Environmental Monitoring Report - Asian …...PEOPLE’S REPUBLIC OF CHINA GANSU BAIYIN URBAN...
Transcript of Environmental Monitoring Report - Asian …...PEOPLE’S REPUBLIC OF CHINA GANSU BAIYIN URBAN...
Environmental Monitoring Report
This report has been submitted to ADB by the Gansu Baiyin Project Management Office and is made publicly available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB.
Project Number: 40051 March 2012
PRC: Gansu Baiyin Urban Development Project
Prepared by Baiyin Environmental Protection Bureau & EASEN International Co., Ltd.
Gansu Province, PRC
PEOPLE’S REPUBLIC OF CHINA GANSU BAIYIN URBAN DEVELOPMENT PROJECT
ADB LOAN LOAN NO. 2407-PRC
Environmental Monitoring Report
(July through December 2011)
Prepared for
Asian Development Bank
by
BAIYIN ADB LOAN PROJECT MANAGEMENT OFFICE
and
EASEN INTERNATIONAL CO., LTD.
March 2012
ADB Loan No. 2407-PRC i
ABBREVIATIONS
ADB Asian Development Bank
BCCB Baiyin City Construction Bureau
BDG Baiyin District Government
BDRC Baiyin Development and Reform Commission
EASEN Easen International Co., Ltd.
EA Executing Agency
EIA Environmental Impact Assessment
BEPB Baiyin Municipal Environmental Protection Bureau
BFB Baiyin Municipal Finance Bureau
BHIPMC Baiyin High-tech Industrial Park Management Committee
BLMB Baiyin Municipal Land Management Bureau
BMG Baiyin Municipal Government
GBUDP Gansu Baiyin Urban Development Project
GPDRC Gansu Provincial Development and Reform Commission
GPG Gansu Provincial Government
GSLA Gansu Provincial Land Management Agency
IA Implementing Agency
LCCDI Lanzhou City Construction Design Institute
MOFPRC Ministry of Finance People’s Republic of China
ICB International Competitive Bidding
IS International Shopping
NCB National Competitive Bidding
PLG Project Leading Group
RP Resettlement Plan
PDG Pingchuan District Government
PDURCB Pingchuan District Urban and Rural Construction Bureau
PMO Project Management Office
PPTA Project Preparation Technical Assistance
PPMS Project Performance Monitoring System
BWHC Baiyin West Heating Co., Ltd
PRC The People’s Republic of China
ADB Loan No. 2407-PRC ii
CONTENTS PROJECT LOCATION MAP
I. INTRODUCTION ...................................................................................................... 1
A. Basis of the Report ....................................................................................................... 3
B. Environmental Procedure Review ............................................................................. 3
C. Legal Requirements ..................................................................................................... 4
II. SOUTHERN BAIYIN INFRASTRUCTURE SUBPROJECT..................................... 6
A. Scope of Subproject ..................................................................................................... 6
B. Subproject Progress .................................................................................................... 6
C. Environmental Management Office ........................................................................... 6
E. Mitigation Measures Implemented and Compliance Assessment ...................... 10
F. Issues and Recommendations ................................................................................. 11
III. BAIYIN DISTRICT ROAD IMPROVEMENTS ........................................................ 12
A. Scope of the Subproject ............................................................................................ 12
B. Subproject Progress .................................................................................................. 12
C. Environmental Management Office ......................................................................... 12
D. Environmental Monitoring ......................................................................................... 13
E. Mitigation Measures Implemented and Compliance ............................................. 15
IV. PINGCHUAN DISTRICT ROAD IMPROVEMENTS SUBPROJECT ..................... 17
A. Scope of the Subproject ............................................................................................ 17
B. Subproject Progress .................................................................................................. 17
C. Environmental Management Office ......................................................................... 17
D. Environmental Monitoring ......................................................................................... 17
E. Mitigation Measures Implemented and Compliance ............................................. 21
F. Issues and Recommendations ................................................................................. 22
V. Baiyin District Heating Services Subproject ...................................................... 23
A. Scope of the Subproject ............................................................................................ 23
B. Subproject Progress .................................................................................................. 23
C. Environmental Management Office ......................................................................... 23
D. Environmental Monitoring ......................................................................................... 23
E. Mitigation Measures Implemented and Compliance ............................................. 28
F. Issues and Recommendations ................................................................................. 29
VI. CONCLUSIONS ..................................................................................................... 30
APPENDIX 1:
Summary Information of Closed Small Boilers Houses by the End of 2011
ADB Loan No. 2407-PRC 1
Map: Project Location Map Project Location: Baiyin Municipality
Baiyin
ADB Loan No. 2407-PRC 2
I. INTRODUCTION
1. Based on the Project Agreement for the Gansu Baiyin Urban Development project
(the Project), the Government of Gansu Province, Baiyin Municipal Government, and each
Project Implementation Agency (PIA) shall ensure that (i) the Project be constructed and
operated in accordance with the national and local environmental regulations and guidelines,
ADB’s Environmental Policy (2002) and the Environmental Impact Assessment reports
(EIAs); (ii) any adverse environmental impacts arising from the construction and operation of
the Project facilities be minimized by implementing the mitigation measures, environmental
monitoring program and other recommendations presented in the EIAs; and (iii) the
implementation of the environmental management plan (EMP) and any violation of safety or
environmental standards, if any, be regularly reported to ADB.
2. Environmental specialists from the consultant firm and the Baiyin PMO visited project
sites during this reporting period. During their visits, in depth discussions were made with the
PIAs during which particular attention was focused on their responsibilities for environmental
monitoring and preparing monitoring reports. The Baiyin PMO has contracted with Baiyin
Municipal Environmental Monitoring Station of Baiyin Environmental Protection Bureau to
monitor the environmental conditions in accordance with the EIAs.
3. The Gansu Baiyin Urban Development project consists of five subprojects, of which
four construction subprojects involve environmental monitoring, including (i) Southern Baiyin
Infrastructure, (ii) Baiyin District Road Improvements, (iii) Pingchuan District Road
Improvements, and (iv) Baiyin District Heating Services. The construction for these four
subprojects has substantially completed. The fifth subproject is the Capacity Development
and Institutional Strengthening, which is a consulting service and does not involve any
environmental monitoring. Under this subproject the consultants provide assistance to the
PMO and PIAs in completing the environmental monitoring requirements and preparing
monitoring reports.
4. This semi-annual environmental report describes the implementation of the
environmental monitoring and mitigation measures recommended in the EIAs, analyzes
environmental data collected from related subprojects during the period of July through
December 2011, and provides recommendations on issues identified.
5. Specifically, this environmental monitoring report covers the following areas: (i)
documentation review and compliance assessment with applicable environmental
regulations, (ii) environmental management institutional structure and responsibilities, (iii)
mitigation measures undertaken to minimize adverse environmental impacts arising from the
construction of each subproject, (iv) environmental monitoring results and analyses, and (v)
conclusions and recommendations.
ADB Loan No. 2407-PRC 3
A. Basis of the Report
6. This semi-annual environmental report has been prepared based on the data and
information from the following sources:
Environmental Monitoring Reports provided by the Baiyin Environmental
Monitoring Station of the Baiyin Environmental Protection Bureau; EIAs for all
subprojects;
Environmental supervision reports provided by each PIA;
EMPs submitted to ADB;
Project Agreement; and
Relevant environmental laws and regulations.
B. Environmental Procedure Review
7. The consultants reviewed the environmental monitoring procedures and data
collections with the PMO and PIAs. Each of the contractors, construction supervision
companies, and the PIA’s designated staff from the site management team plays an
important role in environmental monitoring and supervision. The responsibilities of the staff
includes day-to-day site environmental monitoring of their own contracts, implementation of
mitigation measures as indicated in the environmental action plan, and reporting of the site’s
environmental performance as specified in the contract including self-inspection and
self-monitoring.
8. Most of the environmental monitoring requirements are during the construction priod
of each subproject. At the construction stage, the construction supervision companies are
responsible for the preparation and submission of monthly environmental supervision
reports; meanwhile, the environmental monitoring agency is responsible for the monitoring of
environmental parameters and preparing environmental results reports. The PMO has
designated Ms. Zhang Qiong, with an environmental engineering background, to serve as an
environmental officer for this Project. The PMO, with the assistance from consultants, is
responsible for compiling the semi-annual environmental monitoring reports. Specific
responsibilities of the PIAs, contractors, local environmental monitoring station, and
construction supervision companies have been communicated with relevant parties with
training provided and they summarized as follows:
PIAs:
Develop environmental section of the contract with the assistance from the
consultant;
Provide training to contractors and all other related environmental personnel;
Visit project sites and review results;
Resolve environmental complaints, if any;
ADB Loan No. 2407-PRC 4
Develop and implement pollution prevention measures;
Implement environmental monitoring plans;
Provide monthly environmental monitoring reports to the PMO;
Implement mitigation measures including environment, health and safety; and
Arrange for environmental meetings as necessary.
Local Environmental Monitoring Station:
Prepare environmental monitoring plan;
Conduct environmental monitoring; and
Develop environmental monitoring reports based on the sampled data.
Supervision Companies (during construction period):
Supervise implementation of environment protection measures;
Perform environmental management responsibilities;
Receive complaint calls; and
Report environmental issues on sites.
Contractors (during construction period):
Implement environmental mitigation measures;
Provide basic sanitation facilities to workers;
Perform domestic sewage treatment if it is generated at construction sites;
Perform solid waste management;
Perform noise and dust control measures;
Provide personal protective equipment for workers; and
Take measures to ensure that construction equipment meets relevant national
or local emissions and noise standards.
C. Legal Requirements
9. The following provides a list of some applicable PRC environmental regulations and
standards and ADB environmental policy.
Air Pollutant Emission Standards for Boiler, GB13271-2001
Integrated Air Pollutant Emission Standards, GB16297-1996
Environmental Quality Standards for Surface Water, GB 3838-2002
Ground Water Quality Standards, GB/T 14848-93
ADB Loan No. 2407-PRC 5
Noise Limits for Construction Site, GB 12523-90
Integrated Wastewater Discharge Standards, GB 8978-1996
Noise Standards at Boundary of Industrial Enterprises, GB 12348-2008
Ambient Air Quality Standards, GB 3095-1996
Standard of Environmental Noise in Urban Area, GB 3096-93
Environmental Quality Standards for Soils, GB 15618-1995
Gansu Wastewater and Waste Gas Discharge Standards, DB21-60-89
Water Quality Standard for Wastewater to be Discharged into City sewage
System, CJ 1082-1999 or CJ 0082-1999
ADB Environmental Policy, November 2002
ADB Loan No. 2407-PRC 6
II. SOUTHERN BAIYIN INFRASTRUCTURE SUBPROJECT
A. Scope of Subproject
10. Under this component, the Project will develop, as part of the Southern Baiyin
Industrial Zone (SBIZ), 4.7 km2 of industrial land with basic public infrastructure, including
18.5 km of primary and secondary roads and related water supply pipelines, drainage
pipelines and sewers, heating supply pipelines, optical-fabric cable and electricity distribution
lines, lighting, and public green areas.
11. The PMO and the IA, BHTIP Management Commission reported that scope of this
component needs to be optimized to (i) avoid removal of key facilities of Yinguang Company
such as evaporation pond and explosive warehouse; (ii) avoid relocation of Cha Chuan
Channel which provides irrigation water for more than 2,000 mu farm land for downstream
villages, and avoid acquisition of farmland on southern of Nanweierlu Road; and (iii) improve
land use efficiency of the west part of the industrial park. Optimization of the scope will
resulted in reduction of 6.5 km road construction works for four roads: Nansanhuan Road,
Nansihuan Road, Nanjingerlu Road and Nanweisanlu Road, and the industrial land area to
be developed will be reduced to 4.7 km2. The proposed change was approved by Baiyin
Municipal Development and Reform Commission (Baiyin DRC) in April 2010.
B. Subproject Progress
12. There are three procurement packages (2 NCB and 1 ICB) under the ADB loan. They
are all civil work packages and comprised as follows: C01 - Earth Work, C02 - Southern
Baiyin Infrastructure #1, and C03 - Southern Baiyin Infrastructure #2.
13. The planned total investment for Southern Baiyin Infrastructure Component was CNY
374,959,400 million of which the engineering construction investment was CNY 235,985,500
million. By the end of 2011, the contract amount was completed by CNY 288,132,700, of
which construction investment was completed by CNY 248,812,700. From January to the
end 2011, the contract amount was completed by CNY 56,832,700, which accounts for
53.84% of CNY105.55 million planned investment in 2011.
C. Environmental Management Office
14. The environmental management office (EMO) is required to be established to
monitor the implementation of the EMP. The Baiyin High-tech Industrial Park Management
Committee (BHIPMC) has appointed Mr. Zeng Chengfu to be responsible for the
environmental management of this subproject during the construction period.
1. Air Quality Monitoring
15. One air quality monitoring location downwind from the construction site of the
subproject was selected as the monitoring station and it is located 200 meters from the site
ADB Loan No. 2407-PRC 7
boundary. Both TSP and PM10 were monitored for two days each month from July to
December 2011, and two samples were taken each day. The locations of the monitoring
sites are shown in Figure 1.
16. The results of the air quality monitoring, as seen in Table 1, showed that the
minimum value for TSP was 0.178 mg/m3, and the maximum value was 0.418 mg/m3. Eight
out of 24 samples (or approximately 33%) have the daily values for TSP higher than the
national limit of 0.30 mg/m3. The minimum value for PM10 was 0.075 mg/m3, and the
maximum daily value was 0.166 mg/m3. One of the 24 PM10 samples (4.2%) was higher than
the national limit of 0.15 mg/m3. All high TSP and PM10 concentrations were recorded in
November and December 2011, which were very dry months. Based on the local
precipitation data as shown in Table 2, there was very little precipitation in November and no
precipitation in December.
17. The background TSP concentrations in Baiyin area were also collected and are
shown in Table 3. As it can be seen from this table, the monthly average background TSP
concentrations in December 2011 were over 0.5 mg/m3, which is much higher than the
national standard and also higher than the concentrations near the construction site.
18. The background PM10 concentrations in Baiyin area were also collected and are
shown in Table 4. As it can be seen from this table, the monthly average background PM10
concentrations in November and December 2011 were 0.158 mg/m3 and 0.224 mg/m3,
respectively, and they all exceeded the national ambient air quality standard for PM10.
19. Based on above analysis, it is reasonable to conclude that the high TSP and PM10
concentrations are not likely caused by the project activities. It’s also observed that the
average TSP and PM10 values are lower than the values in the previous semi-annual
environmental monitoring report. The results indicated that the implemented mitigation
measures contribute to improvement.
Table 1: Air Quality Monitoring Results for Southern Baiyin Infrastructure
Sampling Period Sample ID TSP (mg/m3) PM10 (mg/m3)
2011-7-8 1-1 0.233 0.088
1-2 0.189 0.076
2011-7-9 1-3 0.196 0.100
1-4 0.201 0.130
2011-8-2 1-1 0.238 0.126
1-2 0.240 0.130
2011-8-3 1-3 0.235 0.099
1-4 0.201 0.096
2011-9-11 1-1 0.256 0.131
1-2 0.301 0.127
2011-9-12 1-3 0.244 0.090
ADB Loan No. 2407-PRC 8
1-4 0.178 0.086
2011-10-19 1-1 0.238 0.141
1-2 0.205 0.103
2011-10-20 1-3 0.237 0.075
1-4 0.258 0.115
2011-11-5 1-1 0.322 0.121
1-2 0.354 0.144
2011-11-6 1-3 0.289 0.138
1-4 0.311 0.147
2011-12-13 1-1 0.358 0.145
1-2 0.321 0.138
2011-12-14 1-3 0.398 0.166
1-4 0.418 0.150
Source: Baiyin Environmental Protection Bureau
Table 2: Precipitation in Baiyin in 2011
Month Precipitation (mm)
July 28.5
August 35.7
September 44.2
October 9.3
November 0.6
December 0
Source: Baiyin Weather Bureau
Table 3: Ambient TSP Monitoring Data in Baiyin in 2011
Location Month TSP (mg/m³)
HiTech Park December 0.592
Yinguang dependent district December 0.564
Source: Baiyin Environmental Protection Bureau
ADB Loan No. 2407-PRC 9
Table 4: Ambient PM10 Monitoring Data in Baiyin in 2011
Month Monthly Average PM10 (mg/m³)
July 0.094
August 0.073
September 0.060
October 0.084
November 0.158
December 0.224
Note: Data from the monitor station near Electric Power Co.
Source: Baiyin Environmental Protection Bureau
2. Noise Monitoring
20. Noise was monitored in the areas affected by the subproject around the site
boundary during the construction period. The monitoring locations for noise are also shown
in Figure 1. The monitoring lasted for one day each month from July to December 2011, and
the equivalent continuous A-weighted sound pressure level (Leq) was tested during daytime
from 6:00 to 22:00 and during the night from 22:00 to 6:00.
Figure 1: Monitoring Locations for Southern Baiyin Infrastructure Subproject
Tengjia Zhuangzi
Village
1#
△ Noise Monitoring Locations
Air Monitoring Location
21. The applicable standard used for noise monitoring and compliance evaluation is the
Standard of Noise at Boundary of Industrial Enterprises, GB 12348-2008. The area where
△1# △2# Zhaojiataizi Village
National Highway 109
Bai-Lan Expressway
N
Nanhuan road
JingbaRoad
△4#
△3#
ADB Loan No. 2407-PRC 10
monitoring locations were located is the 4th category sound environmental functional area,
where upper noise limits for daytime and night are 70 dB (A) and 55 dB (A), respectively.
22. The noise monitoring results are summarized in Table 5 and showed that the
recorded noise results were in compliance with the standards of 70 dB (A) in daytime and 55
dB (A) at night based on the functional category.
Table 5: Noise Monitoring Results for Southern Baiyin Infrastructure
Leq[dB(A)]
No. Daytime Night
7-8 8-3 9-11 10-19 11-6 12-14 7-8 8-3 9-11 10-19 11-6 12-14
1# 42.5 47.9 49.7 50.1 49.8 49.4 36.3 38.6 41.1 37.5 38.7 38.4
2# 45.6 47.3 48.7 50.6 48.5 47.3 40.0 41.2 38.8 37.8 39.3 37.7
3# 48.6 48.5 47.2 48.8 47.3 48.8 37.3 38.4 37.7 38.3 39.2 36.3
4# 49.8 45.5 47.6 50.8 48.6 48.5 35.9 41.7 40.4 37.5 36.2 39.4
Source: Baiyin Environmental Protection Bureau
23. The monitoring results are lower than the values in previous semi-annual
environmental monitoring report, which indicates that the implemented mitigation measures
contribute to improvement of noise environment.
3. Wastewater Monitoring
24. Since no wastewater is generated from this construction site in the second half of
2011, monitoring data concerning wastewater discharged into the municipal sewers was not
collected during the reporting period.
4. Solid Waste
25. The subproject earth work is conducted during the construction period. Waste soil
excavated during earth work was transported to a designated place and disposed properly.
E. Mitigation Measures Implemented and Compliance Assessment
1. Dust Suppression
26. The Contractor was responsible to implement dust control measures, including
developing a dust suppression program for water spraying, and daily water spraying on the
construction site to suppress fugitive dusts. Particularly, in dry and windy conditions, water
spraying was conducted more frequently. Construction materials were covered to avoid
fugitive dust emissions.
ADB Loan No. 2407-PRC 11
2. Noise Control
27. Construction time was properly planed from 7:00 to 18:00, and night work was
forbidden. The construction sites are far from the sensitive points, such as residential area,
school and hospital etc. Construction equipment with low noise was selected to be used
during the construction period, and the construction equipment was located as close to the
center of the site as possible. Due to the mitigation measures, the noise monitoring results
indicated that noise levels are in compliance with the national standards in China.
3. Wastewater Control
28. No wastewater is generated from this construction site in the second half of 2011.
Once the wastewater is generated from the site, which will be discharged to the municipal
sewer system for further treatment to avoid secondary pollution. Especially the domestic
wastewater from construction sites of procurement package C02 and C01 will be all
discharged to the septic-tank.
4. Solid Waste
29. Truck cleaning facilities were located at the entrance and exit of the construction site
to control fugitive soils caused by truck outside the construction area. The soil from the earth
work was appropriately used and timely transported out when necessary. A guard net was
employed during transportation to avoid fugitive dust. Water spraying was applied following
the backfill. The solid waste was collected, and which was placed on the designated area.
5. Compliance with Safety or Environmental Standards
30. No violations of safety or environmental standards was reported during the reporting
period besides the TSP and PM10 violations identified above.
F. Issues and Recommendations
31. A few monitored TSP and PM10 results exceeded the national standards. However,
based on the background monitoring data, high levels of TSP and PM10 are recorded in
Baiyin area. The TSP and PM10 monitoring results are better than the values in the previous
semi-annual environmental monitoring report. Even though the high TSP and PM10
concentrations were not likely caused by the project activities, it is still recommended that
more air pollution mitigation measures be taken according the EMP to minimize fugitive dust
emissions from the project.
ADB Loan No. 2407-PRC 12
III. BAIYIN DISTRICT ROAD IMPROVEMENTS
A. Scope of the Subproject
32. Under this component, the Project will (i) construct nine new roads with total length
of 23.1 km; and (ii) build connected water supply pipelines, drainage pipelines, sewers,
heating supply pipelines, lighting, bus rider/pedestrian and bicycle facilities. This component
will also (i) build 14 bridges/culverts and (ii) rehabilitate and widen three existing roads with a
total length of 6.1 km.
33. There was a change of scope of this subproject in 2011. The specific changes in
subproject scope are as follows: (i) 3.2 km road sections from East Binhe Road and West
Binhe Road as per the reprioritized urban transport development plan has been removed.
The removed road sections will be constructed at later stage. Baiyin DRC approved the
proposed scope change in March 2011; (ii) Extension of rehabilitation works of Fangzhi
Road of 451 m to ensure the smooth and constant traffic along the whole road. ADB’s review
mission in July 2010 visited the site and noted that that the proposed extension works would
be along the existing Fangzhi Road and will not involve any resettlement. Environmental
impact assessment was performed and it was concluded that there is no substantial negative
environment impact. Baiyin DRC approved the proposed extension in January 2011; and (iii)
Add additional rehabilitation and maintenance works for six primary or secondary roads in
Baiyin District.
B. Subproject Progress
34. There are three procurement packages under the ADB loan for this subproject. Two
of them are civil works packages and one is the equipment procurement package.
35. The planned total investment for this subproject was CNY 338,271,300, of which the
construction investment was CNY 235,985,500. Civil works contract C05 would need to be
amended to reflect the extension of Fangzhi Road rehabilitation works. The contract amount
will be increased from CNY91, 670,400 to CNY94, 690,437 (3% of original contract price).
The contract was extended to 30 June 2012. By the end of 2011, CNY 198,250,000 of
contract amount was completed, of which CNY 92,796,800 of construction investment was
completed. From January to the end 2011, the contract amount was completed by CNY 45
million, which accounts for 35.79% of CNY 125,728,600 of investment planned in 2011.
C. Environmental Management Office
36. The Baiyin City Construction Bureau (BCCB) has appointed Mr. Wang Dongye as the
responsible manager for the environmental management of this subproject as required by
the EMP.
ADB Loan No. 2407-PRC 13
D. Environmental Monitoring
1. Air Quality Monitoring
37. Three air quality monitoring locations downwind from the construction site of the
subproject were selected as monitoring stations and they were located approximately 200
meters from the site boundary. TSP, PM10, and NOx were monitored for three days in
November. The locations of the monitoring stations are shown in Figure 2.
38. The results from the air quality monitoring, as shown in Table 6 below, indicates that
the maximum value of TSP was 0.421 mg/m3. Eight out of nine samples (or approximately
89%) have the daily values for TSP higher than the national limit of 0.30 mg/m3. For PM10,
the maximum daily value was 0.147 mg/m3, which is below the national standard of 0.15
mg/m3. For NOx, the maximum daily value was 0.028 mg/m3, and all of the values were
less than the standard value of 0.08 mg/m3. Compare to the previous data from last
semi-annual environmental report, average values of TSP, PM10 and NOx in three locations
are higher.
Figure 2: Monitoring Locations for Baiyin District Road Improvements Subproject
▲4
▲ Noise Monitoring Location
■ Air Monitoring Location
▲■1 Dijiatai Village
▲■2 Dijiatai Village
Train Station
▲■3 Dijiatai Village
Beijing Road
Wei’er Road
Jinsan Road
National Highway 109
ADB Loan No. 2407-PRC 14
39. The high TSP monitoring results are mainly due to three factors: dry winter season,
high background concentration and inadequate implementation of the TSP mitigation
measures. As explained earlier, the background TSP concentrations in Baiyin area, as
shown in Table 3, were very high in winter months. As it can be seen from Table 3, the
monthly average background TSP concentrations in December 2011 were over 0.5 mg/m3,
which is much higher than the national standard.1
Table 6: Air Quality Monitoring Results for Baiyin District Road Improvements (Daily Value)
unit: mg/m3
Sample ID Sampling
PeriodTSP PM10 NOx
1-1 2011-11-21 0.412 0.121 0.023
1-2 2011-11-22 0.320 0.143 0.020
1-3 2011-11-23 0.406 0.108 0.024
3-Day Average 0.380 0.124 0.022
2-1 2011-11-21 0.421 0.110 0.027
2-2 2011-11-22 0.311 0.138 0.019
2-3 2011-11-23 0.257 0.122 0.028
3-Day Average 0.336 0.123 0.025
3-1 2011-11-21 0.411 0.135 0.020
3-2 2011-11-22 0.402 0.145 0.022
3-3 2011-11-23 0.355 0.147 0.017
3-Day Average 0.389 0.142 0.020
Source: Baiyin Environmental Protection Bureau
2. Noise Monitoring
40. Noise was monitored around the construction sites in July and November 2011. The
monitoring locations are also shown in Figure 2. The noise monitoring at each location
lasted for two days, and the equivalent continuous A-weighted sound pressure level (Leq)
was sampled during day-time from 6:00 to 22:00 and at night from 22:00 to 6:00 of each day.
41. The applicable standard used for noise monitoring and compliance evaluation is the
Standard of Noise at Boundary of Industrial Enterprises, GB 12348-2008. All monitoring
locations were located in the 1st category sound environmental functional area, where the
upper noise limits for daytime and night are 55 dB (A) and 45 dB (A), respectively. The noise
monitoring results, summarized in Table 7 showed that the recorded noise results were in
compliance with the standards of 55 dB (A) in daytime and 45 dB (A) at night based on the
1 Background TSP concentrations in Baiyin area were not available as of the date of the report finalization.
ADB Loan No. 2407-PRC 15
functional category. And most of the values are lower than those in last semi-annual
environmental report, especially at night.
Table 7: Noise Monitoring Results for Baiyin District Road Improvements Leq[dB(A)]
Sample Station
Daytime Night
7-5 7-6 11-21 11-22 7-5 7-6 11-21 11-22
#1 47.3 48.7 47.5 46.0 33.1 34.3 33.1 33.1
#2 46.6 47.8 48.0 47.7 32.3 33.6 32.4 32.7
#3 46.3 47.7 41.4 44.3 33.1 34.3 34.9 36.7
#4 47.1 45.4 43.1 43.5 34.7 33.4 35.3 37.5
Source: Baiyin Environmental Protection Bureau
3. Wastewater Monitoring
42. No monitoring data concerning wastewater discharged into the municipal sewer were
collected during the reporting period.
4. Solid Waste
43. Construction wastes and domestic wastes were produced during the construction
period and they were placed at the designated site and disposed to the authorized solid
waste site.
E. Mitigation Measures Implemented and Compliance
44. Based on the reports from the PIAs and on-site supervision companies, mitigation
measures for environmental protection taken by contractors as well as compliance with
safety and environmental regulations are summarized below.
1. Dust Suppression
45. The contractor implemented dust control measures including spraying water to
suppress dust at the construction site. Particularly, in dry and windy conditions, more water
must be sprayed. Construction materials without packages were placed in a transient
warehouse or covered to avoid fugitive dust emissions.
2. Noise Control
46. According to mitigation plans, construction time must be properly planned and night
work is strictly forbidden. Construction equipment with low noise level was selected during
the construction period, and the construction equipment was located as far as possible from
ADB Loan No. 2407-PRC 16
sensitive areas. However, some high noise levels were measured and this is primarily due to
other noise sources not related to the road construction activities.
3. Wastewater Control
47. Wastewater generated from the construction sites was discharged into municipal
sewers for treatment to avoid secondary pollution.
4. Solid Waste
48. The truck clearing facilities were placed at the site to minimize fugitive dust
emissions. The soil from the pipe trenching was used and timely transported away. Other
construction waste was also transported out of the construction site.
5. Compliance of Safety or Environmental Standards
49. A slight high noise levels were observed. No other violations of safety or
environmental standards were observed and reported during the reporting period.
F. Issues and Recommendations
50. The monitored TSP and PM10 results indicated that some values exceeded the
national standards, and the monitoring results in three locations were also higher than the
previous semi-annual environmental report. It is recommended the IA and contractor
should take more air pollution mitigation measures according the EMP to ensure comply with
the national standards. More specifically, increasing the frequency of water sprays will help
reducing the TSC and PM10 levels. However, based on the background monitoring data, high
levels of TSP and PM10 are often recorded in Baiyin area, especially during winter dry
season. Due to dry climate conditions, baselines levels sometimes exceed the national
standards for TSP and PM10.
ADB Loan No. 2407-PRC 17
IV. PINGCHUAN DISTRICT ROAD IMPROVEMENTS SUBPROJECT
A. Scope of the Subproject
51. Under this component, the Project will construct 12.6 km roads; and the related
sewage pipelines, storm-water pipelines and water supply pipelines; rehabilitate existing one
road with the total length of 3.5 km; (ii) build three new Step River Bridges, and 7 culverts.
B. Subproject Progress
52. This subproject has two packages and both are for civil works. Both contracts have
been awarded and construction activities have substantially completed.
53. The total planned investment for Pingchuan District Component was CNY
210,005,000, of which the construction investment was CNY 160,150,800. By the end of
2011, the investment was completed by CNY 175.1 million accumulatively, of which
construction investment was completed by CNY 138.5 million. From January to the end
2011, the contract amount was completed by CNY 19.1 million, which accounts for 37.58%
of CNY 50,821,000 of investment planned in 2011.
C. Environmental Management Office
54. The Pingchuan District Government (PDG) has established an environmental
management office according to the requirements of the EMP and appointed Mr. Wang
Lianzhong to be responsible for the environmental management of this subproject.
D. Environmental Monitoring
1. Air Quality Monitoring
55. Nine air quality monitoring locations downwind from the construction site of the
subproject were selected as monitoring stations. TSP, PM10, and NOx were monitored for
three days in November 2011. The monitoring locations are shown in Figure 3.
56. The results of the air quality monitoring in November 2011, as seen in Table 8,
showed that the maximum value of TSP was 0.487 mg/m3. All 27 values for TSP were higher
than the national standard of 0.30 mg/m3. For PM10, the maximum daily value was 0.203
mg/m3. Nine values for PM10 are higher than the national standard of 0.15 mg/m3. For NOx,
the maximum daily value was 0.030 mg/m3, and all of the values were less than the national
standard value of 0.08 mg/m3. And the monitoring results in nine locations are higher than
the previous data from the last semi-annual environmental report, especially TSP.
ADB Loan No. 2407-PRC 18
Figure 3: Monitoring Locations for Pingchuan District Road Improvements Subproject
▲ Noise Monitoring Location
■ Air Monitoring Location
▲■3 Hospital
▲■1 Resident Area
▲■2 Resident Area
▲■4 Resident Area
▲■6 School
▲5■ Resident Area
Pinchuanbei Road
No. 1 Road
Kaifa Road
Guangchang road
▲■7 Resident Area
▲■9 Resident Area
▲■8 Resident Area
Gonghe Road
No. 2 Road
ADB Loan No. 2407-PRC 19
57. Even though the background TSP and PM10 concentrations are high in Baiyin area in
winter months due to dry climate, the monitoring results indicate that the dust control
mitigation measures as specified in the EMP are not properly implemented. The PIA must
work closely with the construction contractors to ensure that the mitigation measures are
adequately implemented.
Table 8: Air Quality Monitoring Results for Pingchuan District Road Improvements (Daily Value)
Unit: mg/m3
Sample ID Sampling
Period TSP PM10 NOx
1-1 2011-11-5 0.400 0.203 0.016
1-2 2011-11-6 0.423 0.150 0.010
1-3 2011-11-7 0.445 0.105 0.022
3-Day Average 0.423 0.153 0.016
2-1 2011-11-5 0.428 0.173 0.014
2-2 2011-11-6 0.312 0.156 0.020
2-3 2011-11-7 0.306 0.153 0.025
3-Day Average 0.349 0.161 0.020
3-1 2011-11-5 0.311 0.130 0.019
3-2 2011-11-6 0.388 0.155 0.021
3-3 2011-11-7 0.421 0.110 0.020
3-Day Average 0.373 0.132 0.02
4-1 2011-11-5 0.396 0.125 0.020
4-2 2011-11-6 0.323 0.114 0.017
4-3 2011-11-7 0.311 0.086 0.024
3-Day Average 0.343 0.108 0.020
5-1 2011-11-5 0.303 0.140 0.022
5-2 2011-11-6 0.355 0.162 0.028
5-3 2011-11-7 0.358 0.134 0.023
3-Day Average 0.339 0.145 0.024
6-1 2011-11-5 0.300 0.143 0.020
6-2 2011-11-6 0.323 0.108 0.024
6-3 2011-11-7 0.433 0.170 0.027
3-Day Average 0.352 0.140 0.024
7-1 2011-11-5 0.396 0.168 0.019
7-2 2011-11-6 0.321 0.122 0.028
ADB Loan No. 2407-PRC 20
Sample ID Sampling
Period TSP PM10 NOx
7-3 2011-11-7 0.487 0.135 0.030
3-Day Average 0.401 0.142 0.026
8-1 2011-11-5 0.412 0.138 0.021
8-2 2011-11-6 0.382 0.102 0.020
8-3 2011-11-7 0.354 0.133 0.023
3-Day Average 0.383 0.124 0.021
9-1 2011-11-5 0.366 0.152 0.018
9-2 2011-11-6 0.420 0.117 0.021
9-3 2011-11-7 0.415 0.120 0.020
3-Day Average 0.400 0.130 0.020
Source: Baiyin Environmental Protection Bureau
2. Noise Monitoring
58. Noise levels around the construction site were monitored in September and
November 2011. The monitoring locations are shown in Figure 3 as well. The sample
collection period lasted for two days, and the equivalent continuous A-weighted sound
pressure level (Leq) was collected during daytime from 6:00 to 22:00 and at night from 22:00
to 6:00 of each day.
59. The applicable standard used for noise monitoring and compliance evaluation is the
Standard of Noise at Boundary of Industrial Enterprises, GB 12348-2008. The area where #1
to #4 monitoring locations were located is the 1st category sound environmental functional
area, where noise upper limits for daytime and night are 55 dB (A) and 45 dB (A),
respectively.
60. The noise monitoring results are shown in Table 9 and they showed that five out of
36 recorded daytime noise levels exceeded the standard values of 55 dB(A) slightly.
However, the noise levels are lower than the values for the last semi-annual environmental
report. One of 36 recorded values at night exceeded the standard of 45 dB (A).
Table 9: Results of Noise Monitoring for Pingchuan District Road Improvements
Leq[dB(A)]
Sample Station Daytime Night
9-11 9-12 11-25 11-26 9-11 9-12 11-25 11-26
#1 55.4 54.6 53.3 53.1 42.3 40.5 43.5 42.4
#2 55.6 53.7 54.4 55.2 41.5 43.7 42.2 41.2
#3 52.1 51.6 51.8 52.5 44.2 42.7 45.6 42.3
#4 55.3 52.2 53.7 54.3 43.2 42.2 44.7 43.7
ADB Loan No. 2407-PRC 21
#5 56.2 54.5 53.4 54.6 41.3 41.5 42.3 38.6
#6 54.2 53.3 54.5 52.2 43.5 43.8 43.2 41.0
#7 53.6 51.2 51.2 52.5 42.7 42.5 40.4 40.4
#8 53.5 52.5 53.1 52.1 41.5 42.7 42.6 41.1
#9 54.0 52.1 52.5 53.7 42.1 40.6 40.3 42.4
Source: Baiyin Environmental Protection Bureau
3. Wastewater and Solid Waste
61. No monitoring data concerning wastewater discharged into the municipal sewers was
provided during the reporting period. Construction waste and domestic waste were produced
during the construction period and they were placed at the designated site and disposed of
properly.
E. Mitigation Measures Implemented and Compliance
1. Dust Suppression
62. The Contractor was responsible to implement dust control measures, including
implementing the dust suppression program, and spraying water to suppress dust. It was
reported and observed that the water sprays were applied. Based on the monitoring results,
it indicates that the mitigation measures were not fully implemented.
Figure 4: Water Sprays for Fugitive Dust Control
ADB Loan No. 2407-PRC 22
2. Noise Control
63. The construction time was properly planed, and night work was forbidden.
Construction equipment with low noise was selected and used during the construction
period. Construction equipment should be appropriately located to minimize noise levels.
Mitigation measurements should be enhanced to control noise levels both during daytime
and at night since some noise measurement data exceeded the National Standard.
3. Wastewater Control and Solid Waste Management
64. Wastewater generated by construction activities was collected and discharged into
municipal sewers to avoid secondary pollution. The soil from the earth work was covered
and backfilled regularly. Construction waste during bridge construction was transported out
of the area shortly.
4. Violation of Safety or Environmental Standards
65. Other than the high levels of TSP, PM10 and noise levels identified above, no other
violations of safety or environmental standards was reported during the reporting period.
F. Issues and Recommendations
66. The monitored TSP and PM10 exceeded the national standards, and the monitoring
results in nine locations are also higher than the data from last semi-annual environmental
report, especially TSP. Therefore, it’s recommended more frequent water sprays must be
applied to mitigate the TSP and PM10 emissions.
ADB Loan No. 2407-PRC 23
V. Baiyin District Heating Services Subproject
A. Scope of the Subproject
67. The scope of this subproject includes expanding the district heating service area in
Baiyin District by 3.2 million m2 through (i) building a new heating source plant with 4x58
megawatts (MW) capacity, (ii) laying down 12.6 km of heat transmission pipelines, and (iii)
installing 29 heat exchange stations for connection with the community heat distribution
systems.
B. Subproject Progress
68. The construction of the heating resource plant has been completed. All four boilers
have been installed at the boiler plant. The four boilers were in operation during the heating
season in 2011. As of the end of 2011, 29,160 m of heating pipe networks have been laid
and 14 heating exchange stations have been installed and put into operation. In addition, 60
small coal-fired boilers from 34 small boiler stations have been removed from service and
the area connected to these boilers are now served by the central heating plant.
69. An online continuous emission monitor (CEM) system is required per the approved
environmental impact assessment report by the municipal environmental authority and the
EMP. However, such a system has yet to be installed. To meet this requirement, Baiyin PMO
and MDHC requested to add a new package into the procurement plan for procuring and
installing a CEM system in the heating source plant. This system will monitor the emission of
flue dust, SO2 and NOx, and will be connected to the monitoring system of Baiyin
Environmental Protection Bureau. Cost of this package is estimated at CNY1.28 million.
70. By the end of 2011, the investment was completed by CNY 157.44 million
accumulatively, of which construction investment was completed by CNY 145.94 million.
C. Environmental Management Office
71. An EMO has been established by the IA to monitor the implementation of the EMP.
Minyue District Heating Company (MDHC) has appointed Mr. Zeng Xianlong to be
responsible for the environmental management of this subproject.
D. Environmental Monitoring
1. Air Quality Monitoring
72. Three air quality monitoring stations downwind of the heat source plant were set up
and their locations are shown in Figure 5. TSP was monitored every month from July
through December 2011. The monitoring data was collected two times each month, and
each monitoring period lasted for two days.
ADB Loan No. 2407-PRC 24
Figure 5: Monitoring Locations for Baiyin District Heating Services Subproject
▲1
▲1
▲2 ▲4
▲3
▲Noise monitoring locations at site boundary
■ Air monitoring spots
73. The results of air quality monitoring, shown in Table 10, indicate that the minimum
daily value for TSP was 0.156 mg/m3, and the maximum daily value of 0.410 mg/m3. 20
values of 72 recorded values (27.8%) for TSP were higher than the national standard value
of 0.30 mg/m3. TSP values of November and December were higher than other months.
Since there was no construction activities in these two months, this is mainly due to high
background TSP concentrations during dry winter season as explained earlier and the start
of a new heating season.
Table 10: Air Quality Results Monitoring for Baiyin District Heating Services
July 2011 unit: mg/m3
Sample ID Sampling Period TSP
1-1 2011-7-5 0.201
1-2 2011-7-6 0.225
1-3 2011-7-22 0.189
1-4 2011-7-23 0.212
Coal Yard O
ffice and Pum
p R
oom
Electricity
Boiler House
Draft Room间
Precipitator Room
N
Changan Road
Shanghai Road
Tianjin Road
Slag Yard
■3 north resident area
■1northeast resident area
■2 east resident area
ADB Loan No. 2407-PRC 25
2-1 2011-7-5 0.220
2-2 2011-7-6 0.238
2-3 2011-7-22 0.196
2-4 2011-7-23 0.202
3-1 2011-7-5 0.235
3-2 2011-7-6 0.245
3-3 2011-7-22 0.203
3-4 2011-7-23 0.211
August 2011 unit: mg/m3
Sample ID Sampling Period TSP
1-1 2011-8-4 0.232
1-2 2011-8-5 0.211
1-3 2011-8-19 0.156
1-4 2011-8-20 0.267
2-1 2011-8-4 0.243
2-2 2011-8-5 0.186
2-3 2011-8-19 0.212
2-4 2011-8-20 0.215
3-1 2011-8-4 0.213
3-2 2011-8-5 0.165
3-3 2011-8-19 0.178
3-4 2011-8-20 0.216
September 2011 unit: mg/m3
Sample ID Sampling Period TSP
1-1 2011-9-7 0.236
1-2 2011-9-8 0.174
1-3 2011-9-28 0.234
1-4 2011-9-29 0.253
2-1 2011-9-7 0.253
2-2 2011-9-8 0.216
2-3 2011-9-28 0.256
2-4 2011-9-29 0.176
3-1 2011-9-7 0.245
ADB Loan No. 2407-PRC 26
Sample ID Sampling Period TSP
3-2 2011-9-8 0.223
3-3 2011-9-28 0.156
3-4 2011-9-29 0.167
October 2011 unit: mg/m3
Sample ID Sampling Period TSP
1-1 2011-10-11 0.183
1-2 2011-10-12 0.194
1-3 2011-10-25 0.177
1-4 2011-10-26 0.241
2-1 2011-10-11 0.199
2-2 2011-10-12 0.187
2-3 2011-10-25 0.240
2-4 2011-10-26 0.223
3-1 2011-10-11 0.222
3-2 2011-10-12 0.289
3-3 2011-10-25 0.240
3-4 2011-10-26 0.213
November 2011 unit: mg/m3
Sample ID Sampling Period TSP
1-1 2011-11-2 0.290
1-2 2011-11-3 0.330
1-3 2011-11-20 0.313
1-4 2011-11-21 0.341
2-1 2011-11-2 0.391
2-2 2011-11-3 0.409
2-3 2011-11-20 0.347
2-4 2011-11-21 0.322
3-1 2011-11-2 0.290
3-2 2011-11-3 0.400
3-3 2011-11-20 0.314
3-4 2011-11-21 0.342
December 2011 unit: mg/m3
ADB Loan No. 2407-PRC 27
Sample ID Sampling Period TSP
1-1 2011-12-4 0.377
1-2 2011-12-5 0.357
1-3 2011-12-22 0.266
1-4 2011-12-23 0.294
2-1 2011-6-4 0.337
2-2 2011-6-5 0.358
2-3 2011-6-19 0.383
2-4 2011-6-20 0.367
3-1 2011-6-4 0.404
3-2 2011-6-5 0.329
3-3 2011-6-19 0.329
3-4 2011-6-20 0.410
Source: Baiyin Environmental Protection Bureau
2. Noise Monitoring
74. Noise was monitored in the areas affected by the subproject around the site
boundary during the construction period. The monitoring locations are also shown in Figure
5. The monitoring lasted for two days, and the equivalent continuous A-weighted sound
pressure level (Leq) was measured during daytime from 6:00 to 22:00 and at night from
22:00 to 6:00 of each day. The applicable standard used for noise monitoring and
compliance evaluation is the Standard of Noise at Boundary of Industrial Enterprises, GB
12348-2008.
75. The noise monitoring results, summarized in Table 11, showed that the recorded
results for noise were in compliance with the national standards of 70dB during daytime and
55 dB during night. And the noise monitoring results were lower than the results collected
from last semi-annual environmental report.
Table 11: Noise Monitoring Results for Baiyin District Heating Services Quarter 3 Leq[dB(A)]
Number Daytime Night
7-5 7-6 8-17 8-18 7-5 7-6 8-17 8-18
1# 56.3 56.1 56.8 52.6 45.1 46.6 44.3 46.1
2# 58.5 55.6 56.6 54.4 46.2 44.7 43.4 47.7
3# 55.2 54.8 54.6 55.5 44.4 46.2 46.6 45.4
4# 54.1 53.4 55.4 55.4 43.6 43.5 45.8 45.7
Quarter 4
ADB Loan No. 2407-PRC 28
Number Daytime Night
10-10 10-11 11-20 11-21 10-10 10-11 11-20 11-21
1# 57.4 56.5 61.6 53.6 48.7 49.1 45.9 49.1
2# 56.3 59.3 53.8 53.1 51.4 48.5 51.4 52.6
3# 54.6 56.7 53.7 55.8 52.7 47.8 49.3 47.0
4# 53.3 54.7 55.8 56.8 50.8 50.3 47.5 49.9
Source: Baiyin Environmental Protection Bureau
3. Wastewater Monitoring and Solid Waste Management
76. No monitoring data concerning wastewater discharged into the municipal sewers was
provided during the reporting period. Construction wastes and domestic wastes were placed
at the designated site and disposed of properly.
4. Demolishing Small Boilers
77. No additional small boilers were closed during this reporting period. So far 31 boiler
houses with a total 46 small boilers have been decommissioned.
E. Mitigation Measures Implemented and Compliance
1. Dust Suppression
78. The coal pile at the heat source plant is supposed to be cover to avoid fugitive dust
emissions. However, it was not covered during the site visits. The dust collector in the heat
source plant was put into service for reducing the dust emission.
2. Noise Control
79. Since the construction of the heat source plant has been completed. Noise mitigation
measures have been taken for the fans and pumps in the heat source plant during the
normal operation of the plant.
3. Wastewater Control and Solid Waste Management
80. Wastewater was discharged into municipal sewers to avoid secondary pollution.
Wastewater of the heat source plant was treated and then discharged. The slag and ash
produced from the boiler were sold to a construction company that use it as a raw building
material.
ADB Loan No. 2407-PRC 29
4. Compliance of Safety or Environmental Standards
81. Other than the high TSP levels identified above, no other violations of safety or
environmental standards were reported during the reporting period.
F. Issues and Recommendations
82. TSP, SO2, NOx, and PM10 emissions are required to be monitored at the heat source
plant. Stack emission testing and a CEM system should be installed in 2012.
83. The environmental management of the coal yard needs to be further enhanced. The
coal should be covered to prevent fugitive dust emissions.
ADB Loan No. 2407-PRC 30
VI. CONCLUSIONS
84. The EMPs for the four subprojects were generally implemented during the
construction period in 2011. In accordance with the national and local environmental codes
and regulations, and the requirements of the PIAs, contractors carried out environmental
protection and mitigation measures. The adverse environmental impacts arising from the
construction period were minimized by implementing relevant mitigation measures. In
general, the subprojects were constructed in accordance with the national and local
environmental protection procedures, and the requirements of the EIAs. The noise
monitoring results of the four subprojects were better than the those in last semi-annual
environmental report.
85. However, the monitoring results indicated that TSP emission levels November and
December in many monitoring locations exceeded the national standards for some
subprojects, such as Baiyin District Road improvement Subproject and Pingchuan District
Road Improvement Subproject. The data in some monitoring locations are also higher than
the data from last semi-annual environmental report, This is partly due to the high level of
background TSP levels in Baiyin area. However, it is necessary to take further environmental
protection and mitigation measures to reduce fugitive dust emissions from the construction
sites.
86. The CEM system should be procured, installed and calibrated before the 2012
heating season starts. Environmental acceptance by the Baiyin EPA should be conducted
for the heat source plant during heating season. SO2, NOx and PM10 monitoring data should
be collected and analyzed during both heating season and non-heating season.
Desulfurization and dust removal measures must be conducted to reduce SO2 and flue dust
emission.
ADB Loan No. 2407-PRC 31
Appendix 1. Summary Information of Closed Small Boilers Houses by the End of 2011
No. Owner QuantityOutput of
Boiler (kW)
Efficiency of Boiler
(%)
Start Date
Actual Date of Closure
Heating Area (m2)
Coal heating value
(kJ/kg)
Annual Coal Consumption
(ton)
Heating Days
1 Government of Wangjian Xiang 1 1,400 65 1980 2009 18,000 20,900 1,450 150
2 Club of Tian Shang Ren Jian 1 1,400 65 1981 2009 17,500 20,900 1,450 150
3 Highway Division of Baiyin District 1 1,400 65 1982 2009 18,500 20,900 1,450 150
4 CDC of Baiyin District 1 1,400 65 1988 2010 15,000 20,900 720 150
5 Wangjian Bank of Baiyin District 1 1,400 65 1981 2009 15,000 20,900 1,450 150
6 Housing Administration Department of Baiyin District
1 1,400 65 1980 2010 15,000 20,900 1,450 150
7 Wu School of Baiyin District 1 1,400 65 1979 2010 10,000 20,900 1,450 150
8 Dorm of 21st Yan 3 8,400 65 1979 2010 120,000 20,900 5,000 150
9 Electricity Supply Bureau 2 11,200 75 1980 2010 160,000 20,900 7,000 150
10 Municipal Senior Welfare Apartment 1 1,400 65 1989 2010 15,000 20,900 720 150
11 Local Tax Bureau of Baiyin District 1 350 65 1982 2010 700 20,900 500 150
12 Cotton Fabric Factory of Gansu Shuangjia
2 8,400 68 1976 2009 50,000 20,900 4,000 150
13 Baiyin New Century Business Co. 1 1,400 65 1993 2010 12,000 20,900 720 150
14 Baiyin Ganbao Co. 2 9,100 70 1979 2008 80,000 20,900 6,000 150
15 Baiyin Zhengbu Factory 2 9,100 70 1976 2009 60,000 20,900 5,000 150
16 Baiyin Changtong Factory 2 21,000 75 1976 2009 80,000 20,900 6,000 150
17 Housing Bureau of Baiyin City 1 2,800 65 1979 2009 30,000 20,900 5,000 150
18 West Development Company 2 14,000 68 1990 2010 10,0000 20,900 6,000 150
19 Procuratorate of Baiyin City 1 700 65 1980 2009 9,000 20,900 400 150
20 Baiyin Electricity Supply Co. 2 5,600 65 1982 2009 30,000 20,900 5,000 150
ADB Loan No. 2407-PRC 32
No. Owner QuantityOutput of
Boiler (kW)
Efficiency of Boiler
(%)
Start Date
Actual Date of Closure
Heating Area (m2)
Coal heating value
(kJ/kg)
Annual Coal Consumption
(ton)
Heating Days
21 Municipal Agriculture Bank 1 2,800 65 1982 2010 30,000 20,900 5,000 150
22 Municipal Bank 2 5,600 65 1987 2009 50,000 20,900 4,000 150
23 Shiyan School of Baiyin City 2 4,200 65 1985 2009 50,000 20,900 4,000 150
24 Party School of Baiyin City 1 1,400 65 1982 2010 18,000 20,900 1,450 150
25 Construction Bank of Baiyin City 3 8,400 65 1985 2010 12,000 20,900 4,000 150
26 Fashion Factory of Baiyin City 2 1,190 65 1982 2009 10,000 20,900 700 150
27 Hesun Community of Baiyin City 1 1,400 65 1985 2010 18,000 20,900 720 150
28 Center for Training Teacher of Baiyin City 2 5,600 65 1982 2010 30,000 20,900 5,000 150
29 2nd School of Baiyin City 1 2,800 65 1987 2010 30,000 20,900 5,000 150
30 Municipal Gongxiao Lianshe 1 1,400 65 1985 2010 18,000 20,900 720 150
31 Baiyin Communication Bureau 1 700 65 1987 2010 9,000 20,900 580 150
32 Northwest Mineral and Metal Institute 3 9,100 70 1985 2011 78,000 20,900 3,432 150
33 Jiu Co. 5 19,950 75 1988 2011 180,000 20,900 7,650 150
34 Aluminum Factory Welfare Community 6 15,400 65 1980 2011 91,000 20,900 4,095 150
Total 60 183,190 1,479,700 107107
Source: PIA and consultants estimation.