EMP Report Cisokan Final 15 March 2011

51
PT. PLN (Persero) Jl. Trunojoyo I/135 Jakarta 1212 Upper Cisokan Pumped Storage Hydro Electric Power Plant (1040MW) Environmental Management Plan Final 15 March 2011

Transcript of EMP Report Cisokan Final 15 March 2011

Page 1: EMP Report Cisokan Final 15 March 2011

PT. PLN (Persero) Jl. Trunojoyo I/135 Jakarta 1212

 

 

 

Upper Cisokan

Pumped Storage Hydro Electric Power Plant

(1040MW)  

 

 

 

 

 

 

 

 

 

 

Environmental Management Plan

 

Final 

 

 

 

 

 

 

 

15 March 2011

Page 2: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

Table of Content i

TABLE OF CONTENTS  

TABLE OF CONTENTS………………………………………………………..............………….......................................i 

LIST OF TABLE……………………..............…………………………………………………………………………………………….ii 

LIST OF FIGURE……………………………………………………………….............………………………….......................iii 

APPENDICES…………………………………………………………………….............……………………………………………….iv 

1. INTRODUCTION ……........................................………………….............………………………………………… 1 

1.1  PURPOSE AND OBJECTIVES .......................................................................................................... 1 

1.2  ENVIRONMENTAL APPROVALS .................................................................................................... 2 

1.3  EMP ORGANISATION AND STRUCTURE ....................................................................................... 2 

1.4  ENVIRONMENTAL MANAGEMENT PLAN ROLES AND RESPONSIBILITIES .................................... 7 

1.5  DESCRIPTION OF THE EMP SUB‐PLANS AND ENVIRONMENTAL MONITORING PLAN ................. 8 

1.6  APPROVALS ................................................................................................................................ 16 

1.7  DOCUMENT VERSION CONTROL ................................................................................................ 16 

2. PROJECT OVERVIEW……………………….............………………………………………................................… 17 

2.1  LOCATION ................................................................................................................................... 17 

2.2  PROJECT DESCRIPTION ............................................................................................................... 19 

3. ROLES AND RESPONSIBILITIES ……………………….............………………………………………...............… 22 

3.1  ROLES AND RESPONSIBILITIES FOR EMP IMPLEMENTATION .................................................... 22 

4. LEGAL ASPECTS ……………………….............………………………………………..........................................24 

5. KEY POTENTIAL ENVIRONMENTAL AND SOCIAL IMPACTS ..................................................... 26 

5.1  CONSTRUCTION ......................................................................................................................... 26 

5.2  INUNDATION AND OPERATION.................................................................................................. 26 

6. CONSTRUCTION: ENVIRONMENTAL AND SOCIAL MANAGEMENT ........................................ 28 

7. INUNDATION AND OPERATION ENVIRONMENTAL AND SOCIAL MANAGEMENT ................. 33 

8. ENVIRONMENTAL MONITORING FRAMEWORK ..................................................................... 35 8.1  SUMMARY MATRIX…………………………………………………………………………………………………………..…35 

9. COMMUNICATION AND REPORTING .............................................. ........................................ 36 

9.1  GENERAL COMMUNICATIONS MATRIX ...................................................................................... 36 

9.2  REPORTING ................................................................................................................................. 37 

10. CAPACITY AND TRAINING ........................................ ........................................ ....................... 38 10.1 CAPACITY .................................................................................................................................... 38 

10.2 TRAINING ................................................................................................................................... 38 

11. PLAN MONITORING AND REVIEW ........................................ ................................................... 40 

11.1 EMP REVIEW .............................................................................................................................. 40 

11.2 NEW IMPACTS AND ACTIVITIES ................................................................................................. 40 

11.3 CONTROL AND UPDATE OF THE EMP ........................................................................................ 41 

11.4 GOVERNMENT AGENCY REVIEW................................................................................................ 41 

12.  IMPLEMENTATION COST ........................................ ........................................ ....................... 42 

 

Page 3: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

Table of Content ii

LIST OF TABLE   

Table 1   List of Plans, Tasks, Sub‐Plans and the Roles and Responsibilities for Supervision, Review, Revision, and Implementation .............................................................................................  7 

Table 2.   Technical Details of Upper Cisokan Pumped Storage Hydro Electric Power Plant Project 

..............................................................................................................................................  19 

Table 3.    Roles and Responsibilities .......................... ......... ......... ......... ......... ......... ............. ..........  22 

Table 4.   Soil/Overburden Removal and Placement ...........................................................................  28 

Table 5.   Excavation and Blasting ........................................................................................................ 28 

Table 6.   Material Stockpiling .............................................................................................................. 29 

Table 7.   Tunnel and Power Station Construction ............................................................................... 29 

Table 8.   Concrete Manufacture and Use, and Cement and Flyash Stockpiling and Use .................... 29 

Table 9.   Fuel Storage and Use ............................................................. ..............................................  30 

Table 10.   Physical Cultural Resource Site Disturbance............................................................ ............  30 

Table 11.    Works In and Near Rivers ........................................................... .........................................  30 

Table 12.   General Construction Issues ........................................................... .....................................  31 

Table 13.   Impacts on Villages ............................................................ ..................................................  31 

Table 14.    Mitigation Standards and Measures for Minimizing Impacts  of the Scheme during 

Inundation and Operation ........................................................... ........................................  33 

Table 15.   Monitoring Matrix ................................................................. ..............................................  35 

Table  16.   Communication Matrix ............................................................ ............................................ 36 

Table 17.   Reports and Reporting Requirements .................................................... ............................   37 

Table 18.   Capacity Building ............................................................. ....................................................  38 

 

 

 

 

 

 

 

 

 

 

Page 4: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

Table of Content iii

LIST OF FIGURE 

 

Figure 1   Overview of the EMP Organization for the Pre‐construction Project Phases ......................  3 

Figure 2   Overview of the EMP Organization for the Project Phases (Construction and Operational 

phases)........................................................................................................... ......................  4 

Figure 3   Construction Phase EMP Framework .................... ......................... ......................... ..........  5 

Figure 4   Inundation and Operational Phase EMP Framework ................... ........................... ............ 6 

Figure 5.   Project Location Map .................................................. ............................ ............................. 18 

Figure 6.    Gunung Karang On Karang Sari Village And Sarinagen Village, Cipongkor Sub District, 

West Bandung Districts as Construction Material Source .............................. .....................  21 

Page 5: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

Table of Content iv

APPENDICES 

 

1. ANDAL, RKL and RPL 2007 Approval 

2. Location Maps 

3. Design Details 

4. TOR Environmental Supervision During Construction 

5. Environmental Specification For The Contractors 

6. Guidelines For Preparation of Social And Community Management Plan (SCMP) 

7. Physical Cultural Resources Management Plan (PCRMP) 

8. Biodiversity Management Plan 

9. Reservoir Land Clearance Plan 

10. Transmission Line Environmental Management Plan 

11. Quarry Management Plan 

12. Guidelines For Preparation of Operational Environmental  Management Plan 

13. Environmental Monitoring Plan 

14. EMP Budget 

Page 6: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    1 

INTRODUCTION  

 

 

This  Environmental Management  Plan  (EMP)  identifies methods  for  PT  PLN  (Persero)  (“PLN”)  to 

control  and/or minimize  the  environmental  and  social  impacts  of  construction  and  operational 

activities associated with the 1040MW Upper Cisokan Pumped Storage Hydro Electric Power Plant 

and 500kV Transmission Line (“the Scheme”).  

The EMP details: 

1. Roles and responsibilities of all parties involved in the project 

2. Key environmental and social risks 

3. Mitigation, management and monitoring for all parts of the scheme during: 

- Pre‐construction 

- Construction 

- Inundation 

- Operation 

4. Reporting responsibilities and methods 

5. EMP update processes 

A series of Appendices outline specific environmental management procedures for specific parts of 

construction and operation. 

 

1.1 PURPOSE AND OBJECTIVES 

Implementation of this EMP will ensure that PLN,  its contractors, consultants, and subsidiary 

companies  undertake  construction  and  operation  of  the  Scheme  with  due  regard  to 

protecting and providing for the natural and social environment.  In particular, PLN will: 

1. execute and comply with all relevant environmental legislation (see Section 4) 

2. fulfill all of the commitments in the PLN 1040MW Upper Cisokan Pumped Storage Hydro 

Electric Power Plant Scheme Consolidated Environmental Impact Assessment 2011;  

3. fulfill all of the commitments of the ANDAL, RKL and RPL by Indonesia Regulation; 

4. maintain    the environmental surounding the project ‐ 

5. promote  environmental  compliance,  awareness  and  understanding  among  employees, 

subsidiaries, consultants and contractors, through: 

- training; 

1

Page 7: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    2 

- assignment of roles and responsibilities under this EMP; 

- linkage of performance of environmental responsibilities to overall performance; 

- fostering a shared sense of responsibility  for environmental performance among all 

project participants; 

- monitoring  environmental  performance  and  implement  continuous  improvement 

actions as necessary; 

- ongoing interaction with the range of stakeholders involved in the project. 

6. Communicate  regularly  with  stakeholders,  including  government  institutions  and 

regulatory  bodies,  host  communities  and  interest  groups,  to  report  environmental 

performance, regulatory compliance and progress with the project, and to understand and 

address the concerns of the stakeholders. 

The  implementation of the EMP and the reporting and communication tasks required of PLN 

provide  government  institutions,  the  community  and  other  stakeholders  the  ability  to  stay 

informed of the project and the management of environmental and social  impacts, and allow 

participation  in  the process.   The EMP provides clarity and  transparency around PLN’s plans, 

responsibilities, legal obligations and achievements. 

 

1.2 ENVIRONMENTAL APPROVALS 

Environmental approvals of ANDAL, RKL and RPL  (AMDAL) were  issued  for  the project on 12 

April 2007, under the Environmental Management Act No.23 of 1997. A copy of the approvals 

is  included  in Appendix 1.  Environmental Approval of Supplementary ANDAL on quarry  and 

access road is an ongoing process and expected to be approved by end of March 2011.  

 

1.3 EMP ORGANISATION AND STRUCTURE 

This EMP is designed as an overriding document in a hierarchy of control plans throughout the 

project  phases  (Pre‐construction,  Construction  and  Operation).    The  EMP  sets  out  the 

framework  of  environmental  management  to  be  applied  to  the  project.  It  includes  the 

Environmental  Principles,  Communication,  Reporting, Monitoring  and  Review  Procedures  to 

which  all  parties  are  required  to  comply  with,  including  any  sub  plans.  The  EMP  of  pre‐

construction phase covers: the permits works, the land compensation and the resettlement as 

illustrated in Figure 1.  

The  works  during  pre‐construction  stages  is  not  covered  by  this  EMP  document,  but  it  is 

addressed  in  other  separated  document  namely  LARAP  (Land Acquisition  and  Resettlement 

Action Plan) and EMP for Access Road.

Page 8: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    3 

Figure 1 Pre-Construction Phase EMP Framework 

PRE-CONSTRUCTION

PLANT IMPLEMENTATION QUALITY ASSURANCE

CAPACITY & TRAINING

COMMUNICATIONS & REPORTING

PLAN MONITORING REVIEW AND REVISION

ENVIROMENTAL MONITORING

PERMIT

LOCAL GOVERNMENT’S PERMIT- PRINCIPAL PERMIT- LOCATION PERMIT

MINISTRY OF FORESTRY PERMIT

MINISTRY OF PUBLIC WORKS PERMIT

LAND ACQUISITION

SOCIALIZATION

CENSUS & MEASUREMENT

LAND ACQUISITION & PAYMENT

GRIEVANCE & MEDIATION

NEGOTIATION

RESETTLEMENT

RESETTLEMENT SITE CONSTRUCTION

CAPACITY & TRAINING

MOVEMENT & REPLACEMENT

MONITORING

GRIEVANCE & MEDIATION

LAND APPRAISAL

UPPER CISOKAN HYDRO POWER SCEMEENVIROMENTAL MANAGEMENT PLAN

(PLN Project Management, Enviromental Unit)

HYDROLOGY, WATER QUALITY, HABITAT

SUPERVISION OF CONSTRUCTION

 

The EMP sub‐plans of the Upper Cisokan Hydro Electric Power Plant  for the Project Phases 

during the Construction and Operational phases are: 

1) Construction and Workers’ Camp Management Plan. 

2) Reservoir Clearance Management Plan. 

3) Social and Community Management Plan 

Page 9: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    4 

4) Physical Cultural Resources Management Plan. 

5) Biodiversity Management Plan. 

6) Access Road Construction Environmental Management Plan. 

7) Transmission Line Environmental Management Plan (construction and operation). 

8) Quarry Environmental Management Plan. 

9) Operational Environmental Management Plan. 

i) Social and Community Relations Plan 

ii) Biodiversity Management Plan 

iii) Dam and Reservoir Management Plan 

iv) Watershed Management Plan 

 

The  overview of the EMP Organization for the Project Phases  during  the  Construction  and 

Operational phases  illustrates Figure 2. The detail of EMP  frameworks  for  the Construction Phase 

and the Operational Phases illustrated in Figures 3 and 4 respectively. 

 

Figure 2 Overview of the EMP Organization for the Project Phases (Construction  and Operational) 

 

Page 10: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    5 

Figure 3 Construction Phase EMP Framework 

 

Key: 

 

 

Page 11: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    6 

Figure 4 Inundation and Operational Phase EMP Framework 

 

 

Key 

 

 

Page 12: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    7 

The Environmental Monitoring Plan will cover all phases of the project, and will be updated as 

the project transitions from the construction phase to the Inundation and operational phases.  

During  the Construction Phase  it will sit under  the Upper Cisokan Hydro Electric Power Plant 

Scheme  EMP,  while  during  the  Inundation  and  Operational  Phases  it  will  sit  under  the 

Operational Environmental Management Plan. 

In addition, attached to this EMP (Appendix 4) is a Terms of Reference for the EMP Supervisory role, to be carried out by the Environmental Unit of Supervising Engineer. 

Any reference to ‘the EMP’ in this document means all procedures in this document and compliant sub plans. The relationship between these plans is illustrated in the figures above.  All plans must be consistent with the main plan above  it  in the hierarchy, and must also be consistent with plans at the same level. 

1.4 ENVIRONMENTAL MANAGEMENT PLAN ROLES AND RESPONSIBILITIES 

PLN, the Supervising Engineer, the Contractor and the  Independent Review Panel will all have responsibilities for supervising, implementing, reviewing and / or revising the various sub plans, as shown in the table below. 

PLN Project Management Team will be in PLN Hydro Java (PHJ). 

Table 1 List of Plans, Tasks, Sub-Plans and the Roles and Responsibilities for Supervision, Review, Revision, and Implementation

Plan  Key tasks or sub‐plans  PLN Project Management Team (Environmental Unit) 

Supervising Engineer (Environmental Unit) 

Contractor  Independent Review Panel

UCPS Environmental Management Plan   Supervision 

Review and Revisions 

Implementation      Review and expert advice

  Capacity Training  Supervision  Implementation     

  Plan Monitoring and Review  Supervision  Implementation     

  Communication / Reporting to external agencies 

Supervision  Implementation      

  Environmental Monitoring  Supervision  Implementation      

Construction and Workers Camp Management Plan  

  Supervision  Implementation   

  Traffic Management Plan    Supervision  Implementation    

Reservoir Land Clearance Plan    Supervision  Implementation   

Social and Community Management Plan  Supervision 

Revision 

Implementation  Implementation   

  Connectivity management  Supervision    Implementation   

  Physical Cultural Resources Management  

Supervision 

Implementation 

Implementation 

Supervision of Contractor 

Implementation   

  Grievance processes  Supervision 

Implementation 

Implementation      

  Community Relations  Supervision  Implementation  Implementation   

Page 13: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    8 

Plan  Key tasks or sub‐plans  PLN Project Management Team (Environmental Unit) 

Supervising Engineer (Environmental Unit) 

Contractor  Independent Review Panel

Implementation  Supervision of Contractor 

Biodiversity Management Plan  Supervision 

Revision 

 

Implementation     

Access Road Construction Environmental Management Plan 

Supervision  

Revision 

  Implementation   

Transmission Line Environmental Management Plan 

Supervision of Supervising Engineer 

Implementation 

Supervision of Contractor 

Implementation   

Quarry Environmental Management Plan    Supervision 

Revision 

Implementation   

Operational Environmental Management Plan 

Supervision  

Implementation 

Revision 

    Review and expert advice

  Capacity Training  Implementation       

  Plan Monitoring and Review  Implementation       

  Communication / Reporting to external agencies 

Implementation       

  Environmental Monitoring  Implementation 

Revision 

     

  Social and Community Relations Plan 

Implementation 

Revision 

     

  Biodiversity Management Plan  Implementation 

Revision 

     

  Dam and Reservoir Management Plan 

Implementation 

Revision 

     

Watershed Management Plan    Implementation       

1.5 DESCRIPTION OF THE EMP SUB‐PLANS AND ENVIRONMENTAL MONITORING PLAN 

Each of the sub‐plans and the Environmental Monitoring Plan are described below.  Either the plans, or terms of reference for the plans, are included in the Appendices to this EMP. 

1.5.1 Construction and Workers Camp Management Plan 

Objective: 

To minimize  the  potential  negative  impacts  of  construction  activities,  including workers’ 

camps and construction traffic, on host communities, wildlife and the environment. 

Description: 

Specifications of Environmental  for  the Contractor are  included  in Appendix 5.   The plan 

shall address the following: 

1. Design requirements and environmental protection measures for construction camps. 

Page 14: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    9 

2. Security and safety; 

3. Maintenance of camp facilities; 

4. Worker code of conduct 

5. Provision for camp followers; 

6. Erosion and sedimentation; 

7. Particulate emissions and dust management; 

8. Noise management; 

9. Earthworks, cut and fill slopes; 

10. Stockpiles and borrow pits; 

11. Waste management 

12. Pollution prevention; 

13. Construction traffic management; 

14. Vegetation clearance, revegetation and site restoration. 

Timing Schedule and budget: 

The detailed plan shall be in place at least three months prior to the start of construction. 

The budget is included in contractor’s contract 

Responsibilities: 

The Contractor shall be responsible for the preparation and implementation of the plans. 

The  Supervising  Engineer  shall  be  responsible  for  overseeing  the  implementation  of  the 

plan. 

1.5.2 Reservoir Land Clearance Plan 

Objectives: 

• To minimize biomass loss as a result of reservoir clearing. 

• Coordinate  timing  of  vegetation  removal  to  allow  benefits  to  local  communities  to 

salvage cut vegetation. 

• To minimize the impact on water quality during inundation and operation by removing 

vegetation and contamination sources such as latrines and rubbish dumps. 

• To protect the remnant forest during reservoir preparation. 

Description: 

The plan shall contain methods to: 

1. Delineate  the  areas  to  be  cleared  of  vegetation  to  avoid  unnecessary  cutting  and 

removal of vegetation, and to protect the remnant forest, riparian zones of tributaries 

and other useful habitats. 

Page 15: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    10 

2. Scheduling  in  advance  of  reservoir  filling  to  maximize  the  efficiency  of  vegetation 

removal and salvage, while minimizing the opportunity for vegetation regrowth, 

3. Implementing  dust  control  and  sediment  and  erosion  control  measures  to  reduce 

impacts. 

4. Coordination  of  plans  to  allow  local  communities  the  opportunity  to  salvage  cut 

vegetation. 

5. Procedures for the suitable capping or removal of contamination sources. 

Timing Schedule and budget: 

The plan shall be in place at least three months prior to the start of the reservoir clearance 

process. The budget has been allocated in LARAP budget calculation. 

Responsibilities: 

The  Contractor  shall  coordinate  the  preparation  and  implementation  of  the  plan.    The 

Supervising Engineer shall supervise the implementation of the plan. 

1.5.3 Social and Community Management Plan 

Objectives: 

• To maintain  communications with host  communities,  including providing  information 

about the project, and complaints and issues from the community. 

• To  inform the community about construction risks and  issues, and to  identify suitable 

mitigation and management measures. 

• To manage  any  disruptions  to  community  connectivity  during  construction  and  after 

reservoir inundation. 

• To  coordinate with  the  regard  to grievances and other  social  impacts  that may arise 

during the construction period. 

Description: 

A guidelines  for preparation of Social and Community Management Plan is  included  in Appendix  6.    The  plan will  detail  all  necessary  activities,  institutional  arrangements  and 

budget  requirements,  to manage,  avoid  and minimize  any  negative  impacts  on  the  local 

communities.   This will not  include the processes for compensation and resettlement that 

will be dealt with through the LARAP process.  

The plan will include the following programs / plans: 

1. Cultural and Environmental Education and Awareness Program  for workers  regarding 

host community traditions, lifestyles etc. and a workers code of conduct. 

2. Health  Program  to  manage  the  health  risks  between  the  workers  and  the  host 

communities. 

Page 16: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    11 

3. Community  relations  plan  to  document  procedures  for  communications,  grievance 

processes, changes to connectivity, and risks around reservoir filling, blasting and other 

construction‐related impacts etc. 

4. Traffic Management  Plan  to manage  the  risks  to  the  community  from  construction 

traffic. 

Timing Schedule and budget: 

The plan shall be in place at least one  months before the start of the construction,. 

The  budget  of  plan  preparation  and  implementation  is  included  in  Main  Contractor’s 

contract except the construction permanent bridge is included in LARAP budget calculation. 

Responsibilities: 

The contractor shall be responsible for development and  implementation of the plan.   The 

supervision  of  the  plan  is  the  responsibility  of  the  Supervising  Engineer,  along with  the 

responsibilities to supervise the construction implementation. 

 

1.5.4 Physical Cultural Resources Management Plan  

Objective: 

To prevent any inadvertence loss of physical and cultural resources, or graves and religious 

buildings, during construction and operation.  

Description: 

The plan includes methods to: 

1. Methods and responsibilities to protect resources during construction. 

2. Methods and responsibilities to relocate / remove graves and religious buildings as part 

of the resettlement and reservoir preparation process. 

3. Chance  Find Procedures which  identify what measures  should be  taken  in  the event 

that physical cultural resources are encountered. 

Timing Schedule and budget: 

The plan has been  completed.  

The budget is provided by PLN as attached in EMP appendix 14. 

Responsibilities: 

The further technical detail of plan (if any) will be prepared by Contractor and supervised by 

the Supervising Engineer (with approval / supervision by PLN PHJ).  The Contractor has the 

responsibility of  implementing  the protection of  resources and  following  the  chance  find 

procedures.    The  Supervising  Engineer  has  the  responsibility  of managing  relocation  and 

removal, by coordinating the process with the resettlement process. 

Page 17: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    12 

1.5.5 Biodiversity Management Plan 

Objectives: 

To  protect  and  enhance  the  remnant  forest  community  (both  the  habitat  and  its 

inhabitants) so that it is a self sustaining ecosystem and is not impacted by construction.   

To  protect  and  restore  the  reservoir  greenbelts  to  provide  additional  habitat  for    local 

fauna. 

 

Description: 

The TOR is provided in Appendix 8.  The plan shall include methods to:  

1. Further  evaluate  the  sustainability  and  vulnerability  of  the  remnant  habitat  and  its 

inhabitants. 

2. Identify of suitable management methods to achieve a self‐sustaining habitat. 

3. Implement construction‐effects management and monitoring. 

4. Identify  enhancement  methods  for  the  greenbelts  and  remnant  habitat  during 

construction, in preparation for inundation and operation. 

5. To develop green belt (of 5m vertical around each reservoir) with local forest

species to provide additional, connecting habitat. Development is to begin during

the construction period. The plan will be updated for the Inundation and Operational 

Phases, under the OEMP. 

Timing Schedule and budget: 

The plan shall be in place at least one month  prior to commencement of the main works. 

The budget is included in PLN budget 

Responsibilities: 

The  further  technical  detail  of  plan will  be  prepared  and  supervised  by  PLN  PHJ  (or  its 

delegate).    The  responsibility  of  implementation  is  the  Supervising  Engineer  (or  its 

delegate). 

1.5.6 Access Road Environmental Management Plan 

Objective: 

To minimize the adverse effects of road construction on the host communities, road users 

and the environment. 

To ensure that road safety issues are included in final road design and construction, to 

provide a safer road environment during construction. 

To educate the community about the risks and to address complaints during construction.  

Description: 

The plan has been written and includes: 

Page 18: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    13 

1) Methods to manage the potential impacts on the environment and communities from: 

a) Earthworks, vegetation removal, borrow pits, stockpiles and spoil sites 

b) Working in and near water courses 

c) Road works within existing road alignments, 

d) Storage and use of fuel, asphalt and other pollutants 

e) Workers’ conduct 

f) The disturbance of graves, religious buildings and physical cultural resources *) 

g) Noise and dust 

2) Design features to reduce the risk of traffic accidents near schools, religious buildings, 

bind bends, intersections and within villages. 

3) Physical Cultural Resources Management Plan.*) 

4) Alignment Sheets, illustrating the key risks and design features along the road route. 

Timing Schedule and budget: 

The plan has already completed. 

Budget of plan preparation and implementation is included in Contractor’s contract except 

for *) is provided by PLN 

Responsibilities: 

The  plan  was  written  by  PLN  and  further  technical  detail  of  plan  will  be  prepared 

implemented by the Contractor, and supervised by PLN. 

1.5.7 Transmission Line Environmental Management Plan 

Objectives:  

To mitigate the potential negative impacts from the construction and operation of 35km of 

500kV transmission lines on the environment and host communities. 

Description: 

A plan is included in Appendix 10.  It details the potential impacts and mitigation measures 

relating to: 

1) Location of the towers and transmission lines 

2) Earthworks 

3) Workers’ conduct 

4) Corridor vegetation clearance and maintenance 

5) Electricity transmission. 

Timing Schedule and budget: 

The plan has been completed   

Budget of plan preparation and implementation is included in Contractor’s contract 

 

Page 19: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    14 

Responsibilities: 

Further  technical detail of plan will be prepared and  implemented by  the Contractor, and 

supervised by Supervising Engineer. 

1.5.8 Quarry Management Plan 

Objective:  

To mitigate the potential negative impacts from quarrying activities on the environment and 

host communities. 

Description: 

A  plan  is  included  in Appendix  11.    The  plan will  address  the  specific management  and 

monitoring relating to the operation of a andesite quarry.   

It details the potential impacts and mitigation measures relating to: 

1) Land clearing and overburden stripping 

2) Blasting 

3) Sediment and erosion control 

4) Dust and noise 

Timing Schedule and budget: 

The plan has been completed. 

Budget of plan preparation and implementation is included in Contractor’s contract 

Responsibilities: 

Further  technical detail of plan will be prepared and  implemented by  the Contractor, and 

supervised by Supervising Engineer. 

1.5.9 Operational Environmental Management Plan 

Objectives:  

• To mitigate  the potential negative  impacts  from  the  inundation and operation of  the 

hydro electric power plant scheme on the host communities, downstream communities 

and the environment. 

• To ensure that environmental issues are monitored and managed throughout the life of 

the power scheme.   

• To manage restoration and rehabilitation of the remnant secondary forest and reservoir 

greenbelt areas. 

• To ensure suitable minimum  flows are discharged  from  the dams  to  the downstream 

river environments. 

• To ensure that the reservoirs are secure and the risk of injury or drowning is minimized. 

 

 

Page 20: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    15 

Description: 

The guideline of preparing  the plan  is provided  in Appendix 12.   The plan will document 

procedures to manage: 

1. environmental  flows  downstream  of  each  dam  during  inundation  and  operation (through the Dam and Reservoir Management Plan); 

2. fuel storage and handling; 

3. reservoir access and safety (through the Dam and Reservoir Management Plan); 

4. reservoir  greenbelt  and  biodiversity  management  (through  the  Biodiversity Management Plan); 

5. wastewater and solid waste management; 6. Community  relations  and  complaints  procedures  (through  the  Community  Relations 

Plan). Timing Schedule and budget: 

The plan will be completed six months before reservoir inundation by Supervision Engineer  

Most of the budget of operation is provided by PLN as mentioned in EMP Appendix 14. 

Responsibilities: 

The  further detail of plan will be prepared by Supervision Engineer and  implemented by 

PLN. 

1.5.10 Environmental Monitoring Plan 

Objectives:  

To document the monitoring and reporting procedures for potential environmental impacts 

of the inundation and operation of the scheme.   

To provide evidence for adaptive management of the reservoirs and downstream flows to 

address water quality, biodiversity and downstream water use issues. 

Description: 

A plan  is  included  in Appendix 13.   A detailed monitoring program will be  implemented to 

assess  the  impacts  from  inundation and operation.   The plan will also provide  for  further 

pre‐construction  and  pre‐inundation  baseline  monitoring.    Monitoring  locations  will  be 

based on baseline monitoring sites, control sites and impact sites.   

Monitoring under this plan does not  include the specific monitoring of treatment systems 

and  other  mitigation  and  management  measures  during  construction  that  will  be  the 

responsibility  of  the  Contractor  to  observe  and  measure  under  the  Construction  and 

Workers’ Camp Management Plan. 

Timing Schedule and budget: 

The plan  has been completed. 

Budget is included in Engineering Consultant’s contract 

 

Page 21: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    16 

Responsibilities: 

Environmental monitoring during pre‐construction and construction will be implemented by 

the  Supervision  Engineer. During  inundation  and  operation,  PLN  Environmental Unit will 

update and implement the monitoring plan.   

1.6 APPROVALS 

Relevant  works  shall  not  commence  until  the  document  has  been  approved  and 

conditions of the approval are addressed in the plan. Any subsequent changes to any part 

of the EMP or sub‐plans shall go through the same approval process. 

1.7 DOCUMENT VERSION CONTROL 

The plans are dynamic documents, which may be  subject  to  change or modification as a result of project development or changes on the sites. The review procedures for changes or other alterations are documented in Section 11. 

The  EMP  is  a  controlled  document;  subsequent  versions  shall  be  documented  in  this section, with a brief summary of changes. 

This document is Final version:   

This  EMP  supersedes  any previous  EMP documents  relating  to  the Upper Cisokan Hydro Electric Power Plant Scheme and the associated 500kV Transmission Lines.  

In the future, revision due to any changes will be conducted by PLN and is subject to World Bank’s approval. The revision will be identified as revision 1, 2, 3 etc. 

Page 22: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    17 

PROJECT OVERVIEW  

 

 

In order to meet growing peaking demands and to significantly improve reliability of the Java‐

Bali  power  system,  the  state  owned  power  company,  PT  Perusahaan  Listrik  Negara  (PLN),  is 

proposing  a  1040MW  pumped  storage  hydroelectric  power  scheme  in  the  Upper  Cisokan 

catchment, West Java Province.   

The Upper Cisokan Pumped Storage Hydroelectric Power Scheme comprises Upper and Lower  

reservoirs, each with an active storage of 10,000,000m3.  The upper reservoir will be 80ha when full, 

and the lower reservoir will be 260Ha when full.   

The upper reservoir discharges water to generate electricity during peak load (05‐11pm).  The 

stored water  from  the  lower reservoir  is pumped  to  the upper reservoir during off peak demand, 

after 00.30‐09.30am daily, using energy  supply  from  the base  load power plants.  In addition,  the 

proposed  project  will  provide  spinning  reserves  and  reactive  power,  as  well  as  other  auxiliary 

services  to  the power system.   A pumped storage scheme will allow more  flexibility  in  the power 

network,  and  provide  PLN with  a  cheaper method  of meeting  daily  peak  loads  and  demand  of 

auxiliary services. 

500kV  Transmission  lines  will  convey  electricity  from  the  power  station  to  the  Java‐Bali 

electricity network.    To  the north,  the  scheme will  connect  to  the Cibinong‐Saguling  line by  two 

separate lines and corridors.   

 

2.1 LOCATION 

The general  location of  the scheme  is shown  in Figure 5.   The site  is approximately 150 km  from 

Jakarta,  in West  Java province. The scheme  is  located  in  the hills  that  traverse west  to east along 

Java, the central and most populous island in the Indonesian archipelago.  

The  reservoirs are  located  in  the upper catchments of  the Cisokan River.   The headwaters of  the 

Cisokan River are located on the northern side of the backbone of hill ranges that run west to east 

along Java.  From the headwaters the Cisokan River flows generally from south to north as a major 

tributary of  the Citarum River, which also  flows  to  the  Java Sea on  the north  coast of  Java.   The 

project straddles two local authority Regencies, West Bandung and Cianjur. 

2

Page 23: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    18 

Figure 5. Project Location Map  

Project Location Map

Page 24: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    19 

2.2 PROJECT DESCRIPTION 

2.2.1 Installed Capacity 

The maximum  fall  height  between  the  upper  dam  and  the  power  house  is  301.5 m which  can 

generate  1040MW  of  electricity  at  a water  flow  of  432m3/s.  The  scheme  has  been  designed  to 

operate for 50 years. More basic project design map can be seen at Appendix 3. 

 

2.2.1 Reservoir Configuration 

The Upper Reservoir (approx. 80 Ha) will be fed by the flow of the Cirumamis River, Cipedes River, 

Cipateungteung River, River Cilawang, and Cidongke River.  The Lower Reservoir (260 Ha) will be fed 

by the Citengkong River, Ciawitali River, Cirumamis River and Cisokan River.  

 

2.2.2 Current Land Use 

The current land uses in inundation area are dry agricultural land, rice fields, some settlements and 

production forest. 

 

2.2.4  Technical Details 

The  technical details   of Upper Cisokan Pumped  Storage Hydro  Electric Power Plant Project    are 

described on Table 2.  

Table 2. Technical Details of Upper Cisokan Pumped Storage Hydro Electric Power Plant Project 

I. Plant Data Remarks

Rate Installed Generation Capacity – (MW) Maximum Input – Pumps (MW) Maximum Turbine Discharge (m3/s) Maximum Pumping Discharge (m3/s) Rated Net Head – generation (m) Generation duration at maximum output (hr/day) Pumping duration at maximum input (hr/day)

1,040 (260 MW x 4 units) 1,100 (275 MW x 4 units)

432 324 276 6.5

8.25

II. Reservoir Scale and Hydrology Upper reservoir Lower reservoir

River Catchment Area above the dam (km2) Reservoir Surface Area at high Water Level.(ha) High Water Level (HWL) (m) Low Water Level (LWL) (m) Effective Depth (m) Active Storage (m3) Total volume (m3) Average River inflow (m3/s) Design Flood (1/10,000 years) (m3/s) Bottom outlet – average – maximum discharge (m3/s) Reservoir greenbelt elevation (m)

Cirumamis River 10.5

80 796.5 777.5

19.0 10,000,000 14,000,000

0.4 230

0.5 – 0.96 796.5 -801.5

Cisokan River 355.0

260 499.5 495.0

4.5 10,000,000 63,000,000

14.9 1,100

7.0 – 13.0 499.5 – 504.5

Page 25: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    20 

III. Main Civil Construction 1) Roller Compacted Concrete Dams

Height (m) Crest Length (m) Elevation of Crest (m)

75.5 375

800.5

98.0 294

503.0 2) Bottom Gates

Normal discharge capacity (m3/s) Maximum discharge capacity (m3/s)

0.5

0.96

7.0

13.0 3) Centre Overflow Spillways

Maximum discharge capacity (m3/s) (to cope with 1/10,000 yr flood)

78

1,100

4) 2 Circular Headrace Tunnels Length (m) Inside diameter (m)

Approx, 1,220 (No. 1), 1,160 (No. 2)

7.4 5) 2 Surge Tanks

Inside Diameter (m) Height (m)

15.0

78 6) Embedded Steel Pipe Penstocks

Length (m) Inside Diameter (m)

475 ~ 530

2 (ID = 5.9 m), 4 (ID = 4.17 ~ 3.1m) 7) Underground Powerhouse and Transformer

Height (m) Max. Width (m) Length (m)

51.15

26 156.6

8) 4 Circular Tailrace Tunnels Length (m) Inside diameter (m)

190 ~ 270

5.2 9) 500kV Transmission Lines

Route 1 north 38 towers Cibinong – Saguling (km) Route 2 north 45 towers Cibinong-Saguling (km)

15.50 15.90

10 20kV Distribution Line Cianjur substation to project site (km)

30

 

2.2.5 Construction Materials 

Construction materials  include concrete aggregate material, natural fill and waterproof materials with a 

total  estimated  volume  of  2,133,808m3.  The  tunnel  excavation  material  will  be  disposed  at  three 

locations; Kampung Cipedes, Sukaresmi Village and Bojong Salam, Rongga Sub District. 

Aggregate  for  dam  construction will  be  excavated  from  the  existing  quarry  at  Gunung  Karang,  near 

Karang Sari Village and Sarinagen Village of Cipongkor Sub District, West Bandung Districts; ± 11 km due 

east from the project site.  

Page 26: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    21 

 

Figure 6.  Gunung Karang On Karang Sari Village And Sarinagen Village, Cipongkor Sub District, West Bandung Districts as Construction Material Source. 

 

2.2.6 Access Road 

The access road for the transport of materials, workers and equipment, will extend from Gunung Karang 

Quarry to the upper and lower dam sites. From Gunung Karang to Cipari, the 6.7 km of existing road will 

be improved. A new section of road will be built from Cipari to the lower dam (approximately 27 km).  

‐ Total length of the road plan   = ± 33.7 km 

‐ Improving existing road            = 6.7 km 

‐ Creation of new roads             = ± 27 km 

‐ Width of road       = 8 m 

‐ Total road alignment    = 15‐40 m (varied, based on the technical requirements) 

‐ Type of construction    = asphalt

 

 

 

 

 

 

Page 27: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    22 

ROLES AND

RESPONSIBILITIES  

 

 

3.1 ROLES AND RESPONSIBILITIES FOR EMP IMPLEMENTATION 

PLN remains responsible for the management and implementation of the EMP during construction, 

although  this may be delegated  to  the Supervising Engineer, as  representative of PLN.   Once  the 

reservoirs  are  ready  for  inundation  PLN  will  have  responsibility  for  the  management  and 

implementation of  the operational procedures of  the EMP.   General roles and responsibilities are 

summarized  in  the  table  below.    Roles  and  responsibilities  in  relation  to  the  preparation, 

implementation and supervision of the EMP are provided in Table 3.  

 

Table 3.  Roles and Responsibilities 

POSITION  RESPONSIBILITIES 

PLN PHJ (Environmental Unit)  1. Implementation, monitoring, and compliance of the Project EMP including the performance of contractors, subcontractors, staff and the Supervising Engineer. 

2. Reviewing the performance of the Project EMP and making any changes that may be appropriate for improving the environmental management of site activities. 

3. Compliance of the project activities with the EIA and conditions of the ANDAL approval. 

4. Implementation of the operational environmental management plans. 

Supervising Engineer  1. Preparation and implementation of various sub‐plans (as mentioned in appendices and in the construction, inundation and operation phase EMP Frameworks). 

2. Supervision of various sub‐plans implemented by the Contractor. 

3. Working in accordance with the EMP. 

4. Communicate and report incidents, monitoring and other information to PLN and the relevant government agencies as required. 

5. Making any recommendations to PLN that may be appropriate for improving the environmental management of site activities. 

Lead contractor  1. Preparation and implementation of various sub‐plans, consistent with this document. 

2. Maintain and keep all administrative and environmental records in accordance with the EMP and sub‐plans and the reporting of these records to the Supervising Engineer. 

3. Working in accordance with the project EMP. 

All staff, consultants and subcontractors 

1. Working in accordance with the EMP and sub‐plans. 

2. Making any recommendations to the Contractor, Supervising Engineer and / or PLN that may be appropriate for improving the environmental management of site 

3

Page 28: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    23 

activities. 

PLN Headquarter (Environmental Unit)  

1. Supervisor of environmental management and monitoring. 

2. Receipt and review of environmental management and environmental monitoring reports. 

Environmental Management Agency (BPLHD) Province of West Java 

Receipt and review of environmental management and environmental monitoring reports. 

Environment Agency West Bandung and Cianjur Districts 

1. Receipt and review of environmental management and environmental monitoring reports. 

2. Supervision of the EMF monitoring. 

Duty Labor Officer, West Bandung and Cianjur Districts 

1. Supervisor of local work opportunities 2. Receipt of local work opportunities report 

Head of Cipongkor, Rongga Campaka, Cibeber, Haurwangi and Bojong Picung Sub‐districts 

Supervision of socialization and priority employment of local workers 

Land affairs office of West Bandung and Cianjur Districts 

Supervision of environmental management. 

 

Note: 

Where an incident occurs with the risk of significant environmental harm or injury to people, the work has to be stopped to  ensure  that  the  harm  is minimized,  the  situation  is  safe  and  any  cleanup  or  preventative  action  is  implemented.  Where  this  is  identified by  the  Environmental Supervision Team,  this  should be done  through  the Project Manager  if possible.   If the Project Manager is not available, and there is an urgent need to prevent injury or environmental harm, then the Environmental Supervision Team (or other Site Supervision personnel, including the Contractor) have the ability (and the duty) to stop the relevant part of the work if required to prevent further significant harm or injury. 

 

Page 29: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    24 

LEGAL ASPECTS  

 

 

The  scheme  will  be  constructed  and  operated  within  the  national  standards  of  Indonesia  and 

international standards relating  to dams, power stations, reservoirs and  the  transmission of electricity.  

The following laws and regulations relate to the environmental management aspects in this EMP. 

 

4.1 LAW 

a) Republic of Indonesian Law No. 5 Year of  1960, concerning Agrarian Principles. 

b) Republic of  Indonesian Law No. 5 Year of 1990, concerning Conservation of Natural Resources 

and its Ecosystem. 

c) Republic of Indonesian Law No. 4 Year of 1992, concerning Housing and Housing. 

d) Republic of Indonesian Law No. 14 Year of 1992, concerning Traffic and Road Transportation. 

e) Republic of Indonesian Law No. 23 Year of 1992, concerning Health. 

f) Republic of Indonesian Law No. 32 of 2004 concerning Local Government. 

g) Republic of Indonesia Law No. No.26 Year of 2007, concerning Spatial Plan 

h) Republic of Indonesia Law No. 30 year 2009, concerning Electricity.   

i) Republic  of  Indonesia  Law  No.  32  Year  of  2009,  concerning  Environmental  Protection  and 

Management. 

 

4.2 REGULATION OF GOVERNMENT 

a) Government Regulation of Republic of Indonesia No. 7 Year of 1999 concerning Flora and Fauna 

Conservation 

b) Government Regulation of Republic of Indonesia No. 27 Year of 1999 concerning Environmental 

Impact Assessment.   

c) Government  Regulation  of  Republic  of  Indonesia  No.  41  Year  of  1999,  concerning  Forestry 

Regulation. 

d) Government Regulation of Republic of  Indonesia No. 25 Year of 2000 concerning Authority of 

Government and Province as Autonomous Territory 

 

4

Page 30: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    25 

4.3 PRESIDENT REGULATIONS 

a. Presidential Decree No 23 Year of 1990, concerning:\ Management of Protective Area. 

b. President  Regulation  No  36  Year  of  2005,  concerning  Land  Procurement  for  Development 

Implementation for Public Interest. 

c. President  Regulation  No  65  Year  of  2006,  concerning  Land  Procurement  for  Development 

Implementation for Public Interest. 

4.4 MINISTERIAL DECREE 

a. Ministerial  Decree  of  Mining  and  Energy  No.  103.K/MPE/1994,  concerning  Supervision  on 

Implementation of Environmental Management Plan (RKL) and Environmental Monitoring Plan (RPL) 

in Mining and Energy Sector. 

b. Ministerial  Decree  of Mining  and  Energy  No.  1899.K/MPE/1994,  concerning  Implementation  of 

Electrical Power Environment Monitoring. 

c. Director General  of  Electricity  and  Energy  Development  Decree Number.  75.12/008/600.2/1995, 

concerning  Implementation  Instruction  for  the  Supervision  of  Management  and  Monitoring  of 

Electrical Power Environments. 

d. Ministerial Decree of Environmental No. 48 Year of 1996, concerning Noise Level. 

e. Ministerial Decree  of  Environment No.  KEP‐299/MENLH/11/1996,  concerning  Technical Guidance 

and Social Aspect Assessment in the Arrangement of Environmental Impact Analysis. 

f. Ministerial Decree of Mining and Energy 975.K/47/MPE/99 concerning Free Space for High Voltage 

Network and Extra High Voltage Network for Electric Power Transmission. 

g. Ministerial Decree of Mining and Energy No. 1457 K/28/MEM/2000, concerning Technical Guidance 

of Environmental Management in Mining and Energy Sector. 

h. Ministerial Decree of Environment No. 17 Year of 2001,  concerning Business and/or Activity Plan 

Category which Obligatory to be covered with Environmental Impact Assessment. 

i. Forestry minister decree No. P.14/Menhut‐II/2006 concerning Lending and Using of Forestry Areas 

Guidance 

4.5 HEAD OF BAPEDAL DECREES  

a. Head  of  BAPEDAL  Decree  No.  056  Year  of  1994  concerning  Guidance  for  Important  Impact 

Measurement.   

b. Head  of  BAPEDAL  Decree  No.  299/BAPEDAL/11/1996  concerning  Technical  Guidance  of  Social 

Aspect Study in Arranging of Environmental Impact Assessment. 

c. Head  of  BAPEDAL  Decree  Number  Kep.  105  of  1997,  concerning:  Implementation  Guidance  for 

Environmental Management Plan (RKL) And Environmental Monitoring Plan (RPL). 

Page 31: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    26 

d. Head of BAPEDAL Decree     No. Kep‐124/12/1997 concerning Guidance  for Public Health Aspect  in 

Arranging of Environmental Impact Assessment.  

e. Head  of  BAPEDAL  Decree  No.  08  of  2000  concerning  Public  Involvement  and  Information 

Transparency in the Environmental Impact Assessment Process. 

f. Head  of  BAPEDAL  Decree  No.  09  of  2000  concerning  “Guidance  in  Arranging  of  Environmental 

Impact Assessment.

4.6 MINISTRY REGULATION 

a. State Minister of Environmental Regulation No. 08 Year of 2006 concerning Guidance for Arranging 

Environmental Impact Assessment.

4.7 LOCAL REGULATIONS  

a. West Java Province Regulation No. 3/1994, concerning First Level Provincial Spatial Order for West 

Java. 

b. Regulation  of  Cianjur  Regency  No.  1  Year  of  1997  concerning  Spatial  Restructuring  Planning  of 

Cianjur Regency. 

c. Bandung Regency Regulation Number 2 Year of 2001 concerning Land Use Permit. 

d. Regulation  of Bandung Regency Government No. 12  Year  of  2001  concerning Alteration  of  Local 

Regulation No. 1 Year of 2001 concerning Regional Space Arrangement Plan (RT/RW). 

e. Governor of West Java Decree No. 39 Year of 2001, concerning Water Quality Standard of Citarum 

River and Its Effluents.

4.8 CIRCULARS 

Circular  of  Minister  Population  and  Environmental  No.  31/SE/MENKLH/6/1987,  concerning 

Procedure of Environment Pollution and Damaging Case Undertaking 

Page 32: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    27 

 

 

KEY POTENTIAL ENVIRONMENTAL AND SOCIAL IMPACTS

 

The  following  is a  summary of  the key potential environmental and  social  impacts, as assessed  in  the 

Consolidated EIA Report. 

5.1 CONSTRUCTION Impact  Mitigation Measures 

Water quality and river habitat impacts from construction‐related sediment and pollution discharges 

Controls on construction methods. 

Potential for trees and endangered species in the remnant secondary growth  forest to be harvested or hunted by workers or otherwise disturbed by construction‐related activities 

Controls on workers behavior and access to the forest, through announcement board. 

The resettlement of households and the compensation for livelihoods for those that will lose land, houses and / or economic opportunities, or will suffer social dislocation 

Adequate consultation and compensation processes through the Land Acquisition and Resettlement Plan. 

The disruption to host communities from the influx of workers and construction related noise and air quality issues. 

Controls on workers behavior and camp management. 

Controls on construction work timing and methods. 

Increased risk to road users and pedestrians due to regular heavy vehicle use 

Controls on traffic management and timing of traffic movements. 

The benefits of short term employment and enterprise opportunities during the construction period. 

Offers of local labor where possible. 

5.2 INUNDATION AND OPERATION 

Impact  Mitigation Measures 

Changes to the downstream environment due to reduced river flow during inundation. 

Reservoir filling during rainy season 

Minimum discharges and fluctuating discharges from both dams during filling. 

Reduced river flow to downstream users during inundation. 

Reservoir filling during rainy season 

Minimum discharges and fluctuating discharges from both dams during filling. 

Consultation prior to filling. 

Water quality and habitat changes within the reservoir. 

Reduced downstream flow during low flow conditions, where scheme water demands are close to, or exceed, inflow. 

Minimum discharges from both dams as original inflow related to the season. 

Monitoring of flows to obtain an accurate record of low flow conditions and suitable minimum discharges from the scheme. 

5

Page 33: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    28 

Consulting with downstream users. 

Loss of habitat or endangered species from the remnant secondary growth  forest, due to changes in land uses and the operation of the power scheme. 

Implement further monitoring and a management regime through the Biodiversity Management Plan. 

Use the greenbelt restoration process to provide connecting secondary growth  forest habitat. 

Changing erosion and deposition in the Cisokan River, downstream of the lower dam, due to decreased sediment load. 

Surveying of river channels. 

Land instability with fluctuating water levels.  Engineered land stabilization measures implemented prior to inundation. 

Monitoring of slope stability. 

Loss of access to the river environments and land within the reservoir areas, and changes to community connectivity. 

Alternative fishing location. 

Provision of sanitary facilities 

Provision of bridges across the lower reservoir on previous Cisokan River location. 

Risks to people accessing the reservoir areas  Security and protection measures at both reservoirs to prohibit access. 

Consultation regarding risks. 

Flood risks downstream.  Emergency warning systems and consultation. 

EMF (Electro‐magnetic field) interference and health impacts  

Operations according to national standards and WHO standards. 

Regular monitoring. 

Complaints action process. 

 

Page 34: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    29 

 

CONSTRUCTION: ENVIRONMENTAL AND SOCIAL MANAGEMENT

 

 

Standard  mitigation  measures  and  standards  for  minimizing  the  key  environmental  impacts  during 

construction are shown in the following Table 4 until Table 13. 

 

Table 4. Soil/Overburden Removal and Placement 

ISSUE KEY PRINCIPLE / MITIGATION 

STANDARD MINIMUM MITIGATION MEASURE 

Generation of suspended solids from bare ground and runoff into watercourses 

Development activities outside of water bodies should not give rise to storm water containing elevated suspended solids under the majority of rainfall events. 

• No direct discharge of sediment laden water without treatment.  

• Earthworks and land clearance should be minimized and phased. 

  Provide treatment to achieve a reduction in suspended solids prior to discharge to a natural water course. 

• Storm water should be diverted around exposed work areas.  

• Any discharges to rivers should occur during high flow. • Stockpiling should occur at least 10m from a water 

course. • Compaction and re‐vegetation of exposed areas as 

soon as practicable.  • Provision of storm water cut off drains wherever 

possible to divert run off around work areas. Introduction of invasive species 

Fill material should not contain invasive species. 

• The use of imported fill shall be minimized. • Machinery should be cleaned prior to working on site 

to reduce the opportunity of the spread of weed seeds. Disturbance of land for fill / alluvial material. 

Soils and excavated rock should be reused where possible in the development – to reduce the need for spoil sites, borrow pits and / or the need to import fill.  

• Reuse stockpile soils and excavated rock before excavating new soils. 

Efficiency of control measures over time 

Control measures should continue to work appropriately throughout the construction period. 

• Earthworks control measures should be inspected and maintained in efficient operating condition over the construction period. 

 

Table 5. Excavation and Blasting 

ISSUE KEY PRINCIPLE / MITIGATION 

STANDARD MINIMUM MITIGATION MEASURE 

Noise disturbance of local populations 

Noise must not unreasonably intrude on village life. 

• Keep current lists of all noise producing machinery • This machinery operation to occur only during 

designated hours (to be confirmed by contractor in agreement with villages). 

• Blasting to occur at the same time each day, and/or a warning siren should sound prior to blasting 

Page 35: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    30 

ISSUE KEY PRINCIPLE / MITIGATION 

STANDARD MINIMUM MITIGATION MEASURE 

Vibration disturbance of local populations 

Vibration must not unreasonably intrude on village life. 

• Keep a current list of all vibration producing machinery.  

• This machinery operation to occur only during designated hours (to be confirmed by contractor in agreement with villages). 

• Blasting to occur at the same time each day, and / or a warning siren should sound prior to blasting. 

 

Table 6. Material Stockpiling 

ISSUE KEY PRINCIPLE / MITIGATION 

STANDARD MINIMUM MITIGATION MEASURE 

Runoff of suspended sediments from stockpiles 

Stockpiling activities should not give rise to storm water containing elevated suspended solids.   Provide treatment to achieve a reduction in suspended solids. 

• No direct discharge of sediment laden water without treatment. 

• Stockpiles should be compacted as much as practical and not be exposed for extended periods.  

• Stockpiles should be reused as soon as practicable. • Storm water should be diverted around stockpiles. 

Dust generation from stockpiles 

Dust must not cause a hazard or nuisance to village life. 

• Stockpiles should be compacted as much as practical not be exposed for extended periods. 

• Stockpiles should be reused as soon as practicable. 

 

Table 7. Tunnel and Power Station Construction 

ISSUE KEY PRINCIPLE / MITIGATION 

STANDARD MINIMUM MITIGATION MEASURE 

Contaminants in water discharged from tunnels and power station cavern during construction. 

No direct discharges of tunnel water to any water course. Provide treatment prior to discharge to achieve a reduction in suspended solids and neutralization of pH if necessary. 

• Settlement ponds and / or sediment infiltration gallery. • Monitoring immediately upstream and 50m 

downstream of the discharge with a clarity tube to estimate any effects on clarity; for nutrients to detect explosives residue and for pH. 

• Any discharges to rivers should occur during high flow. • Spill kits and emergency procedures should be used for 

spills of chemicals, fuels and oils and staff trained. 

 

Table 8. Concrete Manufacture and Use, and Cement and Flyash Stockpiling and Use 

ISSUE KEY PRINCIPLE / MITIGATION 

STANDARD MINIMUM MITIGATION MEASURE 

Contaminants in water discharged from concrete manufacturing, storage or use, and cement and fly ash stockpiling, including a rise in pH. 

No direct discharges to any water course. Provide treatment prior to discharge to achieve a reduction in suspended solids and a reduction in pH to between 7 and 9 pH. 

• Settlement ponds and / or sediment infiltration gallery. • Monitoring immediately upstream and 50m 

downstream of the discharge with a clarity tube to estimate any effects on clarity; for pH to detect alkali discharges. 

• Any storm water discharges rivers should occur during high flow. 

• Water to be reused where possible in the process. Procedures for handling of anhydrated cement material and wet cement to avoid spills. 

Community nuisances 

Noise and dust must not unreasonably intrude on village life 

• Concrete batching plants and other noisy / dusty equipment to be located as far as practical from villages. 

• Machinery to be maintained and effective noise muffling equipment to be installed. 

Page 36: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    31 

 

Table 9. Fuel Storage and Use 

ISSUE KEY PRINCIPLE / 

MITIGATION STANDARD MINIMUM MITIGATION MEASURE 

Pollution risk associated with the storage and use of fuels for all plant, generators and vehicles 

No oil, lubricants, fuels or containers should be drained or dumped to ground, streams or rivers.  Accidental spills shall be minimized, and procedures put in place to clean up the environmental damage. 

• Keep a current list of all fuels stored on site.  • Keep the Safety Data Sheet of all hazardous materials 

used on site. • Develop appropriate storage, transport and use 

practices to recognized standards.  • Diesel to be stored in truck tankers or in overhead 

tanks to a maximum of 5000 liters. • Diesel to be stored on flat ground, and at least 100m 

from a waterway. • Bonding to capture 100% of fuel must be placed 

around fuel storage areas. • All refueling of vehicles and plant to be done on flat 

ground.  • All significant vehicle and plant maintenance shall be 

undertaken offsite where possible. • Spill kits and emergency procedures should be used 

and staff trained. • There shall be no deliberate discharge of oil, diesel, 

petrol or other hazardous materials to the surrounding soils and waterways. 

 

Table 10. Physical Cultural Resource Site Disturbance 

ISSUE KEY PRINCIPLE / 

MITIGATION STANDARD MINIMUM MITIGATION MEASURE 

Finding and disturbance of previously unknown sites. 

No sites shall be disturbed once identified. 

• Follow the ‘chance find’ procedure. 

Demolition or damage to a surveyed physical cultural resource site  

No sites shall be disturbed or damaged. 

• Follow the PCR Management plan. 

 

Table 11.  Works In and Near Rivers 

ISSUE KEY PRINCIPLE / 

MITIGATION STANDARD MINIMUM MITIGATION MEASURE 

Sediment discharges arising from working in and near the river.  For blasting in or near the river, refer to the blasting issues, above 

Work in the wetted area of the riverbed should be minimized, and only in relation to the construction of the dams, or to insert culverts and bridges for stream crossings. 

• Stabilize works daily and prior to storm events.   • Works shall be minimized. • Diversion of the river around the work areas 

wherever possible.  • Culverts shall be placed in access tracks where they 

cross streams more than 3 metres wide and 0.5m deep. 

 

 

 

Page 37: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    32 

Table 12. General Construction Issues 

ISSUE KEY PRINCIPLE / MITIGATION 

STANDARD MINIMUM MITIGATION MEASURE 

Noise of machinery associated with construction activities 

Noise must not unreasonably intrude on village life.  

• Keep current lists of all noise producing machinery and noisy activities 

• This machinery operation to occur only during designated hours (to be confirmed by contractor in agreement with villagers). 

• Use of complaints register and procedures to address issues as they arise. 

• Concrete batching plants and other noisy equipment to be located as far as practical from villages. 

• Monitor ambient noise as per the Construction Environmental Monitoring Plan. 

Dust generation from construction activities 

Dust must not cause a hazard or nuisance to village life 

• Water shall be used to suppress dust. • Use of complaints register and procedures to address 

issues as they arise. • Concrete batching plants and other dusty equipment 

to be located as far as practical from villages. Vibration disturbance from construction activities 

Vibration must not unreasonably intrude on traditional village life. 

• Keep a current list of all vibration producing machinery and activities causing vibration.  

• Use of complaints register and procedures to address issues as they arise. 

Increased utilization of roads by traffic associated with construction activities 

There should be no significant increased risk to local populations from traffic associated with construction. 

• Traffic safety measures along the access road, including footpaths, signage and speed humps.  

• Training of locals regarding the hazards of traffic.  • Training of vehicle drivers regarding the driving risks 

through villages and along remote roads. • Use of complaints register and procedures to address 

issues as they arise Pollution risk activities occurring on site 

Develop appropriate storage, transport and use practices for storage and handling of mixed classes of dangerous goods in packages and intermediate bulk containers.  There shall be no solid or liquid waste disposal directly or indirectly to any water course (whether flowing or not). 

• Keep current lists of all potentially contaminating materials used on site.  

• Develop and implement appropriate storage, transport and use practices to recognized standards.  

• Solid waste shall be taken off site for disposal. • Spill kits and procedures should be available and 

training undertaken, for all hazardous or potentially polluting activities. 

Village concerns regarding construction impacts. 

Monitoring shall be undertaken to ensure villager’s concerns are recorded and addressed. 

• A complaints record shall be kept of all issues raised by villagers in response to construction activities. The record shall include responses by the contractor. 

 

Table 13. Impacts on Villages 

ISSUE KEY PRINCIPLE / MITIGATION 

STANDARD MINIMUM MITIGATION METHOD 

Deterioration of current quality of life and livelihoods. 

Villagers understand the staging and progress of the project, and when and how they may be affected. Villagers have the ability to communicate issues to PLN and contractors. Villagers have the expectation that issues will be addressed and resolved by negotiation. Villagers should enjoy the benefit of employment wherever possible. 

• Set up a communication network for discussing issues between PLN, Contractors and the villagers. 

• Ongoing consultation. • Provide opportunities for locals to work on 

the project. • Provide training opportunities for locals 

working on the project. 

Page 38: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    33 

ISSUE KEY PRINCIPLE / MITIGATION 

STANDARD MINIMUM MITIGATION METHOD 

Adequate compensation for lost land, assets and livelihoods and for resettlement. 

All parties receive fair compensation  • The LARAP process to address all compensation and resettlement issues. 

Health and safety risks from such activities as increased traffic, blasting, heavy machinery operating 

Health and safety risks to villagers are minimized. Villagers shall be adequately informed of all potential hazards to health and safety. Villagers have the expectation that issues will be addressed and resolved by negotiation. 

• Refer to the sections above discussing impacts from traffic hazards and blasting hazards. 

Nuisance issues such as noise, dust and vibration 

Nuisances shall be minimized. Villagers have the expectation that issues will be addressed and resolved by negotiation. 

• Refer to the sections above discussing nuisance effects. 

Traffic causing safety risks to road users 

Construction traffic will be managed to minimize the impact on existing road users. 

• Signage to be used to identify current risks to road users. 

• PLN and Contractors to discuss major traffic issues with village representatives prior to the event to discuss course of action. 

Sediment and other discharges affecting river water uses such as fishing and bathing. 

Sediment discharges to the river shall be minimized. There shall be no routine or deliberate discharges or any other substances. 

• Refer to the sections above discussing erosion and sediment control, and the discharge of pollutants to waterways. 

 

Page 39: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    34 

INUNDATION AND OPERATION ENVIRONMENTAL AND SOCIAL

MANAGEMENT  

 

Standard  mitigation  measures  and  standards  for  minimizing  the  key  environmental  impacts  during 

inundation and operation are shown in the following tables. 

 

Table 14.  Mitigation Standards and Measures for Minimizing Impacts  of the Scheme during Inundation and Operation 

A.   Reservoir Impoundment 

ISSUE  MITIGATION OBJECTIVE / STANDARD  MITIGATION MEASURE Increased levels of debris and decaying biomass 

• Debris shall not obstruct water intake devices • Maintain water quality within the range measured in baseline monitoring. 

• Follow procedures outlined in Reservoir Land Clearance Plan. 

Sedimentation  • Maximize  the reservoir’s lifespan  • Revegetation surround the greenbelt area,  

• Develop Watershed Management plan 

Alteration to fish species   • No net loss of fish species   • Monitor fish species Loss of downstream flow during inundation 

• Maintain residual flow from the upper reservoir at around 0.5m3/s, and provide for natural flushing flows whenever possible. 

• Maintain residual flow from the lower reservoir at around 6m3/s, and provide for natural flushing flows whenever possible. 

• Inundation will be done during rainy season. 

• Manage reservoir releases as per the Operational Environmental Management Plan. 

Changes in erosion and deposition patterns downstream of lower dam in the Cisokan River leading to loss or inundation of land. 

• Downstream livelihoods and access to land should be maintained. 

• Monitor erosion and deposition patterns and address compensation issues when / if relevant. 

Changes in water quality  • Maintain water quality within the range measured in baseline monitoring. 

 

 

B.   Dam Operation and Power Generation 

ISSUE  MITIGATION OBJECTIVE / STANDARD  MITIGATION MEASURE Changes in downstream flows. 

• Maintain downstream environmental flows at least the inflow, and no less than 0.2m3/s.   

• Maintain water quality in accordance with baseline water quality.  

• Ensure the integrity of downstream habitats 

• Monitor hydrological flows in the Cirumamis and Cisokan Rivers. 

• Implement policies and operation procedures to maintain environmental flows. 

Noise creation  • Noise levels should not affect local households, livestock or wildlife species. 

• Proper operation of facility equipment and sounds barriers 

Road traffic  • Operation vehicles shall not interfere or affect local villagers 

• Proper maintenance of vehicles  • Maintain the safety features of 

Page 40: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    35 

ISSUE  MITIGATION OBJECTIVE / STANDARD  MITIGATION MEASURE the access road. 

 

D.   Transmission Line Operation 

ISSUE  MITIGATION OBJECTIVE / STANDARD  MITIGATION MEASURE 

Illness, unease or other disturbances regarding electromagnetic field radiation. 

• The effects of EMF radiation on residential properties and workplaces should be minimized. 

• Regular monitoring of EMF. • Maintain a complaints service and follow up on any complaints, to the satisfaction of the complainant. 

 

Page 41: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    36 

ENVIRONMENTAL MONITORING FRAMEWORK

 

 

The  Environmental Monitoring  Plan  is  attached  in Appendix  13  that  details  the minimum monitoring 

requirements.   

 

8.1 SUMMARY MATRIX 

Table  provides a matrix of the parameters to be monitored, the project phase where monitoring 

is required, and the purpose of monitoring. 

 

Table 15. Monitoring Matrix 

PARAMETER 

TIMEFRAME AND TYPE OF MONITORING Preconstruction  Construction  Operation 

Baseline benchmarking 

Construction‐related impacts 

Pre‐operation baseline 

Post construction 

Operation‐related impacts 

River water quality           River habitat and macro‐invertebrates 

         

Fish           Construction discharges           Noise            Dust           Rainfall            Reservoir level            River flows           Groundwater levels           Biodiversity            Weed in reservoir           Physical cultural resources  Dam and land stability  Construction related impacts   

Key 

   Environmental impact monitoring 

  Climatic or operational monitoring 

Page 42: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    37 

COMMUNICATION AND

REPORTING

 

 

9.1 GENERAL COMMUNICATIONS MATRIX 

Table  16  sets  out  the  lines  of  communication  for  local  villagers,  potential  employees, workers, 

government  stakeholders and other  individuals  in  relation  to complaints or enquiries during  the 

construction of the scheme.  

The  following measures are proposed to be  implemented to assist with communication between 

the local villagers, contractors and PLN. 

 

Table  16. Communication Matrix 

STAKEHOLDER  MAIN INTEREST  MEANS OF CONTACT AND RELEVANT MANAGEMENT PLAN 

KEY CONTACT 

Land owners and villagers  

Disturbance from construction activities, environmental and social issues 

• Complaints/inquiries to village representatives  

• ‘One‐Stop‐Service’ on the site for villagers to raise issues, as per the grievance mechanism 

Supervising engineer 

  Information on hazards, including road use and traffic, blasting, vibration, etc. 

• Special consultative procedures with each village. 

Supervising Engineer 

Potential employees 

Employment opportunities 

• Advertise key positions in local papers. • Advertise at project site office. • Maintain register of potential employees • Recruitment of locals at project site office, and through word of mouth. 

Contractor 

General public  General interest, range of concerns 

• Media updates –press releases to local and regional papers as required 

• Complaints / inquiries routes 

PLN PHJ 

Government stakeholders 

Environmental and social  issues 

• Written reports and meetings  PLN PHJ 

Workers  Village issues, code of conduct for behavior, environmental issues 

• Tool box meetings • Memo’s and bulletins 

Supervising Engineer Contractor 

 

 

 

 

9

Page 43: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    38 

9.2 REPORTING  

External reporting by PLN is required as shown in Table 17. 

Table 17. Reports and Reporting Requirements 

TYPE OF REPORT  AND PURPOSE OF: 

FREQUENCY OF SUBMISSION REPORTING  SUBMIT TO 

EMP and any sub‐plans prepared under the EMP For approval prior to implementation 

As required, prior to implementation  • BPLHD West Java Province  • Environment Agency Cianjur and 

West Bandung Districts  EMP updates (including any changes in management and monitoring procedures) For approval, prior to implementation 

As required, prior to implementation  • BPLHD West Java Province  • Environment Agency Cianjur and 

West Bandung Districts  

Key changes in project activities that may affect the Environmental Approvals 

As required, prior to implementation  • BPLHD West Java Province  • Environment Agency Cianjur and 

West Bandung Districts  Incident report   As required, prior to implementation  • PLN Headquarter Non‐compliance report  Within 24 hours of incident (in 

accordance with incident procedures, which outline severity of incident that requires reporting) 

• BPLHD West Java Province  • Environment Agency Cianjur and 

West Bandung Districts  

Non‐compliance report  Within 1 week of a significant event  Otherwise annually for minor breaches that were remedied. 

• BPLHD West Java Province  • Environment Agency Cianjur and 

West Bandung Districts  Physical cultural resource chance find report 

Within 24 hours of finding an archaeological site, human remains or artefact 

• BPLHD West Java Province  • Environment Agency Cianjur and 

West Bandung Districts  Environmental monitoring reports  Annually  • BPLHD West Java Province  

• Environment Agency Cianjur and West Bandung Districts  

Other monitoring data   As Required   • BPLHD West Java Province  • Environment Agency Cianjur and 

West Bandung Districts  

 

Page 44: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    39 

CAPACITY AND TRAINING

 

 

10.1 CAPACITY  

This management plan shall be  implemented within PLN’s Environmental Management System.  

The management system provides PLN with the systems and structures to enable implementation 

of  the  plan,  monitoring,  reporting  and  delegation  of  roles  to  third  parties.  

 

10.2 TRAINING  

10.2.1 Management and Implementation/Operations of the EMP 

All  those responsible  for  the management and  implementation/operation of any aspect of  the 

EMP shall be adequately trained for their role. Evidence of training should be maintained on site, 

for inspection/ auditing purposes. 

The EMP document  include a training schedule, and procedure for keeping records. Records of 

training attendance and training programs shall be kept and be available for inspection/ auditing. 

PLN  PHJ  has  the  Environmental Unit  internally,  has  capacity  to  develop,  implement, monitor, 

evaluate  and  report  on  an  EMP  for  construction  and  operation  of  a  pumped  storage  hydro 

electric  power  plant  scheme.  External  training,  and/  or  the  use  of  third  party  contractors  or 

consultants may be required to develop the in‐house capacity. 

10.2.2 Management and Implementation/Operations of the Sub Plans 

Training  is  required  for all  staff undertaking work  in accordance with  the EMP. A  training 

schedule  shall  be  developed  for  each  sub  plan  to  the  EMP  and  procedure  for  keeping 

records. Records of training attendance and training programs shall be kept and be available 

for inspection / auditing purposes. 

10.2.3 Instream Environmental Monitoring and Interpretation of Results 

Instream monitoring and data  interpretation will be carried out by suitably qualified personnel. 

Where the supervising engineer or PLN do not have these skills, they may subcontract the work. 

10.2.4 Hazardous Substances Management and Emergency Procedures 

All  staff  involved  in  the handling and use of chemicals,  fuel and explosives must be  trained  in 

handling,  spill and emergency procedures. Evidence of  training  should be  kept  for  inspection/ 

auditing purposes. 

10

Page 45: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    40 

10.2.5 Concrete management 

All  staff  involved  in  the manufacturing,  transport and handling of concrete must be  trained  in 

handling, spill, dust, water management and emergency procedures.  

Evidence of training should be kept for inspection / auditing purposes. 

10.2.6 Sediment Control, and Control of Discharges 

Training will  be  provided  by  a  third  party,  or  provide  evidence  of  previous  training,  for  the 

construction, maintenance and monitoring of environmental protection and discharge treatment 

devices.  Evidence of training should be kept for inspection / auditing purposes. 

 

Specific capacity building is required in the following areas (Table 18): 

 

Table 18. CAPACITY BUILDING 

 

CAPACITY BUILDING FOR CONSTRUCTION PHASE 

Implementer  Training Scope  Purpose/Objective  Training Material  Trainees/ Audience 

Schedule & Budget 

Supervision Engineers  

Implementation and  Monitoring of EMP 

• The requirements of the EMP  

• How to execute the environmental requirements of the project,  

• How to supervise, monitor and audit 

• How non‐compliance with the EMP will be handled,   

• Key issues covered in EMP 

• The agreed environmental monitoring checklist,  

• The environmental monitoring form  

• Particular attention will be paid to the specific provisions in each contract’s technical specifications indicating how the EMP is to be complied with 

• Regulation 

• Environmental Supervision Engineers,  

• PLN staff, • Contractor’s Safety and Env.  Officer  

• Workers as part of the training given to the SEO 

• Construction phase. • The budget allocated in Supervision Engineers ‘ contract   

  • Health and Safety  

• The health and safety requirements mentioned in EMP  

• Health issues identified by the Contractors 

• Key issues covered in EMP 

• The agreed environmental monitoring checklist,  

• The environmental monitoring form  

• Health and safety provisions in each contract’s technical specifications  

• Regulation   

• Supervision Engineers,  

• PLN staff, • Contractor’s Safety and Env.  Officer  

• Workers as part of the training given to the SEO 

 

Page 46: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    41 

Implementer  Training Scope  Purpose/Objective  Training Material  Trainees/ Audience 

Schedule & Budget 

  • Hazardous Substances Management and Emergency Procedures: must be trained in handling, spill and emergency procedures 

How to handle, implement dan monitoring the  hazardous substances and emergency procedures 

• Key issues covered in EMP 

• General Hazardous Procedures 

• Hazardous Materials Storage 

• MSDS Requirement • Emergency procedures • Hazardous and Emergency Regulation 

All staff involved in the handling and use of chemicals, fuel and explosives (Contractor, Supervision Engineers, PLN) 

 

  • Concrete and Asphalt management 

How to implement Concrete and Asphalt management in handling, spill, dust, water and emergency procedures. 

• Key issues covered in EMP 

• Emergency procedures • Procedures to handle spill, dust and water. 

All staff involved in the manufacturing, transport and handling of concrete and asphalt (Contractor, Supervision Engineers, PLN)   

 

  • Sediment Control, and Control of Discharges  

• To manage the impact of Construction, and maintenance  

• To manage the environmental protection  

• To monitor discharge  

• Key issues covered in EMP 

• The control of discharge and Sediment Control procedures 

 

• The officers in charge of construction, maintenance and monitoring (Contractor, Supervision Engineers, PLN) 

 

Main Contractors  and Contractor  of Access Road 

• Safe control and driving of heavy road‐construction vehicles  

  

To ensure safe passage during and after working hours 

• Procedure of Safe control of road traffic 

• Procedure of driving the heavy road‐construction vehicles 

• The management of traffic officer 

• Drivers • Pedestrians in and around the project construction areas  

• Construction phase. • The budget allocated in Contractos ‘ contract   

  Training and awareness programs  

The safety risks regarding road construction and heavy vehicle operations. 

• Brochure • Leaflet  

The community, including school children 

 

  • Concrete and Asphalt management 

How to implement Concrete and Asphalt 

• Key issues covered in EMP 

• Emergency procedures 

All staff involved in the manufacturing, 

 

Page 47: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    42 

Implementer  Training Scope  Purpose/Objective  Training Material  Trainees/ Audience 

Schedule & Budget 

management in handling, spill, dust, water and emergency procedures. 

• Procedures to handle spill, dust and water. 

transport and handling of concrete and asphalt 

  • Hazardous Substances Management and Emergency Procedures: must be trained in handling, spill and emergency procedures 

How to handle, implement dan monitoring the  hazardous substances and emergency procedures 

• Key issues covered in EMP 

• General Hazardous Procedures 

• Hazardous Materials Storage 

• MSDS Requirement • Emergency procedures • Hazardous and Emergency Regulation 

All staff involved in the handling and use of chemicals, fuel and explosives  

 

  • Sediment Control, and Control of Discharges  

• To manage the impact of Construction, and maintenance  

• To manage the environmental protection  

• To monitor discharge  

• Key issues covered in EMP 

• The control of discharge and Sediment Control procedures 

 

• The officers in charge of construction, maintenance and monitoring 

 

PLN  • By External specialists (forest ecology, primate ecology, and fish ecology)  

Biodiversity management  

How to implement the biodiversity management plan 

• Biodiversity Management Plan, 

• Options, strategy of the Plan 

PLN Staff   • Prior to main Construction implementation • The budget provided in EMP App. 14 

PLN  • By archaeologists 

Physical Cultural Resources  

How to manage Physical Cultural Resources finding and the appropriate protection techniques and procedures for relocation of the documented religious facilities and graves 

• Procedure of Chance finding  

 

• Officers of Contractor 

• Officers of Supervising Engineer 

• PLN Staff 

• Prior to main Construction implementation • The budget provided in EMP App. 14 

TRAINING FOR INUNDATION AND OPERATION PHASE 

Implementer  Training Scope   Purpose/ Objective  Training Material  Audience  Schedule & Budget 

PLN   • Biodiversity  Understanding the theory and 

• Theory and practicalities of managing habitats for 

PLN Environmental 

• Prior to main Construction 

Page 48: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    43 

Implementer  Training Scope   Purpose/ Objective  Training Material  Audience  Schedule & Budget 

• By External specialists (forest ecology, primate ecology, and fish ecology) 

Management  practicalities of: • reestablishing indigenous habitats in greenbelt areas,  

• the protection of greenbelt areas and the reservoirs from occupation, for safety reasons.  

primates  • Biodiversity Management Plan  

• Reservoir Greenbelt Management 

Unit staff  implementation 

• The budget provided in EMP App. 14 

PLN  

By External specialists (ecologists and hydrologists) 

• River habitat management 

Understanding the theory and practicalities of: 

• ecology and habitat of rivers,  

• the habitat changes due to sediment and flow changes downstream  

• The methods to monitor habitat condition and change downstream of reservoirs.  

• Instream monitoring and data interpretation 

PLN Environmental Unit staff 

 

  • Environmental flows downstream 

Understanding the theory and practicalities of environmental flows downstream of each dam. 

• The relevant procedures for measuring and maintaining environmental flows 

All staff involved in operating the power station 

 

 

 

Page 49: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    44 

 

PLAN MONITORING

AND REVIEW

 

 

The  PLN  Environmental  Unit  will  periodically  monitor  and  audit  the  effectiveness  and 

implementation  of  the  plan whether  a  review  of  the  document  is  required.  The  audit  program  and 

procedures cover the scope, frequency and methods as well as the responsibilities and requirements for 

conducting audits and reporting results. 

The  frequency of audits will  reflect  the  level of  significance of environmental  impacts and  the 

results of previous audits. 

 

11.1 EMP REVIEW 

The  EMP  will  be  reviewed  periodically  to  evaluate  environmental  controls  and  procedures  to 

ensure  they  remain  applicable  to  the  activities.  Reviews  will  be  undertaken  by  the  PLN 

Environmental Unit, as follows: 

- The full EMP will be reviewed at least annually. 

- Relevant parts of the EMP will be reviewed following a reportable incident. 

- Relevant parts of the EMP will be reviewed following the receipt of an updated sub‐plan. 

- At the request of stakeholders, including Government Agency (BPLHD), Contractor, Supervising 

Engineer or the host communities. 

The EMP review will include analysis of the data collection and results, monitoring reports, incident 

reports,  complaints,  feedback  from  stakeholders,  Government  Agency  (BPLHD)  reports, 

consultation  meeting  minutes  and  training  records,  to  evaluate  the  effectiveness  of  the 

procedures. Site visits, interviews and other auditing methods may also be used. 

Updates to the EMP, following the review, will follow the procedure in Section 9.2. 

 

11.2 NEW IMPACTS AND ACTIVITIES 

All  new  activities  and  impacts  not  covered  by  the main  EMP  or  any  of  the  sub‐plans, must  be 

included and a new revision of the plan(s) produced through the update procedure. 

11

Page 50: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    45 

11.3 CONTROL AND UPDATE OF THE EMP 

The  EMP will  be  issued  as  a  ‘controlled  document’  to  all  relevant  staff  and  organizations.  The 

procedure  to  be  followed  to  control  the  issue  of  the  documents,  provide  a  review  of  its 

effectiveness and provide updates is as follows: 

1. Issued copies by the Environmental Unit of PLN will be numbered.  

2. The Environmental Unit will initiate a review of any relevant sections following modification 

to the Environmental Approval, issue of a new approval, or a change to internal procedures 

based on corrective actions or improvements in methodologies. 

3. The Environmental Unit will ensure the document is reviewed and that all sections are up to 

date. 

4. Any parts of  the EMP  that  require Government Agency approval will be  lodged with  the 

relevant agencies  and may not be implemented until an approval has been provided.  

5. All controlled copies will be updated following a change, coordinated by the Environmental 

Unit.  

6. All updated sub‐plans will be forwarded to the Environmental Unit  in order to update the 

relevant appendices in this plan.  

7. Updates will be communicated to all interested and affected stakeholders. 

8. Updates will be recorded in Section 1.7. 

 

11.4 GOVERNMENT AGENCY REVIEW 

All reports, registers and monitoring results must be made available to the Government Agency 

(BPLHD) on request. The Government Agency (BPLHD) must have the ability to audit the results 

and carry out duplicate monitoring or auditing at any time to ensure compliance with the EMP 

and any approvals issued. 

Where  the Government Agency  (BPLHD) does not have  the capacity  to audit, PLN shall ensure 

that an independent audit is carried out at the request of the Government Agency (BPLHD) and 

to their satisfaction. 

11.5 WORLD BANK REVIEW 

The implementation of EMP will be submitted quartely to World Bank for review. 

All EMP revision will be submitted to World Bank for review and approval, before it applied  

 

Page 51: EMP Report Cisokan Final 15 March 2011

Upper Cisokan Pumped Storage Hydro Electric Power Plant Environmental Management Plan

March 2011    46 

 

IMPLEMENTATION COST

 

 

Implementation  cost  for  environmental  management  (RKL),  environmental  monitoring  (RPL)  and 

capacity building  training are based on  the description of activities, methodologies  in accordance with 

Standard Operating Procedure (SOP), volume and time of events that approved in previous AMDAL 2007 

Study. Initial budget for these activities summarized in Appendix 14. 

 

 

 

12