Energy from Waste - imia.com · 1 - Working Group members & organisation Aug 16: contact with EfW...
Transcript of Energy from Waste - imia.com · 1 - Working Group members & organisation Aug 16: contact with EfW...
Energy from WasteA Risk Management / Underwriting / Claims Handling Manual
50th IMIA Annual Conference 2nd to 6th September 2017
Munich
Simon Dejung, SCORAdam Casselman, SOMPO CANOPIUS
2
What you should take away from this presentation
Get an idea of the globally planned EfW projects
Get a feeling for O&M implications
Get a feeling for PML & MFL scenarios
Understand bottlenecks / obstacles & USP’s for EfW technology
3
AGENDA
EfW - Risk Management / Underwriting / Claims Handling Manual
2
3
4
5
6
Working Group members & organization, p.4
EfW Context, p.5-13
T&C, p.23/24
Structure of this paper, p.14-16
Failure mode & Loss Examples, p.17-22
Conclusion, p.25
1
4
1 - Working Group members & organisation
Aug 16: contact with EfW vendors & operators
Sept 16: 3 confcalls prior to IMIA Doha to define paper content
& appoint responsibles
Nov 16: 3 day EfW workshop with 3 plant visits
Jan 17: 50 pages submitted by the WG!!!
Feb 17: «boiled down» to 20 pages
6
2 - EfW Context - Plants in Europe, Asia, North America
WW approx. 2,200 EfW plants - capacity approx. 100m tpy
7
2 - EfW Context - Drivers for capital costs
small <200 MWth centrally located tailor made complex (FGT)
12
2 - EfW Context - Outlook +5% p.a.
Estimation: until 2024 new 550 EfW plants - capacity of 150 m tpy (Ecoprog, 2016).
14
3 - Structure of this paper (1/3)What How to useGive a risk management focused update on past publications
Provide links [9 links] to documents & new media where people get quicker an idea about certain topics
15
3 - Structure of this paper (2/3)What How to useGive risk engineering & assessment recommendationse.g. recommended repairs
Explain typical claims [19 claims]of each process step along the process flowe.g. boiler dray cooking
16
3 - Structure of this paper (3/3)What How to useRisk transfer element [15 failure modes] of each process step & mitigation measures along the process flow
Propose adequate policy wording [31 clauses cited] to manage a potential failure mode or mitigate risk, e.g. waste quality
23
5 - T&C - Policy Wording Implications
Multiple Insured Parties
Construction to Operation
Design, Defects and Maintenance
Business Interruption / Delay in Start-Up
Fortuity
24
5 - T&C - Specific Clauses
Waste Storage
Business Interruption / Delay in Start-Up
Inspection of Boilers / Scheduled Overhaul
Corrosion / Refractory
Waste Quality
25
6 - Conclusion
500 EfW plants expected until 2024 in APAC & EMEA (+5% p.a.)
O&M key for BI exposure
Boiler & Turbine-Generator drive PD & ALOP/BI
TCV’s < $500m will favour local underwriting & cession