220
Anacostia High School 1601 16th Street SE Washington, DC 20020 Date of Report: August 31, 2018 Facility Condition Assessment Submitted By: 3715 Martin Luther King Jr. Avenue, SE Washington, DC 20032

Transcript of Facility Condition Assessment - | dgs

Page 1: Facility Condition Assessment - | dgs

Anacostia High School1601 16th Street SE

Washington, DC20020

Date of Report: August 31, 2018

Facility ConditionAssessment

Submitted By:

3715 Martin Luther King Jr. Avenue, SEWashington, DC 20032

Page 2: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

EXECUTIVE SUMMARY............................................................................................................................................... 31.1 General Description................................................................................................................................................. 31.2 Scope of Work......................................................................................................................................................... 31.3 Definitions................................................................................................................................................................ 41.4 Limiting Conditions................................................................................................................................................... 61.5 Building Summary.................................................................................................................................................... 71.6 Summary Of Findings.............................................................................................................................................. 81.7 Facility Condition Index............................................................................................................................................ 91.8 Expenditure Forecast............................................................................................................................................. 111.9 Assets Observed.................................................................................................................................................... 131.10 Needs Sorted by Plan Type................................................................................................................................. 141.11 Distribution of Immediate (Year 1) Needs by Building System............................................................................ 161.12 Distribution of Future (Year 2-Year 10) Needs by Building System.....................................................................17

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 2 of 220

Page 3: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

EXECUTIVE SUMMARY

1.1 General Description

In accordance with the purchase order contract held between Yes Prep Public Schools, Inc. purchase order P800015870dated June 5, 2018 and Inc., this completed report provides a comprehensive Facility Condition Assessment of theAnacostia High School located at 1601 16th Street SE, Washington , DC, 20020 (The Property). This report has beenprepared for the exclusive and sole use of the Yes Prep Public Schools, Inc.

This report provides a summary of the facility information known to us at the time of the study, the scope of work performed,an equipment inventory, evaluation of the visually apparent condition of the Property together with a forecast of capitalexpenditures anticipated over the next 10 years. The expenditure forecast does not account for typical preventativemaintenance items such as changing filters to fan coil units.

Our cost rates to produce life cycle and replacement cost estimates are based on our knowledge of the local regionalmarket rates. The data in this report represent an opinion of probable cost of construction and is made on the basis of theexperience, qualifications, and best judgment of the professional consultant familiar with the construction industry.

The report provides a summary of the anticipated primary expenditures over the 10-year study period. Further details ofthese expenditures are included within each respective report section and within the deficiency report, in Appendix A.

In this report we have calculated the Facility Condition Index (FCI) which is used in Facilities Management to provide abenchmark to compare the relative condition of a group of facilities. The FCI is primarily used to support asset managementinitiatives of federal, state, and local government facilities organizations.

The FCAs were carried out by Hayat Brown LLC (Contractor) and included a complete and thorough visual, non-destructiveassessment of each facility. The Contractor followed ASTM standards ("ASTM E2018-08") for conducting property conditionassessments, as well as guidance from DGS regarding additional survey information and cost estimates for possible plantadaptations. The FCA Report summarizes the FCA process, which included the following:

• Review of existing documentation provided by the LEA and interviews with LEA personnel regarding aspects ofeach facility.

• Physical assessment to include a limited non-intrusive visual assessment of the buildings and their components.• Identify and categorize each major component for predictive maintenance, testing and/or inspection, preventative

maintenance, emergency maintenance and/or routine maintenance needs.• Based on provided templates surveyed elements included:

o Core and shell: These elements include superstructure, floors, bearing walls, columns, beams, and exterior envelopecomponents.

o Interiors: These elements include interior finishes of floors, walls, ceilings, stairways, etc.o Building equipment and systems: These elements include HVAC systems, and electrical systems, fire protection

systems, and conveyor systems.o Fixed equipment and non-movable furnishings: These elements include fixed equipment such as kitchen equipment,

audio equipment, public address systems, etc.o Building site Improvements: These elements include paved surfaces, playground equipment, fencing, recreational

elements, site lighting, general site drainage and landscaping.

• Evaluated additional elements based on questionnaires provided by the schools. These questionnaires were answeredbased on interviewing the facility staff and visual surveys:

o ADA accessibility: included questions relating to accessibility barriers of interior and exterior elementso Safety and security: included questions relating to safety and security of the facility such as fire protection systemso Access control: included questions relating to controlled access to the facility such as intrusion detection systems and

component hardwareo Hazardous materials: included questions relating to the existence of hazardous materials at each facilityo LEED opportunities: included questions relating to existing components and improving LEED certification pointso Additional space considerations: included additional questions relating to space allocation and the existence of special

features

1.2 Scope of Work

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 3 of 220

Page 4: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

1.3 Definitions

Facility Condition Assessment Report (FCA Report)

Document Reviews and Interviews

Walk Through Site Assessment Survey

Costing

Physical Deficiencies

Survey Information Resulting in Plant Adaptation Recommendations

Life Cycle

Planning Horizon

The work product resulting from completing a FCA is a FCA Report. The FCA Report incorporates the information obtainedduring the Walk-Through Site Assessment Survey, the Document Review, and Interviews to support the iPlan costestimates for components at their RUL.

Includes document reviews, research, and interviews to augment the walk-through survey so as to assist the consultant'sunderstanding of the subject property and identification of physical deficiencies.

The walk-through survey identifies the subject property's elemental components, conditions, RULs, and replacement costsat RUL.

Costing is reported following the ASTM 2018-08 Guidelines Section 9, “Opinions of Costs to Remedy Physical Deficiencies.As such, they include general-scope opinions of costs to assist the user in developing a general understanding of thephysical condition of the subject property. As outlined in ASTM 2018-08, the opinion of probable costs should only beconstrued as preliminary, order of magnitude budgets. Actual costs will vary based on design, quality of materials, fieldconditions and several other factors as outlined in ASTM 2018-08. Generally, costing does not include projectmanagement, contingency, permits, hazardous material remediation (unless specifically stated on a case by case basis)and other overhead costs such as Architect and Engineering fees, profit, or other markups.

Replacement and repair costs herein are based on the two major North American Standards for facility cost estimating:Whitestone Facility Maintenance and Repair Cost Library (Costlabs); and RSMeans. Whitestone visualizes costing from aFacility Maintenance viewpoint while RSMeans approaches costing from a construction viewpoint. Using industry bestpractices, the relative strengths of each costing approach has been integrated into a unified costing guide for the conditionassessment process. The quantities associated with each item have been estimated during a walk-through during the siteassessment and do not represent exact measurements or quantities. Costs have been adjusted to the local WashingtonDC area and are stated in constant 2018 dollars. The cost guide has been utilized by the assessment team as a startingpoint for costing and supplemented by the assessors adjusting costs based upon experience and facility factors (such asinstallation design) to determine maintenance and replacement costs.

In defining good commercial and customary practice for conducting a baseline FCAs, the goal is to identify andcommunicate physical deficiencies to a user. The term physical deficiencies mean the presence of conspicuous defects ormaterial deferred maintenance of a subject property's material systems, components, or equipment as observed during theassessor’s walk-through survey. This definition specifically excludes deficiencies that may be remedied with routinemaintenance, miscellaneous minor repairs, normal operating maintenance, etc., and excludes conditions that generally donot present material physical deficiencies of the subject property.

These are methodical questions based upon defined industry or Owner standards resulting in a general costing amountthat gives an Owner a cash expenditure to plan on within proformas.

There are various approaches for determining an elemental component’s service life such as a “modeling” approach wherean industry standard expected useful life (EUL) is added to a component’s date of installation resulting in a modeled orcalculated expectation of replacement for that item. The methodology used in Hayat Brown LLC’s reported value for theexpected replacement of an elemental component is a field assessed opinion of remaining useful life (RUL). ObservedRUL takes into account a field assessor’s observation of the elemental component along with other factors such asmaintenance records or observed measurable parameters.

Since the life cycles of many elemental components exceed industry standard cash flow proformas, Hayat Brown LLC’sFCA Report only includes a timeframe of importance to an Owner’s immediate cash flow planning. In the case of thisreport, DGS requested a planning horizon window of 10 years. The Planning Horizon years and remaining useful lives(RULs) as defined in this report’s approach are summarized in the table below:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 4 of 220

Page 5: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Planning Horizon Remaining Useful Life(RUL)

Year 1 - "Immediate" or "Current" 0

Year 2 1

Year 3 2

Year 4 3

Year 5 4

Year 6 5

Year 7 6

Year 8 7

Year 9 8

Year 10 9

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 5 of 220

Page 6: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

1.4 Limiting Conditions

This report has been prepared for the exclusive and sole use of the . The report may not be relied upon by any otherperson or entity without the express written consent of .

Any reliance on this report by a third party, any decisions that a third party makes based on this report, or any use at all ofthis report by a third party is the responsibility of such third parties. Any reuse without written verification or adaptation byfor the specific purpose intended will be at user’s sole risk and without liability or legal exposure to .

The assessment of the building/site components was performed using methods and procedures that are consistent withstandard commercial and customary practice as outlined in ASTM Standard E 2018-08 for PCA assessments. As per thisASTM Standard, the assessment of the building/site components was based on a visual walk-through site visit, whichcaptured the overall condition of the site at that specific point in time only.

No legal surveys, soil tests, environmental assessments, geotechnical assessments, detailed barrier-free complianceassessments, seismic assessments, detailed engineering calculations, or quantity surveying compilations have been made.No responsibility, therefore, is assumed concerning these matters. did not design or construct the building(s) or relatedstructures and therefore will not be held responsible for the impact of any design or construction defects, whether or notdescribed in this report. No guarantee or warranty, expressed or implied, with respect to the property, building components,building systems, property systems, or any other physical aspect of The Property is made.

The recommendations and our opinion of probable costs associated with these recommendations, as presented in thisreport, are based on walk-through non-invasive observations of the parts of the building which were readily accessibleduring our visual review. Conditions may exist that are not as per the general condition of the system being observed andreported in this report. Opinions of probable costs presented in this report are also based on information received duringinterviews with operations and maintenance staff. In certain instances, has been required to assume that the informationprovided is accurate and cannot be held responsible for incorrect information received during the interview process. Shouldadditional information become available with respect to the condition of the building and/or site elements, requests that thisinformation be brought to our attention so that we may reassess the conclusions presented herein.

The opinions of probable costs are intended for global budgeting purposes only. has no control over the cost of labor andmaterials, general contractor’s or any subcontractor’s method of determining prices, or competitive bidding and marketconditions. The data in this report represent an opinion of probable cost of construction and is made on the basis of theexperience, qualifications, and best judgment of the professional consultant familiar with the construction industry. cannotand does not guarantee that proposals, bids, or actual construction costs will not vary from this or subsequent CostEstimates. The scope of work and the actual costs of the work recommended can only be determined after a detailedexamination of the site element in question, understanding of the site restrictions, understanding of the effects on theongoing operations of the site/building, definition of the construction schedule, and preparation of tender documents.

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 6 of 220

Page 7: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Items Description

Project Name Anacostia High SchoolDCAM-17-NC-0058

Full Address 1601 16th Street SE Washington, DC 20020

Year Built 1935

Gross Building Area (GSF) 204,105

Current Replacement Value (CRV) $49,189,305

CRV/GSF ($/Sq Ft) $241

1.5 Building Summary

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 7 of 220

Page 8: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

1.6 Summary Of Findings

This report represents summary-level findings for the Property Condition Assessment. The deficiencies identified in thisassessment can be combined with potential new construction requirements to develop an overall Long Term Capital NeedsPlan that can be the basis for a facility wide capital improvement funding strategy. Key findings from the Assessmentinclude:

Key Findings Metric

Current YearFacililty Condition Index 0.31 %

Property Replacement Value(in Current Dollars) $49,189,305

Immediate Capital Needs (Year 1)(included in FCI) $150,648

Year 1 to Year 5 Capital Needs $132,180

5 Year FCI(Year 1-5 Needs/CRV) 0.27 %

Year 1 to Year 10 Capital Needs $2,400,285

10 Year FCI(Year 1-10 Needs/CRV) 4.88 %

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 8 of 220

Page 9: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

1.7 Facility Condition Index

In this report we have calculated the Facility Condition Index (FCI) which is used in Facilities Management to provide abenchmark to compare the relative condition of a group of facilities. The FCI is primarily used to support asset managementinitiatives of federal, state, and local government facilities organizations.

The FCI is the ratio of accumulated Total Cost (TC) (Deferred Maintenance, Capital Renewal and Plant Adaptation) to theCurrent Replacement Value (CRV) for a constructed asset calculated by dividing the TC by the CRV. The range is fromzero for a newly constructed asset, to one for a constructed asset with a TC value equal to its CRV. Acceptable ranges varyby “Asset Type’, but as a general guideline the FCI scoring system is as follows:

FCI =

Deferred Maintenance + Capital Renewal+ Plant Adaptation (TC)

Current Replacement Value of the Facility(s) (CRV)

This CRV is based on the building type from the online Whitestone Facility Maintenance and Repair Cost Library (Costlabs)as of 1 September 2017 (a national recognized publication used in thousands on condition assessments throughout thecountry). Typically, the FCI is calculated using only the current condition values, not taking into account the future needsidentified in the life cycle evaluation or building enhancements or programmatic upgrades that may be identified in ascoping or design process.

Accounting principles indicate that a value of 65%, or the “rule of two-thirds”, be utilized for the FCI threshold for identifyingpotential replacement candidates. Once the current repair costs reach 65%, or roughly two-thirds of the full replacementvalue of the estimated cost to replace a facility, it may not be prudent to continue to fund repairs. In cases where aggressivefacilities planning is expected to be necessary, this threshold may be adjusted to address more pressing need.

Condition Definition Percentage Value

GOOD In a new or well-maintained condition, with no visualevidence of wear, soiling or other deficiencies. 0% to 5%

FAIR Subject to wear and soiling but is still in a serviceable andfunctioning condition. 5% to 10%

POOR Subjected to hard or long-term wear. Nearing the end of itsuseful or serviceable life. Greater than 10%

V-POOR Subjected to hard or long-term wear. Has reached the endof its useful or serviceable life. Renewal now necessary. Greater than 60%

Note that the Category selected is the primary factor understood to be the cause for the recommendation. However, there may be more than one driver of theneed for repair, replacement, or upgrade.

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 9 of 220

Page 10: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Cumulative Effects of FCI Over the Study Period

0.00 %

1.00 %

2.00 %

3.00 %

4.00 %

5.00 %

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

0.31 % 0.34 % 0.35 % 0.35 % 0.57 % 0.57 % 0.57 % 0.57 % 1.76 % 5.19 %

The Chart below indicates the cumulative effects of the FCNI ratio over the study period assuming the required funds andexpenditures are NOT provided to address the identified works and deferred maintenance each year.

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 10 of 220

Page 11: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Expenditure Forecast Over Study Period

$0.00K

$200.00K

$400.00K

$600.00K

$800.00K

$1000.00K

$1200.00K

$1400.00K

$1600.00K

$1800.00K

$2000.00K

EXPE

ND

ITU

RE

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

$150.65K $17.44K $5.71K $0.00K $109.04K $0.00K $0.00K $0.00K $581.92K $1,686.19K

Expenditure Forecast Over Study Period

$0.00K

$200.00K

$400.00K

$600.00K

$800.00K

$1000.00K

$1200.00K

$1400.00K

$1600.00K

$1800.00K

$2000.00K

EXPE

ND

ITU

RE

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

$215.29K $17.44K $5.71K $0.00K $109.04K $0.00K $0.00K $0.00K $581.92K $1,686.19K

Expenditure Forecast – Included in FCI

Expenditure Forecast – FCI & Non-FCI

1.8 Expenditure Forecast

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 11 of 220

Page 12: Facility Condition Assessment - | dgs

Element No. Component Description EUL

(Yrs)RUL (Yrs) Quantity Units Unit Cost Plan Type Priority 2018 2019 2021 2022 2023 2024 2025 2026 2027 TOTAL TOTAL

$ 0 1 3 4 5 6 7 8 9Deferred Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Deferred Scheduled

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

B20B2011 Repoint Brick Veneer, Exterior, 3+ Stories 25 0 800 SF $11.04 Capital Replacement $8,832 $0 $0 $0 $0 $0 $0 $0 $0 $8,832 $0

B2021 Repair Glazing for Windows 0 0 160 SF $11.16 Capital Replacement $1,786 $0 $0 $0 $0 $0 $0 $0 $0 $1,786 $0

$10,618 $0 $0 $0 $0 $0 $0 $0 $0 $10,618 $0

C30C3012 Repair Gypsum Board/Plaster, Interior Wall 0 0 600 SF $3.18 Capital Replacement $1,908 $0 $0 $0 $0 $0 $0 $0 $0 $1,908 $0

C3012 Repair Ceramic Tile, Interior Wall Finish 0 0 500 SF $16.41 Capital Replacement $8,205 $0 $0 $0 $0 $0 $0 $0 $0 $8,205 $0

C3012 Repoint Concrete Block, Exterior 25 0 650 SF $9.18 Capital Replacement $5,967 $0 $0 $0 $0 $0 $0 $0 $0 $5,967 $0

C3024 Repair Concrete Slab 0 0 400 SF $10.23 Capital Replacement $4,092 $0 $0 $0 $0 $0 $0 $0 $0 $4,092 $0

Repair Terrazzo Flooring 0 1 750 SF $23.25 Capital Replacement $0 $17,438 $0 $0 $0 $0 $0 $0 $0 $0 $17,438

Replace Terrazzo Floor Finish 10 8 18,500 SF $25.78 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $476,930 $0 $0 $476,930

C3024 Replace Rubber Floor Finish 15 4 3,942 SF $7.40 Capital Replacement $0 $0 $0 $29,171 $0 $0 $0 $0 $0 $0 $29,171

C3025 Replace Carpet Floor Finishes 8 4 13,360 SF $5.98 Capital Replacement $0 $0 $0 $79,866 $0 $0 $0 $0 $0 $0 $79,866

$20,172 $17,438 $0 $109,037 $0 $0 $0 $476,930 $0 $20,172 $603,404

D20D2018 Replace Drinking Fountains 15 9 204,105 SF $0.24 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $48,985 $0 $48,985

D2018 Replace Drinking Fountains - Annex 15 9 4 EA $1,300.00 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $5,200 $0 $5,200

D2023 Replace Water Treatment, Filtration System 15 9 1 EA $8,975.51 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $8,976 $0 $8,976

D2041 Fix the storm drainage piping that leaks in the main office, when using Emergency Eye wash and Shower.

0 0 1 LS $5,000.00 Routine Maint Minor Repairs $5,000 $0 $0 $0 $0 $0 $0 $0 $0 $5,000 $0

D30Repair the leak of flue piping for Boiler 1. 0 0 1 EA $2,000.00 Routine Maint Minor Repairs $2,000 $0 $0 $0 $0 $0 $0 $0 $0 $2,000 $0

Replace Boiler 3, Gas-fired, 1500 Mbh (x1) 25 0 1 EA $55,545.00 Capital Replacement $55,545 $0 $0 $0 $0 $0 $0 $0 $0 $55,545 $0

Replace Boiler 3, which is down. 0 0 1 EA $55,545.00 Capital Replacement $55,545 $0 $0 $0 $0 $0 $0 $0 $0 $55,545 $0

Repair the leak of flue piping for Boiler 1. 0 0 1 EA $2,000.00 Routine Maint Minor Repairs $2,000 $0 $0 $0 $0 $0 $0 $0 $0 $2,000 $0

Replace Boiler 3, which is down. 0 0 1 EA $55,545.00 Routine Maint Minor Repairs $55,545 $0 $0 $0 $0 $0 $0 $0 $0 $55,545 $0

D3031 Replace Cooling Tower, 250 Ton (x2) 15 9 2 EA $39,762.16 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $79,524 $0 $79,524

D3032 Replace Condensing Unit, ~5 HP 15 9 1 EA $5,967.18 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $5,967 $0 $5,967

D3032 Replace Air-Cooled Condenser, 2 Ton 15 9 1 EA $2,251.84 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $2,252 $0 $2,252

D3032 Replace Air-Cooled Condenser, 2 Ton 15 9 1 EA $2,251.84 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $2,252 $0 $2,252

D3021 $0

$0

$0

$0

$0

$0

Plumbing$0

$0

$0

$0

HVACD3021 $0

$0

$0

$0

$0

C Interiors SUB TOTALS $0

D Services

Interior Finishes$0

$0

$0

$0

C3024 $0

$0

$0

$0

B Shell SUB TOTALS $0

C Interiors

A SubStructure SUB TOTALS $0

B Shell

Exterior Enclosure

10 YEAR EXPENDITURE FORECASTAnacostia High School1601 16TH STREET SEWashington, DC

2020

2Scheduled

A SubStructure

Page 12 of 220

Page 13: Facility Condition Assessment - | dgs

D3041 Replace Energy Recovery Unit, 27,500 CFM 15 9 1 EA $30,000.00 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $30,000 $0 $30,000

D3041 Replace Split A/C System Indoor Unit 15 9 2 EA $1,498.69 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $2,997 $0 $2,997

D3042 Replace Kitchen Exhaust Hood 15 9 1 EA $7,629.74 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $7,630 $0 $7,630

D3045 Replace the chilled water piping cracked at a valve controller. 0 0 1 LS $3,000.00 Capital Replacement $3,000 $0 $0 $0 $0 $0 $0 $0 $0 $3,000 $0

D3052 Replace Rooftop Units, 95 Ton 15 9 1 EA $149,058.09 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $149,058 $0 $149,058

D3052 Replace Rooftop Units, 134 Ton 15 9 1 EA $203,840.27 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $203,840 $0 $203,840

D3052 Replace Rooftop Units, 40 Ton 15 9 1 EA $60,856.40 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $60,856 $0 $60,856

D3052 Replace Rooftop Units, 95 Ton 15 9 1 EA $149,058.09 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $149,058 $0 $149,058

D3052 Replace Rooftop Units, 60 Ton 15 9 1 EA $85,593.37 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $85,593 $0 $85,593

Reattach the thermostat detached from the wall of room M211

0 0 1 EA $100.00 Routine Maint Minor Repairs $100 $0 $0 $0 $0 $0 $0 $0 $0 $100 $0

Replace HVAC Control System 15 9 204,105 SF $2.70 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $551,084 $0 $551,084

Replace VFD Controller for Pump 5. 0 0 1 EA $3,000.00 Capital Replacement $3,000 $0 $0 $0 $0 $0 $0 $0 $0 $3,000 $0

D50D5031 Replace Sound System, 7 Channel 15 9 6 EA $2,067.61 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $12,406 $0 $12,406

D5038 Replace Card Reader 15 9 18 EA $925.55 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $16,660 $0 $16,660

D5038 Replace Electronic Article Surveillance System (EA) 15 9 2 EA $745.00 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $1,490 $0 $1,490

D5038 Replace Screening Magnetometer 15 9 4 EA $3,172.36 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $12,689 $0 $12,689

D5038 Replace Screening X-Ray Machine 15 9 3 EA $46,502.99 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $139,509 $0 $139,509

D5038 Replace Security (LF), Surveillance, Exterior Perimeter 15 9 1,961 LF $29.79 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $58,418 $0 $58,418

$181,735 $0 $0 $0 $0 $0 $0 $0 $1,634,445 $181,735 $1,634,445

E10E1027 Replace Laboratory Sinks 15 9 84 EA $528.23 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $44,371 $0 $44,371

E1027 Replace Laboratory Exhaust Hood 15 9 3 EA $2,457.74 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $7,373 $0 $7,373

$0 $0 $0 $0 $0 $0 $0 $0 $51,744 $0 $51,744

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

G20G2022 Replace Asphalt Paved Parking Lot 20 8 20,610 SF $4.50 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $92,745 $0 $0 $92,745

G2022 Repair Concrete Pavement 0 0 890 SF $1.99 Capital Replacement $1,771 $0 $0 $0 $0 $0 $0 $0 $0 $1,771 $0

G2042 Replace Retaining Wall Cast in Place Concrete 40 8 86 LF $142.34 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $12,241 $0 $0 $12,241

G40G4021 Replace Site Lighting, Bollard, 175W MH 20 2 5 EA $1,141.16 Capital Replacement $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,706

$1,771 $0 $0 $0 $0 $0 $0 $104,986 $0 $1,771 $110,692

Z10Lavatory - Install cover panel 0 0 1 LS $347.60 Capital Replacement $348 $0 $0 $0 $0 $0 $0 $0 $0 $348 $0

Restroom - Install grab bar 0 0 2 EA $325.00 Capital Replacement $650 $0 $0 $0 $0 $0 $0 $0 $0 $650 $0

$998 $0 $0 $0 $0 $0 $0 $0 $0 $998 $0

$215,293 $17,438 $0 $109,037 $0 $0 $0 $581,916 $1,686,189 $215,293 $2,400,285

$215,293 $18,135 $0 $127,558 $0 $0 $0 $796,393 $2,399,973 TOTAL* $2,615,579* - Present Value Dollars

Z General SUB TOTALS $0

Expenditure Totals per Year $5,706

Total Cost (Inflated @ 4% per Yr.) $6,171

G Building Sitework SUB TOTALS $5,706

Z General

General RequirementsZ1010.2 $0

$0

$0

$0

$0

Site Electrical Utilities$5,706

F Special Construction And Demolition SUB TOTALS $0

G Building Sitework

Site Improvements

$0

E Equipment & Furnishing SUB TOTALS $0

F Special Construction And Demolition

D Services SUB TOTALS $0

E Equipment & Furnishing

Equipment$0

Electrical Systems$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

D3068 $0

$0

$0

$0

$0

Page 13 of 220

Page 14: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

A - SubStructure

A10 - FoundationsA20 - Basement Construction

B - Shell

B10 - SuperStructureB20 - Exterior EnclosureB30 - Roofing

C - Interiors

C10 - Interior ConstructionC20 - StairsC30 - Interior Finishes

D - Services

D10 - Conveying SystemsD20 - PlumbingD30 - HVACD40 - Fire Protection SystemsD50 - Electrical Systems

E - Equipment & Furnishing

E10 - EquipmentE20 - Furnishings

F - Special Construction And Demolition

F10 - Special ConstructionF20 - Selective Demolition

G - Building Sitework

G10 - Site PreparationG20 - Site ImprovementsG30 - Site Civil/Mechanical UtilitiesG40 - Site Electrical UtilitiesG90 - Other Site Construction

Z - General

Z10 - General RequirementsZ20 - Bidding Requirements, Contract Forms, ConditionsZ90 - Project Cost Estimate

All assets observed are provided in this report sorted by the Uniformat II coding, indexed is as follows:

1.9 Assets Observed

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 14 of 220

Page 15: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

1.10 Needs Sorted by Plan Type

has prioritized the identified work according to the Plan Type or deficiency categories in order to assist with analyzing thedeficiencies found during the assessment. The following Plan Types are shown below:

The chart below illustrates the breakdown of expenditure according to the Plan Type or deficiency categories providing anopportunity to strategically plan and effectively direct funding.

Plan Type 1Deferred Maintenance:

Maintenance that was not performed when it was scheduled or past its usefullife resulting in immediate repair or replacement

Plan Type 2Routine Maintenance:

Maintenance that is planned and performed on a routine basis to maintain andpreserve the condition

Plan Type 3Capital Renewal:

Planned replacement of building systems that have or will reach the end oftheir useful life

Plan Type 4Energy & Sustainability:

When the repair or replacement of equipment or systems are recommended toimprove energy and sustainability performance

Plan Type 5ADA:

When the repair or replacement of equipment or systems are recommended tocomply with ADA

Plan Type 6Seismic: Projects identified as part of a Seismic Study

Plan Type 7Environmental:

When the repair or replacement of equipment or systems are recommended toremove hazardous materials

Plan Type 8Functionality: Projects identified to improve the functionality of the facility

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 15 of 220

Page 16: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Plan Types Total Cost

Capital Replacement $2,550,934

Routine Maint Minor Repairs $64,645

Total $2,615,579

Planning Horizon Needs by Category

Capita

l Rep

lacem

ent

Routin

e Main

t Mino

r Rep

airs

Plan Type

$0

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000Ex

pend

iture

in D

olla

rs

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 16 of 220

Page 17: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

1.11 Distribution of Immediate (Year 1) Needs by Building System

Building System Estimated Cost Percentage of Total Cost

Boilers $170,635 79.26 %

Building Automation Systems $3,100 1.44 %

Chilled Water Distribution $3,000 1.39 %

Consider: ADA Investments $998 0.46 %

Exterior Wall Construction $8,832 4.10 %

Flooring $4,092 1.90 %

Paving & Surfacing $1,771 0.82 %

Pipe & Fittings $5,000 2.32 %

Wall Finishes to Interior Walls $16,080 7.47 %

Windows $1,786 0.83 %

Total $215,293 100 %

Distribution of Immediate Needs by Building System

Boilers

Exterior Wall Construct

Wall Finishes to Interio

Building Automation S

Flooring

Windows

Chilled Water Distri

Paving & Surfacing

Consider: ADA Invest

Pipe & Fittings

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 17 of 220

Page 18: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

1.12 Distribution of Future (Year 2-Year 10) Needs by Building System

Distribution of Capital Needs by Building System

C30 Interior Finishes

D50 Electrical Systems

G40 Site Electrical Utilities

D20 Plumbing

E10 Equipment

D30 HVAC

G20 Site Improvements

Building System Estimated Cost Percentage of Total Cost

C30 Interior Finishes $603,404 25.14 %

D20 Plumbing $63,161 2.63 %

D30 HVAC $1,330,112 55.41 %

D50 Electrical Systems $241,172 10.05 %

E10 Equipment $51,744 2.16 %

G20 Site Improvements $104,986 4.37 %

G40 Site Electrical Utilities $5,706 0.24 %

Total $2,400,285 100 %

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 18 of 220

Page 19: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

ASSETS OBSERVED DETAILSAll observed assets in this section are sorted by the Uniformat II coding. Each asset will contain an assessed details table,and will also include field notes, images, and expenditures where applicable.

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 19 of 220

Page 20: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

A10 FoundationsItem Description

A10 Foundations Foundations

Condition Fair - Good

Quantity 18,670 SF

Remaining Useful Life (RUL) 15 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 20 of 220

Page 21: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

A1031 Standard Slab on GradeItem Description

A1031 Standard Slab on Grade Standard Slab on Grade

Condition Fair - Good

Quantity 87,837 SF

Remaining Useful Life (RUL) 15 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 21 of 220

Page 22: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

A20 Basement ConstructionItem Description

A20 Basement Construction Basement Construction

Condition Fair - Good

Quantity 2,110 SF

Remaining Useful Life (RUL) 15 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 22 of 220

Page 23: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

B10 SuperStructureItem Description

B10 SuperStructure SuperStructure

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 15 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 23 of 220

Page 24: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Superstructure, Ramps, Exterior,ConcreteItem Description

Superstructure, Ramps, Exterior, Concrete Exterior Concrete Ramps

Condition Good

Quantity 218 LF

Remaining Useful Life (RUL) 44 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 24 of 220

Page 25: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Superstructure, Ramps, Interior,ConcreteItem Description

Superstructure, Ramps, Interior, Concrete Interior Concrete Ramp

Condition Fair - Good

Quantity 107 LF

Remaining Useful Life (RUL) 15 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 25 of 220

Page 26: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Clay Brick, Painted, Exterior, = 3StoriesItem Description

Clay Brick, Painted, Exterior, = 3 Stories Clay Brick Exterior Wall

Condition Fair - Good

Quantity 46,032 SF

Remaining Useful Life (RUL) 15 Year(s)

Uniformat Component Description Plan Type Year Expenditures

B2011 Repoint Brick Veneer, Exterior, 3+ Stories CRP 2018 $8,832

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 26 of 220

Page 27: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Aluminum Louver, 2 StoriesItem Description

Aluminum Louver, 2 Stories Aluminum Louver

Condition Good

Quantity 7 EA

Remaining Useful Life (RUL) 54 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 27 of 220

Page 28: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Aluminum Fixed Window, = 3Stories, 24 Sq FtItem Description

Aluminum Fixed Window, = 3 Stories, 24 Sq Ft Aluminum Fixed Window

Condition Good

Quantity 376 EA

Remaining Useful Life (RUL) 24 Year(s)

Uniformat Component Description Plan Type Year Expenditures

B2021 Repair Glazing for Windows CRP 2018 $1,786

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 28 of 220

Page 29: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Steel w/ Safety Glass, Painted,Exterior DoorItem Description

Steel w/ Safety Glass, Painted, Exterior Door Steel w/ Safety Glass Exterior Door

Condition Good

Quantity 27 EA

Remaining Useful Life (RUL) 69 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 29 of 220

Page 30: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Steel w/ Safety Glass, Painted,Exterior DoorItem Description

Steel w/ Safety Glass, Painted, Exterior Door Steel Exterior Door

Condition Fair - Good

Quantity 9 EA

Remaining Useful Life (RUL) 15 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 30 of 220

Page 31: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Other Doors & Entrances, RollingDoor, SteelItem Description

Other Doors & Entrances, Rolling Door, Steel Stell Doors & Entrances, Rolling Door

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 12 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 31 of 220

Page 32: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Green Roof w Growing Medium,Rubberized AsphaltItem Description

Green Roof w Growing Medium, Rubberized Asphalt Green Roof w Growing Medium

Condition Fair - Good

Quantity 32,800 SF

Remaining Useful Life (RUL) 14 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 32 of 220

Page 33: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Roof Coverings, InvertedMembrane SystemItem Description

Roof Coverings, Inverted Membrane System Inverted Membrane Roof Covering

Condition Good

Quantity 32,800 SF

Remaining Useful Life (RUL) 24 Year(s)

Description:There are leakage from the Roof and need maintenance.

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 33 of 220

Page 34: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Roof Coverings, Metal Panels,CorrugatedItem Description

Roof Coverings, Metal Panels, Corrugated Corrugated Roof Covering

Condition Good

Quantity 26,400 SF

Remaining Useful Life (RUL) 24 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 34 of 220

Page 35: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Roof Coverings, Slate RoofShinglesItem Description

Roof Coverings, Slate Roof Shingles Slate Roof Shingles Roof Covering

Condition Good

Quantity 27,320 SF

Remaining Useful Life (RUL) 64 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 35 of 220

Page 36: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Roof Openings, Metal Framed,Glass SkylightItem Description

Roof Openings, Metal Framed, Glass Skylight Metal Frame Skylights

Condition Good

Quantity 441 SF

Remaining Useful Life (RUL) 24 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 36 of 220

Page 37: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Roof Hatch, AluminumItem Description

Roof Hatch, Aluminum Aluminum Roof Hatch

Condition Good

Quantity 4 EA

Remaining Useful Life (RUL) 44 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 37 of 220

Page 38: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Interior Windows & Storefronts -StandardItem Description

Interior Windows & Storefronts - Standard Interior Windows & Storefronts - Standard

Condition Good

Quantity 1,120 SF

Remaining Useful Life (RUL) 24 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 38 of 220

Page 39: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Aluminum, Fully Glazed, InteriorDoorItem Description

Aluminum, Fully Glazed, Interior Door Aluminum Fully Glazed Interior Door

Condition Good

Quantity 2 EA

Remaining Useful Life (RUL) 44 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 39 of 220

Page 40: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Fire DoorsItem Description

Fire Doors Fire Doors

Condition Good

Quantity 67 EA

Remaining Useful Life (RUL) 34 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 40 of 220

Page 41: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Steel, Interior DoorItem Description

Steel, Interior Door Steel Interior Door

Condition Good

Quantity 32 EA

Remaining Useful Life (RUL) 69 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 41 of 220

Page 42: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Wood Solid Core Safety GlassPainted InteriorItem Description

Wood Solid Core Safety Glass Painted Interior Wood Safety Glass Painted Interior

Condition Good

Quantity 137 EA

Remaining Useful Life (RUL) 34 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 42 of 220

Page 43: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Wood, Solid Core, Painted, InteriorDoorItem Description

Wood, Solid Core, Painted, Interior Door Wood Solid Core Interior Door

Condition Good

Quantity 92 EA

Remaining Useful Life (RUL) 34 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 43 of 220

Page 44: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Concrete, Exterior StairsItem Description

Concrete, Exterior Stairs Concrete Exterior Stairs

Condition Good

Quantity 1,884 SF

Remaining Useful Life (RUL) 44 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 44 of 220

Page 45: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Concrete, Interior StairsItem Description

Concrete, Interior Stairs Concrete Interior Stairs

Condition Fair - Good

Quantity 598 SF

Remaining Useful Life (RUL) 15 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 45 of 220

Page 46: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Interior Stairs, Concrete FilledMetal Pan Type (Riser)Item Description

Interior Stairs, Concrete Filled Metal Pan Type (Riser) Concrete Filled Metal Pan Type Interior Stair

Condition Good

Quantity 460 Riser

Remaining Useful Life (RUL) 69 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 46 of 220

Page 47: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Interior Stairs, Metal, Utility /Access (Riser)Item Description

Interior Stairs, Metal, Utility / Access (Riser) Concrete Interior Stair Utility / Access

Condition Fair - Good

Quantity 32 Riser

Remaining Useful Life (RUL) 15 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 47 of 220

Page 48: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Metal, Painted, Interior StairsItem Description

Metal, Painted, Interior Stairs Metal Interior Stairs

Condition Fair - Good

Quantity 96 SF

Remaining Useful Life (RUL) 15 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 48 of 220

Page 49: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Ceramic Tile, Interior Wall Finish,16 Sq InItem Description

Ceramic Tile, Interior Wall Finish, 16 Sq In Ceramic Tile Interior Wall Finish

Condition Good

Quantity 18,235 SF

Remaining Useful Life (RUL) 69 Year(s)

Uniformat Component Description Plan Type Year Expenditures

C3012 Repair Ceramic Tile, Interior Wall Finish CRP 2018 $8,205

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 49 of 220

Page 50: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Clay Brick, Interior Wall FinishItem Description

Clay Brick, Interior Wall Finish Clay Brick Interior Wall Finish

Condition Fair - Good

Quantity 6,904 SF

Remaining Useful Life (RUL) 15 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 50 of 220

Page 51: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Concrete Block, Interior WallFinishItem Description

Concrete Block, Interior Wall Finish Concrete Block Interior Wall Finish

Condition Fair - Good

Quantity 10,357 SF

Remaining Useful Life (RUL) 15 Year(s)

Uniformat Component Description Plan Type Year Expenditures

C3012 Repoint Concrete Block, Exterior CRP 2018 $5,967

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 51 of 220

Page 52: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Gypsum Board, Interior WallFinishItem Description

Gypsum Board, Interior Wall Finish Gypsum Board Interior Wall Finish

Condition Good

Quantity 51,786 SF

Remaining Useful Life (RUL) 34 Year(s)

Uniformat Component Description Plan Type Year Expenditures

C3012 Repair Gypsum Board/Plaster, Interior Wall CRP 2018 $1,908

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 52 of 220

Page 53: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Ceramic Tile FlooringItem Description

Ceramic Tile Flooring Ceramic Tile Flooring

Condition Good

Quantity 5,822 SF

Remaining Useful Life (RUL) 34 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 53 of 220

Page 54: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Concrete FlooringItem Description

Concrete Flooring Concrete Flooring

Condition Fair - Good

Quantity 16,500 SF

Remaining Useful Life (RUL) 12 Year(s)

Uniformat Component Description Plan Type Year Expenditures

C3024 Repair Concrete Slab CRP 2018 $4,092

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 54 of 220

Page 55: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Floor Finish, Terrazzo, AuthenticItem Description

Floor Finish, Terrazzo, Authentic Terrazzo Floor Finish

Condition Fair - Good

Quantity 18,500 SF

Remaining Useful Life (RUL) 8 Year(s)

Uniformat Component Description Plan Type Year Expenditures

C3024 Repair Terrazzo Flooring CRP 2019 $17,438

C3024 Replace Terrazzo Floor Finish CRP 2026 $476,930

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 55 of 220

Page 56: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Floor Finish, Tile, RubberItem Description

Floor Finish, Tile, Rubber Rubber Floor Finish

Condition Fair

Quantity 3,942 SF

Remaining Useful Life (RUL) 4 Year(s)

Uniformat Component Description Plan Type Year Expenditures

C3024 Replace Rubber Floor Finish CRP 2022 $29,171

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 56 of 220

Page 57: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Floor Finish, Wood StripItem Description

Floor Finish, Wood Strip Wood Strip Floor Finishes

Condition Good

Quantity 27,840 SF

Remaining Useful Life (RUL) 34 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 57 of 220

Page 58: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Floor Finish, Wood, AthleticItem Description

Floor Finish, Wood, Athletic Athletic Wood Floor Finish

Condition Good

Quantity 12,690 SF

Remaining Useful Life (RUL) 34 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 58 of 220

Page 59: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Quarry Tile FlooringItem Description

Quarry Tile Flooring Quarry Tile Flooring

Condition Good

Quantity 2,196 SF

Remaining Useful Life (RUL) 34 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 59 of 220

Page 60: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Vinyl Tile FlooringItem Description

Vinyl Tile Flooring Vinyl Tile Flooring

Condition Fair - Good

Quantity 100,465 SF

Remaining Useful Life (RUL) 12 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 60 of 220

Page 61: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Carpet, Nylon, High Traffic, 20 ozItem Description

Carpet, Nylon, High Traffic, 20 oz Carpet Floor Finishes

Condition Fair

Quantity 13,360 SF

Remaining Useful Life (RUL) 4 Year(s)

Uniformat Component Description Plan Type Year Expenditures

C3025 Replace Carpet Floor Finishes CRP 2022 $79,866

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 61 of 220

Page 62: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Gypsum Board, Finished CeilingItem Description

Gypsum Board, Finished Ceiling Gypsum Board Ceiling Finishes

Condition Good

Quantity 16,500 SF

Remaining Useful Life (RUL) 69 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 62 of 220

Page 63: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Acoustical Tile CeilingItem Description

Acoustical Tile Ceiling Acoustical Tile Ceiling

Condition Good

Quantity 169,640 SF

Remaining Useful Life (RUL) 19 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 63 of 220

Page 64: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Elevator, Hydraulic, 1500 to 2500LB, 3 StoreysItem Description

Elevator, Hydraulic, 1500 to 2500 LB, 3 Storeys Elevators (x2)

Condition Good

Quantity 2 EA

Remaining Useful Life (RUL) 24 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 64 of 220

Page 65: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Lift, Wheel ChairItem Description

Lift, Wheel Chair Wheel Chair Lift

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 19 Year(s)

Wheel Chair Lift

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 65 of 220

Page 66: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Plumbing Fixt (SF), Avg D, Avg QItem Description

Plumbing Fixt (SF), Avg D, Avg Q Typical plumbing fixtures

Condition Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 24 Year(s)

Location Bathroom

Laboratory Sink Mopping Sink

Toilet Seat Urinals

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 66 of 220

Page 67: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Plumbing Fixt, Sink, Kitchen,Commercial Grade (per Basin)Item Description

Plumbing Fixt, Sink, Kitchen, Commercial Grade (perBasin) Commercial Grade Kitchen Sink

Condition Good

Quantity 2 EA

Remaining Useful Life (RUL) 34 Year(s)

Location Kitchen

Kitchen Sink Kitchen Sink

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 67 of 220

Page 68: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Sink, Enameled SteelItem Description

Sink, Enameled Steel Classroom Sinks

Condition Good

Quantity 2 EA

Remaining Useful Life (RUL) 29 Year(s)

Classroom Sink

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 68 of 220

Page 69: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Emergency Eye wash and Shower- PlumbedItem Description

Emergency Eye wash and Shower - Plumbed Emergency Eye wash and Shower

Condition Good

Quantity 10 EA

Remaining Useful Life (RUL) 19 Year(s)

Eye Wash and

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 69 of 220

Page 70: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Shower, Ceramic TileItem Description

Shower, Ceramic Tile Showers

Condition Good

Quantity 32 EA

Remaining Useful Life (RUL) 24 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 70 of 220

Page 71: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Plumbing Fixt (SF), DrinkingFountain, Wall Mount, Dual-HeightItem Description

Plumbing Fixt (SF), Drinking Fountain, Wall Mount, Dual-Height Drinking Fountains

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 9 Year(s)

Drinking Fountain

Uniformat Component Description Plan Type Year Expenditures

D2018 Replace Drinking Fountains CRP 2027 $48,985

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 71 of 220

Page 72: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Plumbing Fixt, Drinking Fountain,Floor MountItem Description

Plumbing Fixt, Drinking Fountain, Floor Mount Drinking Fountains - Annex

Condition Fair - Good

Quantity 4 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Exterior

Drinking Fountain

Uniformat Component Description Plan Type Year Expenditures

D2018 Replace Drinking Fountains - Annex CRP 2027 $5,200

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 72 of 220

Page 73: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Piping (SF), Domestic WaterService & Dist, Avg Density (largeBldg)

Item Description

Piping (SF), Domestic Water Service & Dist, Avg Density(large Bldg) Domestic Water Distribution Piping

Condition Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 34 Year(s)

Domestic Water Piping

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 73 of 220

Page 74: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

DHW Insulated storage tankItem Description

DHW Insulated storage tank Domestic Hot Water Storage Tank, 993 Gal (x2)

Condition Good

Quantity 1,986 GAL

Remaining Useful Life (RUL) 34 Year(s)

Location Boiler Room

Domestic Hot Water Storage Tanks

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 74 of 220

Page 75: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Tankless Water Heater - GasItem Description

Tankless Water Heater - Gas Water Heaters, Gas-fired, 1500 Mbh (x2)

Condition Good

Quantity 3,000,000 BTU

Remaining Useful Life (RUL) 34 Year(s)

Location Boiler Room

Water Heaters

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 75 of 220

Page 76: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Booster Pump, 10.000 HPItem Description

Booster Pump, 10.000 HP Booster Pumps (x5)

Condition Fair - Good

Quantity 5 EA

Remaining Useful Life (RUL) 14 Year(s)

Location M 001 Cistern/Pump Room

Booster Pump Booster Pump

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 76 of 220

Page 77: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Water Flow Meter, 4.00 InItem Description

Water Flow Meter, 4.00 In Water Flow Meter

Condition Good

Quantity 3 EA

Remaining Useful Life (RUL) 19 Year(s)

Location Exterior

Water Meter Water Meter

Water Meter

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 77 of 220

Page 78: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Water Treatment, Filtration SystemItem Description

Water Treatment, Filtration System Water Treatment, Filtration System

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Boiler Room

Water Filtration System

Uniformat Component Description Plan Type Year Expenditures

D2023 Replace Water Treatment, Filtration System CRP 2027 $8,976

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 78 of 220

Page 79: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Medium Density Sanitary WasteSystem (Black/PVC)Item Description

Medium Density Sanitary Waste System (Black/PVC) Waste Piping

Condition Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 19 Year(s)

Sanitary Waste Piping Vent

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 79 of 220

Page 80: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Light Density Rainwater DrainageSyst (Black/PVC)Item Description

Light Density Rainwater Drainage Syst (Black/PVC) Rainwater Drainage Piping

Condition Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 19 Year(s)

Rain Drainage Piping

Uniformat Component Description Plan Type Year Expenditures

D2041 Fix the storm drainage piping that leaks in the mainoffice, when using Emergency Eye wash and Shower. RM 2018 $5,000

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 80 of 220

Page 81: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Pump, Sump, 0.5 HPItem Description

Pump, Sump, 0.5 HP Sump Pumps

Condition Fair - Good

Quantity 4 EA

Remaining Useful Life (RUL) 14 Year(s)

Location Boiler Room

Sump Pumps

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 81 of 220

Page 82: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Solar Panel, 24 Sq FtItem Description

Solar Panel, 24 Sq Ft Solar Panel, 24 Sq Ft

Condition Fair - Good

Quantity 476 EA

Remaining Useful Life (RUL) 14 Year(s)

Location Roof

Inverter Box Solar Panel

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 82 of 220

Page 83: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Boiler, Gas, Hot Water/Steam,1,250~1,500 MBHItem Description

Boiler, Gas, Hot Water/Steam, 1,250~1,500 MBH Boiler 3, Gas-fired, 1500 Mbh (x1)

Condition Poor

Quantity 1 EA

Remaining Useful Life (RUL) 0 Year(s)

Location Boiler Room

Boiler 3...not Working

Uniformat Component Description Plan Type Year Expenditures

D3021 Replace Boiler 3, Gas-fired, 1500 Mbh (x1) CRP 2018 $55,545

D3021 Repair the leak of flue piping for Boiler 1. RM 2018 $2,000

D3021 Replace Boiler 3, which is down. CRP 2018 $55,545

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 83 of 220

Page 84: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Boiler, Gas, Hot Water/Steam,1,250~1,500 MBHItem Description

Boiler, Gas, Hot Water/Steam, 1,250~1,500 MBH Boiler 1&2, Gas-fired, 1500 Mbh (x2)

Condition Good

Quantity 2 EA

Remaining Useful Life (RUL) 19 Year(s)

Location Boiler Room

Boilers Flue Piping Leaking...Boiler 1

Uniformat Component Description Plan Type Year Expenditures

D3021 Replace Boiler 3, which is down. RM 2018 $55,545

D3021 Repair the leak of flue piping for Boiler 1. RM 2018 $2,000

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 84 of 220

Page 85: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Expansion Tank, 400 GalItem Description

Expansion Tank, 400 Gal Expansion Tank, 453 Gal

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 24 Year(s)

Location Boiler Room

Expansion Tank

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 85 of 220

Page 86: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Expansion Tank, 400 GalItem Description

Expansion Tank, 400 Gal Expansion Tank, 400 Gal

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 24 Year(s)

Location Boiler Room

Expansion Tank

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 86 of 220

Page 87: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Heating Hot Water/Steam PipingSyst Light DensityItem Description

Heating Hot Water/Steam Piping Syst Light Density Heating Hot Water Piping

Condition Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 19 Year(s)

Heating Water Piping

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 87 of 220

Page 88: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Chiller, Centrifugal, 201~250 TonItem Description

Chiller, Centrifugal, 201~250 Ton Chiller, 250 Ton (x2)

Condition Good

Quantity 2 EA

Remaining Useful Life (RUL) 19 Year(s)

Location Boiler Room

Chillers

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 88 of 220

Page 89: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Cooling Tower, 250 TonItem Description

Cooling Tower, 250 Ton Cooling Tower, 250 Ton (x2)

Condition Fair - Good

Quantity 2 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Roof

Cooling Towers

Uniformat Component Description Plan Type Year Expenditures

D3031 Replace Cooling Tower, 250 Ton (x2) CRP 2027 $79,524

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 89 of 220

Page 90: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Condenser, Air-Cooled, 2 TonItem Description

Condenser, Air-Cooled, 2 Ton Air-Cooled Condenser, 2 Ton

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Roof

Air-Cooled Condenser

Uniformat Component Description Plan Type Year Expenditures

D3032 Replace Air-Cooled Condenser, 2 Ton CRP 2027 $2,252

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 90 of 220

Page 91: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Condenser, Air-Cooled, 2 TonItem Description

Condenser, Air-Cooled, 2 Ton Air-Cooled Condenser, 2 Ton

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Exterior

Air Cooled Condenser

Uniformat Component Description Plan Type Year Expenditures

D3032 Replace Air-Cooled Condenser, 2 Ton CRP 2027 $2,252

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 91 of 220

Page 92: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Condensing Unit / Compressor(Refrigeration) 5.0 HP (~1.0 Ton),Air Cooled

Item Description

Condensing Unit / Compressor (Refrigeration) 5.0 HP (~1.0Ton), Air Cooled Condensing Unit, ~5 HP

Condition Poor - Fair

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Exterior

Condensing Unit

Uniformat Component Description Plan Type Year Expenditures

D3032 Replace Condensing Unit, ~5 HP CRP 2027 $5,967

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 92 of 220

Page 93: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

DuctworkItem Description

Ductwork Ductwork

Condition Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 24 Year(s)

Ductwork

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 93 of 220

Page 94: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Energy Recovery Ventilator Unit(ERV), 20,000 to 30,000 CFMItem Description

Energy Recovery Ventilator Unit (ERV), 20,000 to 30,000CFM Energy Recovery Unit, 27,500 CFM

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Roof

Condensate piping leaking

Rooftop Unit

Uniformat Component Description Plan Type Year Expenditures

D3041 Replace Energy Recovery Unit, 27,500 CFM CRP 2027 $30,000

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 94 of 220

Page 95: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Fan Coil Unit, DX, 0.5 TonItem Description

Fan Coil Unit, DX, 0.5 Ton Split A/C System Indoor Unit

Condition Fair - Good

Quantity 2 EA

Remaining Useful Life (RUL) 9 Year(s)

Split A/C System Indoor Unit

Uniformat Component Description Plan Type Year Expenditures

D3041 Replace Split A/C System Indoor Unit CRP 2027 $2,997

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 95 of 220

Page 96: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Exhaust / Ventilation, General (SF)Mid-Sized Building / Avg DensityItem Description

Exhaust / Ventilation, General (SF) Mid-Sized Building / AvgDensity Exhaust Fans

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Location Roof

Exhaust Fan

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 96 of 220

Page 97: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Kitchen Exhaust Hood,CommercialItem Description

Kitchen Exhaust Hood, Commercial Kitchen Exhaust Hood

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Kitchen

Kitchen Hood

Uniformat Component Description Plan Type Year Expenditures

D3042 Replace Kitchen Exhaust Hood CRP 2027 $7,630

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 97 of 220

Page 98: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Heating, Hydronic (EA),Convection, Cabinet TypeItem Description

Heating, Hydronic (EA), Convection, Cabinet Type Hydronic Radiators

Condition Good

Quantity 12 EA

Remaining Useful Life (RUL) 24 Year(s)

Hydronic Heater

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 98 of 220

Page 99: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Piping (SF), Chilled Water Supply& Return, Average DensityItem Description

Piping (SF), Chilled Water Supply & Return, AverageDensity Chilled Water Piping

Condition Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 29 Year(s)

Chilled Water Piping Cracked Chilled Water Piping at a Valve Controller- Leakng

Uniformat Component Description Plan Type Year Expenditures

D3045 Replace the chilled water piping cracked at a valvecontroller. CRP 2018 $3,000

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 99 of 220

Page 100: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Air Conditioner, Window, 1 TonItem Description

Air Conditioner, Window, 1 Ton Window A/C Units - Annex

Condition Fair - Good

Quantity 3 EA

Remaining Useful Life (RUL) 14 Year(s)

Window A/C Unit

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 100 of 220

Page 101: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Unit Heater, Electric, 10 kWItem Description

Unit Heater, Electric, 10 kW Electric Unit Heater

Condition Fair - Good

Quantity 20 EA

Remaining Useful Life (RUL) 14 Year(s)

Fan Coil Unit

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 101 of 220

Page 102: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Air Conditioner, Rooftop,Multizone, 100 TonItem Description

Air Conditioner, Rooftop, Multizone, 100 Ton Rooftop Units, 95 Ton

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Roof

Rooftop Unit

Uniformat Component Description Plan Type Year Expenditures

D3052 Replace Rooftop Units, 95 Ton CRP 2027 $149,058

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 102 of 220

Page 103: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Air Conditioner, Rooftop,Multizone, 100 TonItem Description

Air Conditioner, Rooftop, Multizone, 100 Ton Rooftop Units, 95 Ton

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Roof

Rooftop Unit

Uniformat Component Description Plan Type Year Expenditures

D3052 Replace Rooftop Units, 95 Ton CRP 2027 $149,058

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 103 of 220

Page 104: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Air Conditioner, Rooftop,Multizone, 140 TonItem Description

Air Conditioner, Rooftop, Multizone, 140 Ton Rooftop Units, 134 Ton

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Rooftop Unit

Uniformat Component Description Plan Type Year Expenditures

D3052 Replace Rooftop Units, 134 Ton CRP 2027 $203,840

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 104 of 220

Page 105: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Air Conditioner, Rooftop,Multizone, 40 TonItem Description

Air Conditioner, Rooftop, Multizone, 40 Ton Rooftop Units, 40 Ton

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Roof

Rooftop Unit

Uniformat Component Description Plan Type Year Expenditures

D3052 Replace Rooftop Units, 40 Ton CRP 2027 $60,856

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 105 of 220

Page 106: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Air Conditioner, Rooftop, SingleZone, 60 TonItem Description

Air Conditioner, Rooftop, Single Zone, 60 Ton Rooftop Units, 60 Ton

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Roof

Rooftop Unit

Uniformat Component Description Plan Type Year Expenditures

D3052 Replace Rooftop Units, 60 Ton CRP 2027 $85,593

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 106 of 220

Page 107: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Meter, Natural Gas, w/ DigitalPulser, 800 CHFItem Description

Meter, Natural Gas, w/ Digital Pulser, 800 CHF Gas Meter

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 19 Year(s)

Location Exterior

Gas Meter

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 107 of 220

Page 108: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Building Controls (SF), DDC,AverageItem Description

Building Controls (SF), DDC, Average HVAC Control System

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 9 Year(s)

Location M007 Engineering Office

Broken VFD Controller of Hot Water Pump 5 Detached Thermostat in Room 321

Humidity Sensor HVAC Controller

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 108 of 220

Page 109: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Thermostats

Uniformat Component Description Plan Type Year Expenditures

D3068 Replace VFD Controller for Pump 5. CRP 2018 $3,000

D3068 Reattach the thermostat detached from the wall of roomM211. RM 2018 $100

D3068 Replace HVAC Control System CRP 2027 $551,084

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 109 of 220

Page 110: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Sprinkler System (SF), Wet,Ordinary Hazard, CompleteItem Description

Sprinkler System (SF), Wet, Ordinary Hazard, Complete Sprinkler System (SF)

Condition Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 29 Year(s)

Fire Standpiping Sprinkler System

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 110 of 220

Page 111: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Fire Extinguishers (SF)Item Description

Fire Extinguishers (SF) Fire Extinguisher

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Fire Extinguisher Fire Extinguisher Certification Tag

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 111 of 220

Page 112: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Kitchen Fire Suppression System(CO2)Item Description

Kitchen Fire Suppression System (CO2) Kitchen Fire Suppression System

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 14 Year(s)

Location Kitchen

Ansul System Kitchen Hood Sprinkler Nozzles

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 112 of 220

Page 113: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Disconnect Switch, 400 AmpItem Description

Disconnect Switch, 400 Amp Disconnect Switch, 400 Amp

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 24 Year(s)

Location M013 Mechanical Room

Disconnect

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 113 of 220

Page 114: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Disconnect Switch, 600 AmpItem Description

Disconnect Switch, 600 Amp Disconnect Switch, 800 Amp

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 24 Year(s)

Location M003 Electrical

Disconnect

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 114 of 220

Page 115: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Disconnect Switch, 600 AmpItem Description

Disconnect Switch, 600 Amp Disconnect Switch, 600 Amp

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 24 Year(s)

Location M003A Electrical

Disconnect

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 115 of 220

Page 116: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Main Switchgear, 480 Y, 277 V,2,000 AmpItem Description

Main Switchgear, 480 Y, 277 V, 2,000 Amp Main Switchgear, 480 Y, 277 V, 2,000 Amp

Condition Good

Quantity 2 EA

Remaining Useful Life (RUL) 34 Year(s)

Location M003 Electrical

Main Switchgear Switchboard

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 116 of 220

Page 117: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Power Panel Board, 208 Y, 120 V,100 AmpItem Description

Power Panel Board, 208 Y, 120 V, 100 Amp Power Panel Board, 208 Y, 120 V, 125 Amp

Condition Good

Quantity 3 EA

Remaining Useful Life (RUL) 24 Year(s)

Panel Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 117 of 220

Page 118: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Power Panel Board, 208 Y, 120 V,225 AmpItem Description

Power Panel Board, 208 Y, 120 V, 225 Amp Power Panel Board, 208 Y, 120 V, 250 Amp

Condition Good

Quantity 14 EA

Remaining Useful Life (RUL) 24 Year(s)

Panel Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 118 of 220

Page 119: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Power Panel Board, 208 Y, 120 V,400 AmpItem Description

Power Panel Board, 208 Y, 120 V, 400 Amp Power Panel Board, 208 Y, 120 V, 400 Amp

Condition Good

Quantity 12 EA

Remaining Useful Life (RUL) 24 Year(s)

Panel Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 119 of 220

Page 120: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Power Panel Board, 480 Y, 277 V,1,000 AmpItem Description

Power Panel Board, 480 Y, 277 V, 1,000 Amp Power Panel Board, 480 Y, 277 V, 800 Amp

Condition Good

Quantity 3 EA

Remaining Useful Life (RUL) 24 Year(s)

Panel Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 120 of 220

Page 121: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Power Panel Board, 480 Y, 277 V,100 AmpItem Description

Power Panel Board, 480 Y, 277 V, 100 Amp Power Panel Board, 480 Y, 277 V, 125 Amp

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 24 Year(s)

Panel Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 121 of 220

Page 122: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Power Panel Board, 480 Y, 277 V,200 AmpItem Description

Power Panel Board, 480 Y, 277 V, 200 Amp Power Panel Board, 480 Y, 277 V, 250 Amp

Condition Good

Quantity 8 EA

Remaining Useful Life (RUL) 24 Year(s)

Panel Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 122 of 220

Page 123: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Power Panel Board, 480 Y, 277 V,400 AmpItem Description

Power Panel Board, 480 Y, 277 V, 400 Amp Power Panel Board, 480 Y, 277 V, 600 Amp

Condition Good

Quantity 5 EA

Remaining Useful Life (RUL) 24 Year(s)

Panel Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 123 of 220

Page 124: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Power Panel Board, 480 Y, 277 V,400 AmpItem Description

Power Panel Board, 480 Y, 277 V, 400 Amp Power Panel Board, 480 Y, 277 V, 400 Amp

Condition Good

Quantity 5 EA

Remaining Useful Life (RUL) 24 Year(s)

Panel Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 124 of 220

Page 125: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Secondary Transformer, Dry, 113kVAItem Description

Secondary Transformer, Dry, 113 kVA Secondary Transformer, Dry, 112.5 kVA

Condition Good

Quantity 2 EA

Remaining Useful Life (RUL) 24 Year(s)

Transformer

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 125 of 220

Page 126: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Secondary Transformer, Dry, 15kVAItem Description

Secondary Transformer, Dry, 15 kVA Secondary Transformer, Dry, 15 kVA

Condition Good

Quantity 4 EA

Remaining Useful Life (RUL) 24 Year(s)

Transformer

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 126 of 220

Page 127: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Secondary Transformer, Dry, 150kVAItem Description

Secondary Transformer, Dry, 150 kVA Secondary Transformer, Dry, 150 kVA

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 24 Year(s)

Transformer

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 127 of 220

Page 128: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Secondary Transformer, Dry, 225kVAItem Description

Secondary Transformer, Dry, 225 kVA Secondary Transformer, Dry, 225 kVA

Condition Good

Quantity 3 EA

Remaining Useful Life (RUL) 24 Year(s)

Transformer

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 128 of 220

Page 129: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Secondary Transformer, Dry, 30kVAItem Description

Secondary Transformer, Dry, 30 kVA Secondary Transformer, Dry, 30 kVA

Condition Good

Quantity 4 EA

Remaining Useful Life (RUL) 24 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 129 of 220

Page 130: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Transfer Switch, Auto, 600 V, 200AmpItem Description

Transfer Switch, Auto, 600 V, 200 Amp Transfer Switch, Auto, 600 V, 200 Amp

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 12 Year(s)

Location M003A Electrical

Automatic Transfer Switch

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 130 of 220

Page 131: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Transfer Switch, Auto, 600 V, 400AmpItem Description

Transfer Switch, Auto, 600 V, 400 Amp Transfer Switch, Auto, 600 V, 400 Amp

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 19 Year(s)

Location M003A Electrical

Automatic Transfer Switch

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 131 of 220

Page 132: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Electrical (SF) Branch Wiring,Peripheral Devices, AvgCost/Density

Item Description

Electrical (SF) Branch Wiring, Peripheral Devices, AvgCost/Density

Electrical (SF) Branch Wiring, Peripheral Devices, AvgCost/Density

Condition Good

Quantity 202,239 SF

Remaining Useful Life (RUL) 24 Year(s)

Receptacles Switch

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 132 of 220

Page 133: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Electrical (SF) Branch Wiring,Peripheral Devices, HighCost/Density

Item Description

Electrical (SF) Branch Wiring, Peripheral Devices, HighCost/Density

Electrical (SF) Branch Wiring, Peripheral Devices, HighCost/Density

Condition Good

Quantity 1,866 SF

Remaining Useful Life (RUL) 24 Year(s)

Location Science Lab

Receptacles

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 133 of 220

Page 134: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Occupancy Sensors, IndoorLightingItem Description

Occupancy Sensors, Indoor Lighting Occupancy Sensors, Indoor Lighting (SF)

Condition Fair - Good

Quantity 204,105 EA

Remaining Useful Life (RUL) 13 Year(s)

Occupancy Sensor Occupancy Sensor Receptacle

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 134 of 220

Page 135: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Lighting, Exterior Fixture,Economy, Wall or Soffit MountedItem Description

Lighting, Exterior Fixture, Economy, Wall or Soffit Mounted Lighting, Exterior Fixture, Economy, Wall or Soffit Mounted

Condition Fair - Good

Quantity 2 EA

Remaining Useful Life (RUL) 14 Year(s)

Exterior Lights

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 135 of 220

Page 136: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Lighting, Exterior Fixture,Economy, Wall or Soffit MountedItem Description

Lighting, Exterior Fixture, Economy, Wall or Soffit Mounted Lighting, Exterior Fixture, Economy, Wall or Soffit Mounted

Condition Fair - Good

Quantity 34 EA

Remaining Useful Life (RUL) 14 Year(s)

Flood Lights

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 136 of 220

Page 137: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Lighting, Interior (SF),Fluorescent, Avg DensityItem Description

Lighting, Interior (SF), Fluorescent, Avg Density Lighting, Interior (SF), Fluorescent, Avg Density

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Fluorescent Light

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 137 of 220

Page 138: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Communications (SF), P.A.System, Low / Avg DensityItem Description

Communications (SF), P.A. System, Low / Avg Density Communications (SF), P.A. System, Low / Avg Density

Condition Fair - Good

Quantity 240,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Location S004 Telecom Closet

PA Switch PA System

Speaker

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 138 of 220

Page 139: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Sound System, 7 ChannelItem Description

Sound System, 7 Channel Sound System, 7 Channel

Condition Fair - Good

Quantity 6 EA

Remaining Useful Life (RUL) 9 Year(s)

Sound System

Uniformat Component Description Plan Type Year Expenditures

D5031 Replace Sound System, 7 Channel CRP 2027 $12,406

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 139 of 220

Page 140: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Telephone System (SF), AvgDensityItem Description

Telephone System (SF), Avg Density Telephone System (SF), Avg Density

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Location S004 Telecom Closet

Telephone Telephone

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 140 of 220

Page 141: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Master Clock System (SF)Item Description

Master Clock System (SF) Master Clock System (SF)

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Location S004 Telecom Closet

Clock Master Clock

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 141 of 220

Page 142: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Security (SF), Fire Alarm System,Complete, Avg DensityItem Description

Security (SF), Fire Alarm System, Complete, Avg Density Security (SF), Fire Alarm System, Complete, Avg Density

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Location M003A Electrical

Description:The fire alarm was in trouble mode, need routine maintenance.

Alarm in Trouble Mode Fire Alarm Panel

Pull Station Speaker Strobe

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 142 of 220

Page 143: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Strobe

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 143 of 220

Page 144: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Card ReaderItem Description

Card Reader Card Reader

Condition Fair - Good

Quantity 18 EA

Remaining Useful Life (RUL) 9 Year(s)

Card Reader

Uniformat Component Description Plan Type Year Expenditures

D5038 Replace Card Reader CRP 2027 $16,660

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 144 of 220

Page 145: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Magnetic LockItem Description

Magnetic Lock Electronic Article Surveillance System (EA)

Condition Fair - Good

Quantity 2 EA

Remaining Useful Life (RUL) 9 Year(s)

Location Library

EAS Anti Theft System

Uniformat Component Description Plan Type Year Expenditures

D5038 Replace Electronic Article Surveillance System (EA) CRP 2027 $1,490

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 145 of 220

Page 146: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Screening MagnetometerItem Description

Screening Magnetometer Screening Magnetometer

Condition Fair - Good

Quantity 4 EA

Remaining Useful Life (RUL) 9 Year(s)

Metal Detector

Uniformat Component Description Plan Type Year Expenditures

D5038 Replace Screening Magnetometer CRP 2027 $12,689

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 146 of 220

Page 147: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Screening X-Ray MachineItem Description

Screening X-Ray Machine Screening X-Ray Machine

Condition Fair - Good

Quantity 3 EA

Remaining Useful Life (RUL) 9 Year(s)

X Ray Machine

Uniformat Component Description Plan Type Year Expenditures

D5038 Replace Screening X-Ray Machine CRP 2027 $139,509

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 147 of 220

Page 148: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Security (LF), Surveillance,Exterior PerimeterItem Description

Security (LF), Surveillance, Exterior Perimeter Security (LF), Surveillance, Exterior Perimeter

Condition Fair - Good

Quantity 1,961 LF

Remaining Useful Life (RUL) 9 Year(s)

Location Exterior

Damaged Surveillance Camera Surveillance Camera

Uniformat Component Description Plan Type Year Expenditures

D5038 Replace Security (LF), Surveillance, Exterior Perimeter CRP 2027 $58,418

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 148 of 220

Page 149: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Security (SF), Surveillance, Alarm,Avg Density/CostItem Description

Security (SF), Surveillance, Alarm, Avg Density/Cost Security (SF), Surveillance, Alarm, Avg Density/Cost

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Access Control Panel Motion Detector

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 149 of 220

Page 150: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Communications (SF), LANSystem, Avg DensityItem Description

Communications (SF), LAN System, Avg Density Communications (SF), LAN System, Avg Density

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Location M318 Telecom Room

LAN Rack

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 150 of 220

Page 151: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Lightning Protection System (EA)Item Description

Lightning Protection System (EA) Lightning Protection System (EA)

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 19 Year(s)

Location Chimney

Lightning Protection

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 151 of 220

Page 152: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Emergency Lighting (SF)Emergency Light Fixtures, BatteryBackup

Item Description

Emergency Lighting (SF) Emergency Light Fixtures,Battery Backup

Emergency Lighting (SF) Emergency Light Fixtures, BatteryBackup

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Emergency Light

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 152 of 220

Page 153: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Emergency Lighting (SF) EXITSigns, Illuminated, Battery BackupItem Description

Emergency Lighting (SF) EXIT Signs, Illuminated, BatteryBackup

Emergency Lighting (SF) EXIT Signs, Illuminated, BatteryBackup

Condition Fair - Good

Quantity 204,105 SF

Remaining Useful Life (RUL) 14 Year(s)

Exit Sign

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 153 of 220

Page 154: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Generator, NG / LP / Gasoline,190 kW~250 kWItem Description

Generator, NG / LP / Gasoline, 190 kW~250 kW Generator, NG / LP / Gasoline, 300 kW

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 19 Year(s)

Location Exterior

Generator

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 154 of 220

Page 155: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Generator, NG / LP / Gasoline, 65kW~125 kWItem Description

Generator, NG / LP / Gasoline, 65 kW~125 kW Generator, NG / LP / Gasoline, 100 kW

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 19 Year(s)

Location Exterior

Generator

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 155 of 220

Page 156: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Laboratory Exhaust Hood, 4 Ln FtItem Description

Laboratory Exhaust Hood, 4 Ln Ft Laboratory Exhaust Hood

Condition Fair - Good

Quantity 3 EA

Remaining Useful Life (RUL) 9 Year(s)

Laboratory Exhaust Hood

Uniformat Component Description Plan Type Year Expenditures

E1027 Replace Laboratory Exhaust Hood CRP 2027 $7,373

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 156 of 220

Page 157: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Sink, Epoxy Resin, LaboratoryItem Description

Sink, Epoxy Resin, Laboratory Laboratory Sinks

Condition Fair - Good

Quantity 84 EA

Remaining Useful Life (RUL) 9 Year(s)

Laboratory Sinks Laboratory Sinks

Uniformat Component Description Plan Type Year Expenditures

E1027 Replace Laboratory Sinks CRP 2027 $44,371

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 157 of 220

Page 158: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Food Service Equipment,Commercial / Institutional, HighEnd

Item Description

Food Service Equipment, Commercial / Institutional, HighEnd Kitchen Food Service Equipment

Condition Fair - Good

Quantity 2,196 SF

Remaining Useful Life (RUL) 14 Year(s)

Location Kitchen

Kitchen Equipment Kitchen Equipment

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 158 of 220

Page 159: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Fixed Furnishings, Lockers, Metal,PaintedItem Description

Fixed Furnishings, Lockers, Metal, Painted Painted Metal Lockers

Condition Good

Quantity 903 LF

Remaining Useful Life (RUL) 19 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 159 of 220

Page 160: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Fixed Furnishings, Bleachers,TelescopingItem Description

Fixed Furnishings, Bleachers, Telescoping Bleachers

Condition Good

Quantity 520 Seat

Remaining Useful Life (RUL) 93 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 160 of 220

Page 161: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Fixed Furnishings, TheaterSeatingItem Description

Fixed Furnishings, Theater Seating Fixed Furnishings Theater Seating

Condition Good

Quantity 644 Seat

Remaining Useful Life (RUL) 16 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 161 of 220

Page 162: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Seating, Painted Steel,Upholstered - EconomyItem Description

Seating, Painted Steel, Upholstered - Economy Gymnasium Seatings

Condition Good

Quantity 348 EA

Remaining Useful Life (RUL) 16 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 162 of 220

Page 163: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Concrete PavementItem Description

Concrete Pavement Concrete Pavement

Condition Fair - Good

Quantity 13,995 SF

Remaining Useful Life (RUL) 10 Year(s)

Uniformat Component Description Plan Type Year Expenditures

G2022 Repair Concrete Pavement CRP 2018 $1,771

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 163 of 220

Page 164: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Parking Lot, Asphalt Paved, HighCostItem Description

Parking Lot, Asphalt Paved, High Cost Asphalt Paved Parking Lot

Condition Fair - Good

Quantity 20,610 SF

Remaining Useful Life (RUL) 8 Year(s)

Uniformat Component Description Plan Type Year Expenditures

G2022 Replace Asphalt Paved Parking Lot CRP 2026 $92,745

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 164 of 220

Page 165: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Parking Lot, Paving, Concrete,DrivewaysItem Description

Parking Lot, Paving, Concrete, Driveways Concrete Parking Lots

Condition Good

Quantity 19,920 SF

Remaining Useful Life (RUL) 34 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 165 of 220

Page 166: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Fence, 4' Chain LinkItem Description

Fence, 4' Chain Link 4' Chain Link Fence

Condition Fair - Good

Quantity 110 LF

Remaining Useful Life (RUL) 14 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 166 of 220

Page 167: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Fence, MetalItem Description

Fence, Metal Metal Fence

Condition Good

Quantity 1,260 LF

Remaining Useful Life (RUL) 24 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 167 of 220

Page 168: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Retaining Wall, Cast in PlaceConcreteItem Description

Retaining Wall, Cast in Place Concrete Retaining Wall Cast in Place Concrete

Condition Fair - Good

Quantity 86 LF

Remaining Useful Life (RUL) 8 Year(s)

Uniformat Component Description Plan Type Year Expenditures

G2042 Replace Retaining Wall Cast in Place Concrete CRP 2026 $12,241

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 168 of 220

Page 169: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Playing Fields, Football Field, HighSchool or CollegeItem Description

Playing Fields, Football Field, High School or College High School Football Field

Condition Good

Quantity 1 EA

Remaining Useful Life (RUL) 19 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 169 of 220

Page 170: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Playing Fields, Play Structure,SmallItem Description

Playing Fields, Play Structure, Small Playing Fields Small

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 14 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 170 of 220

Page 171: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Playing Fields, Post MountedScoreboard (outdoor)Item Description

Playing Fields, Post Mounted Scoreboard (outdoor) Electronic Marquee Board

Condition Fair - Good

Quantity 1 EA

Remaining Useful Life (RUL) 14 Year(s)

Location Front Lawn

Electronic Marquee Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 171 of 220

Page 172: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Playing Fields, Post MountedScoreboard (outdoor)Item Description

Playing Fields, Post Mounted Scoreboard (outdoor) Playing Fields, Post Mounted Scoreboard (outdoor)

Condition Fair - Good

Quantity 2 EA

Remaining Useful Life (RUL) 14 Year(s)

Location Football Field

Football Score Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 172 of 220

Page 173: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Landscaping, Grass Sodding,Fields, Schools or CollegeItem Description

Landscaping, Grass Sodding, Fields, Schools or College Grass Sodding For Schools

Condition Good

Quantity 30,600 SF

Remaining Useful Life (RUL) 19 Year(s)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 173 of 220

Page 174: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Fuel Distribution, Gas ServicePiping, 2" SteelItem Description

Fuel Distribution, Gas Service Piping, 2" Steel Gas Distribution Piping

Condition Good

Quantity 400 LF

Remaining Useful Life (RUL) 24 Year(s)

Location Exterior

Fuel Gas Piping

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 174 of 220

Page 175: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Site Lighting, Bollard, 175W MHItem Description

Site Lighting, Bollard, 175W MH Site Lighting, Bollard, 175W MH

Condition Poor

Quantity 5 EA

Remaining Useful Life (RUL) 2 Year(s)

Location M318 Telecom Room

Description:Most of the lights are damaged and need to be replaced.

Bollard Light

Uniformat Component Description Plan Type Year Expenditures

G4021 Replace Site Lighting, Bollard, 175W MH CRP 2020 $5,706

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 175 of 220

Page 176: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Site Lighting, Flood Light, 175WHID (1 Fixture)Item Description

Site Lighting, Flood Light, 175W HID (1 Fixture) Site Lighting, Flood Light, Stadium Lights

Condition Fair - Good

Quantity 60 EA

Remaining Useful Life (RUL) 14 Year(s)

Location Football Field

Stadium Lighting

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 176 of 220

Page 177: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Site Lighting, Flood Light, 175WHID (1 Fixture)Item Description

Site Lighting, Flood Light, 175W HID (1 Fixture) Site Lighting, Flood Light, Compact Fluorescent(1 Fixture)

Condition Fair - Good

Quantity 8 EA

Remaining Useful Life (RUL) 14 Year(s)

Location Parking Lot

Site Lights

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 177 of 220

Page 178: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Site Lighting, Flood Light, 175WHID (1 Fixture)Item Description

Site Lighting, Flood Light, 175W HID (1 Fixture) Site Lighting, Flood Light, 175W HID (1 Fixture)

Condition Fair - Good

Quantity 5 EA

Remaining Useful Life (RUL) 14 Year(s)

Location Parking Lot

Site Lights

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 178 of 220

Page 179: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Site Lighting, Poles, ConcreteBaseItem Description

Site Lighting, Poles, Concrete Base Site Lighting, Poles, Concrete Base

Condition Good

Quantity 24 EA

Remaining Useful Life (RUL) 34 Year(s)

Site Light Foundation

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 179 of 220

Page 180: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Site Lighting, Poles, ConcreteBaseItem Description

Site Lighting, Poles, Concrete Base Site Lighting, Poles, Concrete Base

Condition Good

Quantity 8 EA

Remaining Useful Life (RUL) 34 Year(s)

Site Light Foundation

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 180 of 220

Page 181: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Site Lighting, Poles, Steel (10')Item Description

Site Lighting, Poles, Steel (10') Site Lighting, Poles, Steel (10')

Condition Good

Quantity 8 EA

Remaining Useful Life (RUL) 34 Year(s)

Location Front Lawn

Site Light Pole

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 181 of 220

Page 182: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Site Lighting, Poles, Steel (20')Item Description

Site Lighting, Poles, Steel (20') Site Lighting, Poles, Steel (20')

Condition Good

Quantity 10 EA

Remaining Useful Life (RUL) 34 Year(s)

Location Parking Lot

Site Light Pole

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 182 of 220

Page 183: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Site Lighting, Poles, Steel (40')Item Description

Site Lighting, Poles, Steel (40') Site Lighting, Poles, Steel (40')

Condition Good

Quantity 6 EA

Remaining Useful Life (RUL) 34 Year(s)

Location Football Field

Football Site Light Pole

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 183 of 220

Page 184: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

Z1010.2 Consider: ADAInvestmentsItem Description

Z1010.2 Consider: ADA Investments Consider: ADA Investments

Condition Good

Quantity 1

Remaining Useful Life (RUL) 99 Year(s)

Install grab bars in accessible stalls at 36” above the floor. 1

Modify existing lavatory faucets to paddle type faucets 2

Uniformat Component Description Plan Type Year Expenditures

Z1010.2 Restroom - Install grab bar CRP 2018 $650

Z1010.2 Lavatory - Install cover panel CRP 2018 $348

Cost Recommendations:

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 184 of 220

Page 185: Facility Condition Assessment - | dgs

Appendices

APPENDIX A: Photographic Record

Page 185 of 220

Page 186: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

APPENDIX "A": Photographic Record

APPENDIX "A": PhotographicRecord

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 186 of 220

Page 187: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

B1014 Ramps:- View of Exterior Concrete Ramps

B2011 Exterior Wall Construction:- View of Clay BrickExterior Wall

B2021 Windows:- View of Aluminum Fixed Window

B1014 Ramps:- View of Interior Concrete Ramp

B2013 Exterior Louvers, Screens, and Fencing:- View ofAluminum Louver

B2031 Glazed Doors & Entrances:- View of Steel ExteriorDoor

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 187 of 220

Page 188: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

B2031 Glazed Doors & Entrances:- View of Steel w/ SafetyGlass Exterior Door

B3011 Roof Finishes:- View of Corrugated Roof Covering

B3011 Roof Finishes:- View of Inverted Membrane RoofCovering

B2039 Other Doors & Entrances:- View of Stell Doors &Entrances, Rolling Door

B3011 Roof Finishes:- View of Green Roof w GrowingMedium

B3011 Roof Finishes:- View of Inverted Membrane RoofCovering

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 188 of 220

Page 189: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

B3011 Roof Finishes:- View of Slate Roof Shingles RoofCovering

B3022 Roof Hatches:- View of Aluminum Roof Hatch

C1021 Interior Doors:- View of Aluminum Fully GlazedInterior Door

B3021 Glazed Roof Openings:- View of Metal FrameSkylights

C1017 Interior Windows & Storefronts:- View of InteriorWindows & Storefronts - Standard

C1021 Interior Doors:- View of Fire Doors

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 189 of 220

Page 190: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

C1021 Interior Doors:- View of Steel Interior Door

C1021 Interior Doors:- View of Wood Solid Core InteriorDoor

C2011 Regular Stairs:- View of Concrete Filled Metal PanType Interior Stair

C1021 Interior Doors:- View of Wood Safety Glass PaintedInterior

C2011 Regular Stairs:- View of Concrete Exterior Stairs

C2011 Regular Stairs:- View of Concrete Interior StairUtility / Access

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 190 of 220

Page 191: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

C2011 Regular Stairs:- View of Concrete Interior Stairs

C3012 Wall Finishes to Interior Walls:- View of Ceramic TileInterior Wall Finish

C3012 Wall Finishes to Interior Walls:- View of ConcreteBlock Interior Wall Finish

C2011 Regular Stairs:- View of Metal Interior Stairs

C3012 Wall Finishes to Interior Walls:- View of Clay BrickInterior Wall Finish

C3012 Wall Finishes to Interior Walls:- View of GypsumBoard Interior Wall Finish

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 191 of 220

Page 192: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

C3024 Flooring:- View of Athletic Wood Floor Finish

C3024 Flooring:- View of Concrete Flooring

C3024 Flooring:- View of Rubber Floor Finish

C3024 Flooring:- View of Ceramic Tile Flooring

C3024 Flooring:- View of Quarry Tile Flooring

C3024 Flooring:- View of Terrazzo Floor Finish

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 192 of 220

Page 193: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

C3024 Flooring:- View of Vinyl Tile Flooring

C3025 Carpeting:- View of Carpet Floor Finishes

C3032 Suspended Ceilings:- View of Acoustical Tile Ceiling

C3024 Flooring:- View of Wood Strip Floor Finishes

C3031 Ceiling Finishes:- View of Gypsum Board CeilingFinishes

D1011 Passenger Elevators:- View of Elevators (x2)

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 193 of 220

Page 194: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D1011 Passenger Elevators:- View of Elevators (x2)

D1013 Lifts:- Wheel Chair Lift

D2010.0 Water_Fixtures:- Toilet Seat

D1011 Passenger Elevators:- View of Elevators (x2)

D2010.0 Water_Fixtures:- Laboratory Sink

D2010.0 Water_Fixtures:- Urinals

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 194 of 220

Page 195: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D2010.0 Water_Fixtures:- Mopping Sink

D2014 Sinks:- Kitchen Sink

D2016 Wash Fountains:- Eye Wash and

D2014 Sinks:- Classroom Sink

D2014 Sinks:- Kitchen Sink

D2017 Showers:- View of Showers

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 195 of 220

Page 196: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D2018 Drinking Fountains and Coolers:- Drinking Fountain

D2021 Cold Water Service:- Domestic Water Piping

D2022 Hot Water Service:- Water Heaters

D2018 Drinking Fountains and Coolers:- Drinking Fountain

D2022 Hot Water Service:- Domestic Hot Water StorageTanks

D2023 Domestic Water Supply Equipment:- Booster Pump

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 196 of 220

Page 197: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D2023 Domestic Water Supply Equipment:- Booster Pump

D2023 Domestic Water Supply Equipment:- Water Meter

D2023 Domestic Water Supply Equipment:- Water FiltrationSystem

D2023 Domestic Water Supply Equipment:- Water Meter

D2023 Domestic Water Supply Equipment:- Water Meter

D2031 Waste Piping:- Vent

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 197 of 220

Page 198: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D2031 Waste Piping:- Sanitary Waste Piping

D2043 Rainwater Drainage Equipment:- Sump Pumps

D3016 Solar Energy System:- Inverter Box

D2041 Pipe & Fittings:- Rain Drainage Piping

D3016 Solar Energy System:- Solar Panel

D3021 Boilers:- Flue Piping Leaking...Boiler 1

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 198 of 220

Page 199: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D3021 Boilers:- Boilers

D3022 Boiler Room Piping & Specialties:- Expansion Tank

D3022 Boiler Room Piping & Specialties:- Expansion Tank

D3021 Boilers:- Boiler 3...not Working

D3022 Boiler Room Piping & Specialties:- View ofExpansion Tank, 400 Gal

D3022 Boiler Room Piping & Specialties:- Heating WaterPiping

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 199 of 220

Page 200: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D3031 Chilled Water Systems:- Chillers

D3031 Chilled Water Systems:- View of Cooling Tower, 250Ton (x2)

D3032 Direct Expansion Systems:- Air Cooled Condenser

D3031 Chilled Water Systems:- Cooling Towers

D3032 Direct Expansion Systems:- Air-Cooled Condenser

D3032 Direct Expansion Systems:- Condensing Unit

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 200 of 220

Page 201: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D3041 Air Distribution Systems:- Ductwork

D3041 Air Distribution Systems:- Condensate piping leaking

D3041 Air Distribution Systems:- Split A/C System IndoorUnit

D3041 Air Distribution Systems:- Rooftop Unit

D3041 Air Distribution Systems:- View of Energy RecoveryUnit, 27,500 CFM

D3042 Exhaust Ventilation Systems:- Exhaust Fan

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 201 of 220

Page 202: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D3042 Exhaust Ventilation Systems:- View of KitchenExhaust Hood

D3044 Hot Water Distribution:- Hydronic Heater

D3045 Chilled Water Distribution:- Cracked Chilled WaterPiping at a Valve Controller- Leakng

D3042 Exhaust Ventilation Systems:- Kitchen Hood

D3045 Chilled Water Distribution:- Chilled Water Piping

D3051 Terminal Self-Contained Units:- Fan Coil Unit

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 202 of 220

Page 203: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D3051 Terminal Self-Contained Units:- Window A/C Unit

D3052 Package Units:- Rooftop Unit

D3052 Package Units:- Rooftop Unit

D3052 Package Units:- Rooftop Unit

D3052 Package Units:- Rooftop Unit

D3052 Package Units:- Rooftop Unit

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 203 of 220

Page 204: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D3067 Energy Monitoring & Control:- Gas Meter

D3068 Building Automation Systems:- Humidity Sensor

D3068 Building Automation Systems:- Broken VFDController of Hot Water Pump 5

D3068 Building Automation Systems:- Thermostats

D3068 Building Automation Systems:- DetachedThermostat in Room 321

D3068 Building Automation Systems:- HVAC Controller

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 204 of 220

Page 205: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D4012 Sprinkler Pumping Equipment:- Fire Standpiping

D4031 Fire Extinguishers:- Fire Extinguisher

D4095 Hood & Duct Fire Protection:- Kitchen HoodSprinkler Nozzles

D4012 Sprinkler Pumping Equipment:- Sprinkler System

D4031 Fire Extinguishers:- Fire Extinguisher CertificationTag

D4095 Hood & Duct Fire Protection:- Ansul System

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 205 of 220

Page 206: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D5012 Low Tension Service & Dist.:- Disconnect

D5012 Low Tension Service & Dist.:- Disconnect

D5012 Low Tension Service & Dist.:- Switchboard

D5012 Low Tension Service & Dist.:- Disconnect

D5012 Low Tension Service & Dist.:- Main Switchgear

D5012 Low Tension Service & Dist.:- Panel Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 206 of 220

Page 207: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D5012 Low Tension Service & Dist.:- Panel Board

D5012 Low Tension Service & Dist.:- Panel Board

D5012 Low Tension Service & Dist.:- Panel Board

D5012 Low Tension Service & Dist.:- Panel Board

D5012 Low Tension Service & Dist.:- Panel Board

D5012 Low Tension Service & Dist.:- Panel Board

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 207 of 220

Page 208: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D5012 Low Tension Service & Dist.:- Panel Board

D5012 Low Tension Service & Dist.:- Transformer

D5012 Low Tension Service & Dist.:- Transformer

D5012 Low Tension Service & Dist.:- Transformer

D5012 Low Tension Service & Dist.:- Transformer

D5012 Low Tension Service & Dist.:- View of SecondaryTransformer, Dry, 30 kVA

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 208 of 220

Page 209: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D5012 Low Tension Service & Dist.:- Automatic TransferSwitch

D5021 Branch Wiring Devices:- Switch

D5021 Branch Wiring Devices:- Receptacles

D5012 Low Tension Service & Dist.:- Automatic TransferSwitch

D5021 Branch Wiring Devices:- Receptacles

D5021 Branch Wiring Devices:- Occupancy Sensor

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 209 of 220

Page 210: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D5021 Branch Wiring Devices:- Occupancy SensorReceptacle

D5022 Lighting Equipment:- Flood Lights

D5031 Public Address & Music Systems:- Speaker

D5022 Lighting Equipment:- Exterior Lights

D5022 Lighting Equipment:- Fluorescent Light

D5031 Public Address & Music Systems:- PA Switch

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 210 of 220

Page 211: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D5031 Public Address & Music Systems:- PA System

D5033 Telephone Systems:- Telephone

D5036 Clock and Program Systems:- Clock

D5031 Public Address & Music Systems:- Sound System

D5033 Telephone Systems:- Telephone

D5036 Clock and Program Systems:- Master Clock

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 211 of 220

Page 212: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D5037 Fire Alarm Systems:- Strobe

D5037 Fire Alarm Systems:- Speaker Strobe

D5037 Fire Alarm Systems:- Alarm in Trouble Mode

D5037 Fire Alarm Systems:- Pull Station

D5037 Fire Alarm Systems:- Fire Alarm Panel

D5038 Security and Detection Systems:- Card Reader

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 212 of 220

Page 213: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D5038 Security and Detection Systems:- EAS Anti TheftSystem

D5038 Security and Detection Systems:- X Ray Machine

D5038 Security and Detection Systems:- DamagedSurveillance Camera

D5038 Security and Detection Systems:- Metal Detector

D5038 Security and Detection Systems:- SurveillanceCamera

D5038 Security and Detection Systems:- Motion Detector

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 213 of 220

Page 214: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D5038 Security and Detection Systems:- Access ControlPanel

D5091 Grounding Systems:- Lightning Protection

D5092 Emergency Light & Power Systems:- Exit Sign

D5039 Local Area Networks:- LAN Rack

D5092 Emergency Light & Power Systems:- EmergencyLight

D5092 Emergency Light & Power Systems:- Generator

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 214 of 220

Page 215: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

D5092 Emergency Light & Power Systems:- Generator

E1027 Laboratory Equipment:- Laboratory Sinks

E1093 Food Service Equipment:- Kitchen Equipment

E1027 Laboratory Equipment:- Laboratory Exhaust Hood

E1027 Laboratory Equipment:- Laboratory Sinks

E1093 Food Service Equipment:- Kitchen Equipment

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 215 of 220

Page 216: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

E2012 Fixed Casework:- View of Painted Metal Lockers

E2015 Fixed Multiple Seating:- View of Fixed FurnishingsTheater Seating

G2022 Paving & Surfacing:- View of Asphalt Paved ParkingLot

E2015 Fixed Multiple Seating:- View of Bleachers

E2015 Fixed Multiple Seating:- View of GymnasiumSeatings

G2022 Paving & Surfacing:- View of Concrete Parking Lots

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 216 of 220

Page 217: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

G2022 Paving & Surfacing:- View of Concrete Pavement

G2041 Fences & Gates:- View of Metal Fence

G2047 Playing Fields:- Electronic Marquee Board

G2041 Fences & Gates:- View of 4' Chain Link Fence

G2042 Retaining Walls:- View of Retaining Wall Cast inPlace Concrete

G2047 Playing Fields:- View of High School Football Field

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 217 of 220

Page 218: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

G2047 Playing Fields:- View of Playing Fields Small

G2054 Seeding and Sodding:- View of Grass Sodding ForSchools

G4021 Fixtures & Transformers:- Bollard Light

G2047 Playing Fields:- Football Score Board

G3061 Fuel Piping:- Fuel Gas Piping

G4021 Fixtures & Transformers:- Site Lights

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 218 of 220

Page 219: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

G4021 Fixtures & Transformers:- Site Lights

G4022 Poles:- Site Light Foundation

G4022 Poles:- Site Light Pole

G4021 Fixtures & Transformers:- Stadium Lighting

G4022 Poles:- Site Light Foundation

G4022 Poles:- Site Light Pole

Powered by © 4tell™ Solutions, LPHayat Brown LLC Page 219 of 220

Page 220: Facility Condition Assessment - | dgs

Anacostia High School August 31, 2018

G4022 Poles:- Football Site Light Pole