Eng: Eyad Haddad 1
Specification & Quantities Estimating
Lecturer
Eng: Eyad A. HaddadEng: Eyad A. Haddad
College of Applied Engineering& Urban Planning
Eng: Eyad Haddad 2
Course Aims & Objectives
At the completion of this course, the student will:
Recognize the preliminary and detailed estimating methods and focusing on the elements for construction projects
To be familiar with cost analysis and preparation for bidding.
Understanding and be familiar with the construction specification in particular for building.
Eng: Eyad Haddad 3
Course Outline
Part 1 : Quantity SurveyIntroduction to Engineering project including
project cycle, & bidding documents.Quantities surveying and calculation of
different areas.Methods of measurement of the works.Pricing & cost analysis.Payment certificate.Application on Engineering project
Eng: Eyad Haddad 4
Part 2 : Technical specification
Earth worksConcrete worksMasonry worksPlasteringTilingMetal workCarpentry workPainting worksGlazingPlumbing worksElectrical works
Eng: Eyad Haddad 5
The Engineering ProjectThe Engineering Project
ProjectProject
Structural Structural worksworks
Architectural Architectural WorksWorks
Electrical Electrical WorksWorks
Mechanical Mechanical WorksWorks
Eng: Eyad Haddad 6
Types of construction Engineering Types of construction Engineering Projects :Projects :
- Building construction- Roads Construction- Water Systems- Sewerage and Storm water systems
Eng: Eyad Haddad 7
Project Cycle
Studies, design, tendering
Implementation & supervision
Taking- over, and operation
Eng: Eyad Haddad 8
Main stages in construction project1- Concept : identify the project needs, and objectives2- technical studies as feasibility study, possibility of
implementation, primary cost, and possibility of financing …..etc.
3- Preliminary design4- Detailed design including architectural , structural, electrical,
mechanical.5- Tender documents.6 – Tendering7- Contract Award8- contract agreement9- starting construction10- Preliminary handing over the project11- the operation of the project12- maintenance period13- Project final handing over.
Eng: Eyad Haddad 9
Construction Project CycleP
erc
en
t C
om
ple
te
Stage I Stage II Stage III Stage IV
Project "GO" Decision
Major Contracts Let
Installation Substantially Complete
Full Operations
Feasability- P roject Formulation - Feasabiltiy Studies- Strategies Design & Approval
Planning & Design - Base Design - Cost & Schedule- Contract Terms & Conditions. - Detailed P lanning
Turnover & Start Up- Final Testing - Maintenance
Construction - Manufacturing - Delivery - Civil Work - Installation - Testing
Figure 1.1 : Construction Projects Life-Cycle (Ref: PMBK, 2000)
Eng: Eyad Haddad 10
Tender DocumentsTender Documents
Invitation to bid Instruction to bidders Information to bidders & bid data Biding Forms General conditions of contract Specific condition of contract Specification BOQ Drawings Contract forms
Eng: Eyad Haddad 11
The Project Parties
The Employer /OwnerThe consultant: who appointed by the
employer to do the design and bidding documents and supervise the construction work.
The contractor: who was approved by the employer to implement the works according to the submitted bid.
Eng: Eyad Haddad 12
Other PartiesMunicipalities, ministries, suppliers, techniciansSubcontracts, workers,Insurance companiesBanks and other financing agencies.
Eng: Eyad Haddad 13
Construction Project Teams
Main tasks for engineering teams in Main tasks for engineering teams in the project are :the project are :- design- Implementation / construction- supervision
Eng: Eyad Haddad 14
Construction Project Teams
Eng: Eyad Haddad 15
Quantity Surveyor
He the person who is responsible on estimating the quantities from the design drawings, and measurement of the quantities in the site during the project implementation, and preparing the current and final payments.
Eng: Eyad Haddad 16
Quantity Surveys (take off)
It is the quantity of works/material take off , required for the completion of project implementation, and listed as items in table of quantities.
In general we can describe quantity survey In general we can describe quantity survey as follows:as follows:
1.Description and preparation of the bill of quantities and its items required for the tender.
2.Preparation of the site material, material types, and material distribution.
Eng: Eyad Haddad 17
Quantity surveys (take off) .. Cont.Quantity surveys (take off) .. Cont.
Describe the items and preparing BOQPreparing of the cost estimate in BOQ.Preparation of the list of the site needs
(technician / workers)Preparation of the due payment statements
(contractor payments during the construction)
Eng: Eyad Haddad 18
Tasks of the Quantity SurveyorTasks of the Quantity Surveyor
First : in the consultant office :Stage 1 :During the preparation of bidding
documents :- Preparation of the BOQ from the design drawing
which part of bidding documents.- Preparation of cost estimate for items listed in BOQ- Review and check the bids submitted from bidders.- Preparation of the lists of the contents of bids
received.- Sharing in evaluation and preparation of t
recommendation to award the contract to be submitted to owner.
Eng: Eyad Haddad 19
Quantity Surveyor TasksQuantity Surveyor Tasks
22 Stage 2 :Stage 2 : During the supervision of the During the supervision of the constructionconstruction
- Review and checking the payments submitted from the contractor.
- Preparation of the reports about the conformity of the quantities items with contract documents.
Eng: Eyad Haddad 20
Second : In the Contractor CompanySecond : In the Contractor Company
- During the implementation :- During the implementation :- Review and checking the BOQ at the starting of the
work.- Prepare the eng. Measurement for the quantities of
the finished works.- Prepare lists of the site needs (material, workers,
technicians)- Calculate the remuneration of the subcontractors,
workers, equipments,…etc.- Prepare the payment statements- Prepare the detailed reports describing the situation of
the items quantities, (plus or minus the contract BOQ)
Eng: Eyad Haddad 21
Required SkillsRequired Skills
Ability to understand the drawings details, design drawings, shop drawings, as built ).
Excellent knowledge of the calculation of the areas and volumes, knowledge of fees of workers e /technicians/ , rules and law of the contracts,
In addition to the knowledge of related financial issues/ taxes, banks transactions, insurances and its implication.
Knowledge of the productivity of the workers and technicians.
Eng: Eyad Haddad 22
Stages of the Quantity SurveyStages of the Quantity Survey
Stage1 : preparation of the engineering measurement and calculations of the works during the preparation of the bidding documents (consultant) and
- preparation of the measurement of the accomplished works in the site and prepare in the site and prepare the payment (contractor)the payment (contractor)
Stage 2 : preparing BOQStage 3 : review and check the financial
payments.
Eng: Eyad Haddad 23
Eng: Eyad Haddad 24
Areas, Volumes, & Surface areas
See attached PDF file
Eng: Eyad Haddad 25
Eng: Eyad Haddad 26
Eng: Eyad Haddad 27
Eng: Eyad Haddad 28
Eng: Eyad Haddad 29
Eng: Eyad Haddad 30
Eng: Eyad Haddad 31
Eng: Eyad Haddad 32
Eng: Eyad Haddad 33
Eng: Eyad Haddad 34
Eng: Eyad Haddad 35
Next Lecture :Special calculations of the areas and volumes.Measurement of the works.
Eng: Eyad Haddad 36
Lecture # 3
Eng: Eyad Haddad 37
Method of measurements1- Conventional measurement (1- Conventional measurement ( البلدي البلدي الكيل ((الكيل
Depends on experience, and type of project.
Doesn't govern by theories or engineering basics.
Not considered as scientific method.
Doesn't subtract the opening as windows or doors from
the block, plastering, painting works and computing
whole wall.
Another example : as the every 3 steps in stair = 1 m3
2- Engineering measurement (2- Engineering measurement ( الهندسي الهندسي الكيل ((الكيلIt is calculating all the works finished after subtracting all opening.
Eng: Eyad Haddad 38
Cont.unit measurement example
Lump-sum (L.S)
Works have details difficult to be
calculated
Earth work, earthling system (electrical),,
M.R Works have specific length and width
As pipes
No. Works have 3 dim. fixed
Windows, doors,
M2 Works with specific thickness,
as plastering, painting,
M3 Variable dimensions
Footings, columns, stairs,
Ton / kg Have specific width As steel
Day / hrs Labor / equipment Workers wages, equipment,
Eng: Eyad Haddad 39
Types of construction works
Building construction
Roads construction
Water Booster P.S and piping,
Sewage and storm water P.S and piping.
Electrical construction
Eng: Eyad Haddad 40
Preparation of engineering measurements
measurement sheet project name _________________contractor name ____________engineer name _______________
length width heigth Total amountDimension
SN Description Unit Quantity Unit rate
Eng: Eyad Haddad 41
Act. No. Activity Description Unit
0100 General Works
0101 Demolition Works l.s
0200 Earth Work
0201 Excavation m3
0203 Fill with compacted clean sand m3
0300 Concrete Works
0301 Plain concrete B150 m3
0302 R. Concrete B300 for foundation m3
0303 R. Concrete B250 for Ground beams and steps m3
0304 R. Concrete B300 for Necks and Columns m3
0305 R. Concrete B250 for Slaps 25 cm thick. m3
0400 Block Works
0401 Block works for walls 20cm thick. m2
0402 Block works for internal walls 15cm thick. m2
0403 Block works for internal walls 10cm thick. m2
0500 Plastering Works
0501 3-face internal plastering m2
0502 External plastering on walls m2
0600 Tilling Works
0601 Pre cast terrazzo tiles 25*25 cm for floors m2
0602 White ceramic tiles20*30cm for walls m2
0603 White ceramic tiles 20*20cm for floor m2
0700 Painting Works
0701 Internal Painting-Poliside for Ceiling m2
0702 Internal Painting-Supercryle for walls m2
0800 Carpentry Works
0900 Metal and Aluminum Works
1000 Electrical Works
1100 Mechanical Works
1200 Isolation Works
1300 Special Works
1400 Finishing Works
Eng: Eyad Haddad 42
Item unit Method of measurement
Site leveling Lump sum It takes into consideration all site leveling including the excavation, fill, till reach 0+B.M according to design drawing.
Excavation (cut) m3 Measured by 2 methods :1- footings areas according to blinding area * depth of excavation according to drawings.2- external dimensions of the building *depth of footings
Fill (backfill) m3 = excavation – concrete work for footings and columns under ground level. = ground plan *depth of ground beams – (concrete for ground beams and ground floors)
Measurement of works / Earth Work
Eng: Eyad Haddad 43
Example : Measurement of Earth Work / Excavation works
Measured by 2 methods :1- footings areas according to blinding area * depth of excavation according to drawings.
2- external dimensions of the building *depth of footings
Eng: Eyad Haddad 44
Concrete works measures engineering measurement
All opening more than 0.1m2 or 0.1 m3 are
deducted.
The concrete works more than the areas, volumes in
the drawings doesn’t included.
Measurement of works / concrete works
Eng: Eyad Haddad 45
Measurement of works / concrete worksItem unit Method of measurement
Blinding concrete, ground concrete, benching, and slabs concrete with fixed thickness
m2 = length * width (the thickness should be specified in the drawings and specifications) Ribs blocks don’t subtract from the slabs concrete.
Footings, columns, ground beams, stairs, and canopies,
m3 = length*width*thickness-Ground beams are measured from its connection with columns- concrete stars include the stairs , steps, stair slabs, walls supporting the stairs.
Concrete decoration works as curves.
No. The dimensions must be specified in the drawings.
Eng: Eyad Haddad 46
Measurement of works / block worksItem unit Method of measurement
Block works m2 = length * width (the thickness should be specified in the drawings and specifications) - subtracting all openings more than 0.1 cm2.
Eng: Eyad Haddad 47
Measurement of works / Plastering/ painting works
Item unit Method of measurement
Length * width M2 = length * width (engineering measurement after subtracting the openings, more than 0.1 m2) - the area is measured above the skirting (terrazzo chips)
Internal plastering = walls + slabs
Eng: Eyad Haddad 48
Measurement of works / tilling works
Item unit Method of measurement
Terrazzo, marble, ceramic
m2 = length * width (engineering measurement)
Eng: Eyad Haddad 49
Measurement of works / Plastering/ painting works
Item unit Method of measurement
Plastering & painting
M2 = length * width (engineering measurement after subtracting the openings, more than 0.1 m2) - the area is measured above the skirting (terrazzo chips)
Internal plastering = walls + ceiling
Eng: Eyad Haddad 50
Measurement of works / Doors
Item unit Method of measurement
Doors No. The exact dimensions should be specified in the design drawings.Sometimes carpentry works measured in m2 or m length according to the item described in BOQ.
Eng: Eyad Haddad 51
Measurement of works / Windows
Item unit Method of measurement
windows No. The exact dimensions should be specified in the design drawings.Sometimes carpentry works measured in m2 or m length according to the item described in BOQ.
Eng: Eyad Haddad 52
Measurement of works / electrical & sanitary works
Item unit Method of measurement
Electrical and sanitary pieces / accessories
No. The dimensions should be specified clearly in the design drawings as the sockets, lamps, fluorescent lighting,…etc(W.C. , washing basins, sinks, manholes, pumps…etc)
piping M.R The dimension and details should be specified in the drawings, as (cables, pipes, ..etc)
Works with special detail
Lumps sum All details should be specified in the drawings, as earthing, gas network,
Eng: Eyad Haddad 53
Bill of QuantitiesThe results in the quantities book, are recorded in the BOQ table.It is preferable to add 5-10% percentage on the quantities for
contingency to avoid any errors or any…..
Eng: Eyad Haddad 54
Lecture # 4
Eng: Eyad Haddad 55
Estimate the quantities and prepare bill of quantities for the following works:
Concrete for columns.
Concrete for footings.
Plastering, painting and tilting for guest room
Tiling and plastering for bathroom 1, provided that the tiles will cover all the walls.
Knowing that,
Height of the floor is 2.95m
The windows for guest room are150x120cm, 300x120cm, and the doors are 220x90
cm and 220x120 cm
Bathroom1 door is 220x70 cm, and the window is 80x80cm
Depth of excavation is 1.2 m
Dimension of ground beams is 20x50 cm.
Thickness of Blinding concrete is 10 cm and increase 10 cm in each direction.
Dimension for columns and footings described in the following table:
Example 1
Eng: Eyad Haddad 56
Column number/Description
1,2,3,4,5,6, 7,8,9,10, 12,13,
18,19,2011,14,15,16,17,
Columns Dimension 20*50 20*60
Columns’ neck Dimension 25*50 25*60
Footings Dimension 150*150*50 cm 160*160*50
Guest room
living room
Bedroom-2-
Bedroom-1-
KitchenBedroom-3-
Bathroom1B
ath
room
C1 C2 C3 C4 C5
C7
C6
C8C9C10C11C12C13
C14 C15
C16 C17 C18
C19C20
Eng: Eyad Haddad 57
S.N
Item descriptionاألعمال بيان
الوحدة
Unit
الكمية Quant.
Dimensionsاألبعاد
Total Quantitiesالكلية الكمية
Lالطول
Wالعرض
Hاالرتفا
ع
Partiallyالجزئية الكميات Total
اإلجمال+ Positiveي
إضافةNegative –
خصم
Column number/Description
1,2,3,4,5,6, 7,8,9,10,
12,13, 18,19,20
11,14,15,16,17,
Columns Dimension 20*50 20*60
Columns’ neck Dimension
25*50 25*60
Footings Dimension150*150*50
cm160*160*50
Guest room
living room
Bedroom-2-
Bedroom-1-
KitchenBedroom-3-
Bathroom1
Bath
room
C1 C2 C3 C4 C5
C7
C6
C8C9C10C11C12C13
C14 C15
C16 C17 C18
C19
C20
Eng: Eyad Haddad 58
S.N
Item descriptionاألعمال بيان
الوحدة
Unit
الكمية Quant.
Dimensionsاألبعاد
Total Quantitiesالكلية الكمية
Lالطول
Wالعرض
Hاالرتفا
ع
Partiallyالجزئية الكميات Total
اإلجمال+ Positiveي
إضافةNegative –
خصم
Example 2 :Estimate the quantities and prepare bill of quantities for the following works:
Eng: Eyad Haddad 59
S.N
Item descriptionاألعمال بيان
الوحدة Unit
الكمية Quant.
Dimensionsاألبعاد
Total Quantitiesالكلية الكمية
Lالطول
Wالعرض
Hاالرتفاع
Partiallyالجزئية الكميات Total
اإلجمال+ Positiveي
إضافةNegative –
خصم
Example 3 :Estimate the quantities and prepare bill of quantities for the following works:
Eng: Eyad Haddad 60
S.N
Item descriptionاألعمال بيان
الوحدة Unit
الكمية Quant.
Dimensionsاألبعاد
Total Quantitiesالكلية الكمية
Lالطول
Wالعرض
Hاالرتفاع
Partiallyالجزئية الكميات Total
اإلجمال+ Positiveي
إضافةNegative –
خصم
Example 4 :Estimate the quantities and prepare bill of quantities for the following works:
Eng: Eyad Haddad 61
S.N
Item descriptionاألعمال بيان
الوحدة Unit
الكمية Quant.
Dimensionsاألبعاد
Total Quantitiesالكلية الكمية
Lالطول
Wالعرض
Hاالرتفاع
Partiallyالجزئية الكميات Total
اإلجمال+ Positiveي
إضافةNegative –
خصم
Example 5 :Estimate the quantities and prepare bill of quantities for the following works:
Eng: Eyad Haddad 62
S.N
Item descriptionاألعمال بيان
الوحدة Unit
الكمية Quant.
Dimensionsاألبعاد
Total Quantitiesالكلية الكمية
Lالطول
Wالعرض
Hاالرتفاع
Partiallyالجزئية الكميات Total
اإلجمال+ Positiveي
إضافةNegative –
خصم
Example 4 :Estimate the quantities and prepare bill of quantities for the following works:
Eng: Eyad Haddad 63
Item unit Method of measurement
Site leveling Lump sum It takes into consideration all site leveling including the excavation, fill, till reach 0+B.M according to design drawing.
Excavation (cut) m3 Measured by 2 methods :1- footings areas according to blinding area * depth of excavation according to drawings.2- external dimensions of the building *depth of footings
Fill (backfill) m3 = excavation – concrete work for footings and columns under ground level. = ground plan *depth of ground beams – (concrete for ground beams and ground floors)
Measurement of works / Earth Work
Eng: Eyad Haddad 64
Concrete works measures engineering measurement
All openinng more than 0.1m2 or 0.1 m3 are deducted.
The concrete works more than the areas, volumes in the drawings doesn’t included.
Measurement of works / concrete works
Eng: Eyad Haddad 65
Measurement of works / concrete worksItem unit Method of measurement
Blinding concrete, ground concrete, benching, and slabs concrete with fixed thickness
m2 = length * width (the thickness should be specified in the drawings and specifications) Ribs blocks don’t subtract from the slabs concrete.
Footings, columns, ground beams, stairs, and canopies,
m3 = length*width*thickness-Ground beams are measured from its connection with columns- concrete stars include the stairs , steps, stair slabs, walls supporting the stairs.
Concrete decoration works as curves.
No. The dimensions must be specified in the drawings.
Eng: Eyad Haddad 66
Measurement of works / block worksItem unit Method of measurement
Block works m2 = length * width (the thickness should be specified in the drawings and specifications) - subtracting all openings more than 0.1 cm2.
Eng: Eyad Haddad 67
Measurement of works / Plastering/ painting works
Item unit Method of measurement
Length * width M2 = length * width (engineering measurement after subtracting the openings, more than 0.1 m2) - the area is measured above the skirting (terrazzo chips)
Internal plastering = walls + slabs
Eng: Eyad Haddad 68
Measurement of works / tilling works
Item unit Method of measurement
Terrazzo, marble, ceramic
m2 = length * width (engineering measurement)
Eng: Eyad Haddad 69
Measurement of works / Plastering/ painting works
Item unit Method of measurement
Plastering & painting
M2 = length * width (engineering measurement after subtracting the openings, more than 0.1 m2) - the area is measured above the skirting (terrazzo chips)
Internal plastering = walls + ceiling
Eng: Eyad Haddad 70
Measurement of works / Doors
Item unit Method of measurement
Doors No. The exact dimensions should be specified in the design drawings.Sometimes carpentry works measured in m2 or m length according to the item described in BOQ.
Eng: Eyad Haddad 71
Bill of Quantities The results in the quantities book, are recorded in
the BOQ table. It is preferable to add 5-10% percentage on the
quantities for contingency to avoid any errors or any.
Eng: Eyad Haddad 72
Lecture # 5
Eng: Eyad Haddad 73
Methods of EstimatesA) Actual cost: is known at the completion of the work.
B) Detailed Estimates :
must known before the construction stage, and it can
be prepared in four stages as follow:
1. Details of Measurements and calculation of quantities.
(by using Details of Measurements Form )
2. Abstract of estimated cost.
(by using Abstract of estimated Form )
3. Transfer the data to the Bill of Quantities.
4. Summary table
Eng: Eyad Haddad 74
S.N
Item descriptionاألعمال بيان
الوحدة
Unit
الكمية Quant.
Dimensionsاألبعاد
Total Quantitiesالكلية الكمية
Lالطول
Wالعرض
Hاالرتفا
ع
Partiallyالجزئية الكميات Total
اإلجمال+ Positiveي
إضافةNegative –
خصم
1. Details of Measurements Form
Eng: Eyad Haddad 75
2. Abstract of estimated Formmeasurement sheet
project name _________________contractor name ____________engineer name _______________
Eng: Eyad Haddad 76
No. Item description unit Quantity Unit price($ or NIS …)
Total amount($ or NIS …)
1 The works include…… L.S
3. Transfer the data to the Bill of Quantities
See the attached example
Eng: Eyad Haddad 77
The items are classified into categories as shown in the next table.
at the end of BOQ, summary of the items are shown as well as the total amount of the price
Bill of Quantities
Eng: Eyad Haddad 78
NO. DESCRIPTION UNIT QTY UNIT RATE
$
TOTAL AMOUNT
$
1.1 Excavation from natural ground level for foundation up to required designed level. The selected excavated material can be used for back filling, the surplus excavated material from the site. According to Eng. Instructions.
M3
1.2 Backfilling from the selected excavated material around foundation and to make up levels for the school yard in layers 25cm thick (M.D.D 98%)
according to Eng. Instructions and specifications.
M3
1.3 Supply, spread , level and compact Aproved selected Material ( kurkar ) type A in compacted layer 25 an
thick 98% Max .Dry Density around foundation and as per Specification and Eng. Instructions.
M3
1.4 Supply clean sand and fill in compacted layers 25cm thick for school yard to make up levels according to
the drawings.
M3
Total
Example for the Bill of QuantitiesEXCAVATION & EARTHWORKS
Eng: Eyad Haddad 79
Example for the Bill of QuantitiesCONCRETE WORKS
NO. DESCRIPTION UNIT QTY UNIT RATE
$
TOTAL AMOUNT $
The items include shuttering, steel shaping, fixing , supplying and cast the required concrete, striping of shuttering and two coats of water proof
hot bitumen layer of type 75 for foundations, necks and ground beams and all requirement as per specifications, drawings and engineer
instructions.
2.1 Supply and cast plain concrete B (200) kg/cm2 for Blinding beds 5 cm thick and 15cm plain concrete of entrance ramps as per specifications
and drawings.
M3
2.2 Supply and cast ready mix concrete B(250) kg/cm2 for the ground slab 10cm thick with steel mesh 8mm diameter every 20cm including
polythene sheets below concrete slab as per specifications and drawings.
M2
2. 3 Supply and cast ready mix concrete B (250) kg/cm2 for reinforced concrete foundations as per specifications and drawings.
M3
2.7 Supply and cast ready mix concrete B (300) kg/cm2 for reinforced concrete columns and columns necks as per specifications and drawings.
M3
2.12 Supply and cast ready mix concrete B (250) kg/cm2 for suspended hollow block slab 20 cm thick, including the reinforced steel , drop and
inverted beams, decorative arch’s , hollow cement block, 40 x 25 x 14cm and all other materials as per specifications and drawings.
M2
2.14 B250 reinforced concrete for Apron (surface treated with mechanical steel trolled finish) the price include polythene sheets. Reinforcement I 8mm / 20 cm in both way and reinforced edge beam the price including
15cm thick compacted base coarse according to drawing and specification.
M3
Total
Eng: Eyad Haddad 80
4. Summary table
No. Item Total amount($ or NIS …)
1- EXCAVATION & EARTH WORKS
2 CONCRETE WORKS
3- BLOCK WORK
4- CARPENTRY
5- METAL WORK
6- FINISHING WORKS
7- PLUMBING WORKS
8- ELECTRICAL WORKS
9- MISCELLANEOUS
Eng: Eyad Haddad 81
Item description Based on drawings, specification. It should be accurate and reflect the
drawings and specifications, Description should include :
1- description of the works2- unit3- determine the method of measurement.
Eng: Eyad Haddad 82
How to read the description Description of the items Drawings, details Specifications General and specific conditions Instruction of the supervisor engineer
Eng: Eyad Haddad 83
the work price should include The description of the item should
include all the work that the unit price will take account of as will be illustrated in the following
Eng: Eyad Haddad 84
1- Earth work The unit price should include :- Excavation in any kind of soil, rock, etc., starting at reduced
level (bottom of G.B. blinding) down to bottom of foundation blinding including compacting backfill around foundations and shall be applied on layers, 200 mm thick, watered and compacted to 95 % (98%) according to modified AASHTO Density Test T-80.for the excavated foundation and removal of surplus material from site to an approved dumping area complete as per specifications.
- Site Leveling. (Excavation of all Site including External Works). Cut and / or fill in any kind of soil, concrete, or asphalt; to the required Levels approved by the Engineer (Reduced Level). Including scraping of top. Any damage to the external walls, fence, etc. should be maintained without any compensations..
- Test of the soil (4 points at least)- Safety around the site,- Work according to engineer instruction and specifications
Eng: Eyad Haddad 85
اإلجمالي بالحروف
اإلجمالي
بالدوالر
السعر بالدوالر
الكمية الوحدة األعمال بيان البند
مقطوعي
مقطوعي أعمال المدني :-أعمال الحفر والردم والبند يشمل اآلتي:-
أعمال اإلزالة والبند يشمل اآلتي :--إزالة جميع المنشآت وخالفه القائمة 1
والموجودة في الموقع، ونقل أي مخلفات إلى موقع بعيد عن موقع البناء والعمل حسب
المخططات وتعليمات المهندس المشرف . والبند يشمل اآلتي :-أعمال الحفر والردم
أ-تنظيف موقع العمل وإزالة ما هو موجود ونقله إلى المكان الذي يحدده المشرف ونهو األعمال
حسب األصول .ب-التفريغ في أي نوع من التربة دون تفرقة
سواء ترابي أو حوري أو صخري للوصول إلى المناسيب الموضحة بالرسومات المرفقة ثم
الحفر لزوم القواعد واألحزمة األرضية وخالفه حسب المنسوب التصميمى وحتى الوصول إلى التربة األصلية للموقع على أن ال يقل الحفر عن
متر وذلك حسب المخططات وتعليمات 1.50المهندس المشرف, والبند يشمل جميع ما
تتطلبه أعمال الحفريات من إزالة القاذورات وإزالة جذور األشجار أو أي عوائق أخرى تعيق
العمل مثل خطوط المياه أو آبار أ و خطوط مجارى أو خطوط كهرباء وغيره على حساب
المقاول .ج- الردم من الرمل السافية النظيف ونقل جميع المواد الناتجة من الحفر و الغير الزمة إلى خارج الموقع والردم يتم حتى الوصول إلى المناسيب
المطلوبة والموضحة بالمخططات .
� :أوال-1
1-12-1
Eng: Eyad Haddad 86
Concrete workConcrete works include: All formworks and shuttering in any form, shape and size.
Making chamfered and curved edges, allowing for and making grooves and sleeves and the like; removal of forms and cleaning of all exposed tie wires and rods; making good the harmed surfaces and
Supplying, Casting, vibrating and curing as per specifications. Approved additives and admixtures. Incurred costs on Concrete Mix Designs, Sample taking,
testing and providing test results certificates, storing and saving of samples, and preparation of bar bending schedules and workshops.
Supplying reinforcement of any grade, size and length as detailed in the drawings, storing on site including cutting, bending and fixing in position and providing all tying wires, spacers, shop drawings, testing and bar bending schedules
Eng: Eyad Haddad 87
Concrete work (cont’d) Painting of exposed surfaces of underground
reinforced concrete elements with two coats of Bituminous Emulsion. Supply of Polyethylene sheets under ground slabs.
Steel bars used for alignment and fixing of reinforcement works, and extra steel added to assure proper detailing and safety.
Measurement of Concrete elements shall be the net dimensions as detailed in the drawings. All recesses, openings and voids shall be deducted.
Measurement shall be only for the seen surfaces of elements, overlapping and measuring items twice under separate headings shall not be allowed.
Supplying and fixing of the required steel reinforcement as per drawings and specifications.
Eng: Eyad Haddad 88
Block worksRates of Block works include All works of the bill shall be of Concrete blocks of high
quality standards and as per specifications. Vertical and horizontal joints., Cement and mortar,
Galvanized angles and ties., Closed end blocks at all ends, door and window jambs, reveals and the like.
Concrete filling including reinforcing steel to cavities at quoins and door and window openings.
Lintels and bond beams to the full length of the wall, and all needed to complete job as per drawings and
specifications concrete infill and transporting, placing compacting,
curing, surface finishing, protection, construction and expansion joints and all labors and materials and tests.
Eng: Eyad Haddad 89
Block works (cont’d)
Block work shall be bonded to concrete columns, wall and the like with concrete infill B250. block must be stopped in graded shape (10-15 cm from the concrete face) one 8 mm bar must cast in columns during casting with 40 cm length fixed every 42 cm horizontally, in addition to two vertical 10 mm bars.
Eng: Eyad Haddad 90
Plastering works, includes The price shall include, all narrow widths, for taking out
joints on block walls or backing concrete face for key, for making good to frames around pipes and other fittings , plastering to jambs and reveals of openings ( النافذة من جانب
للجدار الخارجى السطح وبين اطارها side of columns, window ,(بينsills; all of which shall be included Price shall also include Expanded metal lath, angle beads at all corners and plaster stops at opening edges, expansion joints, sills, labor, curing, erecting and dismantling of scaffoldings سقاالت), additives, pigments and all incidentals required as specified
Material, workmanship, Galvanized mesh, or plastic mesh, False ceiling from galvanized mesh and plastering (fixing mesh , covering it by 3-coats of rough plaster) reinforcement of the joints between different material as
the joints between the wall and columns.
Eng: Eyad Haddad 91
Tilling works Rate shall include preparation of surfaces under tiles, special tile
peace’s for edges and the like, tile surface finishing, Plastic spacers. Pointing and cleaning and all incidental as per specifications.
Supply, Install and Terrazzo Tiles, include, bedding and jointing in cement and sand mortar, pointing with white cement, required sand fill, and polishing, workmanship, and all incidental as per specifications
Isolation works for kitchen and bathroom (layer of fiber glass, and bitumen layers)
Marble includes connections, joints, mortar, and any other needed work. Supply and install a layer of cement and sand under marble and
porcelain , ceramic, according to specification and engineer instruction. Supply and spread a layer of sand under the tiles. Any decoration works as drawings
Eng: Eyad Haddad 92
Painting works All Paints shall be supplied to site in sealed
container, as approved by the Engineer, and site mixing shall not be permitted.
The Contractor rates shall include for supply of all materials, workmanship, samples, surface preparation , protection of painted surfaces , application to all heights as required of works, repair of all damaged surface, as per specification.
Eng: Eyad Haddad 93
CARPENTRY AND JOINERY WORKS (window & doors) Sizes of carpentry works given in the Bills of Quantities are finished sizes
and shall be as per Drawings. Sizes of doors and other items mentioned in the Bills of Quantities shall
allow for tolerance to suit the structural openings shown in the Drawings. Wooden doors and pair of doors shall be measured in square meter for
each structural opening, unless stated otherwise in the Bills of Quantities. Rates for carpentry and joinery work shall include : Shop and coordinated drawings. frames, architrave (عارضة ), and other holders Allowance for plastering and tiling and the like. Cutting and fitting around obstructions, Bedding and painting. Grounds, blocking and backings. Plugging concrete, block work, and stone work , and making good. Ironmongery including cylindrical locks, handles, stoppers, screws,
temporary fixing, re-fixing, oiling and adjusting.
Eng: Eyad Haddad 94
STEEL AND ALUMINUM WORKS
Rates for metalwork shall include for : Preparing shop drawings, Drilling, counter sinking, screwing, bolting and riveting. Sub frames, including galvanized steel frames for Aluminum
windows and architrave. Gaskets, sashes, double weather strips and external and internal
approved quality silicon filling around frames. Ironmonger including cylindrical locks (Union or equal) , stoppers,
handles, temporarily fixing, refitting, oiling and adjusting. Providing two keys for each lock . Glass and glazing including cutting to size, putty and rubber. Preparing surfaces for and painting one coat of primer before
fixing. Sealing and Painting to any area or width in any location including
work in multicolor and cutting in edges. All other accessories and incidentals required to execute the work.
Eng: Eyad Haddad 95
Electrical works All items price to include Supply, Installing, Connecting and
testing unless otherwise indicated, the contractor are requested to have approved full coordinated work shop drawings before starting contract activities, the price also includes all works necessary to implement electrical works in approved manner.
The contractor intended to order main and final distribution panel boards according to approved manufacturer drawings.
The price to include submittals, catalogs, any manufacturer instruction .
The contractor should install and construct all works according to drawings , specification tender documents, and requirement of Electrical Co.
Contractor should also test & submit the electrical Work to the Electricity Co. & Municipality.
Eng: Eyad Haddad 96
PLUMBING, SANITARY AND MECHANICAL WORKS
Rates shall include all fittings , fixtures , appliances and pipe laying Supply of material, workmanship, installation, testing and commissioning.
Rates to include also all peaces and fittings, including by passes , floats, cleaning outlets , automatic vents, vents and stack covers, valves and non return valves and the like needed to complete works as per specifications.
Insulation and painting as called for in specifications. Excavation and cutting for all pipe laying works, bedding
back filling and all works connected with pipe laying. All ties, sleeves, joints, tie bolts and rods, brackets and
the like. Rates to include Workshops, Coordinated and as- built
drawings as approved by the Engineer
Eng: Eyad Haddad 97
Lecture # 6
Eng: Eyad Haddad 98
Pricing & price analysis Before construction three types of pricing :
1- cost estimate2- pricing3- cost analysis
Eng: Eyad Haddad 99
Eng: Eyad Haddad 100
Factors affecting the pricing
Raw material Workmanship, labor, sub-contractors Administration cost including direct cost as salaries,
equipments, transportation ..etc. and indirect cost as electricity, communication cost, banks , municipality fees, ,,,etc.
Unforeseen expenses & risk (3-5%) Insurances Taxes as income tax, V.A.T, Profit (7-10%)
Eng: Eyad Haddad 101
Productivity of labor
It is necessary to calculate the productivity for the work teams either worker or technicians / equipments to calculate wages, for workers / subcontractors.
Productivity is measured per hour or per day.
Eng: Eyad Haddad 102
Pricing analysis stages :Estimate the price for raw material and
workmanship.Estimate the percentage of the specified
work from the total project work . (work item/total work *100%)
Estimate the cost of administration / management , tax, insurances, risk, and profit.
Estimate the total cost for all works item.Estimate the unit price for each item.
Eng: Eyad Haddad 103
Example:Analyze the prices, and find the unit price for
the following, knowing that, 1- Administrative expenses is fixed (1000$) for
project2- Unfixed expenses / indirect (400$)3- Insurance 200 $
Eng: Eyad Haddad 104
ID Description of work unit quantity
1 Concrete footings M3 78
2 Block works for wall (20*20*24cm) M2 100
3 Internal plastering M2 200
4 Wooden door 90*220 No. 10
Eng: Eyad Haddad 105
1- Price for raw material and workmanship- Concrete footing (B250)
ID Description Raw material per m3
price workmanship
1- Concrete footings (B250) Concrete 190 100Steel 170Wires 5
Nails, bolts 2
Water 1isolation 3
total 371 100Total price (NIS) 471Total price ($) 134$
Total for 78 m3 134*78 = 10,960 $
Eng: Eyad Haddad 106
ID Description Raw material per m2
price workmanship
Block 20*20*40 block 12.5*2=25 6
Morter 3
Moving the blocks
2
Joints, concrete fill
5
total 35 6
Total price (NIS) 41
Total price ($) 11.7
Total for 78 m3 11.7*100= 1170$
Block work (20*20*40 cm)
Eng: Eyad Haddad 107
Internal plastering
ID Description Raw material per m2
price workmanship
Internal plastering scaffolding o.5 6
Morter 4
Angles, metal grid, ..etc
0.5
water 0.5
total 6 6
Total price (NIS) 12
Total price ($) 3.4
Total for 200 m2 3.4*200= 680$
Eng: Eyad Haddad 108
Wooden doors 220*90 cm
ID Description Raw material per m2
price workmanship
Wooden door 220*90 material 400 50
Misce. 20
total 420 50
Total price (NIS) 470
Total price ($) 135
Total for 10 doors 135*10 =1350$
Eng: Eyad Haddad 109
percentage of the specified work from the total project work
ID Description Total work price % from total work
1 Concrete footings (B250) 10960 77.40%
2 Internal plastering 680 4.80%
3 Wooden door 220*90 1350 9.53%
4 Block 20*20*40 1170 8.26%
5 Total 14160 100.00%
Eng: Eyad Haddad 110
2- the cost of administration / management , tax, insurances, risk, and profit.
administration expenses
ID Description fixed (1000$)
variable (400$)
tax (10%)
Insurance
(200$)
risks (5%)
profit (10%)
Total
1 Concrete footings (B250)
774.01 309.6 1096 154.8 548 1096 3978.4
2 Internal plastering
48.02 19.21 68 9.61 34 68 246.8362
3 Wooden door 220*90
95.34 38.14 135 19.07 67.5 135 490.04
4 Block 20*20*40 82.63 33.05 117 16.53 58.5 117 424.70
Eng: Eyad Haddad 111
total cost for all works itemID Description stage (1) stage (2) total
1.00 Concrete footings (B250)
10,960.00 3,978.42 14,938.42
2.00 Internal plastering 680.00 246.84 926.84
3.00 Wooden door 220*90 1,350.00 490.04 1,840.04
4.00 Block 20*20*40 1,170.00 424.70 1,594.70
Eng: Eyad Haddad 112
unit price for each itemID Description unit quantity unit price total
1.00 Concrete footings (B250)
m3 78.00 191.52 14,938.42
2.00 Internal plastering m2 200.00 4.63 926.84
3.00 Wooden door 220*90
no 10.00 184.00 1,840.04
4.00 Block 20*20*40 m2 100.00 15.95 1,594.70
Eng: Eyad Haddad 113
Estimating & Evaluation
Lecture # 7
Eng: Eyad Haddad 114
Form of evaluation based on cost per unitID Description unit Unit price
1 Concrete footings m3 200
2 Block 20*20*40 m2 20
3 Wooden door 220*90 cm no 300
4 Internal plastering m2 6
Eng: Eyad Haddad 115
Cost per m2 of floor area(residential building)
Description (m2)
stores Ground floor
First floor
Structural elements
70 80 60
finishing 40 80 80
total 110 160 140
Eng: Eyad Haddad 116
Cost of housing unit = cost of m2 * the areas of the unit
Eng: Eyad Haddad 117
Analysis of quantitiesAnalysis to raw material quantities for example
:- Concrete : cement, water, aggregate, steel, - Cement in 1m3:- Mixing proportion (4:2:1) = 300kg, 6:3:1 =
200 kg, - 8:4:1 = 150 kg- 1m3 concrete = 80% aggregates, 40% sand- 1m3 (footings) = 60kg
Eng: Eyad Haddad 118
Miscellaneous works1m2 block (40*20*20) = 12.5 block1m2 tiling (25*25) = 16 1 sack of cement = 1 m2 plastering1 sack cement = built 100 blocks
Eng: Eyad Haddad 119
Estimation of Concrete price1 m3 concrete consist of :350 kg cement 1.2 ton aggregates0.8 ton sandPrice of mixing and pouring, transportationThe total price will be = 0.35
*300NIS+1.3*40+0.8*120+20 (mixing)
Eng: Eyad Haddad 120
Steel reinforcement In general and according to practices, the
following elements contains , Steel reinforcement
Footings = 60kg/m3Columns = 200 kg/m3Ground beams, stairs,= 80kg/m3Slabs = 17kg/m2
Eng: Eyad Haddad 121
Payment certificateFinancial Request for payment, prepared by
contractors, and approved by consultant / owner , describing the actual achieved works , by calculating the unit price by the quantity of item done.
It is important for the contractor as well as for the owner. For the contractor, he gets the value of works done, and save to him liquidity
for the owner , he become aware of the progress, achieved (actual) and planned, therefore, he can know if there is any obstacles or delay.
Eng: Eyad Haddad 122
Preparation of payment
Eng: Eyad Haddad 123
Types of payment certificates1- interim payment certificate2- final statement / final payment certificates
Eng: Eyad Haddad 124
1- interim payment certificateIt is request for payment, contains quantity
survey for the accomplished works , and other supporting details submitted by contractor over the progress period of the project, .
The amount of each request should not be less than 10% of the contract value or according to contract conditions
Eng: Eyad Haddad 125
Contents of the payment certificate1- Financial Payment Certificate: it is a survey
of the accomplished works (actual done), multiplied by its value according to the contract.
2- Measurements : 3- Drawings : as built drawings.
Eng: Eyad Haddad 126
Content of the Payment Certificate
It contains :1- summary, describing the commencement date,
project end date, in addition to other data as contract value, variation order, percentage of the accomplished works, value of the current payment, and due payment, any amount to be deducted for retention, Percentage of retention stated in the Contract Data to the total of the above, and Retention Money (if any) stated in the Contract Data; any amounts to be added and deducted for the advance payment , the deduction of amounts certified in all previous Payment Certificates.
Eng: Eyad Haddad 127
Payment Certificate2- total price of the accomplished works, and
percentage of the work done in relation to total project.
3- other supporting documents including the description of the items, progress in each item previously and also current, unit price, total percentage of the project progress.
Second : measurementsAnd it is table of actual quantity survey
accomplished, including item description, number, volume (length, width, height) and the total.
Eng: Eyad Haddad 128
Third : As build drawings, describing the details of the work done,
Payment Certificate
Eng: Eyad Haddad 129
Final payment certificateIt is called the final payment / certificate after
the primary taking over the project.The process of approval as follows:1- after taking over the project, final request
for payment is prepared, the contractor signed the request for
payment and the measurement sheet, and submitting it to engineer / owner.
2- to be paid the following documents should be attached :
Eng: Eyad Haddad 130
Copy of taking over certificate signed form the committee
Copy of the bid submitted from the contractor after considering the prices in the request for payment
defect liability securityAll tests resultsDeduction of the works that mentioned in the
taking over or any liquidated damages.Letters of project extension if it was
extended.
Eng: Eyad Haddad 131
Final payment certificateContents of the final payment certificate :Application for the requestList of the actual accomplished works and its
value.List of measurementsAs build drawings as it was approved from
the engineer.
Eng: Eyad Haddad 132
Lecture # 8
Eng: Eyad Haddad 133
Eng: Eyad Haddad 134
Table of reinforcement steel weights :
Diameter Wt of 1m length (kg) Area of section (mm2) Perimeter (mm)
6 0.222 0.283 1.8848 0.395 0.502 2.521
10 0.617 0.785 3.1412 0.888 1.13 3.76814 1.209 1.539 4.39616 1.58 2.01 5.02418 1.999 2.543 5.65220 2.468 3.14 6.2822 2.986 3.799 6.90825 3.856 4.906 7.8528 4.837 6.154 8.79232 6.318 8.038 10.04836 7.996 10.174 11.30440 9.872 12.56 12.56
Eng: Eyad Haddad 135
Weight of 1m of steel bar = (diameter, cm)2 * 0.617
Area of section = π r2
Perimeter (mm) = 2 π r
Eng: Eyad Haddad 136
Footing tableF1, C1F2, C2 F3, C3F4, C4
Eng: Eyad Haddad 137
Length of steel Bars :F1 : 1.5 x 1.3 x 0.45 m, Reinforcement
= 11φ12 , & 9 φ12F2 = 1.7 x 1.5 x 0.45 m,
Reinforcement = 13φ12 , & 11 φ12F3 = 1.9 x 1.7 x 0.45 m, Reinforcement
= 14φ12 , & 12 φ12F4 = 2.1 X 1.9 X 0.5 m, Reinforcement
= 16φ12 , & 14 φ12Concrete cover = 5 cm
Eng: Eyad Haddad 138
For F1: Length of steel in longitudinal direction: Ls = 1.5 - .05*2 =1.4 m In vertical direction at both sides = (0.45-0.05*2)/3 *2= 0.24 m The total for bar in longitudinal direction =
1.4+0.24+0.12*2=1.88 m The total length for all steel in longitudinal direction = length of 1
bar *number of bars in the direction = 1.88*11=20.57 m In traverse direction: = 1.3 – 0.05*2+0.12*2+0.24 = 1.68m Total length for all steel in the short direction = 9 *1.68 = 15.12
m The total in both direction = 35.69 m WT of steel for one foot type F1 = 35.69 * 0.888= 31.693 kg For all F1 = 31.693 *4 = 126.77kg.
Eng: Eyad Haddad 139
ID Item description
unit Diam. Length of bar
Total length
Wt of 1m
Total Wt
No. of footings
Total WT for all F1
drawings
1 Reinforcement steel for footings :
F1 Kg Φ12 In long direction = 1.88
In short direction = 1.68
1.88*11+1.68*9 =
35.69 m
0.888 31.693
4 126.77
Eng: Eyad Haddad 140
For column neck:
C1 = 25*60, 6φ14 (F1 : 1.5 x 1.3 x 0.45 m,
Reinforcement = 11φ12 , & 9 φ12)Length of one bar:Excavation depth = 1.5 m, floor
height = 0.48 mSteel leg = 1.5 – (0.05*2)/4 = 0.35
mThe total length = 1.5
+0.48+0.35+0.14 – 0.1 – 0.05 – 0.024 = 2.296 m
Eng: Eyad Haddad 141
For stirrups:If length of column section <60cm, one
stirrup is needed, but if it is > 60cm, two ties is needed
Concrete cover for column = 2.5 cmFor C1 = 25*60Length of stirrups= (0.6 – 0.05)*2 = 1.1mWidth of stirrup= (0.25-0.05 )*2 = 0.4mTotal length of the stirrup= 1.1+0.4+0.08*2
= 1.66m