the Government Procurement Policy Board (GPPB) Indicates the scope of the right of the Procuring Entity to inspect the
infrastructure project procured and conduct material tests, to ensure that all materials and workmanship are in accordance with the requirements of the contract.
It was further stated in the said Manual that in case the materials and
workmanship were found defective or not in accordance with the specifications, the Procuring Entity must notify the Contractor immediately of such rejection1.
4.5. Approved Budget for the Contract (ABC)
1 Page 64, Right of Inspection of the LGU, Procurement Manual for LGUs, Volume III
4.0 AUDIT CRITERIA
20
Refers to the budget for the contract duly approved by the Sanggunian. The ABC shall be the upper limit or ceiling for acceptable bid prices.
4.6. Section 2.2.3 of COA Circular No. 2013-004 dated January 30, 2013
For infrastructure projects, a tarpaulin signboard must be suitable framed
for outdoor display at the project location, and shall be posted as soon as the award has been made. The design and format of the tarpaulin, as shown in Annex “A,” shall have the following specifications:
Tarpaulin, white, 8 ft x 8 ft Resolution: 70 dpi Font: Helvetica Font Size: Main Information – 3” Sub-Information – 1” Font Color: Black
4.7. Government Procurement Policy Board (GPPB) Resolution No. 018-2006: Approving and Adopting the Revised Guidelines for the Implementation of Infrastructure Projects by Administration.
4.8. Republic Act No. 8435 or the “Agriculture and Fisheries Modernization Act of 1997;
4.9. Republic Act No. 10601 or the “Agricultural and Fisheries Mechanization (AFMech) Law”;
4.10. Philippine Agricultural Engineering Standards for Farm to Market Roads (PAES 421:2009);
4.11. Republic Act No. 7160 or the “Local Government Code of 1991”;
4.12. Republic Act No. 9184 or the “Government Procurement Reform Act” and its Revised Implementing Rules and Regulation (RIRR);
4.13. Government Procurement Policy Board (GPPB) Resolution No. 018-2006: Approving and Adopting the Revised Guidelines for the Implementation of Infrastructure Projects by Administration;
4.14. COA Circular No. 2012-003 dated October 29, 2012 re: Updated Guidelines for the Prevention and Disallowance of Irregular, Unnecessary, Excessive, Extravagant and Unconscionable Expenditures;
4.15. Generally accepted principles and practices of accounting, sound management and fiscal administration;
21
4.16. Approved plans and specifications, detailed breakdown of project cost, and project implementation schedule of the particular projects subject to the audit.
The Audit Team went through the following activities:
Compliance Audit:
5.1. Identification of applicable design standards for FMR projects and understanding the following laws and rules and regulations:
a. DPWH Department Order No. 11 for FMR construction projects implemented from Calendar Year 2014 and onwards; or
b. PAES 421:2009 for FMR projects not covered by DPWH DO No. 11;
5.2. Obtaining the following relevant documents and information regarding the FMR:
a. Approved Plans and Specifications;
b. Approved and updated Program of Works and Detailed Estimates;
c. Approved Budget for the Contract;
d. Contract Agreement in case of straight contract;
e. As-Built Plan;
f. Latest Statement of Work Accomplished (SWA);
g. Previous Inspection Reports;
h. Disbursement Vouchers covering the expenditures incurred for the projects;
i. Annual Investment Program;
j. Annual Budget or Local Expenditure Program;
5.3. Communicating to the LGU the deficiencies through Audit Observation Memorandum (AOM), if any;
Technical Evaluation and Inspection:
5.4. Evaluation of the approved plans and specifications against applicable design standards;
5.5. Comparison of reported accomplishments against the approved plans and specifications;
5.0 AUDIT METHODOLOGY
22
5.6. Ocular site inspection on the FMR project, which involve the following activities among others: a. Measurement and recording of road dimensions;
b. Taking of photographs;
c. Observation of the project’s current physical condition and the apparent irregularities, if any; and
d. Geo-tagging of the FMR project;
5.7. Computation of quantities of project accomplishments and their costs, aligned with the results of the Technical Evaluation of the projects;
5.8. Comparing the results of inspection against reported accomplishments and taking note of deviations;
5.9. Analysis of the effects of project deviations to the project cost;
5.10. Comparison of the actual time of completion against the project implementation schedule and taking note if there is delay in completion;
5.11. Analysis of the effects of delay on the project completion, and computation of liquidated damages, if any;
Performance Audit:
5.12. Interview with the residents in the area;
5.13. Analysis of the information gathered through interview;
Financial Audit:
5.14. Comparing the fund appropriations of the project against the obligations and actual expenditures incurred;
5.15. Checking of mathematical accuracy of the actual expenditures;
5.16. Verifying the correctness of accounting entries;
5.17. Tracing of accounting entries from Journal Entry Vouchers (JEV) to Accounting Journals and to the Ledgers;
5.18. Checking if all disbursements on FMR projects as of year-end were recorded in the books of that year;
5.19. Analyzing the effects of noted deficiencies on the presentation of financial statement.
23
6.0 AUDIT PERIOD
The Citizen Participatory Audit planning and fieldwork were conducted from
December 2014 to January 2015. Data processing and analysis were conducted from January to June 2015.
Location Inspection Date Puerto Princesa City Jan. 20, 2015 Taytay, Palawan Feb. 4, 2015 Roxas, Palawan Feb. 4, 2015 El Nido, Palawan Feb. 6, 2015 Araceli, Palawan Feb. 10, 2015 Brooke’s Point, Palawan Feb. 2 - 3, 2015 Sofronio Española Jan. 22, 2015
7.1. Implementation of FMR by Contract
7.1.1. Concreting of Kamuning Road Phase II, Barangay Kamuning, Puerto Princesa
City, Palawan
The concreting of Kamuning Road - Phase II Farm to Market Road (FMR) amounting to ₱7,800,438.00 resulted to deficiencies of government funds totaling ₱2,082,277.23.
Section 62.2.2.1 of R-IRR of R.A. No. 9184 states that:
The contractor shall undertake the repair works, at his own
expense, of any damage to the infrastructure on account of the use of
materials or inferior quality, within ninety (90) days from the time the
Head of the Procuring Entity has issued an order to undertake repair.
In case of failure or refusal to comply with this mandate, the procuring
entity shall undertake such repair and shall be entitled to full
reimbursement of expenses incurred upon demand.
Section 2 of the Presidential Decree No. 1445 provides that
It is a declared policy of the state that all resources of the
government shall be managed, expended or utilized in accordance
with laws and regulations and safeguarded against loss or wastage
through illegal or improper disposition for the purpose of ensuring
efficiency, economy and effectiveness in the operations of the
government.
7.0 AUDIT RESULTS
24
Inspection of the project conducted by the Citizen Participatory Audit
(CPA) Team that includes the COA engineers and members of the CSOs and a
representative from the City Engineering Office on January 20, 2015 disclosed
various defects/deficiencies (further details shown in Annex 1A), as follows:
7.1.1.1. Tarpaulin signboard did not comply with the prescribed format of Section 2.2.3 of COA Circular No. 2013-004 dated January 30, 2013 which resulted to a discrepancy amounting to ₱13,401.25 ;
7.1.1.2. The project was already declared 100% completed based on the Accomplishment Report of the City Engineering Department as of December 29, 2014 but not yet actually completed upon actual inspection of the CPA Team on January 20, 2015. The project should have been completed on June 14, 2014 but there were still laborers working on the pavement putting asphalt sealant on weakened joints and in between the cracks that were visible when the Team arrived, which resulted to a time delay of 220 calendar days or liquidated damages amounting to ₱326,058.31;
The construction time was beyond the construction period of
ninety (90) days as stipulated in the contract. Duly approved suspension and/or extension of work order were not submitted despite demands by the Audit Team.
25
7.1.1.3. The contractor put up a makeshift storeroom only instead of constructing field office/bunkhouse to store the construction materials, which resulted to a discrepancy of ₱68,178.88;
7.1.1.4. The road shoulders on both sides of the concrete pavement
throughout the project were made up of river stones instead of the required Aggregate Surface Course (Item 300) as required in the Program of Work and detailed plan, which resulted to a deficiency of ₱1,052,209.24;
7.1.1.5. There was only one line barrel culvert constructed instead of two (2)-line RCPC cross drain with headwall as required on the submitted Program of Works, thus resulted to a deficiency of ₱80,081.62;
7.1.1.6. Serious transverse cracks, uneven brooming and absence of asphalt filler involving 2 concrete blocks at Sta. 0+089 (Latitude: 9°31'43.99"N, Longitude: 118°37'16.82"E), thus resulted to a deficiency of ₱37,403.33;
26
7.1.1.7. Side cracks about five (5) meter in length, uneven brooming, vehicle related concrete scratches and unsealed weakened joints at Sta. 0+123 (Latitude: 9°31'44.06"N, Longitude: 118°37'15.86"E), which calls for the removal of two (2) concrete blocks amounting to ₱37,403.33;
27
7.1.1.8. Settlement of about two (2) concrete blocks coupled with longitudinal cracks beginning at Sta. 0+156 (Latitude: 9°31'44.07"N, Longitude: 118°37'15.33"E), which resulted to a deficiency of ₱37,403.33;
7.1.1.9. Serious transversal cracks located within the middle third of two (2) concrete blocks, absence of asphalt filler, uneven brooming and scaling at Sta. 0+221 (Latitude: 9°31'44.27"N, Longitude: 118°37'12.40"E), which resulted to a deficiency of ₱37,403.33;
28
7.1.1.10. Multiple road defects such as serious scaling, poke marks, absence of asphalt filler, spalling, uneven brooming and serious longitudinal cracks running diagonally in a concrete block were observed from the beginning of Sta. 0+249 (Latitude: 9°31'44.35"N, Longitude: 118°37'11.24"E), which resulted to a deficiency of ₱18,701.66;
29
7.1.1.11. Spalling, serious scaling involving two (2) concrete blocks, longitudinal cracks in single concrete block, vehicle related road scratches, uneven brooming of concrete and unsealed weakened joints at Sta. 0+313 (Latitude: 9°31'44.50"N, Longitude: 118°37'8.58"E), which resulted to a deficiency of ₱56,104.98;
7.1.1.12. Major scaling, longitudinal and transverse cracks involving two (2) concrete blocks; poke marks, unsealed weakened joints, vehicle related scratches and spalling at Sta. 0+402 (Latitude: 9°31'44.69"N, Longitude: 118°37'6.41"E), which resulted to a deficiency of ₱224,419.98;
30
7.1.1.13. Serious transverse cracks located within the middle of third of two (2) concrete blocks, scaling, uneven brooming and absence of asphalt filler at Sta. 0+427 (Latitude: 9°31'44.76"N, Longitude: 118°37'5.61"E), which resulted to a deficiency of ₱37,403.33;
7.1.1.13. Transverse cracks located within the middle third of the concrete block, scaling and unsealed weakened joints at Sta. 0+600 (Latitude: 9°31'45.04"N, Longitude: 118°37'0.31"E), which resulted to a deficiency of ₱37,403.33;
7.1.1.14. One (1) concrete block with serious scaling, transversal cracks, spalling, uneven brooming and unsealed weakened joints at Sta. 0+703 (Latitude: 9°31'45.48"N, Longitude: 118°36'56.98"E), which resulted to a deficiency of ₱18,701.66;
31
7.1.1.15. Stones of about four (4) inches in diameter were observed exposed on the pavement surfaces which indicate that the used of incorrect sizes of gravel as required in the construction of Item 311 – PCCP (Portland Cement Concrete Pavement) located at the beginning of Sta. 0 + 453/493;
32
7.1.1.16. Major scaling, wide transverse/longitudinal cracks and vehicle related scratches running across and along the concrete pavement at intermittent sections of the road ;
Random Samplings were done to verify the thickness of Item 311-RCCP
by digging and removing portion of the road shoulders The project has
complied with the standard thickness of 0.20 meter.
33
As of this date, Management has not yet caused the rectification of these
defects, despite available remedies under R.A. No. 9184 and its R-IRR.
These remedies are summarized as follows:
62.2.2. One (1) year from project completion up to final acceptance or the
defects liability period.
62.2.2.1. The contractor shall undertake the repair works, at his own
expense, of any damage to the infrastructure on account of the use
of materials of inferior quality, within ninety (90) days from the
time the Head of the Procuring Entity has issued an order to
undertake repair. In case of failure or refusal to comply with this
mandate, the procuring entity shall undertake such repair works
and shall be entitled to full reimbursement of expenses incurred
therein upon demand.
62.2.2.2. The defects liability period shall be covered by the Performance
Security of the contractor required in Section 39.1 of this IRR, which
shall guarantee that the contractor performs his responsibilities
stated in the immediately preceding Section. If the contractor fails
to comply with its obligations under Section 62.2.2.1 of this IRR, the
procuring entity shall forfeit its performance security, subject its
property(ies) to attachment or garnishment proceedings, and
perpetually disqualify it from participating in any public bidding. All
payables of the GOP in his favor shall be offset to recover the costs.
With respect to the quality of materials and workmanship the following
guidelines were issued to ensure project quality:
DPWH Order No. 29 series of 2011 dated May 16, 2011, re: Revised Guidelines on the Preparation of Approved Budget for the Contract (ABC), provides for laboratory tests, the cost of which, is part of the indirect cost component of the ABC;
Procurement Manual for Local Government Units (Volume III), GPPB, indicates the scope of the right of the Procuring Entity to inspect the infrastructure project procured and conduct material tests, to ensure that all materials and workmanship are in accordance with the requirements of the contract.
It was further stated in the said Manual that in case the materials and
workmanship were found defective or not in accordance with the
34
specifications, the Procuring Entity must notify the Contractor immediately of
such rejection.
Based on the above guidelines, the agency is equipped/backed-up with
the necessary laws, rules and regulations to ensure the quality of work done
and/or the rectification of defects in the project by the contractors. Non-
availment of these remedies in due time will result in deprivation of the public
of the maximum use and full benefits of the project, and wastage of
government funds and property.
Based on the noted deficiencies, the submitted Field Density Test and
Compaction Test could not be relied upon by the Audit Team, thus, we
requested that coring test be conducted to assure that quality materials were
used. However, the Management had not yet arranged for the coring
equipment to be used and the schedule of testing.
7.1.2. Concreting of Inogbong Road, Bataraza, Palawan
7.1.2.1. The road concreting project minimized the difficulty of farmers within the
area in transporting their farm produce to the market.
The Inogbong Road links the National Highway to the seashore and
traverses for the most part a span of rice fields. The road has rough surface
covered mostly by loose gravel and as such, the transport of farm produce to
the market was difficult particularly during rainy season.
With the concreting of the Inogbong Road, the transport of farm
produce was somehow made easier. The two-lane concrete road provided
easy and comfortable movement of vehicles.
But the project has minimal or limited benefits in that the road
concreting extends only to 400 meters from the National Highway. As shown
in the illustration below, the concrete road (marked as red) takes up fourteen
35
percent (14%) of the entire length of the Inogbong road of approximately
2,774 meters. Thus, farmers with rice fields located in the interior still have
difficulty in mobilizing their products due to the existing road condition.
Ocular inspection likewise disclosed that there were only few farmers
and fisher folks within the area who have access to the road.
7.1.2.2. There were defects noted during the inspection of the Inogbong Road
concreting project which, if not corrected, may eventually compromise the
safety of the riding public and cause damage to the farm produce during
transport.
The concreting project of the road to Inogbong seashore was
completed on March 4, 2014 per certification of the Municipal Engineer
dated March 5, 2014. Almost a year after, the CPA Team conducted an
inspection of the project on February 4, 2015 and noted various defects as
follows:
e. The concrete surface showed light to severe scaling throughout the 400-meter road. Scaling is a local flaking or peeling of a finished surface of hardened concrete which generally starts as localized small patches which later may merge and extend to expose large areas. Light scaling does not expose the coarse aggregate. In contrast, moderate scaling exposes the aggregate and may involve loss of the surface mortar. In severe scaling, more surface has been lost and the aggregate has been clearly exposed and stands out.
36
Light scaling
Moderate scaling
Severe scaling Severe Scaling
f. Minor cracks are beginning to develop.
37
g. The scaling or patches on the pavement showed impurities or presence of objects such as wood in the concrete mixtures.
38
h. No concrete/asphalt sealant at construction joints.
i. Improper brooming affected the roughness of the surface.
The defects were noted or discovered within one (1) year from the date
of the completion, and thus, within the defects liability period and still
covered by the performance security posted by the contractor, E.C.
Timbancaya Enterprises. The Municipal Engineer was verbally instructed by
the COA TAS during inspection to inform the Contractor to address the noted
defects as they are still within the defects liability period.
7.1.2.3. Of the total project cost of ₱4,817,585.00, the funding source for the
amount of ₱2,408,792.50 paid during CY 2014 is doubtful due to lack of
continuing appropriations specifically allocated for the project.
The road concreting project was funded under the 20% Development
Fund for CY 2013. The project was started in CY 2013 but was completed only
in CY 2014. The total project cost of ₱4,817,585.00 was paid as follows :
Date of ObR Charges in ObR Obligation
Request (ObR) No.
Particulars (% of
Accomplishment) Date of OR Amount
Dec. 2, 2013 20% DF – 2013 300-2013-12-5050 First Billing (50%) Dec. 5, 2013 2,408,792.50
Feb. 11, 2014 20% DF – 2013
Continuing
appropriation
300-2014-02-0094 Second Billing
(75%)
Mar. 12, 2014 1,204,396.25
Mar. 20, 2014 20% DF – 2013
Continuing
appropriation
300-2014-03-0593 Final Billing (100%) Mar. 12, 2014 1,204,396.25
Total 4,817,585.00
39
As shown above, payments for the second and final billing in CY 2014
totaling ₱2,408,792.50 were charged to the “20% DF–2013 Continuing
Appropriation” and duly obligated during CY 2014. However, review of the
budget reports such as the Status of Appropriations, Allotments, Obligations
and Balances (SAAOB) disclosed that there were no continuing
appropriations allocated specifically for the concreting of Inogbong seashore
road for CY 2013. The Budget Officer neither reported any obligation in
SAAOB for continuing appropriations representing payment for the second
and final billing in CY 2014 totaling ₱2,408,792.50 although the Obligation
Requests (ObR) attached to the payments showed otherwise.
Section 305 of the Local Government Code of 1991 (RA 7160) states
that “No money shall be paid out of the local treasury or depository except in
pursuance of an appropriations ordinance or law.”
7.1.2.4. The Contractor failed to comply with the project implementation period,
thereby incurring a delay of 13 calendar days.
The contract for concreting of the 400-meter road to Inogbong
seashore was awarded on November 7, 2013 to E. C. Timbancaya Enterprises
declared by the BAC as the single calculated and responsive bidder with the
bid amount of ₱4,817,585.00. The contractor was given notice to commence
the work in 7 days after its receipt of the Notice to Proceed (NTP) on
November 12, 2013. Since the contract duration was for 90 days as indicated
in the Invitation to Bid, the contract time should have started on November
19, 2013 and expected to be completed on February 19, 2014. But as
certified by the Municipal Engineer, the project was completed only on
March 4, 2014, without any request for extension, thereby incurring 13
calendar days of delay.
Section 68 of RA 9184 requires that liquidated damages equivalent to
1/10 of one percent (0.1%) of the cost of unperformed portion shall be paid
by the contractor for every day of delay. Hence, the contractor is liable to
pay for the liquidated damages for such delay.
40
7.1.2.5. The contract agreement does not contain a provision on liquidated
damages contrary to Section 68 of RA 9184.
Section 68 of RA 9184 states that “All contracts executed in accordance
with the Act and this IRR shall contain provision on liquidated damages which
shall be payable by the contractor in case of breach thereof”.
Contrary to the foregoing, the contract agreement executed by and
between the Municipal Government of Bataraza and E.C. Timbancaya
Enterprise does not contain any provision on the imposition of liquidated
damages in case of incurrence of delay. Said contract, however, deemed to
form, and be read and construed as part of the agreement the document
“General and Special Conditions of Contract” which include provisions on
liquidated damages, thus, the Contractor shall still be held liable for such
delay.
7.1.2.6. Non-submission of As-Built Plan and Clearance from the Provincial
Treasurer on payment of sand and gravel fees contrary to COA Circular No.
2012-001.
Item 9.1.1.4 of COA Circular No. 2012-001 dated June 14, 2012 requires
among others the following documents to support the claim for final
payment of infrastructure projects:
1. As-Built Plan 2. Clearance from the Provincial Treasurer that the corresponding sand and
gravel fees have been paid (DPWH Department Order No. 109 s. 1993 dated May 4, 1993 and DO No. 119 s. 1993 dated May 11, 1993)
However, the documents supporting the final payment for the project
do not include the As-Built Plan that should have been submitted by the
Contractor to validate the actual work accomplished and determine any
deviation or variation from the original plan/design. The required Clearance
from the Provincial Treasurer was neither submitted to support the
Contractor’s claim for final payment.
7.1.2.7. Non-observance of the “one-year period after the completion of the
project” in the issuance of the final acceptance of the project.
The LGU Procurement Manual, Volume 3, states that a warranty is
required to ensure that the contractor will correct structural defects and
failures. It should be noted that a one-year period after the completion of
41
the project, called the defects liability period, is observed until final
acceptance by the LGU.
Contrary to the one-year period, the Municipal Mayor issued a
certificate of acceptance dated March 6, 2014, only two (2) days after the
concreting project was completed on March 4, 2014. It should be the
contractor, not the Municipality, who shall assume full responsibility for any
damage or destruction of the works except those occasioned by force
majeure, from the time the project construction was completed up to the
final acceptance of the Municipality.
7.1.2.8. The contract agreement erroneously indicated the Approved Budget for the
Contract (ABC) of ₱4,823,152.88 as the amount to be paid to the Contractor
for the project instead of the bid amount of ₱4,817,585.00.
Pertinent provision in the contract agreement states that:
“WHEREAS, the Entity is desirous that the Contractor execute
Road Concreting 400 mts. to Inogbong Seashore in the
Municipality of Bataraza, Palawan with PhilGEPS ITB Reference
No. 2403419, and the Entity has accepted the Bid for Four Million
Eight Hundred Twenty Three Thousand One Hundred Fifty Two
pesos & 88/100 (PHP 4,823,152.88) by the Contractor for the
execution and completion of such Works and the remedy of any
defects therein.”
The amount of ₱4,823,152.88 cited in the contract to be paid to the
Contractor for the project is the Approved Budget for the Contract (ABC). The
bid amount of the Contractor, E.C. Timbancaya, is actually for ₱4,817,585.00
only. Despite this error, the Municipality was able to pay the Contractor the
correct amount of ₱4,817,585.00.E
7.1.3. Improvement of Malatgao-Culandanum-Panas-Linao Road, Bataraza,
Palawan
7.1.3.1. The contractor failed to comply with the project implementation period
stated in the Contract Agreement, resulting to a delay of 200 calendar days.
Item No. 9 of the Contract Agreement between the Provincial
Government of Palawan and Kim Harrold Trading, Manufacturing &
Construction for the Improvement of Malatgao-Culandanum-Panas-Linao
Road, Bataraza, Palawan states that:
42
The Contractor further agrees to begin work on the Project
within seven (7) days following the date of the NOTICE TO
PROCEED, and to complete the same within 120 calendar days,
including Sundays and legal holidays. The contract time shall begin
on the seventh day following the date of the NOTICE TO PROCEED
unless additional time shall be allowed. (emphasis supplied)
The Notice to Proceed was dated February 15, 2013, hence the contract
time of 120 calendar days began on February 22, 2013 and expired on June
22, 2013. However, pertinent records and transaction documents disclosed
that the project was completed only on January 8, 2014, which was 200
calendar days beyond the contract time.
Review of transaction documents showed that no work suspension or
time extension orders were issued for the delay of project completion.
Accordingly, the project engineer prepared a report showing a computation
of liquidated damages amounting to ₱91,259.59 (see Appendix 5). The said
amount has been deducted from the payment of final billing.
7.1.3.2. Defects such as damaged box culverts, loose surfacing materials, undefined
earth side ditches and crowning of roadways have been observed during
inspection of the Farm-to-Market Road, contrary to the Detailed
Engineering Plans and Specifications of the project.
The submitted plans and specifications on the Improvement of
Malatgao-Culandanum-Panas-Linao Farm-to-Market Road, Bataraza, Palawan
disclosed the following data:
The project starts at Km. 237 + 500 and ends at Km. 248 + 000 with a
total length of 10.50 km., as per submitted Program of Work by the
Agency.
The said project is a Re-shaping and Re-gravelling of 10.5 kilometer road
and Construction of 4 barrels of Reinforce Concrete Box Culvert, with the
following programmed items:
Item No. Description Quantity Unit
SPCL-1 General Requirements
a. Project Sign Board 2.0 sets
b. Safety and Health 1.0 lot
c. Temporary Bunkhouse 1.0 lot
43
Item No. Description Quantity Unit
SPCL -2 Re-Shaping & Ditching 10.50 Km.
200 Aggregate Sub-Base Course 500.00 cu.m.
201 Aggregate Base Course 2,674.00 cu.m.
SPCL -3 Const. of 4 Barrel RCBC 1.0 unit
The Audit Team conducted ocular inspection of the project on January
27, 2015 and performed actual measurement by using a digital type walking
measure and GPS-enabled android cellular phone for Geo-tagging. Project
Billboard was nowhere to be found at the beginning and end of the project.
According to the project engineer, it might have been dismantled by the local
residence.
The following were data collected during the inspection:
Post Kilometer
Reading Station REMARKS
Km 237+500 0+000 Start of the Project and beginning station of re-
shaping of road, Item 200 and Item 201 , Road
Width= 6.1 m
Km 237 + 580 0+180 Road defect: Intermittent Potholes located with
intervals of about 7m.
Km 237+ 966 0+466 Existing Box Culvert not included in the program of
work
Km 238 + 347 0+847 1st Road Intersection, road with 6.0 width
Km 238 + 780 1+280 Undefined earth side ditches and crowning of
roadway and loosed surfacing materials about 5
meters in road length
Km 239 + 101 1+601 Properly maintained and compacted section of
road, with 6.0m width
Km239 + 378 1+878 Loosed surfacing materials with oversized
aggregates about 5 meters in length, undefined
earth side ditches and crowning of roadway with
6.0m width
Km 239 + 490 1+990 Ascending road leading to mountain, properly
maintained with average width 5.5 meters
Km 240 + 377 2 +877 Surfacing materials Stock pile along the road
intended for maintenance of road
Km 240 + 592 3 + 092 2nd Road Intersection with average width 5.5m
Km 240 + 903 3 + 403 Potholes with impounded water , undefined earth
44
Post Kilometer
Reading Station REMARKS
side ditches and crowning of roadway
Km 242 + 074 4 +574 Kulimbawang Village under Brgy. Kulandanum with
road width of 6.1 m, was properly maintained
with defined earth side ditches and crowing of
road
Km 242 + 349 4 + 849 Start of ascending road , start of road maintenance
with width of 6.0 m
Km242 + 735 5+ 235 Damage Reinforce Concrete Box Culvert with
detached front left wing wall
Km 242 + 749 5 +249 End of road maintenance
Km 243 + 445 5 + 945 Undefined earth side ditches and crowning of
roadway with vegetation on both side of the
road, with 5.5 m width
Km 243 + 780 6 +280 Panas Elementary School, Road were properly
maintained and compacted with 6.0 m width
Km 244 + 000 6 + 500 Undefined earth side ditches and crowning of
roadway with vegetation on both sides of the
road, with 5.5 m width
Km 245 + 512 8 +012 Site of Wooden Bridge
Km 246 + 500 9 +000 Properly maintained and compacted section of
road 6.0 m width
Km 247 + 205 9 +705 Loosed surfacing materials with oversized
aggregates
Km 247 + 500 10 +000 Properly maintained and compacted section of
road with 6.0 m width
Km. 247 + 748 10 + 248 Loosed surfacing materials with oversized
aggregates
Km 247 + 838 10 + 338 Existing Reinforce Concrete Box Culvert
Km 248 + 030 10 + 530 Properly maintained and compacted section of
road, with 6.0m width
Km 248 + 600 11 + 100 Site of Linao Elementary, properly maintained and
compacted section of road , 6.0 m width, End of
Project
The damaged four (4) barrel Reinforce Concrete Box Culverts (6 m x 12
m) at station Km 5+235 has a detached left wing wall from its major
structure and an eroded road approach of about 12.5 sq.m. This may be due
to the various debris that block the opening of RCBC waterways and forcing
45
the water to change course and damaged the said section of the RCBC
approached road.
As per gathered data, the 11,100 linear meters (11.1 Km.) actual length
measured by the team has exceeded the programmed length of 10,500
meters (10.5Km.) and the measured average width of 6 meters conformed
with the programmed width.
The defects noted during actual inspection ranging from loose surfacing
materials, undefined earth side ditches and crowning of roadways, are the
common defects that arise in road re-graveling.
7.1.3.3. The implementation of Malatgao-Culandanum-Panas-Linao Farm-to-Market
Road project greatly improved the travel condition of the riding public and
uplifted the living standards of the residents.
The Malatgao-Culandanum-Panas-Linao Road, Bataraza, Palawan
pertained to a secondary road traversing from the Bataraza-Rizal National
Road starting at Barangay Malatgao, Bataraza through Barangay
Culandanum, Sitio Panas, Linao to Barangay Candawaga, Rizal, Palawan.
The project aimed to be an all-weather road and improve the existing
10.5 kilometers road by re-gravelling, re-shaping and construction of 4
barrels reinforced concrete box culvert. It would shorten the travel distance
from southern municipalities of Brooke’s Point and Bataraza to Municipality
of Rizal, Palawan, making it passable to all types of vehicle and thus,
facilitating the transport of goods and services. It was likewise intended to
uplift the living standards of residents in the concerned Barangays and bring
them into the mainstream of economic development.
Upon inspection, the Audit Team found that the total project length
actually measured 11.1 kilometers.
As per interview, the barangay residents expressed appreciation on the project considering that they no longer have to travel very long distances between the southern municipalities due to road shortcut. All of the respondents found the location and design of the road project to be proper and beneficial to nearby residents and more importantly to farmers. Furthermore, most of them agreed that the road provided adequate space and smooth road surface for the safe and convenient transport of products and also for efficient internal circulation within the development area.
46
Overall, the respondents showed highly favorable observations toward the project.
7.2. Implementation of FMR by Administration
7.2.1. Graveling of Loblob to Calitang Road in Bgy. Bucana, El Nido, Palawan
7.2.1.1. The Gravelling of Loblob-Calitang Road project costing P170,479.82 under the 20% Development Fund of CY 2013 was implemented without detailed engineering plans specifying the portion/s of the road for gravelling or patching, equipment utilization and project implementation schedules, monitoring or accomplishment reports and photographs documenting the project accomplishment.
Annex A of the Revised IRR of RA No. 9184 provides, in part, that “No
program of work for any project shall be approved without detailed
engineering.”
Item 2 of the same Annex provides that detailed engineering activities
shall include, among others, the conduct of survey and site investigation and
preparation of design plans, technical specifications, quantity and cost
estimates, program of work and construction schedule.
Based on the submitted Program of Work and Cross-Section Plans, the
scope of works involved patching/grading of 4.0 km long x 4.0 meters wide
unpaved Loblob-Calitang road and repair of 14.0 meter timber footbridge
within it.
Estimated and actual costs incurred on the project are as follows:
Qty Amount Qty Amount
I. Road regravelling
Aggregate base course (in cubic meters) 40 45,000.00 60 45,000.00
Diesel (in liters) 1,000 53,000.00 1,000 53,000.00
Oil and lubricants 32,000.00 6,825.00
130,000.00 104,825.00
II. Repair of footbridge
50 pcs - 2" x 6" x 18" ipil stringer (in board feet) 900 24,300.00 900 24,300.00
61 pcs - 2" x 4" x 10" floor joist (in board feet) 406.66 10,979.82 406.66 10,979.82
55 pcs - 11/2" x 10" x 18" flooring (in board feet) 1,125 30,375.00 1,125 30,375.00
C.W. nail 5" (in kilos) 3 255.00
C.W. nail 4" (in kilos) 3 255.00
C.W. nail 3" (in kilos) 3 255.00
Materials 66,419.82 65,654.82
Labor 3,580.18
70,000.00 65,654.82
Total 200,000.00 170,479.82
Estimated Actual
47
The program of work did not specify the period/ inclusive dates of
project implementation. There were no detailed plans identifying the
locations/stations to be patched within the 4 kilometers stretch of road.
There was also no supporting equipment utilization schedule.
The Office of the Municipal Engineer reported that the “Gravelling of
Loblob-Calitang Road” project was a farm-to-market road project
implemented in August to September 2013. However, there were no
monitoring or accomplishment reports on the project, documentation of
reference points where gravel patch was made and photographs taken
before, during and after project implementation. There were also no fuel
consumption report and equipment (road grader) utilization report
supporting the expenditures for fuel.
The actual accomplishments also were no longer fully visible at the time
of inspection conducted by the CPA team on February 5, 2015. Still, the
technical audit specialist in the team noted the following:
a. Repair of timber footbridge – Only the 12” running boards appeared to be new. Other visible wooden members of the footbridge like flooring and joists appeared to be old and were not replaced. At the time of inspection, the left end portion of the footbridge was noted to have already tilted or collapsed causing difficulty for vehicles to pass by the bridge. Estimated cost of installed flooring is P8,743.00. The estimated cost of repair per Program of Work is P70,000.00 or a discrepancy of P61,257.00. The actual length of timber footbridge is 13.0 meter.
Latitude: 11° 17’ 47.75” Longitude: 119° 25’ 40.25”
48
b. Road Grading –There was a trough of about 30m long and 0.50m deep along the road sections of Km 0+2511, 0+3110, 0+3246, 0+3434 and 0+3745. More re-gravelling and road maintenance along these sections are needed.
Latitude: 11° 17’ 47.75” Longitude: 119° 25’ 40.25”
Km 0+2511
49
Km 0+2511
Lat: 11° 17’ 56”
Long: 119° 25’ 44.125”
Km 0+3110
Lat: 11° 18’ 12.7499”
Long: 119° 25’ 32.8749”
50
Km 0+3246
Lat: 11° 18’ 14.50”
Long: 119° 25’ 29.8749”
Km 0+3110
Lat: 11° 18’ 12.7499”
Long: 119° 25’ 32.8749”
51
Interview with the residents disclosed the following:
a. Reshaping and leveling of road surface and spot re-gravelling in affected areas were undertaken in 2013. However, only thin layers of gravel and sand were placed in sections being patched and that these were not compacted by road rollers. Thus, the materials were easily washed-out by heavy rains or shoved by wheel motion to the outside as well as in-between travelled lanes leading again to rough road surface.
b. During the rainy season, the road turns muddy and slippery making it challenging if not impossible for even motorcycles to pass through.
c. The wooden footbridge cannot withstand heavy loads. Only the top portion or running surface of the footbridge was repaired.
d. The road does not provide adequate space for four-wheeled vehicles as it is only one-lane wide such that, if two vehicles are traveling in opposite directions, each vehicle shall deviate from the lane taking the shoulder in order to give way for the other vehicle to pass. This causes accidents and poses hazard to pedestrians.
e. Aggregates get washed-out to the rice plantations during heavy rains.
Accomplishment reports, reference points of road re-gravelling,
photographs, fuel and equipment utilization reports are necessary for the
Km 0+3246
Lat: 11° 18’ 14.50”
Long: 119° 25’ 29.8749”
52
validation of total project accomplishment and reasonableness of quantity
and cost of materials and fuel incurred on the project.
7.2.2. Construction/Rehabilitation and Maintenance of Local Roads, Barangay
Poblacion to Mauringen, Araceli, Palawan
7.2.2.1. The Barangay Poblacion to Mauringen road maintenance project costing P898,539.56 under the 20% Development Fund of CY 2014 was implemented without detailed engineering plans specifying the portions of the road to be repaired/maintained, equipment utilization and project implementation schedules, monitoring or accomplishment reports and photographs documenting the project accomplishment. Moreover, items totaling to P457,466.28 were charged to the project contrary to the approved Program of Works and Detailed Estimates.
Annex A of the Revised IRR of RA No. 9184 provides, in part, that “No
program of work for any project shall be approved without detailed
engineering.”
Item 2 of the same Annex provides that detailed engineering activities
shall include, among others, the conduct of survey and site investigation and
preparation of design plans, technical specifications, quantity and cost
estimates, program of work and construction schedule.
Based on the submitted Program of Works, the project involved
maintenance of a 33.0 km long x 8.0 meters wide road with total estimated
cost of P899,800.20. The program of works, however, did not specify the
period/ inclusive dates of project implementation. There were no road plans
and profile identifying the locations/stations to be repaired/ maintained
within the 33 kilometers stretch of road. There was also no supporting
equipment utilization schedule.
The approved Program of Works showed the following cost breakdown:
Labor Cost P117,000.00
Fuel, Oil and Spare-parts 743,400.00
VAT 39,400.20
Total P899,800.20
53
The Detailed Estimates are as follows:
Labor No. of
Person
No. of
Days
Daily
Rate Amount
a. Construction Foreman 1 60 350.00 P 21,000.00
b. Operators 2 60 300.00 36,000.00
c. Drivers 2 60 300.00 36,000.00
d. Laborers 2 60 200.00 24,000.00
Total P117,000.00
Equipment Fuel
Qty.
No. of
Days Rate/L Amount
a. 1 – Motorized Road
Grader
70 L 60 59 P247,800.00
b. 1 – Vibratory Roller 40 L 60 59 141,600.00
c. 1 – Loader 60 L 60 59 212,400.00
d. d. 1 – Dumptruck 40 L 60 59 141,600.00
Total P743,400.00
Appropriation for the Barangay Poblacion to Sitio Baing, Barangay
Mauringen road maintenance project amounted to P900,000.00 for calendar
year 2014. Based on the Registry of Appropriations, Allotments and
Obligations submitted by the OIC-Municipal Budget Officer, charges against
the appropriation for the project totaled to P898,539.56 from January to
October 2014. However, the Municipal Accountant was able to submit the
vouchers for transactions amounting to only P736,869.78, broken down as
follows:
Date Check
No. Payee Particulars Amount
Labor
03/07/14 883199 Jessie Paredes & Co. Wages Feb 18-25, 2014 Mason and
Laborer
3,000.00
05/12/14 883314-
315
Aldrin Dadaya &Co. Wages Apr 1-30, 2014 Job Order
MEO
6,900.00
04/10/14 883250 Rico Magbanua Wages Casual at the MEO Mar 1-
31, 2014
4,650.00
04/10/14 883269 Vicente Abalajon Sr. Wages Garbage Collector Mar 1-
31, 2014
4,650.00
05/15/14 883346 Joeben Paredes Wages Apr 14-24, 2014 Helper
widening of National-Provincial
road
1,400.00
54
Date Check
No. Payee Particulars Amount
06/10/14 883397-
400
Aldrin Dadaya &Co. Wages May 1-31, 2014 Job Order
MEO
16,650.00
06/11/14 883428 Joeben Paredes Wages May 9-30, 2014 Helper
widening of National-Provincial
road
3,200.00
07/02/14 883451 Joeben Paredes Wages June 1-6, 2014 Laborer
clearing of barangay roads
1,000.00
08/13/14 883537-
539
Aldrin Dadaya &Co. Wages July 1-31, 2014 Job Order
MEO and Garbage Collector
10,500.00
09/10/14 883608 Aldrin Dadaya &Co. Wages Aug 1-31, 2014 Job Order
MEO
7,500.00
09/17/14 883630 Sixto Buyco Salary July 1-31, 2014 Heavy
Equipment Operator
5,500.00
09/17/14 883631 Sixto Buyco Salary Aug 1-31, 2014 Heavy
Equipment Operator
5,500.00
10/09/14 883664-
671
Aldrin Dadaya &Co. Wages Sep 1-30, 2014 Job Order
MEO
17,005.00
10/10/14 883674 Sixto Buyco Salary Sep 1-30, 2014 Heavy
Equipment Operator
5,500.00
92,955.00
Fuel
06/02/14 883392 Mark Gabriel and
Ghing Ghing Store
630 liters diesel for backhoe
loader and road grader
37,170.00
07/02/14 883465 FGP Commercial 630 liters diesel for backhoe
loader and road grader
37,138.50
07/18/14 883500 Mark Gabriel and
Ghing Ghing Store
630 liters diesel for backhoe
loader and road grader
37,170.00
08/19/14 883583 Mark Gabriel and
Ghing Ghing Store
630 liters diesel for backhoe
loader and dump truck
37,170.00
11/20/14 883714 FGP Commercial 630 liters diesel for backhoe
loader
37,800.00
186,448.50
Others
02/28/14 883173 Mark Gabriel and
Ghing Ghing Store
Oil and lubricants for backhoe
loader
10,420.00
02/28/14 883181 Engr. Raul Valones Reimbursement for 2 pcs tube of
backhoe loader
1,900.00
03/03/14 883182 Kubo Beach Sing-
Along and
Restaurant
Meals and lodging of PEPO
personnel on 1/23/14 re: repair of
bulldozer
2,595.00
55
Date Check
No. Payee Particulars Amount
03/03/14 883183 Western Motors
and Machine Shop
Parts & service in the repair of
differential gear of Mitsubishi
SG1B of motor grader
120,000.00
03/04/14 883184 New CBPP Palawan
Enterprises
Spareparts for dump truck 11,800.00
03/27/14 883234 Joseph Gabinete Freight of materials for MEO 1,900.00
04/11/14 883279 Kubo Beach Sing-
Along and
Restaurant
Meals and lodging of PEPO
personnel on Mar 19-27, 2014
8,605.00
04/11/14 883282 Mark Gabriel and
Ghing Ghing Store
6 gallon oil #40 for road grader 3,960.00
04/30/14 883290 Danilo M. Mandal
Injection Pump
Service
Pump calibration and parts 8,700.00
05/27/14 883383 Mark Gabriel and
Ghing Ghing Store
Oil for bulldozer used in widening
of National-Provincial road
15,700.00
06/30/14 Angelo Sabaybay Materials for repair of bulldozer 1,535.00
07/02/14 883464 FGP Commercial 1unit motolite battery for road
grader
10,000.00
07/16/14 883497 CAMEC JCB
Corporation
Spareparts for backhoe loader 97,381.47
07/16/14 883498 Lea Vulcanizing
Shop and Trading
Tires for backhoe loader 78,582.00
07/21/14 883501 Ernesto Pe Reboring and cutting of blade of
grader
4,300.00
07/22/14 883506 Wenceslao
Barrientos IV
Reimbursement for spareparts of
Mitsubishi Grader
35,399.81
08/14/14 883577 Kubo Beach Sing-
Along and
Restaurant
Meals and lodging of PEPO
personnel on 7/31/14
2,170.00
08/15/14 Mary Grace Beronio Reimbursement of fare for 2 tires
of backhoe loader
750.00
08/15/14 Angelo Villegas Reimbursement of battery clamp
and stainless wire for backhoe
loader and dump truck
277.00
08/15/14 Engr. Raul Valones Reimbursement of fuel filter for
bulldozer
774.00
09/17/14 883633 Joseph Gabinete Fare for tires of backhoe loader,
power sprayer etc.
2,000.00
09/17/14 883634 Engr. Raul Valones Reimbursement for labor for re-
fitting of hydraulic hose of
backhoe loader
5,206.00
09/18/14 883642 James Paredes Unspecified miscellaneous 2,100.00
56
Date Check
No. Payee Particulars Amount
expenses in operation of heavy
equipment in diff. barangays
09/22/14 883647 Engr. Raul Valones Reimbursement of 1 set power
sprayer for MEO
6,426.00
10/20/14 883683 Engr. Raul Valones Reimbursement of 1 unit motolite
battery for backhoe loader
6,665.00
10/20/14 883685 DNT Sari-Sari Store 95 liters diesel and 12 liters regular
gasoline for the Office of the Mun.
Mayor
6,540.00
11/20/14 883715 DNT Sari-Sari Store Diesel, gasoline and oil for dump
truck used in the garbage
collection and in GSO
11,780.00
457,466.28
Total 736,869.78
Charges for labor were not supported by accomplishment reports while
fuel (diesel) expenses for heavy equipment were not supported by fuel and
equipment utilization reports showing that these expenditures were fully
utilized/ incurred in the project implementation.
Moreover, items totaling to P457,466.28 were charged to the project
even though these were not included in the approved Program of Works and
Detailed Estimates.
There were also no detailed plans/drawings; documentation of
reference points of road rehabilitation/maintenance and photographs taken
before, during and after project implementation evidencing project
accomplishments and justifying reasonableness of expenditures on the
project.
The Citizen Participatory Audit (CPA) team conducted project inspection
on February 10, 2015 together with Mr. Angelo R. Villegas, Meter Reader I,
staff in the Office of the Municipal Engineer. The municipal engineer was not
around despite prior commitment to be available in the project inspection.
The municipal mayor assigned Mr. Villegas to assist/guide the CPA team.
The actual length of the project measured 28 km only, short of 5 km as
compared to 33 km identified in the program of works. With the Parola as
reference Sta. 0+000, the following road conditions were noted by the
technical audit specialist in the team:
57
0.0 km – 2.0 km Existing concrete road
2.0 km – 7.85 km Existing damaged asphalt road
7.85 km – 8.46 km Concrete road with a width of 5.0m
9.0 km – 9.34 km Concrete road with a width of 5.0m, shoulder of 1.40m and 1.80m
9.34 km – 16.74 km Gravel road, graded with a width of 6.60m to 9.40m
16.74 km – 16.79 km Concrete road with shoulder of 2.20m and 2.70m
16.88 km – 16.95 km Concrete road with shoulder of 1.80m and 2.10m
17.0 km – 25.0 km Gravel road, graded, with a width from 5.40m to 7.84m
25.0 km – 26.0 km 6.30m damaged earth road with about 20.0 m long earth
displacement as deep as 1.0m
26.0 km – 28.0 km 5.40m to 6.0m earth road, no signs of improvement/rehabilitation
between 0 km – 2.0 km, existing concrete road
between 2.0 km – 7.85 km, existing damaged asphalt road
58
7.85 km – 9.34 km concrete road 9.34 km – 16.74 km gravel road
between 17.0 km – 25.0 km, gravel road
between 25.0 km – 26.0 km, damaged earth road
59
Between 26.0 km – 28.0 km, earth road
7.2.3. Construction of Nalbot-Old Guinlo Road Phase I and II, Bgy. Poblacion – Old
Guinlo, Taytay, Palawan
7.2.3.1. The FMR So. Nalbot to Barangay Old Guinlo has various defects, thus, requiring additional costs for repairs to the government.
During our ocular inspection the Team noted the various defects:
Bridge No. 3 was still incomplete and not yet passable at the time of inspection. As explained by the Municipal Engineer, the lumbers that were supposed to be in the construction were confiscated by Palawan Council for Sustainable Development (PCSD) allegedly illegally cut from the forest.
60
Figure No. 1. Bridge No. 3
Latitude 10°50'23.16"N
Longitude 119°27'40.09"E
Bridge No. 4, a one-span bridge were constructed outside the road location and not yet passable because they have no approaches and riprap protection.
Figure No. 2. Bridge No. 4
Latitude 10°48'22.56"N
Longitude 119°26'33.76"E
61
Road project has no more visible ditch due to siltation and uncontrolled growing of vegetation.
Figure No. 3. Uncontrolled Growing of Vegetation
Latitude 10°48'29.41"N
Longitude 119°28'19.89"E
Most of the Reinforced Concrete Pipe Culvert (RCPC) installed were in the wrong elevations and stations since the same were installed without road cross-section. The installed RCPC of various sizes could not perfectly serve the purpose of diverting the flood water from one side of the road to the other side.
Figure No. 4.Reinforced Concrete Pipe Culverts
Latitude 10°46'56.98"N
Longitude 119°29'24.46"E
62
Some sections of the road has damaged embankment including the headwalls of the RCPC which were already detached from the pipes.
Figure No. 5. Damaged Embankment
Latitude 10°47'5.84"N
Longitude 119°29'7.18"E
Sources of materials were obtained from quarry sites located near or along the road stretch and were not approved by the DPWH or Provincial Engineer’s Office of Palawan.
Figure 6
Latitude 10°47'20.64"N
Longitude 119°28'57.57"E
63
There were oversized stones on the road bed, loose materials, potholes and presence of muck and other unsuitable materials.
Figure No. 7. Visibly Oversized Stones
Latitude 10°46'57.12"N
Longitude 119°29'24.18"E
Cutting of slope is so steep that there is a tendency of possible landslides in some section of the road stretch.
7.2.3.2. The FMR project has no detailed engineering.
Annex “A” of the Revised IRR of RA 9184 provides that, “No program of
work for any project shall be approved without detailed engineering.”
As stated in Paragraph 2 of Annex “A” of the said IRR, a schedule of
detailed engineering activities shall include the following:
a) Survey b) Site investigation c) Soils and foundation investigation d) Construction materials investigation e) Preparation of design plans f) Preparation of technical specifications g) Preparation of quantity and cost estimates h) Preparation of program of work i) Preparation of proposed construction schedule (and estimated cash flow
for projects with schedule over six (6) months)
64
j) Preparation of site or Right-of-Way (ROW) Plans including schedule of acquisition
k) Preparation of utility relocation plan l) Preparation and submission of Design Report m) Environment Impact and Statement for critical project as defined by the
Department of Environment and Natural Resources (DENR) n) Preparation of minimum requirements for a Construction Safety and
health Program for the project being considered
Inquiry with the Municipal Engineer disclosed that the entire FMR
project has no detailed plans and specification, no survey plan, no soil
testing, no investigation as to the riverflow and the identification of flood-
prone and landslide-prone areas. They prepare program of work according
to the allotted fund of the particular year.
7.2.3.3. The reasonableness of the actual cost in the construction of the FMR project could not be validated.
Our audit covers works undertaken for Calendar Years (CY) 2012 and
2013 with corresponding appropriations of P2,000,000 and P1,000,000,
respectively. For CY 2012, it covers the construction of three (3) units one-
span timber bridge, installation/construction of 370 pcs. 10mm diameter x
.6meter RCPC and road grading, gravelling and re-shaping. For CY 2013, it
covers the construction of one (1) unit two-span timber bridge and road
grading, gravelling and re-shaping.
The construction of FMR project has an estimated length of 4.566 km.
and 1.522 km for the P2,000,000 and P1,000,000 programmed projects,
respectively, It has an average width of 6.50 to 7.00 meters as identified by
the Municipal Engineer.This project was undertaken by administration. All
the heavy and light equipment used in the project for quarrying and hauling
of construction materials are the property of the Municipality of Taytay and
free of rentals.
The Team conducted the actual measurement by using digital walking
measure and GEOTAGGING based on the pinpointed location as determined
by the Municipal Engineer. The Audit Team started about 100 meters away
from Palawan North National Highway as identified by the Municipal
Engineer. The Team, however, was unable to locate the exact location of the
beginning and the end of the project because there was no point of
reference or any identified station in the program of works. The results of the
65
Audit Team’s actual measurement using the walking measure were almost
the same as that of the results obtained from the geotagging technique.
Since there was no approved plan, road construction of the FMR
continued only up until the appropriated fund for that particular budgeted
period have been fully exhausted. The appropriated funds were utilized for
the procurement of timber for the construction of bridge and the fuel and
lubricants used by the equipment owned by the LGU.
7.2.3.4. The Team was unable to determine whether the actual work accomplishments are in accordance with the approved plans and specifications.
Our evaluation of the P2M andP1Mprojects lack the following
documents:
1. Approved Road plans, profile and cross section 2. Agency’s design standard 3. Approved bridge plans and all details 4. Sales invoice of all materials involved in the project 5. Delivery receipt of all materials in the project 6. Approved purchase order (PO) of all materials involved in the Bridge
project 7. Certificate of inspection and acceptance for roads and bridges 8. Approved materials source maps from the Provincial Engineering Office
and nearest DPWH District Office 9. Heavy and light equipment utilization report for CY 2012 – 2014 10. Municipal inventory report of existing light and heavy equipment 11. Construction schedule 12. Materials quality control test results 13. Photographs before, during and after construction per RA 6954
The whole FMR project is lacking the detailed engineering as
mentioned in Annex “A” of the Revised IRR of RA 9184.
In view of this, the Team was not able to validate the following:
1. The total work accomplishments of the subject project cannot be validated because there was no submitted statement of work accomplished (SWA)
2. The accomplishment made on the project cannot be validated as to compliance with plans and specifications because there is no approved plans and program of work.
66
3. The project cannot be validated whether the accomplishments was in accordance with the construction schedule because there is no PERT/CPM network diagram or construction schedule.
7.2.4. Reshaping/Road Embankment of Sitio Marirong-Cayasan in Bgy. Nicanor
Zabala, Roxas, Palawan
7.2.4.1. Sitio Marirong to Cayasan farm-to-market road (FMR) project was included in the Annual Investment Plan and Annual Budget of CY 2012. However, it was implemented only on January 08, 2015, thus incurring a three-year delay in the project.
Republic Act No. 7160, otherwise known as the Local Government Code
of 1991, provides that:
Section 18 - Power to Generate and Apply Resources. - Local
government units shall have the power and authority to establish
an organization that shall be responsible for the efficient and
effective implementation of their development plans, program
objectives and priorities; xxx
Section 444(b)(3) Duties of the Municipal Mayor: “Initiate
and maximize the generation of resources and revenues, and
apply the same to the implementation of development plans,
program objectives and priorities xxx
Section 476(b) Duties of the Planning and Development
Coordinator – (4) Monitor and evaluate the implementation of the
different development programs, projects, and activities in the
local government unit concerned in accordance with the approved
development plan.
Likewise, Item 5.0 of the Department of Interior and Local Government
(DILG)-Department of Budget and Management (DBM) Joint Memorandum
Circular (JMC) No. 2011-1 dated April 13, 2011 states that: “It is the
responsibility of every xxx Municipal Mayor xxx to ensure that the 20% of the
IRA is optimally utilized to help achieve desirable socio-economic
development and environmental outcomes. Xxx”
Included in the 2012 Annual Investment Plan of the Municipality of
Roxas is the Farm-to-Market Road (FMR) development of the Marirong road
to Cayasan falls of Barangay Nicanor Zabala, Roxas, Palawan. The said project
67
was also provided with an appropriation of P200,000.00 in the 2012 Annual
Budget under the 20% Development Fund (DF).
The Marirong road to Cayasan falls FMR project, being incorporated in
the AIP and Annual Budget, means that this was identified as one of the
priority projects which should have been implemented by the Municipality in
the budget year 2012. However, despite having available funds, the proposed
project remained unimplemented for three (3) years (2012-2014).
Further examination of the pertinent documents disclosed that the
Municipality already procured the needed fuel, oil and lubricants on January
20, 2014 but was not utilized until January 08, 2015, as per reports submitted
by the Municipal Engineer.
7.2.4.2. The program of works was not supported with detailed plans and specifications prior to implementation of the FMR project.
Annex A of the Revised IRR of RA No. 9184 provides, in part, that “No
program of work for any project shall be approved without detailed
engineering.”
Item 2 of the same Annex provides that detailed engineering activities
shall include, among others, the conduct of survey and site investigation and
preparation of design plans, technical specifications, quantity and cost
estimates, program of work (POW) and construction schedule.
On December 03, 2014, the Audit Team requested for the submission
of the copies of approved plans and specifications and POW with detailed
cost estimates. However, during that time, only the POW was made available
to the team since the detailed engineering plans and specifications were not
prepared prior to project implementation. Moreover, it was noted that the
POW did not specify the period/ inclusive dates of project implementation.
To support actual work done, the approved plans and specifications,
equipment utilization, and photographs of the project were only prepared
later on January 2015 and was submitted to the team on February 13, 2015.
68
7.2.4.3. Actual project implementation was not in accordance with the approved program of works.
Review of pertinent transaction documents revealed that the same
project has a previous different POW dated January 07, 2013 and the
description of works to be done are road reshaping, clearing and grubbing.
The project cost from the original POW amounted to P200,000.00, of
which P193,000.00 pertains to fuel, lubricants and spare parts and P7,000.00
is for other indirect costs. The entire P193,000.00 appropriations for the fuel,
oil and lubricants was not procured through public bidding as a single
transaction. Instead only the amount of P97,783.20 was procured on June
10, 2013 through small value procurement and this was utilized in road
reshaping and embankment of the 2.2 kms existing gravel road of Sitio
Marirong.
The remaining fuel requirement amounting to P 52,216.80 for the FMR
of Marirong-Cayasan project was included in the procurement of fuel and
lubricants through public bidding conducted on December 18, 2013. The
procured fuel and lubricants was delivered and accepted on January 20, 2014
and paid on February 25, 2014 yet the project was not immediately started.
Moreover, the description of works indicated in the POW of
P102,216.80 dated August 15, 2013 is road reshaping and embankment,
however ocular inspection conducted by the team revealed that the actual
work done was road opening.
69
7.2.4.4. The total work accomplished on the subject project cannot be validated because there was no submitted monitoring or accomplishment reports.
The following were noted from ocular inspection, actual measurement
and geotagging:
1. The road stretch is cleared from vegetations, excavated and uprooted
bamboos and trees of different varieties;
70
2. Backfilling materials as road embankment are visible along the road;
3. The road width measurement was recorded resulting in variable widths of 4.0m to 7.8m;
71
4. There was visible rock excavation at side slope for around 100 meters; and
72
5. Actual measurement of the length and geotagging was recorded to have a total length of 1.24km as against the submitted sketch showing a 1.00km length.
7.2.4.5. The results of interview and ocular inspection showed that the FMR project
was not strategically located near key production area of valuable crops and other agricultural products.
The subject FMR project started at a point along Marirong road going to
Cayasan Falls, a potential tourist destination in Barangay Nicanor Zabala,
Roxas which the local government plans to develop/improve.
Based on the location map submitted by the Municipal Planning and
Development Office (MPDO) and Municipal Engineering Office (MEO), the
development made to Marirong road and the opening of road to Cayasan
Falls is actually in connection with the proposed construction of Bgy. Nicanor
Zabala Tourism Road.
The beneficiaries interviewed, all local farmers, gave mostly negative
responses on the project since the FMR implemented in their barangay was
not located on a key production area of valuable crops such as rice, corn and
other high value commercial crops, livestocks and fisheries.
In addition, local farmers found that the location and design of the FMR
project was not safe and convenient to transport agricultural products
because the project was situated in a mountainous area with steep slopes.
73
7.2.5. Maintenance of Iniaran Farm to Market Road, Bgy. Labog, Sofronio Espanola,
Palawan
7.2.5.1. Maintenance of Labog – Iniaran FMR was included in the agency’s 2014 Annual Investment Plan (AIP) and was provided an appropriation of P75,000.00. Cost incurred in implementing the project totaling P56.822.65 is within the appropriated amount.
The Annual Investment Plan (AIP) of the Municipality of Sofronio, Espanola for C.Y. 2014 included the Maintenance of 4.8 kilometers Labog – Iniaran FMR under Reference Code Number 8000-5-153 with an estimated amount of ₱150,000. The project was incorporated in the Annual Budget for C.Y. 2014 and was provided with ₱75,000.00 appropriation under the 20% Development Fund.
Cost incurred on the project totaled ₱56,822.65 as follows:
Reference Payee Particulars Amount
Fuel, Oil and Lubricant
JEV No. 10-14-04-0912
Pulot Petron Station
Payment for fuel and lubricants used for Labog Iniaran FMR
6,331.90
JEV No. 10-14-04-1066
Herenzo Gasoline Station
Payment for fuel and lubricants used for Labog Iniaran FMR
6,532.00
JEV No. 10-14-05-1244
Herenzo Gasoline Station
Payment for fuel and lubricants used for Labog Iniaran FMR
32,370.00
JEV No. 10-14-06-1615
Herenzo Gasoline Station
Payment for fuel and lubricants used for Labog Iniaran FMR
3,014.75
JEV No. 10-15-01-0113-1
Uno Commercial Payment for fuel and lubricants used for Labog Iniaran FMR
2,574.00
Sub-total 50,822.65
Vegetation Control
JEV No. 10-14-06-1542
Gerry Ganusa, et al
Payment of vegetation control of Labog Iniaran FMR
6,000.00
Total: 56,822.65
The foregoing data show that disbursements made during the year did not exceed the amount of fund appropriation, in compliance with Section 305(a) of R.A. 7160 which states that: “No money shall be paid out of the local treasury except in pursuance of an appropriations ordinance or law”.
74
7.2.5.2. The program of work of Iniaran FMR was not supported by detailed engineering plans specifying the portion/s of the road for gravelling or patching, equipment utilization and project implementation schedules, thus reasonableness of the quantity and cost estimates and compliance of accomplishments with plans and specifications and schedule cannot be validated.
Annex A of the Revised IRR of RA No. 9184 provides, in part, that “No
program of work for any project shall be approved without detailed engineering.”
Item 2 of the same Annex provides that detailed engineering activities
shall include, among others, the conduct of survey and site investigation and preparation of design plans, technical specifications, quantity and cost estimates, program of work and construction schedule.
The program of work did not specify the period/ inclusive dates of
project implementation. There were no detailed plans identifying the locations/stations to be patched within the 4.8 kilometers (Iniaran) stretch of roads. There were also no supporting equipment utilization schedules. Thus, reasonableness of the quantity and cost estimates of materials and fuel as well as compliance of accomplishments with plans, specifications and project implementation schedule cannot be validated.
7.2.5.3. There was no monitoring or accomplishment reports, reference points and
photographs documenting the implementation of the road maintenance project, thus the total project accomplishment and the reasonableness of quantity and cost of materials based on actual accomplishment cannot be validated.
The submitted Program of Work for the maintenance of the 4.8
kilometers of Labog-Iniaran FMR did not specify the scope of works involved. As of year-end, the Office of the Municipal Engineer reported that the road maintenance project was 100% implemented. There were no monitoring or accomplishment reports on the project, documentation of reference points where gravel patch was made and photographs taken before, during and after project implementation. There were also no fuel consumption report and equipment utilization report supporting the expenditures for fuel.
The actual accomplishments were no longer fully visible at the time of
inspection conducted by the CPA team on January 22, 2015. Still, the technical audit specialist in the team noted the following:
75
1. The conditions of the graveled sections from Sta.0 + 110 to Sta. 5+000 were almost the same except for some potholes observed at Sta.0 + 801 and Sta. 0 + 867.
Taken at Sta.0+ 867. Latitude: 9° 3'31.00"N; Longitude : 118° 4'3.00"E
2. Road shoulders on both sides of the graveled road were already covered
with vegetation. There were no longer traces of cut/trimmed foliage found when the team arrived.
Latitude: 9° 3'36.00"N ; Longitude : 118° 4'26.00"E
3. There was impounding of water observed at Sta.0 + 801.
Latitude: 9° 3'31.00"N ; Longitude : 118° 4'1.00"E
Due to lack of accomplishment reports, reference points of road re-
gravelling, photographs, fuel and equipment utilization reports, the total
76
project accomplishment and the reasonableness of quantity and cost of materials based on actual accomplishment can no longer be validated.
7.2.5.4. Purchases of various items totaling to P 5,175.65 were charged to the
project contrary to its approved Program of Works:
The Approved Program of Work (POW) for the Maintenance of Labor Iniaran FMR showed the following cost breakdown:
1) Vegetation Control (5 laborers, 9 man days @ 200.00) ₱6,000.00 2) Fuel, Oil and Lubricants
a.) Fuel (1,118 liters @ P55) 61,490.00 b.) Oil and Lubricants (lump-sum) 5,010.00
3) Road Right of Way: 2,500.00
TOTAL ₱75,000.00
Verification of the submitted transaction documents showed that
various items totaling P5,175.65 that were not included in the POW and detailed estimates were procured and charged to the project. Details are as follows:
Check # Check Date
Payee Particulars Amount
408043 4/10/14 Pulot Petron Station
10 ltrs diesel, service to hotspring (owner) P579.50 8 ltrs diesel, service to LabogIniaran hotspring (owner) P458.40
₱1,037.90
408222 4/30/14 Herenzo Gas Station
2 ltrs unleaded Gasoline, motorpool Service for Iniaran Project, hotspring (motorcycle) P136.00 3 ltrs unleaded Gasoline, service to Hotspring (motocycle) 204.00 10 ltrs diesel, service to inspect Iniaran project (delica) 579.00 3 ltrs unleaded gasoline, Service to Iniaran (delica) 204.00
1,123.00
408707 6/27/14 Herenzo 45 ltrs diesel, hauling 3,014.75
77
Check # Check Date
Payee Particulars Amount
Gas Station
Of gravel and sand for Iniaran Elementary School (10WDT) P3,014.75
Total P 5,175.65
7.2.6. Maintenance of Kanangkaan Farm to Market Road, Bgy. Punang, Sofronio
Espanola, Palawan
7.2.6.1. Maintenance of Kanangkaan – Punang FMR was included in the agency’s 2014 Annual Investment Plan (AIP) and was provided an appropriation of P75,000.00. Cost incurred in implementing the project totaling P68,483.00 was within the appropriated amount.
The Annual Investment Plan (AIP) of the Municipality of Sofronio,
Espanola for C.Y. 2014 included the Maintenance of 3.7 kilometers Punang-Kanangkaan FMR under Reference Code Number 8000-5-154 with an estimated amount of P300,000.00. The project was incorporated in the Annual Budget for C.Y. 2014 and was provided with P75,000.00 appropriation under the 20% Development Fund.
Cost incurred on the project totaled P 68,483.00 as follows:
Reference Payee Particulars Amount
Fuel, Oil and Lubricant
JEV No. 10-14-05-1244
Herenzo Gasoline Station
Payment for fuel and lubricants used for Kanangkaan FMR
1,164.00
JEV No. 10-14-12-3455
Herenzo Gasoline Station
Payment for fuel and lubricants used for Kanangkaan FMR
7,175.64
JEV No. 10-15-01-0108
Herenzo Gasoline Station
Payment for fuel and lubricants used for Kanangkaan FMR
17,493.04
JEV No. 10-15-01-0108
Herenzo Gasoline Station
Payment for fuel and lubricants used for Kanangkaan FMR
33,650.32
Sub-total 59,483.00
Vegetation Control
JEV No. 10-15-01-0108
Tejada, et al Payment of vegetation control of Kanangkaan FMR
P9,000.00
Total: 68,483.00
78
The foregoing data show that disbursements made during the year did not exceed the amount of fund appropriation, in compliance with Section 305(a) of R.A. 7160 which states that: “No money shall be paid out of the local treasury except in pursuance of an appropriations ordinance or law”.
7.2.6.2. There was no monitoring or accomplishment reports, reference points and
photographs documenting the implementation of the road maintenance project, thus the total project accomplishment and the reasonableness of quantity and cost of materials based on actual accomplishment cannot be validated.
The submitted Program of Work for the maintenance of the 3.7
kilometers Kanangkaan-Punang FMR did not specify the scope of works involved. As of year-end, the Office of the Municipal Engineer reported that the road maintenance project was 100% implemented. There were no monitoring or accomplishment reports on the project, documentation of reference points where gravel patch was made and photographs taken before, during and after project implementation. There were also no fuel consumption report and equipment utilization report supporting the expenditures for fuel.
The actual accomplishments were no longer fully visible at the time of
inspection conducted by the CPA Team on January 22, 2015. Still, the technical audit specialist in the Team noted the following:
1. There were newly re-shaped section of Kanangkaan road at Sta.2 + 230 2. Road shoulders on both sides of the graveled road were already covered
with vegetation. There were no longer traces of cut/trimmed foliage found when the team arrived.
3. There were potholes and impounding of water observed at various sections of the Kanangkaan FMR
Due to lack of accomplishment reports, reference points of road re-
gravelling, photographs, fuel and equipment utilization reports, the total project accomplishment and the reasonableness of quantity and cost of materials based on actual accomplishment can no longer be validated.
7.2.6.3. Purchases of various items totaling to P 5,175.65 were charged to the
project contrary to its approved Program of Works: The Approved Program of Work (POW) for the Maintenance of
Kanangkaan FMR showed the following cost breakdown:
1) Vegetation Control (5 laborers, 9 man days @ 200.00): P 9,000.00 2) Fuel, Oil and Lubricants 63,500.00 3) Road Right of Way: 2,500.00 TOTAL: P75,000.00
79
Verification of the submitted transaction documents showed that
various items totaling P7,628.68 that were not included in the POW were procured and charged to the project. Details are as follows:
Check # Check Date Payee Particulars Amount
439570 12/19/14 Herenzo Gas Station
2 ltrs unleaded Gasoline, inspection of Project (motorcycle) P118.34 15 ltrs unleaded Gasoline, inspection of Kanangkaan and Hotsping (revo) 887.55 50 ltrs diesel, inspection of various roads and bridges (adventure) 2,401.00 15 ltrs diesel, inspection of Labog hotspring (revo) 887.55 30 ltrs diesel, inspection of Bgy roads at abo-abo (adventure) 1,440.60 30 ltrs diesel, clearing in Slaughterhouse road (grader) 1,440.60
P7,175.64
439804 1/12/15 Herenzo Gas Station
3 ltrs unleaded gasoline, Supervision of projects (motorcycle) 174.78 1 lt unleaded gasoline And ultron, supervision of Projects (motorcycle) 278.26
453.04
Total P 7,628.68
80
7.2.6.4. The program of work of Kanangkaan FMR was not supported by detailed engineering plans specifying the portion/s of the road for gravelling or patching, equipment utilization and project implementation schedules, thus reasonableness of the quantity and cost estimates and compliance of accomplishments with plans and specifications and schedule cannot be validated.
Annex A of the Revised IRR of RA No. 9184 provides, in part, that “No
program of work for any project shall be approved without detailed engineering.”
Item 2 of the same Annex provides that detailed engineering activities
shall include, among others, the conduct of survey and site investigation and preparation of design plans, technical specifications, quantity and cost estimates, program of work and construction schedule.
The program of work did not specify the period/ inclusive dates of
project implementation. There are no detailed plans identifying the locations/stations to be patched within 3.7 kilometers (Kanangkaan) stretch of roads. There were also no supporting equipment utilization schedules. Thus, reasonableness of the quantity and cost estimates of materials and fuel as well as compliance of accomplishments with plans, specifications and project implementation schedule cannot be validated.
7.2.7. Improvement and Rehabilitation of Bgy. Kalatagbak, Quezon, Palawan
7.2.7.1. The Improvement and Rehabilitation of 5 Kilometers Brgy. Kalatagbak Farm
to Market Road (FMR) were not in accordance with the provisions of
Appendix I of Republic Act (RA) 9184 or GPPB Resolution No. 018-2006
dated December 6, 2006. Likewise, disbursements for Fuel, Oil and
Lubricants amounting to P146,594.50 had overlapping consumptions.
Review of the related documents on the implementation of 5
kilometers Brgy. Kalatagbak FMR revealed that the Agency did not prepare a
Detailed Engineering Plan and Specification. The Agency furnished the Audit
team with the Design and Specification of the KALAHI-CIDSS road
construction project that was not part of the FMR project. Confirmation with
the concerned Agency personnel revealed that the FMR project was
requested by the KALAHI-CIDSS as access road so that the heavy equipment
to be used in KALAHI-CIDSS project can easily reach the road construction
location.
The project, which is implemented “By Administration”, was not listed
among the projects to be undertaken in the Annual Procurement Plan (APP)
contrary to Section 3.1 of GPPB Resolution No. 018-2006 dated, December 6,
81
2006 on the conditions and requirement for the use of “By Administration”
which provides that “Projects undertaken by Administration shall be included
in the approved Annual Procurement Plan (APP) of the procuring entity
concerned.”
7.2.7.2. Procurement of fuel, oil and lubricants by the Agency was done through
shopping. Although, the amount of each purchase orders does not exceed
the threshold limit of ₱100,000.00 for the 1st class Municipality, the Agency
still violates Section 54.1 of RA No. 9184 on Splitting of Contracts which
states that:
Splitting of Government Contracts is not allowed. Splitting of
Government Contracts means the division or breaking up of GOP
contracts into smaller quantities and amounts, or dividing contract
implementation into artificial phases or sub-contracts for the purpose
of evading or circumventing the requirements of law and this IRR,
especially the necessity of public bidding and the requirements for the
alternative methods of procurement.
7.2.7.3. The procurement of fuel, oil and lubricants should have been done thru
public bidding since its purpose was only for the Brgy. Kalatagbak FMR. The
Agency divided the procurement into different purchase orders which
resulted in the splitting of contract. This mode of procurement is
disadvantageous on the part of the Government in terms of bulk purchase
discount and lowest competitive price.
Further review of disbursement vouchers (DV) and its supporting
documents disclosed that there were deemed multiple fuel, oil and
lubricants charges made for certain heavy equipments that were used for the
same operating day. Based on the Fuel/Oil Withdrawal Slip and Billing
Statement, there were charges for the same heavy equipment that were
withdrawn the same operating day but charged to different Disbursement
Vouchers amounting to P146,594.50 (see Appendix 6). For instance, fuel, oil
and lubricants of Dump Truck 5 (DT5) withdrawn on May 28, 2014 were
charged separately to DV No. 20-127, 20-133, & 20-134. It was not likely for
DT5 to withdraw fuel and refuel for the same operating day from the project
location to Gasoline station and vice versa since the project location is 22kms
away where the gasoline station is located. Moreover, the billing statement
from the supplier were separately prepared, instead of including all fuel, oil
and lubricants withdrawn for a certain period, the supplier divided the billing
82
statement per heavy equipment group which resulted to overlapping billing
periods. This raised doubts on excessive charging of fuel, oil, and lubricants.
The foregoing deficiencies showed that the Agency has not properly
managed and effectively controlled the use of fuel, resulting in possible
substantial losses due to misuse or abuse. In effect, the costs of fuel
consumption totaling P146,594.50 for this project were doubtful because of
the above-noted deficiencies.
7.2.7.4. Technical evaluation of work accomplishment and programmed work could
not be made due to the absence of the documentary requirements cited
under COA Memorandum No. 2005-027 and COA-Circular No. 2012-001
dated June 14, 2012.
COA Circular No. 2012-001 dated June 14, 2012 provides the list of
documentary requirements for common government transactions and COA
Memorandum 2005-027 provides the documentary requirements for the
evaluation of the technical aspect of all government contracts and inspection
of government projects.
Upon submission, the aforementioned documents it shall be reviewed
by the Auditor to evaluate compliance with the requirements of applicable
laws, rules and regulations and completeness of documentary requirements.
Such contracts shall then be forwarded to the assigned Technical Audit
Specialist for technical review whenever necessary.
Verification of records showed that the management has not submitted
the following documents which were essential to the technical evaluation of
work accomplishment and programmed work:
1. Approved Road plans with Typical road cross section;
2. Delivery Receipt and Sales Invoice of all materials involved in the
project;
3. Certificate of Inspection and Acceptance for the road;
4. Approved Materials Source Maps from the Provincial Engineering Office
and nearest DPWH District Office;
5. Heavy and Light Equipment Utilization Report for CY 2012-CY2014;
6. Municipal Inventory Report of Existing Light and Heavy Equipment;
7. Construction Schedule;
8. Material Quality Control Test Results;
9. Photographs before, during and after construction per RA 6954.
83
7.2.8. Regravelling of Sitio Mati and Paratungon roads, Barangay Pangobilian,
Brooke’s Point, Palawan
Road Maintenance/Re-graveling in Barangay Pangobilian, Brooke’s Point, Palawan, with a project cost of ₱200,000.00 implemented by administration
There were deficiencies noted during the conduct of audit on the project
“road maintenance/re-graveling of 3.24 km farm-to-market road (FMR)”
implemented by administration at Barangay Pangobilian.
7.2.8.1. Road maintenance projects for farm-to-market roads such as re-
graveling offer short-term improvement on road conditions and
require routine upkeep/rehabilitation.
A Citizen Participatory Audit (CPA) was conducted on the road
maintenance/re-graveling of the 3.24 km farm-to-market road (FMR)
project implemented by administration at Barangay Pangobilian,
Brooke’s Point, Palawan. The Municipality appropriated the amount
of ₱200,000.00 for the said road maintenance under the 20%
Development Fund for CY 2013, wherein ₱60,300.00 was allocated for
equipment rental and ₱139,700.00 for fuel requirement in ditching,
crowning, hauling and spreading of 810m3 sub-base coarse
aggregates over the 3.24km stretch of road.
The re-graveling project was undertaken in March 2014 at two
(2) separate locations in Barangay Pangobilian – Sitio Paratungon and
Sito Mati. The total actual cost incurred in implementing the project
amounted only to ₱138,765.00 for the purchase of 2,523 liters of
diesel fuel because the equipment used such as road grader, pay
loader, dump truck are owned by the Municipality.
The CPA Team conducted an ocular inspection on the project
sites on February 2-3, 2015 and observed that spot re-graveling was
undertaken instead of re-graveling the entire road section. The team
further noted the following:
84
While gravel materials were still visible in some areas, portions
have been displaced from the surface to the shoulder area
Gravel surface has started to erode
85
The roadbed gravel has no aggregate binder
86
Road shoulders and ditches were already covered by vegetation
Not all aggregates have undergone road grading/compacting
resulting in uneven and rough surface
87
Areas without gravel due to spot re-gravelling
88
The foregoing observations noted during the ocular inspection
conducted within a year after implementation only show that road re-
graveling projects provide short-term improvement on the road
condition. And compared to concrete, gravel roads require frequent
and routine maintenance or rehabilitation, especially after rainy
season. Thus, road maintenance projects may prove to be costly in
the long run and less beneficial to farmers and constituents alike.
89
7.2.8.2. The total project accomplishment and the reasonableness of the
actual quantity of fuel consumed could not be fully validated due to
the absence of monitoring or accomplishment reports, photographs
documenting the implementation of the road maintenance project
and the limited scope of the ocular inspection conducted.
The Municipality procured 2,523 liters of diesel fuel based on
the 810m3 sub-base coarse aggregates indicated in the Bill of
Materials and Cost Estimates. As reported in the fuel consumption
report, only 2,470 liters of fuel was actually used for re-graveling,
reshaping, ditching and hauling the aggregates from the quarry site to
the farm-to-market roads at Sitio Mati and Sitio Paratungon with
distances from the quarry site of 5.45 km and 5.98 km, respectively as
geotagged by the team.
However, given that the improvements on the project sites
were no longer fully visible almost a year after implementation which
limited the scope of the ocular inspection conducted, thus, it could
not be ascertained whether the Municipality actually used the entire
810m3 of sub-base coarse aggregates on the 3.24 km stretch of farm-
to-market roads as planned. The actual quantity of aggregates used is
relevant in validating the actual fuel consumption on hauling and re-
graveling. Moreover, there was no monitoring or accomplishment
report and photographs taken before, during and after the
implementation of the FMR project.
In the absence of such documents and the limited scope of the
inspection, the total project accomplishment and the reasonableness
of the quantity of fuel used could not be validated.
8.1. Implementation of FMR by Contract
8.1.1. Concreting of Kamuning Kamuning Road Phase II, Barangay Kamuning,
Puerto Princesa City, Palawan
8.1.1.1. On the issue of the construction deficiencies noted during the actual
inspection conducted by the Audit Team, it was noted that the total
deficiency amounting to ₱2,082,277.23 based on the initial findings
gathered from geotagging that need to be rectified by the contractor.
The duration on the repair of the noted deficiencies resulted to
inconvenience in the use of the project.
8.0 AUDIT CONCLUSION
90
8.1.1.2. On the issue of extended construction period without necessary
documentation such as suspension/extension of work orders, the
Audit Team determined that there were no documents submitted to
the Team that may be proved that the proper authority for the
approval of the extension of construction period.
8.1.2. Concreting of Inogbong Road, Bataraza, Palawan
The Inogbong Seashore Road concreting project provided a convenient transport of agricultural and fishery products. However, the safety and service of the road could be compromised if the defects noted would not be addressed immediately.
The compliance of the actual/reported accomplishments with the
approved plans and specifications could not be fully validated due to the absence of as-built plan. Other deficiencies noted in the auditorial review likewise showed non-compliance with RA 9184 and RA 7160.
8.1.3. Improvement of Malatgao-Culandanum-Panas-Linao Road, Bataraza,
Palawan
Overall, the audited Farm-to-Market Road (FMR) projects have attained their objective of providing efficient and effective transport of agricultural and fishery products from within the production areas into the nearest existing roadway systems and thereby improved the living conditions and promoted economic activities in the vicinity of the project.
8.2. Implementation of FMR by Administration
8.2.1. Graveling of Loblob to Calitang Road in Bgy. Bucana, El Nido, Palawan
8.2.2. Construction/Rehabilitation and Maintenance of Local Roads, Barangay
Poblacion to Mauringen, Araceli, Palawan
The maintenance projects failed to provide long-term improvement of
road conditions for safe and convenient transport of agricultural products.
8.2.3. Construction of Nalbot-Old Guinlo Road Phase I and II, Bgy. Poblacion – Old
Guinlo, Taytay, Palawan
The FMR project which is the opening of road from So. Nalbot to
Barangay Old Guinlowhichstarted in year 2010, is approximately 16 kilometers
long. This FMR is the most accessible and shortest route to the Malampaya,
thus, providing easier market access in transporting farm and marine products
from Barangay Old Guinlo and its neighboring barangays to Poblacion,Taytay.
The project, however, was found to be not in compliance with the
Revised IRR of R.A. 9184.
91
8.2.4. Reshaping/Road Embankment of Sitio Marirong-Cayasan in Bgy. Nicanor
Zabala, Roxas, Palawan
The road failed to provide for safe and convenient transport of
agricultural products because the project has steep slopes and is not
strategically located near production areas.
8.2.5. Maintenance of Iniaran Farm to Market Road, Bgy. Labog, Sofronio Espanola,
Palawan
8.2.6. Maintenance of Kanangkaan Farm to Market Road, Bgy. Punang, Sofronio
Espanola, Palawan
8.2.7. Improvement and Rehabilitation of Bgy. Kalatagbak, Quezon, Palawan
Overall, the audited Farm-to-Market Road (FMR) projects have attained their objective of providing efficient and effective transport of agricultural and fishery products from within the production areas into the nearest existing roadway systems and thereby improved the living conditions and promoted economic activities in the vicinity of the project.
8.2.8. Regravelling of Sitio Mati and Paratungon roads, Barangay Pangobilian,
Brooke’s Point, Palawan
Road re-graveling projects do not provide long-term improvement of
road conditions for safe and convenient transport of agricultural products.
9.1. Implementation of FMR by Contract
9.1.1. Concreting of Kamuning Kamuning Road Phase II, Barangay Kamuning,
Puerto Princesa City, Palawan
9.1.1.1. Immediately determine the liabilities of the responsible party/person(s) for the defects and implement the necessary measures/corrections/remedies in accordance with laws, rules and regulations, to correct the defects;
9.1.1.2. Conduct tests of the materials and workmanship of the projects to
ensure that the works are done in accordance with the requirements of the contract or in accordance with specifications;
9.1.1.3. Exercise diligent monitoring and supervision of the implementation of the project to ensure that only those projects done in accordance with the requirements of the contract are accepted and paid;
9.0 RECOMMENDATIONS FOR EXECUTIVE ACTION
92
9.1.1.4. Conduct evaluation and monitoring on the performance and conditions of the structures constructed to ensure that corrective measures could immediately be taken for defective structures; and/or for consideration in the conduct of the detailed engineering, such as in the preparation of specifications, etc.
9.1.1.5. Conduct eight (8) random coring test of the concrete pavement together with the Audit Team.
9.1.2. Concreting of Inogbong Road, Bataraza, Palawan
9.1.2.1. The defects noted in the audit results be addressed immediately and require the contractor, E.C. Timbancaya Enterprises, to undertake the necessary actions to rectify defects. Otherwise, the performance security posted shall be forfeited, and the contractor shall be perpetually disqualified from participating in any public bidding.
9.1.2.2. The Municipal Budget Office be made to explain the discrepancy
between Obligation Requests attached to the disbursements and the reported Status of Appropriations, Allotments, Obligations and Balances pertaining to the Continuing Appropriations of the 20% Development Fund allocation for the subject project.
9.1.2.3. The contractor be required to pay the liquidated damages.
9.1.2.4. The contractor be required to submit the As-Built Plan and Clearance from the Provincial Treasurer that the corresponding sand and gravel fees have been paid.
9.1.2.5. Final acceptance of infrastructure projects shall be made one year after the project completion.
9.1.2.6. All contract agreements be meticulously reviewed or scrutinize as to
the correctness and completeness of contents, terms and conditions
prior to signing by contracting parties.
9.1.3. Improvement of Malatgao-Culandanum-Panas-Linao Road, Bataraza,
Palawan
We recommended that the contractor should strictly follow the provision on contract period in execution of the project. Henceforth, the management should monitor all project implementation schedules and ensure strict adherence to the provisions of the Revised Implementing Rules and Regulations of Republic Act No. 9184.
93
We also recommended that the management should cause the
contractor to make immediate rectification of the aforementioned defects to
avoid further damage to the road project. De-clogging of the opening of the
RCBC will help the free flow of water thru the RCBC and repair of the wing wall
and putting embankment on the damage road approached will lengthen its
years of usage. Henceforth, the management should monitor all infrastructure
projects to ensure conformance with their detailed engineering plans and
specifications.
9.2. Implementation of FMR by Administration
9.2.1. Graveling of Loblob to Calitang Road in Bgy. Bucana, El Nido, Palawan
9.2.1.1. Appropriate funds instead for the Concreting of Loblob-Calitang Road
seeing that the road is being used on a regular basis and that road
reshaping and re-gravelling offers no long term improvement on its
condition;
9.2.1.2. Ensure that no infrastructure projects shall be undertaken without
the required detailed engineering investigations, surveys and plans;
and
9.2.1.3. Monitor, prepare a report on and document project
accomplishments.
9.2.2. Construction/Rehabilitation and Maintenance of Local Roads, Barangay
Poblacion to Mauringen, Araceli, Palawan
9.2.2.1. Appropriate funds for concreting of roads instead of road
rehabilitation since maintenance projects offer no long term
improvement on road conditions;
9.2.2.2. Ensure that no infrastructure projects shall be undertaken without
the required detailed engineering investigations, surveys and plans;
and
9.2.2.3. Monitor, prepare and submit a report on project accomplishments
duly supported by equipment and fuel utilization reports and
photographs taken before, during and after project implementation.
9.2.3. Construction of Nalbot-Old Guinlo Road Phase I and II, Bgy. Poblacion – Old
Guinlo, Taytay, Palawan
94
9.2.3.1. Since the FMR project is still on-going and opening of road only, the LGU should conduct detailed engineering before any construction should be made.
9.2.3.2. The LGU should look for an alternative lumber to finish the bridge No. 4. Total log ban was already imposed in the entire province it is difficult to purchase such kind of hardwood “Ipil” and sizes in any registered lumberyard.
9.2.3.3. Since the construction of the FMR project was undertaken on phase by phase, the program of work should indicate the work to be accomplished in the particular budgeted year.
9.2.3.4. The LGU should ensure the continuity of the fund provided to the project.
9.2.4. Reshaping/Road Embankment of Sitio Marirong-Cayasan in Bgy. Nicanor
Zabala, Roxas, Palawan
9.2.4.1. Appropriate funds for concreting of roads instead of road reshaping
and gravelling since maintenance projects offer no long term
improvement on road conditions;
9.2.4.2. Ensure that no infrastructure projects shall be undertaken without
the required detailed engineering investigations, surveys and plans;
and
9.2.4.3. Monitor and prepare a report on project accomplishments duly
supported by equipment and fuel utilization reports and photographs
taken before, during and after project implementation.
9.2.5. Maintenance of Iniaran Farm to Market Road, Bgy. Labog, Sofronio Espanola,
Palawan
9.2.5.1. Appropriate funds for the concreting of farm-to-market roads instead of road maintenance projects in accordance with DPWH Department Order No. 11 to provide long-term benefits to the constituents
9.2.5.2. Prior to implementation of projects by administration, the LGU should
prepare Program of Work duly supported by the Plans and Specification as required activities of the detailed engineering of Annex “A” of the Revised IRR of RA 9184.Moreover, submission of accomplishment reports, reference points of road re-gravelling, photographs, fuel and equipment utilization reports should be submitted to validate the total project accomplishment and the reasonableness of quantity and cost of materials of the projects.
95
9.2.6. Maintenance of Kanangkaan Farm to Market Road, Bgy. Punang, Sofronio
Espanola, Palawan
9.2.6.1. Appropriate funds for the concreting of farm-to-market roads instead of road maintenance projects in accordance with DPWH Department Order No. 11 to provide long-term benefits to the constituents
9.2.6.2. Prior to implementation of projects by administration, the LGU should
prepare Program of Work duly supported by the Plans and Specification as required activities of the detailed engineering of Annex “A” of the Revised IRR of RA 9184.Moreover, submission of accomplishment reports, reference points of road re-gravelling, photographs, fuel and equipment utilization reports should be submitted to validate the total project accomplishment and the reasonableness of quantity and cost of materials of the projects.
9.2.7. Improvement and Rehabilitation of Bgy. Kalatagbak, Quezon, Palawan
9.2.7.1. Strictly adhere with the provisions set forth under GPPB Resolution No. 018-2006, dated December 6, 2006 in all projects to be undertaken By Administration;
9.2.7.2. Strictly comply with the provisions of R.A. No. 9184 in all government procurement; and
9.2.7.3. Instruct the ICO-Municipal Accountant to carefully review the vouchers’ supporting documents.
We recommended further that the management should cause immediate
submission of the documents identified herein and henceforth ensure strict
adherence with COA Memorandum No. 2005-027, COA-Circular No. 2009-001
and COA-Circular No. 2012-001.
9.2.8. Regravelling of Sitio Mati and Paratungon roads, Barangay Pangobilian,
Brooke’s Point, Palawan
9.2.8.1. Appropriate funds for the concreting of farm-to-market roads instead
of road maintenance projects in accordance with DPWH Department
Order No 11 s. 2014 dated February 03, 2014; and
9.2.8.2. Monitor and prepare a report on project accomplishments duly
supported by equipment and fuel utilization reports and photographs
taken before, during and after project implementation.
96
10.1. Implementation of FMR by Contract
10.1.1. Concreting of Kamuning Kamuning Road Phase II, Barangay Kamuning,
Puerto Princesa City, Palawan
The Local Chief Executive issued Memorandum Order No. 48 and 49 dated March 13, 2015 to the City Inspectorate Team of the City Engineering Office to strictly comply with the Audit Observation Memorandum No. 2015-005 (2014) dated February 18, 2015.
The City Engineering Office Inspectorate Team conducted site inspection
on April 7, 2015, upon the request of the contractor for the final billing and in compliance with the Memorandum Order No. 48 of the City Mayor with the following comments:
10.1.1.1. The program of works indicated two sets of 24” RCCP Drainage
when only one set was installed. The other set of unit was
converted to additional concrete pavement on the Y-intersection at
the entrance portion of the road project from the national highway;
10.1.1.2. Cracks along some blocks that are reported have already been
repaired with substantial material such as concrete epoxy and
asphalt sealant;
10.1.1.3. Pavement shoulder have already been replaced by the approved
aggregates with the required 1.00 meter width;
10.1.1.4. Visible rocks on the surface have been removed with the proper
procedure and replaced with concrete filling;
10.1.1.5. Peeling, scaling and other defects had been repaired accordingly;
10.1.1.6. Portions that are subjected to be “removed and replaced” had been
replaced, some of the remains are still on site; and
10.1.1.7. The bunk house was not visible (only portions remains) when the
COA Team visited the project site on January 2015, because the
project break camp on December 2014, and came back on January
to conduct the sealing of joints and other repairs instructed by the
City Inspectorate Team.
10.0 AUDITEE’S COMMENTS
97
10.1.2. Concreting of Inogbong Road, Bataraza, Palawan
The management has not yet commented on the audit observations.
10.1.3. Improvement of Malatgao-Culandanum-Panas-Linao Road, Bataraza,
Palawan
In response to the audit observations on the Improvement of Malatgao-
Culandanum-Panas-Linao Road, Bataraza, the Provincial Government of
Palawan provided the following comments:
It is indeed unfortunate that the contractor incurred
substantial delay in the implementation of the project. For such reason, please be advised that the proper liquidated damages has been imposed and the same was deducted and/or withheld from the claim for the 10% retention as per Disbursement Voucher No. 14-03-00316.
Furthermore, as per your advice, we have made it the policy of
our office to strictly monitor all project implementation to avoid any unnecessary or unreasonable delay in the completion of the project ant that repeated delay should warrant the blacklisting of the contractor involved.
The project was declared completed and accepted by the
barangay LGU and Municipal Mayor of Bataraza last January 8, 2014. Unfortunately, at the time of inspection last January 27, 2015, the project was already beyond the responsibility of the contractor.
Moreover, as much as we wanted to do repairs based on your
findings, we could no longer do it since DPWH 2nd District already took over the maintenance of the said road as part of the circumferential road they are constructing in the area.
Rest assured that the said concern will be coordinated with
DPWH office to ensure that necessary repairs will be executed.
10.2. Implementation of FMR by Administration
10.2.1. Graveling of Loblob to Calitang Road in Bgy. Bucana, El Nido, Palawan
The management has not yet commented on the audit observations.
98
10.2.2. Construction/Rehabilitation and Maintenance of Local Roads, Barangay
Poblacion to Mauringen, Araceli, Palawan
The management has not yet commented on the audit observations.
10.2.3. Construction of Nalbot-Old Guinlo Road Phase I and II, Bgy. Poblacion – Old
Guinlo, Taytay, Palawan
Management remarked that the observations and recommendations are
highly appreciated and assured that proper diligence will be exercised in truly
putting into practice the audit recommendations.
10.2.4. Reshaping/Road Embankment of Sitio Marirong-Cayasan in Bgy. Nicanor
Zabala, Roxas, Palawan
The management has not yet commented on the audit observations.
10.2.5. Maintenance of Iniaran Farm to Market Road, Bgy. Labog, Sofronio
Espanola, Palawan
The management has not yet commented on the audit observations.
10.2.6. Maintenance of Kanangkaan Farm to Market Road, Bgy. Punang, Sofronio
Espanola, Palawan
The management has not yet commented on the audit observations.
10.2.7. Improvement and Rehabilitation of Bgy. Kalatagbak, Quezon, Palawan
For the Improvement and Rehabilitation of FMR in Brgy. Kalatagbak, the
Municipal Government of Quezon provided the following comments:
The FMR project was some sort of an intervening activity
resulting from the need to rehabilitate to enable the passage of
heavy equipment to the KALAHI-CIDSS project in Brgy. Kalatagbak
which has long been delayed due to the non-passable condition
since it is the only route going to the KALAHI-CIDSS project’s site.
Due to LGU’s haste to address the project so as not to further delay
the implementation of the KALAHI-CIDSS project, the rehabilitation
of the FMR was undertaken by the LGU due to its commitment to
support the implementation of the KALAHI-CIDSS program in this
LGU. The undertaking of the said FMR was admittedly an
inadvertent neglect of the part of LGU to consider strict compliance
to existing laws/policies on the matter, and has committed said
error out of the pressing need to help the start of implementation
of the KALAHI-CIDSS project in the aforesaid barangay. The
rehabilitation of the FMR was likewise thought to be just part of
99
the routinary road improvement/maintenance activities of the LGU,
thus, no detailed engineering plan and specifications was prepared,
and its inclusion in the Annual Procurement Plan was not given due
consideration to be a hindering factor in its implementation, which
was not so, as you have pointed out in the AOM, and we concur
with your observation.
The supplier of fuel, oil and lubricants (FOL) used in the
implementation of FMR project is the LGU’s regular supplier
through a credit scheme, and withdrawal of fuel and oil to be used
for the subject project was on a per need basis. This is the reason
why the supply of FOL for the project was not bidded-out, and as
earlier mentioned, the project was deemed to be just a road
improvement/maintenance activity.
The billings for the withdrawal of FOL from the supplier were
just submitted to us on a monthly basis, after which processing for
payment is effected. During the processing of payments for the FOL
withdrawal, the date of the billings from the supplier went
unnoticed by the concerned staff reviewing and processing the
documents. We have also discussed with the suppler, the dates of
FOL withdrawals as stated in its billings, as it appears that multiple
withdrawals were made on the same day for a single heavy
equipment, and the supplier’s staff concerned admitted that she
inadvertently forgot to change the dates of each billing when she
generated the billings from her computer using the “copy and
paste” method. Nevertheless, we admit the neglect on our
concerned staff’s part to carefully review the documents being
processed, wherein the deficiencies/errors observed by COA could
have been avoided, and it would not appear that there has been a
splitting of contract to circumvent the requirement of the law.
Again, as mentioned, earlier, the withdrawal of FOL from the
supplier was on a per need basis during the implementation of the
FMR project, and billings for payment were just submitted by the
supplier to the LGU.
10.2.8. Regravelling of Sitio Mati and Paratungon roads, Barangay Pangobilian,
Brooke’s Point, Palawan
The required volume of 810m3 of sub-base coarse aggregates has been served in the noted areas. The program was designed for critical road portions
100
and sections requiring urgent rehabilitation, hence, the spot-regraveling. The LGU is however amenable to and will comply with the recommendations.
11.1. Implementation of FMR by Contract
11.1.1. Concreting of Kamuning Kamuning Road Phase II, Barangay Kamuning,
Puerto Princesa City, Palawan
The audit team were not satisfied on the submitted comments of the
City Engineering Inspectorate Team.
The approved Change Order and Request for Change Order with
justification were not submitted to the Audit Team. Based on the presented
pictures, the pavement shoulder aggregates on the same areas still needs
rectification based on the findings of the audit team.
11.1.2. Concreting of Inogbong Road, Bataraza, Palawan
11.1.3. Improvement of Malatgao-Culandanum-Panas-Linao Road, Bataraza,
Palawan
All the audit observations were well-taken by the concerned Auditee
Agencies. The Audit Team shall continue monitoring the actions taken by
management to ensure their compliance with the given recommendations.
11.2. Implementation of FMR by Administration
11.2.1. Graveling of Loblob to Calitang Road in Bgy. Bucana, El Nido, Palawan
11.2.2. Construction/Rehabilitation and Maintenance of Local Roads, Barangay
Poblacion to Mauringen, Araceli, Palawan
11.2.3. Construction of Nalbot-Old Guinlo Road Phase I and II, Bgy. Poblacion – Old
Guinlo, Taytay, Palawan
11.2.4. Reshaping/Road Embankment of Sitio Marirong-Cayasan in Bgy. Nicanor
Zabala, Roxas, Palawan
11.2.5. Maintenance of Iniaran Farm to Market Road, Bgy. Labog, Sofronio
Espanola, Palawan
11.2.6. Maintenance of Kanangkaan Farm to Market Road, Bgy. Punang, Sofronio
Espanola, Palawan
11.2.7. Improvement and Rehabilitation of Bgy. Kalatagbak, Quezon, Palawan
11.0 AUDIT TEAM’S EVALUATION AND REJOINDER
101
All the audit observations were well-taken by the concerned Auditee
Agencies. The Audit Team shall continue monitoring the actions taken by
management to ensure their compliance with the given recommendations.
11.2.8. Regravelling of Sitio Mati and Paratungon roads, Barangay Pangobilian,
Brooke’s Point, Palawan
The approved plan or Bill of Materials and Cost Estimates’ project description was the re-graveling of 3,240 meters of roads in Barangay Pangobilian. Nowhere in the document was it indicated that re-graveling shall apply only to critical road portions or sections. Since improvements on the two (2) sites are no longer fully visible during ocular inspection, we could not verify whether the 810m3 of sub-base coarse aggregates has been actually served in the noted areas.
102
Appendix 1 A - Concreting of Kamuning Road Phase II, Barangay Kamuning, Puerto
Princesa City, Palawan
Republic of the Philippines
Commission on Audit
Special Services Sector
TECHNICAL SERVICES OFFICE
Quezon City
INSPECTION REPORT FOR INFRASTRUCTURE PROJECT
Date of Report: 10 April 2015
Reference No.
Project Description Concreting of Kamuning Farm to Market Road Phase II
Location (as shown in the
approved location plan) Barangay Kamuning, Puerto Princesa City
Contracting Parties City Government of Puerto Princesa & E.V Villaos Trading
and Construction
Contract Date 20 February 2014 Contract Time 90 calendar days
Effectivity Date 16 March 2014 Expiry Date 14 June 2014
Subject of Inspection 100% Work Accomplishment
Objectives of
Inspection
1. To validate the existence of the reported accomplishments
2. To validate compliance of reported accomplishments with the approved plans and specifications
3. To validate if reported accomplishments are in accordance with the contract schedule
Date of Inspection 20 January 2015
Persons/Personnel
present during
Inspection
Name Position/Designation
/Office Signature
Juanito A. Nostratis ATL – Puerto
Princesa City
APPENDIX 1 – TECHNICAL AUDIT REPORT
103
Neomi O. Teope
Audit Team
Member –
Puerto Princesa
City
Nelda P. Gomez
Audit Team
Member –
Puerto Princesa
City
Persons/Personnel
present during
Inspection
John Jester L.
Cabulao
PSU – CSO
Member
Sheila B. Rallos PSU – CSO
Member
Anthony A. Badilla PSU – CSO
Member
Nena C. Zara PSU - CSO
Member
Kimberly Jam de la
Cruz PNNI – Member
Abigail L. Baisa PNNI – Member
Jomar V. Cua PNNI – Member
John Vincent M.
Recio
TAS II, Technical
Services, COA
Region IV-B
Amado M. Dador Project
Engineer, PPC
GROUND TRUTHING
Island: Luzon Province: Palawan City: Puerto Princesa
Barangay: Kamuning Contract Amount: P 7,800,438.00
Geographic Coordinates
(Starting Point)
Latitude : 9°31'44.11"N
Longitude :
118°37'19.71"E
104
A. Travel Description and Landmarks:
The inspected Farm-to-Market Road is located along Puerto Princesa South Road and
approximately 40 km away from Puerto Princesa City proper. The above mentioned
project has a pavement dimension of 5.0m width, 0.20m thick and 739m in length.
105
106
107
108
109
110
111
B. Inspection Results:
Latitude: 9°31'43.75"N
Longitude :
118°37'19.67"E
The project is not yet
complete at the time of
inspection as there were
still workers sealing
asphalt filler on the
concrete weakened joints
and in between visible
cracks when the team
arrived.
112
Latitude: 9°31'44.10"N
Longitude :
118°37'19.75"E
Latitude: 9°31'44.10"N
Longitude :
118°37'19.75"E
113
Latitude: 9°31'44.10"N
Longitude :
118°37'19.75"E
Digging of road side was
requested to verify the
thickness of item 311-PCCP
and found to be okay as
required in the approved
plans.
Latitude:
9°31'43.90"N
Longitude :
118°37'18.47"E
Road shoulders on both
sides of the concrete
pavement were made up of
river stones instead of
required Aggregate Surface
Course (Item-300) as
required in the Program of
Work.
114
Latitude:
9°31'43.90"N
Longitude :
118°37'18.47"E
Latitude:
9°31'43.98"N
Longitude :
118°37'17.28"E
Scaling and uneven
brooming of concrete were
observed at Sta. 0+ 070.*
115
Latitude:
9°31'44.00"N
Longitude :
118°37'17.04"E
Vehicle related scratches,
scaling, uneven brooming
and absence of asphalt
filler at sta. 0+ 080.
Latitude:
9°31'44.00"N
Longitude :
118°37'17.04"E
116
Latitude:
9°31'43.99"N
Longitude :
118°37'16.82"E
Spalling, uneven brooming
and absence of asphalt
filler at Sta. 0+089.
Latitude:
9°31'43.99"N
Longitude :
118°37'16.82"E
Serious transverse cracks,
uneven brooming and
absence of asphalt filler at
sta.0 + 089.
117
Latitude:
9°31'44.01"N
Longitude :
118°37'16.43"E
Scaling, poke marks,
chipping, uneven brooming
and absence of asphalt
filler at Sta. 0+ 098
Latitude:
9°31'44.01"N
Longitude :
118°37'16.43"E
118
Latitude:
9°31'44.15"N
Longitude :
118°37'16.35"E
Latitude:
9°31'44.06"N
Longitude :
118°37'15.86"E
Side cracks about 5m in
length, uneven brooming,
vehicle related concrete
scratches and unsealed
weakened joints at Sta.
0+ 123
119
Latitude: 9°31'44.06"N
Longitude :
118°37'15.86"E
Latitude:
9°31'44.09"N
Longitude :
118°37'15.64"E
120
Latitude:
9°31'44.06"N
Longitude :
118°37'15.64"E
Latitude:
9°31'44.07"N
Longitude :
118°37'15.33"E
Scaling, poke marks,
spillage of concrete were
not removed, unsealed
weakened joints and
uneven brooming were
observed at Sta. 0+130
121
Latitude: 9°31'44.07"N
Longitude:
118°37'15.33"E*
Latitude: 9°31'44.07"N
Longitude: 118°37'15.33"E
122
Latitude: 9°31'44.07"N
Longitude: 118°37'15.33"E
Settlement of about 2
concrete blocks coupled
with longitudinal cracks
beginning at Sta. 0+156
Latitude: 9°31'44.12"N
Longitude: 118°37'14.65"E
123
Latitude: 9°31'44.16"N
Longitude: 118°37'14.24"E
Spalling of weakened joint,
uneven broomimg,
transverse cracks, scaling,
side cracks about 2.5m in
length and poke marks at
Sta. 0+ 180.
124
Latitude: 9°31'44.23"N
Longitude: 118°37'13.16"E
Scaling, spalling of
unsealed weakened joints
and uneven brooming were
observed at Sta. 0+199
125
Latitude: 9°31'44.23"N
Longitude: 118°37'13.16"E
Latitude: 9°31'44.27"N
Longitude: 118°37'12.40"E
Serious transversal cracks
located within the middle
third of two concrete
blocks, absence of asphalt
filler, uneven brooming and
scaling at Sta. 0+ 221
126
Latitude: 9°31'44.27"N
Longitude: 118°37'12.40"E
Latitude: 9°31'44.35"N
Longitude: 118°37'11.24"E
Multiple road defects such
as serious scaling, poke
marks ,absence of asphalt
filler, spalling, uneven
brooming and serious
transverse cracks were
observed from the
beginning of Sta.0 + 249
127
Latitude: 9°31'44.38"N
Longitude: 118°37'11.21"E
Latitude: 9°31'44.45"N
Longitude:
118°37'11.02"E*
128
Latitude: 9°31'44.39"N
Longitude: 118°37'10.39"E
Scaling, spalling, uneven
brooming and spillage of
concrete that were not
remove and unsealed
weakened joints at Sta.
0+284
Latitude: 9°31'44.39"N
Longitude:
118°37'10.39"E
Latitude: 9°31'44.39"N
Longitude: 118°37'10.39"E
129
Latitude: 9°31'44.39"N
Longitude: 118°37'9.89"E
Transverse cracks, scaling,
spalling, vehicle related
concrete scratches, uneven
brooming and unsealed
weakened joints at Sta. 0+
295
Latitude: 9°31'44.41"N
Longitude: 118°37'10.01"E
Latitude: 9°31'44.49"N
Longitude: 118°37'9.48"E
130
Latitude: 9°31'44.49"N
Longitude: 118°37'9.48"E
Latitude: 9°31'44.39"N
Longitude: 118°37'9.59"E
Latitude: 9°31'44.49"N
Longitude: 118°37'9.48"E
131
Latitude: 9°31'44.48"N
Longitude: 118°37'9.24"E
Spalling, serious scaling,
longitudinal cracks, vehicle
related road scratches,
uneven brooming of
concrete and unsealed
weakened joints at Sta.
0+313
Latitude: 9°31'44.48"N
Longitude:
118°37'9.24"E
Latitude: 9°31'44.50"N
Longitude: 118°37'8.58"E
132
Latitude:
9°31'44.58"N*
Longitude: 118°37'7.89"E
Scaling, spalling, vehicle
related road scratches,
concrete spillage which
were not removed/clean,
uneven brooming and
unsealed weakened joints
at Sta. 0+362
Latitude: 9°31'44.58"N
Longitude: 118°37'7.89"E
Latitude: 9°31'44.55"N
Longitude: 118°37'7.62"E
133
Latitude:9°31'44.64"N
Longitude:118°37'7.18"E
Poke marks, vehicle related
road scratches, uneven
brooming and unsealed
weakened joints between
concrete blocks at Sta.
0+384
9°31'44.64"N
118°37'7.18"E
Latitude: 9°31'44.69"N
Longitude: 118°37'6.41"E*
Scaling, longitudinal and
transverse cracks, poke
marks, unsealed weakened
joints, vehicle related
scratches and spalling at
Sta. 0+402.
134
Latitude: 9°31'44.69"N
Longitude: 118°37'6.41"E
Latitude: 9°31'44.69"N
Longitude: 118°37'6.41"E
Latitude: 9°31'44.71"N*
Longitude: 118°37'6.00"E
135
Latitude: 9°31'44.71"N
Longitude: 118°37'6.00"E
Latitude: 9°31'44.76"N
Longitude: 118°37'5.61"E
Transverse cracks, scaling,
uneven brooming and
absence of asphalt filler at
Sta. 0+ 427. Also, captured
in one of the photos taken
is a laborer preparing
asphalt filler as the team
conducts inspection.
Latitude: 9°31'44.76"N
Longitude: 118°37'5.61"E
136
Latitude: 9°31'44.76"N
Longitude; 118°37'5.61"E
Latitude: 9°31'44.75"N
Longitude: 118°37'4.76"E
Scaling of concrete
pavement and stones of
about 4 inches in dia. were
observed exposed on
pavement surfaces which
indicate that incorrect sizes
of gravel were used in the
construction of Item 311 -
Portland Cement Concrete
Pavement located at the
beginning of Sta. 0+ 453.
Latitude:
9°31'44.75"N*
Longitude: 118°37'4.76"E
137
Latitude: 9°31'44.89"N
Longitude:
118°37'3.39"E*
Scaling of concrete
pavement and transverse
cracks were observed at
the beginning of Sta.
0+493. Likewise, stones of
about 4 inches were
exposed on concrete
pavement which indicate
that incorrect sizes of
gravel were used in the
construction of Item 311-
PCCP.
Latitude:
9°31'44.83"N
Longitude: 118°37'3.39"E
Latitude: 9°31'44.83"N
Longitude: 118°37'3.39"E
138
Latitude: 9°31'44.90"N
Longitude: 118°37'2.67"E
Spalling, scaling,
transversal cracks and
unsealed weakened joints
were observed at Sta.
0+519
Latitude:
9°31'44.90"N*
Longitude: 118°37'2.67"E
139
Latitude: 9°31'44.90"N
Longitude: 118°37'2.67"E
Latitude: 9°31'44.97"N
Longitude: 118°37'1.88"E
Concrete spillage were not
removed, spalling of
concrete, unsealed
weakened joints, uneven
brooming and the use of
river stones for road
shouldering among others
were observed at Sta. 0+
548.
Latitude: 9°31'44.97"N
Longitude: 118°37'1.88"E
140
Latitude: 9°31'44.97"N
Longitude: 118°37'1.88"E
Latitude: 9°31'45.04"N
Longitude: 118°37'0.31"E
Transverse cracks located
within the middle third of
the concrete block, scaling
and unsealed weakened
joints at Sta. 0+600.
Latitude: 9°31'45.04"N
Longitude: 118°37'0.31"E
141
Latitude: 9°31'45.48"N
Longitude: 118°36'56.98"E
Transversal cracks,
spalling, uneven brooming
and unsealed weakened
joints at Sta. 0+ 703
Latitude: 9°31'45.48"N
Longitude: 118°36'56.98"E
Latitude: 9°31'45.79"N
Longitude:118°36'56.91"
Serious scaling, uneven
brooming and unsealed
weakened joints were
observed at the end of the
project.
142
Latitude: 9°31'45.79"N
Longitude: 118°36'56.91"E
Latitude: 9°31'45.19"N
Longitude: 118°36'56.44"E
Scaling, chipping of
concrete, uneven
brooming, and unsealed
weakened joints were
observed at the end of the
road project.
Narrative Findings:
The undersigned together with the COA Audit Team and Members of Civil
Society Organization (CSO) mentioned above proceeded to Barangay Kamuning,
Puerto Princesa City on January 20, 2015 to conduct inspection of the infrastructure
project “Concreting of Kamuning Road – Phase II”.
With reference to the submitted documents provided by the agency and
geotagged photos taken at the project site, hereunder are our noted observations:
1. Project Billboard was not found when the team arrived at the project site
which resulted to a discrepancy amounting of - ₱13,401.25;
2. The contractor put up only makeshift store room instead of constructing
field office/bunkhouse to store the construction materials as shown in the
submitted pictures with discrepancy amounting to - ₱68,178.88;
143
3. The concreting of Kamuning Road – Phase II should have been expired on
June 14, 2014 as stated in the documents provided. However, the project
was still on-going as laborers can be seen working at the project site when
the inspectorate team arrived which resulted to a time delay of 220
calendar days, calculated from the time the project expired to the time of
inspection on 20 January 2015 which resulted to Liquidated Damages
amounting to - ₱326,058.31;
4. Road shoulders were made of small river rocks/boulder instead of using
Item 300 – Aggregate Surface Course, as required in the plans, which
resulted to a discrepancy of - ₱1,052,209.24;
5. Only one line RCPC culvert was constructed instead of two with headwall,
with a discrepancy of - ₱80,081.62;
6. Data gathered from geotagging revealed various defects along the sections
of the road as shown in table below:
Station Description Location Deficiencies
Sta.
0+089
Serious
transverse cracks
involving 2
concrete blocks.
Latitude:
9°31'43.99"N
Longitude
118°37'16.82"E
₱37,403.33
Sta.
0+123
Side Cracks about
5m in length
which calls for
the removal of
two (2) concrete
blocks
Latitude:
9°31'44.06"N
Longitude
118°37'15.86"E
₱37,403.33
Sta.
0+156
Settlement of
about 2 concrete
blocks with
longitudinal
cracks.
Latitude:
9°31'44.07"N
Longitude:
118°37'15.33"E
₱37,403.33
Sta.
0+221
Serious
transversal
cracks located
within the middle
third of two
concrete blocks.
Latitude:
9°31'44.27"N
Longitude:
118°37'12.40"E
₱37,403.33
144
Station Description Location Deficiencies
Sta.
0+249
Longitudinal
Cracks running
diagonally in a
concrete block.
Latitude:
9°31'44.35"N
Longitude:
118°37'11.24"E
₱18,701.66
Sta.
0+313
Serious scaling
involving two (2)
concrete blocks;
Longitudinal
cracks in single
concrete block.
Latitude:
9°31'44.48"N
Longitude:
118°37'9.24"E
Latitude:
9°31'44.50"N
Longitude:
118°37'8.58"E
₱56,104.98
Sta.
0+402
Longitudinal
Cracks covering
Two (2) concrete
blocks. Major
scaling involving
Two (2) concrete
blocks and
two(2) blocks
with serious
transverse cracks
Latitude:
9°31'44.69"N
Longitude:
118°37'6.41"E
Latitude:
9°31'44.69"N
Longitude:
118°37'6.41"E
Latitude:
9°31'44.71"N
Longitude:
118°37'6.00"E
₱224,419.98
Sta.
0+427
Serious
transverse cracks
located within
the middle third
of two concrete
blocks.
Latitude:
9°31'44.76"N
Longitude:
118°37'5.61"E
₱37,403.33
Sta.
0+600
Serious
transverse cracks
located within
the middle third
of two concrete
blocks.
Latitude:
9°31'45.04"N
Longitude:
118°37'0.31"E
₱37,403.33
Sta. 0+ One (1) Concrete Latitude: 9°31'45.79"N ₱18,701.66
145
Station Description Location Deficiencies
703 Blocks with
serious scaling
Longitude:118°36'56.91"
Total Amount
₱542,347.93
TOTAL DEFICIENCY = 13,401.25 + 68,178.88 + 326,058.31 +1,052,209.24
+ 80,081.62 +542,347.93
= ₱2,082,277.23
In view of the above, the undersigned in a meeting with the members of CSO
last 05 February 2015 at the office of the City Auditor, PPC, recommends that core
samples shall be taken from various sections of the concrete pavement where the
locations will be specified by members of CSO using coring test to determine further
the extent of additional sections of the concrete pavement which will be subjected for
removal and replacement.
Sections along the road with defects as shown in the gathered geotagged photos
should be rectified by the contractor.
The reported 61.16% complete as reflected in the submitted Statement of Work
Accomplished for the period ending 23 May 2014 cannot be fully validated due to
various discrepancies mentioned above.
The above mentioned deficiencies were based on the initial findings gathered
from geotagging which excludes the deficiencies that may arise from the results of
coring test being requested to the agency.
Inspection conducted by:
SGD.
JOHN VINCENT M. RECIO
TAS II, Technical Services, COA Region IV-B
Date: April 10, 2015
Reviewed by:
SGD.
ROLANDO D. LORENZO
OIC-Service Chief, Technical Services, COA Region IV-B
Date: April 10, 2015
146
Appendix 1B - Concreting of Inogbong Road, Bataraza, Palawan
147
148
149
150
151
152
153
154
155
156
Appendix 1C – Rehabilitation of Malatgao-Culandanum-Panas-Linao Road, Bataraza,
Palawan
TECHNICAL INSPECTION REPORT MALATGAO-CULANDANUM-PANAS-LINAO ROAD
Date of Report: April 20, 2015
Project Description Improvement of Malatgao - Culandanum - Panas - Linao Road
Location (as shown in the
approved location plan) Bataraza, Palawan
Contracting Parties Provincial Government of Palawan & Kim Harold Trading
Manufacturing & Construction , PPC
Contract Date 15 January 2013 Contract Time 120 calendar
days
Effectivity Date 22 March 2013 Expiry Date 19 July 2013
Subject of Inspection 100% Work Accomplishment
Objectives of
Inspection
1. To validate the existence of the reported accomplishments
2. To validate compliance of reported accomplishments with
the approved plans and specifications
3. To validate if reported accomplishments are in accordance
with the contract schedule
Date of Inspection January 27, 2015
Persons/Personnel
present during
Inspection
Name Position/Designation/Office
Edencio R. Berba State Auditor IV / Team Leader
Irish Jay Q. Pasamonte State Auditor II / Team
Member
Elvys Kenneth E. Miguel State Auditor I / Team
Member
Helen Q. Diaz State Auditor III / Team Member
Timothy Siebo T. Boeheme
Isaac E. Saniban
Jerald B. Bagnate
Albert Q. Meorom
Representative of Western
Philippines University, Palawan
157
Erlinda R.J. Goh Private Citizen of Puerto
Princesa City, Palawan
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality:Bataraza
Barangays: Malatgao,
Culandanum, Panas, Linao Others:
Geographic Coordinates
(Starting Point)
Latitude :
8°37'44.36"N
Longitude :
117°28'7.70"E
A. Travel Description and Landmarks:
The Malatgao-Culandanum-Panas-Linao Farm to Market Road is located in Southern
part of Bataraza, Palawan
158
B. Inspection Results:
Narrative
Latitude: 8°37'44.36"N
Longitude : 117°28'7.70"E
Start of the Project and beginning
station of re-shaping of road, Item
200 and Item 201, with 6.1m road
width, Station 0 + 000
Photo
Narrative
Latitude: 8°37'44.36"N
Longitude : 117°28'7.70"E
Intermittent Potholes Located with
intervals of about 7 meters. Geo-tag
at Station 0 + 180
Photo
Narrative
Latitude: : 8°38'18.24"N
Longitude : 117°27'59.48"E
Undefined earth side ditches and
crowning of Roadway and loosed
surfacing materials with 6.0 meters
width. Geo-tag at station 1 + 280
Photo
159
Narrative
Latitude: 8°38'30.77"N
Longitude : 117°27'56.56"E
Loosed surfacing materials with
oversized aggregates about 5 meters
in length, undefined earth side ditches
and crowing of roadways with 6.0
meters in road width. Geo-tag at
Station 1 + 878
Photo
Narrative
Latitude: 8°38'52.05"N
Longitude : 117°26'54.49"E
2nd Road Intersection with ave. width
5.5 meters. Geo-tag at Station 3 + 092
Photo
Narrative
Latitude : 8°39'3.76"N
Longitude : 117°27'2.98"E
Potholes with impounded water,
undefined earth side ditches and
crowning of roadway. Geo-tagged at
Station 3 + 403
Photo
160
Narrative
Latitude: 8°39'27.24"N
Longitude : 117°27'4.19"E
Damaged Reinforced Concrete Box
Culvert with detached front left wing
wall and eroded road approach of
about 12.5 sq.m. Geo-tagged at
Station 5 + 235
Photo
Narrative:
Latitude: 8°39'27.24"N
Longitude : 117°27'4.19"E
Photo shows the clogged upstream
section of RCBC with various debris
that block the opening of its
waterways
Photo
161
Narrative
Latitude: 8°41'35.88"N
Longitude : 117°26'57.06"E
Muddy Pothole with Loosed
Surfacing Materials. Geo-tagged at
Station 10 + 248
Photo
Narrative
Latitude: 8°42'2.29"N
Longitude : 117°26'52.75"E
Properly Maintained Road leading to
end of project. Geo-tagged at Station
11 + 095
Photo
Narrative
Latitude: 8°42'2.25"N
Longitude : 117°26'52.82"E
End of the Project in front of Linao
Elementary School with 6.0m road
width .Geo-tagged at Station 11 +
100
Photo
162
The undersigned proceeded to Puerto Princesa City, Province of Palawan on
January 25, 2015 and coordinated with the Team member. The following day, January
26, 2015, the Team travelled to Bataraza, Palawan. The next day, on January 27, the
Team met with Engr. Regino B. Grande – CE II of PEO, Palawan and discuss with him
the procedures and manner on which the inspection should be done. Review of the
submitted documents revealed the following:
The said project is a Re-shaping and Re-gravelling of 10.5 kilometer road and
Construction of 4 barrels of Reinforce Concrete Box Culvert, with the following
programmed Items.
Item No. Description Quantity Unit
SPCL-1 General Requirements d. Project Sign Board 2.0 sets
e. Safety and Health 1.0 lot
f. Temporary Bunkhouse 1.0 lot
SPCL -2 Re-Shaping & Ditching 10.50 Km. 200 Aggregate Sub-Base Course 500.00 cu.m.
201 Aggregate Base Course 2,674.00 cu.m.
SPCL -3 Const. of 4 Barrel RCBC 1.0 unit
The project starts at Km. 237 + 500 and ends at Km. 248 + 000 with a total
length of 10.50 km., as per submitted Program of Work by the Agency.
The project duration expired last June 21, 2013, but it was only completed on
January 08, 2014, or 202 days after its expiration. Certification submitted by
the agency dated 10 January 2014 disclosed that the said project was
completed beyond project duration and impost Liquidated Damages.
The Team proceeded in the project site on January 27, 2015 and conducted
actual measurement by using of a digital type walking measure and GPS
android cellphone for Geo-tagging.
Project Billboard for the project was nowhere to find at the beginning and end
of the project. According to Engr. Grande it might have been dismantled by the
local residence.
Engr. Grande pinpointed to the team the start of the project with the following
data collected and shown in the geo-tagging:
163
Post Kilometer Reading
Station REMARKS
Km 237+500 0+000 Start of the Project and beginning station of re-shaping of road, Item 200 and Item 201 , Road Width= 6.1 m
Km 237 + 580 0+180 Road defect: Intermittent Potholes located with intervals of about 7m.
Km 238 + 780 1+280 Undefined earth side ditches and crowning of roadway and loosed surfacing materials about 5 meters in road length
Km239 + 378 1+878 Loosed surfacing materials with oversized aggregates about 5 meters in length, undefined earth side ditches and crowning of roadway with 6.0m width
Km 240 + 592 3 + 092 2nd Road Intersection with ave. width 5.5m
Km 240 + 903 3 + 403 Potholes with impounded water , undefined earth side ditches and crowning of roadway
Km242 + 735 5+ 235 Damage Reinforce Concrete Box Culvert with detached front left wing wall
Km. 247 + 748 10 + 248 Loosed surfacing materials with muddy pothole
Km 248 + 600 11 + 100 Site of Linao Elementary, properly maintained and compacted section of road , 6.0 m width, End of Project
The aforementioned collected data were based on measurement thru walking
measure instrument which were not exactly coincided but almost near with the data
collected in the geo-tagging.
The damaged four (4) barrel Reinforce Concrete Box Culverts ( 6 m x 12 m) at
station Km 5+235 has a detached left wing wall from its major structure and an
eroded road approach of about 12. 5sq.m. This may be due to the various debris that
block the opening of RCBC waterways and forcing the water to change course and
damaged the said section of the RCBC approached road. De-clogging of the opening of
the RCBC will help the free flow of water thru the RCBC and repair of the wing wall
and putting embankment on the damage road approached will lengthen its years of
usage.
As per gathered data, the 11,100 linear meters (11.1 Km.) actual length
measured by the undersigned has exceed the programmed length of 10,500 meters
(10.5Km.) and the measured average width of 6 meters conformed with the
programmed width.
The defects noted during actual inspection ranging from loose surfacing
materials, undefined earth side ditches and crowning of roadways, are the common
164
defect that arises in the road re-graveling. Rectification of the said defects should be
done immediately by the contractor to avoid further damage to the road project.
Inspection conducted by:
EDWIN G. IGLESIA
SA II, Technical Services
Reviewed by:
ROLANDO D. LORENZO
OIC- Service Chief, Technical Services
165
Appendix 1 D – Maintenance of Iniaran FMR, Bgy. Labog, Sofronio Española,
Palawan
Republic of the Philippines
Commission on Audit
Special Services Sector
TECHNICAL SERVICES OFFICE
Quezon City
INSPECTION REPORT FOR INFRASTRUCTURE PROJECT
Date of Report: 20 April 2015
Reference No.
Project Description Repair and Maintenance of Labog – Iniaran Farm to
Market Road
Location(as shown in
the approved location
plan)
Barangay Labog, Sofronio Espanola, Palawan
Contracting Parties
Municipal Government of Sofronio Espanola, Palawan and
Pulot Petron Service Station and Herenzo Gasoline Station
for the supply of Fuels and Lubricants ( Project by
Administration)
Contract Date
No Submitted
Contract
Agreement
Contract Time N/A
Effectivity Date N/A Expiry Date N/A
Subject of
Inspection 100% Work Accomplishment
Objectives of
Inspection
4. To validate the existence of the reported accomplishments 5. To validate compliance of reported accomplishments with
the approved plans and specifications 6. To validate if reported accomplishments are in accordance
with the contract schedule
Date of Inspection January 22, 2015
166
Persons/Personnel
present during
Inspection
Persons/Personnel
present during
Inspection
Name Position/Designation
/Office Signature
Engr. Sagani P.
Virrey
Munincipal
Engineer
Corsennie A.
Yan
Audit Team Leader
– Sofronio Espanola
Ma. Aceili V.
Paduga
Audit Team
Member – Sofronio
Espanola
John Vincent
Recio
TAS-II, Technical
Services, COA
Region IV - B
Judith M.
Hilario CSO – Member
Reniel Z.
Rocaberte CSO – Member
Hilda M.
Gabuco CSO – Member
Cecilia C. Castro CSO – Member
Karen D. Banda CSO – Member
Antonio E.
Francisco CSO – Member
Danny P.
Cabiguen CSO – Member
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: Sofronio
Española
Barangay: Labog Project Cost: P75,000.00
Geographic Coordinates
(Starting Point)
Latitude : 9° 3'43.44"N
Longitude :118°
3'38.86"E
167
A. Travel Description and Landmarks:
The inspected Farm-to-Market Road is located along Puerto Princesa South Road,
Sofronio Espanola, Palawan and approximately 21km away from Pulot Center
Quarry Site where aggregates are sourced according to the Municipal Engineer.
168
B. Inspection Results:
Latitude: 9° 3'43.44"N
Longitude : 118° 3'38.86"E
Labog-Iniaran FMR begins with the
exception of an old concrete
pavement from sta.0+000 – sta. 0+110.
169
Latitude: 9° 3'34.00"N
Longitude : 118° 3'52.00"E
Road shoulders were already covered
with vegetation - geotag at Sta.0+505
Latitude: 9° 3'31.00"N
Longitude : 118° 4'1.00"E
Impounding of water at Sta.0+801
170
Latitude: 9° 3'31.00"N
Longitude : 118° 4'3.00"E
Potholes taken at Sta.0+ 867
Latitude: 9° 3'31.00"N
Longitude : 118° 4'3.00"E
171
Latitude: 9° 3'32.00"N
Longitude : 118° 4'6.00"E
Interview with Mr.Hadium Nassad,
local resident thereat, attested that the
Municipal Engineering Office
conducted maintenance work on the
subject road once only last year.
Geotag Photos taken at Sta.0+ 950
Latitude: 9° 3'36.00"N
Longitude : 118° 4'26.00"E
Road Shoulders on both sides of the
graveled road were already covered
with vegetation.
172
Narrative Findings:
The Audit Team III proceeded to the Municipality of Sofronio Espanola on
January 22, 2015 to make courtesy call to Hon. Marsito Acoy, Municipal Mayor,
Sofronio Espanola, Palawan, and discuss the purpose of Team’s visit which pertains to
the issued COA Office Order No. 2014-081 dated December 22, 2014. After some
discussions with Mayor Acoy, the Municipal Accountant brought the Team to the
Office of the Municipal Engineer Headed by Engr. Isagani P. Virrey to interview him
with regards to the contents of the Office Order and requested him for relevant
documents needed in the Team’s Audit Activities only to find out the following:
Latitude: 9° 3'29.00"N
Longitude : 118° 5'41.00"E
Sta. 5+000 end of the road project.
The conditions of the graveled sections
from Sta.0+110 to Sta.5+000 were
almost the same except for some
potholes observed at sta. 0+801 and
sta. 0+867.
The undersigned cannot fully
determine the total consumption of the
various equipment used in the project
due to absence of Program of Works,
Approved Plans and Contract
Agreement.
In an interview by the Audit Team to
Mr. Hadium Nassad a Lupon
Tagapamayapa in the area allegedly
claimed that maintenance work along
Iniaran Road was carried out by the
agency only once last year. As to
alleged vegetation control, there were
no longer traces of cut/trimmed foliage
found when the team arrived.
173
The maintenance of Labog – Iniaran FMR was allegedly implemented in the absence of approved plans, profile and cross-section which were the basic requirements in the preparation of review and inspection;
The only documents provided by the ATL that were gathered from the Municipal Accountant were various Obligation Requests, Journal Entry Voucher, unnumbered Job Order, Withdrawal Slips, Statement of Account and Incomplete OR from Pulot Petron Service Station, Purchase Requests, Collection Receipt from Herenzo Gasoline Station and Program of Works with all items of works expressed in lumpsum;
The alleged work items accomplished in the project can only be identified by the Municipal Engineer thru pinpointing without any documentary reference;
The Team has no recourse but to gather geotag data based on the pinpointed location of the Municipal Engineer. The data collected were shown in the prepared Inspection Report. Evaluation of work accomplished and technical evaluation of the project could
not be made due to the absence of documentary requirements as stated under COA
Memorandum No. 2005-027 and COA Circular No. 2009-001 dated February 12, 2009
and COA-Circular No. 2012-001 dated June 14, 2012, to wit:
1. Approved plans, profile and cross section 2. Agency’s design standard 3. Sales invoice of all materials involved in the project 4. Contract Agreement between the Agency and Suppliers 5. Approved Purchase Order 6. Certificate of Completion 7. Approved Material Source Maps from the Provincial Engineering Office and
Nearest DPWH District Office 8. Heavy and Light Equipment Utilization Report for CY 2014 9. Municipal Inventory Report of existing Light and Heavy Equipment 10. Construction Schedule 11. Materials Quality Control Test Results 12. Photographs before, during and after construction per RA 6954
With reference to Obligation Requests # 20031400749 and 20031400750
provided by the ATL, the amount of items procured for the maintenance of Labog -
Iniaran FMR has reached
P 51,233.909
174
Appendix 1 E – Maintenance of Kanangkaan FMR, Bgy. Punang, Sofronio Española,
Palawan
Republic of the Philippines
Commission on Audit
Special Services Sector
TECHNICAL SERVICES OFFICE
Quezon City
INSPECTION REPORT FOR INFRASTRUCTURE PROJECT
Date of Report: 20 April 2015
Reference No.
Project Description Repair and Maintenance of Kanangkaan FMR
Location (as shown in
the approved location
plan)
Barangay Punang, Sofronio Española, Palawan
Contracting Parties “Project by Administration”
Contract Date
No Submitted
Contract
Agreement
Contract Time N/A
Effectivity Date N/A Expiry Date N/A
Subject of Inspection 100% Work Accomplishment
Objectives of
Inspection
1. To validate the existence of the reported accomplishments 2. To validate compliance of reported accomplishments
with the approved plans and specifications 3. To validate if reported accomplishments are in
accordance with the contract schedule
Date of Inspection January 22, 2015
Name Position/Designation/Office Signature
Engr. Sagani P.
Virrey
Municipal Engineer,
Sofronio Espanola
175
Persons/Personnel
present during
Inspection
Corsennie A. Yan Audit Team Leader –
Sofronio Espanola
Ma. Aceili V. Paduga Audit Team Member
– Sofronio Espanola
John Vincent Recio
TAS II, Technical
Services, COA Region
IV - B
Judith M. Hilario WPU, Palawan
Reniel Z. Rocaberte WPU, Palawan
Hilda M. Gabuco WPU, Palawan
Cecilia C. Castro Pulot Center Farmers
Association
Karen D. Banda Pulot 2 Farmers
Association
Antonio E. Francisco
Piatan Irrigators
Community
Association
Danny P. Cabiguen Palawan NGO
Network
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: Sofronio
Española
Barangay: Kanangkaan Project Cost: P63,500.00 (per submitted Obligation
Request)
Geographic Coordinates
(Starting Point)
Latitude : 9° 0'56.80"N
Longitude :118°
3'17.72"E
C. Travel Description and Landmarks:
176
The Kanangkaan Farm-to-Market Road is located along Puerto Princesa South Road,
Sofronio Espanola, Palawan and approximately 220 lm away from Punang Quarry
Site where aggregates are sourced according to the Municipal Engineer.
177
Latitude: 9° 0'56.80"N
Longitude : 118° 3'17.72"E
to
Latitude: 9° 0'56.80"N
Longitude : 118° 3'17.72"E
Geotagging from the beginning of
Kanangkaan road to sta.0+421(marker 2)
did not pushed through due to presence of
heavy equipment doing maintenance work
when the Team Arrived.
Latitude: 9° 1'27.00"N
Longitude : 118° 2'52.00"
Road intersection between
Kanangkaan road and road leading to
Punang quarry site which is about
220m away. Geotag at Sta 1+208
178
Latitude: 9° 1'32.00"N
Longitude : 118° 2'55.00"E
Punang quarry site, place where the
aggregates used in the maintenance of
Kanangkaan road were extracted and
is just about 220m away from the
intersection of Kanangkaan road.
Latitude: 9° 1'49.00"N
Longitude : 118° 2'29.00"E
Newly re-shaped section of
Kanangkaan road - Geotag at
sta.2+230
179
Latitude: 9° 1'56.00"N
Longitude : 118° 2'3.00"E
The road project ends at
sta.3+160.
The undersigned cannot fully
determine the total consumption of the
various equipment used in the project
since there were already maintenance
activities taking place on various
sections of the subject FMR and due to
absence of Program of Works,
Approved Plans, Contract
Agreementand equipment utilization
report for the project.
In an interview by the Audit Team
to Mr. Zacarias Abid, Punong Barangay
at Barangay Punang allegedly claimed
that maintenance work along
KanangkaanRoad was carried out by
the agency only once last year and
there were 20 truckloads of aggregates
contributed by CERI a nearby mining
firm in the maintenance of
Kanangkaan road.
Narrative Findings:
B. Inspection Results:
The Audit Team III proceeded to the Municipality of Sofronio Espanola on
January 22, 2015 to make courtesy call with Hon. Marsito Acoy, Municipal Mayor,
Sofronio Espanola, Palawan, and discuss the purpose of Team’s visit which pertains
to the issued COA Office Order No. 2014-081 dated December 22, 2014. After
some discussions with Mayor Acoy, the Municipal Accountant brought the Team to
the Office of the Municipal Engineer Headed by Engr. Isagani P. Virrey to interview
him with regard to the contents of the Office Order and requested him for relevant
documents needed in the Team’s Audit Activities only to find out the following:
180
The maintenance of Kanangkaan FMR was allegedly implemented in the absence of approved plans, profile and cross-section which were the basic requirements in the preparation of review and inspection;
The only documents provided by the ATL that were gathered from the Municipal Accountant were Obligation Requests, Withdrawal Slips and Purchase Request;
The alleged work items accomplished in the project can only be identified by the Municipal Engineer thru pinpointing without any documentary reference;
The Team has no recourse but to gather geotag data based on the pinpointed location of the Municipal Engineer. The data collected were shown in the prepared Inspection Report.
Evaluation of work accomplished and technical evaluation of the project
could not be made due to the absence of documentary requirements as stated
under COA Memorandum No. 2005-027 and COA Circular No. 2009-001 dated
February 12, 2009 and COA-Circular No. 2012-001 dated June 14, 2012, to wit:
1. Approved plans, profile and cross section 2. Agency’s design standard 3. Sales invoice of all materials involved in the project 4. Contract Agreement between the Agency and Suppliers 5. Approved Purchase Order 6. Certificate of Completion 7. Approved Material Source Maps from the Provincial Engineering Office and
Nearest DPWH District Office 8. Heavy and Light Equipment Utilization Report for CY 2014 9. Municipal Inventory Report of existing Light and Heavy Equipment 10. Construction Schedule 11. Materials Quality Control Test Results 12. Photographs before, during and after construction per RA 6954
With reference to Obligation Request # 200031400744 provided by the ATL,
the amount of items procured for the maintenance of Kanangkaan FMR was only
P 5,301.00
Inspection conducted by:
JOHN VINCENT M. RECIO
TAS II, Technical Services, COA Region IV-B
Date: April 20, 2015
Reviewed by:
ROLANDO D. LORENZO
OIC-Service Chief, Technical Services, COA Region IV-B
Date: April 20, 2015
181
Appendix 1F – Improvement and Rehabilitation of Bgy. Kalatagbak, Quezon,
Palawan
TECHNICAL INSPECTION REPORT BARANGAY KALATAGBAK FARM-TO-MARKET ROAD
Date of Report: April 20, 2015
Project Description Improvement & Rehabilitation of Barangay Kalatagbak Farm to
Market Road (FMR)
Location(as shown in the
approved location plan) Quezon, Palawan
Contracting Party Municipal Government of Quezon, Palawan
Mode of Procurment By Administration Contract Time Not Stated in POW
Effectivity Date Upon Released of
Fund Expiry Date Not Applicable
Subject of Inspection 100% Work Accomplishment
Objectives of
Inspection
7. To validate the existence of the reported accomplishments
8. To validate compliance of reported accomplishments with the
approved plans and specifications
9. To validate if reported accomplishments are in accordance with
the contract schedule
Date of Inspection January 26, 2015
Persons/Personnel
present during
Inspection
Name Position/Designation/Office
Edencio R. Berba State Auditor IV / Team Leader
Irish Jay Q. Pasamonte State Auditor II / Team Member
Elvys Kenneth E. Miguel State Auditor I / Team Member
Helen Q. Diaz State Auditor III / Team Member
Timothy Siebo T. Boehme
Isaac E. Saniban
Jerald B. Bagnate
Albert Q. Meorom
Representatives of Western Philippines
University, Palawan
Erlinda R.J. Goh Private Citizen of Puerto Princesa
City, Palawan
182
GROUND TRUTHING
Island: Luzon Province: Palawan Municipality: Quezon
Barangay: Kalatagbak Others:
Geographic Coordinates
(Starting Point)
Latitude :
9°15'20.32"N
Longitude :
118°5'59.19"E
A. Travel Description and Landmarks:
Road starts near the Iwahig River at Sitio Maslog and ends at the Barangay Hall.
Photo of Iwahig River:
183
B. Inspection Results:
Narrative
Latitude: 9°15'20.32"N
Longitude : 118°5'59.19"E
Start of the Project and beginning
station of Improvement &
Rehabilitation of Brgy. Kalatagbak
FMR, with 5.0m road width. Geo-
tagged at Station 0 + 000
Photo
Narrative
Latitude: 9°15'18.61"N
Longitude : 118°6’18.12"E
Intermittent Pot holes; Muddy and
loose top material with 5m road
width. Geo-tag at Station 0 + 740
Photo
184
Narrative
Latitude: : 9°15'18.54"N
Longitude : 118°6'40.57"E
Undefined earth side ditches and
crowning of road way, Insufficient
binding materials and oversize
aggregates, with 5.5 m width. Geo-
tag at station 1 + 500
Photo
Narrative
Latitude: 9°15'21.00"N
Longitude : 118°6'54.48"E
Loosed surfacing materials with
oversized aggregates, undefined
earth side ditches and crowing of
roadways with 5.0 meters in road
width. Geo-tag at Station 2 + 000
Photo
185
Narrative
Latitude: 9°15'11.02"N
Longitude : 118°7'9.00"E
Undefined earth side ditches and
crowning of road way , half of the
road is muddy and with loose top
material which resort to water
ponding on road side with 4.5m
road width
Photo
Narrative
Latitude : 9°15'11.63"N
Longitude : 118°7'8.43"E
Potholes with impounded water,
undefined earth side ditches and
crowning of roadway; Muddy and
loose top material with 5m road
width. Geo-tagged at Station 2 +
530
Photo
186
Narrative
Latitude: 9°14 ' 58.94"N
Longitude : 118°7'10.40"E
Deteriorated section of the road,
insufficient surfacing materials with
boulder on middle and side of the
road, with 4.5m width. Geo-tagged
at Station 3 + 000
Photo
Narrative:
Latitude: 9°14'49.08"N
Longitude : 118°7'16.51"E
Intermittent Pot holes with
waterponding; Muddy and loose top
material with 5.0m road width.
Geo-tagged at Station 3 + 400
Photo
187
Narrative
Latitude: 8°41'35.88"N
Longitude : 117°26'57.06"E
Loose surfacing materials and
oversize aggregates with 5m road
width. Geo-tagged at Station 3 +
600
Photo
Narrative
Latitude: 9°14'31.25"N
Longitude : 118°7'11.70"E
Intermittent Pot holes; Muddy and
loose top material with 4.5m road
width. Geo-tagged at Station 3 +
900
Photo
188
Narrative
Latitude: 9°14'24.82"N
Longitude : 118°7'15.04"E
End of the project, landmark:
Kalatagbak Barangay Hall,
Properly maintained and compacted
section of road with 5m width. Geo-
tagged at Station 4 + 100
Photo
The aforementioned gathered data were based on measurement thru walking
measure which did not exactly coincide but almost the same with the data gathered in
the geo-tagging.
The actual length of 4,211.50 linear meters (4.2115 Km.) measured by
the undersigned has exceeded the programmed length of 3,520 linear
meters (3.520 Km.). The actual measured average width was recorded
to be five (5) meters which conformed with the programmed width.
The aforementioned defects noted during actual inspection should be
immediately rectified to avoid further damage to the project.
Evaluation of work accomplishment and technical evaluation of programmed
work could not be made due to the absence of the documentary requirements cited
under COA- Memorandum No. 2005-027 and COA-Circular No. 2009-001 dated
February 12, 2009 and COA-Circular No. 2012-001 dated June 14, 2012, to wit:
1. Approved Road plans with Typical road cross section;
189
2. Delivery Receipt and Sales Invoice of all materials involved in the
project;
3. Certificate of Inspection and Acceptance for the road;
4. Approved Materials Source Maps from the Provincial Engineering Office
and nearest DPWH District Office;
5. Heavy and Light Equipment Utilization Report for CY 2012-CY2014;
6. Municipal Inventory Report of Existing Light and Heavy Equipment;
7. Construction Schedule;
8. Material Quality Control Test Results;
9. Photographs before, during and after construction per RA 6954.
Inspection conducted by:
EDWIN G. IGLESIA
SA II, Technical Services
Reviewed by:
ROLANDO D. LORENZO
OIC- Service Chief, Technical Services
190
Appendix 1G – Regravelling of Sitio Mati and Paratungon roads, Barangay
Pangobilian, Brooke’s Point, Palawan
191
192
193
194
195
196
197
198
199
We acknowledge the following officials and employees of the Commission on
Audit for their contributions to the various activities of the CPA Project and this audit:
Former Chairperson Maria Gracia M. Pulido-Tan who answered the call of President Benigno Simeon Aquino III for transparency and enhanced citizen participation in government operations through the CPA Project;
Commissioner Heidi L. Mendoza who provided the impetus for the modality adopted in this citizen participatory audit;
The CPA Project Management Team;
The CPA Audit Teams
We acknowledge the following for their valuable contributions to the CPA
Project and this audit:
The Australian Agency for International Development (AusAID) for the resource support and facilitation of various activities of the CPA Project;
The Affiliated Network for Social Accountability in East Asia and the Pacific (ANSA-EAP) for providing assistance in all phases of the project and engaging the CSO partners.
Our Civil Society Organization partners for providing technical support and participation:
The Local Government Units of the Province of Palawan through their Governor and
City/Municipal Mayors, together with their Officials and Employees.
APPENDIX 2 - ACKNOWLEDGMENTS
200
Pursuant to Office Order No. 2014-081 dated December 22, 2014 and unnumbered Office Order dated December 17, 2014.
CPA Team 1
Project: Location
a. Malatgao-Culandanum-Panas-Linao Road Bataraza, Palawan
b. Kalatagbak Road Quezon, Palawan
Team Composition
COA Personnel
Name Position Designation
Melchor P. Borja Supervising Auditor Team Supervisor
Edencio R. Berba State Auditor IV Audit Team Leader
Helen Q. Diaz State Auditor III Audit Team Member
Irish Jay Q. Pasamonte State Auditor II Audit Team Member
Elvys Kenneth E. Miguel State Auditor I Audit Team Member
Engr. Edwin G. Iglesia State Auditor II Audit Team Member
Civil Society Organization (CSO) - Citizen Partners
Timothy Siebo T.
Boehme
Western Philippines
University
Audit Team Member
Isaac E. Saniban WPU Audit Team Member
Jerald B. Bagnate WPU Audit Team Member
Albert Q. Meorom WPU Audit Team Member
Erlinda R.J. Goh PICE/Senior Citizens Audit Team Member
CPA Team 2
Project: Location
Kamuning Road Phase II Puerto Princesa City, Palawan
Team Composition
COA Personnel
Name Position Designation
Melchor P. Borja Supervising Auditor Team Supervisor
Juanito A. Nostratis State Auditor IV Audit Team Leader
Nelda P. Gomez State Auditor III Audit Team Member
APPENDIX 3 – AUDIT TEAM COMPOSITION
201
Name Position Designation
Noemi O. Teope State Auditor III Audit Team Member
Ronald C. Mendoza State Auditing Examiner II Audit Team Member
John Vincent Ambrose
Recio
Technical Audit Specialist II Audit Team Member
Civil Society Organization (CSO) - Citizen Partners
Engr. Nena C. Zara,
Dean
PSU College of Engineering
Architecture and
Technology
Audit Team Member
Mr. Anthony A. Badilla PSU College of Arts and
Humanities
Audit Team Member
Sheila B. Rallos PSU Philippine Institute of Civil Engineers Student Organization
Audit Team Member
John Jester L. Cabulao PSU Audit Team Member
Abigail L. Baisa Palawan NGO Network Inc. (PNNI)
Audit Team Member
Kimberly Jam de la Cruz PNNI Audit Team Member
Jomar V. Cua PNNI Audit Team Member
CPA Team 3
Project: Location
a. Iniaran Road Sofronio Española, Palawan
b. Kanangkaan Road Sofronio Española, Palawan
Team Composition
COA Personnel
Name Position Designation
Melchor P. Borja Supervising Auditor Team Supervisor
Corsennie A. Yan State Auditor III OIC - Audit Team Leader
Ma. Aceili V. Paduga State Auditing Examiner II Audit Team Member
John Vincent Ambrose
Recio
Technical Audit Specialist II Audit Team Member
Civil Society Organization (CSO) - Citizen Partners
Judith M. Hilario Western Philippines
University
Audit Team Member
Reniel Z. Rocaberte WPU Audit Team Member
Hilda M. Gabuco WPU Audit Team Member
Cecilia C. Castro Pulot Center Farmers Audit Team Member
202
Association
Karen D. Banda Pulot 2 Farmers
Association
Audit Team Member
Antonio E. Francisco Piatan Irrigators
Community Association
Audit Team Member
Danny P. Cabiguen Palawan NGO Network Inc.
(PNNI)
Audit Team Member
CPA Team 4
Project: Location
a. Inogbong Road Bataraza, Palawan
b. Sitio Mati and Sitio Paratungon Road Brooke’s Point, Palawan
Team Composition
COA Personnel
Name Position Designation
Melchor P. Borja Supervising Auditor Team Supervisor
Ruth C. Garcellano State Auditor III OIC - Audit Team Leader
Monique R. Baniega State Auditor III Audit Team Member
Jimmy S. Renia TAS II Audit Team Member
Civil Society Organization (CSO) - Citizen Partners
Ryan A. Limco Western Philippines
University
Audit Team Member
Jaymark A. Julaton Western Philippines
University
Audit Team Member
Donna May S. Castor Western Philippines
University
Audit Team Member
Glenn A. Besis
Bataraza Municipal
Farmers Irrigators &
Fisherfolks Association
Audit Team Member
Romeo T. Bontoyan Culandanum Farmers
Irrigators Association
Audit Team Member
CPA Team 5
Project: Location
a. Bgy. Poblacion to Mauringen Road Araceli, Palawan
b. Loblob-Calitang Road El Nido, Palawan
c. Marirong to Cayasan Road Roxas, Palawan
203
Team Composition
COA Personnel
Name Position Designation
Melchor P. Borja Supervising Auditor Team Supervisor
Elisa T. Chan State Auditor III OIC - Audit Team Leader
Floriza Faunaliza B.
Lucero
State Auditor II Audit Team Member
Marjorie Ann R.
Pasamonte
State Auditor I Audit Team Member
Reymundo R. Manalo Senior Technical Audit
Specialist
Audit Team Member
Civil Society Organization (CSO) - Citizen Partners
Douglas M. Evio Roxas Seed Growers
Association
Audit Team Member
Shigemi Muramatsu ANSA – EAP Audit Team Member
Arnel Culala ANSA – EAP Audit Team Member
CPA Team 6
Project: Location
Sitio Nalbot to Barangay Old Guinlo Road Taytay, Palawan
Team Composition
COA Personnel
Name Position Designation
Melchor P. Borja Supervising Auditor Team Supervisor
Rudolph M. Garraez State Auditor III OIC - Audit Team Leader
Marco Antonio T.
Asuncion
State Auditor I Audit Team Member
Alex M. Lapidante Senior Technical Audit
Specialist
Audit Team Member
Civil Society Organization (CSO) - Citizen Partners
Michael Maquiling Butil Marketing
Corporation
Audit Team Member
Danilo J. Java Maliliit na Magsasaka sa
Candayog
Audit Team Member
Inoncion M. Samaniego Malampaya – Pancol
Multipurpose Cooperative
Audit Team Member
204
The Audit Team prepared a survey questionnaire based on the provisions of
Philippine Agricultural Engineering Standards (PAES 421:2009) regarding the typical
location (Section 5) and design considerations (Section 6) for Farm to Market Roads.
The questionnaire was composed of ten questions. Positive responses are attained if
questions 1 to 6 were answered “Yes”, while questions 7 to 10 were answered “No”
by the interviewees.
For the Improvement of Malatgao-Culandanum-Panas-Linao Road, Bataraza, Palawan, the Audit Team found nine (9) individuals who willingly responded to the questionnaire. The respondents were composed of eight (8) farmers and one (1) housewife, all of which have been residing within the vicinity of the project for many years. A sample of the accomplished questionnaires was provided on Page 22. The results of which are as follows:
Name of Respondent: Q1 Q2 Q3 Q4 Q5 Q6 Q7 Q8 Q9 Q10
(Favors “Yes” answers) (Favors “No” answers)
● Christopher
Caboteja Yes Yes Yes Yes Yes Yes Yes No Yes No
● Elmer Macabeo Yes Yes Yes No Yes Yes Yes No Yes Yes
● Myrna Aldea Yes Yes Yes Yes Yes Yes Yes No Yes No
● Rocelyn Edlap Yes Yes Yes No Yes Yes Yes No No No
● Mercy Valdez Yes Yes Yes No Yes Yes Yes No Yes No
● Hilario Casiano Yes Yes Yes No Yes Yes No No Yes No
● Rando Lakbay Yes Yes No Yes No Yes Yes No Yes No
● Charles Torres Yes Yes Yes Yes Yes Yes Yes No Yes No
● Antonio Carmaran Yes Yes Yes No Yes Yes Yes No Yes Yes
Favorable Responses: 100% 100% 89% 44% 89% 100% 11% 100% 11% 78%
Based on the foregoing data, questions 4, 7 & 9 got low favorable response rates
due to the following reasons:
1. Only 44% of the respondents found that the road is strong enough to withstand loads without excessive deformation.
APPENDIX 4 – RESULTS OF INTERVIEW
205
2. Most respondents have observed that the road passes through swampy or flooded areas. Such areas have a lower weight bearing capacity and therefore may cause problems in the future.
3. Most respondents also have observed that some parts of the road have steep slopes; hence there is risk of erosion, landslide or vehicular accidents on those areas.
On the other hand, the rest of the questions mostly got favorable responses. All of the respondents found the location and design of the road project to be proper and beneficial to nearby residents and more importantly to farmers. Furthermore, most of them agreed that the road provided adequate space and smooth road surface for the safe and convenient transport of products and also for efficient internal circulation within the development area. Overall, the respondents showed highly favorable observations toward the project.
For the Improvement and Rehabilitation of FMR in Barangay Kalatagbak, Quezon, the Audit Team found twelve (12) individuals who willingly responded to the questionnaire. The respondents were composed of eleven (11) farmers and one (1) heavy equipment operator, all of which have been residing within the vicinity of the project for many years. The results of the interview are as follows:
Name of Respondent: Q1 Q2 Q3 Q4 Q5 Q6 Q7 Q8 Q9 Q10
(Favors “Yes” answers) (Favors “No” answers)
● Nelson Cabudac Yes No No No Yes Yes Yes No Yes Yes
● Ethbert Alvarado No No No No Yes No Yes No Yes Yes
● Erlinda Parenas Yes No No Yes Yes Yes Yes No Yes Yes
● Anthony Mosil Yes Yes No Yes Yes Yes No No Yes No
● Orly Busa Yes Yes No Yes Yes Yes No No Yes No
● Jaydee Abong Yes Yes No No Yes Yes Yes No Yes No
● Belanio Tecklasan Yes No Yes Yes Yes Yes Yes No Yes Yes
● Eme Mosil No No Yes Yes Yes Yes Yes No Yes Yes
● Romy Diong No Yes Yes Yes Yes Yes Yes No Yes Yes
● Pablo Laksian No Yes Yes Yes Yes Yes Yes No Yes Yes
● Bebeth Ingcad Yes No No No Yes No Yes No Yes No
● Julieta Sotes Yes Yes Yes Yes Yes Yes
No Yes Yes
Favorable Responses: 67% 50% 42% 67% 100% 83% 18% 100% 0% 33%
Based on the foregoing data, questions 3, 7, 9 & 10 got low favorable response
rates due to the following reasons:
1. Only 42% of the respondents found that the road provides adequate space and smooth road surface for the safe and convenient transport of produce.
2. Most respondents have observed that the road passes through swampy or flooded areas. Such areas have a lower weight bearing capacity and therefore may cause problems in the future.
206
3. All of the respondents have observed that some parts of the road have steep slopes; hence there is risk of erosion, landslide or vehicular accidents on those areas.
4. Most respondents have observed occurrences of environmental problems such as landslides or forest denudation near the FMR.
Even so, most of the respondents agreed that the FMR benefits local residents and that it provides adequate and efficient internal circulation within the development area. The high favorable scores in questions 1, 4, 5, 6, & 8 show that the respondents appreciated the benefits brought about by the FMR to them.
Sample Questionnaire:
207
APPENDIX 5 – COMPUTATION OF LIQUIDATED DAMAGES
208
Date of Fuel/Oil
Withdrawal
Disb.
Voucher
JEV No. Heavy
Equipment
Billing
Statement
Deemed
Excessive
Billing Statement per
Charge Invoice (CI)
Billing Statement
Period Covered
28-May-2014 20-127 2014-06-02-128 DT5 9,434.00 9,434.00 No Billing Statement
28-May-2014 20-133 2014-06-02-130 DT5 11,236.00 per CI No. 00286 May 28-29,2014
28-May-2014 20-134 2014-06-02-133 DT5 10,038.00 10,038.00 per CI No. 00308 May 28-29,2014
28-May-2014 20-127 2014-06-02-128 DT6 8,190.00 8,190.00 No Billing Statement
28-May-2014 20-133 2014-06-02-130 DT6 9,744.50 per CI No. 00286 May 28-29,2014
28-May-2014 20-134 2014-06-02-133 DT6 9,440.00 9,440.00 per CI No. 00308 May 28-29,2014
28-May-2014 20-127 2014-06-02-128 Payloader 9,276.00 No Billing Statement
28-May-2014 20-133 2014-06-02-130 Payloader 9,276.00 9,276.00 per CI No. 00286 May 28-29,2014
28-May-2014 20-134 2014-06-02-133 Payloader 9,276.00 9,276.00 per CI No. 00308 May 28-29,2014
29-May-2014 20-133 2014-06-02-130 DT6 8,190.00 per CI No. 00286 May 28-29,2014
29-May-2014 20-134 2014-06-02-133 DT6 8,190.00 8,190.00 per CI No. 00308 May 28-29,2014
29-May-2014 20-133 2014-06-02-130 Payloader 5,695.00 5,695.00 per CI No. 00286 May 28-29,2014
29-May-2014 20-134 2014-06-02-133 Payloader 6,787.00 per CI No. 00308 May 28-29,2014
29-May-2014 20-133 2014-06-02-130 Road Grader 5,758.50 5,758.50 per CI No. 00286 May 28-29,2014
29-May-2014 20-134 2014-06-02-133 Road Grader 5,769.00 per CI No. 00308 May 28-29,2014
30-May-2014 20-127 2014-06-02-128 DT6 8,190.00 8,190.00 No Billing Statement
30-May-2014 20-135 2014-06-02-132 DT6 8,815.00 per CI No. 00309 May 30-June 2, 2014
30-May-2014 20-135 2014-06-02-132 Payloader 9,276.00 per CI No. 00309 May 30-June 2, 2014
30-May-2014 20-127 2014-06-02-128 Payloader 5,618.00 5,618.00 No Billing Statement
2-Jun-2014 20-135 2014-06-02-132 Payloader 6,787.00 6,787.00 per CI No. 00309 May 30-June 2, 2014
2-Jun-2014 20-135 2014-06-02-132 DT6 8,315.00 8,315.00 per CI No. 00309 May 30-June 2, 2014
2-Jun-2014 20-136 2014-06-02-134 DT6 9,440.00 per CI No. 00315 June 2-3, 2014
2-Jun-2014 20-136 2014-06-02-134 Payloader 9,276.00 per CI No. 00315 June 2-3, 2014
3-Jun-2014 20-137 2014-06-02-127 DT6 9,440.00 per CI No. 00316 June 3-4,2014
3-Jun-2014 20-136 2014-06-02-134 DT6 8,290.00 8,290.00 per CI No. 00315 June 2-3, 2014
3-Jun-2014 20-137 2014-06-02-127 Payloader 8,434.00 per CI No. 00316 June 3-4,2014
3-Jun-2014 20-136 2014-06-02-134 Payloader 6,787.00 6,787.00 per CI No. 00315 June 2-3, 2014
6-Jun-2014 20-138 2014-06-02-131 Payloader 5,695.00 5,695.00 per CI No. 010397 June 5-6, 2014
6-Jun-2014 20-142 2014-06-02-152 Payloader 8,815.00 per CI No. 00318 June 6-7, 2014
6-Jun-2014 20-138 2014-06-02-131 DT6 8,190.00 8,190.00 per CI No. 010397 June 5-6, 2014
6-Jun-2014 20-142 2014-06-02-152 DT6 9,744.50 per CI No. 00318 June 6-7, 2014
15-Jul-2014 20-187 2014-08-01-205 Payloader 10,149.00 10,149.00 per CI No. 011262 July 14-15, 2014
15-Jul-2014 20-187 2014-08-01-205 DT6 3,276.00 3,276.00 per CI No. 011262 July 14-15, 2014
15-Jul-2014 20-188 2014-08-01-208 DT6 10,037.50 per CI No. 011263 July 15-16,2014
15-Jul-2014 20-188 2014-08-01-208 Payloader 11,701.00 per CI No. 011263 July 15-16,2014
TOTAL ₱ 146,594.50
For the period May to August 2014
20% DF - Improvement and Rehabilitation of Bgy. Kalatagbak Farm to Market Road
Schedule of Fuel, Oil, and Lubricant w/ Multiple Charges
APPENDIX 6 – SCHEDULE OF FUEL, OIL AND LUBRICANTS
209
Item 300/Aggregate Surface Course - consist of a wearing or top course composed of
gravel or crushed aggregate and binder materials.
Item 311/Portland Cement Concrete Pavement – consist of pavement of Portland
Cement Concrete, with or without reinforcement, constructed on the prepared
base.
Geographic Coordinates - either of the two lines of latitude and longitude whose
intersection determines the geographical point of a place.
Latitude - the angular distance of a place north or south of the earth's equator, or of a
celestial object north or south of the celestial equator, usually expressed in degrees
and minutes.
Longitude - the angular distance of a place east or west of the meridian at Greenwich,
England, or west of the standard meridian of a celestial object, usually expressed in
degrees and minutes.
Longitudinal cracks - are non-load-associated cracks. Longitudinal cracks are single
cracks approximately parallel to the centerline. These cracks are primarily due to
the contraction and shrinkage of the surface course, reflection from underlying
pavement joints, poorly constructed paving joints, or roadbed settlement.
Scaling - general loss of surface mortar or mortar surrounding the coarse aggregate
particles on a concrete surface.
Settlement - noticeable or abrupt vertical distortion from the original pavement
profile or cross-slope. Settlement is often associated with fill areas. This condition
may also have associated cracking, Settlement Cracking.
Spalling concrete - is concrete that has broken up, flaked, or become pitted. This is
usually the result of a combination of poor installation and environmental factors
that stress the concrete, causing it to become damaged.
Transverse Cracks - are non-load-associated cracks. Transverse cracks appear
approximately at right angles to the centerline. These cracks are primarily due to
the contraction and shrinkage or the surface course or reflection from underlying
pavement joints.
GLOSSARY