Engineering Design Center Project Schedule

18
ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecesso 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 3 Project Reinitiated 0 days Thu 1/1/15 Thu 1/1/15 Fri 8/3/18 Fri 8/3/18 2 days 937 days 4 Review technical, sustainability and program changes with team 5 days Mon 1/5/15 Fri 1/9/15 Fri 8/3/18 Thu 8/9/18 0 days 935 days 3 5 Project reinitiation meeting with client and stakeholders on any scope changes 1 day Mon 1/12/15 Mon 1/12/15 Fri 8/10/18 Fri 8/10/18 0 days 935 days 4 6 Edit design permit and tender drawings according to feedback 10 days Mon 1/12/15 Fri 1/23/15 Fri 8/10/18 Thu 8/23/18 0 days 935 days 5SS 7 Review safety by construction with electrical, mechanical, structural engineers 5 days Mon 1/26/15 Fri 1/30/15 Fri 8/31/18 Thu 9/6/18 0 days 940 days 6 8 Meeting with engineers and operation & mangament staff on safety by construction designs 1 day Mon 2/2/15 Mon 2/2/15 Fri 9/7/18 Fri 9/7/18 0 days 940 days 7 9 Edit design according to safety by construction review meeting 10 days Mon 2/2/15 Fri 2/13/15 Fri 9/7/18 Thu 9/20/18 0 days 940 days 8SS 10 Value engineering of design permit and tender drawings 5 days Mon 2/16/15 Fri 2/20/15 Fri 9/21/18 Thu 9/27/18 940 days 940 days 9 11 Meeting with value engineering group and review permit and tender drawings 1 day Mon 3/23/15 Mon 3/23/15 Fri 8/3/18 Fri 8/3/18 0 days 880 days 12 Edit design permit and tender drawings according to value engineering 10 days Mon 3/23/15 Fri 4/3/15 Fri 8/3/18 Thu 8/16/18 0 days 880 days 11SS 13 Review meeting with client and stakeholders on design changes 1 day Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 12 14 Design Complete 0 days Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 13SS 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 12/7 cember 1 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 1/1 4/6 12/21 1/4 1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 January 2015 March 2015 May 2015 July 2015 September 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecesso 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days 17 Develop recommendation report to UBC Board of Governors 15 days Mon 1/26/15 Fri 2/13/15 Fri 8/24/18 Thu 9/13/18 9 days 935 days 6 18 Submit recommendation to UBC Board of Governors 0 days Fri 2/27/15 Fri 2/27/15 Fri 9/14/18 Fri 9/14/18 1 day 926 days 17 19 UBC Board of Governors review project recommendations 10 days Mon 3/2/15 Fri 3/13/15 Fri 9/14/18 Thu 9/27/18 0 days 925 days 18 20 Approval from UBC Board of Governors 0 days Mon 3/16/15 Mon 3/16/15 Thu 9/27/18 Thu 9/27/18 925 days 925 days 19 21 Submit construction permits from UBC 0 days Mon 4/6/15 Mon 4/6/15 Fri 9/14/18 Fri 9/14/18 0 days 900 days 14 22 UBC review construction permit 10 days Mon 4/6/15 Fri 4/17/15 Fri 9/14/18 Thu 9/27/18 0 days 900 days 21 23 Approval of construction permit from UBC 0 days Fri 4/17/15 Fri 4/17/15 Thu 9/27/18 Thu 9/27/18 900 days 900 days 22 24 Develop traffic control plans for the delivery of equipment and supplies for project 15 days Mon 7/13/15 Fri 7/31/15 Thu 5/10/18 Wed 5/30/18 0 days 739 days 47 25 Submit traffic control plans to UBC 0 days Fri 7/31/15 Fri 7/31/15 Thu 5/31/18 Thu 5/31/18 0 days 739 days 24 26 UBC review traffic control plans 10 days Mon 8/3/15 Fri 8/14/15 Thu 5/31/18 Wed 6/13/18 0 days 739 days 25 27 Approval from UBC on traffic control plans 0 days Fri 8/14/15 Fri 8/14/15 Thu 6/14/18 Thu 6/14/18 0 days 739 days 26 28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days 35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days 43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days 56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 12/28 ecember 2 Januar Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 2/27 3/16 4/6 4/17 7/31 8/14 1/18 2/8 3/1 3/22 4/12 5/3 5/24 6/14 7/5 7/26 8/16 9/6 9/27 10/18 11/8 11/29 12/20 1/10 1/31 2/21 3/13 4/3 4/24 21 February 11 April 1 May 21 July 11 September 1 October 21 December 11 February 1 March 21 M ry 2015 May 2015 September 2015 January 2016 May 2 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15

Transcript of Engineering Design Center Project Schedule

Page 1: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

3 Project Reinitiated 0 days Thu 1/1/15 Thu 1/1/15 Fri 8/3/18 Fri 8/3/18 2 days 937 days

4 Review technical, sustainability and program changes with team

5 days Mon 1/5/15 Fri 1/9/15 Fri 8/3/18 Thu 8/9/18 0 days 935 days 3

5 Project reinitiation meeting with client and stakeholders on any scope changes

1 day Mon 1/12/15 Mon 1/12/15 Fri 8/10/18 Fri 8/10/18 0 days 935 days 4

6 Edit design permit and tender drawings according to feedback

10 days Mon 1/12/15 Fri 1/23/15 Fri 8/10/18 Thu 8/23/18 0 days 935 days 5SS

7 Review safety by construction with electrical, mechanical, structural engineers

5 days Mon 1/26/15 Fri 1/30/15 Fri 8/31/18 Thu 9/6/18 0 days 940 days 6

8 Meeting with engineers and operation & mangament staff on safety by construction designs

1 day Mon 2/2/15 Mon 2/2/15 Fri 9/7/18 Fri 9/7/18 0 days 940 days 7

9 Edit design according to safety by construction review meeting

10 days Mon 2/2/15 Fri 2/13/15 Fri 9/7/18 Thu 9/20/18 0 days 940 days 8SS

10 Value engineering of design permit and tender drawings 5 days Mon 2/16/15 Fri 2/20/15 Fri 9/21/18 Thu 9/27/18 940 days 940 days 9

11 Meeting with value engineering group and review permit and tender drawings

1 day Mon 3/23/15 Mon 3/23/15 Fri 8/3/18 Fri 8/3/18 0 days 880 days

12 Edit design permit and tender drawings according to value engineering

10 days Mon 3/23/15 Fri 4/3/15 Fri 8/3/18 Thu 8/16/18 0 days 880 days 11SS

13 Review meeting with client and stakeholders on design changes

1 day Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 12

14 Design Complete 0 days Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 13SS

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

1/1

12/7 12/21December 1

November 2014

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

1/1

4/6

12/21 1/4 1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1

November 2014 January 2015 March 2015 May 2015 July 2015 September 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days

17 Develop recommendation report to UBC Board of Governors

15 days Mon 1/26/15 Fri 2/13/15 Fri 8/24/18 Thu 9/13/18 9 days 935 days 6

18 Submit recommendation to UBC Board of Governors 0 days Fri 2/27/15 Fri 2/27/15 Fri 9/14/18 Fri 9/14/18 1 day 926 days 17

19 UBC Board of Governors review project recommendations

10 days Mon 3/2/15 Fri 3/13/15 Fri 9/14/18 Thu 9/27/18 0 days 925 days 18

20 Approval from UBC Board of Governors 0 days Mon 3/16/15 Mon 3/16/15 Thu 9/27/18 Thu 9/27/18 925 days 925 days 19

21 Submit construction permits from UBC 0 days Mon 4/6/15 Mon 4/6/15 Fri 9/14/18 Fri 9/14/18 0 days 900 days 14

22 UBC review construction permit 10 days Mon 4/6/15 Fri 4/17/15 Fri 9/14/18 Thu 9/27/18 0 days 900 days 21

23 Approval of construction permit from UBC 0 days Fri 4/17/15 Fri 4/17/15 Thu 9/27/18 Thu 9/27/18 900 days 900 days 22

24 Develop traffic control plans for the delivery of equipment and supplies for project

15 days Mon 7/13/15 Fri 7/31/15 Thu 5/10/18 Wed 5/30/18 0 days 739 days 47

25 Submit traffic control plans to UBC 0 days Fri 7/31/15 Fri 7/31/15 Thu 5/31/18 Thu 5/31/18 0 days 739 days 24

26 UBC review traffic control plans 10 days Mon 8/3/15 Fri 8/14/15 Thu 5/31/18 Wed 6/13/18 0 days 739 days 25

27 Approval from UBC on traffic control plans 0 days Fri 8/14/15 Fri 8/14/15 Thu 6/14/18 Thu 6/14/18 0 days 739 days 26

28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days

35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days

43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days

56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

12/28 1/18December 21

September 2014 January 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

2/27

3/164/6

4/17

7/31

8/14

1/18 2/8 3/1 3/22 4/12 5/3 5/24 6/14 7/5 7/26 8/16 9/6 9/27 10/18 11/8 11/29 12/20 1/10 1/31 2/21 3/13 4/3 4/24 5/15December 21 February 11 April 1 May 21 July 11 September 1 October 21 December 11 February 1 March 21 May 11

January 2015 May 2015 September 2015 January 2016 May 2016

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 2: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days

28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days

29 Submit construction permits from the City 0 days Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 14

30 City reviews construction permits 30 days Mon 4/6/15 Fri 5/15/15 Fri 8/17/18 Thu 9/27/18 0 days 880 days 29SS

31 Approval from City on Construction permits 0 days Fri 5/15/15 Fri 5/15/15 Thu 9/27/18 Thu 9/27/18 880 days 880 days 30

32 Submit file grading permit to City 0 days Fri 7/10/15 Fri 7/10/15 Fri 9/7/18 Fri 9/7/18 0 days 825 days 47

33 City reviews file grading permits 15 days Mon 7/13/15 Fri 7/31/15 Fri 9/7/18 Thu 9/27/18 0 days 825 days 32SS

34 Approval from City on file grading permits 0 days Fri 7/31/15 Fri 7/31/15 Thu 9/27/18 Thu 9/27/18 825 days 825 days 33

35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days

36 Issue Bid Proposal for Concrete Services 0 days Thu 4/9/15 Thu 4/9/15 Wed 2/7/18 Wed 2/7/18 0 days 740 days

37 Acquire proposals for concrete services 10 days Thu 4/9/15 Wed 4/22/15 Wed 2/7/18 Tue 2/20/18 0 days 740 days 36

38 Evaluation of proposals for concrete services 5 days Thu 4/23/15 Wed 4/29/15 Wed 2/21/18 Tue 2/27/18 1 day 740 days 37

39 Award concrete services to qualified contractors 0 days Fri 5/1/15 Fri 5/1/15 Wed 2/28/18 Wed 2/28/18 0 days 739 days 38

40 Schedule for Concrete supplies and services 15 days Mon 5/4/15 Fri 5/22/15 Wed 10/10/18 Tue 10/30/18 898 days 898 days

41 Order and schedule for steel rebar 15 days Mon 5/4/15 Fri 5/22/15 Fri 9/7/18 Thu 9/27/18 0 days 875 days 39

42 Order and schedule for concrete 15 days Mon 5/4/15 Fri 5/22/15 Fri 9/7/18 Thu 9/27/18 875 days 875 days 41SS

43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days

56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

3/1March 1March 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

4/6

5/157/10

7/31

4/9

5/1

3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1March 2015 May 2015 July 2015 September 2015 November 2015 January 2016

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 3: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days

28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days

35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days

43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days

44 Acquire quotations from qualified suppliers (equipment, machinery, elevator, piping, cables, fixtures, duct, landscaping material)

15 days Fri 5/1/15 Thu 5/21/15 Wed 2/28/18 Tue 3/20/18 0 days 739 days 39

45 Evaluate subcontractor quotations 30 days Mon 5/4/15 Fri 6/12/15 Thu 3/1/18 Wed 4/11/18 0 days 739 days 44SS+1 day

46 Award contract for subcontractors to work on utility and trades work

5 days Mon 6/15/15 Fri 6/19/15 Thu 4/12/18 Wed 4/18/18 0 days 739 days 45

47 Schedule for subcontractor supplies and services 15 days Mon 6/22/15 Fri 7/10/15 Tue 5/22/18 Mon 6/11/18 0 days 762 days

48 Order and schedule for excavation machinery and workers

15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46

49 Order and schedule for elevator and necessary parts and workers

15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46

50 Order and schedule for HVAC parts and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46

51 Order and schedule for plumbing parts and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46

52 Order and schedule for electrical and SCADA cables and parts and workers

15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46

53 Order and schedule for drywall and paint and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46

54 Order and schedule for carpets, windows, frames, doors and workers

15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46

55 Order and schedule for landscapers and plants 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46

3/29March 1 April 1March 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

3/29March 1 April 1March 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25April 1 May 1 June 1 July 1 August 1 September 1 October 1

March 2015 May 2015 July 2015 September 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25April 1 May 1 June 1 July 1 August 1 September 1 October 1

March 2015 May 2015 July 2015 September 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 4: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days

28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days

35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days

43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days

56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days

57 Qualify contractors for Project 70 days Mon 6/22/15 Fri 9/25/15 Mon 6/4/18 Mon 8/27/18 762 days 762 days

58 Develop Request for Qualifications (RFQ) Specifications and Documents

31 days Mon 6/22/15 Mon 8/3/15 Mon 6/4/18 Tue 7/17/18 9 days 771 days

59 Meet with legal team to discuss details on RFQ 1 day Mon 6/22/15 Mon 6/22/15 Wed 5/2/18 Wed 5/2/18 0 days 748 days 47SS

60 Edit RFQ specifications according to legal team details 15 days Tue 6/23/15 Mon 7/13/15 Thu 5/3/18 Wed 5/23/18 0 days 748 days 59

61 Legal team reviews and makes changes to RFQ documents 15 days Tue 7/14/15 Mon 8/3/15 Thu 5/24/18 Wed 6/13/18 0 days 748 days 60

62 RFQ specifications and documents complete 0 days Mon 8/3/15 Mon 8/3/15 Thu 6/14/18 Thu 6/14/18 748 days 748 days 61

63 RFQ Opens 0 days Fri 8/14/15 Fri 8/14/15 Thu 6/14/18 Thu 6/14/18 0 days 739 days 27,58

64 Acquire RFQ 15 days Mon 8/17/15 Fri 9/4/15 Thu 6/14/18 Wed 7/4/18 0 days 739 days 63

65 RFQ Closes 0 days Fri 9/4/15 Fri 9/4/15 Thu 7/5/18 Thu 7/5/18 0 days 739 days 64

66 Evaluation of RFQs 10 days Mon 9/7/15 Fri 9/18/15 Thu 7/5/18 Wed 7/18/18 0 days 739 days 65

67 Create short list of contractors from evaluated RFQs 5 days Mon 9/21/15 Fri 9/25/15 Thu 7/19/18 Wed 7/25/18 0 days 739 days 66

68 Tender/Bid Project 155 days Mon 9/28/15 Mon 5/2/16 Tue 8/28/18 Tue 10/30/18 653 days 653 days

79 Meet with contractors to discuss construction and subcontractor details

1 day Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days 78

6/7June 1

May 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

80 Review and edit costs, supply list, schedules and subcontractors and their qualifications

30 days Tue 5/3/16 Mon 6/13/16 Fri 8/17/18 Thu 9/27/18 599 days 599 days 79

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

6/7June 1

May 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

8/38/14

9/4

6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3 1/17 1/31 2/14June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1

May 2015 July 2015 September 2015 November 2015 January 2016

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3 1/17 1/31 2/14June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1

May 2015 July 2015 September 2015 November 2015 January 2016

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 5: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days

28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days

35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days

43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days

56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days

57 Qualify contractors for Project 70 days Mon 6/22/15 Fri 9/25/15 Mon 6/4/18 Mon 8/27/18 762 days 762 days

68 Tender/Bid Project 155 days Mon 9/28/15 Mon 5/2/16 Tue 8/28/18 Tue 10/30/18 653 days 653 days

69 Develop Tender Specifications and Documents 31 days Mon 9/28/15 Mon 11/9/15 Tue 8/28/18 Wed 10/10/18 79 days 762 days

70 Meet with legal team to discuss details on Tender Specifications

1 day Mon 9/28/15 Mon 9/28/15 Thu 7/26/18 Thu 7/26/18 0 days 739 days 67

71 Edit tender specifications according to legal team details 15 days Tue 9/29/15 Mon 10/19/15 Fri 7/27/18 Thu 8/16/18 0 days 739 days 70

72 Legal team reviews and makes changes to tender specifications documents

15 days Tue 10/20/15 Mon 11/9/15 Fri 8/17/18 Thu 9/6/18 0 days 739 days 71

73 Tender specifications and documents complete 0 days Mon 11/9/15 Mon 11/9/15 Fri 9/7/18 Fri 9/7/18 739 days 739 days 72

74 Bid Opens on BCBids 0 days Mon 2/29/16 Mon 2/29/16 Fri 9/7/18 Fri 9/7/18 0 days 660 days 27,69,66,76SS-15 days

75 Acquire Request for Proposal (RFP) for project construction 15 days Mon 2/29/16 Fri 3/18/16 Fri 9/7/18 Thu 9/27/18 660 days 660 days 74

76 Bid Closes 0 days Mon 3/21/16 Mon 3/21/16 Fri 8/17/18 Fri 8/17/18 0 days 630 days 78SS-30 days

77 Evaluation of Proposals for project construction 30 days Mon 3/21/16 Fri 4/29/16 Fri 8/17/18 Thu 9/27/18 630 days 630 days 76SS

78 Award project to qualified contractors 0 days Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days

79 Meet with contractors to discuss construction and subcontractor details

1 day Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days 78

8/30July 1 September 1

May 2015 September 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

80 Review and edit costs, supply list, schedules and subcontractors and their qualifications

30 days Tue 5/3/16 Mon 6/13/16 Fri 8/17/18 Thu 9/27/18 599 days 599 days 79

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

8/30July 1 September 1

May 2015 September 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

11/92/29

3/21

5/2

9/27 10/25 11/22 12/20 1/17 2/14 3/13 4/10 5/8 6/5 7/3 7/31 8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1 May 1September 2015 January 2016 May 2016 September 2016 January 2017 May 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

9/27 10/25 11/22 12/20 1/17 2/14 3/13 4/10 5/8 6/5 7/3 7/31 8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1 May 1September 2015 January 2016 May 2016 September 2016 January 2017 May 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 6: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days

88 Level Ground 10 days Wed 7/13/16 Tue 7/26/16 Fri 4/22/16 Thu 5/5/16 0 days -59 days 84

89 Bulk Excavate 30 days Wed 7/20/16 Tue 8/30/16 Fri 4/29/16 Thu 6/9/16 0 days -59 days 88FS-5 days

90 Excavate for Elevator 5 days Wed 7/27/16 Tue 8/2/16 Fri 6/3/16 Thu 6/9/16 0 days -39 days 89SS+5 days

91 Install Shoring 47 days Wed 8/31/16 Thu 11/3/16 Fri 6/10/16 Fri 8/12/16 0 days -59 days 89,90

92 Excavate Footings 25 days Fri 11/4/16 Thu 12/8/16 Mon 8/15/16 Fri 9/16/16 0 days -59 days 91

93 Loading of ground work 10 days Fri 12/9/16 Thu 12/22/16 Mon 9/19/16 Fri 9/30/16 0 days -59 days 92

94 Remove loadings 2 days Thu 12/22/16 Fri 12/23/16 Tue 2/7/17 Wed 2/8/17 0 days 33 days 93FS-1 day

95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days

111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days

124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days

137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days

150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days

156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF

7/4

6/5May 11

May 2016

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

6/5May 11

May 2016

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

7/4

3/2

6/26 7/17 8/7 8/28 9/18 10/9 10/30 11/20 12/11 1/1 1/22 2/12 3/5 3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20May 11 July 1 August 21 October 11 December 1 January 21 March 11 May 1 June 21 August 11

May 2016 September 2016 January 2017 May 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

7/3

6/26 7/17 8/7 8/28 9/18 10/9 10/30 11/20 12/11 1/1 1/22 2/12 3/5 3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20May 11 July 1 August 21 October 11 December 1 January 21 March 11 May 1 June 21 August 11

May 2016 September 2016 January 2017 May 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 7: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days

95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days

96 Foundations (Ground Floor) 127 days Mon 10/3/16 Tue 3/28/17 Mon 10/3/16 Fri 5/12/17 0 days 0 days 93

97 Steel rebars get delivered on site (stored offsite) 10 days Mon 10/3/16 Fri 10/14/16 Wed 7/25/18 Wed 8/8/18 472 days 472 days 92SS

98 Form Footings 35 days Fri 12/23/16 Thu 2/9/17 Wed 2/8/17 Tue 3/28/17 0 days 33 days 94FS-1 day

99 Install Reinforcing Steel Footings 15 days Fri 1/20/17 Thu 2/9/17 Wed 3/8/17 Tue 3/28/17 0 days 33 days 98FF

100 Footing inspections 2 days Fri 2/10/17 Mon 2/13/17 Wed 3/29/17 Thu 3/30/17 0 days 33 days 99

101 Place Concrete Footings 2 days Tue 2/14/17 Wed 2/15/17 Fri 3/31/17 Mon 4/3/17 0 days 33 days 100

102 Strip Forms for Footings 10 days Wed 2/15/17 Tue 2/28/17 Mon 4/3/17 Fri 4/14/17 0 days 33 days 101FS-1 day

103 Backfill footings 10 days Wed 3/1/17 Tue 3/14/17 Mon 4/17/17 Fri 4/28/17 0 days 33 days 102

104 Pour concrete for ground floor 10 days Wed 3/15/17 Tue 3/28/17 Mon 5/1/17 Fri 5/12/17 0 days 33 days 103

105 Interior Supports (Ground Floor) 31 days Wed 3/29/17 Wed 5/10/17 Mon 5/15/17 Mon 6/26/17 33 days 33 days

106 Form Supports 16 days Wed 3/29/17 Wed 4/19/17 Mon 5/15/17 Mon 6/5/17 0 days 33 days 104

107 Install Reinforcing Steel Supports 15 days Thu 3/30/17 Wed 4/19/17 Tue 5/16/17 Mon 6/5/17 0 days 33 days 98,106FF

7/4

7/31July 1

May 2016

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

108 Support inspection 2 days Fri 4/21/17 Mon 4/24/17 Wed 6/7/17 Thu 6/8/17 0 days 33 days 107FS+1 day,106FS+1 day

109 Place Concrete Supports 2 days Tue 4/25/17 Wed 4/26/17 Fri 6/9/17 Mon 6/12/17 0 days 33 days 108

110 Strip forms for interior supports 10 days Thu 4/27/17 Wed 5/10/17 Tue 6/13/17 Mon 6/26/17 0 days 33 days 109

111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days

124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days

137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days

150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days

156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

7/31July 1

May 2016

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

7/4

8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4 7/2 7/30 8/27 9/24 10/22 11/19 12/17 1/14 2/11 3/11 4/8July 1 September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1

May 2016 September 2016 January 2017 May 2017 September 2017 January 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

3/2

7/3

8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4 7/2 7/30 8/27 9/24 10/22 11/19 12/17 1/14 2/11 3/11 4/8July 1 September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1

May 2016 September 2016 January 2017 May 2017 September 2017 January 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 8: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days

95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days

111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days

112 Foundation (Mezzanine) 24 days Wed 5/10/17 Mon 6/12/17 Mon 6/26/17 Thu 7/27/17 33 days 33 days

113 Form Mezzanine Floor 15 days Wed 5/10/17 Tue 5/30/17 Mon 6/26/17 Fri 7/14/17 0 days 33 days 110FS-1 day

114 Install Reinforcing Steel for Mezzanine Floor 7 days Mon 5/22/17 Tue 5/30/17 Thu 7/6/17 Fri 7/14/17 0 days 33 days 110FS-5 days,113FF

115 Mezzanine Floor inspections 1 day Thu 6/1/17 Thu 6/1/17 Tue 7/18/17 Tue 7/18/17 0 days 33 days 114FS+1 day

116 Place Concrete for Mezzanine Floor 2 days Fri 6/2/17 Mon 6/5/17 Wed 7/19/17 Thu 7/20/17 0 days 33 days 115

117 Strip Forms for Mezzanine Floor 5 days Tue 6/6/17 Mon 6/12/17 Fri 7/21/17 Thu 7/27/17 0 days 33 days 116

118 Interior Supports (Mezzanine) 16 days Tue 6/13/17 Tue 7/4/17 Fri 7/28/17 Fri 8/18/17 33 days 33 days

119 Form Supports 7 days Tue 6/13/17 Wed 6/21/17 Fri 7/28/17 Mon 8/7/17 0 days 33 days 117

120 Install Reinforcing Steel Supports 7 days Tue 6/13/17 Wed 6/21/17 Fri 7/28/17 Mon 8/7/17 0 days 33 days 113,119FF

121 Support inspection 1 day Fri 6/23/17 Fri 6/23/17 Wed 8/9/17 Wed 8/9/17 0 days 33 days 120FS+1 day

122 Place Concrete Supports 2 days Mon 6/26/17 Tue 6/27/17 Thu 8/10/17 Fri 8/11/17 0 days 33 days 121

4/23AprilQtr 2, 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

123 Strip forms for interior supports 5 days Wed 6/28/17 Tue 7/4/17 Mon 8/14/17 Fri 8/18/17 0 days 33 days 122

124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days

137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days

150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days

156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

4/23AprilQtr 2, 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

4/30 5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24April May June July August SeptemberQtr 2, 2017 Qtr 3, 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

4/30 5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24April May June July August SeptemberQtr 2, 2017 Qtr 3, 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 9: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days

95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days

111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days

124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days

125 Foundation (Second Floor) 35 days Wed 7/5/17 Tue 8/22/17 Mon 8/21/17 Fri 10/6/17 33 days 33 days

126 Form Second Floor 21 days Wed 7/5/17 Wed 8/2/17 Mon 8/21/17 Mon 9/18/17 0 days 33 days 123

127 Install Reinforcing Steel for Second Floor 15 days Thu 7/13/17 Wed 8/2/17 Tue 8/29/17 Mon 9/18/17 0 days 33 days 123FF-5 days,126FF

128 Second Floor inspections 2 days Thu 8/3/17 Fri 8/4/17 Tue 9/19/17 Wed 9/20/17 0 days 33 days 127,126

129 Place Concrete for Second Floor 2 days Mon 8/7/17 Tue 8/8/17 Thu 9/21/17 Fri 9/22/17 0 days 33 days 128

130 Strip Forms for Second Floor 10 days Wed 8/9/17 Tue 8/22/17 Mon 9/25/17 Fri 10/6/17 0 days 33 days 129

131 Interior Supports (Second) 30 days Wed 8/23/17 Tue 10/3/17 Mon 10/9/17 Fri 11/17/17 33 days 33 days

132 Form Supports 15 days Wed 8/23/17 Tue 9/12/17 Mon 10/9/17 Fri 10/27/17 0 days 33 days 130

133 Install Reinforcing Steel Supports 15 days Wed 8/23/17 Tue 9/12/17 Mon 10/9/17 Fri 10/27/17 0 days 33 days 132FF,126

134 Support inspection 2 days Thu 9/14/17 Fri 9/15/17 Tue 10/31/17 Wed 11/1/17 0 days 33 days 133FS+1 day,132FS+1 day

6/4June 1

May 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

135 Place Concrete Supports 2 days Mon 9/18/17 Tue 9/19/17 Thu 11/2/17 Fri 11/3/17 0 days 33 days 134

136 Strip forms for interior supports 10 days Wed 9/20/17 Tue 10/3/17 Mon 11/6/17 Fri 11/17/17 0 days 33 days 135

137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days

150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days

156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

6/4June 1

May 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

6/18 7/2 7/16 7/30 8/13 8/27 9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1

May 2017 July 2017 September 2017 November 2017 January 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

3/2

7/3

6/18 7/2 7/16 7/30 8/13 8/27 9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1

May 2017 July 2017 September 2017 November 2017 January 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 10: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days

95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days

111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days

124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days

137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days

138 Foundation (Third Floor) 35 days Wed 10/4/17 Tue 11/21/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days

139 Form Third Floor 21 days Wed 10/4/17 Wed 11/1/17 Mon 11/20/17 Mon 12/18/17 0 days 33 days 136

140 Install Reinforcing Steel for Third Floor 15 days Thu 10/12/17 Wed 11/1/17 Tue 11/28/17 Mon 12/18/17 0 days 33 days 139FF,135FF-5 days

141 Third Floor inspections 2 days Thu 11/2/17 Fri 11/3/17 Tue 12/19/17 Wed 12/20/17 0 days 33 days 140

142 Place Concrete for Third Floor 2 days Mon 11/6/17 Tue 11/7/17 Mon 7/23/18 Tue 7/24/18 0 days 185 days 141

143 Strip Forms for Third Floor 10 days Wed 11/8/17 Tue 11/21/17 Wed 7/25/18 Tue 8/7/18 185 days 185 days 142

144 Interior Supports (Third ) 36 days Mon 11/6/17 Mon 12/25/17 Thu 12/21/17 Tue 1/30/18 26 days 26 days

145 Form Supports 15 days Mon 11/6/17 Fri 11/24/17 Thu 12/21/17 Wed 1/10/18 0 days 33 days 141

146 Install Reinforcing Steel Supports 15 days Mon 11/6/17 Fri 11/24/17 Thu 12/21/17 Wed 1/10/18 0 days 33 days 139,145FF

8/27August 1

July 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

147 Support inspection 2 days Mon 11/27/17 Tue 11/28/17 Thu 1/11/18 Fri 1/12/18 7 days 33 days 146

148 Place Concrete Supports 2 days Fri 12/8/17 Mon 12/11/17 Wed 12/13/17 Thu 12/14/17 0 days 3 days 147

149 Strip forms for interior supports 10 days Tue 12/12/17 Mon 12/25/17 Wed 1/17/18 Tue 1/30/18 0 days 26 days 148

150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days

156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

8/27August 1

July 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8September 1 October 1 November 1 December 1 January 1 February 1 March 1 April 1September 2017 November 2017 January 2018 March 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

3/2

7/3

9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8September 1 October 1 November 1 December 1 January 1 February 1 March 1 April 1September 2017 November 2017 January 2018 March 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 11: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days

95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days

111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days

124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days

137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days

150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days

151 Form Roof 35 days Tue 12/26/17 Mon 2/12/18 Wed 1/31/18 Tue 3/20/18 0 days 26 days 149

152 Install Reinforcing Steel for Roof 15 days Tue 1/23/18 Mon 2/12/18 Mon 1/29/18 Fri 2/16/18 0 days 4 days 148FF-5 days,151FF

153 Roof inspections 2 days Tue 2/13/18 Wed 2/14/18 Thu 3/22/18 Fri 3/23/18 0 days 27 days 152,151

154 Place Concrete for Roof 2 days Fri 2/16/18 Mon 2/19/18 Mon 3/26/18 Tue 3/27/18 0 days 26 days 153

155 Strip Forms for Roof 10 days Mon 2/19/18 Fri 3/2/18 Thu 2/22/18 Wed 3/7/18 0 days 3 days 154FS-1 day

156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

12/3December 1

November 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

12/3December 1

November 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

3/2

12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17December 1 January 1 February 1 March 1 April 1 May 1 June 1

November 2017 January 2018 March 2018 May 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

7/3

12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17December 1 January 1 February 1 March 1 April 1 May 1 June 1

November 2017 January 2018 March 2018 May 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 12: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days

159 Pipes get delivered to site (stored off site) 14 days Tue 12/26/17 Fri 1/12/18 Wed 3/7/18 Mon 3/26/18 0 days 51 days 149

160 Inspect pipe supplies 15 days Mon 12/25/17 Fri 1/12/18 Thu 2/1/18 Wed 2/21/18 0 days 28 days 159SS-1 day

161 Weld pipes together prior to installation 30 days Mon 1/1/18 Fri 2/9/18 Tue 3/13/18 Mon 4/23/18 25 days 51 days 160SS+5 days

162 Install pipes 18 days Mon 2/12/18 Wed 3/7/18 Tue 3/20/18 Thu 4/12/18 26 days 26 days

163 Install Pipes for Ground Floor 3 days Mon 2/12/18 Wed 2/14/18 Thu 2/15/18 Mon 2/19/18 0 days 3 days 152FS-5 days,151FS-1 day,123,161SS+5 days

164 Install Pipes for Mezzainine Floor 3 days Mon 2/19/18 Wed 2/21/18 Tue 3/27/18 Thu 3/29/18 0 days 26 days 168,136

165 Install Pipes for Second Floor 3 days Mon 2/26/18 Wed 2/28/18 Tue 4/3/18 Thu 4/5/18 0 days 26 days 169,149

166 Install Pipes for Third Floor 3 days Mon 3/5/18 Wed 3/7/18 Tue 4/10/18 Thu 4/12/18 0 days 26 days 170,155

167 Pipe inspections 17 days Thu 2/15/18 Fri 3/9/18 Fri 3/23/18 Mon 4/16/18 26 days 26 days

168 Pipe Inspection for Ground Floor 2 days Thu 2/15/18 Fri 2/16/18 Fri 3/23/18 Mon 3/26/18 0 days 26 days 163

169 Pipe Inspection for Mezzainine Floor 2 days Thu 2/22/18 Fri 2/23/18 Fri 3/30/18 Mon 4/2/18 0 days 26 days 164

170 Pipe Inspection for Second Floor 2 days Thu 3/1/18 Fri 3/2/18 Fri 4/6/18 Mon 4/9/18 0 days 26 days 165

12/3December 1

November 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

171 Pipe Inspection for Third Floor 2 days Thu 3/8/18 Fri 3/9/18 Fri 4/13/18 Mon 4/16/18 0 days 26 days 166

172 Plumbing fixtures get delivered (toilets, sinks, drains, handrails, soap and paper towel dispensers)

5 days Mon 2/12/18 Fri 2/16/18 Fri 6/29/18 Thu 7/5/18 0 days 99 days 163SS

173 Inspection of plumbing fixtures 5 days Mon 2/12/18 Fri 2/16/18 Fri 6/29/18 Thu 7/5/18 99 days 99 days 172SS

174 Install plumbing fixtures 3 days Mon 3/12/18 Wed 3/14/18 Wed 8/1/18 Fri 8/3/18 0 days 102 days 171

175 Inspection of servicability of plumbing fixtures 2 days Thu 3/15/18 Fri 3/16/18 Mon 8/6/18 Tue 8/7/18 102 days 102 days 174

176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days

194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days

216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days

224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

12/3December 1

November 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1

November 2017 January 2018 March 2018 May 2018 July 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

7/3

7/3

12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1

November 2017 January 2018 March 2018 May 2018 July 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 13: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days

176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days

177 Ducting, air vents, heating and air conditioning units get delivered on site

5 days Mon 12/25/17 Fri 12/29/17 Fri 6/29/18 Thu 7/5/18 134 days 134 days 178SS

178 Inspection of equipment and parts 30 days Mon 12/25/17 Fri 2/2/18 Fri 5/25/18 Thu 7/5/18 0 days 109 days 179FF-5 days

179 Weld ducting together 30 days Mon 1/1/18 Mon 2/12/18 Fri 5/25/18 Thu 7/5/18 0 days 104 days 181SF-5 days

180 Install ducting and air vents 18 days Mon 2/19/18 Wed 3/14/18 Tue 4/17/18 Thu 4/26/18 31 days 31 days

181 Install ducting and air vents (Ground Floor) 3 days Mon 2/19/18 Wed 2/21/18 Tue 4/17/18 Thu 4/19/18 0 days 41 days 168,123

182 Install ducting and air vents (Mezzainine Floor) 3 days Mon 2/26/18 Wed 2/28/18 Fri 4/20/18 Wed 4/25/18 0 days 39.5 days 169,136

183 Install ducting and air vents (Second Floor) 3 days Mon 3/5/18 Wed 3/7/18 Tue 4/24/18 Thu 4/26/18 0 days 36 days 170,149

184 Install ducting and air vents (Third Floor) 3 days Mon 3/12/18 Wed 3/14/18 Tue 4/17/18 Thu 4/19/18 0 days 26 days 171,155

185 Inspection of completed ducting and air vents 17 days Thu 2/22/18 Fri 3/16/18 Fri 4/20/18 Mon 4/30/18 31 days 31 days

12/3November 21

September 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

186 HVAC Inspection of Ground Floor 2 days Thu 2/22/18 Fri 2/23/18 Fri 4/20/18 Mon 4/23/18 15 days 41 days 181

187 HVAC Inspection of Mezzainine Floor 2 days Thu 3/1/18 Fri 3/2/18 Wed 4/25/18 Fri 4/27/18 11 days 39.5 days 182

188 HVAC Inspection of Second Floor 2 days Thu 3/8/18 Fri 3/9/18 Fri 4/27/18 Mon 4/30/18 0 days 36 days 183

189 HVAC Inspection of Third Floor 2 days Thu 3/15/18 Fri 3/16/18 Fri 4/20/18 Mon 4/23/18 0 days 26 days 184

190 Heating and air conditioning units get delivered on site 5 days Mon 2/19/18 Fri 2/23/18 Fri 6/29/18 Thu 7/5/18 0 days 94 days 181SS

191 Inspection of heating and air conditioning units 5 days Mon 2/19/18 Fri 2/23/18 Fri 6/29/18 Thu 7/5/18 94 days 94 days 190SS

192 Install heating and air conditioning units (for each room, elevator)

5 days Tue 4/10/18 Mon 4/16/18 Wed 5/23/18 Tue 5/29/18 0 days 31 days 189,232,240

193 30 day test of HVAC system 30 days Tue 4/17/18 Mon 5/28/18 Wed 6/27/18 Tue 8/7/18 11 days 51 days 192

194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days

216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days

224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

12/3November 21

September 2017

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

12/24 1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12 9/2 9/23 10/14 11/4 11/25 12/16 1/6 1/27November 21 January 11 March 1 April 21 June 11 August 1 September 21 November 11 January 1

September 2017 January 2018 May 2018 September 2018 January 2019

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

5/28

7/3

7/3

12/24 1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12 9/2 9/23 10/14 11/4 11/25 12/16 1/6 1/27November 21 January 11 March 1 April 21 June 11 August 1 September 21 November 11 January 1

September 2017 January 2018 May 2018 September 2018 January 2019

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 14: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days

176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days

194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days

195 Lighting fixtures, cables, cable trays get delivered on site

5 days Mon 3/12/18 Fri 3/16/18 Wed 8/1/18 Tue 8/7/18 1 day 102 days 188

196 Inspection of delivered parts 5 days Tue 3/13/18 Mon 3/19/18 Fri 6/29/18 Thu 7/5/18 78 days 78 days 195SS,198FS-5 days

197 Install cable tray 4 days Mon 3/19/18 Thu 3/22/18 Tue 4/24/18 Fri 5/4/18 26 days 26 days

198 Install cable tray on Ground Floor 1 day Mon 3/19/18 Mon 3/19/18 Tue 4/24/18 Tue 4/24/18 0 days 26 days 186,189

199 Install cable tray on Mezzainine 0.5 days Tue 3/20/18 Tue 3/20/18 Fri 4/27/18 Fri 4/27/18 0.5 days 28.5 days 198,187

200 Install cable tray on Second Floor 1 day Wed 3/21/18 Wed 3/21/18 Tue 5/1/18 Tue 5/1/18 0 days 29 days 199,188

201 Install cable tray on Third Floor 1 day Thu 3/22/18 Thu 3/22/18 Fri 5/4/18 Fri 5/4/18 6 days 31 days 200,189

202 Route electrical connections 12 days Tue 3/20/18 Wed 4/4/18 Wed 4/25/18 Wed 5/9/18 25 days 25 days

203 Route connections on Ground Floor 3 days Tue 3/20/18 Thu 3/22/18 Wed 4/25/18 Fri 4/27/18 0 days 26 days 198

2/25February 1

January 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

204 Route connections on Mezzainine 2 days Mon 3/26/18 Tue 3/27/18 Mon 4/30/18 Tue 5/1/18 0 days 25 days 199,203

205 Route connections on Second Floor 3 days Wed 3/28/18 Fri 3/30/18 Wed 5/2/18 Fri 5/4/18 0 days 25 days 200,204

206 Route connections on Third Floor 3 days Mon 4/2/18 Wed 4/4/18 Mon 5/7/18 Wed 5/9/18 0 days 25 days 201,205

207 Label cables with asset tags and input into system 21 days Tue 3/20/18 Tue 4/17/18 Thu 6/7/18 Thu 7/5/18 57 days 57 days 203SS,206FF

208 Install electric boxes 2 days Tue 4/10/18 Wed 4/11/18 Tue 5/15/18 Wed 5/16/18 0 days 25 days 206,232,240

209 Install electric service panel 4 days Thu 4/12/18 Tue 4/17/18 Thu 5/17/18 Tue 5/22/18 0 days 25 days 208,232,240

210 Security cameras, sensors for lights and projectors delivered on site

1 day Thu 4/12/18 Thu 4/12/18 Fri 5/18/18 Fri 5/18/18 0 days 26 days 208

211 Inspection of security and educational equipment 2 days Fri 4/13/18 Mon 4/16/18 Mon 5/21/18 Tue 5/22/18 1 day 26 days 210

212 Install security cameras, sensors for lights, projectors 5 days Wed 4/18/18 Tue 4/24/18 Wed 5/23/18 Tue 5/29/18 0 days 25 days 209,211

213 Connect electrical and SCADA cables with electric boxes, lighting fixtures, heating unit, elevator unit

15 days Wed 4/25/18 Tue 5/15/18 Wed 5/30/18 Tue 6/19/18 0 days 25 days 208,209,212,192

214 Inspection of electrical and SCADA connections 5 days Wed 5/16/18 Tue 5/22/18 Wed 6/20/18 Tue 6/26/18 0 days 25 days 213

215 30 day testing of electrical system 30 days Wed 5/23/18 Tue 7/3/18 Wed 6/27/18 Tue 8/7/18 25 days 25 days 214

216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days

224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

2/25February 1

January 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2 12/16 12/30March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1March 2018 May 2018 July 2018 September 2018 November 2018 January 2019

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

7/3

7/3

7/3

3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2 12/16 12/30March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1March 2018 May 2018 July 2018 September 2018 November 2018 January 2019

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 15: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days

176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days

194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days

216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days

217 Elevator equipment and parts delivered to site 0 days Wed 2/14/18 Wed 2/14/18 Mon 4/23/18 Mon 4/23/18 0 days 47 days 153

218 Inspection of equipment and parts 2 days Thu 2/15/18 Fri 2/16/18 Thu 5/24/18 Fri 5/25/18 0 days 70 days 217

219 Assemble and install elevator shaft 15 days Mon 2/19/18 Fri 3/9/18 Mon 5/28/18 Fri 6/15/18 0 days 70 days 218

220 Inspection of elevator shaft assembly 2 days Mon 3/12/18 Tue 3/13/18 Wed 5/16/18 Thu 5/17/18 30 days 47 days 153FF+5 days,219

221 Connect electrical and mechanical parts 3 days Wed 4/25/18 Fri 4/27/18 Fri 5/18/18 Tue 5/22/18 0 days 17 days 220,213SS

222 Inspection of elevator operations 2 days Mon 4/30/18 Tue 5/1/18 Mon 6/25/18 Tue 6/26/18 0 days 40 days 221

223 30 day test of elevators 30 days Wed 5/2/18 Tue 6/12/18 Fri 5/25/18 Thu 7/5/18 17 days 17 days 193FF,222

224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

1/14January 1January 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

1/14January 1January 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

2/14

6/127/3

1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1January 2018 March 2018 May 2018 July 2018 September 2018 November 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

7/3

1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1January 2018 March 2018 May 2018 July 2018 September 2018 November 2018

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 16: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

226 Drywall 15 days Mon 3/19/18 Fri 4/6/18 Fri 4/27/18 Fri 5/11/18 25 days 25 days

227 Delivery of drywall 0 days Mon 3/19/18 Mon 3/19/18 Tue 3/27/18 Tue 3/27/18 0 days 6 days 198SS

228 Install drywall 10 days Mon 3/26/18 Fri 4/6/18 Fri 5/4/18 Fri 5/11/18 25 days 25 days

229 Install drywall for Ground Floor 3 days Mon 3/26/18 Wed 3/28/18 Fri 5/4/18 Tue 5/8/18 4 days 29 days 168,186,203,227FS+5 days

230 Install drywall for Mezzainine 3 days Wed 3/28/18 Fri 3/30/18 Mon 5/7/18 Wed 5/9/18 3 days 28 days 169,187,204

231 Install drywall for Second Floor 3 days Mon 4/2/18 Wed 4/4/18 Tue 5/8/18 Thu 5/10/18 1 day 26 days 170,188,205

232 Install drywall for Third Floor 3 days Wed 4/4/18 Fri 4/6/18 Fri 4/6/18 Tue 4/10/18 0 days 2 days 171,189,206FS-1 day

233 Carpentry 16 days Mon 3/19/18 Mon 4/9/18 Wed 5/9/18 Tue 8/7/18 37 days 37 days

234 Windows, doors, cabintry delivered on site 0 days Mon 3/19/18 Mon 3/19/18 Wed 7/4/18 Wed 7/4/18 0 days 77 days 227

235 Inspection of parts 2 days Mon 3/19/18 Tue 3/20/18 Wed 7/4/18 Thu 7/5/18 77 days 77 days 234

236 Install windows, doors and cabintry 4 days Wed 4/4/18 Mon 4/9/18 Wed 5/9/18 Mon 5/14/18 25 days 25 days

237 Install Windows/Doors for Ground Floor 1 day Wed 4/4/18 Wed 4/4/18 Fri 4/6/18 Fri 4/6/18 0 days 2 days 229,232SS

3/19

3/19

TMar 11, '18

B

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

238 Install Windows/Doors for Mezzainine 1 day Thu 4/5/18 Thu 4/5/18 Thu 5/10/18 Thu 5/10/18 0 days 25 days 237,230

239 Install Windows/Doors for Second Floor 1 day Fri 4/6/18 Fri 4/6/18 Fri 5/11/18 Fri 5/11/18 0 days 25 days 238,231

240 Install Windows/Doors for Third Floor 1 day Mon 4/9/18 Mon 4/9/18 Mon 5/14/18 Mon 5/14/18 0 days 25 days 239,232

241 Insulation 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 25 days 47 days

243 Paint (walls) 13 days Mon 4/30/18 Wed 5/16/18 Wed 7/4/18 Fri 7/20/18 12 days 47 days

247 Floor Finishes 15 days Mon 5/14/18 Fri 6/1/18 Wed 7/25/18 Wed 8/8/18 0 days 47 days

252 Trades Complete 0 days Fri 6/1/18 Fri 6/1/18 Fri 7/6/18 Fri 7/6/18 24 days 24 days 226FF,233FF,241FF,243FF,247FF

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

TMar 11, '18

B

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

3/19

3/19

S W S T F M T S W S T F M T S W S T F M TMar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18

B E M B

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

6/1

7/3

S W S T F M T S W S T F M T S W S T F M TMar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18

B E M B

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 17: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days

83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days

84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days

85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days

157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days

225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days

226 Drywall 15 days Mon 3/19/18 Fri 4/6/18 Fri 4/27/18 Fri 5/11/18 25 days 25 days

233 Carpentry 16 days Mon 3/19/18 Mon 4/9/18 Wed 5/9/18 Tue 8/7/18 37 days 37 days

241 Insulation 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 25 days 47 days

242 Caulking, air sealing, and draft and fire stop 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 0 days 47 days

243 Paint (walls) 13 days Mon 4/30/18 Wed 5/16/18 Wed 7/4/18 Fri 7/20/18 12 days 47 days

244 Prep drywall for prime coat 3 days Mon 4/30/18 Wed 5/2/18 Wed 7/4/18 Fri 7/6/18 0 days 47 days

245 Prime paint drywall 3 days Mon 5/7/18 Wed 5/9/18 Wed 7/11/18 Fri 7/13/18 0 days 47 days

246 Paint wall 3 days Mon 5/14/18 Wed 5/16/18 Wed 7/18/18 Fri 7/20/18 0 days 47 days

247 Floor Finishes 15 days Mon 5/14/18 Fri 6/1/18 Wed 7/25/18 Wed 8/8/18 0 days 47 days

248 Delivery of carpets 0 days Mon 5/14/18 Mon 5/14/18 Fri 7/6/18 Fri 7/6/18 0 days 39 days

249 Cleaning of floors 5 days Mon 5/21/18 Fri 5/25/18 Wed 7/25/18 Tue 7/31/18 0 days 47 days

250 Waxing of floors 2 days Mon 5/28/18 Tue 5/29/18 Wed 8/1/18 Thu 8/2/18 0 days 47 days

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

251 Installing carpets 3 days Wed 5/30/18 Fri 6/1/18 Fri 8/3/18 Tue 8/7/18 47 days 47 days

252 Trades Complete 0 days Fri 6/1/18 Fri 6/1/18 Fri 7/6/18 Fri 7/6/18 24 days 24 days

253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days

254 Landscaping 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 93 days 93 days

255 Sidewalks, ramps and stairs 10 days Mon 5/14/18 Fri 5/25/18 Mon 8/20/18 Fri 8/31/18 0 days 70 days

256 Handrails 1 day Mon 5/28/18 Mon 5/28/18 Wed 10/10/18 Wed 10/10/18 97 days 97 days

257 Plants 5 days Mon 5/28/18 Fri 6/1/18 Thu 10/4/18 Wed 10/10/18 93 days 93 days

258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Predecessors

82

83

232

242

244FS+2 days

245FS+2 days

249SS-5 days

246FS+2 days

249

5/14

T W T F S S M T W T F S S M TMar 18, '18 Apr 8, '18 Apr 29, '18 May 20, '18 Jun 10, '18 Jul 1, '18

B E M

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Predecessors

250

226FF,233FF,241FF,243FF,247FF

248SS

255

255

85FF,253FF

6/1

7/3

T W T F S S M T W T F S S M TMar 18, '18 Apr 8, '18 Apr 29, '18 May 20, '18 Jun 10, '18 Jul 1, '18

B E M

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: EDC Project Final Ver 2Date: Fri 4/3/15

Page 18: Engineering Design Center Project Schedule

ID Task Name Duration Start Finish Late Start Late Finish Free Slack

Total Slack

Predecessors

1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days

2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days

15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days

81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days

259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

260 Document and Stakeholder Control 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days

261 Biweekly meetings with stakeholders and subcontractors 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS

262 Confirm all documents (transmittals, change orders, shop drawings, reports, manuals) are complete

600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS

263 Total all change orders and submit to client as a report 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS

264 Complete all deficiency items 60 days Wed 7/4/18 Tue 9/25/18 Fri 7/6/18 Thu 9/27/18 2 days 2 days 85

265 Cleaning of site and building 3 days Wed 7/4/18 Fri 7/6/18 Thu 9/6/18 Mon 9/10/18 0 days 46 days 85

266 Contractor final inspection of building 1 day Mon 7/9/18 Mon 7/9/18 Tue 9/11/18 Tue 9/11/18 0 days 46 days 265

267 City final inspection of building 1 day Tue 7/17/18 Tue 7/17/18 Wed 9/19/18 Wed 9/19/18 0 days 46 days 266FS+5 days

268 Issue City user and occupancy certificate 0 days Tue 8/7/18 Tue 8/7/18 Thu 10/11/18 Thu 10/11/18 0 days 46 days 267FS+15 days

269 Meet with client to confirm all requirements were tended to 1 day Wed 8/8/18 Wed 8/8/18 Thu 10/11/18 Thu 10/11/18 0 days 46 days 258,268

270 Meet and train operators on the functionality of building 5 days Thu 8/16/18 Wed 8/22/18 Fri 10/19/18 Thu 10/25/18 0 days 46 days 269FS+5 days

271 Demobilize site trailers 3 days Thu 8/23/18 Mon 8/27/18 Fri 10/26/18 Tue 10/30/18 46 days 46 days 270

272 Grand opening of Engineering Design Center 0 days Fri 9/7/18 Fri 9/7/18 Tue 10/30/18 Tue 10/30/18 38 days 38 days 267

3/13September 1

July 2015

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: EDC Project Final Ver 2Date: Fri 4/3/15

8/7

9/7

6/19 9/25 1/1 4/9 7/16 10/22 1/28 5/6 8/12 11/18 2/24 6/2 9/8 12/15 3/22 6/28 10/4 1/10 4/18 7/25 10/31 2/6 5/15March 21 October 11 May 1 November 21 June 11 January 1 July 21 February 11 September 1 March 21 October 11 May 1

July 2015 September 2016 November 2017 January 2019 March 2020 May 2021 July 2022

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: EDC Project Final Ver 2Date: Fri 4/3/15