Eden Local Plan: Interim Consultation (March 2017)...Email: [email protected] Date:...
Transcript of Eden Local Plan: Interim Consultation (March 2017)...Email: [email protected] Date:...
Eden Local Plan: Interim Consultation (March 2017)
Representations on Behalf of Story Homes
April 2017
Eden Local Plan: Interim Consultation (March 2017)
Representations on behalf of Story Homes
Project Ref: 23955/A3/LD/DM 23955/A3/LD/DM 23955/A3/LD/DM
Status: Draft Draft Final
Issue/Rev: 01 02 03
Date: 28 March 2017 3 April 2017 10 April 2017
Prepared by: LD LD LD
Checked by: - DM DM
Barton Willmore LLP
Tower 12, 18/22 Bridge St,
Spinningfields, Manchester
M3 3BZ
Tel: 0161 817 4900 Ref: 23955/A3/LD/DM
Email: [email protected] Date: April 2017
COPYRIGHT
The contents of this document must not be copied or reproduced in whole or in part without the written consent of Barton Willmore LLP.
All Barton Willmore stationery is produced using recycled or FSC paper and vegetable oil based inks.
CONTENTS
Page
1. INTRODUCTION & EIP PROGRESS TO DATE 2
2. OBJECTIVELY ASSESSED HOUSING NEEDS – REVISED POSITION STATEMENT 3
3. PENRITH – HOUSING DISTRIBUTION AND SITES 9
4. ALSTON – HOUSING DISTRIBUTION AND SITES 13
5. APPLEBY– HOUSING DISTRIBUTION AND SITES 14
6. KIRKBY STEPHEN - HOUSING DISTRIBUTION AND SITES 16
7. KEY HUBS – HOUSING DISTRIBUTION AND SITES 17
8. CONCLUSIONS 22
Appendices
Appendix 1: OAN Overview (August 2016)
Appendix 2: Key Hubs Allocations Site Assessment (Story Homes)
Introduction and EIP Progress to date
1. INTRODUCTION & EIP PROGRESS TO DATE
1.1 On behalf of our Client, Story Homes, we wish to set out our response in relation to
the Eden Local Plan – Interim Consultation.
1.2 Story Homes is the leading housebuilder within Cumbria and have been heavily
involved in the Local Plan process since 2014, with representations submitted to the
Preferred Options (September 2014); Settlement Hierarchy and Land Availability
Assessment (August 2015); and Submission Version (November 2015).
1.3 Examination Hearing Statements were submitted by Barton Willmore on behalf of Story
Homes in April 2016 and we participated within the various Hearing Sessions held in
May 2016; July 2016; and September 2016.
1.4 Throughout the Local Plan process and Hearing Sessions, Story Homes identified
concerns with the Submission Local Plan as drafted, which they do not consider have
been satisfactorily addressed. This remains the case. They do not consider that the
emerging Local Plan is robust or sound nor does it not meet in full the District ’s
housing needs as set out in the NPPF or PPG in relation to full objectively assessed
needs.
1.5 This Report sets out our Client’s response to the issues identified by the Inspector in
relation to the following papers:
• OAN - Revised Position Statement;
• Penrith – Housing Distribution and Sites;
• Alston - Housing Distribution and Sites;
• Appleby - Housing Distribution and Sites;
• Kirkby Stephen - Housing Distribution and Sites; and
• Key Hubs - Housing Distribution and Sites
1.6 It should be noted that our Client continues to maintain an objection to the evidence
base and methodology underpinning the emerging Local Plan.
OAN – Revised Position Statement
2. OBJECTIVELY ASSESSED HOUSING NEEDS – REVISED POSITION
STATEMENT
2.1 Story Homes acknowledges and welcomes the acceptance by the Council of the need
to review their existing position in relation to full objectively assessed needs (“OAN”)
and the proposed uplift to increase the OAN from 200 dpa to 242 dwellings per annum
(“dpa”).
2.2 Notwithstanding this, Story Homes do not support the methodology undertaken by the
Council nor do they consider that it sufficiently addresses the concerns identified in
relation to the OAN within our previous representations. We set out below a number
of comments in relation to the Council’s current position:
• Migration Trends – Within Barton Willmore’s comparative response to the OAN and
the Council’s OAN position, there are differences between the approaches used in
terms of applied mitigation trends. Clarification is required.
• Household Formation Rates – The Council has not reviewed their position in terms
of uplift to 2014 based Housing Formation Rates. They have relied and based their
assumptions on work undertaken by Barton Willmore. It is our view that Cumbria
County Council should be able to provide the Council with this information and
work should be undertaken to ensure that the Council ’s evidence base is robust
and up-to-date. A lack of time and resourcing is not a valid reason why this work
has not been undertaken.
• Market Signals – We consider that the Council should rely on the most up to date
data on affordability ratio for median property princes, and consider that a 20%
uplift is required under the LPEG methodology.
• Revised OAN – Clarification is required from the Council as to how an uplift of 26
dpa has been added to the jobs-led figure to take account of the differences
between the 5 and 10-year migration scenarios.
2.3 In addition to the above, we refer the Council and Inspector to the previous Position
Statement (August 2016) in relation to OAN. It remains Story Homes’ view that the
full OAN for Eden is between 277 – 289 dpa. That evidence remains relevant and it is
Story Homes position that the Council’s alternative model does not reflect the full
OAN – Revised Position Statement
OAN. We therefore respectively ask the Inspector to consider the evidence set out in
the Position Statement (August 2016) (Appendix 1).
2.4 We would also reiterate the comments set out within the HBF response to the Interim
Consultation.
Overall Supply Position
2.5 Story Homes is concerned with the overall approach which has been taken by the
Council and its failure to allocate sufficient land to meet the proposed housing
requirement of the Borough.
2.6 The overall housing land supply position is still unknown. The Council continues to
rely on Neighbourhood Plans and windfall to deliver housing within the Borough, in
addition to extant permissions and sites under construction, which have historically
under-delivered or have stalled. It is Story Homes’ position that further land release
through allocations is the most appropriate way of delivering the housing requirements
of the District.
2.7 It is our Client’s position that the Council has failed to provide a sufficient level of
buffer within their own proposed housing requirement of 242 dpa. If the Inspector is
minded to proceed with a housing requirement of 242 dpa, a suitable buffer must be
applied to the housing requirement to ensure that a minimum of 242 dpa is delivered.
This will enable the delivery of a greater choice of sites, and boost housing delivery
and market choice in accordance with Paragraph 49 of the NPPF, and allows for a
contingency if sites fail to come forward.
Housing Land Supply
2.8 It is Story Homes’ consideration that insufficient land has been allocated to meet the
housing land supply requirement within the District over the Plan period. The Council
continues to rely on Neighbourhood Plans and Windfall sites to meet the supply, and
the strategy appears to be based on allocating the minimum level of land possible.
This is not a sound approach to development.
2.9 It is our Client’s view that the Council has failed to make any allowance or slippage of
commitments or allocations. It is our Client’s view that if a slippage rate of 10% is
assumed, the provision of a 20% buffer will allow for a 10% cushion to the overall
figure, in the event of further slippage. It is therefore our Client’s position that a 20%
OAN – Revised Position Statement
buffer should be applied to the overall housing requirement to ensure that the
minimum housing targets are met.
2.10 Tables 1 and 2 show the housing land distribution based on the Council’s requirement
of 242 dpa, and our Client’s minimum requirement of 277 dpa, utilising a 20% buffer.
EDC’s Position 242 dpa
Housing
Requirement
Distribution
(%)
20% buffer
applied
Completions u/c & Extant
permissions
Residual
Requirement
Target 4,356 100 5,227
TOWNS
Penrith 2,178 50 2,614 167 324 2,123
Alston 131 3 157 2 62 93
Appleby 392 9 470 36 145 289
Kirkby
Stephen
348 8 418 21 48 349
Total Towns 3,049 70 3,659 226 579 2,854
RURAL AREAS
Key Hubs 871 20 1,045 109 260 676
Villages &
Hamlets
436 10 523 36 471 16
Total Rural 1,307 30 1568 145 731 692
Total 4,356 100 5,227 371 1,310 3,546
Table 1 – Residual Requirement based on Council’s requirement of 242 dpa
BW’s Position 277 dpa
Housing
Requirement
Distribution
(%)
20% buffer
applied
Completions u/c & Extant
permissions
Residual
Requirement
Target 4,986 100 5,983
TOWNS
Penrith 2,493 50 2,992 167 324 2,501
Alston 150 3 179 2 62 115
Appleby 449 9 538 36 145 357
Kirkby
Stephen
399 8 479 21 48 410
Total Towns 3,491 70 4,183 226 579 3,383
RURAL AREAS
Key Hubs 998 20 1,197 109 260 828
Villages &
Hamlets
495 10 598 36 471 91
Total Rural 1,485 30 1,795 145 731 919
Total 4,950 100 5,983 371 1,310 4,302
OAN – Revised Position Statement
Table 2 – Residual Requirement based on Council’s requirement of 277 dpa
2.11 This demonstrates there is a need to identify additional housing land to meet the
requirements both overall and within the main towns and Key Hubs.
Housing Supply Composition
2.12 Notwithstanding the above, we have a number of comments in relation to the Council’s
overall table showing the proposed housing distribution within the OAN Statement as
outlined below:
• The level of commitments and completions for Key Hubs is different between the
Table in Paragraph 5.25 of the Key Hubs Paper and the Table on Page 19 of the
OAN Paper. The table below, shows a comparison of these different figures.
Clarification is required.
OAN Commitments Completions Residual Requirement
Key Hubs
Paper
871 259 84 267
OAN Paper 871 260 109 502
Table 3 – Comparison between OAN and Key Hubs Paper
• As identified within the above table, the residual requirement within the Key Hubs
Paper and OAN Paper is different, with the residual requirement within the OAN
Paper substantially higher.
• The evidence base used by the Council to calculate existing commitments and
completions is not up-to-date (base date April 2015). This needs to be updated.
• There are variations in the figures proposed by the Council within each Settlement
Paper in respect of the site capacities, compared to the SHLAA i.e. 234 dwellings
across the Key Hubs, however, when the sites are assessed against the Council’s
previous assessment within the SHLAA, only 192 dwellings are identified as
capable of being accommodated, a further shortfall of 42 dwellings.
• The Council has identified a number of sites within Culgaith, Lazonby and
Langwathby which could be made available if required to meet further housing
needs.
• No information is available in relation to delivery rates in Villages and Hamlets,
other than in the OAN table.
• A 30% windfall allowance for Key Hubs is too high based on past delivery within
Eden.
OAN – Revised Position Statement
• The Council should allocate the land it needs to deliver rather than relying on
windfall which is not evidence based.
• The Council has rolled forward allocations from the 1996 Local Plan. This is no t a
viable approach, because some of the sites have failed to come forward in over
20 years and are considered undeliverable.
• The Council is reliant on windfall sites, however, a number of these sites have
been under-construction, or permitted for a number of years.
• Site capacity should not be treated as a maximum figure, rather it should be a
minimum.
• The overall supply is unknown because the Council is continuing to rely on
Neighbourhood Plans and windfall.
Contingency Method
2.13 It is Story Homes’ position that in relation to housing supply, a contingency plan is
required, to ensure that the Local Plan remains effective and flexible during a range
of economic conditions, in relation to housing supply. This include a range of options
and possible actions to ensure the Plan delivers the minimum housing requirement.
This could include the release of Future Growth Land or an early review of the Local
Plan. The Council has accepted that a higher requirement is needed, however, without
further land release this need cannot be met. Completions and housing allocations
need to be carefully monitored to identity any non-delivery trends.
2.14 We refer the Council and Inspector to the recently published White Paper . This clearly
sets out in Paragraph 2.49 Bullet Point 1, the Government’s approach to the delivery
of housing. If it falls below 95% of the annual requirement the Council will be required
to publish an action plan, setting out its understanding of the key reasons for this
situation and how it will be addressed. If it drops further, they will be required to
release further housing land.
Summary
2.15 The lack of adequate buffer means that further land should be allocated within the
Plan. The Plan as drafted has no contingency plan, therefore effectiveness and
flexibility of the Plan is questionable. The Council should consider contingency
measures and mechanisms to release further land for development if required (e.g.
Future Growth Land or Action Plan (as proposed in the Housing White Paper)), or in
OAN – Revised Position Statement
a worst case scenario, what level of undersupply would trigger an early review of the
Local Plan.
Penrith – Housing Distribution and Sites
3. PENRITH – HOUSING DISTRIBUTION AND SITES
Housing Requirement with Penrith
3.1 The Penrith Housing Distribution Paper seeks to reflect the Council’s proposed latest
OAN position of 242 dpa, with 50% of this growth required to be delivered within
Penrith. This equates to 2,178 dwellings.
3.2 The amended wording for Policy PEN1 states that the Council is only required to deliver
a minimum of 1,687 dwellings over the Plan period. This is the residual requirement
only, rather than the overall requirement. This approach by the Council is incorrect.
3.3 To meet the identified requirement of 1,687, the Council has included a number of
additional sites for allocation and revised the capacity in others. The Penrith Housing
Distribution paper (Table within Paragraph 7.2) states that the proposed sites are
capable of accommodating 1,715 dwellings. When compared to the Council’s identified
residual requirement of 1,687 dwellings, this equates to an oversupply of only 28
dwellings.
3.4 It is our Client’s position that this is insufficient, because it does not account for any
slippage or non-delivery of sites. A suitable buffer is therefore required in the event
of non-delivery and further land release is needed within Penrith.
3.5 It is also Story Homes position that Policies LS2 and PEN1 should be reworded, to
ensure they reflect the overall requirement of 2,178 dwellings (as a minimum if the
Inspector is minded to approve the 242 dpa figure proposed by the Council ) rather
than the residual requirement of 1,686 dwellings, to reflect the overall housing
requirement within Penrith over the Plan period. We refer the Council and Inspector
to our previous representations in relation to Policies PEN1 and LS2 accordingly,
because these policies should be consistent with the housing requirement of Penrith.
3.6 We request that the Council provides an up-to-date position of the Council’s latest
completions, dwellings under-construction and sites with extant permission. Whilst it
is noted that these have been provided, they are reliant on an evidence base of April
2015, and there are inconsistencies between the various consultation documents in
terms of the number of completions etc.
Penrith – Housing Distribution and Sites
3.7 As identified within Section 2 of this Statement, we have undertaken a comparison of
the Council and our Client’s respective housing requirements based on the requirement
of 242 dpa and 277 dpa, when applying a 20% buffer.
Residual requirement Allocations Difference
242 dpa 2,123 1,715 408
277 dpa 2,501 1,715 786
Table 4 – Residual requirement comparison – Penrith
3.8 As shown in the above table, there is a clear need to release additional land within
Penrith to meet the above requirements.
Future Growth Land
3.9 No justification has been provided by the Council for the inclusion of sites as “Future
Growth Land”, nor has any guidance or policy release mechanism been provided as to
when these sites will be released. Clarification is required as to the role of a “Future
Growth” sites and what the Council’s future intention of these sites are. It is noted
that the Council has also previously used the term “reserve land”. Clarification in terms
of the differences between these terms is required.
3.10 It is our Client’s view that sufficient land should be allocated at the outset to ensure
the minimum housing requirement and buffer is met in the first instance. A release
mechanism setting out how any land designed as “Future Growth Land” will be
released is required and could form part of the Council’s contingency plan.
Site Specific Comments
3.11 We set out below our site-specific comments in response to the proposed allocations
within Penrith below.
Site N1A – Salkeld Road/Fairhill Greenfield Extension (Phase 2)
3.12 The site is included within the Submission Draft Local Plan as a “Reserved Site” and it
is now proposed for release as a potential allocation. Story Homes supports the release
of the site. We refer both the Council and Inspector to our previous comments
submitted in relation to this site in November 2015 in response to the Submission
Draft Local Plan.
3.13 We maintain our position that the site should be allocated because it is deliverable
within the Plan period and will help the Council achieve its housing needs. The site is
Penrith – Housing Distribution and Sites
well related to Penrith and is within one single ownership and is deliverable. It forms
a logical extension to Story Homes’ existing site (N1) which benefits from existing
planning permission (and works have commenced on-site). The site is considered to
be suitable, available and achievable and capable of accommodating circa 350
dwellings, significantly more than the 250 dwellings identified by the Council.
3.14 It is further noted that it is the Council’s intention to release only part of the Site, and
for the remainder of the Site to be allocated as an area of “Future Growth” (please
see our previous comments in relation to this in paragraph 3.7). The entire site should
be released for residential development at the outset of the Plan.
Site N2 – White Ox Farm
3.15 Story Homes supports the proposed retention of this site within the emerging Local
Plan and the reduction in the developable site area.
Site P94 – QEGS Annexe
3.16 No comment.
Site N3 – Raiselands
3.17 Story Homes supports the proposed increase in capacity of the site for 230 dwellings.
We offer no further comments in relation to this allocation.
Site PS4 -Bellevue Farm, Salkeld Road
3.18 Story Homes supports the allocation of this site. We offer no further comments in
relation to this allocation.
Site P108 – Land at Green Lane
3.19 No comment.
Site E1 - Land Adjoining/to the north of E1 (Carleton)
3.20 Story Homes supports the allocation of this site, and considers it to be suitable,
available and deliverable within the Plan Period.
Summary
3.21 It is our Client’s position that further land release is required to be allocated within
Penrith. We consider that the Sites identified should be released, but that further land
is release is required, and the most appropriate sites would be those identified as
“Future Growth Land”.
Penrith – Housing Distribution and Sites
3.22 No justification has been provided by the Council in relation to what is meant by a
“Future Growth land” or what mechanism is involved in its release.
Alston – Housing Distribution and Sites
4. ALSTON – HOUSING DISTRIBUTION AND SITES
4.1 Our Client does not support the continued inclusion of Alston as a “Market Town”. We
refer the Council and Inspector to our previous representations made to the
Submission Version, Settlement Hierarchy and Hearing Statements.
4.2 Policy AL1 of the Submission Draft Local P lan identifies land for 86 new homes within
Alston. However, the Council acknowledges within their assessment that delivery rates
within Alston are slow (Table 4.1) and in single figures per annum. There is limited
market demand for new housing within the settlement. It is also recognised within the
Alston Housing Distribution Paper that any increase in the number of houses to be
delivered within Alston would be extremely challenging and it therefore seeks to
reduce the number of dwellings proposed to 67 dwellings and reduce the distribution
target from 4% to 3%. This approach is concerning, and reiterates Story Homes ’ view
that Alston is not an appropriate location for growth, and no sound evidence has been
provided to justify this.
4.3 Of these dwellings, 62 dwellings are already “under-construction” or permitted, but
there are limited completions within the settlement, amounting to a mismatch in the
development strategy. The amount of growth within the settlement is therefore
limited.
4.4 As identified within Section 2 of this Statement, we have undertaken a comparison of
the Council and our Client’s respective housing requirements based on the requirement
of 242 dpa and 277 dpa, when applying a 20% buffer.
Residual requirement Allocations Difference
242 dpa 93 67 26
277 dpa 115 67 48
Table 5 – Residual requirement comparison – Alston
4.5 As shown in the above table, there is a clear need to release additional land to meet
the above requirements.
4.6 Story Homes does not wish to make any further comments in relation to the proposed
allocations within Alston, but refer the Council and Inspector to our previous
representations within the Submission Version, Settlement Hierarchy and Hearing
Statement that Alston should not be a designated Market Town.
Appleby - Housing Distribution and Sites
5. APPLEBY– HOUSING DISTRIBUTION AND SITES
5.1 Appleby is designated as a Market Town within the emerging Local Plan and Story
Homes supports this. The Submission Plan proposed the delivery of a minimum of 155
new homes within Appleby, and the revised distribution strategy proposes an increase
in the residual requirement to 68 dwellings.
5.2 As identified within Section 2 of this Statement, we have undertaken a comparison of
the Council and our Client’s respective housing requirements based on the requirement
of 242 dpa and 277 dpa, when applying a 20% buffer.
Residual requirement Allocations Difference
242 dpa 289 214 75
277 dpa 357 214 143
Table 6– Residual requirement comparison – Appleby
5.3 As shown in the above table, there is a clear need to release additional land to meet
the above requirements.
5.4 We set out our comments in response to the revised allocations below:
Site AP10 – Land to the south of Station Road
5.5 No comment.
Site AP11 – Fields Adjacent to the Cold Yard
5.6 The Council considers that the Site is suitable for release, and is capable of
accommodating 39 dwellings across the Plan period. Story Homes is supportive in
principle of this proposed allocation; however, it is their view that this should be a
minimum housing figure, rather than a maximum figure which may be permitted on-
site, particularly as the Submission Version identified that the Site is capable of
accommodating 90 dwellings. The Noise Report which accompanies the Appleby
Housing Distribution Paper is clear that any assessment would need to take account
at detailed design stage of the application, and there are various options as part of
the design process to mitigate any impact.
5.7 The Council identified within the LAA that the Site is suitable, available and achievable
and considered to be developable. Our Client support the inclusion of this Site as an
Appleby - Housing Distribution and Sites
allocation, on the basis that it is suitable for development because it forms a natural
extension to the settlement and is located close to local services and bounded by the
railway line and any identified constraints can be overcome.
5.8 The Site is therefore considered to be suitable, available and deliverable in the short
term (0 -5 years) and should be included as an allocation.
Site AP16 – Land behind Cross Croft
5.9 Story Homes supports the proposed allocation of the Site for 115 dwellings. It is our
Client’s view that the Site is suitable, available and deliverable and capable of
accommodating the number of dwellings identified by the Council. There is no reason
why the Site should not be allocated within the emerging Local Plan.
Site AP24 – Land at Westmorland Road
5.10 No comment.
Summary
5.11 We support the inclusion of Appleby as a Market Town and consider that it is capable
of accommodating the minimum level of development proposed.
Kirkby Stephen - Housing Distribution and Sites
6. KIRKBY STEPHEN - HOUSING DISTRIBUTION AND SITES
6.1 Kirkby Stephen is designated as a Market Town within the emerging Local Plan and
Story Homes supports this. The Submission Plan proposed the delivery of 252 new
homes within Kirkby Stephen, and the revised distribution strategy proposes an
increase in the minimum residual requirement to 348 dwellings. This increase takes
account of the increase in the proposed OAN figure to 242 dpa, and the additional 1%
requirement taken from Alston.
6.2 As identified within Section 2 of this Statement, we have undertaken a comparison of
the Council and our Client’s respective housing requirements based on the requirement
of 242 dpa and 277 dpa, when applying a 20% buffer.
Residual requirement Allocations Difference
242 dpa 349 281 32
277 dpa 410 281 129
Table 7 – Residual requirement comparison – Kirkby Stephen
6.3 As shown in the above table, there is a need for additional land to meet the above
requirements.
6.4 We refer the Council and Inspector to our comments in Paragraphs 3.9 and 3.10 in
relation to “Future Housing Land”. Our comments within these paragraphs are
applicable to Kirkby Stephen, because “Future Housing Land” has been allocated here.
6.5 Story Homes have no further comments in relation to the revised distribution strategy
for Kirkby Stephen or any of the proposed allocations.
Key Hubs - Housing Distribution and Sites
7. KEY HUBS – HOUSING DISTRIBUTION AND SITES
7.1 Following the initial Hearing Sessions in May 2016 and the Inspector’s
recommendations, the Council has sought to reduce the number of Key Hubs from 28
to 12, focusing on the most sustainable locations. The approach to reduce the number
of Key Hubs is supported by Story Homes, who have advocated this approach
throughout the Local Plan process to date.
Methodology
7.2 Story Homes have concerns with the Council’s approach as drafted and in particular,
the settlements which have been selected as Key Hubs and the “scoring approach”
which has been taken in relation to their designation. We refer the Council and
Inspector to our previous representations in relation to Key Hubs.
7.3 It is Story Homes’ position that the Council’s approach in allocating additional sites or
the numbers of dwellings within each site is flawed, because no detailed assessment
has been carried out in relation to the environmental constraints or opportunities
within each site or settlement, including an update of the Sustainability Appraisal . A
full detailed assessment of the local conditions and characteristics including
employment needs and opportunities, demographic and socio-economic profile,
development constraints and opportunities has not been undertaken.
Greystoke
7.4 It is our Client’s view that Greystoke should be allocated as a Key Hub because it
fulfils the required criteria for a Key Hub. Evidence to support the designa tion of
Greystoke as a Key Hub has been previously been presented to the Inspector and
Council with regard to this matter, and we would invite the Inspector to conclude on
this matter.
Sources of Supply
7.5 The Submission Local Plan proposed to deliver 720 new dwellings within the Plan
period, but did not allocate specific sites. This position was found not be sound by the
Inspector. The Key Hubs Paper seeks to increase this to 871 dwellings, with a residual
requirement of 267 dwellings, once 30% windfall; completions; and commitments have
been deducted. We set out our comments in relation to Neighbourhood Plans and
windfall below.
Key Hubs - Housing Distribution and Sites
Neighbourhood Plans
7.6 Story Homes does not support the Council’s continued reliance on Neighbourhood
Plans and windfall to deliver the levels of housing required and do not consider that
this approach is justified or effective. Progress on Neighbourhood Plans within Eden
is slow, and they are not considered to be a reliable source for delivery of land.
7.7 The table below provides an update on the progress of the Neighbourhood Plans to
date, which with the exception of Langwathby and Lazonby are limited.
Neighbourhood
Plan Area Status No of Dwellings Proposed
Upper Eden
[includes Brough
and Warcop]
Adopted April 2013 No set number.
Bolton Consultation on Final Draft Plan held in Summer 2016. Will be passed to Referendum if it meets all “basic conditions”.
Seeks to limit development to 40 dwellings of which 22 already have planning permission.
Langwathby Formal consultation held in Summer 2015
Seeks to limit development to 60 dwellings on the basis of an allocated site (28 dwellings) and 2 dwellings per annum with only proposals up to 7 dwellings permitted. Story Homes submitted representations to this document.
Greystoke Parish Designated NP Area– no further progress
Lazonby NP documents due to be submitted to Council in March 2017 with Examination in May 2017. Referendum due in June 2017, with adoption in July 2017.
Number of potential development sites have been identified.
Morland Designated NP Area – no further progress
Skelton Designated NP Area – no further progress
Tebay Designated NP Area – no further progress
Ainstable Parish Designated NP Area – no further progress
Alston Moor Parish
Designated NP Area – no further progress
Appleby in Westmorland
Parish
Designated NP Area– no further progress
Asby Parish Designated NP Area– no further progress
Crosby Ravensworth Parish
Designated NP Area – no further progress
Table 8 – Neighbourhood Plan Update
7.8 We refer the Council and Inspector to our previous representations in relation to
Neighbourhood Plans.
Key Hubs - Housing Distribution and Sites
7.9 Additionally, it is Story Homes’ view that there is no certainty that those areas
designated as Neighbourhood Plans areas (Langwathby and Lazonby) will deliver the
level of dwellings required, because there is no firm commitment of what sites will be
delivered through a Neighbourhood Plan, or if this was required to be amended what
sites would be identified. It is our Client’s view that further land release is required
now, and that sites are identified for allocation.
Windfall
7.10 The NPPF sets out that windfall sites are “sites which have not been specifically
identified as available in the Local Plan process. They normally comprise
previously developed sites that have expectantly become available”. It
remains our Client’s position that the Council’s reliance on windfall is not a guaranteed
approach to development, because there is no certainty that the level of housing
required will be delivered from these sites. Windfall will not deliver the numbers
required, nor is there any evidence to suggest that relying on windfall in Key Hubs will
achieve the required levels of completions.
7.11 The Council has failed to provide robust evidence to demonstrate that they are able
to deliver the levels of windfall required within the Key Hubs. The Council has justified
30% windfall based on the number of historical small sites which have come forward.
However, within the Key Hubs, there is limited brownfield land available, and it is our
Client’s view that because the number of Key Hubs has been reduced, the number of
small sites should also decrease. The proposed housing requirement of 242 dpa is a
minimum. It is our Client’s view that any housing derived from windfall should be
additional.
7.12 It is our Client’s view that further land release is required to meet this need now,
rather than relying on an unreliable source of housing supply, which will further
exasperate the Council’s housing delivery problems in the future, when they do not
deliver the level of housing required.
7.13 Story Homes do not consider that an allowance for 30% windfall is appropriate, for
the reasons set out above. To ensure the Plan is effective and that the minimum
housing requirement is met, the reliance on windfall should be removed. Further
allocations within Key Hubs will therefore be required to help meet this requirement.
Key Hubs - Housing Distribution and Sites
7.14 Any small sustainable sites which come forward in addition to this should be approved,
because they will help to boost significantly the supply of housing.
7.15 We have undertaken a comparison of the Council and our Client’s respective housing
requirements based on the requirement of 242 dpa and 277 dpa, when applying a
20% buffer.
Residual requirement Allocations Difference
242 dpa 676 267 409
277 dpa 828 267 561
Table 9 – Residual requirement comparison – Key Hubs
7.16 As shown in the above table, there is a need for additional land to be allocated to
meet the above requirements, particularly within Key Hubs, because it cannot be
guaranteed that this requirement will be met by windfall and Neighbourhood Plans.
Site Specific Comments
7.17 We set out our comments in relation to each Key Hub and its proposed allocations
within Appendix 2.
7.18 In relation to the Key Hubs, the Council has sought to allocate land for 234 dwellings
across the Key Hubs, however, when the sites are assessed against the Council’s
previous assessment within the SHLAA, only 192 dwellings are identified as capable
of being accommodated on the sites, a shortfall of 42 dwellings from the Council’s
figure of 234 dwellings. It is considered that given the constraints identified within
the Table in Appendix 2, the stated supply seems overly optimistic.
7.19 It is therefore Story Homes’ view that further land release is required within the Key
Hubs, and that the Council should not rely on windfall and Neighbourhood Plans to
bring forward housing.
7.20 An overall contingency buffer should be applied to the overall housing supply to allow
for any slippage within the delivery of dwellings within the Key Hubs.
Langwathby
7.21 It is Story Homes’ position that further land release is required within Langwathby,
because it is a Key Hub which is capable of accommodating growth, above the 28
dwellings proposed through the Neighbourhood Plan. It is sustainable settlement with
Key Hubs - Housing Distribution and Sites
both bus and rail linkages. We refer the Council and Inspector to our previous
comments in relation to Langwathby.
Conclusion
7.22 Table 5.25 identifies a residual requirement of 267 dwellings, with 234 dwellings
proposed for allocation within the Key Hubs, equating to an oversupply of only 33
dwellings. We do not consider this to be an appropriate buffer of housing supply for
Key Hubs.
7.23 It is therefore considered that to meet the Council’s residual requirement (when
applying a 20% buffer), as identified within Table 9, land for an additional 409
dwellings is required, and when applying Barton Willmore’s residual requirement based
on 277 dpa, land for an additional 561 dwellings is required. Further land release is
therefore required.
Conclusions
8. CONCLUSIONS
8.1 Story Homes acknowledges and welcomes the Council’s proposed increase in the OAN
from 200 dpa to 242 dpa. However, they do not consider that it addresses the concerns
identified within the previous representations in relation to the OAN. We refer the
Council and Inspector to our previous Position Statement (August 2016 – Appendix
1). It remains Story Homes’ view that the full OAN for Eden is between 277 – 289
dpa.
8.2 it is our Client ’s view that the plan as drafted lacks an adequate buffer. Further land
should therefore be allocated within the Plan. The Plan as drafted in effect has no
contingency plan, and therefore effectiveness and flexibil ity of the Plan is
questionable. The Council should consider the inclusion of contingency measures and
mechanisms to release further land for development if required (e.g. Future Growth
Land or Action Plan (as proposed in the Housing White Paper)), or in a worst case
scenario, what level of undersupply would trigger an early review of the Local Plan.
8.3 In relation to Penrith, the wording of Policies PEN1 and LS2, if the Inspector is minded
to progress with the Council ’s figure of 242 dpa (if 242 dpa is accepted as housing
requirement) this should be amended to reflect the overall requirement of 2,178
dwellings rather than the residual requirement of 1,687 dwellings (50%) within Penrith
over the Plan period.
8.4 Whilst we welcome the Council’s approach to allocate additional sites within Penrith,
we do not consider that a sufficient buffer has been provided because it does not
account for any slippage or non-delivery of sites.
8.5 Additionally, justification is required by the Council in relation to “Future Growth Land”
to this, because whilst the Council proposes to allocate a number as “Future Growth
Sites”, no information been provided in relation to the release mechanism that applies.
Clarification of the Council ’s position on this is required.
8.6 In relation to Key Hubs, our Client does not support the Council’s approach to Key
Hubs, and whilst they welcome the reduction in the number of settlements proposed
as Key Hubs, they maintain that this is not based on a detailed assessment of the
constraints and opportunities of each settlement. Other sustainable Key Hubs such as
Greystoke should be designated as Key Hubs.
Conclusions
8.7 Story Homes do not support the Council’s reliance on 100% commitments plus
Neighbourhood Plans or windfall to deliver the level of housing required within the
Key Hubs. Further land release is therefore required to meet these needs and Story
Homes suggest a 20% buffer to ensure to ensure effectives.
8.8 It is Story Homes’ position that a contingency plan is required, which includes a range
of action including an early review of the Local Plan. The Council has accepted that a
higher requirement is needed, however, without further land release this need cannot
be met. Further land release is therefore required.
8.9 The Interim update and methodology is not therefore sound because it is not based
on a robust methodology, full OAN or reliable delivery mechanism.
APPENDIX 1
OAN OVERVIEW (AUGUST 2016)
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 1 August 2016
1.0 Introduction
1.1 This paper has been produced by Barton Willmore on behalf of Story Homes in order to provide
a Position Statement in respect of the methodology for objectively assessing housing need
(OAHN) in Eden District that was submitted via representations to the May 2016 Local Plan
hearings.
1.2 Barton Willmore’s approach to assessing OAN follows the approach set out in Planning Practice
Guidance (PPG) Housing and Economic Development Needs Assessments (HEDNA) that was
originally issued in March 2014 with subsequent updates in March 2015.
1.3 This paper sets out each of the steps Barton Willmore has made in assessing housing need for
Eden District, following the PPG methodology, presenting the result of each stage of the
assessment. Where possible the Council’s assessment will be presented alongside, in order to
assist the Inspector understand where the main differences between the two assessments lie.
1.4 In presenting Barton Willmore’s approach, this paper also seeks to address the additional
questions raised by the Inspector in the July 2016 Local Plan hearings in relation to the 2014-
based Sub-National Population and Household Projections.
2.0 PPG and Barton Willmore’s methodological approach
i) Starting point estimate of need
2.1 PPG (ID 2a-015) states that the starting point for assessing overall housing need should be
the household projections published by the Department for Communities and Local
Government.
Current position - CLG 2012-based household projections
2.2 At the time of the initial May 2016 hearings the CLG 2012-based household projections were
the latest available and these were utilised by Barton Willmore to establish a starting point
estimate of housing need.
2.3 The 2012-based household projections projected growth of 110 households per annum in Eden
District over the Plan period 2014-2032. Once an allowance for vacancy and second homes
has been applied this results in growth of 122 dwellings per annum. Barton Willmore has
applied a 9.54% vacancy/ second home adjustment based on CLG Council Tax data from 2015.
Growth of 122 dwellings per annum is assumed by Barton Willmore to represent the starting
point estimate of housing need for Eden District.
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 2 August 2016
2.4 Eden District Council (EDC) agree that the 2012-based household projections project growth
of 110 households per annum. EDC apply an 8.9% vacancy/ second home rate based on 2011
Census data which results in growth of 120 dwellings per annum.
2.5 PPG requires local needs assessments to be informed by the latest available information (ID
2a-016). On this basis, Barton Willmore’s use of 2015 CLG data is more up to date than EDC’s
use of the 2011 Census data.
2.6 We therefore consider that the most appropriate 2012-based starting position is
therefore 122 dwellings per annum (2014-2032).
2.7 However, EDC uplift the 2012-based household projection by 10% to address market signals
issues, resulting in growth of 121 households per annum. EDC state that the 10% uplift to
address market signals is in line with Planning Advisory Service (PAS) Guidance. Barton
Willmore consider market signals later in the assessment. Nonetheless it is important to state
that the PAS Guidance has been prepared by Peter Brett Associates (PBA) in isolation. No
consultation took place and therefore the guidance represents the views of one consultant
only. Furthermore the Guidance itself states that:
“The note has no official status. It provides informal advice, which local authorities and others use at their own risk.”1
CLG 2014-based household projections
2.8 At the July 2016 hearings the Inspector raised the question as to whether the recently
published CLG 2014-based household projections should be used as the starting point? Barton
Willmore believe that they should be, given PPG states that local needs assessments should be
informed by the latest available information (ID 2a-016).
2.9 The 2014-based household projections project growth of 80 households per annum over the
Plan period (2014-2032). After an allowance for vacancy and second homes has been applied
(again 9.54% given this is the latest data available) this results in growth of 88 dwellings per
annum.
2.10 Barton Willmore therefore consider that the revised starting point for assessing housing need
in Eden District is 88 dwellings per annum (2014-2032).
1 Paragraph 1.2, page 1, PAS Technical Advice Note: Objectively Assessed Need and Housing Targets, Second Edition, July 2015
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 3 August 2016
2.11 We therefore consider that the most appropriate updated 2014-based starting point
is 88 dwellings per annum (2014-2032).
ii) Adjust demographic starting point estimate
2.12 PPG (ID 2a-015 and 017) allows adjustments to be made to the starting point estimate of need
to reflect factors affecting the underlying demographic projections and household formation
rates (HFRs). The starting point estimate is calculated by applying HFRs to the ONS Sub-
National Population Projections (SNPP).
2.13 Barton Willmore has given consideration to both the SNPP and the HFRs, which at the time of
the original assessment, was the 2012-based SNPP and HFRs.
Household Formation Rates (HFRs)
2.14 PPG states that the household projection-based estimate of housing need may require
adjustment if formation rates have been suppressed historically (ID 2a-015). The analysis
presented in the Barton Willmore OAN Dashboard (April 2016) compared HFRs from the 2008
projection series through to the 2012 series. The analysis identified that the 2012-based HFRs
for Eden District were lower for those people aged 25-44 years compared to the 2008-based
rates for Eden District (used as a benchmark to represent a more positive period), indicating
suppressed household formation in Eden District.
2.15 Supplementary analysis undertaken by Barton Willmore has identified that there was a 42%
increase in the number of concealed families in Eden District between the 2001 and 2011
Census periods. CLG state:
“Concealed households are family units or single adults living within other households, who may be regarded as potential separate households which may wish to form given appropriate opportunity.”2
2.16 Although the increase in concealed households in Eden District was lower than the national
average (71%), there is clearly a local issue which should be addressed.
2.17 In light of the findings, Barton Willmore consider that an adjustment to the 2012 HFRs is
required in order to address the issue household suppression in Eden District. Whilst household
suppression is not unique to Eden District, the 2012 HFRs would not be a prudent basis from
2 Paragraph 3.4, page 42, CLG (authors Glen Bramley et al), Estimating Housing Need, November 2010
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 4 August 2016
which to set a housing target in Local Plan preparation, as it would not be considered to be
‘positively prepared’ in the context of the NPPF (paragraph 182) or to ‘significantly boost’
housing supply.
2.18 As the Cornwall Local Plan Inspector stated in relation to the 2012-based HFRs:
“The HR 2012 may still embed some recessionary effect. It would be inconsistent with the national policy for growth to project any such effect throughout the plan period. Accordingly, the projections developed as part of this further update should show both the HR 2008 and HR 2012 and the mid-point, blended approach. On the current evidence, I consider that the most robust approach for deriving the housing requirement would be a projection using a blended HR rate”3
2.19 Following the release of the CLG 2014-based household projections, Barton Willmore has given
consideration to the more recent 2014-based HFRs in order to determine whether the 2014-
based HFRs indicate suppressed household formation, similar to the 2012-based HFRs. Figure
1.1 presents the projected HFRs from the 2008-based series through to the most recent 2014-
based series for Eden District.
2.20 Figure 1.1 illustrates that in Eden District the 2014 HFRs project lower household formation
than the 2012 HFRs which have been acknowledged as suppressing household formation
particularly for younger people. On this basis it is considered that the 2014 HFRs require a
similar adjustment to the 2012 HFRs.
3 Paragraph 3.8, Cornwall Local Plan Examination, Inspector’s preliminary findings, June 2015)
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 5 August 2016
Local Authority: Eden
Figure 1.1: Analysis of Household Representative (HR) Rates
Comparison of HR rates for persons aged 15+, by 10 year age band, 15 to 74 and for persons 75+ is
presented in the panels below. The HR rates shown are taken from the DCLG 2008-based (blue line), interim 2011-based
(red line), 2012-based projections (green line) and 2014-based series (purple line).
By way of explanation, a rate of 0.5 means that 50% of persons in that age group are said to represent a household, so
that a hypothetical 100 persons is assumed to represent 50 households.
0.30
0.35
0.40
0.45
0.50
0.55
0.60
1991 2001 2011 2021 2031
15+ 2008-based 15+ 2011-based
15+ 2012-based 15+ 2014-based
0.00
0.05
0.10
0.15
0.20
0.25
0.30
1991 2001 2011 2021 2031
15-24 2008-based 15-24 2011-based
15-24 2012-based 15-24 2014-based
0.30
0.35
0.40
0.45
0.50
0.55
0.60
1991 2001 2011 2021 2031
25-34 2008-based 25-34 2011-based
25-34 2012-based 25-34 2014-based
0.40
0.45
0.50
0.55
0.60
0.65
0.70
1991 2001 2011 2021 2031
35-44 2008-based 35-44 2011-based
35-44 2012-based 35-44 2014-based
0.40
0.45
0.50
0.55
0.60
0.65
0.70
1991 2001 2011 2021 2031
45-54 2008-based 45-54 2011-based
45-54 2012-based 45-54 2014-based
0.40
0.45
0.50
0.55
0.60
0.65
0.70
1991 2001 2011 2021 2031
55-64 2008-based 55-64 2011-based
55-64 2012-based 55-64 2014-based
0.40
0.45
0.50
0.55
0.60
0.65
0.70
1991 2001 2011 2021 2031
65-74 2008-based 65-74 2011-based
65-74 2012-based 65-74 2014-based
0.60
0.65
0.70
0.75
0.80
0.85
0.90
1991 2001 2011 2021 2031
75+ 2008-based 75+ 2011-based
75+ 2012-based 75+ 2014-based
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 6 August 2016
2.21 Given PPG does not specify how such an adjustment to HFRs should be made, Barton Willmore
sensitivity test the application of three different HFR adjustments:
a) A gradual full return to the 2008-based household formation rates for 25-44 year olds
by 2032;
b) A gradual return to the 2008-based household formation rates for 25-44 year olds, so
that by 2032 they represent 50% of the projected growth in the original 2008 rates;
c) A gradual full return to 2001 household formation rates for male and females aged 25-
34 and 35-44 years, only where the 2012 rates are projected to decline below the 2001
rates. For Eden, this required an adjustment to the male rates only for those aged 25-
34 years.
2.22 Applying the HFR sensitivities has the impact of increasing the level of housing need indicated
by the 2012-based household projections from 122 dwellings per annum to up to 131 dwellings
per annum (2014-2032). The maximum uplift is therefore only equivalent to an additional 9
dwellings per annum and is relatively small given the older age profile of Eden District and
given the HFR adjustment is only made to the rates for those aged 25-44 years.
2.23 EDC make no adjustment to address suppressed household formation.
Demographic projections
2.24 Barton Willmore has given consideration to the 2012-based SNPP and in particular the
migration trends from the period 2007-2012 they are underpinned by. Table 1.1 presents net
migration counts for Eden District since 2001.
2.25 It is evident from Table 1.1 that net migration to Eden began to decline from 2006/07 onwards
suggesting that trends from the period 2007-2012 may have been restricted due to the
economic recession. The 2012-based SNPP may therefore provide a conservative projection of
population growth in Eden.
2.26 In contrast, prior to the recession, net migration of people to Eden was considerably higher as
a result of more people migrating to Eden to live than there were people moving out of the
district. In the vast majority of Local Plan Evidence bases a 10-year migration trend
is always considered because it incorporates a period of economic buoyancy and
recession providing a more stable longer term trend. Furthermore, the recent LPEG
recommendation to Government is that consideration should be given to the latest SNPP and
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 7 August 2016
10-year migration trend and the higher of the two should be taken to represent demographic-
led need.4
Table 1.1: Historic components of population change for Eden District
Natural change
Net Migration
Other changes Total change Total UPC
2001/02 ‐58 461 ‐6 ‐4 397
2002/03 ‐139 743 ‐2 1 602
2003/04 ‐81 599 ‐3 ‐3 515
2004/05 ‐124 419 10 10 305
2005/06 ‐40 231 2 2 193
2006/07 ‐66 396 ‐10 ‐8 320
2007/08 ‐40 265 ‐9 0 216
2008/09 ‐58 228 ‐2 ‐1 168
2009/10 ‐75 154 4 4 83
2010/11 ‐105 ‐68 ‐3 ‐6 ‐176
2011/12 ‐88 242 0 0 154
2012/13 ‐70 19 2 0 ‐49
2013/14 ‐65 82 6 0 23
2014/15 ‐151 80 6 0 ‐65
Total 2001‐15 ‐1,160 3,851 ‐5 ‐5 2,686
Average 2001/15 ‐83 275 0 0 192
Average 2007/12 ‐73 164 ‐2 ‐1 89
Average 2009/14 ‐81 86 2 0 7
Average 2010/15 ‐96 71 2 ‐1 ‐23
Average 2005/15 ‐76 163 0 ‐1 87 Source: Office for National Statistics
2.27 The Barton Willmore OAN Dashboard (April 2016) presented the results of a 10-year migration
trend taken from the period 2004-2014 which was the latest available at the time. The effect
of using a 10-year migration trend along with the HFR adjustments described earlier is to
increase housing need from the 2012-based starting point estimate of 122 dwellings per annum
to between 148 and 157 dwellings per annum.
2.28 EDC consider that no uplift is required to address alternative migration trends. However, we
believe the above evidence clearly supports an upwards adjustment.
2.29 To summarise, Barton Willmore consider demographic-led housing need for Eden
District to be between 148 and 157 dwellings per annum based on a 10-year
migration trend (2004-2014) incorporating a HFR adjustment. EDC consider
4 Local Plans Expert Group (LPEG) Report to the Communities Secretary and to the Minister of Housing and Planning, March 2016
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 8 August 2016
demographic-led need to be 132 dwellings per annum based on the CLG 2012-based household
projection (unadjusted) with a 10% uplift for market signals.
2.30 The updated 2014-based starting point estimate is based on trends from the 5-year period
2009-2014. Table 1.1 illustrates that average net annual migration to Eden over this period
(86 per annum) was lower than the from the previous 5-year period (2007-2012 = 164 net
migrants per annum) on which the 2012-based starting point estimate was based. This explains
why the 2014-based starting point estimate is lower than the previous 2012-based starting
point.
2.31 The evidence therefore suggests that consideration of a 10-year migration trend is also
necessary in light of the latest 2014-based projections to compensate for the impact of recent
recession which is clearly still impacting the demographic characteristics in Eden
2.32 It is important to point out that when Barton Willmore considers alternative migration trends
we do so by applying an average of migration rates by five-year age and gender – not the total
net migration figure presented in Table 1.1 (which is for ease of illustration only). The benefit
of the rates approach is that it enables the migrant profile specific to Eden District to be taken
into account and therefore does reflect outmigration of younger people and in migration of
older people which is characteristic of Eden.
iii) Assess Labour Force Capacity
2.33 PPG requires plan makers to make an assessment of the likely change in job numbers based
on past trends and/or economic forecasts, also having regard to the growth of the working age
population. Where the working age population that is economically active is less than projected
job growth, plan makers will need to consider how the location of new housing or infrastructure
could help address these problems (ID 2a-018). The implication is that housing numbers
should be increased where this will enable labour force supply to match projected job growth.
2.34 At the July 2016 hearings the Inspector agreed that EDC’s proposed job growth number was
acceptable. EDC proposed growth of between 2,293 and 2,564 jobs in total over the period
2014-2032. This is equivalent to growth of between 127 and 142 jobs per annum – a mid-
point of which is equivalent to 135 jobs per annum.
2.35 Barton Willmore accept the Council’s job growth figure of 135 jobs per annum
(2014-2032).
2.36 Barton Willmore’s analysis (as presented in the April 2016 OAN Dashboard) indicated that the
demographic-led OAN would not support any job growth at all (-37 jobs per annum) in Eden
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 9 August 2016
district, thereby warranting an uplift to housing need in order to support growth of 135 jobs
per annum. EDC also consider an uplift to demographic-led housing need is required to support
growth of 135 jobs per annum.
2.37 Neither Barton Willmore’s nor EDC’s demographic assessment of need will support
growth of 135 jobs per annum. An uplift to demographic housing need is therefore
required to support economic growth of 135 jobs per annum.
2.38 The two parties disagree in respect of the number of dwellings required to support growth of
135 jobs per annum. Barton Willmore identify a need for between 277 and 289 dwellings per
annum (depending on which HFR adjustment is applied), whereas EDC consider 200 dwellings
per annum are required.
2.39 Barton Willmore’s assessment has been undertaken using the POPGROUP and Derived Forecast
(DF) model. EDC criticise the POPGROUP methodology stating that the model automatically
assumes people come into an area to do new or vacant jobs which produces an unrealistic
figure.5 Barton Willmore disagree.
2.40 POPGROUP is well-established model used by over 90 users, including academic and public
service staff in housing, planning, health, policy, research, economic development and social
services. Cumbria County Council are users of the POPGROUP model. POPGROUP provides
the UK standard for local area demographic analysis and forecasting, complementing the
approaches used by the UK statistical agencies including the Office for National Statistics
(ONS).
2.41 In a job-led forecast the POPGROUP model calculates the required population growth needed
to support the future job target, taking account of commuting patterns, unemployment rates
and economic activity rates. In this type of forecast the model forecasts the population through
the cohort component methodology but increases (or decreases) the population accordingly to
meet the set job target by altering migration levels. HFRs are applied to the generated
population forecast in order to determine a housing requirement.
2.42 With regards to commuting, Barton Willmore applies the 2011 Census commuting ratio for Eden
District of 0.95. This ratio implies that Eden is a marginal net importer of labour.
Barton Willmore hold this ratio constant throughout the entire projection. This is common
practise because PPG requires a ‘policy off’ assessment of housing need. To alter the
commuting ratio in respect of recalling commuters would naturally have an impact on
5 Page 12, Eden District Council SHMA – Objectively Assessed Need Progress Note, June 2016
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 10 August 2016
neighbouring authorities and any assessment of need they may have undertaken, and would
be a ‘policy-on’ judgement. The ‘policy-off’ approach to commuting assumptions has been
confirmed by the Oadby & Wigston vs Secretary of State and Bloor Homes (paragraph 31 (i))
and was recently endorsed in the section 78 appeal decision in respect of Land off Tanton
Road, Stokesley (APP/G2713/A/14/2223624). PPG is keen to ensure unsustainable commuting
patterns are prevented (ID 2a-018). The application of a 0.95 commuting ratio within the
POPGROUP model means that the model will assume that 5% of the workforce required to
support growth of 135 jobs per annum will come from people who reside outside of Eden
district. Thereby the model is not providing a dwelling in Eden for those people who live
outside of the district but work in Eden.
2.43 With regards to unemployment, Barton Willmore use modelled estimates from the Annual
Population Survey (APS) assuming that unemployment returns from the 2011 rate (3.9%) to
the pre-recession average (2.0%) by 2021 and then held constant. This is considered to be a
prudent approach.
2.44 With regards to economic activity, Barton Willmore apply economic activity rates by 5-year age
group and gender for Eden District from the 2011 Census and project these forward following
the Office for Budget Responsibility (OBR) November 2015 projection. The OBR rates are used
by the Government to plan activities for the State and are therefore considered to be a robust
source. This view has also been supported by Inspectors in S78 appeals6. Furthermore, LPEG
recommend the use of the OBR rates. The OBR rates project an increase in economic activity
amongst older people to reflect the increase to State Pension Age. The use of the OBR rates
is again, considered to be a prudent approach.
2.45 Barton Willmore’s methodology is therefore robust.
2.46 In contrast EDC’s assessment uses a method developed in-house by the Council and is based
on the application of several basic conversion ratios based on relationships at the time of the
2011 Census. Unlike POPGROUP, EDC’s methodology has not been tested through any Local
Plan Examination, neither has the Council’s methodology been subject to any consultation.
EDC’s methodology results in a level of housing need that is significantly lower than the likely
level of economic-led housing need and will not therefore meet the districts full objectively
assessed needs or boost significantly the supply of housing.
6 Appeal Decision APP/V0728/W/15/3018546 Longbank Farm, Ormesby, Middlesbrough Appeal Ref: APP/W1525/W/15/3049361 Land off Plantation Road, Boreham, Essex
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 11 August 2016
2.47 To summarise, Barton Willmore consider economic-led housing need for Eden District
to be between 277 and 289 dwellings per annum to support growth of 135 jobs per
annum (2014-2032) based on the application of the adjusted 2012-based HFRs. EDC consider
economic-led need to be 200 dwellings per annum.
2.48 Application of adjusted 2014-based HFRs to the economic-led assessment of need would also
result in OAN c277-289 dwellings per annum, possibly slightly higher given that the 2014-
based HFRs are lower than the 2012-based HFRs.
2.49 An updated economic-led OAN is still expected to be in the region of 277-289 dwellings per
annum despite a lower 2014-based starting point. This is because economic-led OAN will still
be based on the requirement to support growth of 135 jobs per annum. The POPGROUP model
has identified that to support growth of 135 jobs per annum, Eden’s resident labour supply will
need to increase by 109 people per annum (taking into account Eden’s commuting,
unemployment and economic activity rates). To provide a resident labour supply of 109 people
per annum, the total population will need to increase by 401 people per annum (taking into
account Eden’s age profile). This assessment in effect remains the same even with an updated
starting point. The key difference will be in the application of 2014-based HFRs rather than
2012-based HFRS to determine the housing requirement.
iv) Assess market signals
2.50 PPG requires plan makers to give consideration to six market signals indicators stating that a
worsening trend in any of these indicators will require an upward adjustment to planned
housing numbers compared to ones based solely on household projections.
2.51 Barton Willmore presented an overview of market signals within the April 2016 OAN dashboard
which identified worsening affordability.
2.52 There is no clear guidance in the PPG on how much of an uplift to OAN should be applied to
account for adverse market signals. Barton Willmore’s approach is to consider how much of
an uplift the OAN (in this instance the economic-led OAN) provides to the starting point
estimate (the household projection) and past delivery of housing in Eden. OAN of between
277 and 289 dwellings per annum provides a 73-81% uplift against past delivery. The Barker
Review (2004) stated that need should exceed past supply by 86% to improve affordability.
2.53 No uplift is therefore made by Barton Willmore for market signals given the OAN of between
277 and 289 dwellings per annum does provide an upward adjustment to the household
projection. OAN of between 277 and 289 dwellings per annum is also considered to improve
affordability in Eden.
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 12 August 2016
2.54 EDC make a 10% market signals uplift to the household projection but this exercise is purely
academic given EDC’s final OAN of 200 dwellings per annum is economic-led and therefore
exceeds the demographic-led OAN (household projection plus 10% uplift).
v) Bringing the evidence together - Conclusion
2.55 Barton Willmore and EDC reach a different conclusion with regards to the demographic-led
OAN for Eden District. EDC calculate demographic need from the 2012-based ONS SNPP/ CLG
household projection (unadjusted) with a 10% uplift for market signals. This generates a need
for 132 dwellings per annum (2014-2032).
2.56 Barton Willmore consider the 2012-based ONS SNPP require adjustment in Eden District to
reflect a more stable migration trend on which to assess future need. Furthermore, the CLG
2012-based HFR have been found to suppress household formation for younger people in Eden
District which is not a prudent basis on which to plan. For this reason, Barton Willmore
calculate demographic need for Eden District using a 10-year migration trend (2004-2014) with
adjusted HFRs. This generates a need for between 148-157 dwellings per annum. Table 1.2
(at the end of this section) summarises the differences between the two assessments.
2.57 Despite the different conclusion in respect of demographic need, both parties agree
that demographic-led OAN will not support projected employment growth of 135
jobs per annum and that a further uplift to housing need is required.
2.58 Therefore both parties agree that full OAN for Eden district is an economic-led OAN. However,
Barton Willmore consider (based on the application of adjusted 2012-based HFRs) full OAN for
Eden district to be between 277 and 289 dwellings per annum and EDC consider full OAN to
be 200 dwellings per annum.
2.59 The main area of disagreement therefore is in respect of how each party calculates the number
of people required to support growth of 135 jobs per annum and in turn the number of
dwellings required to support these people. Barton Willmore has used the well-established
POPGROUP and DF model which is a sophisticated tool designed specifically to forecast
population, households and labour force and the relationship between them. In contrast, EDC
has applied a series of basic ratios from the 2011 Census which is considered to significantly
underestimate the full objectively assessed need for housing in Eden District as required by
PPG. EDC’s methodology is not robust, has not been consulted upon and has not been tested
through the Examination process. On this basis, it is considered Barton Willmore’s
methodology should be preferred and full OAN for Eden District should be taken to
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 13 August 2016
be between 277 and 289 dwellings per annum (2014-2032) based on the application
of adjusted 2012 HFRs.
2.60 Both Barton Willmore’s and EDC’s assessments of housing need were undertaken before the
release of the 2014-based SNPP and household projections. Barton Willmore are of the view
that this latest data release should be taken into account in accordance with PPG. However,
the new projections will only have an impact on the assessment of demographic-led housing
need. It is apparent from initial consideration of the published data that the 2014-based
projections project lower population and household growth than the 2012-based equivalents,
therefore resulting in a lower starting point estimate of need. However, Barton Willmore are
of the view that consideration of a 10-year migration trend remains necessary in light of the
2014-based release.
2.61 Given demographic need based on the 2012-based projections would not support growth of
135 jobs per annum, it can be concluded that neither will an updated demographic need based
on the 2014-based projections given they are lower. Therefore, it is anticipated that an uplift
to housing need would still be required to support EDC’s job target of 135 jobs per annum.
2.62 Full OAN for Eden District is therefore anticipated to remain in the region of between 277 and
289 dwellings per annum, even in light of the 2014-based population and household
projections. However, given the 2014-based HFRs have been found to suppress household
formation more greatly than the 2012-based HFRs (Figure 1.1 of this report), if the 2014-based
HFRs were utilised and the same HFR adjustments applied, housing need could potentially
increase above 277-289 dwellings.
POSITION STATEMENT OBJECTIVELY ASSESSED HOUSING NEED FOR EDEN DISTRICT
23955/A5/DM/kf 14 August 2016
Table 1.2: Comparison of Barton Willmore and EDC’s OAN assessment (2014-2032)
SHMA (final) - Sept 2015
Starting point: 2012-based 110 households per annum equivalent to 120 dpa
2014-based n/a
2011 Census8.90%
1. Demographic OAN 132 dpa
Population projection(ID2a 016, 017). Sensitivity testing of local migration and population change, taking account of the most recent demographic evidence from ONS
2012-based SNPP
Household Formation Rates (HFRs)(ID2a 015, 016) may have been supressed historically by undersupply and worsening affordability of housing. As a result, the CLG 2012-based household formation rate projections may also be suppressed. If so they must be adjusted upwards so that the suppression is removed.
CLG 2012-based household formation rates (all age groups)
Other Uplift of 10% applied to household projection to address market signals
2. Economic OAN 194-206 dpa
Total growth of between 2,293 and 2,564 jobs (equivalent to between 127 and 142 jobs per annum)2,293 derived by applying ratio of 0.94 workers per household to 2012-based household projection.2,564 derived by applying growth rate of 9.16% (uncertain of source) to 2011 Census count of resident workforce plus in-commuters.
Economic activity rates2011 Census economic activity rates for males and females aged 16-74 years held constant
Unemployment ratesn/aSHMA's Jobs to Dwellings Calculator doesn't apply unemployment rate directly
Commuting ration/aSHMA's Jobs to Dwellings Calculator doesn't apply commuting ratio directly
3. Market signals uplift 0
Worsening Market Signals observed?(ID2a 019, 020) of undersupply relative to demand that are worsening trigger an upward adjustment to planned housing numbers that are based solely on household projections. The more significant the affordability constraints, the larger the additional supply response should be
Yes10% uplift applied to starting point to derive
demographic OAN
Full OAN compared to average annual past completions (03/04 to 14/15)
25%
Full OAN compared to starting point 66%
Full OAN 200 dpa
Job Forecast(ID2a 018) based on past trends and or projections should be taken into account. The OAN must be capable of accommodating the supply of working age population that is economically active (labour force supply), if it does not them it should be adjusted upwards.
Vacancy/ second homes rate
80 households per annum equivalent to 88 dpa
110 households per annum equivalent to 122 dpa
BARTON WILLMORE
YesHowever, no specific uplift applied for market
signals because economic OAN provides a significant uplift to starting point and past delivery. Barker Review suggested 86%
increase in housing supply would improve affordability
CLG 2012-based household formation rates adjusted for 25-44 year olds using three sensitivity tests (full return to 2008 rates for males and females, 50% return to 2008 rates for males and females and return to 2001 rates for males only)
Long term migration trend (2004-2014) and 2012-based SNPP
277-289 dpa
Growth of 135 jobs per annum
Mid-point of job growth presented in SHMA (Table 21, page 53)
2011 Census rates by 5 year age group and sex for Eden projected following OBR Nov 15 national projection which assumes increased 3.9% (2011) returning to pre-recession average of 2.0% by 2021 based on ONS data from APS for Eden2011 Census value of 0.95 fixed over the forecast period (assumes Eden is net importer of labour)
0
131-141%
277-289 dpa
148-157 dpa
9.54%CLG 2014
73-81%
APPENDIX 2
KEY HUBS OVERVIEW OF SITES [STORY HOMES]
Appendix 2 – Key Hubs Site Assessment (Story Homes) April 2017
Site Reference Site Name LPA Capacity SHLAA Capacity
Armathwaite
LAR3a Land to the north east of Armathwaite 15 SHLAA - 17
• Access and landscape constraints identified
• No footpath along the highway
• Within a national speed limit area
• Availability in 2014 – no application submitted
• Deemed by LPA to be “uncertain” in terms of suitability
Brough and Church Brough
LBR1 Rowan House 10 SHLAA – 10
• Site has been allocated for housing since the 1996 Local Plan with planning permission obtained for 6
dwellings (outline) in 1989 (89/0334) which was renewed in 1995 but has expired (95/0009). Since this
time, the Site has failed to come forward for delivery.
• Mitigation is required in relation to noise due to A66
• Landowner unknown and no developer interest in site
• Visibility/access constraints
• Availability and Achievability unknown
-
LBR2 Castle View 6 SHLAA - 13
• Site has been allocated for housing since the 1996 Local Plan but has not been delivered
• Cap on development by Upper Eden NP (3.48 dpa)
• Considered that due to this cap, no further development can come forward until the later years of the
plan
• Noise impact, mitigation required
• Flood risk
• PROW restricts the deliverability of the site and requires diversion
• Application for 6 dwellings withdrawn in 2014 (14/0434)
Appendix 2 – Key Hubs Site Assessment (Story Homes) April 2017
Culgaith (no allocations proposed*) 1
LCU1 Land at Rose Bank Farm 14 SHLAA - 14
• Bat activity on site
• Listed building on site
• Potential contamination
• Planning permission for barn conversions has expired
• Redevelopment would require the conversion and reuse of traditional buildings.
LCU3 Land at Lime Tree Farm 18 SHLAA - 18
• Bat activity on site
• Potential visual impact and impact on visual character
• Potential contamination
• PROW ion western edge
• Site promotion in 2007, no further information available in relation to the development of the site
LCU6 Land adjacent to Loaning Head Courtyard 5 SHLAA - 5
• Landscape and visual impact
• Access constraints due to location on a bend
• History of refusal on site for residential development – 4 applications refused
Hesket
LHH2 Land adjacent to Elm Close 15 SHLAA – 0
• Discounted as a site within the SHLAA due to unconfirmed availability
• Significant constraints in terms of highway capacity due to existing and committed developments
Kirkby Thore
LKT1 Land opposite the Primary School 45 SHLAA - 18
• Surface flooding
• Landscape and visual impact
• Archaeological potential – proximity to Kirkby Thore Roman Fort Scheduled Ancient Monument
1 Discounted from overall Key Hubs Allocations
Appendix 2 – Key Hubs Site Assessment (Story Homes) April 2017
• Visibility constraints due to access on a bend
• Traffic calming measures would be required
• Site has been allocated since 1996 with no intention to progress with its development
Langwathby
• No allocations proposed – 28 dwellings to be delivered through NP at Langwathby Hall Farm
• This site is identified as suitable for 14 dwellings only
• Landscape and visual impact
• No planning history
• Not an efficient use of land
SHLAA - 14
Lazonby
• No allocations proposed to be delivered through NP
Nenthead
LNE1 Moredun Garage 5 SHLAA - 6
• Promoted through SHLAA
• Contamination and flooding issues
• AONB
• Surface water flooding
• Currently leased to blacksmith
• SHLAA identifies it as unviable in short -term
• Net loss of local employment land
LNE3 Wright Brothers Garage 13 SHLAA - 13
• Brownfield
• Planning permission for a new bus depot (12/0599)
• Unviable for residential without additional funding
Plumpton
LPL2 Land adjacent to Byrnes Close 28 SHLAA – 30
Appendix 2 – Key Hubs Site Assessment (Story Homes) April 2017
Shap
LSH1 West Lane 8 SHLAA – 8
• Part of 1996 LP designation
• Flooding and drainage issues
• PROW
• Outline pp for affordable dwellings (6) was submitted and withdrawn
LSH5 Land behind Woodville Terrace 14 SHLAA - 14
• Noise impact
• Flooding issues
• Heritage considerations
• Access constraints
• No immediate intention from landowner to develop site
LSH13 Land behind Carl Lofts 15 SHLAA - 15
• No vehicle access
• Noise impact from railway
• Identified as being only of long-term potential
LSH14 Land adjacent to library 5 SHLAA - 5
• Residential amenity issues
LSH16 Former Food Factory 15 SHLAA - 15
• Contamination
• Visual impact
Stainton
LST8 Land to west of Lakeland Free Range Egg Company 20 SHLAA – 10
• Greater new eastern approach to village
• Incorrect reference – should be LST9
• Landscape and visual impact
Appendix 2 – Key Hubs Site Assessment (Story Homes) April 2017
Tebay
LTE5a Land adjacent to Cross Keys Inn 12 SHLAA – 9
• Planning permission but s106 isn’t signed since 2014
LTE5 Land adjacent to Church Rise 9 SHLAA – 9
• Reference should be LST6
• FROW
• Existing uses on site
• Topo constraints
• Visual and landscape impact
• Highway improvements
• PP for 4 dwellings
Overall supply [excluding italics] 234 192