Environmental Safeguard Monitoring Report
Transcript of Environmental Safeguard Monitoring Report
Environmental Safeguard Monitoring Report
Project No. 45203-006 Semestral Report August 2020
Bangladesh: Natural Gas Infrastructure and Efficiency Improvement Project (Component 2 – Chittagong-Bakhrabad Gas Transmission Pipeline)
Prepared by the Gas Transmission Company Limited for the Government of Bangladesh and the Asian Development Bank.
This environmental safeguard monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
This environmental safeguard monitoring report is a document of the borrower and made publicly available in accordance with ADB’s Public Communications Policy 2011 and the Safeguard Policy Statement 2009. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff.
Environmental Safeguards Monitoring Report
Reporting Period January 2020 to June 2020 Date August 2020
Natural Gas Infrastructure and Efficiency improvement Project
(Part B: Constructing an approximately 181-kilometer, 36-inch diameter parallel gas transmission
pipeline traversing Chattogram through Feni to Bakhrabad, Cumilla)
ADB Loan no.3461/3462-BAN & (8318 AIIB)
AIIB Loan no. 000015-1-BGD
Prepared by: Gas Transmission Company Limited (GTCL) for the Asian Development Bank &
Asian Infrastructure Investment Bank
2
LIST OF ABBREVIATIONS
ADB Asian Development Bank
AIIB Asian Infrastructure Investment Bank
CITES Convention on International Trade in Endangered Species of Wild Fauna and Flora
DOE Department of Environment
EA Executing Agency
ECA Environment Conservation Act
ECC Environmental Clearance Certificate
ECR Environment Conservation Rules
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EMRD Energy and Mineral Resources Division
ERP Entrepreneur Resource Planning
ESMS Environment and Safety Management System
GoB Government of Bangladesh
GRC Grievance Redress Committee
GTCL Gas Transmission Company Limited
IEE Initial Environmental Examination
HDD Horizontal Directional Drilling
LCC Locational Clearance Certificate
MOEF Ministry of Environment and Forests
MPEMR Ministry of Power, Energy and Mineral Resources
MS Metering Station
PIU Project Implementation Unit
RoW Right-of-Way
SPS Safeguard Policy Statement
TBS Town Border Station
WEIGHTS AND MEASURES
oC - degree Celsius
dB(A) - A-weighted decibel
ha - hectare
lakh - 100,000
ppb - parts per billion
ppm - parts per million
µg/m3 - microgram per cubic meter
m2 - square meter
GLOSSARY Ambient Surrounding
Bangla Official language of Bangladesh
Haor A bowl-shaped depression located between the natural levees of rivers
Hydrostatic
testing
Process of filling a pipeline with water, or a mixture of water and ethylene
glycol or methanol to test the structural integrity of the pipeline under pressure
Khal Bangla word for a small channel or canal
Thana Sub-district level of government administration, comprising several unions
under the district
Union Smallest unit of local self-government comprising several villages
Union parishad Union council
Upazila Bangla word for sub-district name
Zila Bangla word for district.
3
TABLE OF CONTENTS
Executive Summary 4-5
1.0 Introduction 6
1.1 Brief Project Description 6
1.2 Project Progress Status and Implementation Schedule 8
2.0 Compliance to National Regulations and International Agreements 9
3.0 Compliance to Environmental Covenants from the ADB Loan Agreement 9-10
4.0 Compliance to Project Administration Manual (PAM) 11
5.0 Compliance to Contract 12
6.0 Compliance to Environmental Management Plan 12-14
7.0 Environmental Supervision and Monitoring Results 15
7.1 Environmental Supervision 15
7.2 Quantitative Environmental Monitoring 16-19
7.3 Pollution Control Monitoring 20
7.4 Occupational and Community Health and safety Monitoring 20
8.0 Meaningful Consultation and Grievances Redress 21
9.0 Conclusions and Recommendations 21
Appendices 22
Photographs 22-26
Supporting Documents 27
Reports
Environment Clearance Certificate from DoE
4
EXECUTIVE SUMMARY
Project Name Natural Gas Infrastructure and Efficiency improvement Project, Part B Executing Agency Gas Transmission Company Limited (GTCL)
Implementing Agency Gas Transmission Company Limited (GTCL) Environment Safeguards
Categorization
Category B
Environment Safeguards
Documentation
EIA/IEE/EMP
Project Stage Obtained 1. Commissioning of Gas Transmission Pipeline including valve
stations and river crossing by HDD.
2. Construction of TBS & MS and SCADA System
Detailed Design Required Post-
Approval
No
Contract(s) Awarded Yes
Package Description Award Date
1 36’’ Line Pipe- 181 Km 22-Nov-2017
2
(Lot A) 36’’ ND, 8D radius
Induction Bends
12-Apr-2017
(Lot B) Ball Valves, gate valves and
plug
4-Apr-2017
(Lot C) Butt Weld Fittings 3-Apr-2017
(Lot D) TEG, CP and Coating
Materials
5-Apr-2017
3 River crossing 36-inches by HDD
method
30-Apr-2018
4 2 nos town border station and 1
Metering Station
12-Sep-2018
5 SCADA facilities 11-Nov-2019
Bidding Document(s) Include EMP
Cleared by ADB
Yes
Package Description ADB Approval
date
3 River crossing 36-inches by HDD
method
10-Nov-2017
4 2 nos town border station and 1
Metering Station
18-Dec-2017
5 SCADA facilities 17-Jan-2019
Contract(s) Awarded Include EMP
Cleared by ADB
Yes
Package Description ADB Approval
date
3 River crossing 36-inches by HDD
method
20-Mar-2018
5
4 2 nos town border station and 1
Metering Station
14-May-2018
5 SCADA facilities 9-Oct-2019
National Environment, Health and
Safety Clearance(s) Obtained
Yes (Valid till 06 September 2020
Contractor(s) Given Access to Site Yes
Construction Progress (%) Package Description Progress
(% )
3 River crossing 36-inches by
HDD method
100
4 2 nos town border station
and 1 Metering Station
64
5 SCADA facilities 15
Unanticipated Impacts including
Change of Scope or Design
No
Number of Site Inspections and
Audits Undertaken by Environment
Safeguards Staff in Reporting Period
GTCL during commissioning -2 times
Contractors Representative for all stations
Corrective Action Required from
Previous Reporting Period
No
Outstanding Corrective Action this
Reporting Period
No
Non-Compliances Recorded this
Reporting Period
No
Corrective Action Required No Number of Health and Safety
Incidents
None
GRM Functional Yes Number of Unresolved Grievances
from Prior Reporting Period
None
Number of Grievances Received in
Reporting Period
None
Number of Grievances Resolved this
Reporting Period
N/A
Number of Grievances Still
Outstanding
None
Number of Grievances referred to
Court of Law
None
Number of Grievances referred to the
Accountability Mechanism
None
1.0 Introduction
6
1.1 Brief Project Description
Natural gas is a significant source of commercial energy in Bangladesh and is the prime mover of its
national economy. There is a growing demand for a steady and reliable supply of natural gas in the
Southeast region to support its industrialization and commercial developments. The Government of
Bangladesh (GoB) has recognized this need and considers it a priority to expand the gas transmission
capacity in this region.
GTCL is one of the operating companies of the Bangladesh Oil, Gas & Mineral Corporation (Petro Bangla)
responsible for the centralized operations and maintenance of the national gas grid, and in expanding the
national gas grid to ensure a balanced supply and usage of natural gas in all the regions of Bangladesh.
Petrobangla coordinates the gas sector in Bangladesh and is the state agency for oil and gas exploration,
production, transmission and distribution.
To address the constraints in the gas sector, the GoB, through the Energy and Mineral Resources Division
(EMRD) of the Ministry of Power, Energy and Mineral Resources (MPEMR), has requested the Asian
Development Bank (ADB) and the Asian Infrastructure Investment Bank (AIIB) to provide financing for
the Natural Gas Infrastructure and Efficiency Improvement Project. Gas Transmission Company Limited
(GTCL) is the Executing Agency (EA) and implementing agency of component 2. Implementing the
Component 2: “Construction of Chattogram-Feni-Bakhrabad Gas Transmission Parallel Pipeline Project”
will address this infrastructure requirement as this will constitute loop transmission lines between
Chattogram and Bakhrabad.
The main goal of the project is to establish a sustainable gas transmission pipeline to meet the demand of
gas in the Chattogram-Bakhrabad region and adjoining areas and transmit the gas to the national gas grid.
GTCL has taken up this project in consideration of the present situation and the future higher gas demand
in the region to meet the sustainable development goal.
The Project consists of about 181 km, 36-inch OD gas transmission pipeline from Chattogram to Bakhrabad,
southeast of Bangladesh including 4 nos HDD River crossing, 3 Nos. TBS &MS, SCADA etc. The gas
transmission pipeline route has traversed the districts of Chattogram, Feni, and Cumilla covering 11 sub-
districts (upazila). Following Map shows the location of the pipe line.
The Project is categorized as Red for National and Category B for ADB.
Environmental safeguard requirements has been incorporatd in all contracts and no objection taken from
ADB.
Organogram of Environmental Monitoring:
GTCl Env. Dept
GTCL HSE dept.
Contractor Env.
PD
Project Engr
GR Committee
7
8
1.2 Project Progress Status and Implementation schedule
Project Component Target Completion
Date
Progress Status Percent Completed Remarks
Land Acquisition
(372.10 acre)
28 February 2019
(revised target date
31 December 2019)
Completed 100%
Requisition (681.38
acre)
31 December 2019
(revised target date
31 December 2020)
On-going 80% .Notice served for
Requisition but final
estimate for land
requisition yet to
receive from DC’s
Implementation of
RAP by NGO
30 June 2020
(revised target date
31 December 2020)
On-going 80%
External Expert for
Monitoring NGO
activities
30 June 2020
(revised target date
31 December 2020)
On-going 80%
Materials
Procurement
31 January 2019 Completed 100% 2 Packages
comprising 5 lots
Construction of
pipeline (36” dia x
179.7 km)
30 June 2019
(revised target date
29 February 2020)
Completed 100% RLNG is transported
to National Gas Grid
through this Pipeline
HDD River Crossing
(4 Nos. 1.3 km)
17 October 2019 Completed 100%
Installation of 2 TBS
& Metering Station
27 February 2020
(revised target date
28 February 2021)
On going 64% Contract Awarded to
Valveitalia, Italy.
Materials shipment
is in progress. Civil
works ongoing. Due
to covid 19, TBS-
metering site
construction works
are running at slow
pace with limited
manpower.
Civil Construction 30 September 2020 On going 80% Due to covid 19,
construction works
are running at slow
pace with limited
manpower.
Installation of
SCADA &
Telecommunication
System
10 December 2020
(Revised target date
31 March 2021)
On going 15% Contract Awarded to
Nari Technology,
China. Due to covid
19 progress is slow.
-Gant Chart Attached for TBS & SCADA Contractor.
9
2.0 Compliance to National Regulations and International Agreements
3.0 Compliance to Environmental Covenants from the ADB Loan Agreement
Schedule#
Para #
Covenant Compliance Status
Remarks
Loan
3462,
Schedule
5
Para# 9
Grievance Redress Mechanism:
The Borrower shall ensure and cause BGFCL and
GTCL to ensure, that the grievance redress
mechanisms established in accordance with the RP
and each IEE including the establishment of a
special committee to receive and resolve
complaints/grievances or act upon reports from
stakeholders on misuse of funds and other
irregularities and grievances, including due to
resettlement remain fully operational and in effect
under the Project. The special committee shall (i)
make public of the existence of this grievance
redress mechanism (ii) review and address
grievances of stakeholders of the project, in
relation to either the project any of the service
providers, or any person responsible for carrying
out any aspect of the project; and (iii) proactively
and constructively responding to them.
Complied, ongoing GTCL:
(i) Resettlement Plan: Grievance
Redress Mechanism (GRM) and
Grievance Redress Committee
(GRC) has been established
since December 2017 in
accordance with the approved
RP;
(ii) IEE: Establishment of GRM
& GRC in accordance with
approved IEE document has
been established since October
2018.
Loan
3462,
Schedule
5 Para# 10
Environment:
The Borrower shall ensure, and cause BGFCL and
GTCL to ensure that the preparation, design,
construction, implementation, operation and
decommissioning of the project and all project
facilities comply with (a) all applicable laws and
regulations of the Borrower relating to
environment, health and safety; (b) the
Environmental Safeguards; and (c) all measures
and requirements set forth in an IEE, the EMP and
any corrective or preventative actions set forth in a
Safeguards Monitoring Report.
Complied GTCL:
All the requirements has already
been included in the contract
agreements and GTCL is
monitoring the compliance. All
the contractor submitting
environment report in each
month.
National Regulation Compliance
Requirements under the
Regulation
Compliance Status
Remarks
Environment
Conservation Act
(ECA) of 1995 and
Environment
Conservation Rules
(ECR) of 1997.
any activity needed to
conserve and enhance the
quality of environment
and to control, prevent and
mitigate pollution
complied
10
Schedule#
Para #
Covenant Compliance Status
Remarks
Loan
3462,
Schedule
5 Para# 15
Safeguards-Related Provisions in Bidding
Documents and Works Contracts
The Borrower shall ensure, or cause BGFCL and
GTCL to ensure, that all bidding documents and
contracts for Work contain provisions that require
contractors to:
(a) Comply with the measures relevant to
the contractor set forth in the IEE, the
EMP, and the RP (to the extent they
concern impacts on affected people
during construction), and any corrective
or preventative actions set forth in a
Safeguards Monitoring Report;
(b) Make available a budget for all such
environmental and social measures;
(c) Provide the Borrower with a written
notice of any unanticipated
environmental, resettlement or
indigenous peoples risks or impacts that
arise during construction,
implementation or operation of the
project that were not considered in the
IEE, the EMP, and the RP; and
Adequately record the condition of roads,
agricultural land and other infrastructure prior to
starting to transport materials and construction
Complied GTCL:
Safeguards-Related Provisions
have already been incorporated
in Bidding Documents as well as
Works Contracts. Proper steps
has been taken to ensure the
compliance of these covenants.
11
Schedule#
Para #
Covenant Compliance Status
Remarks
Loan
3462,
Schedule
5 Para# 16
Safeguards Monitoring and Reporting
The Borrower shall do the following, or cause
BGFCL and GTCL to do the following:
(a) Submit semi-annual Safeguards
Monitoring Reports to ADB and disclose
relevant information from such reports to
affected persons promptly upon
submission;
(b) If any unanticipated environmental and
/or social risks and impacts arise during
construction, implementation or
operation of the project that were not
considered in the IEE, the EMP, and the
RP, promptly inform ADB of the
occurrence of such risks or impacts, with
detailed description of the event and
proposed corrective action plan;
(c) No later than 6 months of the Effective
Date, engage qualified and experienced
external experts or qualified NGOs
under a selection process and terms of
reference acceptable to ADB, to verify
information produced through the
project monitoring process, and facilitate
the carrying out of any verification
activities by such external experts; and
(d) Report any actual or potential breach of
compliance with the measures and
requirements set forth in the EMP, or the
RP promptly after becoming aware of
the breach.
Complied, ongoing GTCL
(a) The environmental
monitoring reports for Jan-June
2020 is sent herewith.
(b) Proper action will be taken in
such case as per loan covenant
and approved IEE, EMP and RP
document a s well as such
incident will promptly be
informed ADB including risks or
impacts, with detailed
description of the event and
proposed corrective action plan.
Till date not any unanticipated
environmental and social risks
and impacts has arisen.
(c) A qualified external expert
has been engaged on August 09,
2018 to verify information
produced through the project
monitoring process, and
facilitate the carrying out of any
verification activities. The expert
is submitting the report to ADB.
(d) will be reported accordingly
if occurs.
4.0 Compliance to Project Administration Manual (PAM)
Table 10: The Financial Management Action Plan, page -15 of PAM
Organization Tasks Compliance Status
Remarks
Executing
Agency (GTCL)
Executing agencies will
identify augmentation
needs
and prepare a staffing plan
by December 2017
Complied ADB Loan Review Mission Aide
Memory (2-8 July 2018)
Executing agencies will
review and redefine scope
and coverage of internal
audit function and
accordingly strengthen
internal audit function as
required by December
2017.
Complied ADB Loan Review Mission Aide
Memory (2-8 July 2018)
12
Organization Tasks Compliance Status
Remarks
Executing agencies will put
in place internal
manuals to ensure staff
systematically following a
common set of practices by
December 2017.
Complied ADB Loan Review Mission Aide
Memory (2-8 July 2018)
Executing agencies will
review setting up automated
backup of data or disaster
management systems for
managing information
security
Complied GTCL currently using ERP.
5.0 Compliance to Contract
Contract Package Contract Provisions Compliance Status Remarks
3 the Contractor shall comply
with the measures relevant
to the contractor set forth in
the IEE, the EMP and the
RIPP.
Complied The Contractor submitted monthly
Environmental report to Employer.
4 the Contractor shall comply
with the measures relevant
to the contractor set forth in
the IEE, the EMP and the
RIPP.
Complied, ongoing The Contractor is submitting
monthly Environmental report to
Employer. Employer also
monitoring site activities.
5 the Contractor shall comply
with the measures relevant
to the contractor set forth in
the IEE and the EMP
Being Complied,
ongoing
Site construction work not yet
started.
6.0 Compliance to Environmental Management Plan
Item # Requirement Prior Corrective
Action
Compliance Status
Remarks
Increased noise
level Limit noise-generating
activities
during daytime and
provide
temporary enclosures to
stationary
noise sources.
Provide ear
plugs/muffs to workers
exposed to high-level
noise and
rotate schedule of these
workers
every two hours
NA Complied,
On going Monthly
Environmental
report submitted
by the
Contractors.
13
Item # Requirement Prior Corrective
Action
Compliance Status
Remarks
Increased level of
dust and vehicular
emission
Water will be sprayed
in opened land areas or
in other areas where
dust is generated
NA Complied Water has sprayed
in opened land
areas during
construction at dry
season. Disruption to the
Existing beneficial
uses of Little Feni
River, Muhuri
River,Khalidas
Khal, and Dakatia
River affected by
installation of
pipeline
Alternative water source
(i.e.,water
tank) will be provided to
local
people/households
directly and
adversely affected by
the disruption
in the rivers
NA Complied Due to the
technique of HDD
crossing river
water not
disrupted. It is a
trenchless
technique. River
water not used.
Deep tube well
installed for water
during
construction. Deterioration of
water quality
Construction works will
be undertaken during
the dry season
Construction camps will
be provided with
sanitary facilities,
wash areas, safe
drinking water and
garbage bins to contain
waste generated by
laborers.
Labor camps will be
located away from water
bodies
Local hiring will be a
priority to
minimize number of
workers at
labor camps
NA Complied
Construction
camps established
with sanitary
facilities,
wash areas, safe
drinking water.
Occupational and
public safety risks
Clear and visible danger
and warning
signs/posters will be
installed at and around
the construction sites to
prevent accidents.
Warning signs will
consider people with
disabilities
NA Complied warning
signs/posters has
installed at and
around the
construction sites
to prevent
accidents.
Potential drainage
disruption
Completion of
construction works will
be ensured during the
dry season
NA complied No such
disruption arises
yet.
Potential disruption
to navigation
NA complied No such
disruption arises
yet.
14
Item # Requirement Prior Corrective
Action
Compliance Status
Remarks
Erosion at
riverbanks
NA complied As HDD river
crossing started
far away from
riverbanks (at
least 100 m away),
so no such
incident has
occurred. Deterioration of soil
quality Pipe-laying will be done
following design
specifications and
industry standards to
prevent excessive soil
disturbance.
Sequence of
excavated soil for
backfilling will be
maintained to minimize
the impacts on soil
quality
NA Complied Sequence of
excavated soil for
backfilling has
been maintained
to
minimize the
impacts on soil
quality.
Disturbance to
adjacent lands along
the pipeline route
Construction works will
be limited to the
designated area (i.e.
pipeline RoW and
construction Row or
workspace)
NA Complied Adjacent lands
were not
disturbed.
Loss of crop
production Construction schedule
will consider harvest
time of farmers to
minimize loss of crops.
Affected farmers/
landowners will be
compensated for the loss
of their crops following
GoB applicable
regulations and
requirements of SPS
2009
NA Complied, Ongoing Construction work
started after
harvesting.
Land owners are
being
compensated as
per GoB
regulations.
15
16
7.0 Environmental Supervision and Monitoring Results
7.1 Environmental Supervision
Trainings Number and Position of
Participant/s
Location/s and Date/s Remarks
Personal safety and
Commissioning Risk
40 Fouzdarhat, Chattogram
28-02-2020
Feni-29-02-2020
During Pipeline
commissioning on 28-02-
2020 and 29-02-2020
Activity Allocated Budget % Spend Remarks
Increased noise
level
10.00 Lac 100% Pipeline Construction & HDD River crossing
Contractor borned the cost. Increased level of
dust and vehicular
emission
20.00 Lac 50% Pipeline Construction & HDD River crossing
Contractor borned the cost.
Deterioration of
water quality 30.00 Lac 100% Pipeline Construction & HDD River crossing and
TBS-MS Contractor borned the cost. Occupational and
public safety risks
20.00 Lac 60% Pipeline Construction & HDD River crossing
Contractor borned the cost.
Deterioration of
soil quality
8.00 Lac 100% Pipeline Construction & HDD River crossing
Contractor borned the cost.
Loss of crop
production
2000.00 Lac 50% Pipeline Construction & HDD River crossing
Contractor borned the cost. GTCL will bear the
remaining.
TOTAL 2088.00 Lac
Date Type and Purpose
of Visit
Location/s Visited EA, IA, Consultant
Staff Participating
Remarks
27-02-2020 Risk assessment for
Gas
Commissioning
Fouzdarhat,
Chattogram
DGM, DM of HSE
dept. of GTCL
Corrrective measure
taken as per
instruction provided
by EA representative.
28-02-2020 Risk assessment for
Gas
Commissioning
Kashimpur, Feni DGM, DM of HSE
dept. of GTCL
Corrrective measure
taken as per
instruction provided
by EA representative.
17
7.2 Quantitative Environmental Monitoring
Table 7.2.1: Results of Air Quality Monitoring
Parameter
(Unit)
Sampling Location Result
(February
2020)
Bangladesh
Standard
Duratio
n
Weather
Condition
Analysis
Method
PM10
(µg/m3)
Bakhrabad, Muradnagar,
Cumilla (Metering Station)
75.65 150 24 hr Sunny Gravimetric
Bizra, Laksam, Cumilla (TBS
Station)
80.31
Boratakiya, Mirsharai,
Chattogram (TBS Station)
96.78
Joramtol, Banglabazar,
Sitakunda, Chattogram
53.21
PM2.5
(µg/m3)
Bakhrabad, Muradnagar,
Cumilla (Metering Station)
32.59 65 24 hr Sunny Gravimetric
Bizra, Laksam, Cumilla (TBS
Station)
37.13
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
41.23
Joramtol, Banglabazar,
Sitakunda, Chattogram
59.87
SO2
(µg/m3)
Bakhrabad, Muradnagar,
Cumilla (Metering Station)
31.11
365
24 hr Sunny West-Geake
Bizra, Laksam, Cumilla (TBS
Station)
26.78
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
35.97
Joramtol, Banglabazar,
Sitakunda, Chattogram
54.3
NOx
(µg/m3)
Bakhrabad,Muradnagar,
Cumilla (Metering Station)
37.87 100 Annual Sunny Jacob and
Hochheiser
Bizra, Laksam, Cumilla
(TBS Station)
34.98
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
31.13
Joramtol, Banglabazar,
Sitakunda, Chattogram
61.10
18
Table 7.2.2: Results of Noise Level Monitoring
Sample ID Sampling Location Land Use
Category
Result
(February
2020)
Time Bangladesh
Standard
NM_01 Bakhrabad, Muradnagar,
Cumilla (Metering
Station)
Residential 57.11 15:17-15:32 55
NM_01 Bizra, Laksam, Cumilla
(TBS Station)
57.32 11:30-11:45
NM_01 Boratakiya, Mirsharai,
Chattogram
(TBS Station)
59.22 11:25-11:40
NM_01 Joramtol, Banglabazar,
Sitakunda, Chattogram
60.21 11:20-11:30
- Construction activity near residential areas are scheduled in daytime only and the noisy equipment were prohibited from night operation.
The use of temporary noise barriers, or enclosures was properly examined at the
project locations. The Contractor are trying to ensure that all equipment engines and motors are
equipped with proper mufflers
19
Table 7.2.3: Results of Water Sampling Analysis { DRINKING WATER}
Parameter
(Unit)
Sampling Location Result
(February
2020)
Standard Analysis Method
pH Bakhrabad,Muradnagar, Cumilla
(Metering Station)
7.67 6.5-8.5 Multimeter
Bizra, Laksam, Cumilla
(TBS Station)
7.57
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
7.23
Joramtol, Banglabazar, Sitakunda,
Chattogram
7.23
Electric
Conductivity
(EC)
(µs/cm)
Bakhrabad, Muradnagar, Cumilla
(Metering Station)
331 - Multimeter
Bizra, Laksam, Cumilla
(TBS Station)
269
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
266
Joramtol, Banglabazar, Sitakunda,
Chattogram
321
Arsenic (mg/L) Bakhrabad,Muradnagar, Cumilla
(Metering Station)
0.002 0.05 AAS
Bizra, Laksam, Cumilla
(TBS Station)
0.003
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
0.001
Joramtol, Banglabazar, Sitakunda,
Chattogram
0.002
Iron
(mg/L)
Bakhrabad,Muradnagar, Cumilla
(Metering Station)
0.39 0.3-1.0 AAS
Bizra, Laksam, Cumilla
(TBS Station)
0.41
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
0.33
Joramtol, Banglabazar, Sitakunda,
Chattogram
0.46
20
Table 5.1.4: Results of Water Sampling Analysis { WASTE WATER SAMPLING}
Parameter
(Unit)
Sampling Location Result
(February
2020)
Standard Analysis Method
pH Bakhrabad,Muradnagar,
Cumilla (Metering Station)
9.31 6.5-8.50 Multimeter
Bizra, Laksam, Cumilla
(TBS Station)
9.03
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
9.31
Joramtol, Banglabazar,
Sitakunda, Chattogram
9.21
Electric
Conductivity
(EC)
(µs/cm)
Bakhrabad,Muradnagar,
Cumilla (Metering Station)
769 1200 Multimeter
Bizra, Laksam, Cumilla
(TBS Station)
869
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
765
Joramtol, Banglabazar,
Sitakunda, Chattogram
812
Turbidity (NTU) Bakhrabad,Muradnagar,
Cumilla (Metering Station)
56 - Turbidity meter
Bizra, Laksam, Cumilla
(TBS Station)
54
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
56
Joramtol, Banglabazar,
Sitakunda, Chattogram
59
BOD(mg/L) Bakhrabad,Muradnagar,
Cumilla (Metering Station)
-** 6 5 days
incubation
Bizra, Laksam, Cumilla
(TBS Station)
269.10***
Boratakiya, Mirsharai,
Chattogram
(TBS Station)
265.3***
Joramtol, Banglabazar,
Sitakunda, Chattogram
5.3
**Kindly note that there is no Liquid waste collection site at Bakhrabad. Unfortunately, the project team
were not able to collect liquid waste and laboratory analysis for that site.
***The test results show that, BOD5 level exceeds the national
standard for all of the sampling locations because of the water is being collected from the
wastewater and some construction wastes are disposed in water by different anthropogenic
and commercial activities. Proper measures should be taken for preventing rain wash.
21
However, during heavy rainfall, some rain has been occurred. In future, contactor should
safely and legally manage that waste water from pollution.
7.3 Pollution Control Monitoring
Trainings/Drills/ Inspections
Number and Position of Participant/s
Location/s and Date/s Remarks
Gas Commissioning safety training
40 28-02-2020 Fouzdarhat, Chattogram
Gas Commissioning safety training
40 29-02-2020 Kashimpur, Feni
Type of Materials/Waste
Approximate Volume (units)
Source or Destination
Remarks
Sand for Fill 20301.54 cubic meter Bakhrabad, Cumilla
Land Development for Station
Sand for Fill 22166.29 cubic meter Mirsharia, Chattogram
Land Development for Station
7.4 Occupational and Community Health and Safety Monitoring
Trainings/Drills/ Inspections
Number and Position of Participant/s
Location/s and Date/s
Remarks
Gas Commissioning safety training
40 28-02-2020 Fouzdarhat, Chattogram
Gas Commissioning safety training
40 29-02-2020 Kashimpur, Feni
Number and Position of Person/s Involved
Location/s and Date/s of Incident
Detailed Description of Incident
Time-bound Corrective Action
Fatality - - - -
Non-fatal Injury (Lost Time)
- - - -
Non-fatal Injury (Minor)
- - - -
Near-miss - - - -
Illness 2 Chattogram Cold & Fever Medicine provided
Other Incidents - - - -
22
8.0 Meaningful Consultation and Grievance Redress
Date Format/Venue Participants (Occupation, M/F)
Main Issues Raised
None None None None
Complainant/s or Affected Persons
Location/s and Date/s of Complaint
Description of Grievance/Complaint
Timeline* Time-bound Corrective Action
None None None None None * To be solved within 2 weeks
9.0 Conclusions and Recommendations Environmental safeguards aim to ensure the environmental soundness and sustainability of projects, and to support
the integration of environmental considerations into the project decision-making process. The main aims of this
observing movement are to control and decrease the antagonistic effect during the work. So this is very crucial need
for any project.
This environmental safeguard monitoring is directed in the region of the Chattogram-Feni-Bakhrabad Gas Pipeline
Project through everyday practice and event based. All the Environmental preliminary exercises that would guarantee
that consideration will be given to environmental protection during the balance construction work stage that have been
set up in place. To identify the potential impacts likely to be generated by the project and provide a set of action it
needs to execute so as to meet national and global environmental safeguard standards.
During reporting period no compliance is identified. Moreover, all safety precaution due to pandemic Covid 19 has
been taken and no person get affected.
Non-compliance
Corrective Action to be Taken
Responsibility Timeline Budget
None None None None None
23
APPENDICES
Photographs
Safety Discussion before Commissioning at Fouzdarhat, Chattogram
24
Commissioning Inauguration by MD of GTCL at Fouzdarhat, Chattogram
25
Succesful completion of Commissioning at Bakhrabad, Cumilla
26
Covid-19 awarness banner at site Bizra, Cumilla
27
Working with safety precaution during covid-19, at Bakhrabad, Cumilla
28
Supporting Documents 1. Maps and plans 2. Environmental reports submitted by contractor 3. Clearances from DoE 4. Gant Chart and Covid -19 Action Plan of Contractor
Environmental Monitoring Report for the Month
of February 2020 (Completion Report)
for
Construction of 23 km long x 36 ̋ OD 1000 psig high pressure natural
gas transmission pipeline from Chilimpur, Fouzdarhat, Chittagong to
Mandaritola, Sitakunda, Chittagong (Section-A) under Construction of
Chittagong-Feni-Bakhrabad Gas Transmission Parallel Pipeline
Project
February 2020
Prepared for
ARC CONSTRUCTION COMPANY ASA Tower (Level 11), 23/3, Bir Uttam ANM Nuruzzaman Sharak,
Shyamoli, Dhaka-1207, Bangladesh
Prepared by
Development Solutions Consultant Limited (DSCL)
House-734 (5-B), Road-10, Avenue-04, DOHS Mirpur,
Dhaka -1216, Bangladesh, Tel: +8801822758548
Email: [email protected] Website: www.dsclbd.com
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) i
Table of Contents
Executive Summary ................................................................................................................... ii
1 Introduction ..................................................................................................................... 1
1.1 Project Background .................................................................................................... 1
1.1.1 Project Location ..................................................................................................... 1
1.2 Scope of Works ......................................................................................................... 3
1.3 Methodology ............................................................................................................. 3
1.4 Purpose of the Report ................................................................................................ 4
1.5 Construction Activities during Monitoring Period ............................................................ 4
2 Environmental Safeguard Monitoring ................................................................................... 5
2.1 Environmental Monitoring issues as per EMP ................................................................. 5
2.2 Monitoring Details ...................................................................................................... 5
2.2.1 Air Quality/Dust .................................................................................................. 6
2.2.2 Sound Level ....................................................................................................... 6
2.2.3 Water Contamination .......................................................................................... 6
2.2.4 Waste Management ............................................................................................ 7
2.2.5 Drainage Congestion ........................................................................................... 7
2.2.6 Health and Safety of the workers .......................................................................... 7
2.3 Corrective Actions Plans .............................................................................................. 7
2.4 Compliance with IEE/EMP ........................................................................................... 8
3 Environmental Quality Test ............................................................................................... 10
3.1.1 Air Quality ............................................................................................................ 10
3.1.2 Drinking Water Quality ........................................................................................... 14
3.1.3 Noise Measurement ............................................................................................... 18
3.1.4 Liquid Waste Test .................................................................................................. 20
4 Tree Plantation ................................................................................................................ 24
5 Conclusion ...................................................................................................................... 25
APPENDIX .............................................................................................................................. 26
List of Table
Table 1.1: Scope of Work for Environmental Monitoring During February 2020 .............................. 3
Table 2.1: Outcomes of Environmental Safeguard Monitoring Exercise ........................................... 9
Table 3.1: Test Results of Ambient Air Quality Monitoring ............................................................ 13
Table 3.2: Test Result of Drinking Water Sampling Analysis ......................................................... 17
Table 3.3: Test Result of Noise Level Analysis ............................................................................ 20
Table 3.4: Test Result of Liquid Waste Water Sampling Analysis ................................................... 23
List of Figures
Figure 1.1: Project Location Map ............................................................................................... 2
Figure 2.1: Compliance with Environmental Safeguard ................................................................. 8
Figure 3.1: Air Quality Monitoring at the Project Site ................................................................... 12
Figure 3.2: Drinking Water Sampling of Project Area ................................................................... 16
Figure 3.3: Noise Level Monitoring at the Project Location. .......................................................... 19
Figure 3.4: Liquid Waste Sample Collection at the project location. ............................................... 22
Figure 4.1: Tree Plantation Programme around the Project Location ............................................. 25
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) ii
Executive Summary
Natural gas is a significant source of commercial energy in Bangladesh and is the prime
mover of its national economy. The growing demand for natural gas by the industrial centrist
in Chittagong, Noakhali, Comilla and adjoining areas is not sustained by the Gas
Transmission Company Limited (GTCL). The Project aims to increase the contribution of the
energy sector to sustainable economic growth by financing the improvement of efficiency in
gas production from existing gas field, and expansion of transmission pipeline capacity
through construction of gas transmission pipelines. The project will involve about 181 km of
36-inch diameter gas transmission pipeline and ancillary equipment from Uttar Selimpur,
Upazila Sitakunda in the Chittagong District until Keotgaon, Muradnagar Upazila in Comilla
District.
The project consists of about 181km, 36-inch gas transmission pipeline from Chittagong to
Bakhrabad, southeast of Bangladesh. The gas transmission pipeline route traverses the
districts of Chittagong, Feni, and Comilla covering 11 subdistricts. The safeguard monitoring
studies was covering Section–A of the project which consists of about 22 km and the gas
transmission pipeline route have traversed from Chilimpur, Fouzdarhat, Chittagong to
Mandaritola, Sitakunda, Chittagong.
The fundamental points of this environmental monitoring are to control and lessen the
unfriendly effects during development stage. Development laborers might be influenced
unfavorably because of unsafe workplaces, for example, air quality which is declined
because of development vehicles and hardware; commotion and vibration produced from
development vehicle, water contamination by transfer of development waste and wellbeing
of development specialist for keeping up substantial apparatuses. To make a move to limit
dust age, commotion contamination, water contamination, squander the board and specialist
wellbeing and security. The essential information was gathered from development zones by
visual perception; top off an agenda; note taking; catch photos and interview with site
engineer.
Adequate mitigation measures were devised according to the environmental management
plan (EMP) of Initial Environmental Examination (IEE) to mitigate/minimize all environmental
impacts due to project construction related activities. The completion environmental
monitoring study given a description that the project has to be developed in environmentally
sustainable manner. The Environmental quality test result revealed that the ambient air
quality of the project area is within the national standard according to DoE (ECR,1997). The
result shows that time weighted average value of the sound monitored inside the project are
slightly exceed the standard set for the residential area for the sampling locations at day
time. Most of the drinking water quality are within the national standard according to GoB
(DoE, ECR-1997). Most of the parameters for liquid waste are not yet standard according to
ECR,97 by DoE. Tree planting/revegetation was done to designated areas identified by PIU-
GTCL in consultation with Forest Department.
The environmental safeguard monitoring is conducted in the Project through routine and
event based. The main aims of this monitoring activity are to control and reduce the adverse
impact during construction phase. In order to attain and sustain the expected goals after the
project completion, it is indispensable for project authority to disseminate the manuals, to
use the manuals effectively, and to update the manuals timely. Therefore, the environmental
action plan for dissemination and effective use of the manuals will be prepared through the
discussions with project proponent.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 1
1 Introduction
1.1 Project Background
Natural gas is a significant source of commercial energy in Bangladesh and is the prime
mover of its national economy. There is a growing demand for a steady and reliable supply
of natural gas in the Southeast region to support its industrialization and commercial
developments. The Government of Bangladesh (GoB) has recognized this need and
considers it a priority to expand the gas transmission capacity in this region. The growing
demand for natural gas by the industrial centrist in Chittagong, Noakhali, Comilla and
adjoining areas is not sustained by the Gas Transmission Company Limited (GTCL). At
present, the existing Chittagong Bakhrabad gas transmission pipeline is not adequate to
meet the supply of gas for distribution in this region. The Project aims to increase the
contribution of the energy sector to sustainable economic growth by financing the
improvement of efficiency in gas production from existing gas field, and expansion of
transmission pipeline capacity through construction of gas transmission pipelines. The
project will involve about 181 km of 36-inch diameter gas transmission pipeline and ancillary
equipment from Uttar Selimpur, Upazila Sitakunda in the Chittagong District until Keotgaon,
Muradnagar Upazila in Comilla District. The entire pipeline will traverse the districts of
Chittagong, Feni and Comilla.
1.1.1 Project Location
The project consists of about 181km, 36-inch gas transmission pipeline from Chittagong to
Bakhrabad, southeast of Bangladesh. The gas transmission pipeline route traverses the
districts of Chittagong, Feni, and Comilla covering 11 subdistricts. The safeguard monitoring
studies was covering Section–A of the project which consists of about 22 km and the gas
transmission pipeline route have traversed from Chilimpur, Fouzdarhat, Chittagong to
Mandaritola, Sitakunda, Chittagong. The Project location map is shown in Figure 1.1.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 2
Figure 1.1: Project Location Map
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 3
1.2 Scope of Works
This environmental monitoring report has been prepared keeping in view the Environmental
Management Plan (EMP) for Section–C of the Chittagong-Feni-Bakhrabad Gas
Transmission Parallel Pipeline Project The scope of the present environmental monitoring
report follows the EMP including drainage congestion monitoring, ambient air and water
quality and ambient sound level monitoring along with monitoring of the health and safety of
the workers. Environmental trainings and awareness raising camps also include in the
scopes.
According to the EMP the environmental safeguard monitoring reports (monthly) of this
project includes in the table 1.1:
Table 1.1: Scope of Work for Environmental Monitoring During February 2020
Environmental Component Parameters/Activities Remarks
Air Quality/Dust Control Dust control Regularly
Sound Level All Machinery were repaired and checked before work for effective sound reducing
Regularly
Water Contamination ▪ Visual observation of nearby water bodies from pollution; ▪ Prevent disposal of wastes into water bodies;
Regularly
Drainage congestion ▪ Check drainage plan implemented correctly. ▪ Conduct regular inspection
Regularly
Waste Management ▪ Check storage, transportation, disposal, handling of hazardous waste.
▪ Waste and effluents to be collected and disposed safely from all camps;
▪ Waste and garbage from bridge construction site to be disposed safely.
Regularly
Health and Safety ▪ Check quality of food and accommodation at construction camp.
▪ Check safe water supply, hygienic toilet at camps and construction of drain at camp sites.
▪ Check toilets are close to construction site and separate toilet for female.
▪ First-Aid kit with required tools and medicine; ▪ The heavy construction material to handled and stored
safely putting due care on public safety;
Regularly
1.3 Methodology
The following steps were followed to prepare the report:
❖ The IEE reports and EMP Table were reviewed to get proper idea about the EMP.
❖ Regular meetings were conducted with the consultants.
❖ Regular site visit was done by the Environmental Expert to monitor the environmental
safeguard of the project area.
❖ Photographs were taken from the site of the construction activities.
❖ Environmental screening checklist was fulfilled to monitor the environmental
safeguard.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 4
1.4 Purpose of the Report
The main purpose of the report includes,
❖ To present the scenario of the project site in after the civil works.
❖ To monitor the environmental safeguard of the project area.
❖ To monitor the public health and safety of the project area.
❖ To monitor the environmental pollution in the project area due to the construction
activities.
1.5 Construction Activities during Monitoring Period (Completion Month)
During this reporting month for the month of February 2020, all major activities include
excavation, trenching, boring, pipeline stringing, welding, back-filling, testing and
commissioning, clean-up and joint coating has been completed. All the places the pipeline is
already ready and major work has been finished. These major activities have been
scheduled efficiently to ensure the completion of the total pipeline construction within the dry
working season. Tree planting/revegetation was done to designated areas identified by PIU-
GTCL in consultation with Forest Department.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 5
2 Environmental Safeguard Monitoring
The Contractors are made aware of this obligation and their safeguard performance
monitoring during construction was closely supervised and monitored by Environmental
Specialist and Project Engineers with close supervision of the Project Supervision
Consultants.
The environmental safeguard monitoring report is prepared through regular basis field visit
within the construction areas of impacted zone for various components of the environment.
The condition of environmental quality in the locality of project site serves as the basis for
identification, prediction and evaluation of impacts. The environmental quality is assessed
through construction sites visited; capture some photograph; consultation with site engineer
within the impacted zone for various components of the environment. In order to depict the
existing physical environment in the project area, a few of the major parameters are
considered like drainage system, air pollution, noise and vibration, surface and ground water
quality, waste management etc.
In the Chittagong-Feni-Bakhrabad Gas Pipeline Project, environmental and social impacts of
the projects were identified and the mitigation measures of these impacts have been
addressed through Environmental Management Plan (EMP) submitted to Contractors before
commencement of construction work. The protection and enhancement of human-wellbeing
is a common demonstrator for both government and donor’s system and can be seen as
ultimate goal of sustainable development.
2.1 Environmental Monitoring issues as per EMP
During the monitoring period, the issues which were monitored include,
❖ Environmental pollution (dust, noise, soil and water) due to project activities.
❖ Monitoring of several issues listed in the EMP.
❖ Provision of safe water, sanitary toilet facility for workers.
❖ Provision of adequate occupational health safety, fire safety facilities.
❖ Monitoring of waste management system.
❖ Monitoring drainage system and vegetation.
2.2 Monitoring Details
Environmental monitoring is an essential tool for environmental management as it provides
the basic information for rational management decisions. The purpose of the monitoring
program is to ensure that the envisaged purposes of the project are achieved and result in
desired benefits to the target population.
Some of the important impacts associated with the proposed project are associated with
land use, land stability (soil erosion), soil compaction and contamination, water availability,
water quality, ground water contamination, waste and wastewater disposal, ambient air
quality, ambient noise levels, vegetation, tree cutting, drainage system, hydrology, climate
change, construction material sourcing and occupational health and safety. Adequate
mitigation measures are devised to mitigate/minimize all likely environmental impacts and
the same have been presented along with the impacts. During the field observation and data
collection, consultations were also held with the person of designated site engineer by
contractor and consultant. Outcome of these consultations were used in impact assessment
and devising mitigation measures.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 6
2.2.1 Air Quality/Dust
Construction work involves excavation, trenching, boring, pipeline stringing, welding, back-
filling, testing and commissioning, clean-up and joint coating. Possible sources of air
pollution was dust due to construction activities, machinery movement and other sources.
However, due to the openness of construction sites and wind conditions the dust and
engine emissions are expected to have limited effect on the air quality. Dispersal of
pollutants depends upon factors like prevailing wind direction and other weather
conditions, atmospheric stability, height of the source. Dust generation due to construction
activities, transport of construction materials and emission from vehicles, equipment and
machinery.
Mitigation Measures
Construction materials at the site were properly covered while hauled and stored. Spraying
of water is the main way of controlling dust. To mitigate dust problem during construction
period, all relevant areas are suggested to spray at least two times (morning and evening) by
use sprinkler properly. Limit the speed of heavy good vehicles over unpaved surfaces.
2.2.2 Sound Level
Noise from the machines and vibrations caused by the construction activities are the major
pollutants in the construction site of the project. Being a agricultural cum residential area, the
ambient standard is Leq 55 dB (A) (daytime) and Leq 45 dB (A) (night time) (DoE, 2006).
Vehicles horns, movement and starting vehicle are making noise in the busy road of project
corridor. Vibration also caused by large truck, lorry and highway bus movement because of
the undulation road conditions.
Mitigation Measures
All powered mechanical equipment and machinery were repaired and checked before
commencing the work for effective sound reducing; in full compliance with the DoE
regulations. The noisiest operations were performed during daytime. Proper equipment
maintenance and restricted operation between 0700 to 1800 hours to reduce noise.
2.2.3 Water Contamination
In the project influenced area, about 80% of the domestic water supply is obtained from the
middle aquifer, extracted by tube wells throughout the city. Recent studies have shown that
water levels have fallen dramatically, and suggest that the aquifer may be changing from a
confined to an unconfined condition, which could make it vulnerable to contamination.
Groundwater quality decreased by liquid wastes can have serious effects on the quality of
drinking water in the Project area for several years. Uncontrolled dumping of drilling wastes,
and accidental spillage of fuels and chemicals into the water bodies may pollute surface
water. Disposal of wastes from the drilling works surface water bodies may also deteriorate
surface water quality.
Mitigation Measures
The water body near the construction yard is also protected by temporary fencing which
might be developed as permanent boundary very soon. Moreover, there are waste collection
bins in the camp site and workers are storing the wastes in a specific place.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 7
2.2.4 Waste Management
Wastes were generated from the pipe lying, joint coating, pile straining and other
construction works. Several numbers of workers were working and moving the worksites and
generating types of wastes.
Mitigation Measures
Contractor removed the equipment, surplus material, rubbish and temporary structure of all
types and made the site/sites in clean condition to the satisfaction of local people and of the
completion of the regular works. Solid and liquid drilling wastes were managed according to
the national regulations. As a rule, solid waste must not be dumped, buried or burned at or
near the project site, but disposed of at the nearest sanitary landfill or site having and
complying with the necessary permits. At conclusion of the project, all debris and waste were
removed. Solid and liquid wastes were not being deposed of in open water bodies and
streams or other natural drainage path, fragile slopes, flood ways, religious or other sensitive
areas.
2.2.5 Drainage Congestion
The natural drainage system of the project area is already haphazard with several illegal
infrastructures and other development activities. Construction wastes may cause additional
drainage congestions if not take proper mitigations.
Mitigation Measures
All water and waste products arising from the sites was collected and removed from the site
via a suitably designed temporary drainage system. Regular cleaning of channels to avoid
choking. Drainage systems are periodically cleaned to maintain storm water flow during
construction.
2.2.6 Health and Safety of the workers
Since heavy works were going on it is necessary to use the PPE. The workers were
instructed to wear the PPE regularly during construction period. During the monitoring period
it was seen that, all the workers were using the personal protective equipment. They were
using safety boots, hard helmet and lightening vests during heavy work.
2.3 Corrective Actions Plans
We were properly implemented and solve the problems the construction area. We were
submitted to Environmental Monthly Monitoring Report, Baseline Environmental Monitoring
Report and Site-specific Environmental Management Plan. Every time we were follow our
Environmental Management plan (EMP).
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 8
Figure 2.1: Compliance with Environmental Safeguard
2.4 Compliance with IEE/EMP
In the Chittagong-Feni-Bakhrabad Gas Pipeline Project environmental and social impacts of
the projects were identified and the mitigation measures of these impacts have been
addressed through EMP submitted to Contractors before the commencement of construction
work. The protection and enhancement of human-wellbeing is a common demonstrator for
both the government and donor’s system and can be seen as the ultimate goal of
sustainable development. During construction work always tried to properly follow the EMP.
The outcome of the environmental safeguard monitoring is given in Table 2.1.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 9
Table 2.1: Outcomes of Environmental Safeguard Monitoring Exercise
Sl. Environmental Issues Observation Suggestion Remarks
1 Wearing of PPE All the engineers and workers are well equipped with helmet, highly visible clothing, and safety shoes.
Follow the mitigation measures in EMP properly Fully complied
2 First aid kits A well-equipped first aid box is kept in the site Follow the mitigation measures in EMP properly Fully complied
3 Labor rights • Payment records and attendance records are maintained.
• The labors work 10 hours a day with 1-hour lunch break.
• No below 15 child workers is seen in the site
Follow the labor law properly Fully complied
4 Disturbance to Public Utility The construction activity is not causing disturbance to any public utility.
No construction related activity beyond the project boundary.
Fully complied
5 Noise and vibration impact to nearby settlements or other environmentally sensitive areas
• Though some noise and vibrations occurred due to construction activities but no complain from the neighbors yet.
Follow the mitigation measures in EMP properly Fully complied
6 Possible groundwater contamination
• Project activities do not have any possibility to contaminate the groundwater by fuel, grease or oil.
Follow the mitigation measures in EMP properly Fully complied
7 Surface water pollution • Rainwater washed out construction materials to the surface water bodies only at the time of heavy rainfall.
The surface water bodies should be protected with earthen boundary.
Fully complied
8 Air or dust pollution • Water is sprayed regularly for controlling dust.
• Construction vehicles are checked regularly and repaired in case of any fault.
Follow the mitigation measures in EMP Fully complied
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 10
3 Environmental Quality Test
The existing environmental quality in the project influence area serves as the basis for
identification, prediction and evaluation of potential environmental impacts of the proposed
project interventions. The examining of environmental quality had been directed in
monitoring period during January 2019 to February 2020 at project site during construction
period. This present environmental quality test has been completed in these monitoring
period to look at the past condition and the current condition.
3.1.1 Air Quality
Ambient air quality data at the Contract site was measured initially to collect the baseline air
quality data and then to compare this data with the air quality data measured during project
activities to check if there are any significant changes. If there are any increased air
pollution levels as a result of the construction activities then appropriate mitigation measures
are considered and implemented as applicable.
The main air pollutants are nitrogen oxides (NOx), sulphur dioxide (SO2), PM10 (particulate
matter with diameter of 10 microns or smaller), PM2.5 (particulate matter with diameter of 2.5
microns or smaller), Motor vehicles are the major source of Particulate Matter (PM) pollution.
Most of the Particulate Matter (PM) pollutants (greater than 80%) come from diesel-run
vehicles. Dispersal of pollutants depends upon factors like prevailing wind direction and
other weather conditions, atmospheric stability, height of the source. The air quality testing
was performed at the project locations on 29 January 2019, 29 May 2019, 22 July 2019, 22
August, 06 November and 05 February 2020 (Figure 3.1). Filter paper and each chemical
were measured before testing. Electro-Chemical Sensor device were calibrated before
testing some other parameters. Results of the air quality monitored at the project location
have been showed in Table 3.1. The details analysis of the report is given in Appendix B.
Baseline Condition (January 2019)
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 11
May 2019
July 2019
August 2019
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 12
November 2019
February 2020
Figure 3.1: Air Quality Monitoring at the Project Site
The measurement results (Table 3.1) showed achievement of all air quality standards as per
scheduled mentioned in EMP. Based on the ambient air quality standard of DoE, air quality
in the project area can be stated as in good condition. Particulate matter PM10 value was
70.5 to 38.98 and PM2.5 value was 43.56 to 72.2 µg/m3 which are far below the DoE
standard. The increase of the particulate matters is due to the alteration of ground cover for
construction works and it will be returned same as the baseline shortly when construction
personnel will be withdrawn.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 13
Table 3.1: Test Results of Ambient Air Quality Monitoring
Parameter Unit
Baseline (January 2019)
For the month of May 2019
For the month of July
2019
For the month of
August 2019
For the month of November
2019
For the month of February
2020
Bangladesh Standard
Duration (hours)
Weather Condition
Method of Analysis
AAQ_01 AAQ_01 AAQ_01 AAQ_01 AAQ_01 AAQ_01
22° 30’39.3’’ N 91° 41’ 58.6’’ E
22.51003°N 91.70038°E
22.51003°N 91.70038°E
22.51003°N 91.70038°E
22.51003°N 91.70038°E
22.49333°N 91.70745°E
Kazipara (Kumira Valve
Station)
Kazipara (Kumira
Valve Station)
Kazipara (Kumira
Valve Station)
Kazipara (Kumira
Valve Station)
Kazipara (Kumira Valve
Station)
Joramtol, Banglabazar
PM2.5 µg/m3 38.98 58.5 65.4 68.4 72.2 59.87 65 24
Sunny
Gravimetric
PM10 µg/m3 43.56 68.6 70.5 65.5 69.8 53.21 150 24 Gravimetric
SO2 µg/m3 37.54 75.36 79.5 75.5 78.9 54.3 365 24 West- Geake
NOx µg/m3 26.21 86.5 88.3 76.2 80.1 61.1 100 Annual Jacob and Hochheiser
DSCL Environmental Laboratory, 2019-20
** The Bangladesh National Ambient Air Quality Standards have been taken from the Environmental Conservation Rules, 1997 which was amended on 19th July 2005 vide
S.R.O. No. 220-Law/2005 .
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 14
3.1.2 Drinking Water Quality
Drinking water, also known as potable water, is water that is safe to drink or to use for food
preparation. The amount of drinking water required to maintain good health varies, and
depends on physical activity level, age, health-related issues, and environmental conditions.
Drinking Water samples from the project influenced locations has been collected on 29
January 2019, 29 May 2019, 22 July 2019, 22 August, 06 November and 05 February 2020
(Figure 3.2). It was help to get idea that how changes the water quality from baseline
condition to construction phase condition. The parameters measured were pH, Total
Dissolved Solids (TDS), Electric Conductivity (EC), Temperature, Dissolved Oxygen (DO),
Iron (Fe), Chromium (Cr), Lead (Pb), Arsenic (As) and Oil & Grease. The samples were
collected in plastic sampling bottles, kept in an ice cooler, after necessary stabilization
/fixing, and analyzed within 72 hours of being collected. The Laboratory tests were
conducted in DPHE Laboratory. Results of drinking water sampling analysis of project area
are given at Table 3.2.
Baseline Condition (January 2019)
May 2019
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 15
July 2019
August 2019
November 2019
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 16
February 2020
Figure 3.2: Drinking Water Sampling of Project Area
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 17
Table 3.2: Test Result of Drinking Water Sampling Analysis
Parameters Unit
For the month of January 2018
For the month of May 2019
For the month of
July 2019
For the month of August 2019
For the month of
November 2019
For the month of
February 2020 Standards
for drinking Water*
Analysis Method DW_01
22° 30’ 41.9’’ N 91° 42’ 02.0’’ E
DW_01 22.51003°N 91.70038°E
DW_01 22.51003°N 91.70038°E
DW_01 22.51003°N 91.70038°E
DW_01 22.51003°N 91.70038°E
DW_01 22.49301°N 91.70737°E
Kazipara, Kumira Valve
Station
Kazipara, Kumira Valve
Station
Kazipara, Kumira Valve
Station
Kazipara, Kumira Valve
Station
Kazipara, Kumira Valve
Station
Joramtol, Banglabazar
pH* - 7.98 8.05 8.34 7.88 7.92 7.23 6.5-8.5 Multimeter
Electric Conductivity (EC)*
µs/cm 345 322 345 322 311 321
NYS Multimeter
Total Coliform (TC) N/100 ml 0 0 0 0 0 0 0 MFM
Arsenic mg/L 0.001 0.001 0.002 0.003 0.003 0.002 0.05 AAS
Iron mg/L 0.38 0.68 0.56 0.55 0.55 0.46 0.3-1.0 AAS
Chromium mg/L 0.002 0.001 0.002 0.003 0.003 0.002 0.05 AAS
Lead mg/L 0.002 0.002 0.005 0.002 0.002 0.001 0.05 AAS
Oil and Grease mg/l BDL BDL BDL BDL BDL BDL NYS 3114.C
*Standards for Drinking Water followed Environmental Conservation Rule (ECR)’97 *On-site Test Result
Source: DPHE 2019-20.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 18
The test results (Table 3.2) revealed that most of the parameters are within the national
standard for the project location during construction period according to ECR, 1997. The
laboratory test result is given in Appendix C of the report.
3.1.3 Noise Measurement
Noise Level Measurement was analyzed at project location on 29 January 2019, 29 May
2019, 22 July 2019, 22 August, 06 November and 05 February 2020 (Figure 3.3). It will help
to get idea that how changes the concentration of noise from baseline condition to
construction phase condition. The test result is given in Appendix D of this report. Noise level
data were taken during daytime are summarized along with GPS coordinate in Table 3.3.
Noise measurement at sampling location was done continuously for 10 minutes at day time.
Baseline Condition (January 2019)
May 2019
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 19
July 2019
August 2019
November 2019
February 2020
Figure 3.3: Noise Level Monitoring at the Project Location.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 20
Table 3.3: Test Result of Noise Level Analysis
Sample ID
Sample Location GPS Location Land Use Category
Time Noise Level
(dBA) (LAeq)
Bangladesh Standard (dB A)**
January 2019
NM_01 Vill: Kazipara (Kumira
Valve Station) 22° 30’39.3’’ N 91° 41’ 58.6’’ E
Residential 15:28-15:38 51.32 55
May 2019
NM_01 Vill: Kazipara (Kumira
Valve Station) 22.51013°N 91.70036°E
Residential 10:34-10.45 54.7 55
July 2019
NM_01 Vill: Kazipara (Kumira
Valve Station) 22.51013°N 91.70036°E
Residential 11:00-11.10 55.2 55
August 2019
NM_01 Vill: Kazipara (Kumira
Valve Station) 22.51013°N 91.70036°E
Residential 12:00 to 12:10 54.5 55
November 2019
NM_01 Vill: Kazipara (Kumira
Valve Station) 22.51013°N 91.70036°E
Residential 10:07 to 10:17 57.39 55
February 2020
NM_01 Joramtol Banglabazar 22.49301°N
91.70737°E Residential 11:20 to 11:30 60.21 55
Notes: ▪ Land use category is based on the classification provided in the Noise Pollution Control Rules (2006) ▪ Shaded cell indicates noise levels in excess of Noise Pollution Control Rules ambient noise limits for a given land use area ▪ The sound level standards for residential area are 55 at day time and 45at night time. ▪ Noise Level is the average noise recorded over the duration of the monitoring period
The result shows that time weighted average value of the sound monitored inside the project
exceeded the standard set for the residential area during the construction work due to
construction work and people movement. The details analysis of the report is given in
Appendix D of the report.
3.1.4 Liquid Waste Test
When the construction work had finished, some liquid waste is left in the construction site.
To analysis the quality liquid waste sample were collected from project influenced locations
on 29 May 2019, 22 July 2019, 22 August, 06 November and 05 February 2020 (Figure 3.4).
The parameters measured were pH, Electric Conductivity (EC), Iron (Fe), Chromium (Cr),
Lead (Pb), Arsenic (As) and Total Coliform (TC), Turbidity, BOD, Oil and Grease. The
samples were in plastic sampling bottles, kept in an ice cooler, after necessary stabilization
/fixing, collected and analyzed within 72 hours of being collected. The Laboratory tests were
conducted in DPHE Laboratory.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 21
May 2019
July 2019
August 2019
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 22
November 2019
February 2020
Figure 3.4: Liquid Waste Sample Collection at the project location.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 23
Table 3.4: Test Result of Liquid Waste Water Sampling Analysis
Parameters Unit
For the month of May 2019
For the month of July 2019
For the month of
August 2019
For the month of May November
2019
For the month of May February 2019
Standards for Inland Surface
Water Analysis Method
LW_01 23.10054°N 91.27560°E
LW_01 23.10054°N 91.27560°E
LW_01 23.10054°N 91.27560°E
LW_01 23.10054°N 91.27560°E
LW_01 22.49319°N 91.70741°E
Construction Site of the
Project
Construction Site of the
Project
Construction Site of the
Project
Construction Site of the
Project
Construction Site of the Project
pH* - 8.6 8.5 8.2 8.6 9.21 6.5-8.5 Multimeter
Electric Conductivity (EC)*
µs/cm 322 320 355 444 812 NYS Multimeter
TDS Mg/l 2678 2678 2732 2889 2339
Turbidity NTU 42 43 45 49 59 NYS Turbidity Meter
BOD mg/L 5 6 6 2 5.3 NYS 5 days incubation
Chromium mg/L 0.002 0.003 0.003 0.003 0.003 NYS AAS
Lead mg/L 0.002 0.004 0.002 0.004 0.002 NYS AAS
Oil and Grease mg/l Less than 2.0 Less than 2.0 Less than 2.0 Less than 2.0 Less than 2.0 NYS 5520.B
*Standards for Inland Surface Water is followed Environmental Conservation Rule (ECR)’97 * On-site Test Result
Source: DPHE Laboratory Test, 2019-20; NYS = Not Yet Standardized
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 24
The liquid waste water quality standard is yet not developed in the ECR 1997 except for few
parameters. Above the tested parameters and results the BOD values are below the national
standard for the sampling location. The details analysis id given in Appendix E of the report.
4 Tree Plantation
Some Tree, herbs and shrubs has been damaged/cut during site preparation and work
activities for proposed route of pipeline. The aquatic flora and habitat have been damaged
/affected when gas pipeline cross the water body. In order to mitigate this impact, avoid
felling of trees as much as possible. Give proper compensation against homestead tree
felling to the owners. Local people request to avoid large water bodies, homestead garden
for the installation of gas pipe line.
Trees absorb carbon dioxide and release oxygen in daytime due to photosynthesis, thus
clean air from noxious carbon-di-oxide gas. The timber, fruit, fuel and medicine values of
tree are immense. Roadside trees intercept dust with leaves and twigs keeping ambient air
dust free. Tree plantation has other general advantages like improvement of environment,
ecology and economy therefore, planting tree on road side slopes and other available
spaces within the ROW would enhance environment, economy and help alleviating rural
poverty through work generation. In addition, dense tree plantation at both sides of the road
embankment has special positive impact like protection of the coastal area from cyclonic
storm. They also conduct tree plantation program in four villages. Tree plantation and
distribution program enhance the perception of people on good environment and also
conservation of the biodiversity. The objective of the tree plantation and replacement
programme is to compensate for the loss of trees due to the proposed implementation of
road upgrading. Other major objectives of the programme are to protect the affected
cultural/sensitive areas and to enhance the health of the existing ecosystem. Tree
planting/revegetation was done to designated areas identified by PIU-GTCL in consultation
with Forest Department.
Gypsum and GTCL staffs, official and villagers were participated in this program. Some snap
of that awareness programme is given below:
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 25
Figure 4.1: Tree Plantation Programme around the Project Location
5 Conclusion
The environmental safeguard monitoring has been conducted in the vicinity of the
Chittagong-Feni-Bakhrabad Gas Pipeline Project through routine and event based. The main
aims of this monitoring activity are to control and reduce the adverse impact during the work.
All the environmental preparatory activities that have ensure that consideration was given to
environmental protection during the construction stage have been put in place. In order to
attain and sustain the expected goals after the project completion, it is indispensable for
project authority to disseminate the manuals, to use the manuals effectively, and to update
the manuals timely. Therefore, the environmental action plan for dissemination and effective
use of the manuals will be prepared through the discussions with project proponent. To
identify the potential impacts likely to be generated by the project and provide a set of action
it needs to implement in order to meet national and international environmental safeguard
standards.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 26
APPENDIX
Appendix A: Environmental Monitoring Checklist
No. Aspects of Environmental issues
Compliance Status
Remarks
FC PC NC
A. General
1. Legal working hours approval The workers work 10 hours a day at site including 1-hour lunch break. Sometimes worker taking rest if they feel bored due to work.
2. Employment Record keeping arrangement
The employment records are kept in a register book manually every day in the field.
3. Payment Record keeping arrangement The payment records are kept in a register book manually every day in the field.
4. Environment, Health and Safety Officer designated
Environmental officer is appointed.
5. Provision for monthly meeting for inspection of site activities
Meetings are called about working progress, environmental compliance and future planning every month.
B. Health and Sanitation
Occupational Health
1. First-Aid Box availability at work sites A well-equipped first aid box is available at the site
2. Provision of personal protection equipment’s (PPEs)
Site Engineers, supervisors and workers are provided with PPEs including vests, helmets, safety boots etc.
3. Handling of cement and other hazardous materials by workers
No hazardous materials are used.
4. Workers’ complains taken care of by the supervisor
A supervisor for the workers is appointed to take care of the problems and receiving complaints from the workers and solving those problems accordingly.
5. Children below 15 employment There is no below 15 child working in the site
C. Environmental Pollution
Dust and emission control
1. Construction vehicles and machineries maintained properly to reduce emissions
The vehicles and machineries are maintained properly with least pollution.
2. Proper storage of materials and regular watering.
The materials are stored in proper manner and watering is done regularly to mitigate air pollution.
Noise Pollution
1. Movement of vehicles at desired hours Heavy vehicles movements are done mostly from morning to afternoon.
2. Noise control measures at sites Noise created due to construction and heavy machineries affects less on the surrounding
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 27
No. Aspects of Environmental issues
Compliance Status
Remarks
FC PC NC
households.
Water Pollution
1. Wastes, cement, effluents and junks not disposed in water
No wastes are disposed in water. Proper measures are taken for preventing rain wash.
Flora and Fauna
1. Trees and bushes outside the construction area preserved from damages
The trees and bushes outside the construction area are fully preserved from damages.
2. Disturbance to terrestrial fauna minimized
There are not much highly disturbing works going, no hazardous substances used on in the project site. But if noise producing work needed, works are done within day time with noise control measures to minimize the disturbance.
3 Tree Plantation Tree planting/revegetation was done to designated areas identified by PIU-GTCL in consultation with Forest Department
Waste Management
1. Construction wastes are removed off site regularly
The wastes are kept in a specific place and they are removed off site regularly.
2. Chemical wastes, if any, collected and disposed of properly
During the monitoring period, no sources of chemical wastes are seen.
D. Environmental documents at Field Office and Project sites
1. Field Office possesses copies of EMP, contract document and Technical Specifications
All the documents are kept in the field office.
2. Heavy equipment maintenance records Few heavy equipment issued in the site and the maintenance records are kept.
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 28
Appendix B: Air Quality Test Results
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 29
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 30
Appendix C: Drinking Water Quality Test Results
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 31
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 32
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 33
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 34
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 35
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 36
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 37
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 38
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 39
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 40
Appendix D: Noise Level Measurement Test Result
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 41
Appendix E: Liquid Waste Quality Test Results
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 42
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 43
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 44
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 45
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 46
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 47
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 48
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 49
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 50
Section A: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring Report for the Month of February 2020 by ARC Construction Company (Completion Report) 51
Environmental Monitoring and Quality Test
Report for the Month of February 2020
for
Installation of Two (02) Town Bordering Station (TBS) and One (01)
Metering Station Under Construction of Chittagong-Feni-Bakrabad
Gas Transmission Parallel Pipeline Project
February 2020
Prepared for
SUNNEX LIMITED
65, Dilkusha C/A, 2nd Floor; Dhaka-1000, Bangladesh
Tel: 956-2146; Fax: 8802-2-956-4423
Email: [email protected]
Prepared by
Development Solutions Consultant Limited (DSCL)
House-734 (5-B), Road-10, Avenue-04, DOHS Mirpur,
Dhaka -1216, Bangladesh, Tel: +8801822758548
Email: [email protected] Website: www.dsclbd.com
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakhrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited i
Table of Contents
EXECUTIVE SUMMARY ................................................................................................... 1
1 Introduction ........................................................................................................... 2
1.1 Project Background .......................................................................................... 2
1.1.1 Project Location ............................................................................................ 2
1.2 Scope of Works ............................................................................................... 4
1.3 Environmental Management Control Objectives .................................................. 4
1.4 Purpose of the Report ...................................................................................... 4
1.5 Methodology ................................................................................................... 4
1.6 Construction Activities during Monitoring Period.................................................. 5
2 Environmental Safeguard Monitoring ........................................................................ 5
2.1 Environmental Monitoring Issues as per EMP ...................................................... 5
2.2 Monitoring Details ............................................................................................ 5
2.2.1 Sound Level ................................................................................................. 6
2.2.2 Water Quality ............................................................................................... 6
2.2.3 Air Quality/Dust ............................................................................................ 6
2.2.4 Drainage Congestion ..................................................................................... 7
2.2.5 Waste Management ...................................................................................... 7
2.2.6 Health and Safety of the workers ................................................................... 7
2.3 Corrective Actions Plans ................................................................................... 9
2.4 Compliance with IEE/EMP ................................................................................. 9
3 Environmental Quality Test..................................................................................... 11
3.1 Air Quality ...................................................................................................... 11
3.2 Drinking Water Quality .................................................................................... 13
3.3 Noise Measurement......................................................................................... 17
3.4 Liquid Waste Quality ....................................................................................... 19
4 CONCLUSION ........................................................................................................ 21
APPENDIX ................................................................................................................... 22
Section H: Construction of Chittagong-Feni-Bakhrabad Gas Transmision Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited ii
List of Table
Table 2.1: Outcomes of Environmental Safeguard Monitoring Exercise .............................. 10
Table 3.1: Test Results of Ambient Air Quality Monitoring ................................................ 12
Table 3.2: Description of the Surrounding Environment ................................................... 13
Table 3.3: Test Result of Drinking Water Sampling Analysis ............................................. 15
Table 3.4: Description of the Surrounding Environment ................................................... 16
Table 3.5: Test Results of Noise Level Monitoring at Location .......................................... 17
Table 3.6: Description of the Surrounding Environment ................................................... 18
List of Figures
Figure 1.1: Project Location Map ....................................................................................................... 3
Figure 2.1: Compliance with Environmental Safeguard ..................................................... 8
Figure 3.1: Air Quality Monitoring at the Project Locations ............................................... 11
Figure 3.2: Drinking Water Sampling of Project Location ................................................. 14
Figure 3.3: Noise Level Monitoring at the Project Location. .............................................. 17
Figure 3.4: Liquid waste collection from the Project Location ........................................... 19
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 1
Executive Summary
The Construction of Chittagong-Feni-Bakhrabad Gas Transmission Parallel Pipeline Project
is funded by Asian Development Bank (ADB) with cofinancing from the Asian Infrastructure
Investment Bank. The growing demand for natural gas by the industrial centres in
Chittagong, Noakhali, Comilla and adjoining areas is not sustained by the GTCL. At present,
the existing Chittagong-Bakhrabad gas transmission pipeline is not adequate to meet the
supply of gas for distribution in this region. The Project will involve the construction of gas
transmission pipeline from Chittagong to Bakhrabad in the Southeast region of Bangladesh.
The main purpose of this report is the project is developed in an environmentally sound and
sustainable manner ensuring that all negative effects are mitigated and positive impacts are
enhanced. More specifically, the aims of the baseline report are to identify potential impacts
likely to be generated by the project; to quantify and where possible value these, providing a
set of actions it needs to implement in order to meet national and international environmental
safeguard standards.
The gas transmission pipeline route traverses the districts of Chittagong, Feni, and Comilla
covering 11 subdistricts (upazila). The nearest distance of project site from the border of
India is about 10 km. The project was involving the construction of gas transmission pipeline
(36-inch, 181 km), nine associated valve stations, a pig launcher, two town border station
(TBS), a pig receiver and a metering station. The monitoring studies was covering the
installation of Two (02) town bordering station which is in (i) Mireshorai, Chittagong; (ii)
Bizra, Comilla Site and One metering station in in the Bakhrabad, Comilla site.
The main aims of this environmental monitoring are to control and reduce the adverse
impacts during construction phase. Construction workers may be affected adversely due to
hazardous working environments such as air quality which is declined due to construction
vehicles and machineries; noise and vibration generated from construction vehicle, water
pollution by disposal of construction waste and health of construction worker for maintaining
heavy machineries. To take action to minimize dust generation, noise pollution, water
pollution, waste management and worker health and safety. The primary data were collected
from construction areas by visual observation; fill-up a checklist; note taking; capture
photographs and consultation with site engineer.
From the environmental assessment it is found that all the air quality parameters are within
national standard of Bangladesh. Noise level are exceeding the national standard for the
sampling location for construction noise. The contractors are trying to mitigate noise level
pollution by the use temporary noise barriers, equipment engines and motors are equipped
with proper mufflers and by using the sound reducing modern techniques. Drinking water
quality concentration levels were within the national standard. From the liquid waste results,
it is seen that, the parameters contain higher value in the project locations. In order to
mitigate liquid waste pollution proper measures should be taken for preventing rain wash. In
future, contactor should must safely and legally manage that waste water from pollution.
Adequate mitigation measures were devised according to the environmental management
plan (EMP) of Initial Environmental Examination (IEE) to mitigate/minimize all environmental
impacts due to project construction related activities. During the field observation and data
collection, consultations were also held with the person of designated site engineer by
contractor and consultant. Outcome of these consultations were used in impact assessment
and devising mitigation measures.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 2
1 Introduction
1.1 Project Background
Natural gas is a significant source of commercial energy in Bangladesh and is the prime
mover of its national economy. There is a growing demand for a steady and reliable supply
of natural gas in the Southeast region to support its industrialization and commercial
developments. The Government of Bangladesh (GoB) has recognized this need and
considers it a priority to expand the gas transmission capacity in this region. The growing
demand for natural gas by the industrial centrist in Chittagong, Noakhali, Comilla and
adjoining areas is not sustained by the Gas Transmission Company Limited (GTCL). At
present, the existing Chittagong Bakhrabad gas transmission pipeline is not adequate to
meet the supply of gas for distribution in this region. The Project aims to increase the
contribution of the energy sector to sustainable economic growth by financing the
improvement of efficiency in gas production from existing gas field, and expansion of
transmission pipeline capacity through construction of gas transmission pipelines.
1.1.1 Project Location
The gas transmission pipeline route traverses the districts of Chittagong, Feni, and Comilla
covering 11 subdistricts (upazila). The nearest distance of project site from the border of
India is about 10 km. The project was involving the construction of gas transmission pipeline
(36-inch, 181 km), nine associated valve stations, a pig launcher, two town border station
(TBS), a pig receiver and a metering station. The monitoring studies was covering the
installation of Two (02) town bordering station which is in (i) Mireshorai, Chittagong; (ii)
Bizra, Comilla Site and One metering station in in the Bakhrabad, Comilla site. The project
location map is shown in Figure 1.1. of the report.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 3
Figure 1.1: Project Location Map
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 4
1.2 Scope of Works
This environmental monitoring report has been prepared keeping in view the Environmental
Management Plan (EMP) for Installation of Two (02) Town Bordering Station (TBS) and One
(01) Metering Station of the Chittagong-Feni-Bakhrabad Gas Transmission Parallel Pipeline
Project. The scope of the present environmental monitoring report follows the EMP including
drainage congestion monitoring, ambient air and water quality and ambient sound level
monitoring along with monitoring of the health and safety of the workers.
1.3 Environmental Management Control Objectives
❖ The level of air dust is increased due to construction activities and transport of
construction materials; air quality is declined due to construction vehicle and
machineries; action to be taken to minimized dust generation.
❖ The noise and vibration generated during the construction period from construction
vehicle, equipment and machineries to impact on the surrounding areas; use
modern plant of all powered mechanical equipment with noise abating gear such as
muffler for effective noise control.
❖ Water body at construction area is polluted by disposal of construction waste;
proper method uses for construction waste disposal and control water pollution.
❖ The construction area keeps clean and tidy, construction waste, garbage in a timely
manner to be dealt with and free from clutter.
❖ To ensure the health of construction workers prevented from harm; to ensure the
nearby residents are not affected; to ensure the safety of road pedestrians and
vehicles.
1.4 Purpose of the Report
The main purpose of the report includes,
➢ To present the scenario of the project site in every month.
➢ To monitor the environmental safeguard of the project area.
➢ To monitor the occupational and public health and safety of the project area.
➢ To monitor the environmental pollution in the project area due to the construction
activities.
1.5 Methodology
The following steps were followed to prepare the report:
➢ The IEE reports and EMP Table were reviewed to get proper idea about the EMP.
➢ Regular meetings were conducted with the site engineers.
➢ Regular site visit was done by the Environmental monitoring officer to monitor the
environmental safeguard of the project area.
➢ Photographs were taken from the site of the construction activities.
➢ Environmental screening checklist was fulfilled to monitor the environmental
safeguard.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 5
1.6 Construction Activities during Monitoring Period
During this reporting month of February 2020, major activities include site preparation, civil
work for the construction of site control building, casting and piling work at Mirsharai, Bizra
and Bakhrabad construction site. These major activities have been scheduled efficiently to
ensure the completion of the project construction work within the dry working season. Waste
from construction activities has been collected regularly and disposed of at sites designated
by project proponent.
2 Environmental Safeguard Monitoring
The environmental safeguard monitoring report is prepared through regular basis field visit
within the construction areas of impacted zone for various components of the environment.
The condition of existing environmental quality in the locality of project site serves as the
basis for identification, prediction and evaluation of impacts. The environmental quality is
assessed through construction sites visited; capture some photograph; consultation with site
engineer within the impacted zone for various components of the environment. In order to
depict the existing physical environment in the project area, a few of the major parameters
are considered like drainage system, air pollution, noise and vibration, surface and ground
water quality, waste management etc.
The Contractors are made aware of this obligation and their safeguard performance
monitoring during construction was closely supervised and monitored by Environmental
Officer and Project Engineers with close supervision of the Project Supervision Consultants.
In Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project, environmental and
social impacts of the projects were identified and the mitigation measures of these impacts
have been addressed through Environmental Management Plan (EMP). The protection and
enhancement of human-wellbeing is a common demonstrator for both government and
donor’s system and can be seen as ultimate goal of sustainable development.
2.1 Environmental Monitoring Issues as per EMP
During the monitoring period, the issues which were monitored include,
❖ Environmental pollution (dust, noise, soil and water) due to project activities.
❖ Monitoring of several issues listed in the EMP.
❖ Provision of safe water, sanitary toilet facility for workers.
❖ Provision of adequate occupational health safety, fire safety facilities.
❖ Monitoring of waste management system.
❖ Monitoring drainage system and vegetation.
2.2 Monitoring Details
Environmental monitoring is an essential tool for environmental management as it provides
the basic information for rational management decisions. The purpose of the monitoring
program is to ensure that the envisaged purposes of the project are achieved and result in
desired benefits to the target population.
Some of the important impacts associated with the project are associated with land use, land
stability (soil erosion), soil compaction and contamination, water availability, water quality,
ground water contamination, waste and wastewater disposal, ambient air quality, ambient
noise levels, vegetation, tree cutting, drainage system, hydrology, climate change,
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 6
construction material sourcing and occupational health and safety. Adequate mitigation
measures are devised to mitigate/minimize all likely environmental impacts and the same
have been presented along with the impacts. During the field observation and data
collection, consultations were also held with the person of designated site engineer.
Outcome of these consultations were used in impact assessment and devising mitigation
measures.
2.2.1 Sound Level
Noise from the machines and vibrations caused by the construction activities are the major
pollutants in the construction site of the project. Being an agricultural cum residential area,
the ambient standard is Leq 55 dB (A) (daytime) and Leq 45 dB (A) (night time) (DoE, 2006).
The increase in noise was not significant during construction since the project area is
already under fencing by retaining wall.
Mitigation Measures
All powered mechanical equipment and machinery were repaired and checked before
commencing the work for effective sound reducing; in full compliance with the DoE
regulations. The noisiest operations were performed during daytime. Proper equipment
maintenance and restricted operation between 0700 to 1800 hours to reduce noise.
2.2.2 Water Quality
In the project influenced area, about 80% of the domestic water supply is obtained from the
middle aquifer, extracted by tube wells throughout the city. Recent studies have shown that
water levels have fallen dramatically, and suggest that the aquifer may be changing from a
confined to an unconfined condition, which could make it vulnerable to contamination.
Groundwater quality decreased by liquid wastes can have serious effects on the quality of
drinking water in the Project area for several years. Uncontrolled dumping of drilling wastes,
and accidental spillage of fuels and chemicals into the water bodies may pollute surface
water. Disposal of wastes from the drilling works into the near surface water bodies may also
deteriorate surface water quality.
Mitigation Measures
The water body near the construction yard is also protected by temporary fencing which will
be developed as permanent boundary very soon. Moreover, there are waste collection bins
in the camp site and workers are storing the wastes in a specific place.
2.2.3 Air Quality/Dust
Construction work involves breaking up, digging, transporting, and dumping large
quantities of dry material. It will inevitably lead to an increase in particulate matter in and
around the construction zones. Possible sources of air pollution were dust due to
construction activities, machinery movement and other sources. However, due to the
barrier of construction sites and wind conditions the dust and engine emissions are
expected to have limited effect on the air quality. Dispersal of pollutants depends upon
factors like prevailing wind direction and other weather conditions, atmospheric stability,
height of the source. Dust generation due to construction activities, transport of
construction materials and emission from vehicles, equipment and machinery.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 7
Mitigation Measures
Spraying of water is the main way of controlling dust. To mitigate dust problem during
construction period, all relevant areas are suggested to spray at least two times (morning
and evening) by use sprinkler properly. However, due to the dry period the surface was
mostly dry in most of the cases thus additional water spraying was conducted sometimes at
that condition.
2.2.4 Drainage Congestion
The natural drainage system of the project area is in significant level. Construction wastes
may cause additional drainage congestions if not take proper mitigations.
Mitigation Measures
All water and waste products arising from the sites was collected and removed from the site
via a suitably designed temporary drainage system. Regular cleaning of channels to avoid
choking. Drainage systems are periodically cleaned to maintain storm water flow during
construction.
2.2.5 Waste Management
Wastes were generated from the borehole drilling works and civil works construction.
Several numbers of workers were working and moving the worksites and generating types of
wastes.
Mitigation Measures
Removing of all the equipment, surplus material, rubbish and temporary structure of all types
and made the site/sites in clean condition to the satisfaction of local people and of the
completion of the regular works. Solid and liquid drilling wastes were managed according to
the national regulations. As a rule, solid waste must not be dumped, buried or burned at or
near the project site, but disposed of at the nearest sanitary landfill or site having and
complying with the necessary permits. At conclusion of the project, all debris and waste were
removed. Solid and liquid wastes were not being deposed of in open water bodies and
streams or other natural drainage path, fragile slopes, flood ways, religious or other sensitive
areas.
2.2.6 Health and Safety of the workers
Since heavy works were going on it is necessary to use the PPE. The workers were
instructed to wear the PPE regularly during construction period. During the monitoring period
it was seen that, all the workers and site engineers were using the personal protective
equipment. They were using safety boots, hard helmet and lightening vests during heavy
work.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 8
Workers Using Personal Protective Equipment During the Construction Works
Figure 2.1: Compliance with Environmental Safeguard
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 9
2.3 Corrective Actions Plans
We were properly implemented and solve the problems the construction area as per the
instruction and requirements of GoB. We were submitted to Baseline Environmental
Monitoring Report. Every time we were follow our Environmental Management plan (EMP).
2.4 Compliance with IEE/EMP
In the Chittagong-Feni-Bakhrabad Gas Pipeline Project environmental and social impacts of
the projects were identified and the mitigation measures of these impacts have been
addressed through EMP submitted before the commencement of construction work. The
protection and enhancement of human-wellbeing is a common demonstrator for both the
government and donor’s system and can be seen as the ultimate goal of sustainable
development. During construction work always tried to properly follow the EMP. The
outcome of the environmental safeguard monitoring is given in Table 2.1.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited
10
Table 2.1: Outcomes of Environmental Safeguard Monitoring Exercise
Sl. Environmental Issues Observation Suggestion Remarks
1 Wearing of PPE All the engineers and workers are well equipped with helmet, highly visible clothing, and safety shoes.
Follow the mitigation measures in EMP properly
Fully complied
2 Surface water pollution Rainwater washed out construction materials to the surface water bodies only at the time of heavy rainfall.
The surface water bodies should be protected with earthen boundary.
Partially complied
3 Air or dust pollution • Water is sprayed regularly for controlling dust.
• Construction vehicles are checked regularly and repaired in case of any fault.
Follow the mitigation measures in EMP
Fully complied
4 Labor rights
• Payment records and attendance records are maintained er.
• The labors work 10 hours a day with 1 hour lunch break.
• No below 15 child worker is seen in the site
Follow the labor law properly Fully complied
5 First aid kits • A well-equipped first aid box is kept in the site Follow the mitigation measures in EMP properly
Fully complied
6 Disturbance to Public Utility The construction activity is not causing disturbance to any public utility.
No construction related activity beyond the project boundary.
Fully complied
7 Noise and vibration impact to nearby settlements or other environmentally sensitive areas
• Though some noise and vibrations occurred due to construction activities but no complain from the neighbors yet.
Follow the mitigation measures in EMP properly
Partially complied
8 Possible groundwater contamination
• Project activities do not have any possibility to contaminate the groundwater by fuel, grease or oil.
Follow the mitigation measures in EMP properly
Fully complied
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 11
3 Environmental Quality Test
The existing environmental quality in the project influence area serves as the basis for
identification, prediction and evaluation of potential environmental impacts of the proposed
project interventions. The environmental quality has been assessed through field studies
during 05 February to 06 February, 2020 within the impact zone and analysis the information
for various components of the environment, viz. air, noise, water etc. The quality test has
been carried out in February 2020 to compare the previous condition (baseline condition)
and the existing condition.
3.1 Air Quality
Ambient air quality data at the project site measured to verify the current quality of air. The
aim was to collect the baseline air quality data and to compare the data with the air quality
data during future project activities to check if there is any high air pollution level due to the
construction activities and to design adequate mitigation measures, as applicable. The main
air pollutants are nitrogen oxides (NOx), sulphur dioxide (SO2), PM10 (particulate matter with
diameter of 10 microns or smaller), PM2.5 (particulate matter with diameter of 2.5 microns or
smaller), Motor vehicles are the major source of Particulate Matter (PM) pollution. Most of
the Particulate Matter (PM) pollutants (greater than 80%) come from diesel-run vehicles.
Dispersal of pollutants depends upon factors like prevailing wind direction and other weather
conditions, atmospheric stability, height of the source. The air quality testing was performed
at the 03 project locations from 05 February to 06 February, 2020 (see Figure 3.1). Filter and
each chemical were measured before testing. Electro-Chemical Sensor device were
calibrated before testing some other parameters. Results of the air quality monitored at the
project locations have been showed in Table 3.1. The details of this result are shown in
Appendix B of this report.
Borotakiya, Upa: Mireshorai, Dist: Chittagong
Bakhrabad, Up: Muradnagar; Dist: Comilla Bizra, Upa: Laksham; Dist: Comilla
Figure 3.1: Air Quality Monitoring at the Project Locations
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 12
Table 3.1: Test Results of Ambient Air Quality Monitoring
Parameter Unit
Concentration Present on February 2020 Concentration Present on November 2019
(Baseline)
Bangladesh Standard
Duration (hours)
Weather Condition
Method of Analysis
AAQ_Mireshorai AAQ_Bakhrabad AAQ_Bizra AAQ_Mireshorai AAQ_Bakhrabad AAQ_Bizra
23.75178°N 090.57397°E
23.63168°N 090.89047°E
23.31529°N 090.09068°E
23.75178°N 090.57397°E
23.63168°N 090.89047°E
23.31529°N 090.09068°E
Boratakiya Upa: Mireshorai, Dist: Chittagong
Bakhrabad, Upa:
Muradnagar; Dist: Comilla
Bizra; Upa:
Laksham; Dist:
Comilla
Boratakiya Upa: Mireshorai, Dist: Chittagong
Bakhrabad, Upa:
Muradnagar; Dist: Comilla
Bizra; Upa:
Laksham; Dist:
Comilla
PM2.5 µg/m3 41.23 32.59 37.13 39.76 33.56 35.39 65 24 Sunny Gravimetric
PM10 µg/m3 96.78 75.65 80.31 98.65 76.39 78.32 150 24 Gravimetric
SO2 µg/m3 35.97 31.11 26.78 34.49 28.98 30.76 365 24 West- Geake
NOx µg/m3 31.13 37.87 34.98 29.31 36.90 33.66 100 Annual Jacob and Hochheiser
DSCL Environmental Laboratory, February 2020
** The Bangladesh National Ambient Air Quality Standards have been taken from the Environmental Conservation Rules, 1997 which was amended on 19th July 2005 vide S.R.O. No. 220-
Law/2005.
*CO Concentrations are 8 hours only
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 13
Table 3.2: Description of the Surrounding Environment
Location Sample Site Description
AAQ_Mireshorai
(Boratakiya, Upa: Mireshorai, Dist: Chittagong)
➢ The weather was mostly sunny. ➢ Lower Amount of Dust Particles are present. ➢ Vehicle and people movement was high. ➢ Beside Economic Zone Access Road. ➢ Construction work ahead.
AAQ_Bakhrabad
(Bakhrabad, Upa: Muradnagar;
Dist: Comilla)
➢ The weather was mostly sunny. ➢ Moderate Amount of Dust Particles are present. ➢ Lower amount of people movement. ➢ Beside Local Road. ➢ Construction work ahead.
AAQ_Bizra
(Bizra; Upa: Laksham; Dist: Comilla)
➢ The weather was mostly sunny. ➢ Lower Amount of Dust Particles is present. ➢ People Movement was high. ➢ Some construction works ahead.
PM10: Particle pollution, also called particulate matter or PM is a mixture of solids and liquid
droplets floating in the air. Some particles are released directly from a specific source, while
others form in complicated chemical reactions in the atmosphere.PM10 are 2.5 to 10
micrometers in diameter. Sources include crushing or grinding operations and dust stirred up
by vehicles on roads. From the above table of test results, it is seen that, for all of the
locations, the value was within the national standard.
PM2.5: PM2.5 are 2.5 micrometers in diameter or smaller, and can only be seen with an
electron microscope. Fine particles are produced from all types of combustion, including
motor vehicles, power plants, residential wood burning, forest fires, agricultural burning, and
some industrial processes. The test results show that for all of the locations the values of
PM2.5 was within the national standards.
SOx: Sulfur oxides (SOx) are compounds of sulfur and oxygen molecules. Sulfur dioxide
(SO2) is the pre-dominant form found in the lower atmosphere. It is a colorless gas that can
be detected by taste and smell in the range of 1,000 to 3,000 micrograms per cubic meter
(μg/m3). From the test results it can be said that, for all of the locations, the value was in
within the national standard.
NOx: In atmospheric chemistry, NOx is a generic term for the nitrogen oxides that are most
relevant for air pollution, namely nitric oxide (NO) and nitrogen dioxide (NO2). These gases
contribute to the formation of smog and acid rain, as well as tropospheric ozone. The test
results above show that, for all of the locations the values of NOx are within the national
standard.
3.2 Drinking Water Quality
Drinking water, also known as potable water, is water that is safe to drink or to use for food
preparation. The amount of drinking water required to maintain good health varies, and
depends on physical activity level, age, health-related issues, and environmental conditions.
Three (03) Drinking Water sample were collected from the project influenced locations form
05 February 2020 to 06 February 2020 (Figure 3.2). The parameters measured were pH,
Electric Conductivity (EC), Iron (Fe), Chromium (Cr), Lead (Pb), Arsenic (As), Total Coliform
(TC) and Oil & Grease. The samples were collected in plastic sampling bottles, kept in an ice
cooler, after necessary stabilization /fixing, and analyzed within 72 hours of being collected.
The Laboratory tests were conducted in DPHE Laboratory. Results of drinking water
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of
Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 14
sampling analysis of project area are given at Table 3.3. The details of this result are shown
in Appendix C of this report.
Bakhrabad, Up: Muradnagar; Dist: Comilla
Borotakiya, Upa: Mireshorai, Dist: Chittagong Bizra, Upa: Laksham; Dist: Comilla
Figure 3.2: Drinking Water Sampling of Project Location
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 15
Table 3.3: Test Result of Drinking Water Sampling Analysis
Parameters Unit
Concentration Present on February 2020 Concentration Present on November 2019
(Baseline)
Standards for drinking Water*
Analysis Method
DW_Mireshorai DW_Bakhrabad DW_Bizra DW_Mireshorai DW_Bakhrabad DW_Bizra
23.75237°N 090.57401°E
23.63147°N 090.89409°E
23.31496°N 091.09035°E
23.75237°N 090.57401°E
23.63147°N 090.89409°E
23.31496°N 091.09035°E
Borotakiya Upa:
Mireshorai, Dist:
Chittagong
Bakhrabad, Upa:
Muradnagar; Dist: Comilla
Bizra; Upa:
Laksham; Dist:
Comilla
Borotakiya Upa:
Mireshorai, Dist:
Chittagong
Bakhrabad, Upa:
Muradnagar; Dist: Comilla
Bizra; Upa:
Laksham; Dist:
Comilla
pH* - 7.23 7.67 7.56 7.79 7.96 7.74 6.5-8.5 Multimeter
Electric Conductivity (EC)*
µs/cm 266 331 269 274 398 287 NYS Multimeter
Total Coliform (TC)
N/100 ml
0 0 0 0 0 0 0 MFM
Arsenic mg/L 0.001 0.002 0.001 0.002 0.001 0.003 0.05 AAS
Iron mg/L 0.33 0.39 0.41 0.39 0.41 0.37 0.3-1.0 AAS
Chromium mg/L 0.001 0.002 0.003 0.001 0.003 0.002 0.05 AAS
Lead mg/L 0.003 0.002 0.001 0.003 0.002 0.001 0.05 AAS
Oil & Grease mg/L BDL BDL BDL BDL BDL BDL NYS 3114.C
*Standards for Drinking Water followed Environmental Conservation Rule (ECR)’97
*On-site Test Result.
NYS-Not Yet Standardized; BDL-Below Detection Limit
Source: DPHE and DU February 2020
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 16
Table 3.4: Description of the Surrounding Environment
Sample Location and ID Sample Site Description
DW_Mireshorai
(Boratakiya Upa: Mireshorai, Dist: Chittagong)
➢ Boring was 300ft. ➢ The source was established in 2018. ➢ The water is used for drinking purposes.
DW_Bakhrabad
(Bakhrabad, Upa: Muradnagar; Dist: Comilla)
➢ Boring was 350 ft. ➢ The source was established on 2018. ➢ The water is used for drinking purposes. ➢ The owner of the source is GTCL.
DW_Bizra
(Bizra; Upa: Laksham; Dist: Comilla)
➢ Boring was 300-320ft. ➢ The source was established in 2019. ➢ Distance of the source from septic tank is 50m. ➢ The water is used for drinking purposes
pH: The "desirable" range of pH prescribed by the DoE is between 6.5 and 8.5. This is the
range, which provides adequate protection to the life of fresh water fish and bottom dwelling
invertebrates. The pH value of the all drinking water samples was within the national standard.
Electrical Conductivity (EC): EC stands for electrical conductivity, which measures the
potential for a material to conduct electricity. The test results show that the values of EC is
within the national standard for all of the sampling location.
Iron (Fe): Natural waters contain variable amounts of iron depending on the geological area
and other chemical components of the waterway. Iron in groundwater is normally present in the
ferrous or bivalent form [Fe++] which is soluble. It is easily oxidized to ferric iron [Fe+++] or
insoluble iron upon exposure to air. The concentration of iron was within the national standard
for the all of the sampling locations.
Arsenic (As): Arsenic is a natural component of the earth’s crust and is widely distributed throughout the environment in the air, water and land. It is highly toxic in its inorganic form.
People are exposed to elevated levels of inorganic arsenic through drinking contaminated
water, using contaminated water in food preparation and irrigation of food crops, industrial
processes, eating contaminated food and smoking tobacco. The concentration of arsenic was
within the acceptable limit for the drinking water samples.
Total Coliform (TC): Total coliforms are a group of bacteria that are widespread in nature. All
members of the total coliform group can occur in human feces, but some can also be present in
animal manure, soil, and submerged wood and in other places outside the human body. Thus,
the usefulness of total coliforms as an indicator of fecal contamination depends on the extent to
which the bacteria species found are fecal and human in origin. The values of TC were nil for all
of the sampling locations.
Lead (Pb): Lead can enter drinking water when service pipes that contain lead corrode,
especially where the water has high acidity or low mineral content that corrodes pipes and
fixtures. Homes may have internal plumbing materials containing lead. The concentration of
Lead was with the national limit for the sampling locations.
Chromium (Cr): Chromium is an odorless and tasteless metallic element. Chromium is found
naturally in rocks, plants, soil and volcanic dust, and animals. The most common forms of
chromium that occur in natural waters in the environment are trivalent chromium (chromium-3)
and hexavalent chromium (chromium-6). The concentration of chromium was within the
acceptable limit for all of the drinking water samples.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 17
Oil & Grease: Oil & grease enter the sewer system from restaurants, residences, and industrial
food facilities. Its release into the sewer system results in a continuous build-up that causes
eventual blockage of sewer pipes. The value of oil & grease was BDL (Below Detection Limit)
for the sampling location.
3.3 Noise Measurement
Noise Level Measurement was analyzed at three (03) sites of the project location form 05
February to 06 February 2020. The laboratory test result is given in Appendix D of this report.
Noise level data were taken during daytime are summarized along with GPS coordinate in
Table 3.5. Noise measurement at three (03) sampling locations was done continuously for 15
minutes at day time.
Borotakiya, Upa: Mireshorai, Dist: Chittagong
Bakhrabad, Up: Muradnagar; Dist: Comilla Bizra, Upa: Laksham; Dist: Comilla
Figure 3.3: Noise Level Monitoring at the Project Location.
Table 3.5: Test Results of Noise Level Monitoring at Location
Sample ID Sample Location GPS
Location
Land Use
Category
Time Noise
Level
(dBA)
(LAeq)
Bangladesh
Standard
(dBA)** Start End
February 2020
NM_
Mireshorai
Borotakiya, Upa: Mireshorai, Dist: Chittagong
23.75178°N 090.57397°E
Residential 11:25
am
11:40
am 59.22 55
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 18
Sample ID Sample Location GPS
Location
Land Use
Category
Time Noise
Level
(dBA)
(LAeq)
Bangladesh
Standard
(dBA)** Start End
February 2020
NM_
Bakhrabad
Bakhrabad, Up: Muradnagar; Dist: Comilla
23.63168°N 090.89047°E
Residential 15:17
pm
15:32
pm 57.11 55
NM_Bizra Bizra, Upa: Laksham; Dist: Comilla
23.31529°N 090.09068°E
Residential 11:30
am
11:45
am 57.32 55
November, 2019 (Baseline)
NM_
Mireshorai
Borotakiya, Upa: Mireshorai, Dist: Chittagong
23.75178°N 090.57397°E
Residential 12:44
pm
12:59
pm 61.21 55
NM_
Bakhrabad
Bakhrabad, Up: Muradnagar; Dist: Comilla
23.63168°N 090.89047°E
Residential 16:34
pm
16:49
pm 53.97 55
NM_Bizra Bizra, Upa: Laksham; Dist: Comilla
23.31529°N 090.09068°E
Residential 09:54
am
10:09
am 54.98 55
Notes:
▪ Land use category is based on the classification provided in the Noise Pollution Control Rules (2006) ▪ The sound level standards for residential area are 55 at day time and 45 at night time. ▪ Noise Level is the average noise recorded over the duration of the monitoring period
Abbreviation:
NM- Noise Measurement, dB- decibel
Table 3.6: Description of the Surrounding Environment
Sample Location and ID Sample Site Description
NM_Mireshorai
(Borotakiya, Upa: Mireshorai, Dist: Chittagong)
➢ Traffic volume was high. ➢ The place is a residential zone. ➢ People movement High. ➢ Construction work ahead. ➢ Beside Economic Zone Access Road
NM_ Bakhrabad
(Bakhrabad, Up: Muradnagar; Dist: Comilla)
➢ The place is in residential zone. ➢ People movement was low. ➢ Beside local road. ➢ Traffic volume was moderate. ➢ Construction work ahead.
NM_Bizra
(Bizra, Upa: Laksham; Dist: Comilla)
➢ The place is in residential zone. ➢ Beside local road. ➢ People movement was low. ➢ Traffic volume was bit less ➢ Construction work ahead.
The result shows that time weighted average value of the sound monitored inside the project
location are the exceed the national standard set for the residential area due to traffic volume,
operating construction machinery and during unloading and loading of material. The Contractor
are trying to ensure that all equipment engines and motors are equipped with proper mufflers.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 19
3.4 Liquid Waste Quality
Liquid waste can be defined as such Liquids as wastewater, fats, oils or grease (FOG), used
oil, liquids, solids, gases, or sludges and hazardous household liquids. These liquids that are
hazardous or potentially harmful to human health or the environment.
To analysis the quality liquid waste sample were collected from project influenced locations on
05 February 2020 to 06 February 2020 from the project location. Liquid waste water is collected
form the Bizra and Mirsharai Site Location. Kindly note that there is no Liquid waste collection
site at Bakhrabad. Unfortunately, the project team were not able to collect liquid waste and
laboratory analysis for that site. So, the sampling team collected the liquid waste sample form
2 locations and the parameters measured were pH, Electric Conductivity (EC), Chromium (Cr),
Lead (Pb), Turbidity, TDS, BOD, Oil and Grease. The samples were collected in plastic
sampling bottles, kept in an ice cooler, after necessary stabilization /fixing, and analyzed within
72 hours of being collected. The Laboratory tests were conducted in DPHE and DU Laboratory.
The laboratory test result is given in Appendix E of the report.
Borotakiya, Upa: Mireshorai, Dist: Chittagong
Bizra, Upa: Laksham; Dist: Comilla
Figure 3.4: Liquid waste collection from the Project Location
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 20
Table 3.5: Test Result of Liquid Waste Sampling Analysis
Parameters Unit
Concentration Present on February 2020
Standards for Waste Water*
Analysis Method
LW_Mireshorai LW_Bizra
23.75237°N
90.57401°E
23.31496°N 91.09035°E
Borotakiya
Upa: Mireshorai, Dist: Chittagong
Bizra; Upa: Laksham; Dist: Comilla
pH* - 9.31 9.03 6-9 Multimeter
Electric Conductivity (EC)*
µs/cm 765 869 1200 Multimeter
TDS* mg/L 2887 2998 2100 Multimeter
Chromium mg/L 0.004 0.003 1.0 AAS
Lead mg/L 0.003 0.002 1.0 AAS
Turbidity mg/L 56 54 NYS
BOD mg/L 265.3 269.1 250
Oil & Grease mg/L Less than 5.0 Less than 5.0 NYS 3114.C
Standards for Waste Water followed Environmental Conservation Rule (ECR)’97
*On-site Test Result.
NYS-Not Yet Standardized; BDL-Below Detection Limit
Source: DPHE and DU February 2020
pH: The "desirable" range of pH prescribed in the ECR,97 by the DoE is between 6 and 9. This
is the range, which provides adequate protection to the life of fresh water fish and bottom
dwelling invertebrates. The pH value of the liquid waste water samples are exceeding the
national standard.
Turbidity: Turbidity is a measure of the degree to which the water loses its transparency due to
the presence of suspended particulates. The more total suspended solids in the water, the
murkier it seems and the higher the turbidity. The concentration of Turbidity is Higher in
Bakhrabad than Bizra site location.
Total Dissolved Solids (TDS): Dissolved solids" refer to any minerals, salts, metals, cations or
anions dissolved in water. Total dissolved solids (TDS) comprise inorganic salts (principally
calcium, magnesium, potassium, sodium, bicarbonates, chlorides, and sulfates) and some
small amounts of organic matter that are dissolved in water. The TDS value of the liquid waste
water samples are exceeding the national standard.
Electrical Conductivity (EC): EC stands for electrical conductivity, which measures the
potential for a material to conduct electricity. The test results show that the values of EC are
within the national standard for all of the sampling location.
Lead (Pb): Lead can enter drinking water when service pipes that contain lead corrode,
especially where the water has high acidity or low mineral content that corrodes pipes and
fixtures. Homes may have internal plumbing materials containing lead. The concentration of
Lead was with the national limit for the sampling locations.
Chromium (Cr): Chromium is an odorless and tasteless metallic element. Chromium is found
naturally in rocks, plants, soil and volcanic dust, and animals. The most common forms of
chromium that occur in natural waters in the environment are trivalent chromium (chromium-3)
and hexavalent chromium (chromium-6). The concentration of chromium was within the
acceptable limit for all of the drinking water samples.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 21
Oil & Grease: Oil & grease enter the sewer system from restaurants, residences, and industrial
food facilities. Its release into the sewer system results in a continuous build-up that causes
eventual blockage of sewer pipes. The value of oil & grease was less than 5.0 for the sampling
locations.
Biochemical Oxygen Demand (BOD5): Biochemical Oxygen Demand is supposed to measure
the amount of food (or organic carbons) that bacteria can oxidize. The standard of waste water
for BOD5 is 250 or less mg/L. The test results show that, BOD5 level exceeds the national
standard for all of the sampling locations because of the water is being collected from the
wastewater and some construction wastes are disposed in water by different anthropogenic
and commercial activities. Proper measures should be taken for preventing rain wash.
However, during heavy rainfall, some rain has been occurred. In future, contactor should must
safely and legally manage that waste water from pollution.
4 CONCLUSION
The project will increase the contribution of the energy sector to sustainable economic growth
by the improvement of efficiency in gas production from existing gas field, and expansion of
transmission pipeline capacity through construction of gas transmission pipelines. For
implementing the mitigation plan to reduce adverse impacts the baseline environmental
parameters assessed and the existing environmental conditions of the project area. From the
environmental assessment it is found that all the air quality parameters are within national
standard of Bangladesh. Noise level are exceeding the national standard for the sampling
location for operating construction machinery and due to loading unloading of materials.
Drinking water quality concentration levels were within the national standard. From the liquid
waste results, it is seen that, the parameters contain higher value in the project locations
because of the water is being polluted by different anthropogenic and construction activities. n
future, contactor should must safely and legally manage that waste water from pollution by
preventing rain wash.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 22
APPENDIX
Appendix A: Environmental Monitoring Checklist
No. Aspects of
Environmental issues
Compliance Status
Remarks
FC PC NC
A. General
1. Legal working hours approval
The workers work 10 hours a day at site including 1-hour lunch break. Sometimes worker taking rest if they feel bored due to work.
2. Employment Record keeping arrangement
The employment records are kept in a register book manually every day in the field.
3. Payment Record keeping arrangement
The payment records are kept in a register book manually every day in the field.
4. Environmental Monitoring Officer designated
Environmental Monitoring Officer is appointed.
5. Provision for monthly meeting for inspection of site activities
Meetings are called about working progress, environmental compliance and future planning every month.
B. Health and Sanitation
Occupational Health
1. First-Aid Box availability at work sites
A well-equipped first aid box is available at the site
2. Provision of personal protection equipment’s (PPEs)
Site Engineers, supervisors and workers are provided with PPEs including vests, helmets, safety boots etc.
3. Handling of cement and other hazardous materials by workers
Try to use Nonhazardous materials. Hazardous and Non-Hazardous materials were collected by a separate waste bin.
4. Workers complains taken care of by the supervisor
Planning to appoint a supervisor for the workers is appointed to take care of the workers problems and receiving complaints from the workers and solving those problems accordingly.
5. Children below 15 employment
There are no below 15 children working in the site
C. Environmental Pollution
Dust and emission control
1.
Construction vehicles and machineries maintained properly to reduce emissions
Try to maintain the vehicles and machineries with least pollution.
2. Proper storage of materials and regular watering.
The materials are stored in proper manner and watering is done two times a day (morning and afternoon) regularly to mitigate air pollution. Removal of dust fully is quite difficult but our project team is trying to remove by water spraying in an environmentally friendly manner.
Noise Pollution
1. Movement of vehicles at desired hours
Heavy vehicles movements are done mostly from morning to afternoon.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 23
No. Aspects of
Environmental issues
Compliance Status
Remarks
FC PC NC
2. Noise control measures at sites
Noise created due to construction and heavy machineries affects less on the surrounding household because the construction site is surrounding by permanent fencing.
Water Pollution
1. Wastes, cement, effluents and junks not disposed in water
Some wastes are disposed in water. Proper measures are taken for preventing rain wash. However, due to heavy rainfall, some rain washes already occurred. In future more, precaution will be taken to prevent this.
Flora and Fauna
1.
Trees and bushes outside the construction area preserved from damages
Trying to preserved trees and bushes outside the construction area. In future more, precaution will be taken to prevent this.
2. Disturbance to terrestrial fauna minimized
If noise producing work needed, works are trying to done within day time with noise control measures to minimize the disturbance. In future more precaution will be taken to prevent this.
Waste Management
1. Construction wastes are removed off site regularly
The wastes are kept in a specific place and they are removed off site regularly in and environmentally friendly manner.
2. Chemical wastes, if any, collected and disposed of properly
During the monitoring period, no sources of chemical wastes are seen.
D. Environmental documents at Field Office and Project site
1.
Field Office possesses copies of EMP, contract document and Technical Specifications
All the documents are kept in the field office.
2. Heavy equipment maintenance records
Few heavy equipment issued in the site and the maintenance records are kept.
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 24
Appendix B: Air Quality Test Result
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 25
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 26
Appendix C: Drinking Water Quality Test Result
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 27
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 28
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 29
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 30
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 31
Appendix D: Noise Level Measurement Test Result
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 32
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 33
Appendix E: Liquid Waste Quality Test Result
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 34
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 35
Installation of Two (02) Town Bordering Station (TBS) and One (01) Metering Station Under Construction of Chittagong-
Feni-Bakrabad Gas Transmission Parallel Pipeline Project
Environmental Monitoring and Quality Test Report for the Month of February 2020 by Sunnex Limited 36
ID Task Name Duration Start Finish
1 PROJECT EXECUTION PLAN OF
VSD180267-343-344_GTCL_CFB
139
days
Sun 6/21/20 Thu
12/31/20
2 Design Service 52 days Sun 7/5/20 Tue 9/15/20
3 Control building 0 days Thu 7/9/20 Thu 7/9/20
4 Skid,valve and pipe support foundation 0 days Thu 7/9/20 Thu 7/9/20
5 CC walkway, surface drain, stone pitching, light post
foundation
12 days Sun 8/2/20 Mon
8/17/20
6 Cable layout of control building 6 days Mon 7/20/20Sat 7/25/20
7 Caple pit 6 days Sat 7/25/20 Fri 7/31/20
8 General Layout Drawing 0 days Thu 7/9/20 Thu 7/9/20
9 Sanitary and swerage system 8 days Sat 9/5/20 Tue 9/15/20
10 Electrical cable and panel layout 26 days Sun 7/5/20 Fri 8/7/20
11 Security post 0 days Thu 7/9/20 Thu 7/9/20
12 Pump house
13 STI, STD and HIV/AIDS Alleviatioin Program 126
days
Thu 7/9/20 Thu
12/31/20
14 Phase 1 for civil team (Completed) 126 days Thu 7/9/20 Thu 12/31/20
15 Phase 2 for mechanical team 88 days Tue 9/1/20 Thu 12/31/20
16 Phase 3 for E & I team 23 days Tue 12/1/20 Thu 12/31/20
17 All Civil Works including Piling 134 daysSun 6/28/20 Thu 12/31/20
18 Base Foundation, RCC pipe/valve support, lighting pole
foundation, cable pit
126
days
Thu 7/9/20 Thu
12/31/20
19 Construction of skid base foundation 20 days Thu 7/9/20 Wed 8/5/20
20 Construction of light pole foundation 6 days Mon 8/10/20Sat 8/15/20
21 Construction of cable pit 7 days Sun 8/23/20 Sun 8/30/20
22 Construction of CC walkway 21 days Mon 11/2/20Mon 11/30/20
23 Construction of surface drain in processs plant area 11 days Tue 12/1/20 Tue 12/15/20
24 Construction of RCC internal road 23 days Thu 10/1/20 Sat 10/31/20
25 Stone pitching around the process plant 23 days Tue 12/1/20 Thu 12/31/20
26 Chain link fence 9 days Tue 12/15/20Fri 12/25/20
27 Control Building 126 daysThu 7/9/20 Thu 12/31/20
28 Site Survey and Soil Test 0 days Thu 7/9/20 Thu 7/9/20
29 Mobilization 0 days Thu 7/9/20 Thu 7/9/20
30 Piling of control building 0 days Thu 7/9/20 Thu 7/9/20
31 Pile cap, grade beam GF super structure 0 days Thu 7/9/20 Thu 7/9/20
32 1st floor superstructure of control building 0 days Thu 7/9/20 Thu 7/9/20
33 Door, windows, plastering,plumbing, electrification,
flooring
23 days Thu 10/1/20 Sat 10/31/20
34 Building earting system with lighting arrestor 22 days Tue 9/1/20 Wed 9/30/20
35 Installation of water wll, submersible pump 12 days Sat 8/15/20 Mon 8/31/20
36 Air conditioning system, fire protection & smoke
detection system
22 days Sun 11/1/20 Mon
11/30/20
37 Septic tank, soak well, over head water tank 22 days Tue 9/1/20 Wed 9/30/20
7/9
7/9
7/9
7/9
7/9
7/9
7/9
7/9
7/9
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 Feb
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Project Execution Plan_
Date: Thu 7/9/20
ID Task Name Duration Start Finish
38 Environmental monitoring with submission of report 126 days Thu 7/9/20 Thu 12/31/20
39 Generator Building with Switchgear cum Substation,
Security Post , Pump House
41 days Sun 6/28/20 Mon
8/24/20
40 Construction of security post 17 days Fri 7/31/20 Mon 8/24/20
41 Construction of pump house 17 days Sun 6/28/20 Mon 7/20/20
42 Construction of generator building 28 days Sun 6/28/20 Tue 8/4/20
43 Custom Clearence 67 days Thu 7/9/20 Sat 10/10/20
44 1st partial shipment 0 days Thu 7/9/20 Thu 7/9/20
45 2nd partial shipment 0 days Sat 8/1/20 Sat 8/1/20
46 3rd partial shipment 0 days Wed 9/30/20Wed 9/30/20
47 4th partial shipment 0 days Sat 10/10/20 Sat 10/10/20
48 Mechanical Erection & Fabrication 81 days Tue 9/1/20 Tue 12/22/20
49 Welding,fabrication,cutting intra skid pipeline and fittings54 days Thu 10/1/20 Tue 12/15/20
50 Installation of condensate tank on RCC base 12 days Tue 9/1/20 Wed 9/16/20
51 Installation of regulating skid and VME on RCC base 8 days Sun 11/1/20 Tue 11/10/20
52 Installation of WBS's and TCB (except BKB) 4 days Fri 9/25/20 Wed 9/30/20
53 Fabrication and Installation of Steel Structures 17 days Sun 10/11/20Sat 10/31/20
54 NDT of welding joints 34 days Sun 11/1/20 Wed 12/16/20
55 Painting of above ground piping and steel structure 15 days Tue 12/1/20 Sun 12/20/20
56 Installation of orifice metering skid on RCC base 22 days Tue 9/1/20 Wed 9/30/20
57 Installation of intraskid,condensate and low flow piping 9 days Tue 11/10/20Fri 11/20/20
58 Hookup TBS/MS with offtake 8 days Thu 12/10/20Sun 12/20/20
59 Fabrication and installation of metering shed 4 days Wed 11/25/20Mon 11/30/20
60 Construction and installation of interconnecting pipeline 33 days Sun 11/1/20 Tue 12/15/20
61 Hydrotest 6 days Tue 12/15/20Tue 12/22/20
62 Electrical Instrumentation 139 daysSun 6/21/20 Thu 12/31/20
63 Cable laying 12 days Fri 11/20/20 Sat 12/5/20
64 Drawing 440, 3Phase power connection from nearest 11KV60 days Sun 6/21/20 Thu 9/10/20
65 Cable Termination 11 days Thu 11/26/20Thu 12/10/20
66 Installation of light pole 15 days Tue 11/10/20Mon 11/30/20
67 Cable loop check 15 days Tue 12/1/20 Sun 12/20/20
68 Installation of standby generator 5 days Sat 8/15/20 Thu 8/20/20
69 Installation of earthing and CP system 23 days Tue 12/1/20 Thu 12/31/20
70 Installation and commissioning of solar panel and IP
camera
30 days Sun 11/1/20 Thu
12/10/20
71 Installation of field instrument 9 days Tue 12/15/20Fri 12/25/20
72 Power up the control room 0 days Wed 12/30/20Wed 12/30/20
73 Precommissioning & Commissioning 12 days Thu 12/10/20Fri 12/25/20
7/9
8/1
9/30
10/10
12/30
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 Feb
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: Project Execution Plan_
Date: Thu 7/9/20
Action
Officer,
Designation
(Follow-up date)
1COVID Infections
during travelling
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case.
Give advance safety
advice day before travel
to site
5 4 20 5 2 10 Site Supervisor
2Infected Workers
Entering to Site
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Creating awareness
among worker about the
early symptom of Covid-
19 and display caution
sign
5 5 25 5 1 5 Site Supervisor
3COVID Infections
during close contact
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Creating awareness
among worker about the
early symptom of Covid-
19 and display caution
sign
5 7 35 5 3 15 Site SupervisorConducting construction works
Display safety banner
about covid-19,
Using raspatory
mask, goggles',
maintain physical
distance, washing
hand repeatedly at
workplace
Workers arrive at site from
dormitory
Check body
temperature at the
site entrance
Pro
ba
bil
ity
Risk
Priority
Number
Additional Risk
Control Measures
Arriving site using public
transport
Use proper
respiratory mask,
hand gloves, googles,
use hand sanitizer
frequently, maintain
physical distance
1. HAZARD IDENTIFICATION 2. RISK EVALUATION 3. RISK CONTROL
No. Step / Sequence/Event Potential HazardsPossible Health &
Persons-at-Risk
Existing Risk Control
(if any)
Se
ve
rity
Action
Officer's
SignatureSe
ve
rity
Pro
ba
bil
ity
Risk
Priority
Number
CONDUCTED BY:
(Names, Designations,
Signatures)
MD. MAHMUDUL HASAN, MANAGER- PROJECTS & PROGRAM, SUNNEX LIMITED
APPROVED BY:
(Name, Designation,
Signature)
JAMAL U. AHMED, DIRECTOR, SUNNEX LIMITED NEXT REVIEW DATE: 7/12/2020
RISK ASSESSMENT ON COVID-19
EPC CONTRACTOR: VALVITALIA SpA- Systems Devision, Italy.
Local Sub Contractor: Sunnex Limited
Rev.00
TASK / LOCATION: WORKPLACE ACTIVITIES, MIRSHARAI-BIZRA-BAKHRABAD DATE OF REVIEW: 7/7/2020
4COVID Infections
during close contact
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Education workers about
Covid-19 and teach
importance of maintain
personnel hygiene at work
place
5 3 15 5 1 5 Site Supervisor
5COVID Infection during
close contact
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Isolation of new workers
for 7 days at dormitory
before allowing to site.
Educating workers about
covid-19 and encourage
repeatedly hand washing
with soap water.
5 8 40 5 2 Site Supervisor
6COVID Infection during
close contact
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Not allowing workers to go
outside without any valid
reason and nominate
designated person to
minimize risk for groceries
and shopping for others
6 8 48 5 3 15 Site Supervisor
7COVID Infections
during close contacts
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Not allowing unauthorized
personnel at workers
dormitory.
5 8 40 5 3 15 Site SupervisorReturning to dormitory
Ensure that soap
solution is used for
washing hand before
entering to
dormitory gate.
Wash cloth and
having shower
immediately after
return from outside.
Going outside for groceries and
other essential shopping
Ensure not to go
outside without
wearing Gloves, Face
shield, respiratory
mask, goggles.
Workers having lunch in
workplace
Make sure physical
distance & hygiene
of plates, water
bottle during lunch
and snacks break.
Staying at dormitory
Ensure sure physical
distance & personnel
hygiene maintain.
Nobody allowed to
go outside of
dormitory without
emergency. Provide
vitamin C, and
ensure plenty of
sleep for boost
immune system
8
COVID Infections
during due to lack of
awareness
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Educating workers at
workplace 5 6 30 5 2 10 Site Supervisor
9
COVID Infections
during due to lack of
awareness
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Educating at workplace 5 9 45 5 1 5 Site Supervisor
10
COVID Infections
during due to lack of
awareness
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Site security at the
entracne5 7 35 5 0 0 Site Supervisor
11 Spreading COVID
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Isolatin Area at workplace 8 7 56 5 2 10 Site SupervisorEncountered sudden fever and
severe coughing of workers
Display contact no.
of nearby COVID
designated hospital
at site office to
handle emergency
situation
Encountered undesignated
people at the site
Reinforcement of
security measures
and not allowing to
the workplace
without ID card
Encountered Heedless
Workers/Supervisor at
Workplace
Conducting
awareness and
trainning program
about COVID/19
Recruitement of unaware
workers
Postering about
COVID-19 around
the workplace to
intnsify awareness
and not recruting
heedless
workers/manpower
12Spreading/Infections of
COVID-19
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Keeping safe physical
distance while briefing to
contractor or workers
5 7 35 5 2 10 Site Supervisor
13Spreading/Infections of
COVID-19
mild illness to
pneumonia, fever,
cough, sore throat and
headaches even death
in severe case
Creating awareness about
emergency situation10 7 70 5 4 20 Site Supervisor
Severity Scale: 10= Very Hazardous; 0 = Not Hazardous
Probability Scale: 10= Very Likely; 0 = Not Likely
`
Encounter unforseen event
about covid 19 at the workplace
which goes beyond workplace
control
Monitoring and
controlling the
COVID-19 situation
at workplace and
reporting to
Employer in a regular
fashion
Employers representatives visit
at site
Display contact no.
of nearby COVID
designated hospital,
police station at site
office to handle
emergency situation
and report of GTCL
headquarted for
further assistance
ID Name Duration Start Finish Predecessors
1 GTCL SCADA&Telecom Project2 EPC contract sign 1 d 2019/11/11 2019/11/113 Contract effectiveness date 1 d 2020/3/17 2020/3/174 Overall project duration 400 d 2020/3/17 2021/4/205 Procurement 168 d 2020/3/17 2020/8/316 Design procurement 126 d 2020/3/17 2020/7/20 3SS7 SCADA/RTU Procurement 126 d 2020/3/17 2020/7/20 3SS8 Telecom Procurement 168 d 2020/3/17 2020/8/31 3SS9 BD Civil & Installation Team
procurement168 d 2020/3/17 2020/8/31 3SS
10 Design 62 d 2020/7/21 2020/9/2011 SCADA/RTU System design 20 d 2020/7/21 2020/8/9 712 Telecom System design 20 d 2020/9/1 2020/9/20 813 Civil Design 20 d 2020/9/1 2020/9/20 914 Equipment Manufacture 92 d 2020/8/10 2020/11/915 SCADA /RTU equipment Manufacture 40 d 2020/8/10 2020/9/18 1116 Telecom equipment Manufacture 50 d 2020/9/21 2020/11/9 1217 Transportation 97 d 2020/9/19 2020/12/2418 SCADA、RTU equipment transportatio 45 d 2020/9/19 2020/11/2 1519 Telecom equipment transportation 45 d 2020/11/10 2020/12/24 1620 Site construction,installation &
commissioning175 d 2020/9/21 2021/3/14
21 Civil construction 90 d 2020/9/21 2020/12/19 1322 SCADA equipment installation and
testing60 d 2020/11/10 2021/1/8 18FS+7 d
23 Tower & Telecom equipment installation and testing
50 d 2021/1/4 2021/2/22 19FS+10 d
24 Pre-commissioning 20 d 2021/2/23 2021/3/14 2325 Completion of Facilities 7 d 2021/3/15 2021/3/21 2426 SCADA & Telecom training 14 d 2021/3/22 2021/4/4 2527 Acceptance of Facilities 30 d 2021/3/22 2021/4/20 25
11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5tr 4 2020 Qtr 1 2020 Qtr 2 2020 Qtr 3 2020 Qtr 4 2021 Qtr 1 2021 Qtr 2
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Roolup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Schedule
Manual Schedule
Note: Procurement and design work has been postponed by covid-19.Especially Telecom procurement,because India sub contractor's company has been severely impacted by covid-19,and not sure when will back to smoothly operation.
Project: GTCL SCADA & Telecom ProjectDate: 2020/7/11
RISK ASSESSMENT AND MANAGEMENT PLAN ON COIVD-19
CONTRACK NAME Design, Build, Procurement & Supply, Installation, Construction, Testing and Commissioning of SCADA and Telecommunication System for Chattogram-Feni-Bakhrabad Gas Transmission Parallel Pipeline Project
CONTRACT No. 28.14.0000.817.02.009.19 dated 11st November 2019
EMPLOYER Gas Transmission Company Limited (GTCL) EPC CONTRACTOR NARI TECHNOLOGY CO.LTD
LOCAL SUB CONTRACTOR Castle Construction Co.Ltd TASK / LOCATION Chattogram-Feni-Bakhrabad
DATE OF REVIEW: 2020/7/12 REVISON 01
CONDUCTED BY:Md. Abdul Hai,Senior Manager (Engineering)
APPROVED BY:Syed Nayeem Abdullah,CEO.(Names, Designations,
Signatures)(Name, Designation,
Signature)
PART I: RISK ASSESSMENT AND MANAGEMENT PLAN ON COIVD-19
1. HAZARD IDENTIFICATION 2. RISK EVALUATION 3. RISK CONTROL
No. Step / Sequence/Event Potential Hazards Possible Health & Persons-at-Risk
Existing Risk Control (if any)
Seve
rity
Prob
abili
ty
Risk Priority Number
Additional Risk Control Measures
Seve
rity
Prob
abili
ty
Risk Priority Number
ActionAction Officer's
SignatureOfficer
Designation(Follow-up date)
1 Arriving site using public transport COIVD-19 Infections during travelling
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case.
Give advance safety advice day before travel to site 5 6 30
Use proper respiratory mask, hand gloves, googles, use hand sanitizer frequently, maintain physical distance
5 3 15 Site Supervisor
2 Workers arrive at site from dormitory Infected Workers Entering to Site
mild illness to pneumonia, fever, cough, sore throat and headaches even deathin severe case
Creating awareness among worker about the early symptom of COIVD-19 and display cautionsign
5 6 30 Check body temperature at the site entrance 5 2 10 Site Supervisor
3 Conducting construction works COIVD-19 Infections during close contact
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Creating awareness among worker about the early symptom of COIVD-19 and display caution sign
5 7 35
Display safety banner about COIVD-19, Using raspatory mask, goggles, maintain physical distance, washing hand repeatedly at workplace
5 3 15 Site Supervisor
4 Workers having lunch in workplace COIVD-19 Infections during close contact
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Education workers about COIVD-19 and teach importance of maintain personnel hygiene at work place
5 4 20Make sure physical distance & hygiene of plates, water bottle during lunch and snacks break.
5 1 5 Site Supervisor
5 Staying at dormitory COIVD-19 Infection during close contact
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Isolation of new workers for 7 days at dormitory before allowing to site. Educating workers about COIVD-19 and encourage repeatedly hand washing with soap water.
5 8 40
Ensure sure physical distance & personnel hygiene maintain. Nobody allowed to go outside of dormitory without emergency. Provide vitamin C, andensure plenty of sleep for boost immune system
5 2 10 Site Supervisor
6 Going outside for groceries and other essential shopping
COIVD-19 Infection during close contact
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Not allowing workers to go outside without any valid reason and nominate designated person to minimize risk for groceries and shopping for others
6 8 48Ensure not to go outside without wearing Gloves, Face shield, respiratory mask, goggles.
6 3 18 Site Supervisor
7 Returning to dormitory COIVD-19 Infections during close contacts
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Not allowing unauthorized personnel at workers dormitory. 5 8 40
Ensure that soap solution is used for washing hand before entering to dormitory gate.Wash cloth andhaving shower immediately after return from outside.
5 3 15 Site Supervisor
1 / 3
RISK ASSESSMENT AND MANAGEMENT PLAN ON COIVD-19
8 Recruitement of unaware workersCOIVD-19 Infections during due to lack of awareness
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Educating workers at workplace 6 6 36
Postering about COIVD-19 around the workplace to intnsify awareness and not recruting heedless workers/manpower
5 2 10 Site Supervisor
9 Encountered Heedless Workers/Supervisor at Workplace
COIVD-19 Infections during due to lack of awareness
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Educating at workplace 6 9 54Conducting awareness and trainning program about COIVD-19
5 1 5 Site Supervisor
10 Encountered undesignated people at the site
COIVD-19 Infections during due to lack of awareness
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Site security at the entracne 6 7 42Reinforcement of security measures and not allowing to the workplace without ID card
5 0 0 Site Supervisor
11 Encountered sudden fever and severe coughing of workers Spreading COIVD-19
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Isolatin Area at workplace 8 7 56
Display contact no. of nearby COIVD-19 designated hospital at site office to handle emergency situation
5 4 20 Site Supervisor
12 Employers representatives visit at site Spreading/Infections of COIVD-19
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Keeping safe physical distance while briefing to contractor or workers
5 7 35
Check body temperature at the site entrance;Display contact no.of nearby COIVD-19 designated hospital, police station at site office to handle emergency situationand report of GTCL headquarted for further assistance
5 2 10 Site Supervisor
13Encounter unforseen event about COIVD-19 at the workplace which goes beyond workplace control
Spreading/Infections of COIVD-19
mild illness to pneumonia, fever, cough, sore throat and headaches even death in severe case
Creating awareness about emergency situation 10 7 70
Monitoring and controlling the COIVD-19 situation at workplace and reporting to Employer in a regular fashion
5 4 20 Site Supervisor
NOTE: Severity Scale: 10= Very Hazardous; 0 = Not Hazardous
Probability Scale: 10= Very Likely; 0 = Not Likely
Risk Priority = Severity x Probability
2 / 3
RISK ASSESSMENT AND MANAGEMENT PLAN ON COIVD-19
PART 2: EMERGENCY MEASURES
1 Emergency measures
1.1 Identify the nearby COVID-19 designated hospital,display contact number of hospital
1.2 Set police station at site office as isolation area to handle emergency situation
1.3 Report to GTCL and Local public health authorities to seek for further assistant and medical treatment
1.4 Inform workers and tracking their health condition
2 General Flow Chat for Emergency Protocol
3 / 3