EMCAL: project update - Italy - LNF - Frascati • Fixture production • Module assembly (proto) • WLS fibers processing • Lead procurement (proto) CT- Catania • APD characterization and test • SM Crates production Federico Ronchetti INFN, Laboratori Nazionali di Frascati

description

Federico Ronchetti INFN, Laboratori Nazionali di Frascati. EMCAL: project update - Italy -. LNF - Frascati Fixture production Module assembly (proto) WLS fibers processing Lead procurement (proto) CT- Catania APD characterization and test SM Crates production. LNF status. - PowerPoint PPT Presentation

Transcript of EMCAL: project update - Italy -

Page 1: EMCAL: project update - Italy -

EMCAL: project update- Italy -

LNF - Frascati• Fixture production

• Module assembly (proto)• WLS fibers processing

• Lead procurement (proto)

CT- Catania• APD characterization and test

• SM Crates production

Federico Ronchetti INFN, Laboratori Nazionali di Frascati

Page 2: EMCAL: project update - Italy -

LNF status• Module production

– design fixed recently (25-26 june)• Universal fixture production

– Completed: Base, tool-plates, sleds, cylindrical rails– Ongoing: center-blocks, load cell plates, cross-beam

• Vacuum chamber for WLS fibers processing– Magnetron gun finally delivered and installed– Chamber closed– Out gassing chamber (10-8 bar)

• WLS fiber polishing – First bundles ice-polished– Quality checks underway

• Lead procurement– Lead tiles for prototype delivered– Ongoing reshuffling (from by-measure to by-module packs)

Page 3: EMCAL: project update - Italy -

LNF universal fixture

Design by eng. Mario Del Franco

Page 4: EMCAL: project update - Italy -

4Design by Mario Del Franco

Module front plateIs the governing dimension

Fixture parts

Page 5: EMCAL: project update - Italy -

Fixtures realization progress

Picture not up-2-date: more components than shown have been machined

Page 6: EMCAL: project update - Italy -

U. Fixture• All components

materials for missing parts are at hand

• Design for proto is module finalized (WSU EMCAL meeting last 25-26 of June)

• Full fixture production (2xLNF) over by the end of July.

Page 7: EMCAL: project update - Italy -

Compression Table

Page 8: EMCAL: project update - Italy -

Fiber processing chamber

Page 9: EMCAL: project update - Italy -

At present: out gassing phase

Page 10: EMCAL: project update - Italy -

WLS fibers polishing

APD / light guide coupled side

Side to be aluminized

Page 11: EMCAL: project update - Italy -

Fiber module insertion tools

Modified WSU design by M. D. F.

Page 12: EMCAL: project update - Italy -

Lead tiles metrological tests

Tile thickness

Page 13: EMCAL: project update - Italy -

Lead tiles metrological testsHole diameter

Page 14: EMCAL: project update - Italy -

Lead tiles metrological tests

Inter-hole distance

Page 15: EMCAL: project update - Italy -

Short term schedule LNF TIME

Lead retooling mid July

Bond Paper Received from WSU

Fibers Aluminization Aug 1st

Test conical holes scintillator

AL2024 plates + pins + bushing

Aug 1st

(outsource?)

Plastic fiber collars Received from WSU

Washers ordered

Guiding rods From WSU (next week)

Black shroud From WSU (mid july)

Fixture full assembly Aug 1st

Page 16: EMCAL: project update - Italy -

CT work in progress

• Undergoing activity in CT:– EMCAL Super-Module Crate Prototype– Installation of universal module stacking

fixture (delivered by LNF)• Activity in CERN– Mechanical Integration of SM-crate– Load Tests

Page 17: EMCAL: project update - Italy -

The crate prototype

Page 18: EMCAL: project update - Italy -

• Design– blueprints– materials– safety

• Realization– The SM-

crate proto has been tested at 0° angle

SM crate load test @ CERN

Page 19: EMCAL: project update - Italy -

SM crate load test @ CERN

Dummy strip modules

Page 20: EMCAL: project update - Italy -

Additional testing phases

Page 21: EMCAL: project update - Italy -

Mechanical work summary for 2007

Work in progress @ CT:– Installation of 1 universal stacking fixture and 1

compression table.– Procurement of ancillary equipment (load cells,

amplifiers, etc)

Work in progress @ CERN:– Load Test of the SM crate proto at 90°– Insertion test SM– Construction of the insertion plane

Catania planning for 2007-8

(mechanical)

Page 22: EMCAL: project update - Italy -

Catania activity electronics, offline New lab space available for massive APD tests

Procured all the cards of the standard PHOS/EMCal electronic chain to be used for the APD test. This standard CERN set-up is almost ready (work is in progress on the software installation).

Draft for protocol for APD test established

First prototype for APD characterization as a function of the temperature is ready. Characterization of ALL 85 APD+CSP is done.

First version of track-matching ready and in CVS.

Page 23: EMCAL: project update - Italy -

Alice-jet1 Catania

First set-up for APD characterization

LED flasherBox cointaing APD

Page 24: EMCAL: project update - Italy -

Alice-jet1 Catania

First prototype for APD characterization as a function of the temperature

Standard –EMCal electronic chain

Light from LED flasher

Fluid from a chiller at a fixed temperaure

Page 25: EMCAL: project update - Italy -

Alice-jet1 Catania

Page 26: EMCAL: project update - Italy -

Alice-jet1 Catania

Barrel to EMCAL track matchingTrack matching efficiency and contamination for PHYTHIA minimum bias events

First version of track-matching ready and in CVS.

Presented to ACAT07

Aim: To clean the cluster sample for photon analysis (jets)adding PID information from EMCAL to high momentum charged tracks

Page 27: EMCAL: project update - Italy -

Catania planning for 2008

(electronics, offline)

• APD procurement

• Test setup optimization

• start of massive APD testing

• Test beam data and cosmic ray data analysis

• Track-matching optimization and simulation studies on jet and electron showers.