Eqp Foundation

download Eqp Foundation

of 41

Transcript of Eqp Foundation

  • 7/29/2019 Eqp Foundation

    1/41

    20-06-13

    Date

    Copyright 2010 Larsen and Toubro, Mumbai. All Rights Reserved.

    Larsen and Toubro

    Powai CampusDoc No. : L&T/RIL/AEP/44PS4800/C/201 Revision No. : 0

    PROJECT

    132KV AIS SWITCHYARD PACKAGE - DATA CENTRE - NAGPUR

    Owner : RELIANCE INDUSTRIES LTD

    DESIGN OF EQUIPMENT FOUNDATION

    FOR CT, PT, LA AND BPI

    Owner's Consultant : JACOBS

    Revision Prpd By Chkd By

    Consultant : Alif Engineers & Planners, Mumbai

    Project No : 44PS4800

    R0 ASK SA

  • 7/29/2019 Eqp Foundation

    2/41

  • 7/29/2019 Eqp Foundation

    3/41

    Normal SCF

    Maximum vertical load at PL = 0.530 Ton 0.530 Ton

    Maximum shear at PL = 0.216 Ton 0.200 Ton

    Maximum moment at PL = 0.434 Tm 0.940 Tm

    Back to Back of angles in elevation = 0.500 m

    Back to Back of angles in side view = 0.500 m

    CG of vert angle = 1.41 cm

    Design Data:

    Dep th o f Foundation = 2 m

    Depth of filling 0 m

    Safe Bearing capacity of soil = 11 t/m2

    Density of soil = 1.7 t/m3

    Gross Bearing capacity of soil = 11 x 1.25 + 1.7

    x 2

    = 17.15 t/m2

    Grade of concrete = 30

    Density of concrete = 2.5 t/m3

    Reinforcement yield stress = 500 N/mm2

    FOS = 2 1.5 (SCF)

    Coefficient of friction between soil&conc = 0.6

    Angle of repose = 6 degrees

    0.3

    2.0

    0.2

    1.30

    ALIF ENGINEERS AND PLANNERS Design calculation LA FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/201

    REV R0

    Larsen and Toubro 3

  • 7/29/2019 Eqp Foundation

    4/41

    ALIF ENGINEERS AND PLANNERS Design calculation LA FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/201

    REV R0

    Assume size of raft as follows

    L = 1.30 m

    B = 1.30 m

    t = 0.2 m

    Depth of foundation from FGL D = 2.0 m

    Pedestal size pxp = 0.70 m x 0.700 m

    Plinth level from FGL = 0.30 m

    Height of pedestal = 2.1 m

    SCF

    Factored Longitudinal moment at base M = 1.86 tm 2.1 tm

    Height of soil = 1.80 m

    Calculation of down thrust

    Weight of raft w1 = 1.3 x 1.3 x 0.2

    x 2.5

    = 0.845 t

    Weight of pedestal w2 = 0.7 x 0.7 x 2.1

    x 2.5 x 2

    = 5.15 t

    Total wr = 5.99 t

    Weight of soil ws = ( 1.3 x 1.3 ) - ( 1 x 0.7

    x 0.7 ) x ( 1.8 x 1.7 )

    ws = 3.67 t

    Vertical load Equip + str = 0.53 t 0.53 t

    Factored Total vertical load P = 20.38 t 15.29 t

    Unfactored loads = 10.19 t 10.19 t

    Check for eccentricity,bearing pressure &overturning

    Maximum soil pressure p1 (Considering unfactored loads) = 6.03 + 2.54

    = 8.57 t/m2< 17.15 SAFE

    F.O.S against overturning = 20.38 x 1.3 / 2

    = 1.86

    = 7.12 > 1.5 SAFE

    F.O.S against sliding = 15.29 x 0.6

    0.216= 42.47 > 1.5 SAFE

    F.O.S against overturning = 15.29 x 1.3 / 2

    SCF Cond = 2.10

    = 4.73 > 1.5 SAFE

    F.O.S against sliding = 15.29 x 0.6

    SCF Cond 0.200

    = 45.86 > 1.5 SAFE

    Larsen and Toubro 4

  • 7/29/2019 Eqp Foundation

    5/41

    ALIF ENGINEERS AND PLANNERS Design calculation LA FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/201

    REV R0

    Design of bottom pad

    Downward pressure to concrete = 0.2 x 2.5

    = 0.5 t/m

    Downward pressure due to earth = 1.8 x 1.7

    = 3.06 T/m

    Net upward pressure on pad = 8.57 - 3.56

    = 5.01 t/m

    Maximum overhang = 1.3 - 0.70

    2

    = 0.3 m

    Maximum bending moment = 5.01 x 0.32

    2

    = 0.23 tm

    Factored maximum moment = 0.23 x 2

    = 0.34 tm

    Effective depth d = 145 mm

    Mu/bd2 = 3319338

    1000 x 1452

    = 0.16 N/mm2

    % steel = 0.036 %

    Minimum % steel = 0.12 %

    Ast required = 174.00 mm

    Assume diameter of bars as = 10 mm

    centre to centre spacing = 200 mm OK

    Ast provided = 392.6 mm2

    Hence provide 10 mm @ 200 mm c/c at Top and Bottom

    Check for shear:-

    one way shear

    Maximum shear at a distance "d" from the face of the column

    Overhang from the face of the column = 0.3 - 0.145

    = 0.155 m

    Shear force = 5.01 x 0.155

    = 0.78 t/m

    Factored Shear force Vu = 1.55 t

    Maximum shear stress Tv = 15540

    1000 x 145

    = 0.11 N/mm2

    For pt '= 0.27

    b factor = 12.86

    Permissible shear stress = t c = 0.38 N/mm2 SAFE

    Larsen and Toubro 5

  • 7/29/2019 Eqp Foundation

    6/41

    ALIF ENGINEERS AND PLANNERS Design calculation LA FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/201

    REV R0

    Two way shear

    Critrical section at d/2 from face of pedestal = 72.5 mm

    Perimeter for fractured pyramid = 2 * (B1+d+L1+d) = 3090 mm

    Area of fractured pyramid = (B1+d) * (L1+d) = 0.714025 m2

    Punching shear = V = (1-Pyramid Area/Area of footing) * P Max

    = 2.895 Ton

    Eff depth at critical section 145 mm

    Shear stress = Vu / (Perimeter * Min Depth) = 0.10 N/MM2

    Allowable shear stress = 0.25 * SQRT(Fck) = 1.37 N/MM2

    HENCE SAFE

    Design of Pedestal

    Pedestal size = 0.7 m x 0.70 m

    Vertical load on pedestal = 20.384 t

    self weight of pedestal = 2.1 x 0.7 x 0.7

    x 2.5= 2.57 t

    Total vertical load = 22.96 t

    shear at plinth level = 0.22 t

    Moment at the base of the pedestal 0.22 x ( 2.3 - 0.2 )

    = 0.45 tm

    0.3

    2 0.70

    10 mm @ 200 mm c/c @Bottom

    0.2

    1.3 m x 1.3 m

    Factored Total vertical load = 45.91 t

    Factored Moment at the base of the pedestal = 0.91 tm

    Larsen and Toubro 6

  • 7/29/2019 Eqp Foundation

    7/41

    ALIF ENGINEERS AND PLANNERS Design calculation LA FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/201

    REV R0

    A. COMPRESSION WITH BENDING

    lef = 2.1 x 2 4.20 m

    lef / D = 6.00 < 12 Short Column

    Total Moment = 0.91 + 0.00 = 0.91 Tm

    Since Load is is very less only minimum reinforcement as per cl. 25.5.3(g) of IS 456 will be required.

    Concrete area required to resist direct vertical load= 45.91 x 10000

    0.36 x 30.00

    = 42512.04 mm2

    Minimum Ast required = 0.8 % of the concrete area required to resist direct vertical load

    = 0.80 x 42512.04 = 340.10 mm2

    100.00

    Provide longitudinal reinforcement of 12 nos 12 dia

    Ast Provided = 1356.48 mm2

    Spacing between reinforcement = 206.67 < 300.00 OK

    Design for lateral ties :

    Spacing of lateral ties shall be least of the following :-

    I) Least lateral dimn of column = 700.00 mm

    ii) 16 x dia of longitudinal reinf = 16.00 x 12.00 = 192.00 mm

    iii) 48 x dia of transverse reinforcement= 48.00 x 8.00 = 384.00 mm

    Privide 8mm ties at 190 mm c/c.

    XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

    Larsen and Toubro 7

  • 7/29/2019 Eqp Foundation

    8/41

    Normal SCF

    Maximum vertical load at PL = 0.530 Ton 0.530 Ton

    Maximum shear at PL = 0.207 Ton 0.501 Ton

    Maximum moment at PL = 0.434 Tm 2.335 Tm

    Back to Back of angles in elevation = 0.400 m

    Back to Back of angles in side view = 0.400 m

    CG of vert angle = 1.41 cm

    Design Data:

    Depth o f Foundation = 2 m

    Depth of filling 0 m

    Safe Bearing capacity of soil = 11 t/m2

    Density of soil = 1.7 t/m3

    Gross Bearing capacity of soil = 11 x 1.25 + 1.7

    x 2

    = 17.15 t/m2

    Grade of concrete = 30

    Density of concrete = 2.5 t/m3

    Reinforcement yield stress = 500 N/mm2

    FOS = 2 1.5 (SCF)

    Coefficient of friction between soil&conc = 0.6

    Angle of repose = 6 degrees

    ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Larsen and Toubro 8

  • 7/29/2019 Eqp Foundation

    9/41

    ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    0.3

    2.0

    0.2

    1.30

    Assume size of raft as follows

    L = 1.30 m

    B = 1.30 m

    t = 0.2 m

    Depth of foundation from FGL D = 2.0 m

    Pedestal size pxp = 0.60 m x 0.600 m

    Plinth level from FGL = 0.30 m

    Height of pedestal = 2.1 m

    SCF

    Factored Longitudinal moment at base M = 1.82 tm 5.23095 tm

    Height of soil = 1.80 m

    Calculation of down thrust

    Weight of raft w1 = 1.3 x 1.3 x 0.2

    x 2.5

    = 0.845 t

    Weight of pedestal w2 = 0.6 x 0.6 x 2.1

    x 2.5 x 2

    = 3.78 t

    Total wr = 4.63 t

    Weight of soil ws = ( 1.3 x 1.3 ) - ( 1 x 0.6

    x 0.6 ) x ( 1.8 x 1.7

    ws = 4.07 t

    Vertical load Equip + str = 0.53 t 0.53 t

    Factored Total vertical load P = 18.45 t 13.84 t

    Unfactored loads = 9.22 t 9.22 t

    Check for eccentricity,bearing pressure &overturning

    Maximum soil pressure p1 (Considering unfactored loads) = 5.46 + 2.49

    = 7.94 t/m2< 17.15 SAFE

    F.O.S against overturning = 18.45 x 1.3 / 2

    = 1.82

    = 6.59 > 1.5 SAFE

    Larsen and Toubro 9

  • 7/29/2019 Eqp Foundation

    10/41

    ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    F.O.S against sliding = 13.84 x 0.6

    0.207

    = 40.11 > 1.5 SAFE

    F.O.S against overturning = 13.84 x 1.3 / 2

    SCF Cond = 5.23

    = 1.72 > 1.5 SAFE

    F.O.S against sliding = 13.84 x 0.6

    SCF Cond 0.501

    = 16.57 > 1.5 SAFE

    Design of bottom pad

    Downward pressure to concrete = 0.2 x 2.5

    = 0.5 t/m2

    Downward pressure due to earth = 1.8 x 1.7

    = 3.06 T/m2

    Net upward pressure on pad = 7.94 - 3.56= 4.38 t/m

    2

    Maximum overhang = 1.3 - 0.60

    2

    = 0.35 m

    Maximum bending moment = 4.38 x 0.352

    2

    = 0.27 tm

    Factored maximum moment = 0.27 x 2

    = 0.40 tmEffective depth d = 145 mm

    Mu/bd2 = 3951219

    1000 x 1452

    = 0.19 N/mm2

    % steel = 0.043 %

    Minimum % steel = 0.12 %

    Ast required = 174.00 mm2

    Assume diameter of bars as = 10 mm

    centre to centre spacing = 200 mm OK

    Ast provided = 392.6 mm2

    Hence provide 10 mm @ 200 mm c/c at Top and Bottom

    Larsen and Toubro 10

  • 7/29/2019 Eqp Foundation

    11/41

    ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Check for shear:-

    one way shear

    Maximum shear at a distance "d" from the face of the column

    Overhang from the face of the column = 0.35 - 0.145

    = 0.205 m

    Shear force = 4.38 x 0.205

    = 0.90 t/m

    Factored Shear force Vu = 1.80 t

    Maximum shear stress Tv = 17974

    1000 x 145

    = 0.12 N/mm2

    For pt '= 0.27

    b factor = 12.86

    Permissible shear stress = t c = 0.38 N/mm2 SAFE

    Two way shear

    Critrical section at d/2 from face of pedestal = 72.5 mm

    Perimeter for fractured pyramid = 2 * (B1+d+L1+d) = 2690 mm

    Area of fractured pyramid = (B1+d) * (L1+d) = 0.555025 m2

    Punching shear = V = (1-Pyramid Area/Area of footing) * P Max

    = 2.944 Ton

    Eff depth at critical section 145 mm

    Shear stress = Vu / (Perimeter * Min Depth) = 0.11 N/MM2

    Allowable shear stress = 0.25 * SQRT(Fck) = 1.37 N/MM2

    HENCE SAFE

    Design of Pedestal

    Pedestal size = 0.6 m x 0.60 m

    Vertical load on pedestal = 18.450 t

    self weight of pedestal = 2.1 x 0.6 x 0.6

    x 2.5

    = 1.89 t

    Total vertical load = 20.34 t

    shear at plinth level = 0.21 t

    Moment at the base of the pedestal 0.21 x ( 2.3 - 0.2

    = 0.43 tm

    0.3

    2 0.60

    10 mm @ 200 mm c/c @Bottom

    0.2

    1.3 m x 1.3 m

    Larsen and Toubro 11

  • 7/29/2019 Eqp Foundation

    12/41

    ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Factored Total vertical load = 40.68 t

    Factored Moment at the base of the pedestal = 0.87 tm

    A. COMPRESSION WITH BENDING

    lef = 2.1 x 2 4.20 m

    lef / D = 7.00 < 12 Short Column

    Total Moment = 0.87 + 0.00 = 0.87 Tm

    Since Load is is very less only minimum reinforcement as per cl. 25.5.3(g) of IS 456 will be required.

    Concrete area required to resist direct vertical load= 40.68 x 10000

    0.36 x 30.00

    = 37665.93 mm2

    Minimum Ast required = 0.8 % of the concrete area required to resist direct vertical load

    = 0.80 x 37665.93 = 301.33 mm2

    100.00

    Provide longitudinal reinforcement of 12 nos 12 dia

    Ast Provided = 1356.48 mm2

    Spacing between reinforcement = 173.33 < 300.00 OK

    Design for lateral ties :

    Spacing of lateral ties shall be least of the following :-

    I) Least lateral dimn of column = 600.00 mm

    ii) 16 x dia of longitudinal reinf = 16.00 x 12.00 = 192.00 mm

    iii) 48 x dia of transverse reinforcement= 48.00 x 8.00 = 384.00 mm

    Privide 8mm ties at 190 mm c/c.

    XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

    Larsen and Toubro 12

  • 7/29/2019 Eqp Foundation

    13/41

    ALIF ENGINEERS AND PLANNERS Design calculation BPI FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Larsen and Toubro 13

  • 7/29/2019 Eqp Foundation

    14/41

    01

    Larsen and Toubro 14

  • 7/29/2019 Eqp Foundation

    15/41

    01

    )

    Larsen and Toubro 15

  • 7/29/2019 Eqp Foundation

    16/41

    01

    Larsen and Toubro 16

  • 7/29/2019 Eqp Foundation

    17/41

    01

    )

    Larsen and Toubro 17

  • 7/29/2019 Eqp Foundation

    18/41

    01

    Larsen and Toubro 18

  • 7/29/2019 Eqp Foundation

    19/41

    01

    Larsen and Toubro 19

  • 7/29/2019 Eqp Foundation

    20/41

    Normal SCF

    Maximum vertical load at PL = 1.010 Ton 1.010 Ton

    Maximum shear at PL = 0.246 Ton 0.175 Ton

    Maximum moment at PL = 0.514 Tm 0.823 Tm

    Back to Back of angles in elevation = 0.700 m

    Back to Back of angles in side view = 0.700 m

    CG of vert angle = 1.41 cm

    Design Data:

    Depth o f Foundation = 2 m

    Depth of filling 0 m

    Safe Bearing capacity of soil = 11 t/m2

    Density of soil = 1.7 t/m3

    Gross Bearing capacity of soil = 11 x 1.25 + 1.7

    x 2

    = 17.15 t/m2

    Grade of concrete = 30

    Density of concrete = 2.5 t/m3

    Reinforcement yield stress = 500 N/mm2

    FOS = 2 1.5 (SCF)

    Coefficient of friction between soil&conc = 0.6

    Angle of repose = 6 degrees

    0.3

    2.0

    0.2

    1.30

    ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Larsen and Toubro 20

  • 7/29/2019 Eqp Foundation

    21/41

    ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Assume size of raft as follows

    L = 1.30 m

    B = 1.30 m

    t = 0.2 m

    Depth of foundation from FGL D = 2.0 m

    Pedestal size pxp = 0.850 m x 0.850 m

    Plinth level from FGL = 0.30 m

    Height of pedestal = 2.1 m

    SCF

    Factored Longitudinal moment at base M = 2.16 tm 1.83825 tm

    Height of soil = 1.80 m

    Calculation of down thrust

    Weight of raft w1 = 1.3 x 1.3 x 0.2

    x 2.5

    = 0.845 t

    Weight of pedestal w2 = 0.85 x 0.85 x 2.1

    x 2.5 x 2

    = 7.59 t

    Total wr = 8.43 t

    Weight of soil ws = ( 1.3 x 1.3 ) - ( 1 x 0.85

    x 0.85 ) x ( 1.8 x 1.7

    ws = 2.96 t

    Vertical load Equip + str = 1.01 t 1.01 t

    Factored Total vertical load P = 24.80 t 18.60 t

    Unfactored loads = 12.40 t 12.40 t

    Check for eccentricity,bearing pressure &overturning

    Maximum soil pressure p1 (Considering unfactored loads) = 7.34 + 2.95

    = 10.29 t/m2< 17.15 SAFE

    F.O.S against overturning = 24.80 x 1.3 / 2

    = 2.16

    = 7.47 > 1.5 SAFE

    F.O.S against sliding = 18.60 x 0.60.246

    = 45.37 > 1.5 SAFE

    F.O.S against overturning = 18.60 x 1.3 / 2

    SCF Cond = 1.84

    = 6.58 > 1.5 SAFE

    F.O.S against sliding = 18.60 x 0.6

    SCF Cond 0.175

    = 63.78 > 1.5 SAFE

    Larsen and Toubro 21

  • 7/29/2019 Eqp Foundation

    22/41

    ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Design of bottom pad

    Downward pressure to concrete = 0.2 x 2.5

    = 0.5 t/m2

    Downward pressure due to earth = 1.8 x 1.7

    = 3.06 T/m

    2

    Net upward pressure on pad = 10.29 - 3.56

    = 6.73 t/m2

    Maximum overhang = 1.3 - 0.85

    2

    = 0.225 m

    Maximum bending moment = 6.73 x 0.2252

    2

    = 0.17 tm

    Factored maximum moment = 0.17 x 2

    = 0.26 tmEffective depth d = 145 mm

    Mu/bd2 = 2505731

    1000 x 1452

    = 0.12 N/mm2

    % steel = 0.027 %

    Minimum % steel = 0.12 %

    Ast required = 174.00 mm2

    Assume diameter of bars as = 10 mm

    centre to centre spacing = 200 mm OK

    Ast provided = 392.6 mm2

    Hence provide 10 mm @ 200 mm c/c at Top and Bottom

    Check for shear:-

    one way shear

    Maximum shear at a distance "d" from the face of the column

    Overhang from the face of the column = 0.225 - 0.145

    = 0.08 mShear force = 6.73 x 0.08

    = 0.54 t/m

    Factored Shear force Vu = 1.08 t

    Maximum shear stress Tv = 10764

    1000 x 145

    = 0.07 N/mm2

    For pt '= 0.27

    b factor = 12.86

    Permissible shear stress = t c = 0.38 N/mm2 SAFE

    Larsen and Toubro 22

  • 7/29/2019 Eqp Foundation

    23/41

    ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Two way shear

    Critrical section at d/2 from face of pedestal = 72.5 mm

    Perimeter for fractured pyramid = 2 * (B1+d+L1+d) = 3690 mm

    Area of fractured pyramid = (B1+d) * (L1+d) = 0.990025 m2

    Punching shear = V = (1-Pyramid Area/Area of footing) * P Max

    = 2.786 Ton

    Eff depth at critical section 145 mm

    Shear stress = Vu / (Perimeter * Min Depth) = 0.08 N/MM2

    Allowable shear stress = 0.25 * SQRT(Fck) = 1.37 N/MM2

    HENCE SAFE

    Design of Pedestal

    Pedestal size = 0.85 m x 0.85 m

    Vertical load on pedestal = 24.804 t

    self weight of pedestal = 2.1 x 0.9 x 0.9x 2.5

    = 3.79 t

    Total vertical load = 28.60 t

    shear at plinth level = 0.25 t

    Moment at the base of the pedestal 0.25 x ( 2.3 - 0.2

    = 0.52 tm

    0.3

    2 0.8510 mm @ 200 mm c/c @Bottom

    0.2

    1.3 m x 1.3 m

    Factored Total vertical load = 57.19 t

    Factored Moment at the base of the pedestal = 1.03 tm

    Larsen and Toubro 23

  • 7/29/2019 Eqp Foundation

    24/41

    ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    A. COMPRESSION WITH BENDING

    lef = 2.1 x 2 4.20 m

    lef / D = 4.94 < 12 Short Column

    Total Moment = 1.03 + 0.00 = 1.03 Tm

    Since Load is is very less only minimum reinforcement as per cl. 25.5.3(g) of IS 456 will be required.

    Concrete area required to resist direct vertical load= 57.19 x 10000

    0.36 x 30.00

    = 52956.90 mm2

    Minimum Ast required = 0.8 % of the concrete area required to resist direct vertical load

    = 0.80 x 52956.90 = 423.66 mm2

    100.00

    Provide longitudinal reinforcement of 12 nos 12 dia

    Ast Provided = 1356.48 mm2

    Spacing between reinforcement = 256.67 < 300.00 OK

    Design for lateral ties :

    Spacing of lateral ties shall be least of the following :-

    I) Least lateral dimn of column = 850.00 mm

    ii) 16 x dia of longitudinal reinf = 16.00 x 12.00 = 192.00 mm

    iii) 48 x dia of transverse reinforcement= 48.00 x 8.00 = 384.00 mm

    Privide 8mm ties at 190 mm c/c.

    XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

    Larsen and Toubro 24

  • 7/29/2019 Eqp Foundation

    25/41

    ALIF ENGINEERS AND PLANNERS Design calculation CT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Larsen and Toubro 25

  • 7/29/2019 Eqp Foundation

    26/41

    01

    Larsen and Toubro 26

  • 7/29/2019 Eqp Foundation

    27/41

    01

    )

    Larsen and Toubro 27

  • 7/29/2019 Eqp Foundation

    28/41

    01

    Larsen and Toubro 28

  • 7/29/2019 Eqp Foundation

    29/41

    01

    )

    Larsen and Toubro 29

  • 7/29/2019 Eqp Foundation

    30/41

    01

    Larsen and Toubro 30

  • 7/29/2019 Eqp Foundation

    31/41

    01

    Larsen and Toubro 31

  • 7/29/2019 Eqp Foundation

    32/41

    Normal SCF

    Maximum vertical load at PL = 0.930 Ton 0.930 Ton

    Maximum shear at PL = 0.228 Ton 0.175 Ton

    Maximum moment at PL = 0.493 Tm 0.823 Tm

    Back to Back of angles in elevation = 0.500 m

    Back to Back of angles in side view = 0.500 m

    CG of vert angle = 1.41 cm

    Design Data:

    Depth o f Foundation = 2 m

    Depth of filling 0 m

    Safe Bearing capacity of soil = 11 t/m2

    Density of soil = 1.7 t/m3

    Gross Bearing capacity of soil = 11 x 1.25 + 1.7

    x 2

    = 17.15 t/m2

    Grade of concrete = 30

    Density of concrete = 2.5 t/m3

    Reinforcement yield stress = 500 N/mm2

    FOS = 2 1.5 (SCF)

    Coefficient of friction between soil&conc = 0.6

    Angle of repose = 6 degrees

    0.3

    2.0

    0.2

    1.30

    ALIF ENGINEERS AND PLANNERS Design calculation PT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Larsen and Toubro 32

  • 7/29/2019 Eqp Foundation

    33/41

    ALIF ENGINEERS AND PLANNERS Design calculation PT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Assume size of raft as follows

    L = 1.30 m

    B = 1.30 m

    t = 0.2 m

    Depth of foundation from FGL D = 2.0 m

    Pedestal size pxp = 0.70 m x 0.700 m

    Plinth level from FGL = 0.30 m

    Height of pedestal = 2.1 m

    SCF

    Factored Longitudinal moment at base M = 2.03 tm 1.83825 tm

    Height of soil = 1.80 m

    Calculation of down thrust

    Weight of raft w1 = 1.3 x 1.3 x 0.2

    x 2.5

    = 0.845 t

    Weight of pedestal w2 = 0.7 x 0.7 x 2.1

    x 2.5 x 2

    = 5.15 t

    Total wr = 5.99 t

    Weight of soil ws = ( 1.3 x 1.3 ) - ( 1 x 0.7

    x 0.7 ) x ( 1.8 x 1.7

    ws = 3.67 t

    Vertical load Equip + str = 0.93 t 0.93 t

    Factored Total vertical load P = 21.18 t 15.89 t

    Unfactored loads = 10.59 t 10.59 t

    Check for eccentricity,bearing pressure &overturning

    Maximum soil pressure p1 (Considering unfactored loads) = 6.27 + 2.78

    = 9.05 t/m2< 17.15 SAFE

    F.O.S against overturning = 21.18 x 1.3 / 2

    = 2.03

    = 6.77 > 1.5 SAFE

    F.O.S against sliding = 15.89 x 0.60.228

    = 41.81 > 1.5 SAFE

    F.O.S against overturning = 15.89 x 1.3 / 2

    SCF Cond = 1.84

    = 5.62 > 1.5 SAFE

    F.O.S against sliding = 15.89 x 0.6

    SCF Cond 0.175

    = 54.47 > 1.5 SAFE

    Larsen and Toubro 33

  • 7/29/2019 Eqp Foundation

    34/41

    ALIF ENGINEERS AND PLANNERS Design calculation PT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Design of bottom pad

    Downward pressure to concrete = 0.2 x 2.5

    = 0.5 t/m2

    Downward pressure due to earth = 1.8 x 1.7

    = 3.06 T/m

    2

    Net upward pressure on pad = 9.05 - 3.56

    = 5.49 t/m2

    Maximum overhang = 1.3 - 0.70

    2

    = 0.3 m

    Maximum bending moment = 5.49 x 0.32

    2

    = 0.25 tm

    Factored maximum moment = 0.25 x 2

    = 0.37 tmEffective depth d = 145 mm

    Mu/bd2 = 3632673

    1000 x 1452

    = 0.17 N/mm2

    % steel = 0.040 %

    Minimum % steel = 0.12 %

    Ast required = 174.00 mm2

    Assume diameter of bars as = 10 mm

    centre to centre spacing = 200 mm OK

    Ast provided = 392.6 mm2

    Hence provide 10 mm @ 200 mm c/c at Top and Bottom

    Check for shear:-

    one way shear

    Maximum shear at a distance "d" from the face of the column

    Overhang from the face of the column = 0.3 - 0.145

    = 0.155 mShear force = 5.49 x 0.155

    = 0.85 t/m

    Factored Shear force Vu = 1.70 t

    Maximum shear stress Tv = 17007

    1000 x 145

    = 0.12 N/mm2

    For pt '= 0.27

    b factor = 12.86

    Permissible shear stress = t c = 0.38 N/mm2 SAFE

    Larsen and Toubro 34

  • 7/29/2019 Eqp Foundation

    35/41

    ALIF ENGINEERS AND PLANNERS Design calculation PT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    Two way shear

    Critrical section at d/2 from face of pedestal = 72.5 mm

    Perimeter for fractured pyramid = 2 * (B1+d+L1+d) = 3090 mm

    Area of fractured pyramid = (B1+d) * (L1+d) = 0.714025 m2

    Punching shear = V = (1-Pyramid Area/Area of footing) * P Max

    = 3.168 Ton

    Eff depth at critical section 145 mm

    Shear stress = Vu / (Perimeter * Min Depth) = 0.11 N/MM2

    Allowable shear stress = 0.25 * SQRT(Fck) = 1.37 N/MM2

    HENCE SAFE

    Design of Pedestal

    Pedestal size = 0.7 m x 0.70 m

    Vertical load on pedestal = 21.184 t

    self weight of pedestal = 2.1 x 0.7 x 0.7

    x 2.5

    = 2.57 tTotal vertical load = 23.76 t

    shear at plinth level = 0.23 t

    Moment at the base of the pedestal 0.23 x ( 2.3 - 0.2

    = 0.48 tm

    0.3

    2 0.70

    10 mm @ 200 mm c/c @Bottom

    0.2

    1.3 m x 1.3 m

    Factored Total vertical load = 47.51 t

    Factored Moment at the base of the pedestal = 0.96 tm

    Larsen and Toubro 35

  • 7/29/2019 Eqp Foundation

    36/41

    ALIF ENGINEERS AND PLANNERS Design calculation PT FoundationDOC.NO:

    L&T/RIL/AEP/44PS4800/C/

    REV R0

    A. COMPRESSION WITH BENDING

    lef = 2.1 x 2 4.20 m

    lef / D = 6.00 < 12 Short Column

    Total Moment = 0.96 + 0.00 = 0.96 Tm

    Since Load is is very less only minimum reinforcement as per cl. 25.5.3(g) of IS 456 will be required.

    Concrete area required to resist direct vertical load= 47.51 x 10000

    0.36 x 30.00

    = 43993.52 mm2

    Minimum Ast required = 0.8 % of the concrete area required to resist direct vertical load

    = 0.80 x 43993.52 = 351.95 mm2

    100.00

    Provide longitudinal reinforcement of 12 nos 12 dia

    Ast Provided = 1356.48 mm2

    Spacing between reinforcement = 206.67 < 300.00 OK

    Design for lateral ties :

    Spacing of lateral ties shall be least of the following :-

    I) Least lateral dimn of column = 700.00 mmii) 16 x dia of longitudinal reinf = 16.00 x 12.00 = 192.00 mm

    iii) 48 x dia of transverse reinforcement= 48.00 x 8.00 = 384.00 mm

    Privide 8mm ties at 190 mm c/c.

    XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

    Larsen and Toubro 36

  • 7/29/2019 Eqp Foundation

    37/41

    01

    Larsen and Toubro 37

  • 7/29/2019 Eqp Foundation

    38/41

    01

    )

    Larsen and Toubro 38

  • 7/29/2019 Eqp Foundation

    39/41

    01

    Larsen and Toubro 39

  • 7/29/2019 Eqp Foundation

    40/41

    01

    )

    Larsen and Toubro 40

  • 7/29/2019 Eqp Foundation

    41/41

    01