Eqp Foundation
Transcript of Eqp Foundation
-
7/29/2019 Eqp Foundation
1/41
20-06-13
Date
Copyright 2010 Larsen and Toubro, Mumbai. All Rights Reserved.
Larsen and Toubro
Powai CampusDoc No. : L&T/RIL/AEP/44PS4800/C/201 Revision No. : 0
PROJECT
132KV AIS SWITCHYARD PACKAGE - DATA CENTRE - NAGPUR
Owner : RELIANCE INDUSTRIES LTD
DESIGN OF EQUIPMENT FOUNDATION
FOR CT, PT, LA AND BPI
Owner's Consultant : JACOBS
Revision Prpd By Chkd By
Consultant : Alif Engineers & Planners, Mumbai
Project No : 44PS4800
R0 ASK SA
-
7/29/2019 Eqp Foundation
2/41
-
7/29/2019 Eqp Foundation
3/41
Normal SCF
Maximum vertical load at PL = 0.530 Ton 0.530 Ton
Maximum shear at PL = 0.216 Ton 0.200 Ton
Maximum moment at PL = 0.434 Tm 0.940 Tm
Back to Back of angles in elevation = 0.500 m
Back to Back of angles in side view = 0.500 m
CG of vert angle = 1.41 cm
Design Data:
Dep th o f Foundation = 2 m
Depth of filling 0 m
Safe Bearing capacity of soil = 11 t/m2
Density of soil = 1.7 t/m3
Gross Bearing capacity of soil = 11 x 1.25 + 1.7
x 2
= 17.15 t/m2
Grade of concrete = 30
Density of concrete = 2.5 t/m3
Reinforcement yield stress = 500 N/mm2
FOS = 2 1.5 (SCF)
Coefficient of friction between soil&conc = 0.6
Angle of repose = 6 degrees
0.3
2.0
0.2
1.30
ALIF ENGINEERS AND PLANNERS Design calculation LA FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/201
REV R0
Larsen and Toubro 3
-
7/29/2019 Eqp Foundation
4/41
ALIF ENGINEERS AND PLANNERS Design calculation LA FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/201
REV R0
Assume size of raft as follows
L = 1.30 m
B = 1.30 m
t = 0.2 m
Depth of foundation from FGL D = 2.0 m
Pedestal size pxp = 0.70 m x 0.700 m
Plinth level from FGL = 0.30 m
Height of pedestal = 2.1 m
SCF
Factored Longitudinal moment at base M = 1.86 tm 2.1 tm
Height of soil = 1.80 m
Calculation of down thrust
Weight of raft w1 = 1.3 x 1.3 x 0.2
x 2.5
= 0.845 t
Weight of pedestal w2 = 0.7 x 0.7 x 2.1
x 2.5 x 2
= 5.15 t
Total wr = 5.99 t
Weight of soil ws = ( 1.3 x 1.3 ) - ( 1 x 0.7
x 0.7 ) x ( 1.8 x 1.7 )
ws = 3.67 t
Vertical load Equip + str = 0.53 t 0.53 t
Factored Total vertical load P = 20.38 t 15.29 t
Unfactored loads = 10.19 t 10.19 t
Check for eccentricity,bearing pressure &overturning
Maximum soil pressure p1 (Considering unfactored loads) = 6.03 + 2.54
= 8.57 t/m2< 17.15 SAFE
F.O.S against overturning = 20.38 x 1.3 / 2
= 1.86
= 7.12 > 1.5 SAFE
F.O.S against sliding = 15.29 x 0.6
0.216= 42.47 > 1.5 SAFE
F.O.S against overturning = 15.29 x 1.3 / 2
SCF Cond = 2.10
= 4.73 > 1.5 SAFE
F.O.S against sliding = 15.29 x 0.6
SCF Cond 0.200
= 45.86 > 1.5 SAFE
Larsen and Toubro 4
-
7/29/2019 Eqp Foundation
5/41
ALIF ENGINEERS AND PLANNERS Design calculation LA FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/201
REV R0
Design of bottom pad
Downward pressure to concrete = 0.2 x 2.5
= 0.5 t/m
Downward pressure due to earth = 1.8 x 1.7
= 3.06 T/m
Net upward pressure on pad = 8.57 - 3.56
= 5.01 t/m
Maximum overhang = 1.3 - 0.70
2
= 0.3 m
Maximum bending moment = 5.01 x 0.32
2
= 0.23 tm
Factored maximum moment = 0.23 x 2
= 0.34 tm
Effective depth d = 145 mm
Mu/bd2 = 3319338
1000 x 1452
= 0.16 N/mm2
% steel = 0.036 %
Minimum % steel = 0.12 %
Ast required = 174.00 mm
Assume diameter of bars as = 10 mm
centre to centre spacing = 200 mm OK
Ast provided = 392.6 mm2
Hence provide 10 mm @ 200 mm c/c at Top and Bottom
Check for shear:-
one way shear
Maximum shear at a distance "d" from the face of the column
Overhang from the face of the column = 0.3 - 0.145
= 0.155 m
Shear force = 5.01 x 0.155
= 0.78 t/m
Factored Shear force Vu = 1.55 t
Maximum shear stress Tv = 15540
1000 x 145
= 0.11 N/mm2
For pt '= 0.27
b factor = 12.86
Permissible shear stress = t c = 0.38 N/mm2 SAFE
Larsen and Toubro 5
-
7/29/2019 Eqp Foundation
6/41
ALIF ENGINEERS AND PLANNERS Design calculation LA FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/201
REV R0
Two way shear
Critrical section at d/2 from face of pedestal = 72.5 mm
Perimeter for fractured pyramid = 2 * (B1+d+L1+d) = 3090 mm
Area of fractured pyramid = (B1+d) * (L1+d) = 0.714025 m2
Punching shear = V = (1-Pyramid Area/Area of footing) * P Max
= 2.895 Ton
Eff depth at critical section 145 mm
Shear stress = Vu / (Perimeter * Min Depth) = 0.10 N/MM2
Allowable shear stress = 0.25 * SQRT(Fck) = 1.37 N/MM2
HENCE SAFE
Design of Pedestal
Pedestal size = 0.7 m x 0.70 m
Vertical load on pedestal = 20.384 t
self weight of pedestal = 2.1 x 0.7 x 0.7
x 2.5= 2.57 t
Total vertical load = 22.96 t
shear at plinth level = 0.22 t
Moment at the base of the pedestal 0.22 x ( 2.3 - 0.2 )
= 0.45 tm
0.3
2 0.70
10 mm @ 200 mm c/c @Bottom
0.2
1.3 m x 1.3 m
Factored Total vertical load = 45.91 t
Factored Moment at the base of the pedestal = 0.91 tm
Larsen and Toubro 6
-
7/29/2019 Eqp Foundation
7/41
ALIF ENGINEERS AND PLANNERS Design calculation LA FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/201
REV R0
A. COMPRESSION WITH BENDING
lef = 2.1 x 2 4.20 m
lef / D = 6.00 < 12 Short Column
Total Moment = 0.91 + 0.00 = 0.91 Tm
Since Load is is very less only minimum reinforcement as per cl. 25.5.3(g) of IS 456 will be required.
Concrete area required to resist direct vertical load= 45.91 x 10000
0.36 x 30.00
= 42512.04 mm2
Minimum Ast required = 0.8 % of the concrete area required to resist direct vertical load
= 0.80 x 42512.04 = 340.10 mm2
100.00
Provide longitudinal reinforcement of 12 nos 12 dia
Ast Provided = 1356.48 mm2
Spacing between reinforcement = 206.67 < 300.00 OK
Design for lateral ties :
Spacing of lateral ties shall be least of the following :-
I) Least lateral dimn of column = 700.00 mm
ii) 16 x dia of longitudinal reinf = 16.00 x 12.00 = 192.00 mm
iii) 48 x dia of transverse reinforcement= 48.00 x 8.00 = 384.00 mm
Privide 8mm ties at 190 mm c/c.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
Larsen and Toubro 7
-
7/29/2019 Eqp Foundation
8/41
Normal SCF
Maximum vertical load at PL = 0.530 Ton 0.530 Ton
Maximum shear at PL = 0.207 Ton 0.501 Ton
Maximum moment at PL = 0.434 Tm 2.335 Tm
Back to Back of angles in elevation = 0.400 m
Back to Back of angles in side view = 0.400 m
CG of vert angle = 1.41 cm
Design Data:
Depth o f Foundation = 2 m
Depth of filling 0 m
Safe Bearing capacity of soil = 11 t/m2
Density of soil = 1.7 t/m3
Gross Bearing capacity of soil = 11 x 1.25 + 1.7
x 2
= 17.15 t/m2
Grade of concrete = 30
Density of concrete = 2.5 t/m3
Reinforcement yield stress = 500 N/mm2
FOS = 2 1.5 (SCF)
Coefficient of friction between soil&conc = 0.6
Angle of repose = 6 degrees
ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Larsen and Toubro 8
-
7/29/2019 Eqp Foundation
9/41
ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
0.3
2.0
0.2
1.30
Assume size of raft as follows
L = 1.30 m
B = 1.30 m
t = 0.2 m
Depth of foundation from FGL D = 2.0 m
Pedestal size pxp = 0.60 m x 0.600 m
Plinth level from FGL = 0.30 m
Height of pedestal = 2.1 m
SCF
Factored Longitudinal moment at base M = 1.82 tm 5.23095 tm
Height of soil = 1.80 m
Calculation of down thrust
Weight of raft w1 = 1.3 x 1.3 x 0.2
x 2.5
= 0.845 t
Weight of pedestal w2 = 0.6 x 0.6 x 2.1
x 2.5 x 2
= 3.78 t
Total wr = 4.63 t
Weight of soil ws = ( 1.3 x 1.3 ) - ( 1 x 0.6
x 0.6 ) x ( 1.8 x 1.7
ws = 4.07 t
Vertical load Equip + str = 0.53 t 0.53 t
Factored Total vertical load P = 18.45 t 13.84 t
Unfactored loads = 9.22 t 9.22 t
Check for eccentricity,bearing pressure &overturning
Maximum soil pressure p1 (Considering unfactored loads) = 5.46 + 2.49
= 7.94 t/m2< 17.15 SAFE
F.O.S against overturning = 18.45 x 1.3 / 2
= 1.82
= 6.59 > 1.5 SAFE
Larsen and Toubro 9
-
7/29/2019 Eqp Foundation
10/41
ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
F.O.S against sliding = 13.84 x 0.6
0.207
= 40.11 > 1.5 SAFE
F.O.S against overturning = 13.84 x 1.3 / 2
SCF Cond = 5.23
= 1.72 > 1.5 SAFE
F.O.S against sliding = 13.84 x 0.6
SCF Cond 0.501
= 16.57 > 1.5 SAFE
Design of bottom pad
Downward pressure to concrete = 0.2 x 2.5
= 0.5 t/m2
Downward pressure due to earth = 1.8 x 1.7
= 3.06 T/m2
Net upward pressure on pad = 7.94 - 3.56= 4.38 t/m
2
Maximum overhang = 1.3 - 0.60
2
= 0.35 m
Maximum bending moment = 4.38 x 0.352
2
= 0.27 tm
Factored maximum moment = 0.27 x 2
= 0.40 tmEffective depth d = 145 mm
Mu/bd2 = 3951219
1000 x 1452
= 0.19 N/mm2
% steel = 0.043 %
Minimum % steel = 0.12 %
Ast required = 174.00 mm2
Assume diameter of bars as = 10 mm
centre to centre spacing = 200 mm OK
Ast provided = 392.6 mm2
Hence provide 10 mm @ 200 mm c/c at Top and Bottom
Larsen and Toubro 10
-
7/29/2019 Eqp Foundation
11/41
ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Check for shear:-
one way shear
Maximum shear at a distance "d" from the face of the column
Overhang from the face of the column = 0.35 - 0.145
= 0.205 m
Shear force = 4.38 x 0.205
= 0.90 t/m
Factored Shear force Vu = 1.80 t
Maximum shear stress Tv = 17974
1000 x 145
= 0.12 N/mm2
For pt '= 0.27
b factor = 12.86
Permissible shear stress = t c = 0.38 N/mm2 SAFE
Two way shear
Critrical section at d/2 from face of pedestal = 72.5 mm
Perimeter for fractured pyramid = 2 * (B1+d+L1+d) = 2690 mm
Area of fractured pyramid = (B1+d) * (L1+d) = 0.555025 m2
Punching shear = V = (1-Pyramid Area/Area of footing) * P Max
= 2.944 Ton
Eff depth at critical section 145 mm
Shear stress = Vu / (Perimeter * Min Depth) = 0.11 N/MM2
Allowable shear stress = 0.25 * SQRT(Fck) = 1.37 N/MM2
HENCE SAFE
Design of Pedestal
Pedestal size = 0.6 m x 0.60 m
Vertical load on pedestal = 18.450 t
self weight of pedestal = 2.1 x 0.6 x 0.6
x 2.5
= 1.89 t
Total vertical load = 20.34 t
shear at plinth level = 0.21 t
Moment at the base of the pedestal 0.21 x ( 2.3 - 0.2
= 0.43 tm
0.3
2 0.60
10 mm @ 200 mm c/c @Bottom
0.2
1.3 m x 1.3 m
Larsen and Toubro 11
-
7/29/2019 Eqp Foundation
12/41
ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Factored Total vertical load = 40.68 t
Factored Moment at the base of the pedestal = 0.87 tm
A. COMPRESSION WITH BENDING
lef = 2.1 x 2 4.20 m
lef / D = 7.00 < 12 Short Column
Total Moment = 0.87 + 0.00 = 0.87 Tm
Since Load is is very less only minimum reinforcement as per cl. 25.5.3(g) of IS 456 will be required.
Concrete area required to resist direct vertical load= 40.68 x 10000
0.36 x 30.00
= 37665.93 mm2
Minimum Ast required = 0.8 % of the concrete area required to resist direct vertical load
= 0.80 x 37665.93 = 301.33 mm2
100.00
Provide longitudinal reinforcement of 12 nos 12 dia
Ast Provided = 1356.48 mm2
Spacing between reinforcement = 173.33 < 300.00 OK
Design for lateral ties :
Spacing of lateral ties shall be least of the following :-
I) Least lateral dimn of column = 600.00 mm
ii) 16 x dia of longitudinal reinf = 16.00 x 12.00 = 192.00 mm
iii) 48 x dia of transverse reinforcement= 48.00 x 8.00 = 384.00 mm
Privide 8mm ties at 190 mm c/c.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
Larsen and Toubro 12
-
7/29/2019 Eqp Foundation
13/41
ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Larsen and Toubro 13
-
7/29/2019 Eqp Foundation
14/41
01
Larsen and Toubro 14
-
7/29/2019 Eqp Foundation
15/41
01
)
Larsen and Toubro 15
-
7/29/2019 Eqp Foundation
16/41
01
Larsen and Toubro 16
-
7/29/2019 Eqp Foundation
17/41
01
)
Larsen and Toubro 17
-
7/29/2019 Eqp Foundation
18/41
01
Larsen and Toubro 18
-
7/29/2019 Eqp Foundation
19/41
01
Larsen and Toubro 19
-
7/29/2019 Eqp Foundation
20/41
Normal SCF
Maximum vertical load at PL = 1.010 Ton 1.010 Ton
Maximum shear at PL = 0.246 Ton 0.175 Ton
Maximum moment at PL = 0.514 Tm 0.823 Tm
Back to Back of angles in elevation = 0.700 m
Back to Back of angles in side view = 0.700 m
CG of vert angle = 1.41 cm
Design Data:
Depth o f Foundation = 2 m
Depth of filling 0 m
Safe Bearing capacity of soil = 11 t/m2
Density of soil = 1.7 t/m3
Gross Bearing capacity of soil = 11 x 1.25 + 1.7
x 2
= 17.15 t/m2
Grade of concrete = 30
Density of concrete = 2.5 t/m3
Reinforcement yield stress = 500 N/mm2
FOS = 2 1.5 (SCF)
Coefficient of friction between soil&conc = 0.6
Angle of repose = 6 degrees
0.3
2.0
0.2
1.30
ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Larsen and Toubro 20
-
7/29/2019 Eqp Foundation
21/41
ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Assume size of raft as follows
L = 1.30 m
B = 1.30 m
t = 0.2 m
Depth of foundation from FGL D = 2.0 m
Pedestal size pxp = 0.850 m x 0.850 m
Plinth level from FGL = 0.30 m
Height of pedestal = 2.1 m
SCF
Factored Longitudinal moment at base M = 2.16 tm 1.83825 tm
Height of soil = 1.80 m
Calculation of down thrust
Weight of raft w1 = 1.3 x 1.3 x 0.2
x 2.5
= 0.845 t
Weight of pedestal w2 = 0.85 x 0.85 x 2.1
x 2.5 x 2
= 7.59 t
Total wr = 8.43 t
Weight of soil ws = ( 1.3 x 1.3 ) - ( 1 x 0.85
x 0.85 ) x ( 1.8 x 1.7
ws = 2.96 t
Vertical load Equip + str = 1.01 t 1.01 t
Factored Total vertical load P = 24.80 t 18.60 t
Unfactored loads = 12.40 t 12.40 t
Check for eccentricity,bearing pressure &overturning
Maximum soil pressure p1 (Considering unfactored loads) = 7.34 + 2.95
= 10.29 t/m2< 17.15 SAFE
F.O.S against overturning = 24.80 x 1.3 / 2
= 2.16
= 7.47 > 1.5 SAFE
F.O.S against sliding = 18.60 x 0.60.246
= 45.37 > 1.5 SAFE
F.O.S against overturning = 18.60 x 1.3 / 2
SCF Cond = 1.84
= 6.58 > 1.5 SAFE
F.O.S against sliding = 18.60 x 0.6
SCF Cond 0.175
= 63.78 > 1.5 SAFE
Larsen and Toubro 21
-
7/29/2019 Eqp Foundation
22/41
ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Design of bottom pad
Downward pressure to concrete = 0.2 x 2.5
= 0.5 t/m2
Downward pressure due to earth = 1.8 x 1.7
= 3.06 T/m
2
Net upward pressure on pad = 10.29 - 3.56
= 6.73 t/m2
Maximum overhang = 1.3 - 0.85
2
= 0.225 m
Maximum bending moment = 6.73 x 0.2252
2
= 0.17 tm
Factored maximum moment = 0.17 x 2
= 0.26 tmEffective depth d = 145 mm
Mu/bd2 = 2505731
1000 x 1452
= 0.12 N/mm2
% steel = 0.027 %
Minimum % steel = 0.12 %
Ast required = 174.00 mm2
Assume diameter of bars as = 10 mm
centre to centre spacing = 200 mm OK
Ast provided = 392.6 mm2
Hence provide 10 mm @ 200 mm c/c at Top and Bottom
Check for shear:-
one way shear
Maximum shear at a distance "d" from the face of the column
Overhang from the face of the column = 0.225 - 0.145
= 0.08 mShear force = 6.73 x 0.08
= 0.54 t/m
Factored Shear force Vu = 1.08 t
Maximum shear stress Tv = 10764
1000 x 145
= 0.07 N/mm2
For pt '= 0.27
b factor = 12.86
Permissible shear stress = t c = 0.38 N/mm2 SAFE
Larsen and Toubro 22
-
7/29/2019 Eqp Foundation
23/41
ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Two way shear
Critrical section at d/2 from face of pedestal = 72.5 mm
Perimeter for fractured pyramid = 2 * (B1+d+L1+d) = 3690 mm
Area of fractured pyramid = (B1+d) * (L1+d) = 0.990025 m2
Punching shear = V = (1-Pyramid Area/Area of footing) * P Max
= 2.786 Ton
Eff depth at critical section 145 mm
Shear stress = Vu / (Perimeter * Min Depth) = 0.08 N/MM2
Allowable shear stress = 0.25 * SQRT(Fck) = 1.37 N/MM2
HENCE SAFE
Design of Pedestal
Pedestal size = 0.85 m x 0.85 m
Vertical load on pedestal = 24.804 t
self weight of pedestal = 2.1 x 0.9 x 0.9x 2.5
= 3.79 t
Total vertical load = 28.60 t
shear at plinth level = 0.25 t
Moment at the base of the pedestal 0.25 x ( 2.3 - 0.2
= 0.52 tm
0.3
2 0.8510 mm @ 200 mm c/c @Bottom
0.2
1.3 m x 1.3 m
Factored Total vertical load = 57.19 t
Factored Moment at the base of the pedestal = 1.03 tm
Larsen and Toubro 23
-
7/29/2019 Eqp Foundation
24/41
ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
A. COMPRESSION WITH BENDING
lef = 2.1 x 2 4.20 m
lef / D = 4.94 < 12 Short Column
Total Moment = 1.03 + 0.00 = 1.03 Tm
Since Load is is very less only minimum reinforcement as per cl. 25.5.3(g) of IS 456 will be required.
Concrete area required to resist direct vertical load= 57.19 x 10000
0.36 x 30.00
= 52956.90 mm2
Minimum Ast required = 0.8 % of the concrete area required to resist direct vertical load
= 0.80 x 52956.90 = 423.66 mm2
100.00
Provide longitudinal reinforcement of 12 nos 12 dia
Ast Provided = 1356.48 mm2
Spacing between reinforcement = 256.67 < 300.00 OK
Design for lateral ties :
Spacing of lateral ties shall be least of the following :-
I) Least lateral dimn of column = 850.00 mm
ii) 16 x dia of longitudinal reinf = 16.00 x 12.00 = 192.00 mm
iii) 48 x dia of transverse reinforcement= 48.00 x 8.00 = 384.00 mm
Privide 8mm ties at 190 mm c/c.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
Larsen and Toubro 24
-
7/29/2019 Eqp Foundation
25/41
ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Larsen and Toubro 25
-
7/29/2019 Eqp Foundation
26/41
01
Larsen and Toubro 26
-
7/29/2019 Eqp Foundation
27/41
01
)
Larsen and Toubro 27
-
7/29/2019 Eqp Foundation
28/41
01
Larsen and Toubro 28
-
7/29/2019 Eqp Foundation
29/41
01
)
Larsen and Toubro 29
-
7/29/2019 Eqp Foundation
30/41
01
Larsen and Toubro 30
-
7/29/2019 Eqp Foundation
31/41
01
Larsen and Toubro 31
-
7/29/2019 Eqp Foundation
32/41
Normal SCF
Maximum vertical load at PL = 0.930 Ton 0.930 Ton
Maximum shear at PL = 0.228 Ton 0.175 Ton
Maximum moment at PL = 0.493 Tm 0.823 Tm
Back to Back of angles in elevation = 0.500 m
Back to Back of angles in side view = 0.500 m
CG of vert angle = 1.41 cm
Design Data:
Depth o f Foundation = 2 m
Depth of filling 0 m
Safe Bearing capacity of soil = 11 t/m2
Density of soil = 1.7 t/m3
Gross Bearing capacity of soil = 11 x 1.25 + 1.7
x 2
= 17.15 t/m2
Grade of concrete = 30
Density of concrete = 2.5 t/m3
Reinforcement yield stress = 500 N/mm2
FOS = 2 1.5 (SCF)
Coefficient of friction between soil&conc = 0.6
Angle of repose = 6 degrees
0.3
2.0
0.2
1.30
ALIF ENGINEERS AND PLANNERS Design calculation PT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Larsen and Toubro 32
-
7/29/2019 Eqp Foundation
33/41
ALIF ENGINEERS AND PLANNERS Design calculation PT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Assume size of raft as follows
L = 1.30 m
B = 1.30 m
t = 0.2 m
Depth of foundation from FGL D = 2.0 m
Pedestal size pxp = 0.70 m x 0.700 m
Plinth level from FGL = 0.30 m
Height of pedestal = 2.1 m
SCF
Factored Longitudinal moment at base M = 2.03 tm 1.83825 tm
Height of soil = 1.80 m
Calculation of down thrust
Weight of raft w1 = 1.3 x 1.3 x 0.2
x 2.5
= 0.845 t
Weight of pedestal w2 = 0.7 x 0.7 x 2.1
x 2.5 x 2
= 5.15 t
Total wr = 5.99 t
Weight of soil ws = ( 1.3 x 1.3 ) - ( 1 x 0.7
x 0.7 ) x ( 1.8 x 1.7
ws = 3.67 t
Vertical load Equip + str = 0.93 t 0.93 t
Factored Total vertical load P = 21.18 t 15.89 t
Unfactored loads = 10.59 t 10.59 t
Check for eccentricity,bearing pressure &overturning
Maximum soil pressure p1 (Considering unfactored loads) = 6.27 + 2.78
= 9.05 t/m2< 17.15 SAFE
F.O.S against overturning = 21.18 x 1.3 / 2
= 2.03
= 6.77 > 1.5 SAFE
F.O.S against sliding = 15.89 x 0.60.228
= 41.81 > 1.5 SAFE
F.O.S against overturning = 15.89 x 1.3 / 2
SCF Cond = 1.84
= 5.62 > 1.5 SAFE
F.O.S against sliding = 15.89 x 0.6
SCF Cond 0.175
= 54.47 > 1.5 SAFE
Larsen and Toubro 33
-
7/29/2019 Eqp Foundation
34/41
ALIF ENGINEERS AND PLANNERS Design calculation PT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Design of bottom pad
Downward pressure to concrete = 0.2 x 2.5
= 0.5 t/m2
Downward pressure due to earth = 1.8 x 1.7
= 3.06 T/m
2
Net upward pressure on pad = 9.05 - 3.56
= 5.49 t/m2
Maximum overhang = 1.3 - 0.70
2
= 0.3 m
Maximum bending moment = 5.49 x 0.32
2
= 0.25 tm
Factored maximum moment = 0.25 x 2
= 0.37 tmEffective depth d = 145 mm
Mu/bd2 = 3632673
1000 x 1452
= 0.17 N/mm2
% steel = 0.040 %
Minimum % steel = 0.12 %
Ast required = 174.00 mm2
Assume diameter of bars as = 10 mm
centre to centre spacing = 200 mm OK
Ast provided = 392.6 mm2
Hence provide 10 mm @ 200 mm c/c at Top and Bottom
Check for shear:-
one way shear
Maximum shear at a distance "d" from the face of the column
Overhang from the face of the column = 0.3 - 0.145
= 0.155 mShear force = 5.49 x 0.155
= 0.85 t/m
Factored Shear force Vu = 1.70 t
Maximum shear stress Tv = 17007
1000 x 145
= 0.12 N/mm2
For pt '= 0.27
b factor = 12.86
Permissible shear stress = t c = 0.38 N/mm2 SAFE
Larsen and Toubro 34
-
7/29/2019 Eqp Foundation
35/41
ALIF ENGINEERS AND PLANNERS Design calculation PT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
Two way shear
Critrical section at d/2 from face of pedestal = 72.5 mm
Perimeter for fractured pyramid = 2 * (B1+d+L1+d) = 3090 mm
Area of fractured pyramid = (B1+d) * (L1+d) = 0.714025 m2
Punching shear = V = (1-Pyramid Area/Area of footing) * P Max
= 3.168 Ton
Eff depth at critical section 145 mm
Shear stress = Vu / (Perimeter * Min Depth) = 0.11 N/MM2
Allowable shear stress = 0.25 * SQRT(Fck) = 1.37 N/MM2
HENCE SAFE
Design of Pedestal
Pedestal size = 0.7 m x 0.70 m
Vertical load on pedestal = 21.184 t
self weight of pedestal = 2.1 x 0.7 x 0.7
x 2.5
= 2.57 tTotal vertical load = 23.76 t
shear at plinth level = 0.23 t
Moment at the base of the pedestal 0.23 x ( 2.3 - 0.2
= 0.48 tm
0.3
2 0.70
10 mm @ 200 mm c/c @Bottom
0.2
1.3 m x 1.3 m
Factored Total vertical load = 47.51 t
Factored Moment at the base of the pedestal = 0.96 tm
Larsen and Toubro 35
-
7/29/2019 Eqp Foundation
36/41
ALIF ENGINEERS AND PLANNERS Design calculation PT FoundationDOC.NO:
L&T/RIL/AEP/44PS4800/C/
REV R0
A. COMPRESSION WITH BENDING
lef = 2.1 x 2 4.20 m
lef / D = 6.00 < 12 Short Column
Total Moment = 0.96 + 0.00 = 0.96 Tm
Since Load is is very less only minimum reinforcement as per cl. 25.5.3(g) of IS 456 will be required.
Concrete area required to resist direct vertical load= 47.51 x 10000
0.36 x 30.00
= 43993.52 mm2
Minimum Ast required = 0.8 % of the concrete area required to resist direct vertical load
= 0.80 x 43993.52 = 351.95 mm2
100.00
Provide longitudinal reinforcement of 12 nos 12 dia
Ast Provided = 1356.48 mm2
Spacing between reinforcement = 206.67 < 300.00 OK
Design for lateral ties :
Spacing of lateral ties shall be least of the following :-
I) Least lateral dimn of column = 700.00 mmii) 16 x dia of longitudinal reinf = 16.00 x 12.00 = 192.00 mm
iii) 48 x dia of transverse reinforcement= 48.00 x 8.00 = 384.00 mm
Privide 8mm ties at 190 mm c/c.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
Larsen and Toubro 36
-
7/29/2019 Eqp Foundation
37/41
01
Larsen and Toubro 37
-
7/29/2019 Eqp Foundation
38/41
01
)
Larsen and Toubro 38
-
7/29/2019 Eqp Foundation
39/41
01
Larsen and Toubro 39
-
7/29/2019 Eqp Foundation
40/41
01
)
Larsen and Toubro 40
-
7/29/2019 Eqp Foundation
41/41
01