Environmental Management Plan-Catanduanes

25
ROAD UPGRADING AND PRESERVATION PROJECT (RUPP) ENVIRONMENTAL MANAGEMENT PLAN For PBM-4 SURIGAO-DAVAO ROAD SURIGAO (LIPATA) – AGUSAN DEL NORTE BOUNDARY K1113+500 TO K1237+000 PROVINCES OF SURIGAO DEL NORTE AND AGUSAN DEL NORTE REGION XIII (CARAGA)

description

Environmental

Transcript of Environmental Management Plan-Catanduanes

Page 1: Environmental Management Plan-Catanduanes

ROAD UPGRADING AND PRESERVATION PROJECT (RUPP)

ENVIRONMENTAL MANAGEMENT PLAN

For

PBM-4 SURIGAO-DAVAO ROAD SURIGAO (LIPATA) – AGUSAN DEL NORTE BOUNDARY K1113+500 TO K1237+000

PROVINCES OF SURIGAO DEL NORTE AND AGUSAN DEL NORTE REGION XIII (CARAGA)

Submitted by:

EQUI-PARCO CONSTRUCTION COMPANY

Page 2: Environmental Management Plan-Catanduanes

ENVIRONMENTAL MANAGEMENT PLAN DURING CONSTRUCTION AND OPERATION

Issues Potential Impact Mitigation measurePersons to Implement

Persons to Monitor

Cost of Mitigation

Remarks

PRE-CONSTRUCTION PHASEEstablishment of work Camp

Increase of TSP noise, level and economic activities

Avoid occupying/using highly productive land instead occupy open land or coconut land. Limit working period from 7AM to 7PM.

Contractor DPWH, CSC LGU

5Million The contractor replied as the submitted EMP

CONSTRUCTION PHASE (a) Natural EnvironmentSoil and MaterialTopsoil Loss of fertility of arable

land The topsoil (about 15cm) will be kept and refilled after excavation is over to minimize the impact on productive lands.It may be necessary to construct new access roads to aggregate sites, and place them through agricultural lands. These temporary roads will be made along existing farm tracks so as to avoid losses to agricultural lands. Contractors will be required to present proposed construction road alignment and hauling schedule for approval before construction is to commence. In unavoidable circumstances,

suitable compensation will be paid to people whose land will be temporarily acquired for the duration of the operations. The compensation will cover for loss of income for the duration of acquisition and land restoration.

Contractor DPWH,CSC The contractor’s excavation activities only concentrated on the construction limits per approved plans, complied the EMP.

Soil erosion -High suspended soil contents of river, sedimentation

Visual monitoring and inspection of soil erosion at borrow areas, quarries embankments and other places expected to be affected, will be carried out once a month for dry season and once a week for rainy season as suggested in monitoring plan. On hill sections and other erodible site,

Contractor DPWH,CSC The construction supervision team considered the highly prone landslide areas by putting up berm and catchwall.

Page 3: Environmental Management Plan-Catanduanes

appropriate vegetation that retards erosion will be planted. Design consideration for erosion: slope and pier protection with retaining structure. Construction activities in hilly areas to be taken up only during dry season.

Reclaimed pavement Solid waste Contractors will be encouraged to recycle reclaimed aggregate in granular or stabilized surface material for subgrade and base layers and village access road maintenance and to use recyclable materials as much as possible. The material that cannot be reused will be taken to specific official waste dumping sites approved by the DENR. All suitable material obtained from roadway excavation work will be used for construction of embankment/earthen shoulder

Contractor, LGU Residents

DPWH, MMT, CSC

Not applicable. All existing PCCP are exempted from the project.

Slope Stability Landslides

-During cuts and excavation works, instability of soil or potential failure of exposed soil and rock materials can take place.

Retaining structures will be constructed for protection of landslides for the Project. The long term solution for landslides will be to maintain uphill vegetation cover, and appropriate agricultural activities in the steep banks with a diversification of crops and cropping techniques.

Removal of vegetation and cutting of trees will be done judiciously and limited to minimum possible extent.

Vegetative cover by planting grass and coconut are considered for the identified eroded section.

Contractor DPWH, CSC The constructions of catch wall and landslide protection were already considered in our preparation of As-stake plans.

Degradation of borrow areas

Loss of topsoil and disfigurement of landscape

Borrow pits and quarries will be redeveloped as per standard procedure. Rehabilitation of quarries and borrow sites will be undertaken immediately after excavation to prevent soil erosion.o Redevelopment will include:o Regrading slopes to minimize erosion,o Replacing stockpiled soil cover,o Replanting grass, shrubs, and trees,

Contractor DPWH, MMT, CSC

Cutting and removal of vegetation only up to the design construction limits

Page 4: Environmental Management Plan-Catanduanes

Quarry sites located close to the alignment with high level of accessibility and level gradient are preferred

Operation of quarry site on river banks

Sedimentation and siltation downstream and riverbank destruction

Changing the river pattern will have a beneficial impact to the flow regime of the rivers

No work will be permitted to site with fine sediments.

The depth of excavation from the river will be limited

Identify the riverbed, which has excessive sediments, and limits the excavation to ideal section and depth of the river

Permit to quarry site away from drinking water intakes and tributaries used by the community for domestic purposes

Depth and area of extraction limitation should be imposed to prevent loose materials disturbance that may trigger siltation. However, since one of the major problems in the area is soil erosion, landslide and flooding, excavation should be done in such a way that the flow of rivers should be improved.

Contractor LGU, DPWH, MMT

Siltation Adverse effects on channel stability Increasing coverage of open surface area

by planting grass so that washing away of materials from sloped surfaces would be reduced to a significant extent.

Construction materials containing fine particles, e.g. limestone or laterite, should be stored in an enclosure such that sediment laden water does not drain into nearby watercourses, but rather

Contractor DPWH, CSC All slope cutting were based on the approved design / as-stake.

Planting of trees are not part of the contractor’s approved contract but

percolates slowly into the soil. Sediment laden construction water will

be discharged into settling lagoons or tanks prior to final discharge.

maybe consider in the preparation of the As-stake plan if the environmental office concerned recommend for possible inclusion

Page 5: Environmental Management Plan-Catanduanes

thereto.Air, Noise, and Vibration

Emission from construction vehicles and equipment

Health hazard to workers and close by residents

Vehicles and machinery used for construction are to be regularly maintained. Idling of engines will be discouraged.

Each vehicle related to the construction has to have valid “Emission from for motor vehicle” during construction

Vehicular traffic through communities will be avoided as far as possible. Vehicle speeds will be kept low if they should pass through communities

Contractor DPWH, MMT, CSC

The contractor has vehemently complied with the EMP requirements.

Concrete plants Noise, DustAir Pollution

Set-up of concrete plants will be more than 1km of settlements and environmentally sensitive areas and preferably located on the leeward side

ECC permit Batching plants should be first secured prior to operation

Contractor’s ESO

DPWH, MMT, CSC

The contractor has vehemently complied with the EMP requirements. ECC for erected plants of the contractor was already issued. See attached copy.

Dust/Odor Air Pollution Water will be sprayed during the construction phase in all mixing areas where dry materials are handled and/or crushed. Temporary access roads to aggregate sites must be included in the dust suppression program. A spraying schedule will be prepared by the contractor and will serve as the basis of a dust control program. The Project authorities will regularly monitor this schedule.

Contractor DPWH, MMT, CSC

The contractor provided water truck for watering of all location that has construction activities to eradicate dust / air pollution.

Vehicles delivering materials to and from the construction sites will be covered to reduce spills.

Mixing and crushing plants/operations will be equipped with dust suppression devices such as water sprays. Operators will wear dust masks and ear protection.

The contractor has prepared canvas coverings on their dumptrucks.Plants have been erected with dust collector that will help

Page 6: Environmental Management Plan-Catanduanes

minimize the dust from spreading. Workers involved on plant operation are issued with related protective gears for their protection.

Dust and noise from borrow pits

Noise & Dust Ensure noise control measures to comply with national standards.

Watering of the earth roads close to the settlement, use covered truck.

Secure appropriate environmental permits

The borrow and material dumping sites must be access controlled to keep away unauthorized entry of people, grazing cattle and any other stray animals

Protective gear like ear plugs will be provided to operating personnel if they are exposed to noise levels beyond threshold limits

Contractor DPWH, MMT, CSC

The contractor provided water truck for watering of all location that has construction activities to eradicate dust / air pollution. Warning signage’s were installed on excavation areas.

Noise from construction activities

Noise pollution to the settlements

Noise standards at aggregate crushing plants and bitumen preparation sites will be strictly enforced to prevent noncompliance of acceptable noise standards 55 dBA for residential area in the day time and 45 dBA during the night time and 65 dBA for commercial and 75 dBA for industrial area. Maintenance of machinery and vehicles will be enhanced

Contractor DPWH, MMT, CSC

No construction activity at night time within the area that are fully populated. Contractor are willing to comply to the EMP requirements.

to minimize noise. When construction is taking place at

<500 m from the villages along both sides, and the road passes within 150m of sensitive area such as health centers, construction will be stopped from 21:00 to 06:00. This will reduced nighttime noise levels

Noise inspection will be done before construction equipments enter into construction site. All equipments shall

Page 7: Environmental Management Plan-Catanduanes

fulfill the noise control requirements of the project. Special attention shall be taken a regular maintenance of construction equipments for their best working condition.

WasteStorage of hydrocarbon and toxic chemicals

Contaminations from harmful and toxic chemicals (paints, fuel and lubricant, and oil

Hydrocarbon and toxic material will be stored in designated sites. Vehicle maintenance and refueling will be confined to areas in construction sites designed to contain spilled lubricants and fuels. Spill waste will be disposed at approved disposal sites.

Adequate precaution will be taken to prevent oil/lubricant/hydrocarbon contamination of channel beds. Spillage if any will be immediately cleared with utmost caution to leave no traces

All areas intended for storage of hazardous materials will be quarantined and provided with adequate facilities to combat emergency situations complying all the applicable statutory stipulation

The personnel in-charge of these sites will be properly trained and these areas will be access controlled and entry will be allowed only under authorization

Contractor’s ESO

DPWH, MMT, CSC

Adequate precaution taken by the contractor to prevent the oil/lubricants/hydrocarbon contamination.

The contractor compromised that any slippage will be immediately acted.

Solid waste from contractor’s yard

Contamination from solid waste

All construction materials will be reused, recycle and properly disposed of. All worn out parts. Equipment and empty containers must be removed from the site to a proper storage location designated by DENR.Solid waste and garbage will be collected in bins and disposed of daily, according to a brief and basic waste management plant prepared by the contractor and approved by prior to the commencement of civil works.There will be no site-specific landfills established by the contracts. All solid waste will be collected and removed from the works camps and disposed in local waste disposal sites

Contractor’s ESO

DPWH, MMT, CSC

Contractor complied with the EMP requirements

Page 8: Environmental Management Plan-Catanduanes

Sewerage in contactor’s yard/ construction camps

Contamination from sewerage

Primary treatment will be carried out if needed by larger camps

Prior to initiating work, the contractor will present a simple sewage management plant to the DPWH for approval.

Sewage to be discharged in soak pits or municipal severs when possible; construction camps to be located away from rivers.

Septic tank must be provided at each construction campsite and construction field.

Construction materials, including chemicals such as oils and painting, shall not be stocked near streams and drinking water will. Construction materials shall be covered with enough tarpaulin and looked after by special person, and shall be protected from entering into water body accompanied with rainwater.

Contractor’s ESO

DPWH, MMT, CSC

The contractor has properly installed / constructed sewerage system in their camp complying the EMP.

The formation of standing water on construction sites often leads to the spread on insect-borne diseases such as malaria. Therefore there must be a vigorous program by the contractor to avoid such standing waters; including removal of old materials such as used tires and storage drums.

Flora Minor vegetation loss Construction vehicles will operate with the corridor of impact, i.e., approximately 10m to either side of the carriageway centerline, to avoid damaging soil and vegetation. It will be most important to avoid soil compaction around trees. Generally the rule will be to avoid driving heavy equipment or trucks anywhere in the ‘drip-line’ of a tree.

No trees will be removed without prior approval of DPWH and a Permit to cut trees will be secured.

Contractor DPWH, MMT, CSC

The contractor limited their construction operation up to design construction limits following the EMP Requirements

Page 9: Environmental Management Plan-Catanduanes

The contractor will not use or permit the use of wood as fuel for execution of any part of the Works, including but not limited to the heating of bitumen and bitumen mixtures, and to the extent practicable shall ensure that fuels other than wood are used for cooking, and water heating in all his camps and living accommodations

Strict implementation of DPWH D.O 131, Series of 1995: Planting of trees along National Roads

Fauna Impact of Fauna No work camps will be located in the protected and conservation areas

Adequate knowledge to provide to workers regarding the protection of fauna

Stream crossings that are dry during the work period will be kept unobstructed at all times and the channel will not altered.

Contractor DPWH, MMT, CSC

The contractor had established their camps away from protected and conserved areas. No stream crossings and channel are found around the contractor’s camp.

Bridge rehabilitation will be scheduled in dry season to avoid adverse impact on fishery, birds and river water quality

No Activity

Socio-economic Environment

Local road Disturbance and damage to local road

All existing roads will be maintained in traffic worthy condition and uninterrupted movement of traffic will be maintained.

Traffic will be diverted for safe and smooth movement of the traffic

Access to all the roadside properties will be properly maintained

Temporary bypasses will be constructed and maintained (including dust control) during the construction period particularly at bridge crossings.

A grievance redress committee will formed in association with affected population before starting the civil works and advance notice must be given to the community about the construction

Contractor DPWH, MMT, CSC

The contractor followed the EMP Requirements

Page 10: Environmental Management Plan-Catanduanes

schedule. Repair the damaged local roads to their

original condition after project completion

Compensation for Landuse and trees

Social instability and loss of vegetation

The LARRIP policy of DPWH is the basis in determining the compensation and resettlement compensation: what will be the compensation mechanisms, how much the compensation will be paid according to the type of damages.

Contractor DPWH, MMT, CSC

The 2nd Engineering Office and ESSO authorized representative settled all compensation for the affected properties, trees, etc. within the RROW limits.

Community involvement

Stresses in the community Construction worksites may place stresses on resources and infrastructure of nearby communities. The contractor will provide temporary worksite facilities such as health care, eating space, and praying places.

Contractor DPWH, MMT, CSC

The contractor complied with the EMP on hiring of local folks more than 50% of their labor working force in the area.

Establish grievances redress committee. Labor intensive construction and the use

of local labor are recommended. At least 50% hiring of unskilled labor &

30% of skilled labor from the local residents are to be hired (RA6685 and DPWH department order 51 series of 1990)

Cemetery and Graveyard

Social grievances Graveyards and cemetery, cultural and religious relics affected in this Project, it is still highly recommended that contractor consult with local people during civil works close to these sites if it can be avoided.

Any material of historical importance found during the clearing operations, like treasure trove, slabs with epigraphical evidence or edicts, or sculptures, will be handed over to the government.

Contractor DPWH, MMT, CSC

The contractors complied with the EMP.

Traffic safety Road accidents Control speed of construction vehicles through road safety education and fines.

Contractor DPWH and Police

The contractor

Page 11: Environmental Management Plan-Catanduanes

Allow adequate traffic flow around construction areas.

Provide adequate signage, barriers and flag persons for traffic control

provided sufficient signages on the areas that construction activities are ongoing. Signages also are installed on narrow road areas to prevent accidents.

Traffic jams and congestion

Social havoc Communicate to the public through community consultation and newspaper announcements regarding the scope and schedule of construction, as well as certain construction activities causing disruption or access restrictions

Appropriate traffic diversion schemes or a Traffic Management Plan shall be implemented to avoid inconvenience due to protect operations to present road users,

Contractor DPWH The contractor provided sufficient flagmen on site together with adequate warning and directional signages.

particularly during night time Proper diversion schemes will be

implemented to ensure smooth traffic flow and minimize accidents, traffic holds ups and congestion

The diversion signs would be bold and clearly visible particularly at night

Any vehicles or equipment being used for the works must be parked off the carriageway

Contract procedures and specifications

Faulty construction Contractors conformity with contract procedures and specifications during construction will be carefully monitored.

Main contractors are responsible for ensuring that subcontractors conform to general construction guidelines (good engineering practice and standard good working practices). Otherwise, the quality of works subcontracted will be poor.

Contractors will be made to

Contractor DPWH,MMT, CSC

The contractor compromised to follow the EMP requirements

Page 12: Environmental Management Plan-Catanduanes

follow standard construction practices, monitored and supervised by construction supervision consultants.

Worker’s health, safety, and hygiene

Health impact Make certain that there is good drainage at all construction areas, to avoid creation of stagnant water bodies, including water in old tires especially in urban areas.

Provide adequate sanitation and waste disposal at construction sites.

Provide adequate health care for workers and locate worksites away from sensitive areas.

Contractor will not hire children and pregnant women

Provide education to construction personnel on preventing contracting the disease, protective measures and disease control

Contractor’s, ESO

DPWH,MMT, CSC

The contractor had installed drainage systems to drain their water waste. Unusable containers and old tires were properly disposed and / or stockpiled away on dry areas to avoid inhabitation of mosquitoes and other sickness carrier insects. Compos pit and recycling area are also secured to avoid scattering of solid wastes.

Provide construction personnel with necessary self-protection devices, such as safety helmet, earplug and other safety protection devices.

Set up enclosures at construction site and other dangerous place to prevent the public from trespassing.

Contractor’s, ESO

DPWH,MMT, CSC

Hardhats, mask, etc. are provided to all individuals involved in all construction activities.

Contamination and odor from sanitary waste

All work sites will be equipped with latrines. All toilet facilities will be at least 300m from water sources or existing residences.

Sanitary wastes will be disposed depending on the size of the work camps, (1) Small treatment facilities (for large works camps), (2) on-site storage and disposal to municipal disposal systems (when camps are located close to municipalities) or (3) septic tanks with ground seepage (smaller works camps not located adjacent to watercourses).

Contractor’s, ESO

DPWH,MMT, CSC

Bathrooms and Comfort rooms with proper septic tanks are provided on offices and plant sites.

Page 13: Environmental Management Plan-Catanduanes

Any untreated discharge to local watercourses will be prohibited.

Drinking water quality Drinking water will meet national potable water quality standards and it will be treated if it exceeds standards

The construction camps will have rationing facilities particularly for kerosene/LPG so that dependence on firewood for cooking is avoided to the extent possible

Contractor’s, ESO

DPWH,MMT, CSC

Safe drinking water are provided by the contractor.

entertainment The construction camps will have in-house community/common entertainment facilities. Dependence of local entertainment outlets by the construction camps will be discouraged/prohibited to the extent possible

Contractor’s, ESO

DPWH,MMT, CSC

Bunk houses for stay-in employee are provided. Common areas are also provided by the contractor

Location of camp site and storage depots

Loss of productive land Coordinate with LGU for identification of construction camps

Campsites and storage depots will be located preferably on unproductive/barren lands. Use of agricultural lands/cultivable lands will be discouraged. No camp sites and material storage sites in protected and conservation forests

Ensure abandonment of construction camp after the completion of the project. If required, donate work camp buildings as public facilities such as schools, barangay center, hospital etc.

Contractor DPWH,LGU, CSC

The construction supervision team strictly instructed to submit the methodology of procedures and carefully and carefully monitored on site execution.

HIV/AIDS and STD Spread to the community along the corridors.

All construction workers will be adequately trained in basic sanitation and health care issues (e.g., how to avoid transmission of sexually transmitted diseases such as HIV/AIDS).

Group consultation will be done to create awareness among the community about these diseases.

Contractor’s ESO

DPWH, CSC The contractor followed the EMP requirements.

Page 14: Environmental Management Plan-Catanduanes

Operational Phase

Dust and Air Pollution Air pollution

- Excessive discharges of dust impact on visibility on roads in the immediate vicinity of the Project.

- Visible soiling of clean surfaces, such as cars, window ledges, and household washing; dust deposits on flowers, fruit or vegetables

- Potential contamination of collected water supplies that are in the vicinity of the road and access areas of travelling equipment.

Maintain and clean roads properly. Keep unpaved roads and exposed

surfaces damp. Cover surfaces with coarse materials

where practicable. Compact all unconsolidated surfaces

where practical. Replace roadside tree plantations lost to

construction and encourage new afforestation and landscaping projects.

DPWH DPWH The contractor compromised to follow all the EMP requirements

Noise Noise pollution Preventing blowing horns near schools, hospitals and other sensitive areas,

Minimize engine revs when passing nearby houses

Equipment should not be left idling while parked or unattended.

Regularly inspect and maintain equipment

Provide earmuffs to construction workers exposed to noise.

DPWH DPWH No night activities to be done at populated areas to prevent the wanted noise disturbances. Complying to EMP requirements.

Road Safety Road accidents Enhancement of Traffic Accident Reporting System (TARAS), Enhancing road safety manuals and handbooks, and promoting road safety awareness

Properly maintain road signs and

DPWH PMO The contractor sufficiently provides proper signages along the road in

Page 15: Environmental Management Plan-Catanduanes

markings, information display board and streetlights.

Police or traffic enforcer must be assigned to regulate traffic in thickly populated areas.

compliance with the EMP requirements

Improve access Exploitation of natural resources in the area, quarrying and miningUnplanned urbanization

Increase business potentialIncreased delivery of agricultural and marine products

Tourism

Ensure that existing environmental management policies are effectively implemented and proper coordination involves different agencies

Responsible institutional order and existing regional development policies prevail.

Adherence to land use and zoning regulations

Encourage business in designated centers Improvement of the existing port in

Hinipaan and Pandan to accessibility and convenience to localized transport navigation, fisherman and farmers

Promote tourism in the area though advertisement from the loc and nationwide venue. Improve the tourist centers in the area, beaches etc.

Contractor LGU, DENR

DPWH,NHA,LGU

LGU,LHA, HLURB

DTI, LGU

DOT,LGU

The contractor has effectively coordinated to the offices concerned to comply with the EMP requirements

Note : Acronyms use in the EMP – CSC: Construction Supervision Consultant; DPWH: Department of Public Works and Highways; MMT: Multi-Partite Monitoring Team; DENR: Department of Environment and Natural Resources; DOT: Department of Tourism; DTI: Department of Trade and Industry; ESO: Environmental Safety Officer of Contractor; HLURB: Housing and Landuse Regulatory Board; LGU: Local Government Unit; NHA: National Housing Authority

Submitted by:

Page 16: Environmental Management Plan-Catanduanes

PEDRO ABECIA

Project Manager

Equi-parco Construction Company