Engineering Drawings required for Solar Projects

3
Engineering Submittal Essential for a SPV Power Plant Design & Engineering is an integral part of the implementation of the SPV power plants. Engineering drawings & documents convey specifications, construction methodology, dimensions, tolerances etc capturing the scope of works and presenting a first-hand idea on the final by product that would be constructed. Typical Master Deliverable list can be divided in two broad categories of Civil & Electrical which would each entail the following: S.No. Category Particulars 1 Start offs Land Contour & Topographical Analysis 2 Geo-tech analysis 3 Water test report 4 Module Mounting Structures 5 Evacuation Single line diagram 6 Major Equipment Selection - Transformer, HT panels and String Monitoring Boxes 7 Module Mix (wattage & make) 8 Leadoff Plant Layout 9 Switchyard / Sub Station layout 10 Civil - Fence Boundary Fence 11 Transformer Yard Fence 12 Switchyard Fence 13 Civil – Road Periphery 14 Internal 15 Civil - Land Development & Cleaning Land Development, Grading & Filling 16 Civil- Buildings General Arrangement of Inverter room 17 General Arrangement of control room 18 Structural of Inverter Room 19 Structural of Control Room 20 Watch Tower 21 Security Cabin

Transcript of Engineering Drawings required for Solar Projects

Page 1: Engineering Drawings required for Solar Projects

Engineering Submittal Essential for a SPV Power Plant

Design & Engineering is an integral part of the implementation of the SPV power plants.

Engineering drawings & documents convey specifications, construction methodology, dimensions,

tolerances etc capturing the scope of works and presenting a first-hand idea on the final by product

that would be constructed.

Typical Master Deliverable list can be divided in two broad categories of Civil & Electrical which would

each entail the following:

S.No. Category Particulars

1 Start offs Land Contour & Topographical Analysis

2 Geo-tech analysis

3 Water test report

4 Module Mounting Structures

5 Evacuation Single line diagram

6

Major Equipment Selection - Transformer, HT panels and String Monitoring Boxes

7 Module Mix (wattage & make)

8 Leadoff Plant Layout

9 Switchyard / Sub Station layout

10 Civil - Fence Boundary Fence

11 Transformer Yard Fence

12 Switchyard Fence

13 Civil – Road Periphery

14 Internal

15

Civil - Land Development & Cleaning

Land Development, Grading & Filling

16 Civil- Buildings

General Arrangement of Inverter room

17

General Arrangement of control room

18 Structural of Inverter Room

19 Structural of Control Room

20 Watch Tower

21 Security Cabin

Page 2: Engineering Drawings required for Solar Projects

S.No. Category Particulars

22 Gates Main + Wicket Gate

23

Plumbing & Module cleaning System

Water reservoirs

24 Pipeline layout and P&ID

25 Reverse Osmosis P&ID

26 Drainage Drains cross-section and Layouts

27

Foundation details , location & coordinate markings

Lightning Arrestors

28 Weather Monitoring Station

29 Inverter Transformer

30 Auxiliary Transformer

31 Street Light

32 CCTV

33 Switchyard equipment

34 Electrical – SLD DC SLD

35 SCADA SLD & Architecture

36 Auxiliary SLD

37 Electrical – Routings

DC Cable trench

38 AC cable Trench

39 Solar cable routing

40 Auxiliary cable routing

41 Inverter Room trenching

42 Control Room trenching

43 Earthing PV array

44 Inverter Room earthing

45 Control Room earthing

46 Switchyard

47

Panels & Distribution Boards

AC power distribution board

48 Illuminations Street lights

49 Inverter Room Illuminations

50 Control Room Illuminations

51 Plant Protection Layout of CCTV and cabling

52 Lightning Arrestors

53 Weather Monitoring Station

54 SCADA architecture

Page 3: Engineering Drawings required for Solar Projects

S.No. Category Particulars

55 Fire Fighting & Protection System

56 PV array String Combiner Box Layout

57 String Distribution & Numbering

58 Cable Schedules SPV module to SCB

59 SCB to inverters

60 LT AC Cable schedule

61 HT AC cable Schedule

62 Communication cable schedule

63 Auxiliary cable schedule

The drawing should be able to serve site related changes, capture details of vast and remote access,

and be clear in nature to aid faster construction.

Apart from the above drawings the developer should also seek out for relevant technical

specifications, quality assurance plans, design basis reports, generation yield assessments,

implementation schedules & bill of material with quantities.