Early Commissioning of ATLAS First North American ATLAS Physics Workshop Tucson J. Pilcher...
-
Upload
arline-cannon -
Category
Documents
-
view
220 -
download
3
Transcript of Early Commissioning of ATLAS First North American ATLAS Physics Workshop Tucson J. Pilcher...
Early Commissioning of ATLAS
First North American ATLAS Physics Workshop
Tucson
J. PilcherUniversity of Chicago
20-Dec-2004 J. Pilcher 2
Early Commissioning of ATLAS
10 Dec 04
20-Dec-2004 J. Pilcher 3
Commissioning Goals Establish operation of full systems
Readout Calibration systems Low Voltage, High Voltage Control and Monitoring Cryogenics, Gas, Cooling
Establish initial calibrations Mev/ADC count Alignment and timing
Chamber or sensors within a detector system Relative alignment and timing of different detector systems
Demonstrate performance levels Noise levels Physics signals
20-Dec-2004 J. Pilcher 4
Commissioning Stages
Calibration systems only Cosmic ray muons
MIP signals and inelastic interactions Stand-alone detector systems (2005-6) Full ATLAS detector (2007)
Initial beam operation Single beam operation
Beam-gas interactions Beam halo muons
Beam-beam operation Minimum bias interactions
Early beam-beam collisions Use physics signals ( , -j, Z-j, j-j, ) Z → l +l − W → jj
20-Dec-2004 J. Pilcher 5
This talk Concentrate on first three stages Other talks on commissioning with beam-beam physics signals Special emphasis on calorimeter systems
More details at: Tatra Workshop:
http://agenda.cern.ch/fullAgenda.php?ida=a041267
Overview week at Freiburg: commissioning session http://agenda.cern.ch/fullAgenda.php?ida=a041780#s0
Overview week at Prague: commissioning session http://agenda.cern.ch/fullAgenda.php?ida=a03190#s2
This talk draws on the work of many people R. Teuscher, R. McPherson, J. Huston, …
20-Dec-2004 J. Pilcher 6
Preliminary commissioning already being done Combined test beam in 2004 Tilecal operation on cosmic muons in Bldg. 185 LAr operation on cosmic muons in Bldg. 180 Muon chamber operation with cosmics TileCal barrel on HF truck in UX15
Commissioning is iterative with larger scale integration at each step
20-Dec-2004 J. Pilcher 7
Now: TileCal Commissioning on HF Truck in UX15
Photo from September 28, 2004
Record data from UX15 testing TTC, CANbus, HV, laser fibres via LED, BCID @ 100 kHz L1A, CIS, readout noise, …
Charge InjectionPulses OK
Noise Test OK
RM
S (
AD
C c
ount
s)
20-Dec-2004 J. Pilcher 8
Barrel calorimeters move to z=0 August 2005 when BT is assembled
Detectors fully assembled and equipped with on-detector electronics
Connect to services Stand-alone commissioning with calibration systems
Eg. for TileCal (1/2 the system)– Charge injection to all readout channels (4K in barrel)– Cesium source activates tiles and fibers (220K in barrel)– Laser system activates each PMT (4K in barrel)
First large-scale detailed commissioning
20-Dec-2004 J. Pilcher 9
Charge Injection Calibration of TileCal
Pulse individual channels over full dynamic range establish gain, linearity, stability
Uncorrected channel-to-channel uniformityRMS ~ 1.3 counts/pC (1.6%)
Gain variation over 4 months of CTBRMS ~ 0.2%
20-Dec-2004 J. Pilcher 10
Cs Calibration of TileCal
Cs-137 source illuminates individual tiles
Stainless tubes pass through all tiles in the system
Source capsule driven through tubes hydraulically
Single tile response measured at 2% level
Cell response measured at 0.3% level
Week-to-week variations in cell response ~ 0.5%
20-Dec-2004 J. Pilcher 11
Cosmic Ray Commissioning
Full G3 simulation done by Rob McPherson and Pavel Nevski
20-Dec-2004 J. Pilcher 12
Cosmic Ray Commissioning
Rates are substantial 2.3 KHz for a hit anywhere in detector 0.5 Hz for |Z| < 60 cm, R < 20 cm
Natural to trigger with muon system RPCs + … Global ATLAS cosmic muon run planned for 40 days in
April 2007 before LHC starts Attractive to run barrel calorimeters on cosmics from late
2005 Before RPCs available Evaluated trigger using TileCal
back-to-back trigger towers
20-Dec-2004 J. Pilcher 13
TileCal Response to Muons
Test beam data for 180 GeV muons at =0.05
Energy depends on path length through calorimeter
1K muons in a tower gives response to 1%
S/N ~ 40
Tower Energy (pC) (~1.1 pC/GeV)
20-Dec-2004 J. Pilcher 14
TileCal Cosmic-Muon Trigger
Consider back-to-back TileCal towers x =0.1 x 0.1, full calorimeter depth Especially useful because tracks pass close to interaction point Analyze McPherson/Nevski simulation for rate and event properties
S. Zenz (Chicago undergraduate)
20-Dec-2004 J. Pilcher 15
TileCal Cosmic-Muon Trigger Require 2 back-to-back towers with E > 1.5 GeV
Lower peak corresponds to additional towers struck (corners clipped)
Rate is ~ 130 /hr for 16 top + 16 bottom modules in coincidence
~ 100K / month
20-Dec-2004 J. Pilcher 16
-distribution of muons -distribution of muons passing Tilecal triggerpassing Tilecal trigger
-0.1-0.2-0.3-0.4-0.5
PX14 PX16
D = 18 m D = 12.6 m
Effect of PX14 shaft isclearly seen
TileCal Cosmic-Muon Trigger
20-Dec-2004 J. Pilcher 17
Typical Events
20-Dec-2004 J. Pilcher 18
Typical Events (2/2)
Example of muon scattering in detector
20-Dec-2004 J. Pilcher 19
Muons in LAr BarrelDue to Accordion geometry, muons are reconstructed in middle compartmentby summing two cells in .
S()/N 7
Barrel middle compartment
Test-beam data
With 100 events muon signal in LAr can be measured with ~ 3% precision
• For first shake-down
Could use cosmic ray muons to measure first LAr physics pulse shapes and compare to calibration pulses.
Useful to reconstruct combined muons in LAr + TileCal to match EM energy scale and timing.
Note : S/N ratio too small in strip and back compartments
20-Dec-2004 J. Pilcher 20
Muons in LAr Using TileCal Trigger TileCal Trigger tower size (0.10.1) corresponds to 44 LAr middle
cells Resulting maximum non-projectivity : 3º, muons can cross at most 2
cells in and in non-projectivity probably not a problem, due to natural sharing
between cells (two cells are summed)
CellEnergy
Studies of rate in LAr using TileCal cosmic trigger (back-to back towers) by Philippe Schwemling and Emmanuel Monnier. Est. ~ 6 months run
20-Dec-2004 J. Pilcher 21
With ~ 100 muons/cell in middle compartment
• Check calorimeter timing to < 1 ns input to optimal filtering in ROD• Check calorimeter position in / wrt other sub-detectors to < 1 mm
t = 1.62 ns/E (GeV) + 19 ps(from calibration)
MuonsE~300 MeVt ~ 6 ns
Test-beam data
1% precision measured with ~1000 with ~ 5000 : 0.5 % precision (~ 100 /cell integrated over )
20-Dec-2004 J. Pilcher 22
Hardware Needed for TileCal Cosmic Trigger
Electronics drawers in barrel (128) LV power (in TileCal fingers)
Bulk LV power (200V for USA15) Cabling and fibers TTC hardware
Standalone clock LVL1 trigger interface hardware
Patch panels to separate tower and muon signals Receiver boards (64 towers each) Initially use custom trigger logic for cosmic ray running
ROD/LVL2 hardware ROD modules, ROD crate and controller (ROD crate DAQ) Output hardware from ROD crate to PC via Ethernet
Later use ROBIN/ROS
20-Dec-2004 J. Pilcher 23
TileCal Muon Trigger Logic
LVL1 trigger not designed to run on back-to-back muons Adapting it would be a diversion Also scheduled to arrive late compared to initial stand-alone
calorimeter operation
Build some simple coincidence logic
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
0 20 40 60 80 100 120
Threshold (mV)
Trigger Efficiency
Test by injecting muon signal into trigger tower
Vary tower threshold and check efficiency
20-Dec-2004 J. Pilcher 24
Time Table for Cosmic Ray Commissioning
TileCal barrel complete Mar-06 (following checkout) Stand alone operation begins
LAr barrel complete Aug-06 (following checkout) Stand alone operation begins
Global commissioning Dec-06 through Feb-07 ATLAS cosmic run
Mar-07 through Apr-07
ATLAS ready for beam 4/27/07
20-Dec-2004 J. Pilcher 25
First commissioning with single beam
Beam halo muons Generated by machine group Simulated in ATLAS
Beam gas events
Beam-gasBeam-halo
Scoring plane
20-Dec-2004 J. Pilcher 26
A “typical” beam-gas event
Beam-gas collisions are essentially boosted minimum-bias events low-pT particles
Rate : ~ 2500 interactions/m/s
20-Dec-2004 J. Pilcher 27
Beam-gas Rates & Properties
Vertex ZVertex Z Rate (Hz)Rate (Hz) TotalTotal (2 months, (2 months, =30%)=30%)
23 m23 m 1.2x101.2x1055 2.1x1011
3 m 1.6x104 2.4x1010
20 cm 1.1x103 1.6x109
pT > 1 GeV 1.0x103 1.5x109 inside 3m pT > 1 GeV 0.3x103 5.6x108 inside 3m
ET spectrum in ECAL E spectrum in FCAL
ET charged particles
20-Dec-2004 J. Pilcher 28
Beam Halo Muons
Total rate 105 kHz E > 10 GeV 16 kHzE > 100 GeV 1 kHzE > 1 TeV 10 Hz
L=1034
Muons at cavern entranceMuons at cavern entrance
Especially useful for endcaps and ID disks and wheels
20-Dec-2004 J. Pilcher 29
Beam-Halo Rates
Estimate rates for 200 times less current than design Totals in table for 2 month run at 30% efficiency
Detector Rate (B-field off )
Total (B-field off)
Rate (B-field on)
Total (B-field on)
MDT barrel 15 Hz 2.5x107 72 Hz 1.5x108
MDT end-cap
145 Hz 2.5x108 135 Hz 2.5x108
Pixel/SCT 1.8/17 Hz 3x106 / 3x107 2/19 Hz 3x106 / 3x107
EM E > 5 GeV
2 Hz 3.5x106 1 Hz 1.7x106
Tile/HEC E > 20 GeV
1.7/1.2 Hz 2.9/2.1x106 1.6/0.9 Hz 2.8/1.6x106
20-Dec-2004 J. Pilcher 30
Triggering on Beam Halo and Beam-Gas events
Minimum-bias scintillators being added in front of LAr end caps
z ~ ± 3.5 m 14 cm < R < ~ 100 cm ~1.9 < < ~3.9 8 channels in , 2 channels in Readout via TileCal electronics drawer
Joey Huston is project leader on this.
20-Dec-2004 J. Pilcher 31
Conclusions
Good prospects for progressive commissioning process Stand alone detector systems with calibration systems and
cosmic muons Global detector with cosmic muons Beam halo muons and beam-gas events in early 2007 Minimum bias beam-beam interactions by mid 2007
Fully simulated samples of cosmic muons, beam-halo muons and beam gas events exist
R. McPherson et al.
Final commissioning phase will be with physics signals Essential for final tune-up Essential for showing we understand the detector behavior