Energy Performance Contracting

November 3, 2009

Performance ContractingDecember 11, 2009

Page 2: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Topics of Discussion

Why Look at Performance Contracting

Financial Options

Performance Contracting Process

Sample Improvements and Benefits

Implementation

Initial review – Johnson Controls

Page 3: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Performance Contracting Fundamentals

Page 4: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Participants

• NMU as the Customer• Environmental Services

Contractor ESCO as a partner

– Design/Build with Guaranteed Savings

– Competitively Bid work, open book– NMU participates in design, review

and fund disbursement

Page 5: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Performance Contracting uses guaranteed energy and operational savings to fund infrastructure

improvements and renewable energy projects

New Operational Costs

Annual Debt Service

Budget Neutral Approach

Current Operational Costs

Excess SavingsBefore After

Financial Fundamentals

Page 6: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Key Advantages

Low risk guaranteed energy savings – or ESCO pays the difference

Utilize professional service company to implement program

Maximize energy savings as soon as possible through improvements that decrease operational costs

Results: healthier, more comfortable and productive environments, including green solutions,

Savings finance debt service

Page 7: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

University Control

• University participates in project selection

• Construction draw schedule with release approvals by NMU

• ESCO is paid out of construction funds NOT as portion of savings

• Annual Measurement and Verification determined by service agreement between NMU and ESCO

Page 8: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

University Control

• Savings and performance are guaranteed

• Savings above guarantee stay with NMU

• Rebates, Grants and Incentives

– Identify any and all funds during business case analysis

– Document preparation and proposal writing services

Page 9: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Comprehensive Process

Competitive Process

Commitment to Provider

Project Cost, Savings and Performance are Guaranteed

First Payment at end of construction

Page 10: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Systems & Equipment Opportunities

HVAC– Re-Commissioning– Heat Recovery– Mechanical Equipment Replacement

Lighting – Perform a Detailed Lighting Audit– Standardize inventory– Lighting controls

Water Conservation– Domestic water – Non-Domestic water

Page 11: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Systems and Equipment Opportunities

Direct Digital Controls– Audit Existing Control Systems– Control Commissioning– Building System Monitoring

Performance Technologies– Utility tracking and analysis– Real-time reporting– Campus asset management

Page 12: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Additional Benefits

Page 13: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Current Status

• Verify Opportunity- completed 12/10/09

• Three Buildings Jacobetti Center ‘80, JXJ ‘69, UC ‘66

• HVAC/Controls. Electrical, H2O consumption

• Preliminary indication of 20% savings possible

Page 14: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Implementation Schedule

Dec 10-11 Preliminary analysisDec 23 Draft reportJan 5 Final report Jan 15 Issue RFQFeb 1 Proposals due from

ESCOFeb 7 Select ESCO PartnerFeb 7-May 1 Design, bid, orderMay 1- Aug 1 Implementation

Page 15: Energy Performance Contracting November 3, 2009 Performance Contracting December 11, 2009.

Questions

• Energy Conservation• Sustainability• Space Utilization• Performance Contracting