European Developments
description
Transcript of European Developments
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
European Developments
Transmission Workgroup
5th July 2012
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
Gas Balancing Update
Transmission Workgroup
ENTSOG - Current project plan
3
Stakeholder
Workshop
Dec Jan Feb Mar Apr June JulyMayNov Jun JulOct Apr Aug Sep Nov
Invitation from Commission
SubmitNetwork Code
Project launch13/14 Dec 23 SJWS
7-8 SJWS
Consultation
May
Workshop
FG Development of Network Code with stakeholder on the basis of the final Framework Guidelines ACER
2011 2012
Development of draft network code in cooperation with stakeholders ENTSOG
Oct
9 SJWS 26 SJWS
11-12 SJWS
Date Event
12 June 2012 Deadline for responses to the public consultation
26 July 2012 Post-consultation workshop
22 August 2012 Code and supporting document published; Stakeholder process starts
4 September 2012 Stakeholder Support process ends
5 November 2012 Final ENTSOG – drafted Code submitted to ACER
Responses to ENTSOG consultation on draft balancing code
Total of 50 stakeholder responses received by ENTSOG
2 confidential
8 UK
Responses are generally supportive of work done to date
150 issues are being investigated by ENTSOG
Majority of issues are relatively minor in nature
Some text changes will be made as a result of the feedback received
Next steps
ENTSOG response to be presented at Refinement Workshop on 26th July
Legal text to be amended accordingly and will be finalised in August prior to the start of the stakeholder support process in September
EU CAM Network Code and CMP Guideline Update
Transmission Workgroup
Capacity Allocation Mechanisms (CAM) - Update
ACER published Reasoned Opinion no. 04/2012 on CAM 5th June 2012
“.. Generally shows a high degree of compliance with the Agency's Framework Guidelines (FGs).” However.. some specific provisions not in line with the FGs; or with the objectives; or are out of scope.”
Items considered not to be fully in line:
Definitions
Virtual Interconnection points (Entry / Exit systems rather than Transmission networks)
Additional Capacity (CMP definition instead of CAM)
Capacity Contract (Prefer Transport Contract)
Capacity Allocation Mechanisms(CAM) - Update
Application to New Technical Capacity
Code does not include incremental Capacity however opinion considers that incremental Capacity is only exempt from the auction allocation process, allowing for other mechanisms to allocate incremental capacity.
All other sections of the FGs should be applicable to incremental such as
bundling and capacity products / durations should apply.
Standard Contracts
Code defines standardised capacity services and allocation mechanism (FGs defines a standardised content and general T&Cs). Assessment needed to see whether full standardisation can be done due to different national legal frameworks.
Capacity Allocation Mechanisms(CAM) - Update
TSO Cooperation
Code defines the sharing of information with Users. Further details required for TSO to TSO information sharing such as flow forecasts, network availability and potential congestion.
Capacity Breakdown
Concerns expressed that auctioning 90% for 15 years could create barriers for new entrants and suggests no room for ‘learning lessons’
NRAs to review amount of capacity for each long and short term service
Considers that more to be withheld for shorter term horizons (4-5 yrs)
A quarterly product offered more than just year ahead alongside a yearly product would allow Users a ‘second chance’
More flexibility to implement at IP level shorter term (and more stringent) quotas
Needs to be aligned either side of IP
Subject to consultation with Users, TSOs and NRA agreement.
Capacity Allocation Mechanisms (CAM) – Update
Sale of Unbundled Firm Capacity
FG sets out the objective to progressively bundle the entire technical capacity, including new capacity
The offer of unbundled capacity up to 15 yrs may therefore prevent the objective of progressively bundling capacity at IPs
Suggest that limiting the sale of unbundled to, for instance, up to the rolling monthly auction.
Amendment of Existing Capacity Contracts
Amend NRAs “shall” to NRAs “may” mediate.
Capacity Allocation Mechanisms (CAM) – Update
Interruptible Capacity
Justification and NRA approval to reduce interruption lead times below 2 hours
Relationship to Noms / Renoms process in Balancing Code highlighted.
Tariffs
Removal of the Revenue Equivalence Principle
Equal split of premium revenues
Removal of revenue shortfalls and tariff adjustments
Temporary nature of Tariff aspects contained in CAM due to forthcoming Tariff Code.
Capacity Allocation Mechanisms (CAM) – Update
Incentive Regimes
Recognises the merits of incentives when it will have an effect on the cross-border capacity offer, but consider is not necessary to explicitly include in Code.
Interim Period
Removal of the interim period for applying auctions (subject to NRA decision) as the FGs leaves the decision on interim measures to the Comitology process.
Capacity Allocation Mechanisms (CAM) – Update
Initial discussions already held between ENTSOG and ACER & EC
European Commission (EC) expect Comitology to start no later than Dec 2012
Early indication is that ACER & EC consider that opinion should be applied and Code amended
Ongoing ENTSOG analysis into impacts and options currently being considered.
Constraint Management Principles (CMP) Update
CMP approved by Member States at the Comitology meeting on 20th April 2012
GB has to be compliant by 1st October 2013 (July 2016 for Firm Day Ahead UIOLI)
Compliance / Impact Assessment discussed with Ofgem
We understand that Ofgem is also discussing compliance with GB Interconnector Operators.
Constraint Management Principles (CMP) Update
National Grid considering:
How can we make CMP for Oct13 work?
Implications
TSO – TSO cooperation – obligation to work with other TSOs.
Ten Year Network Development Plan 2013 – 2022 Update
Transmission Workgroup
TYNDP Background
As per the 3rd Energy Package, ENTSOG has to produce a European Ten Year Network Development Plan every two years, the last report was published February 2011. The next iteration of the report will cover the period of 2013 to 2022.
The proposed TYNDP improvements are based on 3 different types of feedback received from the previous report
ACER Official Opinion
Main improvements expected in, demand analysis, market integration assessment & stakeholder involvement
Stakeholder Joint Working Sessions
ENTSOG organised 7 sessions between January and May this year around demand, supply, infrastructure projects, security of supply and market integration, these session were attended by a wide range of stakeholders
Bilateral Talks with ENTSOG
ENTSOG are always willing to hold bilateral talks to discuss very detailed points or confidential issues
17
TYNDP Improvements
Demand
Upgraded consistency and transparency in the assumptions and methodologies of the demand scenarios
Attention to power generation dynamics: reviewing the link between the electricity and gas systems
Consideration of EU political goals
Supply
Based on publicly available data, ENTSOG will define a maximum, medium and minimum supply potential by source
Market Integration
The expansion of the supply penetration assessment, investigating in particular to see if every country has physical access to every source, and if not why not.
18
TYNDP Improvements Continued
Security of Supply
Only a slight evolution in the definition of disruptions (especially technical ones) and UGS low deliverability in comparison with TYNDP 2011-2020
Infrastructure
The clustering used for modelling will remain based on 2 scenarios: “existing infra. + FID” & “Existing infra. + FID + non-FID” combined with 3 dates: 2013, 2017 & 2022
At a recent TYNDP Workshop, ENTSOG produced 61 slides on the new TYNDP Concept, it is important to highlight there is a wealth of information available to those that want to know more on the ENTSOG website.
http://www.entsog.eu/events/TYNDP5/presented.html
19
TYNDP Next steps Now to Mid-September is the data collection period
All data has to be collected by mid-September 2012.
ENTSOG will gather the supply and demand data, whilst the TSOs’ will submit their infrastructure projects
Third-party (non-TSO) infrastructure project collection is now officially available
From Mid-September to December macro-analysis and simulations to be completed
ENTSOG will analyse the supply and demand scenarios at European level
200 cases will be modelled and analysed
ENTSOG will then produce the report focusing on the clarity of the results
Finally from January to February the report to be approved and published
A major report like the TYNDP requires extensive internal approval
Targeted public release for February 2013 opening a 3-month formal consultation period before submission to the ACER
20
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
EU Incremental Capacity
Transmission Workgroup
Incremental Capacity
Council of European Energy Regulators (CEER) have started work on “Identification and Allocation of Incremental Capacity”
Looking at in the context of existing Gas Target Model, EC Energy Infrastructure Proposal, & CAM Framework Guideline
ENTSOG have started preliminary consideration
National Grid will fully participate in process and look to share experience of GB model
Further update when CEER views / plans are made available.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
Interoperability & Data Exchange Update
Transmission Workgroup
EU Interoperability & Data Exchange Code
ACER’s consultation on Framework Guidelines has concluded
National Grid NTS’ response was summarised at last month’s meeting
We expect the following to be completed in July:
ACER’s final Framework Guideline proposals
ACER’s evaluation of consultation responses
Impact Assessment produced by ACER’s consultant
ENTSOG is preparing its Project Plan and Launch Documentation
The 12 month period for Code development is expected to commence in early September 2012