EMG Corporate Headquarters 10461 Mill Run Circle, Suite 1100, Owings Mills, MD 21117 www.EMGcorp.com p 800.733.0660 PREPARED BY: EMG 10461 Mill Run Circle, Suite 1100 Owings Mills, Maryland 21117 800.733.0660 www.EMGcorp.com EMG CONTACT: Joseph Bernatowicz Program Manager 800.733.0660 x6318 [email protected] EMG PROJECT #: 116732.15R000-019.017 DATE OF REPORT: March 3, 2016 ON SITE DATE: January 27, 2016 FACILITY CONDITION ASSESSMENT prepared for Maury County Public Schools 501 West 8 th Street Columbia, Tennessee 38401 Stan Breeden FACILITY CONDITION ASSESSMENT OF RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401

Transcript of FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR...

Page 1: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

EMG Corporate Headquarters 10461 Mill Run Circle, Suite 1100, Owings Mills, MD 21117 www.EMGcorp.com p 800.733.0660

PREPARED BY: EMG 10461 Mill Run Circle, Suite 1100 Owings Mills, Maryland 21117 800.733.0660 www.EMGcorp.com EMG CONTACT: Joseph Bernatowicz Program Manager 800.733.0660 x6318 [email protected] EMG PROJECT #: 116732.15R000-019.017 DATE OF REPORT: March 3, 2016 ON SITE DATE: January 27, 2016

FACILITY CONDITION ASSESSMENT

prepared for Maury County Public Schools 501 West 8th Street Columbia, Tennessee 38401 Stan Breeden

FACILITY CONDITION ASSESSMENT OF

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401

Page 2: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com
Page 3: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com
Page 4: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

TABLE OF CONTENTS CERTIFICATION ........................................................................................................................................................... 1 1. EXECUTIVE SUMMARY ........................................................................................................................................ 2

1.1. PROPERTY INFORMATION AND GENERAL PHYSICAL CONDITION .................................................... 2 1.2. SPECIAL ISSUES AND FOLLOW-UP RECOMMENDATIONS.................................................................. 3 1.3. OPINIONS OF PROBABLE COST ............................................................................................................. 3 1.1.1. METHODOLOGY .......................................................................................................................................... 3 1.1.2. IMMEDIATE REPAIRS AND SHORT TERM COSTS ................................................................................... 3 1.1.3. REPLACEMENT RESERVES ....................................................................................................................... 4

2. PURPOSE AND SCOPE ........................................................................................................................................ 5 2.1. PURPOSE .................................................................................................................................................. 5 2.2. SCOPE ....................................................................................................................................................... 5 2.3. PERSONNEL INTERVIEWED .................................................................................................................... 6 2.4. DOCUMENTATION REVIEWED ................................................................................................................ 6 2.5. PRE-SURVEY QUESTIONNAIRE .............................................................................................................. 6 2.6. WEATHER CONDITIONS .......................................................................................................................... 6

3. CODE INFORMATION AND ACCESSIBILITY ...................................................................................................... 7 3.1. CODE INFORMATION, FLOOD ZONE AND SEISMIC ZONE ................................................................... 7 3.2. ADA ACCESSIBILITY ................................................................................................................................. 7

4. EXISTING BUILDING ASSESSMENT ................................................................................................................... 8 4.1. AREA TYPE ............................................................................................................................................... 8 4.2. AREAS OBSERVED ................................................................................................................................... 8

5. SITE IMPROVEMENTS .......................................................................................................................................... 9 5.1. UTILITIES ................................................................................................................................................... 9 5.2. PARKING, PAVING, AND SIDEWALKS ..................................................................................................... 9 5.3. DRAINAGE SYSTEMS AND EROSION CONTROL ................................................................................ 10 5.4. TOPOGRAPHY AND LANDSCAPING ..................................................................................................... 11 5.5. GENERAL SITE IMPROVEMENTS .......................................................................................................... 12

6. BUILDING ARCHITECTURAL AND STRUCTURAL SYSTEMS ......................................................................... 14 6.1. FOUNDATIONS........................................................................................................................................ 14 6.2. SUPERSTRUCTURE ............................................................................................................................... 14 6.3. ROOFING ................................................................................................................................................. 15 6.4. EXTERIOR WALLS .................................................................................................................................. 15 6.5. EXTERIOR AND INTERIOR STAIRS ....................................................................................................... 16 6.6. EXTERIOR WINDOWS AND DOORS ...................................................................................................... 16 6.7. PATIO, TERRACE, AND BALCONY ........................................................................................................ 17 6.8. COMMON AREAS AND INTERIOR FINISHES ........................................................................................ 17 6.8.1 CAFETERIA ................................................................................................................................................. 18 6.8.2 GYMNASIUM ............................................................................................................................................... 19 6.8.3 LIBRARY ...................................................................................................................................................... 19

7. BUILDING MECHANICAL AND PLUMBING SYSTEMS ..................................................................................... 20 7.1. BUILDING HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) ............................................. 20 7.2. BUILDING PLUMBING AND DOMESTIC HOT WATER .......................................................................... 21 7.3. BUILDING GAS DISTRIBUTION .............................................................................................................. 22 7.4. BUILDING ELECTRICAL .......................................................................................................................... 22 7.5. BUILDING ELEVATORS AND CONVEYING SYSTEMS ......................................................................... 23 7.6. FIRE PROTECTION AND SECURITY SYSTEMS ................................................................................... 24

8. OTHER STRUCTURES ........................................................................................................................................ 25 9. RECOMMENDED OPERATIONS AND MAINTENANCE PLAN .......................................................................... 26

9.1. ESSENTIAL COMPONENTS OF AN O&M PLAN .................................................................................... 27 9.2. PREVENTIVE MAINTENANCE PROCEDURES AND TABLES .............................................................. 27

10. APPENDICES ....................................................................................................................................................... 32

Page 5: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

1 www.EMGcorp.com p 800.733.0660

C E R TI F I C A TI ON

Maury County Public Schools retained EMG to perform this Facility Condition Assessment in connection with Randolph Howell Elementary, 653 Bear Creek Pike, Columbia TN 38401, the “Property”. It is our understanding that the primary interest of Maury County Public Schools is to locate and evaluate materials and building system defects that might significantly affect the value of the property and to determine if the present Property has conditions that will have a significant impact on its continued operations. The conclusions and recommendations presented in this report are based on the brief review of the plans and records made available to our Project Manager during the site visit, interviews of available property management personnel and maintenance contractors familiar with the Property, appropriate inquiry of municipal authorities, our Project Manager’s walk-through observations during the site visit, and our experience with similar properties. No testing, exploratory probing, dismantling or operating of equipment or in depth studies were performed unless specifically required under Section 2 of this report. This assessment did not include engineering calculations to determine the adequacy of the Property’s original design or existing systems. Although walk-through observations were performed, not all areas were observed (See Section 4.2 for areas observed). There may be defects in the Property, which were in areas not observed or readily accessible, may not have been visible, or were not disclosed by management personnel when questioned. The report describes property conditions at the time that the observations and research were conducted. This report has been prepared on behalf of and exclusively for the use of Maury County Public Schools for the purpose stated within Section 2 of this report. The report, or any excerpt thereof, shall not be used by any party other than Maury County Public Schools or for any other purpose than that specifically stated in our agreement or within Section 2 of this report without the express written consent of EMG. Any reuse or distribution of this report without such consent shall be at Maury County Public Schools and the recipient’s sole risk, without liability to EMG.

Prepared by: David Harrell PE,CEM Project Manager

Reviewed by:

Daniel White

Project Reviewer for Joseph Bernatowicz, Program Manager [email protected] 800.733.0660 x6318

Page 6: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

2 www.EMGcorp.com p 800.733.0660

1 . EX E C U TI VE SU M M A R Y

1.1. PROPERTY INFORMATION AND GENERAL PHYSICAL CONDITION The property information is summarized in the table below. More detailed descriptions may be found in the various sections of the report and in the Appendices.

PROPERTY INFORMATION Address: 653 Bear Creek Pike, Columbia, Tennessee 38401 Year constructed: 1998 Current owner of property: Maury County Public Schools

Management Point of Contact: Stan Breeden 931.388.8403

Property type: Elementary School Site area: 17.50 Acres Gross floor area: 81,600 Square Feet Number of buildings: 1 Number of stories: 1 Parking type and number of spaces: 145 spaces in open lots EMG Observed School Capacity 925

Current School Enrollment 650 / 70% Building construction: Concrete topped metal decks

Roof construction: Flat roof with modified bitumen

Exterior Finishes: Brick Veneer

Heating and/or Air Conditioning: Common Area- Heating Geothermal System

Common Area- Cooling Geothermal System

Fire and Life/Safety: Fire sprinklers, hydrants, smoke detectors, alarms, strobes, extinguishers, pull stations, alarm panel, exit signs

Dates of visit: 27 January 2016

Point of Contact (POC):

Dave Hall, Construction Manager Maury County Public Schools 931.388.8403

Assessment and Report Prepared by: David Harrell

Generally, the property appears to have been constructed within industry standards in force at the time of construction. The property appears to have been well maintained since it was first occupied and is in good overall condition. According to property management personnel, the property has had a limited capital improvement expenditure program over the past three years, primarily consisting of a new covered walkway over the main entrance. Supporting documentation was not provided in support of these claims but the work is evident.

Page 7: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

3 www.EMGcorp.com p 800.733.0660

1.2. SPECIAL ISSUES AND FOLLOW-UP RECOMMENDATIONS As part of the FCA, a limited assessment of accessible areas of the building(s) was performed to determine the presence of mold, conditions conducive to mold growth, and/or evidence of moisture. Property personnel were interviewed concerning any known or suspected mold, elevated relative humidity, water intrusion, or mildew-like odors. Sampling is not a part of this assessment.

There are no visual indications of the presence of mold growth, conditions conducive to mold growth, or evidence of moisture in representative readily accessible areas of the property.

The following study is recommended. The walls are in poor condition. There are notable cracks throughout the walls in the building. A professional engineer must be retained to analyze the existing condition, provide recommendations and, if necessary, estimate the scope and cost of any required repairs. The cost of this study is included in the cost tables. Due to the ambiguity of the required repair scope at the time of this assessment, the cost for any possible subsequent repairs is not included. Refer to section 6.2 for further discussion.

1.3. OPINIONS OF PROBABLE COST Cost estimates are attached at the front of this report (following the cover page). These estimates are based on Invoice or Bid Document/s provided either by the Owner/facility and construction costs developed by construction resources such as R.S. Means and Marshall & Swift, EMG’s experience with past costs for similar properties, city cost indexes, and assumptions regarding future economic conditions. Opinions of probable costs should only be construed as preliminary, order of magnitude budgets. Actual costs most probably will vary from the consultant’s opinions of probable costs depending on such matters as type and design of suggested remedy, quality of materials and installation, manufacturer and type of equipment or system selected, field conditions, whether a physical deficiency is repaired or replaced in whole, phasing of the work (if applicable), quality of contractor, quality of project management exercised, market conditions, and whether competitive pricing is solicited, etc. ASTM E2018-08 recognizes that certain opinions of probable costs cannot be developed within the scope of this guide without further study. Opinions of probable cost for further study should be included in the FCA.

1.1.1. METHODOLOGY Based upon site observations, research, and judgment, along with referencing Expected Useful Life (EUL) tables from various industry sources, EMG opines as to when a system or component will most probably necessitate replacement. Accurate historical replacement records, if provided, are typically the best source of information. Exposure to the elements, initial quality and installation, extent of use, the quality and amount of preventive maintenance exercised, etc., are all factors that impact the effective age of a system or component. As a result, a system or component may have an effective age that is greater or less than its actual chronological age. The Remaining Useful Life (RUL) of a component or system equals the EUL less its effective age. Projections of Remaining Useful Life (RUL) are based on continued use of the Property similar to the reported past use. Significant changes in tenants and/or usage may affect the service life of some systems or components. Where quantities could not be derived from an actual take-off, lump sum costs or allowances are used. Estimated costs are based on professional judgment and the probable or actual extent of the observed defect, inclusive of the cost to design, procure, construct and manage the corrections.

1.1.2. IMMEDIATE REPAIRS AND SHORT TERM COSTS Immediate repairs are opinions of probable costs that require immediate action as a result of: (1) material existing or potential unsafe conditions, (2) material building or fire code violations, or (3) conditions that, if not addressed, have the potential to result in, or contribute to, critical element or system failure within one year or will most probably result in a significant escalation of its remedial cost. Short term costs are opinions of probable costs to remedy physical deficiencies, such as deferred maintenance, that may not warrant immediate attention, but that require repairs or replacements, which should be undertaken on a priority basis in addition to routine preventive maintenance. Opinions of probable costs may include costs for testing, exploratory probing, and further analysis should this be deemed warranted by the consultant. The performance of such additional services is beyond the FCA scope of work. Generally, the time frame for such repairs is within one to two years.

Page 8: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

4 www.EMGcorp.com p 800.733.0660

1.1.3. REPLACEMENT RESERVES Replacement Reserves are for recurring probable expenditures, which are not classified as operation or maintenance expenses. The replacement reserves should be budgeted for in advance on an annual basis. Replacement Reserves are reasonably predictable both in terms of frequency and cost. However, Replacement Reserves may also include components or systems that have an indeterminable life but, nonetheless, have a potential for failure within an estimated time period. Replacement Reserves exclude systems or components that are estimated to expire after the reserve term and are not considered material to the structural and mechanical integrity of the subject property. Furthermore, systems and components that are not deemed to have a material effect on the use of the Property are also excluded. Costs that are caused by acts of God, accidents, or other occurrences that are typically covered by insurance, rather than reserved for, are also excluded. Replacement costs are solicited from ownership/property management, EMG’s discussions with service companies, manufacturers' representatives, and previous experience in preparing such schedules for other similar facilities. Costs for work performed by the ownership’s or property management’s maintenance staff are also considered. EMG’s reserve methodology involves identification and quantification of those systems or components requiring capital reserve funds within the assessment period. The assessment period is defined as the effective age plus the reserve term. Additional information concerning system’s or component’s respective replacement costs (in today's dollars), typical expected useful lives, and remaining useful lives were estimated so that a funding schedule could be prepared. The Replacement Reserves Schedule presupposes that all required remedial work has been performed or that monies for remediation have been budgeted for items defined in the Immediate Repair and Short Term Cost Estimate.

Page 9: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

5 www.EMGcorp.com p 800.733.0660

2 . P U R PO SE A ND SC OP E

2.1. PURPOSE EMG was retained by the client to render an opinion as to the Property’s current general physical condition on the day of the site visit. Based on the observations, interviews and document review outlined below, this report identifies significant deferred maintenance issues, existing deficiencies, and material code violations of record at municipal offices, which affect the Property’s use. Opinions are rendered as to its structural integrity, building system condition and the Property’s overall condition. The report also notes building systems or components that have realized or exceeded their typical expected useful lives. The physical condition of building systems and related components are typically defined as being in one of five conditions: Excellent, Good, Fair, Poor, Missing/Failed, or a combination thereof. For the purposes of this report, the following definitions are used:

Excellent = New or very close to new; component or system typically has been installed within the past year, sound and performing its function. Eventual repair or replacement will be required when the component or system either reaches the end of its useful life or fails in service.

Good = Satisfactory as-is. Component or system is sound and performing its function, typically within the first third of its lifecycle. However, it may show minor signs of normal wear and tear. Repair or replacement will be required when the component or system either reaches the end of its useful life or fails in service.

Fair = Showing signs of wear and use but still satisfactory as-is, typically near the median of its estimated useful life. Component or system is performing adequately at this time but may exhibit some signs of wear, deferred maintenance, or evidence of previous repairs. Repair or replacement will be required due to the component or system’s condition and/or its estimated remaining useful life.

Poor = Component or system is significantly aged, flawed, functioning intermittently or unreliably; displays obvious signs of deferred maintenance; shows evidence of previous repair or workmanship not in compliance with commonly accepted standards; has become obsolete; or exhibits an inherent deficiency. The present condition could contribute to or cause the deterioration of contiguous elements or systems. Either full component replacement is needed or repairs are required to restore to good condition, prevent premature failure, and/or prolong useful life.

NA = Not Applicable. New or recommended components or systems necessary to meet client requested needs. Throughout sections 5 through 9 of this report, each report section will typically contain three subsections organized in the following sequence: A descriptive table (and/or narrative), which identifies the components assessed, their condition, and other key data points. A simple bulleted list of Anticipated Lifecycle Replacements, which lists components and assets typically in Excellent, Good, or Fair

condition at the time of the assessment but that will require replacement or some other attention once aged past their estimated useful life. These listed components are typically included in the associated inventory database with costs identified and budgeted beyond the first several years.

A bulleted cluster of Actions/Comments, which include more detailed narratives describing deficiencies, recommended repairs, and short term replacements. The assets and components associated with these bullets are/were typically problematic and in Poor or Missing/Failed condition at the time of the assessment, with corresponding costs included within the first few years.

2.2. SCOPE The standard scope of the Facility Condition Assessment includes the following: Visit the Property to evaluate the general condition of the building and site improvements, review available construction documents in

order to familiarize ourselves with, and be able to comment on, the in-place construction systems, life safety, mechanical, electrical, and plumbing systems, and the general built environment.

Identify those components that are exhibiting deferred maintenance issues and provide cost estimates for Immediate, Short Term, and Replacement Reserves based on observed conditions, maintenance history and industry standard useful life estimates. This will include the review of documented capital improvements completed within the last five-year period and work currently contracted for, if applicable.

Provide a full description of the Property with descriptions of in-place systems and commentary on observed conditions.

Page 10: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

6 www.EMGcorp.com p 800.733.0660

Provide a general statement of the subject Property’s compliance to Title III of the Americans with Disabilities Act. This will not constitute a full ADA survey, but will help identify exposure to issues and the need for further review.

Perform a limited assessment of accessible areas of the building(s) for the presence of mold, conditions conducive to mold growth, and/or evidence of moisture. EMG will also interview Project personnel regarding the presence of any known or suspected mold, elevated relative humidity, water intrusion, or mildew-like odors. Potentially affected areas will be photographed. Sampling will not be considered in routine assessments.

List the current utility service providers. Review maintenance records and procedures with the in-place maintenance personnel. Observe a representative sample of the interior tenant spaces/units, including vacant spaces/units, in order to gain a clear

understanding of the property’s overall condition. Other areas to be observed include the exterior of the property, the roofs, interior common areas, and mechanical, electrical and elevator equipment rooms.

Appropriate inquiries of municipal officials regarding the existence of pending unresolved building, zoning or fire code violations on file, and a determination of the current zoning category, flood plain zone, and seismic zone for the Property.

Provide recommendations for additional studies, if required, with related budgetary information. Tenant responsibility for maintenance, repair or replacement of finishes, fixtures, or equipment is not addressed by this scope of

services. Provide an Executive Summary at the beginning of this report with a Project-At-A-Glance cost estimate as a quick, user-friendly

summary of the Property’s condition and the assigned costs by category. These costs are tied to the report sections where reference to the issues are clearly defined and expanded.

2.3. PERSONNEL INTERVIEWED The following personnel from the facility and government agencies were interviewed in the process of conducting the FCA:

NAME AND TITLE ORGANIZATION PHONE NUMBER Michael Ford, Principal Maury County Public Schools 931.540.1032

The FCA was performed with the assistance of Michael Ford, Principal, Maury County Public Schools, the on-site Point of Contact (POC), who was cooperative and provided information that appeared to be accurate based upon subsequent site observations. The on-site contact is completely knowledgeable about the subject property and answered most questions posed during the interview process. The POC’s management involvement at the property has been for the past 5 years.

2.4. DOCUMENTATION REVIEWED Prior to the FCA, relevant documentation was requested that could aid in the knowledge of the subject property’s physical improvements, extent and type of use, and/or assist in identifying material discrepancies between reported information and observed conditions. The review of submitted documents does not include comment on the accuracy of such documents or their preparation, methodology, or protocol. The Documentation Request Form is provided in Appendix E. Although Appendix E provides a summary of the documents requested or obtained, the following list provides more specific details about some of the documents that were reviewed or obtained during the site visit. Trane Study Dated February 27, 2014

2.5. PRE-SURVEY QUESTIONNAIRE A Pre-Survey Questionnaire was conducted on site with the POC. The questionnaire is included in Appendix E. Information obtained from the questionnaire has been used in preparation of this report.

2.6. WEATHER CONDITIONS 27 January 2016: Clear, with temperatures in the 40s (°F) and light winds.

Page 11: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

7 www.EMGcorp.com p 800.733.0660

3 . C O D E I N FO R MA T I O N A N D AC C E SSI B I L I T Y

3.1. CODE INFORMATION, FLOOD ZONE AND SEISMIC ZONE According to the Flood Insurance Rate Map, published by the Federal Emergency Management Agency (FEMA) and dated 4-16-2007 the property is located in Zone X, defined as an area outside the 500-year flood plain with less than 0.2% annual probability of flooding. Annual Probability of Flooding of Less than one percent. According to the 1997 Uniform Building Code Seismic Zone Map of the United States, the property is located in Seismic 1, defined as an area of low probability of damaging ground motion.

3.2. ADA ACCESSIBILITY Generally, Title III of the Americans with Disabilities Act (ADA) prohibits discrimination by entities to access and use of “areas of public accommodations” and “commercial facilities” on the basis of disability. Regardless of its age, these areas and facilities must be maintained and operated to comply with the Americans with Disabilities Act Accessibility Guidelines (ADAAG). Buildings completed and occupied after January 26, 1992 are required to comply fully with the ADAAG. Existing facilities constructed prior to this date are held to the lesser standard of compliance to the extent allowed by structural feasibility and the financial resources available. As an alternative, a reasonable accommodation pertaining to the deficiency must be made. During the FCA, a limited visual observation for ADA accessibility compliance was conducted. The scope of the visual observation was limited to those areas set forth in EMG’s Abbreviated Accessibility Checklist provided in Appendix D of this report. It is understood by the Client that the limited observations described herein does not comprise a full ADA Compliance Survey, and that such a survey is beyond the scope of EMG’s undertaking. Only a representative sample of areas was observed and, other than as shown on the Abbreviated Accessibility Checklist, actual measurements were not taken to verify compliance. The facility generally appears to be accessible as stated within the defined priorities of Title III of the Americans with Disabilities Act.

A full ADA Compliance Survey may reveal additional aspects of the property that are not in compliance.

Page 12: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

8 www.EMGcorp.com p 800.733.0660

4 . EX I ST I NG B U I L D I N G A SS ESS M E N T

4.1. AREA TYPE All 81,600 square feet of the building are owned and occupied by Maury County Public Schools.

4.2. AREAS OBSERVED All of the property was observed in order to gain a clear understanding of the property’s overall condition. Other areas accessed included the exterior of the property and the roof. All areas of the property were available for observation during the site visit.

Page 13: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

9 www.EMGcorp.com p 800.733.0660

5 . S I TE I M PR OVE M E N TS

5.1. UTILITIES The following table identifies the utility suppliers and the condition and adequacy of the services.

SITE UTILITIES

UTILITY SUPPLIER CONDITION AND ADEQUACY

Sanitary sewer Columbia Power and Water Good

Storm sewer Catch Basins, Swales, discharging into landscaped areas

Good

Domestic water Columbia Power and Water Good

Electric service Columbia Power and Water Good

Natural gas service ATMOS Energy Good

Actions/Comments: According to the POC, the utilities provided are adequate for the property. There are no unique, on-site utility systems such as

emergency electrical generators, septic systems, water or waste water treatment plants, or propane gas tanks.

5.2. PARKING, PAVING, AND SIDEWALKS

ITEM DESCRIPTION

Main Ingress and Egress Tom Sharp Road

Access from Southeast

Additional Entrances N/A

Additional Access from N/A

PAVING AND FLATWORK

ITEM MATERIAL LAST WORK DONE

CONDITION

Entrance Driveway Apron Asphalt >3 years Fair

Parking Lot Asphalt >3 years Fair

Drive Aisles Asphalt >3 years Fair

Service Aisles Asphalt >3 years Fair

Sidewalks Cast In Place Concrete >10 years Good

Page 14: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

10 www.EMGcorp.com p 800.733.0660

PAVING AND FLATWORK

ITEM MATERIAL LAST WORK DONE

CONDITION

Curbs Cast in Place Concrete >10 years Good

Pedestrian Ramps Cast in Place Concrete >10 years Good

PARKING COUNT

OPEN LOT CARPORT PRIVATE GARAGE

SUBTERRANEAN GARAGE

FREESTANDING PARKING

STRUCTURE

145 Not applicable Not applicable Not applicable Not applicable

Number of ADA Compliant Spaces 8

Number of ADA Compliant Spaces for Vans 4

Total Parking Spaces 145

Parking Ratio (Spaces/SF) 1.8

Method of obtaining parking count Physical count

Anticipated Lifecycle Replacements: Asphalt seal coating Asphalt pavement

Actions/Comments: The asphalt pavement exhibits isolated areas of failure and deterioration, such as alligator cracking, transverse cracking, extensive

raveling, and localized depressions. The most severely damaged areas of paving must be cut and patched in order to maintain the integrity of the overall pavement system.

In order to preserve the asphalt pavement throughout the site resealing and striping of the pavement will be required during the evaluation period.

5.3. DRAINAGE SYSTEMS AND EROSION CONTROL

DRAINAGE SYSTEM AND EROSION CONTROL

SYSTEM EXISTS AT SITE CONDITION

Surface Flow ☒ Good

Page 15: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

11 www.EMGcorp.com p 800.733.0660

DRAINAGE SYSTEM AND EROSION CONTROL

SYSTEM EXISTS AT SITE CONDITION

Inlets ☒ Good

Swales ☒ Good

Detention pond ☐ --

Lagoons ☐ --

Ponds ☐ --

Underground Piping ☐ --

Pits ☐ --

Municipal System ☐ --

Dry Well ☐ --

Anticipated Lifecycle Replacements: No components of significance

Actions/Comments: There is no evidence of storm water runoff from adjacent properties. The storm water system appears to provide adequate runoff

capacity. There is no evidence of major ponding or erosion. Soil erosion occurs in the vicinity of the basketball court. The affected area must be restored to prevent additional erosion and

damage.

5.4. TOPOGRAPHY AND LANDSCAPING

ITEM DESCRIPTION

Site Topography Slopes gently down from the north side of the property to the south property line.

Landscaping Trees Grass Flower

Beds Planters Drought Tolerant Plants

Decorative Stone None

☒ ☒ ☐ ☐ ☐ ☐ ☐

Landscaping Condition

Fair

Irrigation

Automatic Underground Drip Hand Watering None

☐ ☐ ☐ ☒

Irrigation Condition --

Page 16: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

12 www.EMGcorp.com p 800.733.0660

RETAINING WALLS

TYPE LOCATION CONDITION None -- --

Surrounding properties include a middle school, farmland, and residential developments.

Anticipated Lifecycle Replacements: No components of significance

Actions/Comments: The topography and adjacent uses do not appear to present conditions detrimental to the property. There are no significant areas of

erosion.

5.5. GENERAL SITE IMPROVEMENTS

PROPERTY SIGNAGE

Property Signage Building Mounted

Street Address Displayed? No

SITE AND BUILDING LIGHTING

Site Lighting

None Pole Mounted Bollard Lights Ground Mounted

Parking Lot Pole Type

☐ ☐ ☐ ☐ ☒

Fair

Building Lighting

None Wall Mounted Recessed Soffit

☐ ☒ ☐

Fair

SITE FENCING

TYPE LOCATION CONDITION Chain link with metal posts Perimeter of playground Fair

REFUSE DISPOSAL

Refuse Disposal Common Area Dumpsters

Page 17: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

13 www.EMGcorp.com p 800.733.0660

REFUSE DISPOSAL

Dumpster Locations Mounting Enclosure Contracted? Condition

Adjacent Cafeteria Concrete Pad None Yes Fair

OTHER SITE AMENITIES

DESCRIPTION LOCATION CONDITION

Playground Equipment Metal Northwest side of school campus

Fair

Basketball Court Concrete Paved Northwest side of school campus

Fair

The playground and basketball courts are surrounded by a chain link fence.

Anticipated Lifecycle Replacements: Site fencing Playground equipment

Actions/Comments: No significant repair actions or short term replacement costs are required. Routine and periodic maintenance is recommended. The playground equipment is reaching its EUL (estimated useful life). A budgetary cost for updating is provided.

Page 18: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

14 www.EMGcorp.com p 800.733.0660

6 . B U I L DI NG A RC H I TE C T U R AL A ND S T R U C TU R A L S YS T E MS

6.1. FOUNDATIONS

BUILDING FOUNDATION

ITEM DESCRIPTION CONDITION

Floor Concrete Slab on grade Fair

Footings Concrete perimeter footings Fair

Basement and Crawl Space None --

Anticipated Lifecycle Replacements: No components of significance

Actions/Comments: The substructure is concealed. Walls and floors appear to be plumb, level, and stable. There are no significant signs of deflection or

movement.

6.2. SUPERSTRUCTURE

BUILDING SUPERSTRUCTURE

ITEM DESCRIPTION CONDITION

Framing Steel Columns Good

Upper Floors Truss Joints Good

Roof Structure Open web steel joists Good

Roof Sheathing Roof Decks Topped with Concrete Good

Anticipated Lifecycle Replacements: No components of significance

Actions/Comments: The superstructure is exposed in some locations, which allows for limited observation. There is significant evidence of deflection,

movement and cracking throughout the building and classrooms. A Professional Engineer with specific expertise in structural design and construction in this geographical area must be retained to evaluate the structure and to provide remedial recommendations consistent with local regulatory and code requirements. Refer to section 1.2 for follow on discussion.

Page 19: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

15 www.EMGcorp.com p 800.733.0660

6.3. ROOFING

PRIMARY ROOF

Type Flat Finish Single-ply membrane

Maintenance Outside Contractor Roof Age 5 Years

Flashing Membrane Warranties Expires 2031

Parapet and Copings Parapet with sheet metal coping Roof Drains Scupper, leaders and downspouts

Fascia Metal Panel Insulation Rigid Board

Soffits Concealed Soffits Skylights No

Attics None Ponding No

Ventilation Source-1 Power Vents Leaks Observed No

Ventilation Source-2 N/A Roof Condition Good

The primary roof is observed at all locations of the building.

Anticipated Lifecycle Replacements: No components of significance

Actions/Comments: The roof finishes were reportedly installed in 2011. The roofs are covered by a 20 year warranty. A copy of the warranty was

requested but was not available. The roofs are maintained by an outside contractor. According to the POC, there are no active roof leaks. There is no evidence of active roof leaks. There is no evidence of roof deck or insulation deterioration. The roof substrate and insulation should be inspected during any future

roof repair or replacement work. Roof drainage appears to be adequate. Clearing and minor repair of drain system components should be performed regularly as part

of the property management’s routine maintenance and operations program.

6.4. EXTERIOR WALLS

BUILDING EXTERIOR WALLS

TYPE LOCATION CONDITION

Primary Finish Brick Veneer GOOD

Accented With None --

Soffits Not Applicable --

Building sealants (caulking) are located between dissimilar materials, at joints, and around window and door openings.

Page 20: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

16 www.EMGcorp.com p 800.733.0660

Anticipated Lifecycle Replacements: No components of significance

Actions/Comments: No significant repair actions or short term replacement costs are required. Routine and periodic maintenance including patching

repairs and sealant replacement are recommended. The exterior finishes have isolated areas of cracks in the brick along the southeast elevation. The damaged finishes must be

repaired.

6.5. EXTERIOR AND INTERIOR STAIRS Not applicable. There are no exterior or interior stairs.

6.6. EXTERIOR WINDOWS AND DOORS

BUILDING WINDOWS

WINDOW FRAMING GLAZING LOCATION WINDOW SCREEN CONDITION

Insulated Metal panels with fixed frames Double Pane All elevations ☐ FAIR

BUILDING DOORS

Main School Entrance Doors Service Doors

Door Type Condition

Metal Door With Vision Glass FAIR

Cylindrical

Lockset Handle Security Chain Deadbolts Spy-Eyes Door

Knockers

Yes Pull Not Applicable

Not Applicable

Not Applicable

Not applicable

Exterior classrooms doors

Door Type Count Condition

Metal 78 FAIR

Interior Classroom Doors Wood set in metal frame Approx. 59 FAIR

Service and Corridor Doors Metal 6 Double 5 Single FAIR

Main building Entrance Door and Vestibule Metal 4 Double FAIR

Anticipated Lifecycle Replacements: Exterior windows Exterior doors Interior doors

Page 21: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

17 www.EMGcorp.com p 800.733.0660

Actions/Comments: The exterior windows and doors as well as interior doors are approaching their EUL (expected useful life). Budgetary costs for

replacements are provided. As a security measure it is recommended that a magnetic lock and card access control reader be installed on the main entry door

and vestibule

6.7. PATIO, TERRACE, AND BALCONY Not applicable. There are no patios, terraces, or balconies.

6.8. COMMON AREAS AND INTERIOR FINISHES The main school entry is accessed via the south side of the property. The main classroom wings are located on the east and west side of the school. The gymnasium and cafeteria are located on the north side of the building. Common area restrooms are located within the 300 and 400 school wings. The following table identifies the interior common areas and generally describes the finishes in each common area.

COMMON AREA FLOORS WALLS CEILINGS

School entry Vinyl Tile Painted CMU Suspended T-bar (Acoustic)

Cafeteria Vinyl Tile Painted CMU Suspended T-bar (Acoustic)

Kitchen Quarry Tile Painted CMU Suspended T-bar (Acoustic)

Library Vinyl Tile Painted CMU Suspended T-bar

(Acoustic)

Gymnasium Vinyl Tile Painted CMU Painted Structure (Steel Trusses)

Corridors Vinyl Tile Painted CMU Suspended T-bar (Acoustic)

Classrooms Vinyl Tile Painted CMU Suspended T-bar (Acoustic)

Restrooms Ceramic Tile Painted CMU Suspended T-bar (Acoustic)

Overall General Condition Fair Fair Fair

Page 22: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

18 www.EMGcorp.com p 800.733.0660

INTERIOR DOORS

ITEM TYPE CONDITION Interior Doors Solid Core Wooden FAIR Door Framing Metal FAIR

Anticipated Lifecycle Replacements: Vinyl tile Ceramic tile Interior paint Suspended acoustic ceiling tile

Actions/Comments: It appears that the interior finishes in the common areas are original. There are isolated instances of water damaged, warped and deteriorated ceiling tiles throughout the building. The damaged and

missing ceiling tile must be replaced. Based on condition and Remaining Useful (RUL) life replacement of the acoustic ceiling tile is recommended.

Vinyl floor tile is noted in overall fair condition. Based on condition and Remaining Useful Life (RUL) replacement of all vinyl floor tiles is recommended.

The interior paint finishes is beginning to show signs of wear. Repainting of the walls is recommended.

6.8.1 CAFETERIA The school has a single cafeteria. The cafeteria kitchen is a full cooking kitchen. Vinyl flooring, suspended acoustic tile and painted CMU walls are finishes within the space. The kitchen areas have a variety of commercial appliances, fixtures, and equipment as follows:

APPLIANCE COMMENT Refrigerators 1 walk-in ; 2 reach-in ; 4 chest Freezers 2 walk-in Ovens 3 convection Tilting skillet 1 electric Heated cabinet 3 cabinet Hood 1 with fire suppression Dishwasher 1 automatic Work tables Stainless steel Shelving Stainless steel

Observations/Comments: The kitchen appliances appear to be in satisfactory condition. Based on their estimated Remaining Useful Life (RUL), some of the kitchen appliances may require replacement during the evaluation period. The estimated cost of this work is included in the Replacement Reserves Report.

Page 23: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

19 www.EMGcorp.com p 800.733.0660

6.8.2 GYMNASIUM The school is equipped with one gymnasium. The main gym is located on the north side of the school building. The gymnasium has a composite vinyl tile floor, exposed structure ceiling, and painted CMU walls. The gymnasium has two basketball drops and wall pads.

6.8.3 LIBRARY The library is located at the main entrance of the building. The library has vinyl tile flooring, painted CMU, suspended acoustic tile ceiling and free standing bookshelves.

Page 24: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

20 www.EMGcorp.com p 800.733.0660

7 . B U I L DI NG M EC H A NI C AL A ND PL U MBI N G S YS T E MS

7.1. BUILDING HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

BUILDING CENTRAL HEATING SYSTEM Primary Heating System Type Geothermal System and Heat Pumps

Quantity

39 Geothermal Unit Ventilator Heat Pump; 19 Rooftop Heat Pumps (1.5 ton, 5kW 2X); (3 ton,

12kW 4X); (4 ton, 17kW 4X); (6.25ton, 20kW 3X); (12.5 ton, 36kW 2X); (15 ton, 36kW 1X); (20 ton,

72kW 3X) Heating Fuel Electric

Heating System Input Capacity (kW) 3.8/UV Manufactured Rated Efficiency (COP) 2.2

Location of Equipment Classrooms; Rooftop Space Served by System Classrooms, offices, cafeteria, kitchen, library

Age 15 Heating Plant Condition Fair

BUILDING CENTRAL COOLING SYSTEM Primary Cooling System Type Geothermal System and Heat Pumps

Quantity

39 Geothermal Unit Ventilator Heat Pump; 19 Rooftop Heat Pumps (1.5 ton, 5kW 2X); (3 ton,

12kW 4X); (4 ton, 17kW 4X); (6.25ton, 20kW 3X); (12.5 ton, 36kW 2X); (15 ton, 36kW 1X); (20 ton,

72kW 3X) Refrigerant R-22

Cooling System Capacity (Tons) 3.75Ton (39x), 1.5Ton (2X), 3Ton (4X), 4Ton (4X),

6.25Ton (3X), 12.5Ton (2X), 15Ton (1X), 20Ton (3X)

Cooling Tower Size None Manufactured Rated Efficiency 10.8 EER

Location of Equipment Classrooms; Rooftop Space Served by System Classrooms, offices, cafeteria, kitchen, library

Age 15 Cooling Plant Condition FAIR

DISTRIBUTION SYSTEM Hot// chilled Water Distribution System --

Hot Water Circulation Pump Size and Qty. -- Chilled Water Circulation Pump Size and Qty --

Air Distribution System Constant Air Handling Unit Location Packaged RTU Air Handling Unit- Serving offices, cafeteria, kitchen, library Location Fan Coil Unit (s) None

Page 25: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

21 www.EMGcorp.com p 800.733.0660

DISTRIBUTION SYSTEM Spaces Served by Fan Coil Unit (s) None Common Area Temperature Control Non-Programmable

Building Ventilation Roof Top Exhaust Fans Distribution System Condition FAIR

Air distribution is provided to supply air registers by ducts concealed above the ceilings. The heating and cooling system are controlled by local thermostats. The bathrooms and other areas are ventilated by mechanical exhaust fans. Large capacity ventilation fans are mounted on the roof and are connected by concealed ducts to each ventilated space.

Anticipated Lifecycle Replacements: Package units Split system heat pumps

Actions/Comments: The HVAC systems are maintained by an outside contractor. Records of the installation, maintenance, upgrades, and replacement

of the HVAC equipment at the property have been maintained since the property was first occupied. Approximately 95 percent of the HVAC equipment is original. The property is relatively new and has not required any major HVAC

equipment replacements. The HVAC equipment appears to be functioning adequately overall. The property management staff was interviewed about the

historical and recent performance of the equipment and systems. No chronic problems were reported and an overall sense of satisfaction with the systems was conveyed. However, due to the inevitable failure of parts and components over time, some of the equipment will require replacement. A budgetary cost for this work is included.

7.2. BUILDING PLUMBING AND DOMESTIC HOT WATER

BUILDING PLUMBING SYSTEM

TYPE DESCRIPTION CONDITION

Water Supply Piping Copper GOOD

Waste/Sewer Piping Cast Iron Pipe GOOD Vent Piping PVC Pipe GOOD

Water Meter Location unknown

DOMESTIC WATER HEATERS OR BOILERS

Component(s) Water Heater

Fuel Natural Gas

Storage Capacity -- gal

Input Capacity 285,000 Btuh

Supplementary Storage Tanks? Yes

Storage Tank Volume 257 gal

Page 26: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

22 www.EMGcorp.com p 800.733.0660

DOMESTIC WATER HEATERS OR BOILERS

Quantity of Storage Tanks 1

Boiler or Water Heater Condition: FAIR

Domestic Hot Water Circulation Pump/s (HP) 0.25

Pressure and Flow of Hot Water Adequate

Domestic Water Booster Pumps (hp) --

Pressure and Flow of City Water Adequate

COMMON AREA PLUMBING FIXTURES

Water Closets Commercial Grade

Water Closets Rating 1.6 GPF

Common Area Faucet, GPM 1.0 GPM

Condition Good

Anticipated Lifecycle Replacements: Water heater

Actions/Comments: The plumbing systems appear to be well maintained and functioning adequately. The water pressure appears to be sufficient. No

significant repair actions or short term replacement costs are required. Routine and periodic maintenance is recommended. The water heater exhibits minor evidence of corrosion and damage. The water heater is recommended for replacement.

7.3. BUILDING GAS DISTRIBUTION Gas service is supplied from the gas main on the adjacent public street. The gas meter and regulator are located along the exterior walls of the building. The gas distribution piping within the building is malleable steel (black iron).

Anticipated Lifecycle Replacements: No components of significance

Actions/Comments: The pressure and quantity of gas appear to be adequate. The gas meter and regulator appear to be functioning adequately and will require routine maintenance. Only limited observation of the gas distribution piping can be made due to hidden conditions.

7.4. BUILDING ELECTRICAL

BUILDING ELECTRICAL SYSTEMS Electrical lines run Underground Transformer Pad-mounted

Service size (Amps) 3,000 Amps Volts 277/480 Volt, three-phase

Page 27: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

23 www.EMGcorp.com p 800.733.0660

BUILDING ELECTRICAL SYSTEMS

Meter and panel location On main transformer

panel in equipment room Branch wiring Copper

Conduit Metallic Circuit Breaker Panel

Located throughout the building

Number of Buildings Single Building Intercom System Yes

Distribution Condition Good Panel and Transformer

Condition Good

Lighting Condition Good

Anticipated Lifecycle Replacements: No components of significance

Actions/Comments: The on-site electrical systems up to the meter are owned and maintained by the respective utility company. The electrical service and capacity appear to be adequate for the property’s demands.

7.5. BUILDING ELEVATORS AND CONVEYING SYSTEMS

LIFT-1

Elevator Category Passenger

Elevator Type Lift

Elevator Capacity 750 Lbs

Elevator Manufacturer Savaria

Equipment Location Gymnasium

Elevator Safety Stop electronic

Elevator Emergency Communication Yes

Elevator Cab Floor Painted steel

Elevator Cab Wall Painted steel

Elevator Cabin Lighting --

Machinery Condition Good

Controls Condition Good

Cab Finish Condition Good

Anticipated Lifecycle Replacements: No components of significance

Page 28: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

24 www.EMGcorp.com p 800.733.0660

Actions/Comments: The lift appears to provide adequate service. The lift will require continued periodic maintenance. The lift is inspected on an annual basis by the municipality, and a certificate of inspection is on file in the management office. The emergency communication equipment in the elevator cabs appears to be functional. Equipment testing is not within the scope of

the work.

7.6. FIRE PROTECTION AND SECURITY SYSTEMS

ITEM DESCRIPTION Type Wet

Fire Alarm System

None ☐ Battery Operated Smoke Detectors ☐ Strobe Light Alarms ☒

Central Alarm Panel ☒ Hard-wired Smoke Detectors ☒ Illuminated EXIT Signs ☒

Battery backup Light Fixtures ☒ Hard-wired Smoke

Detectors/ with battery Backup

☐ Annunciator Panels ☒

Alarm System Condition Good

Sprinkler System

None ☐ Standpipes ☐ Flow Switches ☒

Pull Station ☒ Fire Pumps ☐ Siamese Connections ☒

Alarm horns ☐ Backflow Preventer ☒ Hose Cabinets ☐ Suppression

Condition Good

Central Alarm Panel System

Location of Alarm Panel Age of Alarm panel

Office 15 years

Fire Extinguishers

Last Service Date Estimated Quantity

October 2015 15 Hydrant Location 100 yards from main entrance; 20 yards from rear entrance

Siamese Location Adjacent to kitchen entrance

Special Systems Kitchen Suppression System ☒ Computer Rm. Suppression System ☐

Anticipated Lifecycle Replacements: No components of significance

Actions/Comments: No significant repair actions or short term replacement costs are required. Routine and periodic maintenance is recommended.

Page 29: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

25 www.EMGcorp.com p 800.733.0660

8 . O T H E R S T R U C T U R E S

A maintenance storage building is located on the northwest section of the property. The maintenance building is a pre-manufactured wood structure.

Anticipated Lifecycle Replacements: Storage shed

Actions/Comments: No significant repair actions or short term replacement costs are required. In addition to the lifecycle replacements recommended

above, routine and periodic maintenance is recommended.

Page 30: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

26 www.EMGcorp.com p 800.733.0660

9 . R E C O MM E N DED O PE R A TI O NS A N D MAI N TE N A N CE PL A N

The quality of the maintenance and the operation of the facility’s energy systems has a direct effect on its overall energy efficiency. The following is a list of activities that should be performed as part of the routine maintenance program for the property. These actions will ensure that the energy conservation measures identified in this report will remain effective. The following general recommendations should be continued or implemented.

Building Envelope 1. Ensure that the building envelope has proper caulking and weather stripping.

2. Patch holes in the building envelope with foam insulation and fire rated caulk around combustion vents

3. Inspect building vents semiannually for bird infestation

4. Inspect windows monthly for damaged panes and failed thermal seals

5. Repair and adjust automatic door closing mechanisms as needed.

Heating and Cooling 1. Ensure that the combustion vents exhaust outside the conditioned space and the vent dampers are functional.

2. Ensure the duct work in unconditioned space is un-compromised and well insulated

3. Duct cleaning is recommended every 10 years. This should include sealing of ducts using products similar to ‘aero-seal’.

4. Ensure that the air dampers are operating correctly

5. Return vents should remain un-obstructed and be located centrally.

6. Temperature settings reduced in unoccupied areas and set points seasonally adjusted.

7. Evaporator coils and condenser coils should be regularly cleaned to improve heat transfer

8. Refrigerant pipes should be insulated with a minimum of ¾” thick Elastomeric Rubber Pipe Insulation

9. Ensure refrigerant pressure is maintained in the condensers

10. Change air filters on return vents seasonally. Use only filters with ‘Minimum Efficiency Rating Value’(MERV) of 8

Central Domestic Hot Water 1. Never place gas fired water heaters adjacent to return vents so as to prevent flame roll outs.

2. Ensure the circulation system is on timer to reduce the losses through re-circulation.

3. Ensure all hot water pipes are insulated with fiberglass insulation at all times

4. Replacement water heaters should have Energy Factor (EF)>0.9

5. Tank-type water heaters flushed monthly.

Lighting 1. Utilize bi-level lighting controls in stairwells and hallways.

2. Use energy efficient replacement lamps (lower wattage 28W T-8 and CFLs)

Page 31: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

27 www.EMGcorp.com p 800.733.0660

3. Clean lighting fixture reflective surfaces and translucent covers.

4. Ensure that timers and/or photocells are operating correctly on exterior lighting

5. Use occupancy sensors for offices and other rooms with infrequent occupancy

Existing Equipment and Replacements 1. Ensure that refrigerator and freezer doors close and seal correctly

2. Ensure kitchen and bathroom exhaust outside the building and the internal damper operates properly

3. Ensure that bathroom vents exhaust out

4. Office/ computer equipment either in the “sleep” or “off” mode when not used

9.1. ESSENTIAL COMPONENTS OF AN O&M PLAN

The following preventive maintenance procedures are a guideline for an effective Operations and Maintenance Plan. Reference should be made to the specific equipment manufacturer guidelines as well as any organizational policies and criteria regarding equipment and building component routine and planned maintenance activities.

For an O&M plan to be successful, a detailed inventory of all equipment and components along with photographic records, records of the installation date, most recent service date and model and serial number must be carried out. This inventory should be recorded electronically as part of a building, facility and portfolio Computerized maintenance Management System, School Dude, that includes methods for generating, tracking, managing and approving individual work orders for specific equipment and components that can be tied dynamically to the individual assets must be implemented.

Only appropriately trained, qualified and experienced maintenance personnel should perform preventive maintenance tasks, supplemented or augmented by appropriately trained and licensed trade subcontractors as necessary. All facility specific safety requirements are to be followed when carrying out preventive maintenance along with all OSHA mandated workplace safety practices. Any and all equipment that is electrically operated must be fully de-energized and locked/tagged out of service prior to the commencement of any preventive maintenance activity.

9.2. PREVENTIVE MAINTENANCE PROCEDURES AND TABLES The following tables provide recommended maintenance schedules and individual maintenance tasks for the various equipment and system components. These procedures should be read in conjunction with the specific manufacturer-recommended preventive maintenance procedures for each individual components and pieces of equipment. The frequencies of preventative maintenance procedures are shown below. All other frequencies shown are given in time intervals, for example – 36-months. A = Annual Preventative Maintenance Procedures M = Monthly Preventative Maintenance Procedures Q = Quarterly Preventative Maintenance Procedures W= Weekly Preventative Maintenance Procedures SA = Semi-Annual Preventative Maintenance Procedures

Page 32: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

28 www.EMGcorp.com p 800.733.0660

Equipment Description PM Procedure FrequencyPackaged Roof Top Units Check unit for excessive noise or vibration Q

Check intake side of condenser coils, fans and intake screens QCheck belts for condition, proper tension and mis-alignment and adjust as necessary QLubricate shaft bearings and motor bearings QInspect piping and valves for leaks and tighten connections as necessary QReplace air filters QCheck refrigerant pressure and add as necessary QCycle the reverse cycle valve to ensure proper operation QClean area around equipment and report deficiencies to maintenance contractor QClean electrical wiring and connections, tighten all connections QClean coils, evaporator drain pan, blowers, fans, motors and drain piping QPerform operational check of unit and make adjustments on controls as necessary QWhile unit is in pperation, check refrigerant level and add as necessary QCheck compressor oil level and add as necessary QInspect fan(s) for bent blades, check balance of fan blades, adjust and clean as necessary A

Equipment Description PM Procedure FrequencyWater Source Cabinet Heaters Check unit electrical connections and tighten as necessary A

Check operation of blower motor if equipped ACheck around unit, remove cover and thoroughly clean AVisually inspect condition of heating water supply and return piping for leaks A

Equipment Description PM Procedure FrequencyCirculating Pumps Check operation of system pumps under load for unusual noise, vibration and excessive heat M

Lubricate pump motor bearings AInspect couplings and check for leaks AVisually inspect pump and motor mounting, pump head and all mechanical seals for leaks AInspect and clean all pump strainers ACheck motor electrical connections and tighten as necessary ACheck drive alignment, wear, bearing and coupling seating and operation A

Equipment Description PM Procedure FrequencyFans (Exhaust, Supply, Return) Inspect fan unit assembly for unusual noise and vibration Q

Inspect belts for proper tension and wear QInspect fan and motor assembly for proper alignment QClean interior of fan assembly, motor housing and belt drive housing QCheck fan intake grills for dirt/debris QFor fans greater than 2HP rating, check load amps AInspect fan and motor pulleys for proper alignment AInspect fan blades and moving parts for excessive wear AInspect all fan wiring for deterioration AEnsure tightness of all electrical connections AInspect motor/starter control center AEnsure that overload settings are consistent with recommended manufacturer guidelines AVerify correct operation of starter AInspect electrical contact surfaces AVerify tightness of fan balance weights A

Page 33: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

29 www.EMGcorp.com p 800.733.0660

Equipment Description PM Procedure FrequencyDomestic Hot Water heaters Check water heater and controls for operation A

Inspect storage tank, piping and valves for leaks ADrain and flush storage tank AInspect and clean burners, check auto pilot operation, inspect flue (natural gas units) AConduct amprage and voltage test (electrical units) AInspect temperature and pressure relief valve for proper operation AWith compressed air, blow out the overflow and drain lines AMeasure the end point outflow temperature and adjust if necessary (maximum 120o F) A

Equipment Description PM Procedure FrequencyPlumbing System Inspect plumbing fixtures for cracks SA

Check operation of all water valves and faucets SAInspect domestic water supply and waste piping for leaks SACheck operation of flush valves and flush sensors and inspect valve seats for leaks SAInspect drains and drain lines for leaks and blockages SAVisually inspect base of all commodes for leaks at flange wax ring AVisually inspect all plumbing lines and valves at HVAC equipment for leaks and corrosion A

Page 34: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

30 www.EMGcorp.com p 800.733.0660

Equipment Description PM Procedure FrequencyElectrical Distribution Systems Switchgear

Thoroughly clean exterior and interior of the switchgear housing 36 MonthsClean all vents, grills and louvers 36 MonthsThoroughly inspect top of switchgear case and immediate vicinity of switchgear for signs of moisture intrusion and/or water seepage 36 MonthsVisually inspect insulators and conductor supports for signs of wear, physical damage or overheating 36 MonthsExamine and tighten as necessary all connections; inspect conductors for signs of wear, cracking, overheating or damage 36 MonthsVerify operation of all cicruit breakers, arc interrupters, disconnects and auxiliary devices 36 MonthsBattery Stations and ChargersThoroughly clean battery surfaces, remove any corrosion on terminals and battery lugs, inspect and clean battery studs, inspect braided cable for corrosion, check electrolytre levels and specific gravity AVisually inspect chargers and thoroughly clean, verify operation of all relays, inspect and clean all vents and openings ACheck and test operation of charger units ACables, Bus Ducts and RacewaysVisually inspect for surface damage, excessive tension, soft spots, damaged insulation, corrosion and evidence of overheating 36 MonthsRemove bus duct joint covers and perform a thermographic survey of the bus duct under load to determine potential overheating 36 MonthsTransformersThoroughly clean all coils, insulators and connections and tighten all connections AIf cooling fans are installed, ensure proper operation and lubricate according to manufacturer's specific instriuctions AFor liquid-filled transformers, sample and test insulating liquid for dielectric breakdown, acidity, color, power factor and interfacial tension AFor liquid-filled transformers, examine the transformer tank and bushings for leakage AUPS SystemClean interior and exterior of cabinets and enclosures; clean all vent and air circulation openings; clean cooling fan blades (if installed) and motor housings; lubricate motor bearings and ensure fan blades are properly secured to drive shafts ACheck inverters for fluid leaks from wave-forming capacitors; check capacitors for signs of bulging or discoloration AAll systemsInfrared or thermographic survey under load 36 MonthsLighting and receptaclesCheck for normal operation of all lighting fixtures and verify operation of all switches and receptacles M

Equipment Description PM Procedure FrequencyElevators Check cables for deterioration SA

During full range of operating motion, check for unusual noise or car movement SAInspect brake shoes for deterioration SACheck all panel buttons in car and at each floor for proper function SACheck operation of elevator car doors, including auto door opening devices and other safety features SATest emergency communication system SA

Page 35: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

31 www.EMGcorp.com p 800.733.0660

Equipment Description PM Procedure FrequencyBuilding exteriors Check for graffitti and remove M

Inspect walls for cracks, painting requirements and condition of mortar joints in masonry SACheck illuminated signage and directional signage for proper operation SAVisually inspect entrances, steps, handrails, porches and patios A

Equipment Description PM Procedure FrequencyRoof Remove any trash or debris from roof and remove any debris from roof drain covers M

Inspect and clean all gutters and downspouts SAVisually inspect entire roof surface for blisters, cracks, wrinkles, delamination of membrane, punctures, loose or damaged flashing, leaking pitch pans, ridge and saddle condition (pitched roofs) AVisually inspect all roof access ladders and roof access hatches for integrity, correct fastening and for full range of motion A

Equipment Description PM Procedure Frequency

Doors and hardwareCheck all doors for normal operation and for full range of motion, note any biding at door head or jamb SACheck all door latching hardware, dead bolts, magnetic catches, numeric key pads, electronic locking and latching mechanisms and all safety devices (for example panic bars) for normal operation SACheck, adjust and lubricate door closers SAInspect doors and frames for general condition and alignment including all door glazing, kick plates, push plates and weather stripping (exterior doors) SA

Equipment Description PM Procedure FrequencyWindows and Hardware Check general condition of glazing and replace broken or cracked panes SA

Visually inspect condition of window seals and exterior caulking and sealants SACheck operation of all window loacks SAOpen and close all windows to verify operation and to check for binding and adjust as necessary SACheck condition of window screens (where fitted) and replace or repair damaged screens SA

Page 36: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

32 www.EMGcorp.com p 800.733.0660

1 0 . A PP E N DI CE S

Appendix A: PHOTOGRAPHIC RECORD

Appendix B: SITE AND FLOOR PLANS

Appendix C: SUPPORTING DOCUMENTATION

Appendix D: EMG ACCESSIBILITY CHECKLIST

Appendix E: PRE-SURVEY QUESTIONNAIRE

Appendix F: ACRONYMS

Appendix G: GLOSSARY OF TERMS

Page 37: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT  

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

APPENDIX A:

PHOTOGRAPHIC RECORD

Page 38: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

 Randolph Howell Elementary 653 Bear Creek Pike Columbia, Tennessee 38401  EMG PROJECT NO: 116732.15R000-019.017

 

 

www.EMGcorp.com   p 800.733.0660     

PHOTO #1: 

HOWELL ELEMENTARY (MAIN ENTRANCE) 

 

PHOTO #2:

HOWELL ELEMENTARY (SOUTHEAST ELEVATION) 

 

PHOTO #3: 

HOWELL ELEMENTARY (SOUTHWEST ELEVATION)

 

PHOTO #4:

HOWELL ELEMENTARY (INTERIOR COURTYARD) 

 

PHOTO #5: 

HOWELL ELEMENTARY (EAST ELEVATION) 

 

PHOTO #6:

PLAYGROUND  

      

Page 39: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

 Randolph Howell Elementary 653 Bear Creek Pike Columbia, Tennessee 38401  EMG PROJECT NO: 116732.15R000-019.017

 

 

www.EMGcorp.com   p 800.733.0660     

PHOTO #7: 

FACULTY RESTROOM 

PHOTO #8:

CLASSROOM 

PHOTO #9: 

CAFETERIA  

PHOTO #10:

MAIN ENTRANCE  

PHOTO #11: 

GIRLS RESTROOM 

 

PHOTO #12:

STAGE IN GYMNASIUM 

 

      

Page 40: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

 Randolph Howell Elementary 653 Bear Creek Pike Columbia, Tennessee 38401  EMG PROJECT NO: 116732.15R000-019.017

 

 

www.EMGcorp.com   p 800.733.0660     

PHOTO #13: 

LIBRARY  

PHOTO #14:

LIFT FOR STAGE IN GYMNASIUM 

PHOTO #15: 

LAVATORIES FOR GIRL/BOY RESTROOM 

 

PHOTO #16:

LIBRARY 

PHOTO #17: 

GYMNASIUM FLOORING 

PHOTO #18:

PREFABRICATED STORAGE BUILDING

 

      

Page 41: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

 Randolph Howell Elementary 653 Bear Creek Pike Columbia, Tennessee 38401  EMG PROJECT NO: 116732.15R000-019.017

 

 

www.EMGcorp.com   p 800.733.0660     

PHOTO #19: 

ASPHALT PAVEMENT  

PHOTO #20:

ASPHALT PAVEMENT  

PHOTO #21: 

ASPHALT PAVEMENT  

PHOTO #22:

CHAIN LINK FENCE  

PHOTO #23: 

CRACKING IN CMU  

PHOTO #24:

CRACK IN CMU  

      

Page 42: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

 Randolph Howell Elementary 653 Bear Creek Pike Columbia, Tennessee 38401  EMG PROJECT NO: 116732.15R000-019.017

 

 

www.EMGcorp.com   p 800.733.0660     

PHOTO #25: 

CRACKING IN MASONRY 

PHOTO #26:

ICEMAKER 

PHOTO #27: 

FOOD WARMER  

PHOTO #28:

REFRIGERATED CHEST  

PHOTO #29: 

CERAMIC TILE FLOORING 

PHOTO #30:

FREEZER/COOLER  

      

Page 43: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

 Randolph Howell Elementary 653 Bear Creek Pike Columbia, Tennessee 38401  EMG PROJECT NO: 116732.15R000-019.017

 

 

www.EMGcorp.com   p 800.733.0660     

PHOTO #31: 

CORRIDOR FINISHES  

PHOTO #32:

DISHWASHER 

PHOTO #33: 

REACH-IN COOLER  

PHOTO #34:

CONVECTION OVEN  

PHOTO #35: 

TILTING SKILLETT  

PHOTO #36:

REFRIGERATED CHEST  

      

Page 44: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

 Randolph Howell Elementary 653 Bear Creek Pike Columbia, Tennessee 38401  EMG PROJECT NO: 116732.15R000-019.017

 

 

www.EMGcorp.com   p 800.733.0660     

PHOTO #37: 

DAMAGED VINYL TILE 

PHOTO #38:

ACOUSTICAL TILE CEILING 

 

PHOTO #39: 

GEOTHERMAL HEAT PUMP 

PHOTO #40:

PACKAGED ROOFTOP HEAT PUMP

 

PHOTO #41: 

PACKAGED ROOFTOP HEAT PUMP 

 

PHOTO #42:

DOMESTIC WATER HEATER  

      

Page 45: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

 Randolph Howell Elementary 653 Bear Creek Pike Columbia, Tennessee 38401  EMG PROJECT NO: 116732.15R000-019.017

 

 

www.EMGcorp.com   p 800.733.0660     

PHOTO #43: 

DOMESTIC WATER HEATER 

PHOTO #44:

PREFABRICATED TEMPORARY BUILDING

 

  

Page 46: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT  

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

APPENDIX B:

S ITE AND FLOOR PLANS

Page 47: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

Site Plan

Project Name: Randolph Howell Elementary

Project Number: 116732.15R000-019.017

Source: Google Earth Pro

On-Site Date: January 27, 2016

Page 48: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com
Page 49: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT  

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

APPENDIX C:

SUPPORTING DOCUMENTATION

Page 50: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

                              

 

TT HH II SS AA PP PP EE NN DD II XX II SS II NN TT EE NN TT II OO NN AA LL LL YY LL EE FF TT

BB LL AA NN KK ..                            

Page 51: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT  

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

APPENDIX D:

EMG ACCESSIBILITY CHECKLIST

Page 52: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

Site Name: Randolph Howell Elementary Site Location: Columbia, Tennessee Date of onsite: January 27, 2016 Project No.: 116732.15R000-019.017

EMG Abbreviated Accessibility Checklist

Building History Yes No N/A Comments

1. Has the management previously completed an ADA review?

2. Have any ADA improvements been made to the property?

3. Does a Barrier Removal Plan exist for the property?

4.

Has the Barrier Removal Plan been reviewed/approved by an arms-length third party such as an engineering firm, architectural firm, building department, other agencies, etc.?

5. Has building ownership or management received any ADA related complaints that have not been resolved?

6. Is any litigation pending related to ADA issues?

Parking Yes No N/A Comments

1. Are there sufficient parking spaces with respect to the total number of reported spaces?

2. Are there sufficient van-accessible parking spaces available (96” wide/ 96” aisle for van)?

3.

Are accessible spaces marked with the International Symbol of Accessibility? Are there signs reading “Van Accessible” at van spaces?

4.

Is there at least one accessible route provided within the boundary of the site from public transportation stops, accessible parking spaces, passenger loading zones, if provided, and public streets and sidewalks?

5. Do curbs on the accessible route have depressed, ramped curb cuts at drives, paths, and drop-offs?

6. Does signage exist directing you to accessible parking and an accessible building entrance?

Page 53: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

EMG Abbreviated Accessibility Checklist

Ramps Yes No N/A Comments

1. If there is a ramp from parking to an accessible building entrance, does it meet slope requirements? (1:12)

2. Are ramps longer than 6 ft complete with railings on both sides?

3. Is the width between railings at least 36 inches?

4. Is there a level landing for every 30 ft horizontal length of ramp, at the top and at the bottom of ramps and switchbacks?

Entrances/Exits Yes No N/A Comments

1. Is the main accessible entrance doorway at least 32 inches wide?

2. If the main entrance is inaccessible, are there alternate accessible entrances?

3. Can the alternate accessible entrance be used independently?

4.

Is the door hardware easy to operate (lever/push type hardware, no twisting required, and not higher than 48 inches above the floor)?

5. Are main entry doors other than revolving door available?

6.

If there are two main doors in series, is the minimum space between the doors 48 inches plus the width of any door swinging into the space?

Paths of Travel Yes No N/A Comments

1. Is the main path of travel free of obstruction and wide enough for a wheelchair (at least 36 inches wide)?

2.

Does a visual scan of the main path reveal any obstacles (phones, fountains, etc.) that protrude more than 4 inches into walkways or corridors?

3. Are floor surfaces firm, stable, and slip resistant (carpets wheelchair friendly)?

4. Is at least one wheelchair-accessible public telephone available?

5. Are wheelchair-accessible facilities (toilet rooms, exits, etc.) identified with signage?

6. Is there a path of travel that does not require the use of stairs?

7. If audible fire alarms are present, are visual alarms (strobe light alarms) also installed in all common areas?

Page 54: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

EMG Abbreviated Accessibility Checklist

Elevators Yes No N/A Comments

1. Do the call buttons have visual signals to indicate when a call is registered and answered?

2. Are there visual and audible signals inside cars indicating floor change?

3. Are there standard raised and Braille marking on both jambs of each host way entrance?

4. Do elevator doors have a reopening device that will stop and reopen a car door if an object or a person obstructs the door?

5. Do elevator lobbies have visual and audible indicators of car arrival?

6. Does the elevator interior provide sufficient wheelchair turning area (51” x 68”)?

7. Are elevator controls low enough to be reached from a wheelchair (48 inches front approach/54 inches side approach)?

8.

Are elevator control buttons designated by Braille and by raised standard alphabet characters (mounted to the left of the button)?

9. If a two-way emergency communication system is provided within the elevator cab, is it usable without voice communication?

Restrooms Yes No N/A Comments

1. Are common area public restrooms located on an accessible route?

2. Are pull handles push/pull or lever type?

3. Are there audible and visual fire alarm devices in the toilet rooms?

4. Are corridor access doors wheelchair-accessible (at least 32 inches wide)?

5. Are public restrooms large enough to accommodate a wheelchair turnaround (60” turning diameter)?

6. In unisex toilet rooms, are there safety alarms with pull cords?

7. Are stall doors wheelchair accessible (at least 32” wide)?

8. Are grab bars provided in toilet stalls?

9. Are sinks provided with clearance for a wheelchair to roll under (29” clearance)?

10. Are sink handles operable with one hand without grasping, pinching or twisting?

Page 55: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

EMG Abbreviated Accessibility Checklist

Restrooms (cont.) Yes No N/A Comments

11. Are exposed pipes under sink sufficiently insulated against contact?

12. Are soap dispensers, towel, etc. reachable (48” from floor for frontal approach, 54” for side approach)?

13. Is the base of the mirror no more than 40” from the floor?

Page 56: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT  

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

APPENDIX E:

PRE-SURVEY QUESTIONNAIRE

Page 57: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com
Page 58: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com
Page 59: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com
Page 60: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com
Page 61: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT  

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

On the day of the site visit, provide EMG's Field Observer access to all of the available documents listed below. Provide copies if possible.

INFORMATION REQUIRED 1. All available construction documents (blueprints) for the original construction of the building or for any tenant improvement work or other recent construction work. 2. A site plan, preferably 8 1/2" X 11", which depicts the arrangement of buildings, roads, parking stalls, and other site features. 3. For commercial properties, provide a tenant list which identifies the names of each tenant, vacant tenant units, the floor area of each tenant space, and the gross and net leasable area of the building(s). 4. For apartment properties, provide a summary of the apartment unit types and apartment unit type quantities, including the floor area of each apartment unit as measured in square feet. 5. For hotel or nursing home properties, provide a summary of the room types and room type quantities. 6. Copies of Certificates of Occupancy, building permits, fire or health department inspection reports, elevator inspection certificates, roof or HVAC warranties, or any other similar, relevant documents. 7. The names of the local utility companies which serve the property, including the water, sewer, electric, gas, and phone companies.

8. The company name, phone number, and contact person of all outside vendors who serve the property, such as mechanical contractors, roof contractors, fire sprinkler or fire extinguisher testing contractors, and elevator contractors. 9. A summary of recent (over the last 5 years) capital improvement work which describes the scope of the work and the estimated cost of the improvements. Executed contracts or proposals for improvements. Historical costs for repairs, improvements, and replacements. 10. Records of system and material ages (roof, MEP, paving, finishes, furnishings). 11. Any brochures or marketing information. 12. Appraisal, either current or previously prepared. 13. Current occupancy percentage and typical turnover rate records (for commercial and apartment properties). 14. Previous reports pertaining to the physical condition of property. 15. ADA survey and status of improvements implemented. 16. Current / pending litigation related to property condition.

Your timely compliance with this request is greatly appreciated.

Page 62: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT  

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

APPENDIX F:

ACRONYMS

Page 63: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT  

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

ASTM E2018-08 Acronyms ADA - The Americans with Disabilities Act

ASTM - American Society for Testing and Materials

BOMA - Building Owners and Managers Association

BUR - Built-up Roofing

DWV – Drainage, Waste, Ventilation

EIFS - Exterior Insulation and Finish System

EMF – Electro Magnetic Fields

EMS - Energy Management System

EUL - Expected Useful Life

FCA – Facility Condition Assessment

FEMA - Federal Emergency Management Agency

FFHA - Federal Fair Housing Act

FIRMS - Flood Insurance Rate Maps

FRT- Fire Retardant Treated

FOIA - U.S. Freedom of Information Act (5 USC 552 et seq.) and similar state statutes.

FOIL - Freedom of Information Letter

FM - Factory Mutual

HVAC - Heating, Ventilating and Air Conditioning

IAQ - Indoor Air Quality

MEP – Mechanical, Electrical and Plumbing

NFPA - National Fire Protection Association

PNA – Physical Needs Assessment

PCR - Property Condition Report

PML - Probable Maximum Loss

RTU - Rooftop Unit

RUL - Remaining Useful Life

STC – Sound Transmission Class

UBC – Uniform Building Code

Page 64: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT  

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

APPENDIX G:

GLOSSARY OF TERMS

Page 65: FACILITY CONDITION ASSESSMENT...FACILITY CONDITION ASSESSMENT RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017 3 ww w.EMGcorp.com

FACILITY CONDITION ASSESSMENT  

RANDOLPH HOWELL ELEMENTARY 653 BEAR CREEK PIKE COLUMBIA, TENNESSEE 38401 EMG PROJECT NO: 116732.15R000-019.017

www.EMGcorp.com p 800.733.0660

Glossary of Terms and Acronyms ECM Energy Conservation Measures are projects recommended to reduce energy consumption. These can be No/Low cost items implemented as part of routine maintenance or Capital Cost items to be implemented as a capital improvement project.

Initial Investment The estimated cost of implementing an ECM project. Estimates typically are based on R.S. Means Construction cost data and Industry Standards.

Annual Energy Savings The reduction in energy consumption attributable to the implementation of a particular ECM. These savings values do not include the interactive effects of other ECMs.

Cost Savings The expected reduction in utility or energy costs achieved through the corresponding reduction in energy consumption by implementation of an ECM.

Simple Payback Period The number of years required for the cumulative value of energy or water cost savings less future non-fuel or non-water costs to equal the investment costs of the building energy or water system, without consideration of discount rates.

EUL Expected Useful Life is the estimated lifespan of a typical piece of equipment based on industry accepted standards.

RUL Remaining Useful Life is the EUL minus the effective age of the equipment and reflects the estimated number of operating years remaining for the item.

SIR The savings-to-investment ratio is the ratio of the present value savings to the present value costs of an energy or water conservation measure. The numerator of the ratio is the present value of net savings in energy or water and non-fuel or non-water operation and maintenance costs attributable to the proposed energy or water conservation measure. The denominator of the ratio is the present value of the net increase in investment and replacement costs less salvage value attributable to the proposed energy or water conservation measure. It is recommended that energy-efficiency recommendations be based on a calculated SIR, with larger SIRs receiving a higher priority. A project typically is recommended only if the SIR is greater than or equal to 1.0, unless other factors outweigh the financial benefit. Life Cycle Cost The sum of the present values of (a) Investment costs, less salvage values at the end of the study period; (b) Non-fuel operation and maintenance costs: (c) Replacement costs less salvage costs of replaced building systems; and (d) Energy and/or water costs.

Life Cycle Savings The sum of the estimated annual cost savings over the EUL of the recommended ECM, expressed in present value dollars.

Building Site Energy Use Intensity The sum of the total site energy use in thousands of Btu per unit of gross building area. Site energy accounts for all energy consumed at the building location only not the energy consumed during generation and transmission of the energy to the site.

Building Source Energy Use Intensity The sum of the total source energy use in thousands of Btu per unit of gross building area. Source energy is the energy consumed during generation and transmission in supplying the energy to your site.

Building Cost Intensity This metric is the sum of all energy use costs in dollars per unit of gross building area.

Greenhouse Gas Emissions Although there are numerous gases that are classified as contributors to the total for Greenhouse Emissions , the scope of this energy audit focuses on carbon dioxide (CO2). Carbon dioxide enters the atmosphere through the burning of fossil fuels (oil, natural gas, and coal), solid waste, trees and wood products, and also as a result of other chemical reactions (e.g., manufacture of cement).