Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry...

17
Earned Value Analysis by John Cornman

Transcript of Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry...

Page 1: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Earned Value Analysisby

John Cornman

Page 2: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Introduction

• “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its completion date and final cost, and provide schedule and budget variances along the way.

• Based on just 3 data points, it can provide consistent, numerical indicators with which you can evaluate and compare projects.

Page 3: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

The 3 fundamental metrics

• Budgeted Cost of Work Performed.

• Budgeted Cost of Work Scheduled.

• Actual Cost of Work Performed.

Page 4: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Budgeted Cost of Work Performed

• This is the “Earned Value.”

• Abbreviated as BCWP.

• For completed work, it is the cost originally budgeted to accomplish that work.

• “How much work was actually done?”

Page 5: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Budgeted Cost of Work Scheduled

• Abbreviated BCWS.

• It is the total budgeted cost up to the analysis date.

• Approximated by the total budget multiplied by the fraction of total project duration at the analysis date.

• “How much work should have been done?”

Page 6: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Actual Cost of Work Performed

• Abbreviated ACWP.

• What it actually cost to accomplish all the work completed as of the analysis date.

• “What did the work that was actually done actually cost?”

Page 7: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Derived Metrics

• Schedule Variance (SV)

• Schedule Performance Index (SPI)

• Cost Variance (CV)

• Cost Performance Index (CPI)

Page 8: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

A Few More Acronyms

• BAC - Budget At Completion • = Total Original Budgeted Cost• Same as BCWS at completion

• EAC - Estimate At Completion• = Cumulative Actuals + Estimate-To-Complete

• VAC - Variance At Completion• = Forecast of final cost variance

Page 9: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Doing The Math• SV = BCWP - BCWS

• Negative means Behind Schedule

• SPI = BCWP / BCWS• Less than 1.00 means Behind Schedule

• CV = BCWP - ACWP• Negative means Over Budget

• CPI = BCWP / ACWP• Less than 1.00 means Over Budget

• EAC = BAC / CPI

Page 10: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

An Example: Lemonade

• Make 1,000 cups over 50 days

• Steady rate of 20 cups per day

• Budgeted cost per cup is $0.50

• Total project budget is $500

Page 11: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Lemonade Progress

• At end of day 10:

• 150 cups have been made

• Total actual cost is $90 (ACWP)

Page 12: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Lemonade Status

• BCWS = $100• 10 days x 20 cups per day x .50/cup budget

• BCWP = $75 (Earned Value)• 150 cups x .50/cup budget

• SV = BCWP - BCWS = -$25• SPI = BCWP / BCWS = 0.75• CV = BCWP - ACWP = $75 - $90 = -$15• CPI = BCWP / ACWP = 0.833

Page 13: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Lemonade Forecast

• EAC = BAC / CPI = $500 / 0.833 = $600

• VAC = BAC - EAC = $500 - $600 = $100 (unfavorable)

• Schedule at Completion =50 / SPI = 50 / 0.75 = 66.67 days

Page 14: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

MS Project 98 Support

ID Task Name BCWS BCWP ACWP SV CV EAC BAC VAC

1 MS Project 98 Example $1,920.00 $840.00 $960.00 ($1,080.00) ($120.00) $2,760.00 $2,400.00 $360.00

F S SNo

Page 15: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Five Simple Criteria forEarned Value Applications

1.Define (scope) the project. . .with a WBS

2.Plan and schedule the project scope

3.Budget cost account plans to functions

4.Establish and maintain a performance baseline

5.Monitor performance and forecast final results

Fleming & Hoppleman. 1996. Earned Value Management. PMI

Page 16: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Page 17: Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.

Earned Value Management

http://www.acq.osd.mil/pm/