Earned Value Analysis

32
Earned Value Analysis Earned Value Analysis compares the Current Project status with the Baseline Plan Earned Value for a task = (budgeted cost of task)x(% completion of task) Task Progress Conventions Estimated by a knowledgeable unbiased assessor X% complete when task started and other (1-X)% when task finished. Usually 50-50 or 0-100 Earned Value for the entire project is the summation of earned values for all tasks 07/04/22 Ardavan Asef-Vaziri 7-1

description

Earned Value Analysis. Earned Value Analysis compares the Current Project status with the Baseline Plan Earned Value for a task = (budgeted cost of task)x(% completion of task) Task Progress Conventions Estimated by a knowledgeable unbiased assessor - PowerPoint PPT Presentation

Transcript of Earned Value Analysis

Page 1: Earned Value Analysis

Earned Value Analysis

Earned Value Analysis compares the Current Project status with the Baseline Plan

Earned Value for a task =

(budgeted cost of task)x(% completion of task)Task Progress Conventions

Estimated by a knowledgeable unbiased assessor X% complete when task started and other (1-X)%

when task finished. Usually 50-50 or 0-100

Earned Value for the entire project is the summation of earned values for all tasks

04/21/23 Ardavan Asef-Vaziri 7-1

Page 2: Earned Value Analysis

PV, EV, and AC

PV: Planned Value, baseline cost of scheduled work. Also known as Budgeted Cost of Work Scheduled (BCWS)

AC: Actual cost of work performed. Also shown by (ACWP)

EV: Earned Value, budgeted cost of work performed. Also shown by (BCWP)

04/21/23 Ardavan Asef-Vaziri 7-2

Page 3: Earned Value Analysis

Control System Example 1

Week 2: Task expenses = 460 worker-hours

370

380

390

400

410

420

430

440

450

460

470

1 2 3 4

Week

Cos

t (i

n w

ork

er-h

ours

)

WeekPlanned Cost

(BCWS) Actual Cost

Cumulative Actual Cost

(ACWP)

1 400 420 4202 400 460 880

Is the task “out of control”?

Actual

Planned

04/21/23 Ardavan Asef-Vaziri 7-3

Page 4: Earned Value Analysis

Control System Example 1

Week 3: Task expenses = 500 worker-hrs

WeekPlanned cost

(worker-hours)Actual cost

(worker-hours)Cumulative cost (worker-hours)

1 400 420 4202 400 460 8803 400 500 1380

Again, is the task “out of control”?

0

100

200

300

400

500

600

1 2 3 4

Week

Wor

ker-

hour

s

Actual

Planned

04/21/23 Ardavan Asef-Vaziri 7-4

Page 5: Earned Value Analysis

Controlling Projects

Key decisions in controlling performance in project management: What is the optimal review frequency? What are appropriate acceptance levels at each review stage?

“Both over-managed and under-managed development processes result in lengthy design lead time and high development costs.”

R.H. Ahmadi, R. Wang. 1999. Managing Development Risk in Product Design Processes. Operations Research 47, 235-246

04/21/23 Ardavan Asef-Vaziri 7-5

Page 6: Earned Value Analysis

6

Types of System Variation

Common cause variation: “in-control” or normal variation

Special cause variation: variation caused by forces that are outside the system

Treating common cause variation as if it were special cause variation is called “tampering”

Tampering always degrades the performance of a system – W.E. Deming

04/21/23 Ardavan Asef-Vaziri 7-6

Page 7: Earned Value Analysis

7

Performance Metrics for Example 1

PV: Planned Value, baseline cost of scheduled work. AC: Actual cost of work performed. EV: Earned Value, budgeted cost of work performed. PWC: percentage of work completed.

Week PV AC PWC EV1 400 420 23% 3682 800 880 50% 8003 1,200 1,380 85% 13604 1,600 1,500 100% 1600

04/21/23 Ardavan Asef-Vaziri 7-7

Page 8: Earned Value Analysis

Schedule Variance

Schedule variance: difference between value of work completed and value of scheduled work SV = EV – PV

04/21/23 Ardavan Asef-Vaziri 7-8

Week PV AC PWC EV SV1 400 420 23% 368 -322 800 880 50% 800 03 1,200 1,380 85% 1360 1604 1,600 1,500 100% 1600 0

Page 9: Earned Value Analysis

Cost Variance

Cost variance: difference between value of work completed and actual expenditures CV = EV – AC

04/21/23 Ardavan Asef-Vaziri 7-9

Week PV AC PWC EV SV CV1 400 420 23% 368 -32 -522 800 880 50% 800 0 -803 1,200 1,380 85% 1360 160 -204 1,600 1,500 100% 1600 0 100

Page 10: Earned Value Analysis

Total Variance

Total variance: Cost Variance–Schedule Variance

=(EV-AC)-(EV-PV) TV = PV – AC

04/21/23 Ardavan Asef-Vaziri 7-10

Week PV AC PWC EV SV CV TV1 400 420 23% 368 -32 -52 -202 800 880 50% 800 0 -80 -803 1,200 1,380 85% 1360 160 -20 -1804 1,600 1,500 100% 1600 0 100 100

Page 11: Earned Value Analysis

Earned Value Chart

04/21/23 Ardavan Asef-Vaziri

TimeNow

Dol

lars

Schedulevariance

Costvariance

PV(baseline)

AC

EV

Actual cost

Value completed (Earned Value)

7-11

Page 12: Earned Value Analysis

Earned Value Chart 2

04/21/23 Ardavan Asef-Vaziri

Time

Dol

lars

PVAC

EV

7-12

Page 13: Earned Value Analysis

Earned Value Chart 3

04/21/23 Ardavan Asef-Vaziri

Time

Dol

lars

PV

AC

EV

7-13

Page 14: Earned Value Analysis

Earned Value Chart 4

04/21/23 Ardavan Asef-Vaziri

Time

Dol

lars

PV

AC

EV

7-14

Page 15: Earned Value Analysis

Earned Value Chart 5

04/21/23 Ardavan Asef-Vaziri

Time

Dol

lars

PV

AC

EV

7-15

Page 16: Earned Value Analysis

Earned Value Chart 6

04/21/23 Ardavan Asef-Vaziri

Time

Dol

lars

PV

AC

EV

7-16

Page 17: Earned Value Analysis

Control System Example 2

Progress report at the end of week #5:

Cumulative Percent of Work Completed:

Worker-Hours Charged to Project:

04/21/23 Ardavan Asef-Vaziri 7-17

Page 18: Earned Value Analysis

Control System Example 2

We ekPlan 1 2 3 4 5 6 7 8 9 10 TotalTask A 6 6 6 8 10 36Task B 12 12 12 36Task C 10 10 12 12 12 56Scheduled work-hrs 6 6 6 20 22 22 10 12 12 12PV work-hrs 6 12 18 38 60 82 92 104 116 128

04/21/23 Ardavan Asef-Vaziri 7-18

Page 19: Earned Value Analysis

Control System Example 2

We ekPlan 1 2 3 4 5 6 7 8 9 10 TotalTask A 6 6 6 8 10 36Task B 12 12 12 36Task C 10 10 12 12 12 56Scheduled work-hrs 6 6 6 20 22 22 10 12 12 12PV work-hrs 6 12 18 38 60 82 92 104 116 128Actual 1 2 3 4 5 6 7 8 9 10Task A 5 6 8 10 10Task B 15 10Task CActual work-hrs 5 6 8 25 20AC 5 11 19 44 64

04/21/23 Ardavan Asef-Vaziri 7-19

Page 20: Earned Value Analysis

Control System Example 2

04/21/23 Ardavan Asef-Vaziri 7-20

We ekPlan 1 2 3 4 5 6 7 8 9 10 TotalTask A 6 6 6 8 10 36Task B 12 12 12 36Task C 10 10 12 12 12 56Scheduled work-hrs 6 6 6 20 22 22 10 12 12 12PV work-hrs 6 12 18 38 60 82 92 104 116 128Actual 1 2 3 4 5 6 7 8 9 10Task A 5 6 8 10 10Task B 15 10Task CActual work-hrs 5 6 8 25 20AC 5 11 19 44 64% work completed 1 2 3 4 5 6 7 8 9 10Task A 0.15 0.3 0.4 0.6 0.8Task B 0.25 0.65Task C% work completed 1 2 3 4 5 6 7 8 9 10Task A 5.4 10.8 14.4 21.6 28.8Task B 9 23.4Task CEV 5.4 10.8 14.4 30.6 52.2

SV -0.60 -1.20 -3.60 -7.40 -7.80CV 0.40 -0.20 -4.60 -13.40 -11.80

Page 21: Earned Value Analysis

Schedule and Cost Indices

SPI: Schedule Performance Index SPI = EV / PV CPI: Cost Performance Index CPI = EV / AC

04/21/23 Ardavan Asef-Vaziri 7-21

We ekPlan 1 2 3 4 5 6 7 8 9 10PV work-hrs 6 12 18 38 60 82 92 104 116 128AC 5 11 19 44 64EV 5.4 10.8 14.4 30.6 52.2

SV -0.60 -1.20 -3.60 -7.40 -7.80CV 0.40 -0.20 -4.60 -13.40 -11.80SPI 0.900 0.900 0.800 0.805 0.870CPI 1.080 0.982 0.758 0.695 0.816

Page 22: Earned Value Analysis

Budget and Estimate at Completion

04/21/23 Ardavan Asef-Vaziri 7-22

BAC: Budget At Completion EAC: Estimate At Completion ETC: Estimated to Completion

Page 23: Earned Value Analysis

Updating Forecasts: Future is the same as actual

Assumes that the progress in future is the same as actual

04/21/23 Ardavan Asef-Vaziri 7-23

9.92649.156

9.156816.0

128

ACEACETC

EAC

CPI

BACEAC

Page 24: Earned Value Analysis

Updating Forecasts: Future is the same as schedule (Example 2)

Assumes that the progress in future is the same as schedule

04/21/23 Ardavan Asef-Vaziri 7-24

8.65648.139

8.1398.11128

ACEACETC

EAC

CVBACEAC

Page 25: Earned Value Analysis

TIME To Completion: (Example 2)

04/21/23 Ardavan Asef-Vaziri 7-25

Weeks5.655.11CompletionToTime

CompletionToTime

5.1187.0

10

nowp

p

pp

-TET

ET

SPI

TET

Assumes that the progress in future is the same as actual

Tp: Project duration

ETp: Estimated project duration

Tnow: Elapsed time

Page 26: Earned Value Analysis

Updating Forecasts: Optimistic Viewpoint (Example 2)

04/21/23 Ardavan Asef-Vaziri 7-26

Weeks75.5575.10CompletionToTime

-CompletionToTime

75.10)75.0(10

7500.87

55

-Variance Time

nowp

p

pp

nownow

TET

ET

tVTET

.tV

SPI

TTtV

Assumes that the progress in future is the same as schedule

Page 27: Earned Value Analysis

Example 3

Budgeted cost for finished task = $850K. Actual cost to date = $550K; Task is 70% complete, but was scheduled to be 80% complete by now. The project was scheduled for 12 months. It is now end of month 10.

AC = 550, PV = 0.8×850 = 680, EV = 0.7×850 = 595

Cost variance = EV – AC = +45

Schedule variance = EV – PV = -85

CPI = EV / AC = 1.082

SPI = EV / PV = 0.875

04/21/23 Ardavan Asef-Vaziri 7-27

Page 28: Earned Value Analysis

Example 3

BAC= 850. AC = 550; % Complete = 70%, Scheduled % Complete = 80%. Scheduled Duration = 12 months, now = end of month 10. PV = 0.8×850 = 680, EV = 0.7×850 = 595

CV = EV – AC = +45, SV = EV – PV = -85

CPI = EV / AC = 1.082, SPI = EV / PV = 0.875

Estimated Remaining Cost = 850/1.082 -550= 236

Estimated Remaining Time = Tp/0.875 –Tnow= 12/0.875-10 = 13.71-10 = 3.71 months

Estimated Remaining Cost = 850-CV -AC= 850-(45) – 550 = 255

tV = Tnow - Tnow /0.875 =- 1.43

Estimated Remaining Time = Tp –tV – Tnow = = 12- (-1.43) – 10 = 3.43 months

04/21/23 Ardavan Asef-Vaziri 7-28

Page 29: Earned Value Analysis

Critical Ratio

The critical ratio is the product of a schedule ratio and a cost ratio. Indicates when a task or process is becoming unacceptable, typically when the ratio drops below 1.

04/21/23 Ardavan Asef-Vaziri

cost actual

progress actualfor cost budgeted

progress scheduled

progress actual

04/21/23 Ardavan Asef-Vaziri 7-29

If both progress and budget are on the same curve, then it is

ACPV

EV

AC

EV

PV

EV

2

Page 30: Earned Value Analysis

Monitoring the Critical Ratio

Although Task 1 is behind schedule, the cost is correspondingly below budget so everything is fine if lateness is no problem for this activity.

Task 2 is on budget but progress is lacking so too much money was spent than should have been spent; when the project is completed, it will probably go over budget.

04/21/23 Ardavan Asef-Vaziri04/21/23 Ardavan Asef-Vaziri 7-30

Page 31: Earned Value Analysis

Critical Ratios With Control Limits

04/21/23 Ardavan Asef-Vaziri 7-31

Page 32: Earned Value Analysis

Cost Control Chart

04/21/23 Ardavan Asef-Vaziri 7-32