Expansion of state highway 1

29
EXPANSION OF STATE HIGHWAY -1,ANDHRA PRADHESH HYDERABAD-KARIMNAGAR-RAMAGUNDAM ROAD FEASIBILITY REPORT PRESENTATION BY K.SNEHA ROLL NO:131564 EXPANSION OF STATE HIGHWAY-1 HYDERABAD-KARIMNAGAR- RAMAGUNDAM ROAD FEASIBILITY REPORT PRESENTATION CONSTRUCTION ECONOMICS AND FINANCE BY K.SNEH A 131564

Transcript of Expansion of state highway 1

Page 1: Expansion of state highway 1

EXPANSION OF STATE HIGHWAY -1,ANDHRA PRADHESH

HYDERABAD-KARIMNAGAR-RAMAGUNDAM ROAD

FEASIBILITY REPORT PRESENTATION

BYK.SNEHAROLL NO:131564

EXPANSION OF STATE HIGHWAY-

1

HYDERABAD-KARIMNAGAR-

RAMAGUNDAM ROAD

FEASIBILITY REPORT

PRESENTATION

CONSTRUCTIO

N ECONOMICS

AND FINANCE

BYK.SNE

HA13156

4

Page 2: Expansion of state highway 1

PROJECT BACKGROUND The State Government of Andhra Pradesh (GOAP) through the

Government of India (GOI) has applied for a loan from the International Bank for Re-construction and Development (IBRD)

As per the GOAP’s strategic vision, the state has identified the need to upgrade and operate the high traffic roads in the State through Public Private Partnership(PPP) arrangements and has entrusted the responsibility to Andhra Pradesh Road Development Corporation (APRDC).

A set of eight State Highways have been selected for four laning under phase-wise programme.

Page 3: Expansion of state highway 1

The project road Hyderabad – Karimnagar – Ramagundam Road (State Highway-1) is 207.400 Km

long and starts from Km. 28.200 in Rangareddy District and ends near

Mancherial (NH-16 Joining point) at Km. 235.600. The project districts

comprises of Rangareddy, Medak, Karimnagar.

Project Road and Area

Page 4: Expansion of state highway 1

Need for the Expansion of SH-1

‘Rajiv Rahadhari’ or State Highway-1 is the lifeline of Karimnagar district as it is not connected to a railway network to Hyderabad.Once it was converted into a double-lane and became ‘Rajiv Rahadari’, the accidents have increased steadily. Reasons were many as it could be due to the high density of vehicular movement, rapid urbanization and industrial activity in the coal belt region. Following the high accident rates, there was a clamor for converting the road into four lane by public representatives, and accordingly, the foundation stone was laid in 2008.

Page 5: Expansion of state highway 1

LOCATION OF PROJECT ROAD

Page 6: Expansion of state highway 1

Budget for the total project

Total cost of the expansion process is Rs1,358.19crore including LA, utility shifting and environmental cost under BOT (Built, Operate and Transfer) process and Concession Period of 15 years.

Page 7: Expansion of state highway 1

Existing Road Features

Page 8: Expansion of state highway 1

Existing Traffic

Mixed traffic flow is observed along the highway. The average daily traffic along HKR Road ranges from the maximum of 20643 PCUs to as low as 16237 PCUs in different sections.

Page 9: Expansion of state highway 1

Proposed Road Features

Alignment proposalPavementGeometric Design

AspectsService RoadsUnderpassesCross Drainage

StructuresDesign of IntersectionsTraffic Control and Road

safety Features

Page 10: Expansion of state highway 1

PAVEMENT

Flexible pavements are proposed for all through out the road except at the toll plazas where rigid pavement is proposed. This is due to the high

cost of construction involved for rigid pavements.

Page 11: Expansion of state highway 1

Geometric Design aspects

The design speed has been kept quite consistent, and speed difference between two consecutive curves is not exceeded. All horizontal curves are designed for 100kmph or 80kmph and the lowest one is 15-35 kmph,

All geometric design aspects have been carried out as per the IRC standards and specifications.

Page 12: Expansion of state highway 1

Underpasses 10 cattle, 6 pedestrian and 5 cattle cum

pedestrian underpasses have been proposed to ease access of local traffic and population

The project road has 7 major bridges and 32 minor bridges. These bridges shall be retained as two lanes and parallel new bridges shall be provided on the new 3-lane portion.

Traffic control devices and road safety features, including Traffic Signs, Road Markings, Road lighting & Crash Barriers are proposed and designed as per relevant IRC codes and standards.

Cross Drainage Structures

Traffic Control and Road safety features

Page 13: Expansion of state highway 1

• Apart from widening to four lanes from the existing 2 lane carriageway, the project have also proposed several other enhancements such as bus-bays, truck lay-byes, toll plazas and Rest areas with Restaurant, toilet facilities, ATM facility, Emergency First Aid, Repair / Maintenance facility, Parking provisions for trucks and cars, PCO and Police outposts.

Page 14: Expansion of state highway 1
Page 15: Expansion of state highway 1
Page 16: Expansion of state highway 1

Organization chart

Page 17: Expansion of state highway 1

o Foundation Stone was laid on : October 25th,2008o Pre-Construction Stage : June 26th 2009o Construction Stage : March 12th,2010o Operation Stage :November 27th 2011o Completion of the project : August 21st 2013.

Page 18: Expansion of state highway 1

Feasibility testsFeasibility tests are to be made so as to confirm

the project is to be processed or not, some of them are

Operational tests.Technical tests.Economic and cost benefit analysis 0.1Area details and Land Acquisition 0.2 Financial details 0.3 Payback Period 0.4 Break Even Analysis 0.5 Net present value 0.6 Benefit Cost Analysis 0.7 Depreciation

Page 19: Expansion of state highway 1

Technical Feasibility

The EIA has been included in project preparation to streamline environmental issues in project design, constructional and operational stages. The scope of the Environmental Assessment (EA) as envisaged in the Terms of Reference (ToR) includes the delivery of a Technical Feasibility Report, which shall contain Environmental Screening and Preliminary Environmental Assessment of the project.

Preliminary Environmental Screening : A Rapid Assessment

Survey (RAS) was undertaken to identify the Valued Ecosystem Components (VECs) during the feasibility stage and were categorised into various environmental components for screening and to assess their subsequent impacts due to the project.

Page 20: Expansion of state highway 1

0.1 Area Details and Land acquisition

Total land required for widening and upgrading the project corridor is” 41.137 ha “of which only 0.955 shall be diverted from forest lands. The rest are to be acquired from private and other government land holdings. The bulk of the land is required for widening and up gradation of the existing road while 4.913 ha of land shall be required for building toll plaza.

Page 21: Expansion of state highway 1

Financial details

Cash outflow :

Total Budget of the project is estimated to be 1358.19crores.

The cash will be given at different phases of the project.

The budget allocated will be strictly considered.

The projected cash outflow may be considered as single payment.

Page 22: Expansion of state highway 1

2014 2015 2016 20170

50

100

150

200

250

300

350

400cash inflow chart

cash inflow chart

Am

ou

nt

in c

rore

s

Years

Page 23: Expansion of state highway 1

Payback Period

Payback period in capital budgeting refers to the period of time required for the return on an investment to "repay" the sum of the original investment. Since the project is done under BOT Process, From the cash inflow, Invested capital is going to be recovered in 4years 2months 15days.

Inflow cash per year : 323.0688 crores

Page 24: Expansion of state highway 1

Net Present Value

NPV can be describes as “difference amounts” between the sums of discounted: cash inflows and cash outflows. It compares the present value of money today to the present value of money in the future, taking inflation and returns into account.

Page 25: Expansion of state highway 1

State highway which is going to be constructed is expected to have a life time of 15 years without any expansion being required in between.

Net present Value =2,458.55crores

As the net present value is greater than the total investment project seems to be feasible.

Page 26: Expansion of state highway 1

Benefit- Cost analysis Just as income and expenses are used in

private sector, so cost benefits are used in public sector to signify the economic consequences of economic decisions.

Net-Benefit cost Ratio = PVB-I/I IF, BCR >1 : Accepted BCR<1 : Rejected Calculated value of BCR for the project = 1402.8

/1358.19 =1.033

Benefit-cost ratio (BCR) = Present value of Benefit (PVB)/Investment

BCR>1, SO ACCEPTED

Page 27: Expansion of state highway 1

Conclusion

Traffic between Hyderabad and karimnagar is heavy, due to lack of train facility between secunderabad and karimnagar.

So conversion of state highway-1 to 4-lane toll pay road is necessary.

Lot of villages are being connected by this road expansion and it is not access controlled as high speed vehicular movement is not possible due to access everywhere.

Page 28: Expansion of state highway 1

References

Page 29: Expansion of state highway 1

THANK YOU