ENVIRONMENTAL IMPACT ASSESSMENT CONCRETE BATCHING PLANT JUNE 1, 2016 GROUP 40 Elliot Gorman Peter Pham Katherine Rose Schwartz Andy Van

Transcript of EIA-Final-Report (1)

 

   

ENVIRONMENTAL  IMPACT  ASSESSMENT  CONCRETE  BATCHING  PLANT  

JUNE  1,  2016  

GROUP  40                  

Elliot  Gorman  Peter  Pham  

Katherine  Rose  Schwartz  Andy  Van  

 

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  1    

Contents  1.   Brief  Background  &  Site  Description  ..............................................................................................  2  

2.   Project  Impacts  ...............................................................................................................................  2  

3.   Significant  Impacts  .........................................................................................................................  3  

3.1  Noise  .............................................................................................................................................  3  

3.1.1  Noise  criteria  .........................................................................................................................  3  

3.1.2  Quantifying  Noise  ..................................................................................................................  3  

3.1.3  Noise  Contribution  from  Agitator  Trucks  ..............................................................................  4  

3.2  Traffic  ...........................................................................................................................................  5  

3.2.1  Victoria  St  ..............................................................................................................................  5  

3.2.2  Frank  St  ..................................................................................................................................  5  

3.3  Waste  ...........................................................................................................................................  6  

4.   Community  Consultation  ................................................................................................................  7  

5.   Alternative  Technologies  ................................................................................................................  7  

6.   Alternative  Sites  .............................................................................................................................  8  

6.1  Criteria  ......................................................................................................................................  8  

6.2  Suggested  Site  ..........................................................................................................................  8  

6.3  Alternative  Site  1:  St  Marys  ......................................................................................................  8  

6.4  Alternative  Site  2:  Yennora  .......................................................................................................  9  

7.   Recommendation  ...........................................................................................................................  9  

8.   Reflections  on  EIA  .........................................................................................................................  10  

8.1  Strengths  of  EIA  ..........................................................................................................................  10  

8.2  Flaws  of  EIA  ................................................................................................................................  10  

8.3  Improvements  ............................................................................................................................  10  

9.   Reference  .....................................................................................................................................  11  

10.   Appendix  ..................................................................................................................................  12  

Appendix  A:  Calculation  of  source  noise  ..........................................................................................  12  

Appendix  B:  Calculation  of  agitator  truck  noise  ...............................................................................  12  

B1:  Victoria  St  (Reference  AB)  ......................................................................................................  12  

B2:  Frank  St  (Reference  AC)  .........................................................................................................  12  

Appendix  C:  Calculation  of  traffic  volume  ........................................................................................  12  

C1:  Victoria  St  ...............................................................................................................................  12  

C2:  Frank  St  ..................................................................................................................................  13  

Appendix  D:  Calculation  of  slurry  waste  ..........................................................................................  13  

Appendix  E:  Calculation  of  water  waste  ...........................................................................................  13  

 

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  2    

1.  Brief  Background  &  Site  Description    The  Development  project  proposed  is  a  concrete  batching  plant  situated  at  376-­‐384  Victoria  St,  Wetherill  Park  (Fairfield  City  Council).  The  site  is  between  Frank  Street  and  Victoria  Street,  and  just  East  of  Elizabeth  Street.  Wetherill  Park  It  lies  34  km  west  of  Sydney’s  central  business  district  and  has  a  high  proportion  of  immigrants.  The  majority  of  the  suburb  is  an  industrial  area  with  6,026  people  living  in  the  southeast  sector.  The  northern  edge  of  the  suburb  lies  along  the  Prospect  Nature  Reserve.  The  suggested  site  has  a  total  area  of  115,000  m2  and  lies  in  the  largest  industrial  area  in  the  southern  hemisphere.  

The  purpose  of  the  batching  plant  will  be  to  serve  the  needs  of  local  contractors  with  a  supply  of  50,000m3  of  concrete  per  annum  with  190  trucks  accessing  the  site  daily. The  site  will  employ  8  people  and  will  operate  24/7  under  the  provision  that  noise  and  traffic  regulations  are  satisfied.    

2.  Project  Impacts A  concrete  batching  plant  combines  various  ingredients  to  produce  concrete:  calcium,  silica,  alumina,  magnesia,  iron  oxide,  sulfur  dioxide  compounds,  fly  ash,  aggregates,  and  admixtures.  Poorly  monitored  batching  plants  have  the  potential  to  release  highly  alkaline  wastewater,  dust,  excess  noise  and  other  impacts  outlined  in  table  2.1.  Traffic  and  parking  assessment,  air  quality  assessment,  a  surface  water  management  plan,  a  waste  management  plan,  and  an  environmental  noise  assessment  need  to  be  assessed  and  analysed.    

   

Figure  1.1:  Aerial  map  view  of  site    

Table  2.1:  Impact  Analysis  Table  

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  3    

3.  Significant  Impacts  3.1  Noise  3.1.1  Noise  criteria    The  project  noise  criterion  has  been  set  out  by  the  NSW  Industrial  Noise  Policy  1999.  The  standard  and  non-­‐standard  operating  hours  were  determined  by  adding  +5dBA  and  +10dBA  to  background  noise,  respectively  (Table  3.1.1).    For  the  proposed  development,  background  noise  was  assumed  since  no  data  exists  for  the  site.  

3.1.2  Quantifying  Noise  The  site  is  located  in  an  industrial  zone  within  Wetherill  Park,  where  the  closest  sensitive  receiver  is  located  in  a  residential  region  (R1),  approximately  660m  away,  as  determined  by  Google  Maps.  Sound  levels  for  multiple  locations  were  also  determined,  including  a  commercial  hub,  C1,  and  immediate  industrial  neighbours,  I1  (Figure  3.1.2).  

 

 

 

 

 

 

 

 

 

 

 

 

   

Table  3.1.1:  Project  Noise  Criterion  

Figure  3.1.2:  Receiver  locations  (blue)  from  the  centre  of  the  site  (red).  Also  illustrated  are  road  distances  between  Victoria  St  and  

Frank  St  from  receiver  at  A  (black).  

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  4    

To  quantify  the  noise  levels,  sound  pressure  levels  from  a  similar  development  by  Holcim,  Perth,  were  used  to  determine  the  site  noise  (URS  2012).  Holcim  measured  the  sound  pressure  level  from  the  slumping  and  loading  processes  of  three  agitator  trucks  simultaneously,  measuring  a  sound  pressure  level  of  approximately  55dBA  at  100  metres.  Operating  sound  pressure  level  at  10  metres  was  back  calculated  to  be  75dBA  (Ref.  Appendix  A).  All  locations  were  found  to  comply  with  the  noise  criterion  as  determined  in  section  3.1.1  (Table  3.1.3).  

 

3.1.3  Noise  Contribution  from  Agitator  Trucks  To  determine  suitable  road  noise,  sound  pressure  levels  for  a  single  agitator  truck  (AS2436-­‐2010  Table  A.1)  was  used  to  calculate  the  noise  level  between  Victoria  Street  and  Frank  Street,  and  the  residential  receiver  (Figure  3.1.2).  Trucks  utilising  Victoria  Street  do  not  comply  with  the  residential  sound  limit  of  50dBA  (Table  3.1.4).  Comparatively,  trucks  utilising  Frank  Street  produced  sound  levels  below  the  lowest  limit  of  45dBA  for  non-­‐standard  operating  hours  (Ref.  Appendix  B).  

 

This  indicates  24-­‐hour  operation  may  be  possible  if  trucks  are  directed  to  Frank  Street  during  non-­‐standard  hours.  However,  despite  satisfying  the  noise  criterion,  sound  pressure  levels  were  only  marginally  lower,  and  noise  mitigation  should  still  be  considered.  Hoppers,  silos  and  conveyors  should  be  lined  with  sound-­‐deadening  material,  compressors  and  pumps  should  be  concealed,  and  fine  aggregates  should  be  weighed  first.  

   

Table  3.1.3.  Sound  Pressure  Level  of  Receivers  

Table  3.1.4.  Sound  pressure  levels  of  Victoria  Street  and  Frank  Street  from  a  receiver  in  the  residential  region.  

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  5    

3.2  Traffic  3.2.1  Victoria  St  The  site  has  access  to  two  roads.  The  southern  road,  Victoria  Street,  is  a  4-­‐lane  undivided  road  with  bus  lanes  either  side.  To  quantify  the  road  system,  the  Road  and  Maritime  Services  traffic  volume  data  was  utilized  to  determine  vehicle  counts  during  peak  hour  (RMS  2016).  Approximately  875  vehicles  travelled  in  the  eastern  direction  every  hour,  where  10%  was  assumed  to  consist  of  heavy  vehicles  equivalent  to  3.5pcu/hr.  The  addition  of  16  agitator  trucks  yields  a  total  traffic  volume  of  1152pcu/hr  (Ref.  Appendix  C1),  which  is  well  below  the  capacity  of  Victoria  Street  as  determined  in  Table  4.3  of  the  RTA  Guide  to  Traffic  Generating  Developments.  

 

3.2.2  Frank  St  The  northern  road,  Frank  Street,  is  a  single-­‐laned  road  with  adjacent  parking,  corresponding  to  a  capacity  of  900pcu/hr  (RTA  2002).  Since  traffic  data  was  not  available,  an  estimation  based  on  the  gross  floor  area  was  used,  yielding  a  volume  of  345  vehicles  per  hour  during  peak  periods.  Similarly,  the  addition  of  16  trucks  did  not  impact  this  road  system,  producing  a  total  traffic  volume  of  489pcu/hr,  remaining  below  the  roads  capacity  (Ref.  Appendix  C2).  

The  proposed  development  should  not  impact  the  road  systems.  Although  Frank  St  is  more  advantageous  during  peak  hours,  manoeuvrability  will  be  limited.  Additionally,  main  roadways  such  as  the  Cumberland  Highway,  Greater  Western  Highway  or  M4,  will  still  be  accessible.  

   

Figure  3.2.1.  Victoria  Street  Entrance   Figure  3.2.2.  Frank  Street  Entrance  

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  6    

3.3  Waste  The  number  of  waste  streams  identified  for  the  proposed  development  has  been  narrowed  down  to  three  main  concrete  batching  byproducts.  

The  first  form  will  be  solid  waste  and  will  generally  be  in  the  form  of  excess  concrete.  The  plant  will  be  producing  specific  volumes  for  contracted  jobs,  therefore,  excess  concrete  waste  will  be  minimal  and  completely  recycled.  All  excess  concrete  will  be  returned  to  the  plant  and  transported  to  licensed  recycling  facilities,  such  as  the  Elizabeth  Drive  Landfill  Facility.  

The  second  waste  stream  will  be  washout  slurry.  Boral  Concrete  and  Quarries  Country  Queensland  (BCQCQ)  states  that  approximately  25  tonnes/week  is  produced  for  70  truck  movements  per  day  (Planning  NSW  2003).  Assuming  similarity,  the  amount  of  slurry  produced  from  the  proposed  development  will  be  approximately  68  tonnes/week  or  2.8%  (Ref.  Appendix  D).  This  waste  will  be  sent  to  licensed  recycling  facilities  in  accordance  with  the  POEO  (Waste)  Regulation  2005.  

The  final  waste  stream  is  the  amount  of  water  utilized  on  site.  Using  waste  production  from  BCQCQ  (Planning  NSW  2003),  an  estimated  32,000  cubic  metres  of  water  will  be  used,  amounting  to  64.3%  of  the  total  plant  capacity  (Ref.  Appendix  E).  In  addition  to  the  2.8%  contribution  from  slurry,  this  totals  67%  of  the  plant  capacity,  and  is  greater  than  the  63%  target  as  set  out  by  the  Waste  Avoidance  and  Resource  Recovery  Act  2007.  

The  proposed  development  has  neglected  to  specify  any  form  of  water  treatments  on-­‐site.  To  comply  with  legislations,  water  treatment  must  be  incorporated,  since  the  largest  contribution  is  from  water.  Facilities  such  as  stormwater  run-­‐off  tanks  and  washout  pits  or  ponds  are  highly  recommended.  

   

Figure  3.3.1  Waste  Treatment  Pyramid  

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  7    

4.  Community  Consultation    The  main  stakeholders  for  this  project  are  the  Fairfield  city  council,  New  South  Wales  Environment  Protection  Authority,  and  the  neighbours  in  the  community.    

In  order  to  respond  to  the  concerns  of  stakeholders  who  are  adversely  affected  by  or  had  concerns  about  the  project,  we  want  to  bring  a  focus  to  community  involvement  with  the  design/construction  of  this  concrete  batching  plant.  Because  of  this,  it  is  important  to  have  an  interactive  engagement  process  with  the  community  to  work  collaboratively  with  them  to  achieve  a  common  understanding  of  the  happenings  at  the  plant.  In  order  to  facilitate  this  interaction,  we  will  have  two  dialogue  processes  that  reach  out  to  the  entire  community.    

The  demographics  of  Fairfield  City  Council  show  that  there  is  an  even  distribution  of  people  aged  above  and  below  40,  and  we  wanted  to  ensure  all  members  of  the  community  have  the  opportunity  to  be  engaged  with  this  project.  The  two  dialogue  processes  we  came  up  with  were  first,  there  will  be  community  meetings  where  members  of  the  community  can  participate  in  a  series  of  2-­‐3  hour  sections  in  a  series  of  consecutive  weeks  while  the  decision-­‐making  process  is  occurring.  In  addition,  we  will  create  an  online  forum  where  community  members  can  find  the  newest  information  on  the  concrete  batching  plant,  participate  in  polls,  and  facilitate  an  online  discussion.    

This  method  of  interaction  helps  to  target  and  involve  the  younger  part  of  the  community.  The  community  meetings  will  occur  during  the  initial  decision-­‐making  process;  we  want  this  deliberative  dialogue  to  reach  a  common  ground  for  construction.    

Once  we  get  to  the  construction  stage  these  meetings  will  evolve  into  information  sessions  to  keep  the  community  informed  on  what  is  going  at  the  site  and  if  there  are  any  changes  or  new  technologies.  It  is  important  that  we  have  limits  on  what  is  negotiable  between  the  project  and  the  community  members  during  the  weekly  meetings  prior  to  construction.  This  way  we  can  ensure  that  while  the  community  members  have  a  voice,  there  will  not  be  delays  with  the  construction  moving  forward.    

5.  Alternative  Technologies  Some  alternative  technology  that  will  mitigate  dust  emissions  at  batching  plants  are:    

-­‐   Use  chemical  suppressant  products,  or  practice  regular  light  watering  -­‐   The  layout  and  design  of  the  site  itself  will  ideally  minimize  truck  travel  distances  by  putting  

truck  and  wash  facilities  near  the  exit  of  the  site  and  maintaining  vehicle  speed  limits  and  regular  sweeping  to  prevent  dust  build  up.    

-­‐   As  for  the  aggregate  that  is  stored  on  site  in  stockpiles,  these  should  be  contained  in  storage  bunkers  with  windshields  that  project  above  the  bunker  wall,  and  these  bins  should  be  filled  with  at  least  0.5m  of  room  at  the  top  to  prevent  too  much  blowing  in  the  wind.    

-­‐   The  conveyors  should  also  have  design  to  prevent  fugitive  dust  emissions  by  covering  them  with  a  roof  and  installing  side  protection  barriers  and  implementing  spill  trays.    

-­‐   Belt  cleaning  devices  can  also  be  installed  to  reduce  spillage.    -­‐   Mixer  loading  areas  should  also  be  roofed  on  either  side.    -­‐   Water  sprays  and  an  air  extraction  and  filtration  system  would  also  minimize  the  dust.    -­‐   Fabric  filters  are  another  alternative  technology  that  can  be  installed  in  storage  silos  so  that  

concentration  of  solid  particles  doesn’t  exceed  100  mg.m3.    

   

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  8    

6.  Alternative  Sites  6.1  Criteria  The  criteria  set  for  choosing  a  site  for  this  project  are:    

-­‐   The  site  area  must  be  large  enough  to  accommodate  the  project.  This  includes  sufficient  area  for  the  required  equipment,  office  space  and  storage  warehouse.    

-­‐   Any  roads  surrounding  the  site  should  be  low  traffic  and  very  wide.  This  is  to  accommodate  trucks  going  in  and  out  of  the  compound.  The  site  should  also  be  close  to  major  roads,  highways  and  motorways  to  allow  ease  of  transportation  to  and  from  the  site  

-­‐   There  should  be  public  transport  available  nearby  for  the  employees  to  commute.    -­‐   The  site  should  be  far  away  from  noise  receivers  and  any  nature  reserves,  parks  and  river  

6.2  Suggested  Site  The  suggested  site  at  Wetheril  Park  for  the  concrete  batching  plant  meets  all  the  criteria  set  above.  Therefore  it  is  a  suitable  site  for  the  project.  The  suggested  site  is  large  enough,  with  bus  stop  right  outside  on  Victoria  Street.  Also  all  surrounding  roads  have  low  traffic  and  connect  to  major  highways.        

6.3  Alternative  Site  1:  St  Marys  40  Forrester  Rd,  St  Marys  NSW  is  a  candidate  for  an  alternative  site  with  an  area  of  130,000m2,  with  a  bus  stop  and  train  station  400m  from  the  site.  The  issues  associated  with  this  site  are  noise  and  the  environmental  impacts.  The  nearest  noise  receptor  is  350m  away  and  the  main  route  that  the  trucks  take  to  reach  the  Great  Western  Highway,  via  Glossop  Street,  is  residential  housing  on  one  side.  The  site  is  also  situated  next  to  South  Creek  Park,  with  Whalan  Reserve  1.3km  away.  Therefore  any  air  and  water  pollution  could  affect  the  local  flora  and  fauna  in  the  area.      

Figure  6.3.1.  Aerial  map  view  of  St  Marys  Site  

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  9    

6.4  Alternative  Site  2:  Yennora  The  second  alternative  site  is  at  38  Pine  Rd,  Yennora  NSW,  this  site  is  very  similar  to  the  suggested  site.  As  it  is  also  situated  in  an  industrial  estate,  with  a  site  area  of  120,000m2.  The  nearest  noise  receptor  is  600m  away  and  Fairfield  Road  Park  is  500m  away.  Yennora  train  station  is  500m  away  and  there  is  also  a  freight  train  line  across  the  road,  which  could  be  utilised  to  transport  materials  and  aggregates  to  the  plant.  This  site  is  also  close  to  Horsley  drive,  which  connects  to  the  Cumberland  highway,  M4,  M5  and  M7.  The  only  potential  issue  is  that  there  is  already  an  established  concrete  batching  plant  nearby,  therefore  demand  may  not  be  as  high.      

 

7.  Recommendation    It  is  recommended  that  the  project  should  proceed  at  either  the  Wetheril  Park  or  Yennora  site.  As  these  two  sites  satisfy  the  all  of  the  criteria  set  for  choosing  a  site  for  this  project.  But  we  don’t  recommend  the  alternative  site  at  St  Marys  as  it  produces  too  many  issues  in  the  form  of  noise  to  the  local  residents  as  well  as  pollution  to  the  environment  and  the  local  flora  and  fauna.      

Figure  6.4.1.  Aerial  map  view  of  Yennora  Site  

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  10    

8.  Reflections  on  EIA  The  purpose  of  an  EIA  is  to  identify  the  potential  effects  a  project  may  have  on  its  surrounding  environment  and  determine  a  suitable  site  for  the  project.  The  EIA  process  consists  of:  

-­‐   Examining  the  project  proposal  and  its  site  location.    -­‐   Identifying  and  assess  all  impacts  based  on  the  site  location  and  the  surrounding  

environment.  -­‐   Identify  any  significant/major  impacts  and  find  ways  of  mitigation  and  management.  -­‐   Consult  with  stakeholders  and  the  local  community  where  the  project  is  to  be  built.      -­‐   Review  all  the  information  obtained  from  the  project  proposal,  site  location,  impact  

assessment  and  consultation.  And  determine  if  the  project  proposal  is  suitable  for  the  current  site.  

8.1  Strengths  of  EIA  The  strengths  of  an  EIA  include:  

-­‐   A  thorough  assessment  of  the  environmental,  social  and  economic  impacts.    -­‐   Incorporates  public  opinion  and  community  consultation,  into  the  project  stages  to  ensure  

that  all  stakeholders  associated  are  satisfied  with  the  project.  -­‐   Provides  mitigation  and  management  of  impacts  for  the  project,  to  minimise  the  effect  of  

impacts  on  the  surrounding  environment.  

8.2  Flaws  of  EIA  The  flaws  of  an  EIA  include:  

-­‐   The  EIA  process  is  quite  lengthy  and  will  take  a  lot  of  time  and  dedication  to  complete  properly.  

-­‐   EIA  reports  are  generally  quite  long  and  difficult  to  understand  with  a  lot  of  technical  jargon  and  calculations.  

8.3  Improvements  Several  improvements  which  could  be  incorporated  into  the  EIA  process  include:  

-­‐   Having  a  set  guideline  and  specific  detail  for  what  should  be  included  in  an  EIA.  This  reduces  any  redundant  information  and  ensures  that  lesser  technical  jargon  is  used  to  allow  a  better  understanding.    

-­‐   An  online  website,  for  users  to  generate  an  EIA,  with  a  pre-­‐set  template.  This  will  allow  an  EIA  to  be  easily  generated  by  any  user  and  allows  multiple  users  to  work  on  an  EIA  together.      

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  11    

9.  Reference  NSW  Industrial  Noise  Policy  1999,  viewed  16  May  2016,  http://www.epa.nsw.gov.au/noise/industrial.htm/  

Planning  NSW,  2003,  Assessment  Report  for  Development  Application  No.  DA-­‐76-­‐2-­‐3003-­‐I  Pursuant  to  Section  80  of  the  Environmental  Planning  and  Assessment  Act,  1979,  Department  of  Urban  and  Transport  Planning,  Sydney,  viewed  17  May  2016,  http://majorprojects.planning.nsw.gov.au/index.pl?action=view_job&job_id=1910/  

Protection  of  the  Environment  Operations  Act  1997,  viewed  15  May  2016,  http://www.epa.nsw.gov.au/legislation/actsummaries.htm/  

Protection  of  the  Environment  Operations  (Waste)  Regulation  2005,  viewed  16  May  2016,  http://www.legislation.nsw.gov.au/inforce/15937bef-­‐eef8-­‐c8ed-­‐d2c1-­‐dd4c148cc79c/2005-­‐497.pdf/  

Roads  and  Maritime  Services,  Traffic  Volume  Viewer,  2016.  RMS,  New  South  Wales,  viewed  17  May  2016,  http://www.rms.nsw.gov.au/about/corporate-­‐publications/statistics/traffic-­‐volumes/index.html/  

RTA  Guide  to  Traffic  Generating  Developments  2002,  viewed  15  May  2016,  http://www.rms.nsw.gov.au/documents/projects/guide-­‐to-­‐generating-­‐traffic-­‐developments.pdf/  

Standards  Australia  2010,  Australian  Standard  AS2436:  Guide  to  noise  and  vibration  control  on  construction,  demolition  and  maintenance  sites,  Standards  Australia,  Sydney.  

URS  2012,  Report:  Environmental  Management  Plan  East  Perth  Concrete  Batching  Plant,  URS  Australia  Pty  Limited,  Western  Australia,  viewed  17  May  2016,  http://www.vincent.wa.gov.au/files/bbf31579-­‐9249-­‐4ed5-­‐8e79-­‐a166010d828c/tesg0276r6_east_perth_cbp_emp.pdf/  

Waste  Avoidance  and  Resource  Recovery  2007,  viewed  17  May  2016,  http://www.epa.nsw.gov.au/resources/wastestrategy/070226-­‐WARR-­‐report07.pdf/  

NSW  Department  of  Planning  &  Environment,  Environmental  Impact  Assessments  2016,  viewed  20  May  16,  https://www.planningportal.nsw.gov.au/lodge-­‐track-­‐applications/lodge-­‐your-­‐application-­‐or-­‐certificate/lodge-­‐your-­‐application-­‐department/environmental-­‐impact-­‐assessment    

Australian  Government:  Department  of  Environment,  Environmental  Assessments  2016,  viewed  20  May  2016,  https://www.environment.gov.au/protection/environment-­‐assessments    

Environmental  Protection  Authority,  EIA  Process  2016,  viewed  20  May  2016,  http://www.epa.wa.gov.au/eia/assessdev/Pages/default.aspx    

 

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  12    

10.   Appendix  Appendix  A:  Calculation  of  source  noise  The  noise  level  at  a  distance  𝑅#,  from  the  receiver,  𝑅$,  can  be  calculated  as  follows.  

𝑆𝑜𝑢𝑛𝑑  𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒  𝐿𝑒𝑣𝑒𝑙   𝑆𝑃𝐿 = 𝑆𝑃𝐿2 − 10 log𝑅$#

𝑅##  

Where,  𝑆𝑃𝐿2 = 𝑠𝑜𝑢𝑛𝑑  𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒  𝑙𝑒𝑣𝑒𝑙  𝑎𝑡  𝑎  𝑘𝑛𝑜𝑤𝑛  𝑙𝑜𝑐𝑎𝑡𝑖𝑜𝑛  𝑅$ = 𝑠𝑒𝑛𝑠𝑖𝑡𝑖𝑣𝑒  𝑟𝑒𝑐𝑒𝑝𝑡𝑜𝑟  𝑝𝑜𝑖𝑛𝑡  𝑅# = 𝑙𝑜𝑐𝑎𝑡𝑖𝑜𝑛  𝑜𝑓  𝑘𝑛𝑜𝑤𝑛  𝑠𝑜𝑢𝑛𝑑  𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒  

Therefore,  using  an  estimated  sound  pressure  level  of  55  dBA  at  100  metres  (Holcim),  the  source  sound  pressure  at  10  metres  from  the  site  can  be  calculated  as:  

𝑆𝑃𝐿$A = 55 − 10 log10#

100#  

= 75  𝑑𝐵𝐴  

Appendix  B:  Calculation  of  agitator  truck  noise  B1:  Victoria  St  (Reference  AB)  Taking  𝑆𝑃𝐿2 = 76  𝑑𝐵𝐴  at  10  m  for  a  single  agitator  truck  (AS2436-­‐2010  Table  A.1)  

𝑆𝑃𝐿GH = 76 − 10 log170#

10#  

= 51.39  𝑑𝐵𝐴   >  50  𝑑𝐵𝐴  

B2:  Frank  St  (Reference  AC)  Similarly,  using  an  𝑆𝑃𝐿2 = 76  𝑑𝐵𝐴.  

𝑆𝑃𝐿GM = 76 − 10 log700#

10#  

= 39.1   <  45  𝑑𝐵𝐴  

Appendix  C:  Calculation  of  traffic  volume  C1:  Victoria  St  From  Table  4.3  of  the  RTA  Guide  to  Traffic  Generating  Development  2002,  a  4-­‐lane  undivided  road  has  a  capacity  of  1800  𝑝𝑐𝑢/ℎ𝑟,  assuming  clearway  conditions  due  to  the  presence  of  bus  lanes  on  either  side.  Traffic  volume  data  estimated  to  be  3500  𝑣𝑒ℎ𝑖𝑐𝑙𝑒𝑠/ℎ𝑟  during  peak  hour  (6AM-­‐10AM  and  3PM-­‐7PM)  Therefore,  

𝑁𝑢𝑚𝑏𝑒𝑟  𝑜𝑓  𝑣𝑒ℎ𝑖𝑐𝑙𝑒𝑠  𝑝𝑒𝑟  ℎ𝑜𝑢𝑟 =35004

 

= 875  𝑣𝑒ℎ𝑖𝑐𝑙𝑒𝑠/ℎ𝑟  Total  of  190  trucks  per  day  yields  approximately  16  trucks  per  hour.  Assuming  10%  of  the  volume  consist  of  heavy  vehicles  then,  88  heavy  vehicles  per  hour.  Each  heavy  vehicle  is  equivalent  to  3.5  pcu.  Hence,  

𝑇𝑜𝑡𝑎𝑙  𝑝𝑎𝑠𝑠𝑒𝑛𝑔𝑒𝑟  𝑐𝑎𝑟  𝑢𝑛𝑖𝑡  𝑝𝑒𝑟   𝑝𝑐𝑢 = 876 − 88 + 88 + 16 ∗ 3.5  = 1152  𝑝𝑐𝑢/ℎ𝑟 < 1800  𝑝𝑐𝑢/ℎ𝑟  

CIVL3010:  EIA  Final  Report    

Group  40       Page  |  13    

C2:  Frank  St  From  Table  4.3  of  the  RTA  Guide  to  Traffic  Generating  Development  2002,  a  single-­‐laned  road  with  adjacent  parking  lane  has  a  capacity  of  900  pcu/hr.  According  to  Table  3.7  of  the  RTA  Guide  to  Traffic  Generating  Development,  if  no  traffic  data  exists  then  an  estimate  of  volume  can  be  determined  by  calculating  the  gross  floor  area  (GFA)  of  buildings  along  Frank  St.  Taking  measurements  from  Google  Maps,  an  approximation  can  be  determined.  

𝐺𝐹𝐴 = 138000𝑚#  From  Table  3.7  for  industrial  factories  during  peak  periods,  the  ratio  of  vehicles  to  gross  floor  area  is  1/100𝑚  #.  Therefore,  

𝑁𝑢𝑚𝑏𝑒𝑟  𝑜𝑓  𝑣𝑒ℎ𝑖𝑐𝑙𝑒𝑠 =𝐺𝐹𝐴4ℎ𝑟

∗1

100𝑚#  

=1380004 ∗ 100

 

= 345  𝑣𝑒ℎ𝑖𝑐𝑙𝑒𝑠/ℎ𝑟  Assuming  heavy  vehicle  capacity  of  10%,  then  34.5  heavy  vehicles  per  her  utilize  the  road  space.  Hence,  

𝑇𝑜𝑡𝑎𝑙  𝑝𝑐𝑢 = 345 − 35 + (35 + 16) ∗ 3.5  = 488.5  𝑝𝑐𝑢/ℎ𝑟 < 900  𝑝𝑐𝑢/ℎ𝑟  

Appendix  D:  Calculation  of  slurry  waste  According  to  Boral  Concrete  and  Quarries  Country  Queensland,  25  tonnes/week  of  slurry  is  produced  in  washout  pits  for  70  truck  movements  per  day.  Assuming  similarity,  

𝐴𝑚𝑜𝑢𝑛𝑡  𝑜𝑓  𝑠𝑙𝑢𝑟𝑟𝑦 =2570

∗ 190  

= 67.86  𝑡𝑜𝑛𝑛𝑒𝑠/𝑤𝑒𝑒𝑘  The  percentage  of  waste  relative  to  the  total  production  capacity  can  be  calculated  as  follows,  

𝑃𝑒𝑟𝑐𝑒𝑛𝑡𝑎𝑔𝑒 =67.86 ∗ 52125000

 

= 2.8%  

Appendix  E:  Calculation  of  water  waste  Boral  Concrete  and  Quarries  estimates  approximately  1184  𝑚a/𝑦𝑟  of  contaminated  water  will  be  utilized  for  70  truck  movements  per  day.  

𝐴𝑚𝑜𝑢𝑛𝑡  𝑜𝑓  𝑤𝑎𝑡𝑒𝑟 =118470

∗ 190  

= 32137  𝑚a/𝑦𝑟  Therefore,  the  percentage  of  contaminated  water  relative  to  the  total  production  capacity  can  be  calculated  as  follows,  

𝑃𝑒𝑟𝑐𝑒𝑛𝑡𝑎𝑔𝑒 =3213750000

 

= 64.27%