FALL 2015 CA/NV AWWA CONFERENCE · •original interior coal tar enamel removal/ epoxy recoat...
Transcript of FALL 2015 CA/NV AWWA CONFERENCE · •original interior coal tar enamel removal/ epoxy recoat...
• Eastern portion of San Diego County
• 250,000 people served• 56,000 service
connections• 24 Tank Structures• Progressive Asset
Maintenance Program
HELIX WATER DISTRICT
PROJECT INFORMATION
• Contractor: Paso Robles Tank, Inc.• Project Cost: $1,000,000• Project Location: Lakeside, CA• Tank Volume: 2.25 MG• Tank Height: 75 FT• Tank Const. Yr.: 1971• Key Factors: Public Relations
Public RelationsPublic RelationsColor ChangeLead Paint AbatementTank Height
• ORIGINAL INTERIOR COAL TAR ENAMEL REMOVAL/ EPOXY RECOAT
PROJECT SCOPE
• ORIGINAL EXTERIOR LEAD PRIMER REMOVAL/ EPOXY URETHANE RECOAT• STRUCTURAL MODIFICATIONS
• RAFTER BEAM CONNECTIONS/ CENTER COLUMN SUPPORT/ OVERFLOW/ ACCESS MANWAYS/ ROOF ACCESS HATCH/ ROOF VENT
• INTERIOR LADDER REMOVAL/ RELOCATION• EXTERIOR LADDER REMOVAL/ CIRCULAR STAIRWAY INSTALLATION• CATHODIC PROTECTION SYSTEM
PUBLIC RELATIONS
• TANK LOCATED IN CENTER OF RETIREMENT COMMUNITY• HISTORY OF CHALLENGING NEIGHBORHOOD RELATIONS
PUBLIC RELATIONS (CONT.)
• Extensive public outreach• Six months prior to construction
• Informational letter and brochure to surrounding community
• Private Meeting with Property Managers
• Three months prior to construction• Community Meeting• Project Hotline Established• FAQ Sheet Distribution• Information posted on Helix
website
PUBLIC RELATIONS (CONT.)
• Extensive public outreach• One month prior to construction
• Public meeting with immediate impacted residents, contractor, HWD staff, property managers
• Ongoing outreach• Media releases
• channel 10 news report• HWD press releases• Local news outlets
• Progress updates at monthly community board meeting