EN-CV status

EHN1 Extension Project

Jérôme Rodary EN-CV-PJ 2015/08/06

Page 2: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.

Contents 1. Works in progress

• Cold boxes works (Vertex 1&2, CMS, ATLAS H8)

• Fan coil for barrack HNA 494

2. North wall dismantling • Dismantling works (water networks, ventilation,…)

3. Future design activities• Future design activities : GAr extraction system, general

ventilation

• User requirements missing

4. Schedule – CV activities

Page 3: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.

1. Works in progress

• Cold boxes Vertex & CMS-RD5 • piping networks completed

• components & instrumentation installed

• next step : pressure tests (before 2015/08/14)

• final step : functional tests with the CB connected !

https://edms.cern.ch/document/1527243/0.1

Page 4: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.

1. Works in progress

• Cold box ATLAS H8 (Saleve side) • piping & components supply in progress

• VIC done on 2015/08/05

• works will be done until end of august 2015

• New fan coil for barrack HNA 494 • cooling power 6,3 kW

• procurement launched

• installation in September 2015

Page 5: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.

2. North wall dismantling

• Works completed : • firefighting network interception

• chilled water disconnected barrack HNA 910

• mixed water station removed (north wall)

• old fan coil removed from barrack HNA 494

• raw water network interception (several places)

• Works to be scheduled before end of 2015 : • To be removed:

• ventilation ducts

• CW pipes & equipments

• drinking water loop

• To be rerouted: • compressed air loop

• demi water network

• raw water network

Specific care to asbestos !

Page 6: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.

3. Future design activities

• GAr extraction system : • pre-study in progress

• extraction flowrate to be frozen

• technical meeting scheduled on

friday 2015/08/07 regarding GAr system

GAr preliminary 3D model including extraction units & ducts

Page 7: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.

3. Future design activities

• Building general ventilation: • adding of 2 new ventilation units

• total flowrate: 210 000 m3/h

• total heating power: 2 440 kW

WP will be edited

Existing ventilation unit inside EHN1 building

Page 8: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.

3. Future design activities

• User requirements missing EN-CV needs technical data & requirements for designing the future extended networks as listed below:

• chilled water (for HVAC purposes)

• chilled water (for cooling down other some equipments)

• compressed air

• raw water

• demineralized water

• domestic water (hot and cold)

• fire fighting system

• gas extraction (other gases except GAr ?)

• ventilation for cryostat assembly clean room

• other… ?

Page 9: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.

4. Schedule – CV activities

Task Start DurationInstall new cooling system Barrack BE-BI in progress Mon 04.09.15 1 day

Reroute CMS cold box to raw water in progress Mon 20.07.15 1 week

Reroute Vertex cold boxes to raw water in progress Mon 27.07.15 1 week

Reroute Atlas cold box to raw water in progress Mon 28.09.15 1 week

Install scaffolding on Jura side (EN-MEF-SI?) to be advanced ? Thu 01.10.15 2 days

Cut drinking water (pipe loop already drained) to be advanced ? Mon 05.10.15 2 days

Cut Ventilation duct and pipe on Jura side Wed 07.10.15 1 day

Remove drinking water from NW (Asbestos) Thu 08.10.15 2 days

Page 10: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.

4. Schedule – CV activities

Task Start DurationDisconnect cooling system from CMS Barrack 902 Mon 02.11.2015 1 day

Install scaffolding on Saleve side (EN-MEF-SI?) Mon 02.11.2015 1 day

Cut and remove chilled water pipe Wed 04.11.15 1 week

Cut Ventilation duct and pipe on Saleve side Wed 11.11.15 1 day

Install new Chilled water pipe (Gallery + Barrack BE-BI) Thu 12.11.15 3 days

Connect the new cooling system for Barrack BE-BI Tue 17.11.15 1 day

Rerouted Gallery Pipes (2 demi water, 2 raw water, 1 compressed air) Mon 04.01.16 2 weeks