Entergy Transmission System Overview

23
Entergy Transmission System Overview Iraq Ministry of Electricity April 19, 2010

Transcript of Entergy Transmission System Overview

Page 1: Entergy Transmission System Overview

Entergy Transmission System Overview

Iraq Ministry of ElectricityApril 19, 2010

Page 2: Entergy Transmission System Overview

NEW ENERGY DELIVERYORGINIZATION STRUCTURE

VP T&D Asset

ManagementMike Vaughan

Mgr System Outage

ResponseMike Fricke

DirTransmission

OperationsWilliam Alt

VPEnergy DeliveryRandy Helmick

DirT&D PlanningDoug Powell

DirTrans PM &

ConstructionGreg Grillo

AssistantExecutive

Grace Wilson

DirTransmissionCompliance

Gregory Pierce

VPTrans Reg

ComplianceMark McCulla

Design

DirTransmissionEngineering

George Bartlett

SOCTOCs

Planning ProjectManagement

CIPCompliance

OperationalPlanning

SCADAEMS

ConfigurationManagement

Arthur Barfield

Page 3: Entergy Transmission System Overview

North American Electric GridsEntergy lies within the Eastern Interconnection and is a member of the SERC Reliability Corporation.

Entergy complies with NERC Planning, Operating, and Cyber Standards.

Page 4: Entergy Transmission System Overview

• Over 15,000 miles of transmission lines

• 1,550 substations• ~ 1,000 employees• ~ 24,000MW of Entergy generation• ~ 21,000MW of Entergy load

Entergy’s Transmission System Statistics

JURISDICTION 69 115 138 161 230 345 500 TotalEAI 11 2114 0 1438 159 159 891 4772EGSI 1536 30 2229 0 728 37 544 5104ELI 30 1624 15 0 634 16 243 2562EMI 0 1872 0 6 506 0 358 2742ENOI 0 148 0 0 56 0 0 204TOTAL 1576 5788 2245 1443 2083 213 2035 15384

VOLTAGE LEVEL (kV)

source: 2000 FERC Form 1

Page 5: Entergy Transmission System Overview

Entergy’s 500kV Transmission System

Southern Company

AECI

TVAOKG&E

Page 6: Entergy Transmission System Overview

ENTERGY INTERFACESEntergy has 75 transmission interconnections with 14 adjacent systems

TVA

CLECO

SMEPA

LAFA

AMERENEDE

SPA

OG&E

CSW

AECI

CAJUN LEPA

Entergy

SOUTHERN

BATESVILLE

Simultaneous Import Capability: 3,500 MWSimultaneous Export Capability: 1,500 MWThermal capability of all tie-line interfaces: 25,000 MW

Page 7: Entergy Transmission System Overview

Entergy’s Operations Centers

Gretna

Monroe

Pine Bluff

Beaumont

Jackson

New Orleans

Little Rock

Entergy Headquarters

Transmission Operations Center

System Operations Center

Page 8: Entergy Transmission System Overview

Middle from Upstairs

Page 9: Entergy Transmission System Overview

Transmission Customers

0

10

20

30

40

50

60

70

80

90

Native Load Wholesale Network Service

80%

15% 5%

Revenue by Customer Class

Page 10: Entergy Transmission System Overview

Wholesale Transactions Across the Entergy System

30,000

50,000

90,000

107,000

146,000

10,000

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

1997 1998 1999 2000 2001 2002

Page 11: Entergy Transmission System Overview

Current Transmission Planning Process

GOAL: Ensure transmission system reliability through compliance with planning criteria

• Load and resource forecasts from native load and network service customers– Resources are generally the existing native Entergy generation.

• Update models• Determine transmission system constraints (load flow, short

circuit, and stability)• Develop solutions and preliminary cost estimates

Page 12: Entergy Transmission System Overview

Transmission Planning Process

• Perform cost vs. benefit analyses– Rank and score proposed solutions based upon

contingency probability, amount of load at risk, and estimated project cost ($ per megawatt-hour saved)

– Some projects are deemed mandatory (e.g., government-mandated, safety)

• Present proposed projects for approval to each of the jurisdictions– 3-year Expansion Plan– Approved budget for year 1– Plan does not include projects to accommodate bulk

power transfer

Page 13: Entergy Transmission System Overview
Page 14: Entergy Transmission System Overview

Entergy’sResponse

to Major

Hurricanes

Page 15: Entergy Transmission System Overview

Katrina had unprecedented impact on Entergy1.1 million customers out; severe flooding

800,000 ETR Louisiana

outages

Katrina Storm surge approaches Michoud plant, photo by Entergy Michoud plant manager Donald G McCrosky

300,000ETR Mississippi

outages

Page 16: Entergy Transmission System Overview

Flooding - affected a significant portion of our New Orleans customers

Entergy New Orleansprojects approximately half of their customers may be unable to take service without significant reconstruction

St. Bernard

Lower 9th

Ward

New Orleans East

Lakeview

Mid-City

CBD

Customers Affected by Floodwaters

Levee Breaches

Page 17: Entergy Transmission System Overview

Resources- a monumental support effort

Hurricane Katrina Nationwide ResponseHurricane Katrina Nationwide Response

Rita … 13,000 tool workers 130 companies from 33 states 4500 support personnel

Katrina … 10,200 tool workers 100 companies from 29 states 3500 support personnel

Hurricane Rita Nationwide ResponseHurricane Rita Nationwide Response

Page 18: Entergy Transmission System Overview

BryanHuntsville

Harrison

LakeCharles

Port Arthur

Orange

Beaumont

Conroe

McComb

Houma

New Orleans

Baton Rouge

Lafayette

Little Rock

MonroeVicksburg Jackson

Brookhaven

GrenadaGreenville

El Dorado

Pine Bluff

Ruston

Jonesboro

Russellville

Hot Springs

Hurricane KatrinaLogistics

Cities with Major Staging Sites =

• Entergy Mississippi had 11 Major Staging Sites

• Entergy Louisiana had 13 Major Staging Sites with 6 “Tent Cities,” providing 4,500 cots

• Entergy New Orleans had 2 Major Staging Sites

• Over 715,000 meals served

• Acquired over 224,000 bed nights

• Over 185 logistics workers involved

Jennings

Woodville Amite

WestbankSulphur

Winnie

Natchez

AttalaWinona

Canton

Magee

Liberty

HammondGonzales

Page 19: Entergy Transmission System Overview

BryanHuntville

Harrison

LakeCharles

Port Aurthur

Orange

Beaumont

Conro

McComb

Houma

New Orleans

Baton Rouge

Lafayette

Little Rock

MonroeVicksburg Jackson

Brookhaven

GrenadaGreenville

El Dorado

Pine Bluff

Ruston

Jonesboro

Russellville

Hot Springs

Jennings

WodvilleAmite

WestbankSulphur

Winnie

Natchez

AttalaWinona

Canton

Magee

Liberty

Hurricane RitaCities with Major Staging Sites =

• Entergy Louisiana had 8 Major Staging Sites, which included 2 “Tent Cities,” providing 1,000 cots

• Entergy Texas had 12 Major Staging Sites, which included 4 “Tent Cities” providing 3,750 cots

• Over 551,000 meals served

• Acquired over 255,000 bed nights

• Over 145 logistics workers involved

Hammond

Gonzales

Page 20: Entergy Transmission System Overview

Tent City Images

Page 21: Entergy Transmission System Overview

Innovative Restoration Techniques

Page 22: Entergy Transmission System Overview
Page 23: Entergy Transmission System Overview

Restoration• “SAFETY TRUMPS SPEED”

• 1.87 million total electric customers

• 145,000 gas customers

• 28,900 Distribution poles replaced

• 522 Transmission lines out of service

• 715 Substations out of service

• 29 fossil/1 nuclear units shut down