Fabrication of Steel Pipework

download Fabrication of Steel Pipework

of 10

Transcript of Fabrication of Steel Pipework

  • 8/16/2019 Fabrication of Steel Pipework

    1/10

    THIRTY SECOND CONFERENCE

    F B R I C T I O N O F S T E E L P IP EW O R K

    By J. H. BECKLEY

    Introduction

    The sugar industry is to some extent dependent upon steel tube

    for production, and failure of a pipe installation could result in costly

    delays. It is important therefore, that the engineers associated with

    the industry should have a sound knowledge of the various codes that

    have been developed to cover the design and fabrication of pipework.

    This paper briefly describes the more important aspects of these codes,

    and outlines the various methods used to fabricate steel tube.

    Calculating Tube Wall Thickness for Pressure Purposes

    British Standard No. 806- Ferrous Pipes and Piping Installations

    for and in connection with Land Boilers has been endorsed as Australian

    Standard No. B.65. This code covers most aspects of the design of steam

    and feed pipework and serves as a basis for the design of other pipework

    used for pressure purposes. The formula for calculating tube wall thickness

    PD

    has been derived from the well-known Barlow's formula of

    t c

    2s

    where t he wall thickness,

    =

    the design pressure, D the diameter

    of the tube, and S the allowable stress.

    PL

    The formula given in Clause 63 Part

    5

    of AS.B65 is

    t

    2

    se YP

    and the allowable stress S ) at the design temperature, the efficiency of

    the longitudinal joint

    e)

    for the various types of tube and the various

    values for

    y

    are ll clearly set out. The code requires the value of

    t

    to be multiplied by 1.125 if the tube is to be bent and depending upon

    the size and wall thickness of tube, an extra percentage must be allowed

    to ensure that ii the tube as ordered is rolled to the minimum wall thick-

    ness as allowed by the manufacturing code, then the final thickness

    is suitable for the working conditions.

    Branch Design

    Where a branch is required on a main, allowance must be made

    for the weakening effect of the hole which is cut in the main to form

    the branch. The method of calculating the strength of a branch pipe is

    set out in AS.B66 Clause

    79

    and where two or more branches are fitted

    in close proximity, allowance must also be made for the effect of one

    branch upon the other.

    As an example of the weakening effect a branch exerts on a main,

    a pipe with a

    90

    unreinforced equal branch has a safe working pressure

    of only

    70

    per cent of the safe working pressure of the straight pipe.

    Reinforcement to compensate for the metal cut out of the main to form

    the branch can be added (a) by fitting compensating rings, (b) by a

    technique developed by Stewarts and Lloyds Limited, known as Triform

    Reinforcement .

  • 8/16/2019 Fabrication of Steel Pipework

    2/10

    9

    T

    RTY SECOND CONFERENCE

    Fig.

    l Triform reinforced Tee piece.

    Typical details of the latter method using three horseshoe shaped

    reinforcing sections welded around the branch axe shown in Figure 1

    The fitting of reinforcement to a branch pipe is costly and can often be

    avoided by slightly thickening the main and branch pipes.

    the design of steam or other hot product mains

    is sufficiently flexible to absorb its own expansion

    without exerting undue force on equipment to which it connects, or

    developing stresses in excess of the allowable maximum in the pipe

    itself. Expansion can be absorbed by the use of expansion bends, bellows

    and joints, all of these methods requiring special guides and anchors.

    If

    possible, these special devices should be avoided and the route of the

    main selected to allow sufficient flexibility to give trouble free service.

    The expansion allowance per

    100

    feet of pipeline is set out in Table

    6

    of

    AS B65

    Stresses and thrusts due to expansion are reduced by pre-

    stressing or applying cold-draw to steam mains and other hot product

    lines. The minimum amount of cold draw which should be allowed is

    50

    per cent of the total expansion, but modern practice is to pre-stress

    the main to the maximum allowable stress in the cold condition, thus

    substantially relieving the stress on the pipework and connecting equip-

    ment .in the hot condition.

    Several methods are available for the computation of the stresses,

    thrusts and bending moments of a main operating at a high temperature.

    The method used by Stcwarts and Lloyds is that set out in

    a

    paper by

    Thyer

    [l]

    This method has been further developed by this company

    and has now been incorporated in a computor programme which can

    be used to ascertain stresses, thrusts, moments and movements in three

    planes in mains having up to six anchor points.

    Ben

    Both hot and cold processes are used to form bends in tube. AS.1365

    lists the permissible minimum radii to which the various sizes of tube

    may be bent, making allowance for the reduction in wall thickness as

    covered by the Code. Tubes can be bent to a smaller radius, but additional

    wall thickness must be provided to allow for the greater thinning which

    takes place in a tight radius bend.

    For hot bending the pipes are tightly packed with sand or river

    gravel, which supports the pipe wall during the bending process and

    thus prevents collapse or deformation of the tube. The arc length of the

  • 8/16/2019 Fabrication of Steel Pipework

    3/10

  • 8/16/2019 Fabrication of Steel Pipework

    4/10

    THIRTY SECOND CONFERENCE 1965

    ST TION RY

    FORMER

    Fig. 4 Compression bending.

    groove. To resist the side thrust a shaped slipper is used and as with

    compression bending deformation is prevented by the circular shape

    in which the tube is held. For small radii bends down to one and a half

    to two times the bore diameter additional support is required and a

    mandrel is held in the bore of the tube located so that it supports the

    outer surface of the bend and maintains the circular cross section through

    the bend. Tight radius bends for superheaters are bent on this type of

    machine and they are also used for the manufacture of tubular furniture.

    e 5 shows general details of this system of bending.

    ROT T I

    ENDING

    ORM

    Fig. 5 Tension bending.

    Bends can also be formed using either the fully gussetted technique

    or the cut and shut type bend. In the fully gussetted type angular seg-

    mental sections are cut and welded together to form a bend of the required

    angle. The

    minimum

    requirements are that the angle between adjacent

    segments does not exceed30 and the width of the throat of each segment

    is not less than one and a half inches. This type of bend is used

    for large diameter rolled and welded pipes and care should be taken

    to ensure that the location of the longitudinal weld in the various segments

    is staggered to avoid the formation of crucifix welds. The cut and shut

    process gives a better form to the bend and typical details of the pre-

    paration of the pipe are given in Figure 6.

    Gussetted bends are permitted by the Pipe Welding Code CB.15

    for pressures up to 250 pounds per square inch but at this pressure

    great care would have to be taken to ensure that complete penetration

    of the weld between the segments is obtained and the requirements

    of the Code in regard to circumferential buttwelds must be observed

    in welding this type of bend. Bends of this type are normally used for

    low pressure systems. Gussetted and cut and shut type bends are avoided

  • 8/16/2019 Fabrication of Steel Pipework

    5/10

    TH IRTY SECOND CONFERENCE

    I 9

    @ POINTS AT WHICH HWT IS APPJ~Q

    MbXlMUM CHANGE OF

    LINE AT EACH CUT 3 ° bPPWX

    SUITABLE HOLE DRILLED AT THE END f C ?

    VI W

    AFTFH

    BENOIMii

    Fig

    6 Cut

    and

    shut

    bend.

    in high pressure pipework where small radii can be obtained by the use

    of hot forged long or short radius elbows manufactured in accordance

    with BS.1640.

    Buttwelding elbows formed to this standard are manufactured

    with

    a

    radius equal to the bore for short radius elbows and one and a

    half times the bore for long radius elbows. These bends are formed by

    process which avoids thinning on the back of the bend and are suitable

    for pressures equal to straight pipe of similar dimensions.

    Methods of oining Pipes

    Various methods of joining pipes are adopted, the three most common

    being by screwed connection, flanges or by welding. Other types of

    joints such as Victaulic and Viking Johnson joints using rubber rings

    for the sealing medium are also employed, various grades of rubber

    being used for different purposes.

    Screwed joints are usually adopted for low pressvres and temp-

    eratures but flanges and welding can be used for

    ll

    conditions for which

    the tube or flange is designed. BS.10, which is now entitled Flanges

    and Bolting for Pipes, Valves and Fittings , and gives dimensions of

    ll

    standard flanges, has recently been extensively revised and has been

    endorsed s Australian Standard B.52.

    This code now includes a flange rating table whereby the allowable

    pressure for all flange tables decreases as the temperature increases and

    vice versa. For example, Table 'H' flanges are now suitable for 250

    pounds per square inch at 80Q°F, but the allowable pressure drops to

    115 pounds per square inch at 900°F, and rises again to 500 pounds

    per square inch for temperatures up to 450°F.

    Welded on flanges are now widely used and the methods of welding

    the flange to the tube are given in Clause 77 of AS.B65. The four main

    methods being

    :

    Type

    l Welding neck type flange where the flange is secured to

    the pipe by circumferential weld. The end of the flange

    is machined to match the pipe bore and outside diameter.

    Type

    2 Face and back welded on flanges.

    ype 3

    Bore and back welded on flanges.

    These three types of flanges are suitable for all design and pressure

    conditions.

  • 8/16/2019 Fabrication of Steel Pipework

    6/10

    9 IRTY SECOND CONFERENCE 1965

    Type 6. Bore and rear fillet welds--(slip on type flanges)-These

    flanges are suitable for all d and pressure conditions

    covered by British Standard Flange Tables up to and

    including 750 pounds per square inch and Table

    'H'.

    Figure 7 shows the above types of flanges.

    r P ~ I

    ~JLE-2

    TLP ~ i s 6

    Fig. 7 Types

    o

    welded flanges.

    Five other variations of these welding preparations are also given

    in AS.B05 and show the welding preparation for positional welds, and

    for limited temperature and pressure conditions. Normally the faces of

    flanges Tables 'E' to 'F' inclusive are machined with a flat surface, but

    for flanges over Table 'F', a raised face with a gramophone finish is

    employed.

    Oxy-acetylene welding and manual metallic arc welding are now

    used' for pipework for all operating pressures and temperatures. A welded

    joint gives maintenance free service and

    is

    adopted in major power

    stations operating at pressures of up to 2,450 pounds per square inch

    at temperatures of 1,050°F. Entire steam mains including the connections

    to valves, boilers and turbines are all welded.

    Acceptable methods for preparing pipe ends for welding and the

    special requirements for all welding of pressure pipework are given in

    Australian Standard No. CB.15. A plain buttweld is used for most low

    pressure installations, but buttwelding using a backing ring is preferred

    for higher pressures and temperatures. A straight 35 bevel with inch

    toe, is used for pipes up to approximately inch thickness, but

    a

    'J'

    shape welding preparation is employed for thicker pipes to reduce

    the amount of weld metal which is to be deposited. Figure

    of some of the various types of welding preparations. Whilst the backing

    Fig. 8 Tube

    end preparation

    or butt

    weld.

  • 8/16/2019 Fabrication of Steel Pipework

    7/10

    1965

    THIRTY SECOND CONFERENCE 97

    ring is not essential for high pressure welds, it helps to ensure that complete

    root penetration is achieved, guarantees alignment of the pipe bores,

    and minimizes the possibility of cracking of the base run of weld.

    A

    requirement of the Code for Pipe Welding, CB.15 is that the

    bores of adjacent pipes should match exactly. The permissible variations

    are shown in Table 1

    T BLE I--Permissible variations in bores o adjacent pipes for welding

    -

    .

    Maximum permissible

    Nom inal bore difference in internal Maximu m ou t of

    inches diame ter alignment at th e bo re

    inches inches

    U p t o and including

    4

    O ver 4 up t o and including

    1 6 :

    ver 10 up t o and including 4

    .

    Manufacturing tolerances generally allow a greater bore variation

    than that given above and it is usually necessary to match the bores

    of adjoining pipes either by machining or expanding.

    ranch Welds

    In a branch, welds must conform to the requirements of the

    Australian Code for pipe welding, CB.15. For high pressure work, two

    methods of attaching are adopted,

    a

    set on ,

    b

    set in . Sectional views

    of these two types of welding are shown in Figure

    9.

    The root gap and

    the angle of bevel are designed to enable full penetration to be achieved,

    but where possible an internal sealing run should be applied. The set on

    type of welding also allows the weld to be carried out using a temporary

    backing ring which can be machined out after welding, thus ensuring

    complete penetration of the branch weld.

    For low pressure pipework, the end of the branch may be cut to

    follow the profile of the main pipe and square to the centre-line, a bevelled

    weld preparation not being required. An internal sealing weld is parti-

    cularly desirable in this type of branch welding preparation.

    Fig. 9---Weld prepa rations for branches.

  • 8/16/2019 Fabrication of Steel Pipework

    8/10

    9 TH RTY SECOND CONFERENCE 1965

    Prior to any welding being carried out preheat as shown in Tables.

    I1 and I11 should be applied.

    Il-Preheating temperatures for gas welding

    -

    p

    r

    Minimum preheating temperature

    Thickness

    l

    ..

    Carbon steels Alloy steels

    Ill-Preheating tempe ratures for metal-arc welding

    p

    I TT

    U p t o and including 11/16

    . .

    100°C (211°F)

    Ov er 11/16 up t o including 718 . 200°C (392°F)

    Ov er 718

    . . .

    300°C (572°F)

    Parent metal

    Carbon steel (up to 0.2 6% )

    .

    200°C (392°F)

    200°C (392°F)

    300°C (572°F)

    Carbon steel (0 .2 6- 0. 40 x)

    .

    Chromium-molybdenum steel

    Thickness

    up to and including

    14

    Ov er 314

    all thicknesses

    all thicknesses

    Preheating temp.

    (minimum)

    Following welding stress relieving is carried out at the following

    temperatures

    or carboa steels-within the range of 600-650°C.

    or alloy

    steels-within the range of 630-660°C.

    These temperatures are maintained for approximately one hour per

    inch of pipe thickness with a minimum of half an hour.

    Pipework 44 inches outside diameter or less may be normalized i

    conditions of access make stress relieving impossible. Normalizing temp-

    eratures are

    carbon

    steels--within the range of 900-950°C.

    alloy

    steels-within the range of 925-975°C.

    This temperature is maintained for not less than two minutes and

    can be measured by means of one or more thermocouples an optical

    pyrometer or temperature responsive crayons. The width of the zone

    heat treated at the specified temperature extends at least half an inch

    on either side of the weld. Immediately after normalizing the joint is

    covered with a suitable or asbestos cloth to ensure slow and even

    cooling. Full details of heat treatment with specific requirements

    are given in Clause 330 of the Pipe Welding Code CR.15.

    Pressures and temperatures of steam generating equipment used

    in the sugar industry are not generally sufficiently high to require the

    use of alloy tube. The codes we have referred to for most of the foregoing

    data also contain full information to cover the fabrication of high tensile

    carbon tube as well as the various types of alloy material. The welding

    preparation for welding flanges to alloy tube is slightly different to that

    required for carbon steel a greater depth of welding being required

    but for branch and buttwelds welding preparation is similar to that

    used for carbon steel. The pre-and post-heat treatment of the high carbon

    and alloy steels is most important and the requirements of the code

    must be rigidly followed when fabricating these materials.

  • 8/16/2019 Fabrication of Steel Pipework

    9/10

  • 8/16/2019 Fabrication of Steel Pipework

    10/10

    1 TH IRTY SECOND CONFERENCE

    1965

    between the rubber and the steel, it is also usual to sand blast the bore

    to remove all rust or

    mill

    scale immediately, prior to the application of

    the adhesive solution to the pipe bore.

    Personnel engaged in the design of pipework will agree that one of the

    most diacult aspects of this work is to arrange for adequate simple

    supports. Hot product lines are subject to expansion and allowance

    must be made for movement in arranging the length of hanger rods,

    where vertical expansion will take place, springs must be provided.

    Where movements greater than two inches are anticipated constant

    load supports can be obtained which are designed to give

    an

    even

    supporting efIort over a range of movement of up to approximately

    18 inches.

    Anchors in a main subject to expansion should generally be welded

    to the pipework and take the form of special brackets which can be

    bolted to the building steelwork. Use of U bolts is not always satisfactory

    as they have a tendency to slip. Pipe clips should be made from sub-

    stantial flat sections and fully designed to carry the required load and

    hanger rods should include a means for adjustment of length and also

    be fitted with spherical washers to obtain even support when angularly

    displaced due to expansion. Holes in supporting structures should be

    large enough to accommodate angular movement of hanger rods.

    The foregoing remarks are intended as a guide to those responsible

    for pipework installations. The relevant Australian and British codes

    cover all aspects of this work and provided the full requirements of these

    codes are followed, no trouble should be experienced in the fabrication

    and installation of industrial pipework.

    of the Standards Association of Australia to print

    extracts from the Australian Codes B.65- Ferrous Pipes Piping

    Installations for and ifi connection with Land Boilers , and

    CB.15-

    Pipe Welding , is atefully acknowledged.

    l]

    Thyer

    A. M.: 1938.

    Trans.

    Inst.

    Eng.

    Aust. Vol.

    XIX.

    Stewarts and Lloyds Australia) Pty. Ltd.,

    Sydney,

    N.S.

    W .