EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
-
Upload
syed-umair-hashmi -
Category
Documents
-
view
287 -
download
4
Transcript of EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
1/39
~ o o ~ ~ ~ ~ ~ m ~ 4 ~ ~ ~ ~ ~ ~ ~ ; , & ~
SINOHYDRO GROUP LIMITED
Doha Expressway (Package 6
East Industrial Road Interchanges at Intersection with Street
10
and Street
23
Contact No. C2011/085
Document No. EXW POOS 0000 GSSHC MT-00003
Method Statement
for
Surveying and Setting
Out
1 13-May-12 Comply the comments from Parsons dated 14-Apr-12
0
4-Mar-12 Submittal
Revision Date Reason
for
Issue
Contractor Check l s t
Reviewed y
Checked y Approved
by
Luo, Tao Mukattash, Mahran
Sun, Jinhui
Consultant Comments
o Approved o Approved with Comments o
Approved
Engineer s Representative
Date
Doha - Stateof Qa tar
Tel 97 4-44126471
Fax
974-44 126471 wwwsmohydrocom
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
2/39
SINOHYDRO GROUP LIMITED
Doha ExpresswayPackage 6
East Industrial Road Interchanges at Intersection with Street 10 and Street 23Contact No. C2011/085
Doha State of Qatar Tel: +974-44126471Fax: +974-44126471 www.sinohydro.com
Submittal Information
1. Document NumberEXW-P006-0000-GS-SHC-MT-00003
2. DescriptionMethod Statement for Surveying and Setting Out
3. Pages39
4. RevisionRev.1
5. Reference NumberNil
6. Country of OriginQatar
7. BOQ Ref.1.05
8. Specification Ref.QCS 2010, Section 1, Part 13 & 15
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
3/39
SINOHYDRO GROUP LIMITED
Doha ExpresswayPackage 6
East Industrial Road Interchanges at Intersection with Street 10 and Street 23Contact No. C2011/085
Doha State of Qatar Tel: +974-44126471Fax: +974-44126471 www.sinohydro.com
Index
1. General Description of Package 6 Project
2. Purpose and Scope of Work
3. Specification and Standard
4. Abbreviations
5. Utilization of Existing Information
6. Manpower
7. Equipment
8. General Surveying Method
9. Process of Survey Works
10. Quality Assurance Procedure
11. Safety and Health Plan for survey works
12. Inspection & Testing
13. Appendix
Appendix 1. List of Survey Equipment (Used on P6 Site)
Appendix 2.Inspection for formation level/base slab/roof slab/backfilling surface of sheet
Appendix 3. Inspection for formation level/base slab/roof slab/backfilling surface drawing
Appendix 4. Setting Out for excavation sheet
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
4/39
SINOHYDRO GROUP LIMITED
Doha ExpresswayPackage 6
East Industrial Road Interchanges at Intersection with Street 10 and Street 23Contact No. C2011/085
Doha State of Qatar Tel: +974-44126471Fax: +974-44126471 www.sinohydro.com
Appendix 5. Manhole/chamber inspection for base slab level sheet
Appendix 6. Inspection for level of the installed pipeline sheet
Appendix 7. Formwork checking for kerb blinding
Appendix 8 Survey data for compacted ground/sub-grade/sub-base
Appendix9Inspection for kerb stone sheet
Appendix10Inspection deviation drawing for kerb stone
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
5/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 1 of 35
1 General Descr ipt ion of Package 6 Project
Package 6 of the Doha Expressway mainly covers the existing East Industrial Road
Alignment. The section of the road included in this contract, starts almost 850 m south of
the Industrial Roundabout up to its junction with the extension of Al Muntazah Street 33
with a total length of about 3.5 km.
The scope of work includes the upgrading of the existing East Industrial Road to provide a
three lane in each direction for the mainline traffic. The local traffic will be served through a
continuous service roads network providing safe and efficient movement between the
main line traffic to the adjacent existing facilities along the route. scope of works include:
a) Roads
b) Junctions and interchanges
c) Hard and soft landscape
d) Potable Water supply and reticulation systems
e) Irrigation supply and distribution systems
f) Wastewater system
g) Surface and ground water drainage system.
h) Electrical supply and distribution networks including 66/11 kV
i) Telecommunications and ELV duct network
j) Road and amenity lighting
k) Traffic control and street signs
2 Purpose and Scope of Works
2.1 Purpose
This plan provides the survey methodology and inspection scope adopted by Sinohydro
for Survey Works.
2.2 Scope of Works
1) Benchmarks
2) Earthworks
3) Concrete Works
4) Manhole and Chamber
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
6/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 2 of 35
5) Pipeline Works
6) Road Works
3 Specification and Standard
Unless otherwise provided or required by the Engineer, following standards and
specifications shall be used in performing survey works:
a) Basic survey data source: Qatar National Grid (QNG) and Qatar National Height
Datum (QNHD)
b) Qatar Construction Specification 2010
c) Qatar Survey Manual
d) Project General Specification
e) Other Survey Specification
f) Information and document of Engineer
4 Abbreviations
The following abbreviations are used in this Plan.
GPS Global Position System
GIS Geographic information system
QNG Qatar National Grid
QNHD Qatar National Height Datum
TGO Trimble Geomatics Office
TBC Trimble Business Center
LGO LEICA Geo Office
RTK Real Time Kinematic
RFI Request for Inspection
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
7/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 3 of 35
5 Utilization of Existing Information
Qatar National Benchmarks will be the basis for survey works, Benchmarks provided by
center for GIS. Details please see Table 1 and Appendix 11
Table 1
Point No.Horizontal Coordinates (QNG95) Vertical (QNHD95)
Easting Northing Used Elevation
570001 224096.741 382207.121 19.481
560046 223366.897 383367.888 20.618
560080 223109.127 383197.218 22.054
560047 222681.230 383860.419 ---------
560048 222940.056 384007.725 ---------
560061 222591.112 384553.745 ---------
560062 222327.402 384396.843 ---------
Before starting survey works,every Qatar national benchmark will be checked. Accroding
checked result some benchmark not ues for this survey works.Benchmark of the above
table is the first class control point for the construction. Some new benchmark will be
established base on the condition of site survey during construction.
6 Manpower
Total 5 personnel are involved in this work. According to the site actual situation, It
increase suitably with the reduction surveyor. Details please see Table 2.
6.1 List of Personnel
Table 2S/N Name Age
WorkExperience
Position
1 Wang Shaolin 49 30 Survey Manager
2 Zhang jisheng 43 20 Site Survey Chief
3 Bao Yanjie 31 8 Office Survey Chief
4 Qi Wanyi 25 2 Land Surveyor
5 Shen Jianchao 25 2 Land Surveyor
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
8/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 4 of 35
6.2 Organization Chart
7 Equipment
7.1 Survey Instrument
The following survey instrument should be involved in the site survey works.
a) GPS Receiver 2 unit
b) Total Station 1 unit
c) Electronic Level 1 unit
d) Automatic Level 1 unit
According to the actual site situation, It increase suitably with the reduction survey
instrument. Survey instrument should be regular get of calibration certificate.
7.2 Survey Software
The following software should be involved in the survey works.
a) Trimble Geomatics Office (TGO)
b) Trimble Business Center (TBC)
c) LEICA Geo Office (LGO)
d) AutoCAD
e) Nikon Data Transfer
Survey ManagerWang ShaoLin
Site SurveyChief
Zhang JiSheng
Office SurveyChief
Bao YanJie
Site Survey Team
Shen JianChao,Qi WanYi
Office Surveyor
Shen JianChao,Qi WanYi
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
9/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 5 of 35
7.3 Other Equipment
According to work requirement, Computer and site vehicle will be involved in the survey
works. Details equipment info please see appendix 1. List of Survey Equipment (Used on
P6 Site).
8 General Surveying Method
8.1 Surveying Method for GPS
8.1.1 Static Survey
GPS static measurements, is the use of measurement-based GPS receivers to locate a
measurement. Mainly used to create various kinds of control net. Static GPS
measurements carried out that the GPS receiver antenna in the location of the observation
process is static, in data processing, it will be the location of the antenna as a receiver
does not change over time, the amount of change, through the received satellite data to
seek a change in the coordinates of points to be determined. In the measurement, GPS
static measurements of the specific observation model is more than one receiver at
different stations on the static synchronous observation time from 20 minutes to 10 hours
range.Relevant Technical Index
No.s of observation session1.8
Length of observation session: 25 minutes
Valid observation satellite:4 pcs
Geometry pattern strength PDOP6
Satellite height angle: 15
Data collection interval 15s
8.1.2 RTK Survey
Set up GPS base station on a benchmark. The tripod is erected on the benchmark and
strictly centered. Antenna installed, Input point numbers and coordinates. And at least two
benchmarks shall be surveyed for checking purpose. The two control-benchmarks will be
surveyed at least 5 sec.
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
10/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 6 of 35
8.2 Surveying Method for Total Station
8.2.1 Fixed Station
Set up total station on a know benchmark. The tripod is erected on the benchmark and
strictly centered. Input station and backsight point number and coordinates, and input
instrument height. Observation backsight point and measurement coordinates record, and
checking other benchmarks. If checking point coordinates exceed 10mm shall be re-set up
station.
The fixed station relevant Technical Index, please as following Figure1:Sketch of Fixed
Station.
Distance of survey point Distance of BS.point
Accuracy of Check point 10 mm
Figure1: Sketch of Fixed Station
8.2.2 Free Station
Set up total station on anywhere and strictly leveling. At least input two backsight point
number and coordinates. Observation backsight point and measurement coordinates
record,and checking other benchmarks. If checking point coordinates exceed 10mm shall
be re-set up station.
The free station relevant Technical Index, please as following Figure2:Sketch of Free
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
11/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 7 of 35
Station.
Angle r is 30~ 150
Distance to a and b700 m
Distance of survey point Distance of BS.point
Accuracy of Check point 10 mm between 90~ 190from BS. Point
Points surveyed from a free station shall be placed in site or here the polygon
between the known points used for determine the free station point.
Figure2: Sketch of Free Station
8.3 Surveying Method for Leveling
8.3.1 Closed Leveling
From the known elevation point of the beginning, and finally closed in fact point to the
standard route. Single survey and middle thread reading method was adopted for the
leveling survey, the sequence of reading is back-front-front-back. The reading is saved to
the five places of decimal.
8.3.2 Annexed leveling
From the known elevation point of beginning and end another known elevation point of
standard route. Single survey and middle thread reading method was adopted for the
leveling survey, the sequence of reading is back-front-front-back. The reading is saved to
the five places of decimal.
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
12/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 8 of 35
8.4 The Detailed Survey Procedure
If the control / check survey shows that the result does not comply with the tolerance, the
responsible engineer in the construction or QA/QC group shall be informed immediately.
The result shall be submitted for the Engineer accept as soon as it have been completed.
RFI from QA/QCDepartment
Setting-Out orInspection
Uesing GPS,Total
Station or Leveling for
Setting-out/Inspection
Transfer DesignCoordinates to
GPS/Total Station
Approved ShopDrawings
Download GPS,Totalstation or Leveling
survey raw data
Prepare data to sheet andautocad drawing (please see
appendix)
Hand over hard copyand soft copy to
QA/QC
Not OK
Hand over hard copy andsoft copy to Engineer
acceptance
Not OK
Engineer ApprovedAnd return to QA/QC
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
13/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 9 of 35
9 Process of Survey Works
9.1 Benchmarks
9.1.1 Temporary Benchmarks
a) Survey used instruments
GPS and total station should be adopted for horizontal coordinates. Total station and level
instrument should be adopted for vertical.
b) Survey Method
Horizontal control should be established by GPS static survey, opening and closing
traverses, resection, intersection, free-station etc.
Vertical control should be established by closed and annexed leveling line, total stationtriangulation etc.
c) Tolerance
Horizontal : Points position 10mm, relative total length closing error of traverse 1/35000.
Vertical : 4 L mm (where L is the distance leveled in kilometers).
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including temporary benchmarks
results, calculation processing for Horizontal and vertical.
9.1.2 Maintenance and Monitoring for Benchmarks
Site surveyors should be regular maintenance and monitoring the site benchmarks,
Maintenance including point name, safety fence etc. Monitoring including horizontal and
vertical coordinates checked.
a) Monitoring Time
Horizontal monitoring frequency: should be carried out every six months
Vertical monitoring frequency: should be carried out every three months.
b) Used Instrument
Horizontal check should be used RTK-GPS
Vertical check should be used level instrument.
c) Checking Method
Horizontal coordinates checking method: Set up GPS base station on a national
benchmark560046provided by center for GIS. The tripod is erected on the benchmark
and strictly centered. Antenna installed. Input point numbers for each point .Two groups of
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
14/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 10 of 35
data were measured on each points. With min. 20 minute interval or counter check. The
observation section were not less than 5 second and data were recorded .
Vertical elevation checking method: One closed leveling line origins and terminates on the
national benchmark 560046, elevation is based leveling 570001 and 560046. Single
survey and middle thread reading method was adopted for the leveling survey, the
sequence of reading is back-front-front-back. The reading is saved to the five places of
decimal. Relevant specifications were followed in the progress of survey.
d) Tolerance
Horizontal : Points position 20mm+1ppm
Vertical : 4 L mm (where L is the distance leveled in kilometers).
e) Results Submit shall be submitted for engineer
acceptance.
9.2 Earthworks
9.2.1 Setting-Out for Excavation
a) Used Instrument
Horizontal setting-out should be used RTK-GPS or Total Station.
b) Setting-out Method
The excavation coordinates for center line, boundary line and key points from the
approved shop drawing, are transfer into the GPS data collector or total station. The
setting out points shall be show at intervals of not more than 25m along the setting out line.
But also every key point must be staked out.
c) Tolerance
Setting-out points horizontal tolerance 50mm.d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.2.2 Final Survey for Formation Level
a) Used Instrument
Horizontal checked should be used RTK-GPS or Total Station
Vertical checked should be used RTK-GPS, Total Station or Level Insrument.b) Checking Methods
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
15/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 11 of 35
Formation level checked for pipeline: A point surveyed / checked every 10 m along the
centerlines.
Formation level checked for concrete works
Building: Max grid of 10m x 10m,and every key point must be checked.
c) Tolerance
Horizontal : 50mm, Vertical : - 150mm / +10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.3 Concrete Works
9.3.1 Blinding
Setting-out for Blinding
a) Used Instrument
RTK-GPS (RTK-GPS only horizontal and vertical ues level instrument) or Total Station
should be adopted for this works.
b) Setting-out Method
Setting-out coordinates for centerline, boundary lines and key points for blinding, screed,base slab, wall and roof slab from the approved shop drawing (please see appendix). are
transfer into the GPS data collector or total station. In each section min. 6 point shall be
marked / staked out. But also every key point must be staked out.
c) Tolerance
Horizontal : 20mm, Vertical : 10mm.
9.3.2 Base Slab
Setting-out for Base Slab
a) Used Instrument
Total station should be adopted for this works.
b) Setting-out Method
Setting-out base slab method is the same as the blinding method.
c) Tolerance
Horizontal : 10mm, Vertical : 10mm.
d) Results SubmitA RFI should be submitted for engineer acceptance, RFI including deviation drawing,
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
16/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 12 of 35
survey data and soft copy.
9.3.3 Wall and Column
Setting-out for Wall and Columna) Used Instrument
Total station and level instrument should be adopted for this works.
b) Setting-out Method
Setting-out wall and column method is the same as the blinding method.
c) Tolerance
Horizontal : 10mm, Vertical : 10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.3.4 Roof Slab
Setting-out for Floor and Roof Slab
a) Used Instrument
Total station and level instrument should be adopted for this works.
b) Setting-out Method
Setting-out roof slab method same to as blinding method.
c) Tolerance
Horizontal : 10mm, Vertical : 10mm.
Random check can be done any time by SST.
9.3.5 Inspection after formworks completed
a) Used Instrument
Total station and level instrument should be adopted for this works.b) Inspection Method
After formworks completed, survey actual horizontal coordinates and level for boundary
lines and key point. Comparison between the checked Survey Results and the design
Results. Where the difference between checked Survey Results and design Results
not exceed the tolerance the formworks is ok, if exceed the tolerance the formworks shall
be adjusted.
c) Tolerance
Horizontal : 10mm Vertical : 10mm.
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
17/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 13 of 35
Random check can be done any time by SST.
d) Results Submit
Deviation drawings, survey data should be submitted for engineer acceptance
9.3.6 Elevation Checking for Roof Slab (final surface)
a) Used Instrument
Total station and level instrument should be adopted for this works.
b) Checking Method
Elevation check for roof slab method same to as elevation check for screed method.
c) Tolerance
Vertical : 10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.4 Manhole and Chamber
9.4.1 Blinding
Setting-out for Blinding
a) Used Instrument
RTK-GPS or Total Station should be adopted for this works.
b) Setting-out Method
Setting-out coordinates for centerline, boundary lines and key points from the approved
shop drawing, are transfered into GPS data collector or total station. But also every key
point must be staked out.
c) Tolerance
Horizontal : 20mm, Vertical : 10mm.
9.4.2 Base Slab
9.4.2.1 Setting-out for manhole and chamber position
a) Used Instrument
Total Station should be adopted for this works.
b) Setting-out MethodSetting-out coordinates for manhole and chamber from the approved shop drawing, are
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
18/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 14 of 35
transfered into total station, Site surveyor shall be setting-out manhole and chamber.
c) Tolerance
Horizontal : 20mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.4.2.2 Elevation Check for Base Slab
a) Used Instrument
Total station and level instrument should be adopted for this works.
b) Checking Method
Every manhole and chamber center points and boundary points are checked.
c) Tolerance
Storm Water Vertical : - 30mm / +10mm
Sewer Water Vertical : 10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including checked drawing,
survey data and soft copy.
9.4.3 Manhole and Chamber Cover
Cover level checked after manhole and chamber completed.
a) Used Instrument
Total station and level instrument should be adopted for this works.
b) Checking Method
Every manhole and chamber cover center points shall be checking.
c) Tolerance
Vertical : 10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including checked drawing,
survey data and soft copy.
9.5 Pipeline Works
9.5.1 Setting out for pipeline
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
19/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 15 of 35
a) Used Instrument
RTK-GPS and Total station should be adopted for this works.
b) Setting out method
Setting out method for pipeline work is to set out a point every 10m along the centerlines.
and key point must be staked out.
c) Tolerance
Wastewater pipeline: Horizontal tolerance: Pipe diameter 800mm: 20mm, 800mm:
30mm.
Storm pipeline: Horizontal tolerance : Pipe diameter 800mm: 20mm, 800mm:
30mm.
Irrigation pipeline: Horizontal tolerance : 100mm.
Potable Water pipeline: Horizontal tolerance : 100mm.
9.5.2 Wastewater Pipeline
Sewer pipeline elevation check after installation.
a) Used Instrument
Total station and level instrument should be adopted for this works.
b) Checking Method
Pipeline between two manhole or chamber is checked, Distance between point surveyed
shall not exceed 10 m along the centerlines.
c) Tolerance
Pipe diameter 800mm, Horizontal : 20mm, Vertical : 10mm.
Pipe diameter 800mm, Horizontal : 30mm, Vertical : 10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.5.3 Storm Pipeline
Storm pipeline elevation check after installation.
a) Used Instrument
Total station and level instrument should be adopted for this works.
b) Checking Method
Checking method for storm pipelines is the same as checking method Sewer Pipelines.c) Tolerance
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
20/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 16 of 35
Pipe diameter 800mm, Horizontal : 20mm, Vertical : 10mm.
Pipe diameter 800mm, Horizontal : 30mm, Vertical : 10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.5.4 Irrigation Pipeline
Irrigation pipeline elevation check after installation.
a) Used Instrument
RTK-GPS and Total station should be adopted for this works.
b) Checking MethodChecking method for irrigation pipelines is to survey a point every 10m-20m along the
centerlines. Key point must be checked.
c) Tolerance
Horizontal : 100mm, Vertical : 25mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.5.5 Potable Water Pipeline
Potable Water pipeline elevation check after installation.
a) Used Instrument
RTK-GPS and Total station should be adopted for this works.
b) Checking Method
Checking method for potable water is the same as the checking method for irrigation pipe.
c) Tolerance
Horizontal : 100mm, Vertical : 25mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.6 Road Works
9.6.1 Setting out and OGL survey of Road works
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
21/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 17 of 35
a) Used Instrument
RTK-GPS should be adopted for this works.
b) Survey Method
Setting-out Method: Coordinates for centerline, boundary lines and key points from the
approved shop drawing, are transfered into GPS data collector. Center line and both
boundary lines shall be show at intervals of not more than 25m, and every key point must
be staked out.
OGL Survey Method: Each cross section not more than 25 m and every cross section for 5
point shall be survey. Every cross section survey width exceed road design width.
c) Tolerance
Setting-Out Horizontal : 20mm.d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.6.2 Survey inspection of compacted grounda) Used Instrument
RTK-GPS should be adopted for this works.
b) Inspection Method
Each cross section not more than 25 m and every cross section for 4~6 points shall be
survey. Every cross section survey width exceed road design width. Details please see
appendix.10.
c) Tolerance
Horizontal : 20mm, Vertical : 30mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including survey data and
deviation.
9.6.3 Survey inspection for formation level (final layer of sub-grade)a) Used Instrument
Leveling Instrument and Total Station should be adopted for this works.
b) Inspection Method
Each cross section not more than 25 m, every cross section for 4~6 points shall be survey.
Construction guy first marking every checked point, the points are fix offset from
kerb-stone. Site surveyor used leveling instrument or total station survey every marked
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
22/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 18 of 35
points, and calculation deviation..
c) Tolerance
Vertical:-20mm/+15mm
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including survey data and
deviation.
9.6.4 Setting out of kerb-stone
a) Used Instrument
Total Station and Leveling Instrument should be adopted for this works.
b) Setting-out Method
Setting out method for kerb stone work is to set out a point every interval of 20 meters for
straight as well as every 5 meters for curved. And key point must be staked out.
c) Tolerance
Horizontal : 10mm, Vertical : 10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.6.5 Survey Inspection for Kerb-stonea) Used Instrument
Total Station and Leveling Instrument should be adopted for this works.
b) Inspection Method
Inspection method for kerb stone work is to checked point every interval of 20 meters for
straight as well as every 5 meters for curved. And key point must be checked.
c) Tolerance
Horizontal : 10mm, Vertical : 5mm.d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
23/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 19 of 35
10 Quality Assurance Procedure
10.1 Management and Responsibi lities
10.1.1 Purpose
The purpose of this procedure is to carry through a whole course control the whole
process of the survey works so that a satisfactory survey result can be achieved in
accordance with contract.
10.1.2 Responsibi lit ies
Survey Manager shall fully take charge of survey work of the project, and implement the
regulations in quality assurance plan in the survey work and achieve survey resultconforming to the requirement of Project Specification.
Chief surveyor shall participate in the planning of survey technical design, and take
charge of on-site survey, calibration of survey instruments and checking of survey results.
Site surveyor team shall be responsible for conducting on-site survey works.
Office surveyor shall be responsible for the post-processing of data and preparation of
drawings.
10.2 Quality Assurance Process
The quality assurance process includes survey planning, survey preparation, on-site
survey, post-processing data and acceptance checking.
10.2.1 Survey Planning
As per contract requirement, survey manager and chief surveyor shall participate in
planning works, includes the following:
General description and scope of work
Technical and quality requirement
Determination of program and completion time
Work method
Survey preparation includes: joint checking of drawings, method, quality control index,
instrument maintenance, and personnel training.
10.2.2 On-site Survey
Every procedure of survey works (horizontal control, elevation control) shall be carried out
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
24/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 20 of 35
as per relevant specifications.
Effective measures should be taken for the protection of the instrument in storage and
delivery. Special attention should be paid to maintain accuracy and sensitivity of the
instruments.
Survey records should be made in a uniform form and includes all necessary information.
For topography survey refer to plan In-survey.
10.2.3 Post-processing
Chief survey shall make further arrangements for data and documents review and check
relevant site record and calculation data. Drawer shall cooperate with each other and
make self-assessment. Survey team leader shall make final checking.Survey superintendent shall be responsible for preparation of technical report, checking
of relevant survey record and data calculation.
10.2.4 Acceptance Checking
Team leader shall make final acceptance checking after self-checking of on-site survey
team.
Checking content: content of works fulfils specification requirements, survey method
should be suitable for the work, result drawing conform to requirement of construction
works, survey data and document be complete and correct.
The survey result shall be self-checked by surveyor, reviewed by checker, verified by
survey superintendent and approved by survey manager finally.
Final acceptance and submittal: All survey products together with relevant records shall be
submitted to QC department of the project for approval. And survey team shall print out the
survey product and submit it to Engineers for approval.
10.3 Resources Management
10.3.1 Personnel Training
a) Training programs will be prepared. Such program shall be established taking into
account any impact resulting from changes in technology and other survey
processes.
b) Training shall be provided to ensure that personnel are aware of the importance
and relevance of their activities. Records of the training are maintained.
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
25/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 21 of 35
10.3.2 Instrument Control
a) All survey instruments shall be selected and controlled with consideration to range,
accuracy and tolerance to accomplish the required results
b) Survey instrument shall as a minimum be calibrated as stated on the valid
calibration certificate , and record of calibration should be filed. If it is indicated the
an instrument is out of calibration, it will immediately be handed over to the
responsible chief surveyor so a re-calibration can be carried out.
c) All survey instruments shall be calibrated, adjusted and maintained at prescribed
intervals or prior to use against internationally or certified nationally recognized
standards. Where no such standards the basis and method for calibration shall be
documented
10.4 Control of Document
Relevant survey document will be controlled as per document control procedures. The
document management system will cover control over approval, publishing,
communication, change, maintenance of relevant supporting document to assure validity,
integrity and applicability of document. Special attention should be paid to laws,
specifications and standards concerning survey works.
Change and revision of documents: Any change and revision of documents shall be
implemented by approval department. And revised documents shall be identified clearly.
Document controller will be assigned to manage the relevant survey documents and will
be in charge of management, handling, collection, catalog, maintenance of relevant
documents.
10.5 Quality Record
Relevant quality record shall be prepared and shall be provided to engineer as per their
requirement. And a quality controller shall be assigned for the arrangement, catalog, filing
and maintenance of quality record. Information of relevant points should be maintained.
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
26/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 22 of 35
11 Safety and Health Plan for survey works
11.1 Risk Assessment
Risk Potential Danger Control Measures Reference
Inadequateknowledge of
Projectrequirements
Personal injuryInjury to othersIgnorant to site
regulations
Attend Sinohydro Safety Induction forNew Employees
Moving vehicles/ Machinery
Road accident,Personal injury, loss of
life, property andequipment damages
Attend driver training conducted bySinohydro Safety Department
Not familiar withwork execution
Personal injuryInjury to Others
Struck by machinery
Attend the daily program conducted bysupervisor / foreman
Personnel onground
Hit by moving vehicleHit by moving truck
Wear proper high visibility vestProvide shed / covering
Vehicles fallingfrom the edge ofthe excavation
Back Injury, Fractures,Cuts, Bruises, Death
Rigid safety barriers shall be erectedaround all excavations to preventvehicles falling into them. Vehicles
shall be kept away from excavationswherever possible. Where vehicles
have to tip materials into excavations,stop blocks to prevent them fromover-running shall be used and abanksman shall be present before
discharging the load.Fallen material
from highPersons injured
Equipment damaged
Wear Safety helmet ;Keep away from dangerous place.
Falls fromHeight
Back Injury, Fractures,
Cuts, Bruises, Death
Suitable signs will be positioned andrigid edge protection will be erected atplaces where the falls of more than 2m
could occur. Personal suspensionequipment will be used by operatives
working at or near the edge.Training, toolbox talks and
instructions shall be provided to all
operatives and supervisory staffinvolved in the use of suspension
equipment such as lines andharnesses, and how to inspect andassess PPE of this type before use.
11.2 Protective & Safety Equipment
All workers involved shall be equipped with adequate PPE as follows:
Safety helmet
Safety boots
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
27/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 23 of 35
Safety vest
11.3 Contractual Requirements
Safety induction for New Employees
PPE requirements
Inspection of Machinery
Emergency Procedures
Welfare facilities
First aid requirements
Defensive driving training
Water tank for drinkingCommunications (walktalking, mobile telephone)
11.4 Emergency Procedures
In the event of an accident, the following shall be activated:
The area supervisors shall act as the Rescue Team Leader and attend to the accident
He shall inform the emergency controller of the accident
In the absence of the Project Manager, the Construction Manager shall act as the
Emergency Controller
The emergency controller shall alert the emergency response team, comprising of first
aiders to attend the accident when required.
The emergency controller shall alert the fire fighting team should there be a fire.
The rescue team leader shall alert the emergency controller for additional assistance from
other rescue team leaders
The emergency controller shall arrange for transportation to send the injured person to the
clinic or hospital if required
The accident area shall be barricaded and nothing shall be removed from the area.
A watchman shall be engaged to protect the area from unauthorized entry
The emergency controller shall call for a post mortem meeting after the emergency with
the people involved in the emergency.
The S&H representative shall organize the safety committee to perform a full accident
investigation
All information leading to the accident including information, description, photos, time,
location, sources, witness statements, police and medical reports shall be prepared a
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
28/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 24 of 35
submitted by the Project Manager.
Defensive driver permit
12 Inspection & testing
Inspections and testing will be performed by Sinohydro; the procedure should be
subjected to Document EXW-P006-0000-GS-SHC-IT-00001.
13 Appendix
Appendix.1 List of Survey Equipment (Used on P6 Site)
Appendix 2.Inspection for formation level /base slab/roof slab/backfilling surface of sheet
Appendix 3.Inspection for formation level /base slab/roof slab/backfilling surface drawing
Appendix 4.Setting out for excavation sheet
Appendix 5. Manhole/chamber inspection for base slab level sheet
Appendix 6 . Inspection for level of the installed pipeline sheet
Appendix 7.Formwork checking for kerb blinding
Appendix 8. Survey data for compacted ground/sub-grade/sub-base
Appendix 9. Inspection for kerb stone sheet
Appendix 10Inspection deviation drawing for kerb stone
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
29/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 25 of 35
Appendix.1 L is t of Survey Equipment (Used on P6 Site)
Item Type Model ManufacturerManufactures
Serial No
Calibration
DateExpireDate Remarks
Survey
Instrument
Automatic
Level
FOIF
NAL-124FOIF T97212
19-Mar-20
1218-Sept-2012
GPS
ReceiverR6 Trimble 4822153875
24-Dec-20
1123-Dec-2012
GPS
ReceiverR6 Trimble 4822153857
24-Dec-20
1123-Dec-2012
Total Station DTM532 Nikon 03275313-Mar-20
1212-Sept-2012
Electronic
LevelDINI12 Trimble 703163A
20-Feb-20
1219-Aug-2012
Survey
Software
TBC 2.4 Trimble
TGO 1.63 Trimble
AutoCAD 2006/2010 Autodesk
LGO LEICA
Nikon Data
TransferNikon
Computer unit 1
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
30/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 26 of 35
Appendix 2.Inspect ion for formation level /base slab/roof slab/backfi ll ing sur face ofsheet
Location.____ Inspection for formation level/screed/base slab/roof slab/backfi lling surface
CHAINAGE ELEVATION CHECKED POINTS DESIGNELEVATIONDEVIATIONP.N EAST NORTH ELEVATION
SURVEY INSTRUMENT: GPS / TOTAL STATION / LEVELING
DESCRIPTI P.N EAST NORTH ELEVATIONSTATION
BS
CHECK .BS
Surveyor:_________ Date:_________
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
31/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 27 of 35
Appendix 3.Inspection for formation level /base slab/roof slab/backfi ll ing surfacedrawing
N
3300.00
1400.0
0
3850.00 3850.00
480
0.0
3
4799.97
Surveyor:_________ Date:_________
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
32/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 28 of 35
Appendix 4.Setting out for excavat ion sheet
Location.______ Setting out for excavation
CHAINAGESETTING OUT POINTS
P.N EAST NORTH ELEVATION
SURVEY INSTRUMENT: GPS / TOTAL STATION / LEVELING
DESCRIPTION P.N EAST NORTH ELEVATIONSTATION
BS
CHECK .BS
Surveyor:_________ Date:_________
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
33/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 29 of 35
Appendix 5. Manhole/chamber inspection for base slab level sheet
MANHOLE/CHAMBER NO. INSPECTION FOR BASE SLAB LEVEL (STORM / SEWER / IRRIGATION / POTABLE)
Manhole/CHAMBER P/NCHECK POINTS COORDINATE DESIGN COORDINATE DEVIATION(mm)
EAST NORTH ELEVATION EAST NORTH ELEVATION EAST NORTH ELEVATION
SURVEY INSTRUMENT GPS/TOTAL STATION/LEVELINGN.O. EAST NORTH ELEVATION
STATION
BS
CHECK
POINTS
REFERENCE DRAWING:
Surveyor:_________ Date:_________
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
34/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 30 of 35
Appendix 6 . Inspection for level of the instal led pipel ine sheet
SURVEY INSTRUMENT:GPS / TOTAL STATION / LEVELING
N.O. EAST NORTH ELEVATION
STATION
B.S.
CHECK POINTS
REFERENCE DRAWING :
Surveyor:_________ Date:_________
CH.______ INSPECTION FOR LEVEL OF THE INSTALLED PIPELINE(STORM/SEWER/IRRIGATION/POTABLE)
CHAINAGE P/NCHECK POINT COORDINATE DESIGN DEVIATION(mm)
EAST NORTH ELEVATION ELEVATION ELEVATION
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
35/39
Sinohydro Group LimitedDoha Expressway Package 6 M
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012
Appendix 7.formwork chencking for kerb blinding
FORMWORK CHECKING FOR KERB BLINDING ( CH. __________)
CHAINAGEKERBLEVEL
OFFSET FROM KERB LINE CHECKED COORDINATES
L R POINT NO. E N ELEVATION
Surveyor: Date:
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
36/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 32 of 35
Appendix 8. Survey data for compacted ground/sub-grade/sub-base.
CHAINAGE NO.
SURVEY COORDINATEAND LEVEL
FINISHEDROADLEVEL
SUB-GRADELEVEL(TOP)
DIVATIONLEVEL(mm)
EAST NORTH LEVEL
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
SURVEYOR: DATE:
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
37/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 33 of 35
Appendix 9.Inspect ion for kerb stone sheet
NO.CHECK POINT COORDINATE DESIGN
ELEVATIONDEVIATION
ELEVATION(mm)EAST NORTH ELEVATION
1
23
4
NO. EAST WEST ELEVATION
STATION FREE
BS
CHECK BS
LEVELING BS
SURVEY INSTRUMENT:TOTAL STATION AND AUTO-LEVEL
SURVEYOR: DATE:
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
38/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 34 of 35
Appendix 10inspection deviation drawing for kerb stone.
Surveyor:__________ Date:____________
-
8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1
39/39
Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out
Appendix 11inspection deviation drawing for kerb stone.