Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September...

23
Examples of Commissioning Examples of Commissioning Cost Savings Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL

Transcript of Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September...

Page 1: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Examples of Commissioning Examples of Commissioning Cost SavingsCost Savings

Commissioning for Sustained Building PerformanceSeptember 29, 2011

MarriottBirmingham, AL

Page 2: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

What Are Trying to Avoid?

Page 3: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Design Team or CxA?

• Chilled water valve is modulating to maintain AHU leaving air temperature at setpoint.

• Chilled water valve is modulating in a stable and uniform manner as required to maintain AHU leaving air temperature at setpoint without offset. Leaving air temperature setpoint is automatically adjusted as required to minimize reheat.

Page 4: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Design Team or CxA?

• Water chillers are sequenced on and off as required to maintain chilled water supply temperature at setpoint.

• Water chillers are sequenced on and off in the most cost-effective manner possible as required to maintain chilled water supply temperature at setpoint and as required to ensure regular exercise of all equipment, automatic response in the event of an equipment failure, and regular exposure of all surfaces to water treatment chemicals.

Page 5: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

TAB or CxA?

• Laboratory space pressure is negative with respect to the corridor during occupied and unoccupied modes of operation.

• Laboratory space pressure is negative with respect to the corridor during occupied and unoccupied modes of operation and during transitions from occupied mode to unoccupied mode and from occupied mode to unoccupied mode.

Page 6: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

TAB or CxA?

• VAV terminal air flow modulates from minimum to maximum air flow settings as required to maintain space temperature at setpoint.

• VAV terminal air flow modulates from minimum to maximum air flow settings as required to maintain space temperature at setpoint. Minimum air flow setting is automatically reset during unoccupied periods to minimize reheat.

Page 7: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Exhaust fan hardwired in an “always on” position [Mittal and Hammond 2008]

Sample Findings

Hot water valve motion impeded by piping layout [EMC no date (a)]

Rust indicates poor anti-condensation heating control setpoints in supermarket refrigeration cabinet [Sellers and Zazzara 2004]

Source: Evan Mills, LBNL, 7/21/2009

Page 8: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Sample Findings

Inadequate fan cooling and excessive fan power due to poor fit between the light fixture and ducting, causing significant duct leakage [Martha Hewett, MNCEE]

Zone damper actuator arm broken (no temperature control) [Martha Hewett, MNCEE]

Source: Evan Mills, LBNL, 7/21/2009

Masonry unit balanced on conduit above door [ASHE]

Page 9: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Sample Findings

Failed window film applications

Building envelope moisture entry [Aldous 2008]

Photosensor “sees” the electric lamps rather than task-plane illumination [Deringer 2008]

Photosensor (for daylight harvesting) shaded by duct [Deringer 2008]

Air leakage in an underfloor air-distribution system [Stum 2008]

Page 10: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Retro-CommissioningRetro-Commissioning

Commissioning for Sustained Building PerformanceSeptember 29, 2011

MarriottBirmingham, AL

Page 11: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Source: Evan Mills, LBNL, 7/21/2009

Page 12: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Retro-Commissioning Process

Page 13: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Process Frequency

Page 14: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Energy Cost Reduction Opportunities

• Utility Rate Analysis• Training and Education• Unbundled Natural Gas Purchasing• Power Factor Correction• Lighting Controls and Retrofits• Weekly Equipment Schedules• Night Set-Back / Night Set-Up• Supply Air Temperature Reset• Minimum Airflow Settings• Free Cooling

Page 15: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Energy Cost Reduction Opportunities

• Building Pressure Control• Variable Speed and Volume Control• Pumping Modifications• Air Terminal Settings• Exhaust Fan Balancing• Energy Management System (EMS) Tuning• Review EMS Graphics

Page 16: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Typical Commissioning Cost

Source: Evan Mills, LBNL, 7/21/2009

Page 17: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Operational Cost Savings

Source: Evan Mills, LBNL, 7/21/2009

Page 18: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Return on Investment

Source: Evan Mills, LBNL, 7/21/2009

Page 19: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Case Study A Item Before After Savings (%) Remarks

Electricity Consumption (kWh) 10,175,200 8,884,600 12.7  

Average Peak Demand (kW) 1,499 1,403 6.4  

Electricity Consumption (kWh/SF/year) 49.9 43.6 12.7 Average is 32 kWh/SF/year

Electricity Load Factor (%) 77 72 6.7  

Average Peak Demand (watts/SF) 7.3 6.9 6.4  

Natural Gas Consumption (MMBtu) 35,507 28,283 20.3  

Natural Gas Consumption (Therms/SF/year)

1.7 1.4 20.3 Average is 1.23 therms/SF/year

Total Energy Consumption (MMBTU) 70,235 58,606 16.6  

Energy Utilization Index (kBTU per SF) 396 330 16.6 Average is 232 kBTU/SF/year

Total Energy Cost ($/year) 1,121,614 801,141 28.6  

Energy Cost Index ($/SF/year) 5.50 3.93 28.6 Average is $2.85/SF

Page 20: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Case Study A Retro-Commissioning Economics

Retro-Commissioning Cost $55,000

ATC Retrofits $353,000

Infrastructure Upgrade $238,000

Total Cost ($) $646,000

Less Electrical Service ($210,000)

Less Water Chiller And Tower ($250,000)

Less Cath Lab AHU ($90,000)

Less CEP Expansion ($218,000)

Net Cost ($) ($122,000)

Page 21: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Case Study BItem Before After Savings (%) Remarks

Electricity Consumption (kWh) 7,808,800 5,249,800 32.8  

Average Peak Demand (kW) 1,230 929 24.5  

Electricity Consumption (kWh/SF/year) 44.0 29.6 32.8 Average is 32 kWh/SF/year

Average Peak Demand (watts/SF) 6.93 5.23 24.5  

Natural Gas Consumption (MMBtu) 43,114 23,523 45.4  

Natural Gas Consumption (Therms/SF/year)

2.43 1.33 45.4 Average is 1.23 therms/SF/year

Total Energy Consumption (MMBTU) 70,137 41,457 40.9  

Energy Utilization Index (kBTU per SF) 393 233 40.6 Average is 232 kBTU/SF/year

Total Energy Cost ($/year) 916,182 540,058 41.1  

Energy Cost Index ($/SF/year) 5.16 3.04 41.1 Average is $2.85/SF

Page 22: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Case Study B Retro-Commissioning Economics

Preliminary Energy Audit $8,350

Phase 1A and 1B $199,439

Total Cost ($) $207,789

Simple Payback ~ 9 Months

Page 23: Examples of Commissioning Cost Savings Commissioning for Sustained Building Performance September 29, 2011 Marriott Birmingham, AL.

Comm

issioning for SustainedCom

missioning for Sustained

Building Performance

Building Performance

Birmingham, AL

Marriott9/29/11

Questions

Michael W. Hardy, PE, LEED® AP, CCP Phone: (678) 254-1206Email: [email protected]