Electrical 2 EPR

download Electrical 2 EPR

of 11

Transcript of Electrical 2 EPR

  • 7/24/2019 Electrical 2 EPR

    1/11

    emonstration

    of Competencies

    Career Episode One

    The University

    Of

    Westminster UoW), Little Titchfield Street

    July 2011 - Present

    The project

    is

    a refurbishment of the UoW Little litchfield Street Campus,

    which mainly consists of creating a new 380 seat lecture theatre and a general

    re-design to the layout of main floors. The project value is approximately

    3.5M.

    Gifford were appointed by The University Of Westminster via traditional

    procurement

    I took on the project as a lead Building Services Engineer from the start of

    defining the scope of the project, with responsibility for developing the design

    from Stage C to Stage E I tender - overseeing the production of all technical

    information by the project team and ensuring all Q procedures were followed

    and documented.

    My

    first involvement

    on

    the project was to meet with the Client representative

    and Architect in order to develop an understanding of the key objectives and

    goals

    on

    this project. I then produced a report identifying a number of options

    for the scope of M E works, and also keys risks and opportunities for

    assessment by the

    Client and QS. In line with the UniversHy s aspiration of

    providing a sustainable building; I proposed the use of LED lighting throughout

    all

    refurbished areas. I presented the M E strategy to the Client and design

    team at the next meeting which met positive reviews, however some members

    of the team were still unsure and had concerns whether this new tech

    no

    ogy

    would be able to achieve the higher lux levels required

    in

    some of the rooms,

    and

    one team member thought that high frequency compact fluorescents

    would

    be

    the best solution. I demonstrated via a lighting calculation that 500

    lux average could

    be

    achieved

    in

    the double height lecture theatre with the use

    of

    high

    output LED downlighters. I also explained, through a previous detailed

    study produced by myself, that the use

    of LED

    technology combined with

    appropriate lighting control would create an innovative, energy optimised

    lighting solution

    and

    would have a short payback period. This strategy was

    subsequently adopted.

    I also requested a visit from the lighting manufacturer to a site where this

    4

    MCIBSE

    Competence

    Objective

    C1,C3, C4

    A1,A2, 82,

    B3,C2, E2

  • 7/24/2019 Electrical 2 EPR

    2/11

    specific type of luminaire is installed in order to for me to check the

    performance

    and

    the achieved lux levels. The results were positive,

    and

    I then

    carried my lighting calculations for all remaining spaces using Dialux lighting

    software to ensure I was meeting the CIBSE

    and

    British Standard guidelines

    for all different spaces.

    One

    significant technical challenge on this project was the lack of existing

    record drawings

    and

    information. I overcame this by carrying out a detailed

    photographic

    survey,

    and taking on site measurements of cable containment

    routes. Also, at the start of the stage E design, I was informed that the

    mechanical engineer will be off work for two weeks due to an illness, I

    thereafter decided to commission a 3D photographic survey through the main

    pinch

    points, an exercise which was carried by

    an

    external company and

    proved to be very useful to the mechanical engineer and ensured there was no

    delay

    to

    the issue of our design.

    Following the completion of the

    M E

    design, I took part in interviewing

    tendering contractors

    and

    carrying out a technical and commercial review of

    tender returns, identifying any non-compliances between the tender returns

    and

    the tender requirements

    and

    advising the client team

    as

    to quality of

    tenders received against the client's assessment criteria.

    Upon the completion of the first phase of works which was handed over to the

    University last summer, I carried out all site visits, snagging and attended site

    to witness the various electrical systems with the NICEIC electrical sub

    contractor and once satisfied, I signed the necessary forms. I assisted in

    preparing the Operation and Maintenance manuals with the contractor in order

    to

    reach

    practical completion for handover.

    I have been personally responsible for checking and documenting the quality

    and technical accuracy of all project deliverables in line with Ramboll QA

    policy.

    This included hosting a technical review meeting before the tender

    issue date with all the internal design

    team

    members. I took minutes

    and

    ensured it was logged onto our internal management system. I signed off all

    the check certificates for all documents and drawings.

    My other key responsibilities on this job include being the Gifford/Rarnboll

    representative at all design team meetings as well

    as

    being the main point of

    contact controlling all correspondence

    and

    technical output between our

    5

    8

    E1,

    C1

    C2,D2

    D1

    C4,D1

    C1,D3

    c

    c

    0

    0

    0

    0

    0

    D

    /

    \

    \___

    (. )

    l

  • 7/24/2019 Electrical 2 EPR

    3/11

    .

    building services team, Client team, architect, quantity surveyor, contract

    manager and . structural engineer. I have developed strong working

    relationships with all parties.

    Following the handover of the first

    phase

    I advised the universijy of

    Westminster that they consider replacing the lighting wijhin the toilet areas

    which

    were not part of the refurbishment

    works

    with efficient LED lighting. This

    was agreed with the Client and gave Rarnboll further work with the University,

    and now Ramboll are part of a framework

    signed

    with the university for future

    work.

    6

    B1

  • 7/24/2019 Electrical 2 EPR

    4/11

    Career Episode Two

    Venture

    Victory

    Academies Norwich

    June 2012-Present

    Both

    projects have a combined value of approximately 30M and procured

    under the National Academies

    D B

    Framework with Balfour Beatty. Victory

    Ormiston Academy is in Norwich and will provide a new three storey brick

    building, as

    well as retaining the recently completed teaching block. Venture

    Ormiston Academy is in Great Yarmouth; with works include the refurbishment

    of existing building and building a new extension.

    I took over the running of both these projects after the completion of the stage

    0

    due to both Electrical and Mechanical engineers leaving the company.

    I

    was

    responsible for managing a junior engineer and a team of technicians to meet

    the project requirements.

    After reviewing the stage D proposals and drawings

    on

    Victory Academy, one

    item came to my attention - the site-wide electrical servicing strategy was

    based on the main sub-station feeding the switchboard

    in

    the new main

    building which thereafter fed the surrounding existing blocks. Beartng in mind

    some of the existing blocks were the other side of the sub-station in relation to

    the new building. It was clear to me that this would cause major electrical

    distribution problems due to the number and size cabling required to meet the

    voltage drop limits and the problems terminating the cables onto the local

    LV

    panels within the mobile blocks.

    I devised a new strategy, where a new customer switch kiosk was

    to

    be built,

    from which new and existing blocks would be fed. After presenting the new

    MCIBSE

    Competence

    Objective

    C3

    A2 81

    proposed distribution strategy, the

    QS

    had concerns with the costs associated A1,81,82,01,

    with building the new switchroom kiosk

    and

    the introduction of a new 02 03

    switchboard, I then explained the new proposal will provide a saving

    in

    terms

    of quantity and sizes of cables required. After further discussions with the

    design team and academy, it was agreed that one of the existing building could

    be used to accommodate the main academy switchboard, instead of the

    customer switch kiosk originally proposed, this way I ensured there was no

    increase

    in

    cost.

    One

    of the main challenges on Venture Academy was the diversion of

    underground services due to the phasing and demolition works, as well as the

    7

    c

    0

    0

    0

    0

    0

    0

    )

    j

    )

    )

    (

    I

  • 7/24/2019 Electrical 2 EPR

    5/11

    new building being built in place of the part demolished existing, while linking

    the retained element of the building either side . I was involved in regular on

    site meetings and site walk-arounds with the contractor, the structural

    engineer and the architect where we've agreed the best routes, whilst making

    sure this wouldnt affect the running of the school.

    I used Amtech software to create a model of the existing

    LV

    electrical

    distribution network, and then modified the model to incorporate the new loads.

    I was able to use this software to size all the new submains cables

    &

    final

    circuits and discrimination of the protection devices.

    Whilst designing the external lighting scheme for Victory, the architect pointed

    out that further to discussions with planners and local residents, the car park

    lighting would have to be controlled to avoid any spillage to the surrounding

    residents areas in-order to comply with the ILE guide Guidance Notes For The

    Reduction Of Obtrusive Light . Therefore, I specified lighting columns complete

    with a back light shield which controls the light spillage.

    During the design stage, I carried out a Designer's CDM risk assessment to

    cover those aspects of the design which have risks attached and which a

    competent contractor would not be aware of. These formed part of the growing

    Healthy & Safety Plan being gradually compiled by the CDM coordinator. I then

    took part

    in

    CDM workshops alongside the rest of the design team in order to

    identify ways in which residual risks could be eliminated.

    Another challenging aspect of the project was that Ramboll's fee for both

    projects was very tight. As a result I have been reviewing the financial 'health'

    of the job using our Maconomy financial reporting software. I've also set up

    reviews with the Project Associate to flag up any potential issues

    on

    the job.

    I also carried out the change process throughout the post-tender period using

    the appropriate Change Request forms which I obtained from the company's

    internal website. I was also involved

    in

    negotiating the value and programme

    for delivery of the associated re-design works with the Client and PM.

    With both projects running parallel to each other on site, significant demands

    were placed upon y team as well as working to a compressed design

    program. I overcame this by agreeing a phased delivery of drawings and

    documents to meet their requirements while also negotiating an extension to

    the design period.

    8

    A2,82,C1

    82,83

    E1,E3

    C1,D2,E2

    C2

    D1,D3

    C1 D1 ,D3

  • 7/24/2019 Electrical 2 EPR

    6/11

    Career Episode Three

    Thetford cademy

    October 2 11 Present

    Predominantly new build,

    an

    18M government funded scheme capable of

    accommodating up to 2,050 pupils by tts completion in September 2013. This

    project

    is

    one of four academies procured through the same D B framework

    contract with Gifford appointed as Building Services and Sustainability

    consultants by the Main Contractor (Balfour Beatty Construction Limited). The

    end client is Norfolk County Council.

    Works include the provision of new sports pitches and external games areas; a

    public sports hall; a new sixth form centre; an entrance cafe/reception area

    and an outdoor amphitheatre located next to the new drama and assembly hall

    facilities. Low energy features include a biomass plant run on wood pellets and

    a series of photovoltaic panels to convert sunlight into electricity.

    On this project, our team had a new graduate engineer, Michael,

    and

    I decided

    I would use this project

    as

    training for him, and at the same time try and make

    use of his time to help me on the production of the design. I first started by

    introducing him into all aspects of the design process. Thereafter I after I've

    showed him on how to carry out cable sizing calculations; I assigned him with

    his first task of calculating all lighting and power final circuits on the job, which

    I've checked and carried our QA review in accordance with the company's

    standards. I also asked him to complete a number of the drawings, this

    exercise proved to be very effective, as it allowed me to focus

    on

    other

    elements

    of

    the design such as report wrtting and producing schedules.

    During the design stage and whilst drawings were being produced by the C D

    team, I wasn't satisfied with the quality of the work which was given back

    to

    me. I suspected that in-house checking by the CAD team was not taken place.

    Even though I was under pressure to meet deadlines, I refused to let drawings

    go out with errors or bad presentation, so I exercised my usual professional

    care at all times. To try and increase the quality, I spoke to the C D manager

    and encouraged

    him

    to ensure his team evaluated and double checked their

    work before passing back to the engineers. Once this checking had been

    put

    into place, I noticed considerably fewer problems.

    9

    MCIBSE

    Competence

    Objective

    C1,C3

    C2,C4,E1

    c

    0

    0

    0

    0

    0

    0

    )

    l

    u

    }

    _)

    _)

    )

    \

    \

    . '

  • 7/24/2019 Electrical 2 EPR

    7/11

    The architect

    on

    this project had a particular interest in the lighting scheme,

    and alter the issue of our design, he's requested me to change a the proposed

    linear light fitting on all stair cases to a circular 2D light, one's he's used on his

    previous job. However, alter reviewing the performance of the proposed fitting,

    it was clear

    to

    me that the efficacy figure (luminaire lumens per circuit watt) did

    not

    achieve the requirements as listed on part L2A. After reviewing a number

    of other lighting manufacturers, me and the architect agreed on the use of an

    alternative fitting, that he was happy with aesthetically and I ensured it met the

    required performance.

    A requirement imposed by the client and local council is to achieve BREEAM

    rating of very good as well as a 10% carbon off

    on

    site via on-stte renewable

    technologies.

    One of the technologies outlined by the performance specification was the use

    of a photovoltaic system

    on

    the roof to feed 50kWp into the academy's main

    LV panel. This was the first time I encountered this technology and as a result I

    had to carry out extensive research to understand the system via technical

    reports and talking to manufacturers. I've also set up an in-house CPD on the

    subject, which was very useful to the entire team as many of us haven't come

    across this

    on

    their jobs.

    Once the M&E installation had progressed sufficiently, I carried out snagging

    inspections on stte by comparing what was designed against what was

    installed, commenting

    on

    the qualtty of installation and progress against

    programme, as well as taking photographic,evidence. One of the major snags

    I noticed that the M&E sub-contractor hasn't provided cross equipotential

    bonding between cable containment trays and trunkings, as well riser gratings.

    This could have had serious consequences.

    With the project handover approaching next month I contacted the Contractor

    A2,E1,E3,D2,

    D3

    E3

    A1,A2,E4

    B3,D1,E2

    well in advance of this date, and asked him to prepare

    an

    agenda so that I

    C

    could witness all the Electrical systems in one day, as tt talkes me the entire

    day to visit site.

    10

  • 7/24/2019 Electrical 2 EPR

    8/11

    Career Episode Four

    69 Grosvenor Street London

    November

    2012

    Present

    My role

    on

    this project is the lead electrical engineer with the reasonabiltly of

    overseeing the electrical design from RI8A stage D through

    to

    stage

    ElF

    including preparing a full package of tender drawings specifications

    schedules and COM risk assessment.

    One significant technical challenge on this job is working within the constraints

    of the existing building whilst striving to maximise the leasable office space. I

    overcame this by vistting site surveying and recording existing risers/voids

    which could be re-used and encouraged the design team

    to

    have early stage

    reviews of the electrical services implications.

    I undertook detailed research and investigation into modern technologies to

    ensure that the electrical distribution strategy was designed in such a manner

    that there would be minimal space requirements for the electrical intake rooms

    electrical risers and main

    V

    swttchroom. One main example

    on

    the current

    available new technologies; was the specification of the main distribution panel

    board in place of the classic switchboard an exercise which ensured at least

    10m2 of floor area was available to be le t as part of an office.

    MCIBSE

    Competence

    Objective

    C1 E2

    C2

    A1 A2

    During a design team meeting the client requested to install a number of floor 82 83 01 02

    boxes within the proposed office spaces. This was a difficult exercise as I knew 3

    that there will be no floor void provided within some of these rooms. I then

    decided

    to

    use the complete 3D cloud model

    lor

    the building

    in

    order to

    understand the floor build up where I managed to position the floor boxes in

    between the existing floor joists.

    However I explained

    to

    the design team that the existing depth within joists will

    only be able

    to

    accommodate 65mm deep floor-boxes which are only capable

    of using Cat. 5 structured cabling and not Cat. 6 due to the cable bending

    radius test. Thereafter I recommended that the use Cat 6. Infrastructure will

    maximise the flexibility and attractiveness of the office space to potential

    tenant. Alter attending a number of workshops between myself the structural

    engineer

    and

    the contractor it was decided to increase the floor void by

    Bmm 81

    in

    order

    to

    installed the 85mm deep boxes via providing feather boards that sit

    on

    top of the joists.

    11

    U

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    u

    ( -

    \

  • 7/24/2019 Electrical 2 EPR

    9/11

    After the pre-tender cost plan had been prepared, the project appeared to be

    over budget and I prepared some Value Engineering options for the Client to

    choose from, and put together some estimated costs. As I had only provided

    the

    bare minimum requirements

    in

    the first place, this was quite a difficult

    exercise. The Client eventually chose to reduce the CCTV coverage within

    leasable office space, saving approximately 1 Ok

    Whilst attending an accredited CIBSE seminar on circuit protection; the

    speaker referred to a clause in BS 7671 regulation which requires all protective

    devices to be connected to conductors intended to operate at a temperature

    not exceeding

    70

    C. However, I knew that the standard maximum temperature

    for XLPEISWA cables proposed

    on

    the job is

    90

    C. I carried further

    investigation and obtained a specialist input from Schneider Electric

    on

    how to

    ensure the above is achieved, and it was via reducing the rating of the circuit

    protection to match the current carrying c p c ~ y of the cable

    at 70 C

    (instead

    of

    the current carrying capacity at the maximum temperature of

    90

    C).

    Thereafter, I specified adjustable setting MCCBs, and issued a schedule

    indicating the maximum required design current for

    each

    of

    the

    protective

    devices.

    I m also currently responsible for regular site inspections, attendance at

    progress meetings, responding to technical RFis and checking and approving

    installation drawings.

    2

    B3

    A1,A2,E4

    C4

  • 7/24/2019 Electrical 2 EPR

    10/11

    General Work Practices xtra Curricular ctivities

    I was chosen from Gifford (now Ramboll) to represent and attend the CIBSE

    national conference

    in

    April

    2011

    in London. Following this; I gave a

    presentation to y colleagues summarizing the

    main

    key notes discussed and

    raised at

    the conference using PowerPoint.

    I have a keen interest

    in

    process improvement and regularly contribute

    suggestions to our internal Best Practice team based upon my own

    experience

    and

    innovation including various calculation

    and

    project

    management tools.

    I

    always

    try

    and further

    y

    development

    on

    technical knowledge

    and

    keep

    up

    to

    date wnh all new technologies out

    in

    the market. I do this by attending

    regular technical seminars and speaking to fellow engineers and sales

    representatives from various manufacturers. I also regularly read technical

    magazines including the Building Services Journal magazine, lET magazine

    and various others. This gives me

    the

    knowledge to speak to

    y

    clients,

    architects, developers and other engineers about possible low carbon

    technologies and sustainable solutions.

    I

    have been involved

    in

    training many engineers to become proficient

    in

    the

    use

    of Amtech Pro-Design

    as

    well as making a change in the format

    and

    the

    way of issuing distribution board and sub-main schedules externally. This was

    a battle at the start, when Gifford merged with Ramboll,

    as

    the more senior

    Ramboll engineers used excel spread sheets for that, and

    I

    explained that a

    complete LV model is built for the job as

    it

    should

    be)

    then this information can

    be

    exported directly from Amtech without the need for the excel spreadsheets.

    This has now been agreed

    and

    used as

    the

    official way of issuing distribution

    boards schedules externally.

    During early stages of y career, I was

    the

    person responsible for organising

    relevant

    CPD

    accredited seminars on a weekly basis.

    13

    02 03

    A2,B1

    E3,E4,A2

    B2,C3,E4

    E4

    c

    c

    c

    c

    c

    c

    c

    c

    c

    c

    C;

    c

    c

    (

    (

  • 7/24/2019 Electrical 2 EPR

    11/11

    Training og

    I have regularly attended CPO seminars and undergone the following

    professional training:

    I attended a 2 day external course on Health and Safety in

    Construction Design and Management. (June 2008)

    I attended a 1 day CIBSE seminar

    on

    LED lighting. (May 2009)

    I attended 1 day external training course on the changes to the 17'

    Edition, BS7671 :2008 (November 2008).

    I attended a 1 day introductory training course on REVIT Building

    Information Modelling. (July 2012).

    I attended a 1 day seminar on risk assessment of lightning protection

    in

    accordance with

    S EN

    62305 (August 2009).

    I attended a 1 day introductory training course on REVIT Building

    Information Modelling. (July 2012)

    I attended a 1 day training course

    on

    the use of AMTECH NES

    specification software. (May 2013)

    I'm also attending 1 hour seminars

    on

    regular basis, below is a sample:

    Switchboards and forms of separation.

    Use of Busbar trunking for LV distribution.

    Lightning Protection risk assessment seminar.

    Introduction to circuit breakers

    Low voltage circuit protection.

    Prysmian cable seminar (Cables for life safety systems).

    Office Lighting.

    Energy metering systems.

    Medium Voltage Transformers and Switchgear

    Emergency lighting by inverter system.

    Protection study

    I

    discrimination on LV system.

    KNX Building Management Systems.

    Utility electrical distribution systems.

    CIBSE Lighting Control & Daylighting

    14

    E2 E4