DSWMA SOUTH LANDFILL FINAL COVER CONSTRUCTION
Engineering and Environmental Solutions, LLC Blaine Litteral
![Page 2: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/2.jpg)
CLOSURE OVERVIEW
§Final cover was completed in three phases. §Phase I of closure was completed in 1997 & 1998
closed 6.59 acres. §Phase II was completed in 2013 closing 11.05 acres. §Phase III was completed in 2016 closing the final 5.27
acres of the south landfill. §Active gas collection was installed in 3 phases in 1997,
2012 and 2016.
E & E Solutions, LLC
![Page 3: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/3.jpg)
South Landfill Map
E & E Solutions, LLC
![Page 4: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/4.jpg)
CLOSURE OVERVIEW
§Phase I included PVC cover FML over areas lined with single PVC liner. §Phase II and III included a composite cover system of
LLDPE FML and GCL materials over areas lined with a double composite liner system that included GCL, HDPE FML, and drainage composite components.
E & E Solutions, LLC
![Page 5: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/5.jpg)
SETTLEMENT ISSUES IN DESIGN §Observed significant
settlement of final cover between construction of each phase. §Required redesign of cover
grades resulting in loss of airspace. §Expect field adjustments at
the tie in to older cover areas.
E & E Solutions, LLC
![Page 6: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/6.jpg)
Adjustment between 2013 and 2016 final cover.
E & E Solutions, LLC
![Page 7: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/7.jpg)
LIMITTING AIRSPACE LOSS DUE TO SETTLEMENT §Use of temporary covers to
increase time before closure to allow refilling settled areas. §Avoid terminated closure
phase perpendicular to the slope and avoid closure boundary that runs across slope when possible.
E & E Solutions, LLC
![Page 8: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/8.jpg)
The flow from the secondary collection system began exceeding regulatory limits following construction of the second phase of final cover.
SECONDARY FLOW EXCEEDANCES
E & E Solutions, LLC
![Page 9: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/9.jpg)
INVESTIGATION OF SOURCES §Analytical testing showed
liquid was representative of storm water. § Investigation into the
source identified two suspected points of entry for the storm water.
E & E Solutions, LLC
![Page 10: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/10.jpg)
Leakage around leachate pump station and poor drainage combined with flaws in primary to secondary welds at site perimeter.
TWO CAUSES IDENTIFIED BY THE INVESTIGATION
E & E Solutions, LLC
![Page 11: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/11.jpg)
LEAKAGE AT PUMP HOUSE § It was discovered that
storm water was building up on top of the final cover/exposed primary liner. §Attachment of liner system
to pump house provided liquid entry to secondary.
E & E Solutions, LLC
![Page 12: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/12.jpg)
Primary liner connection at building corner.
E & E Solutions, LLC
![Page 13: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/13.jpg)
Leakage around leachate pump station was addressed by sealing apparent openings, installing a rain flap to direct storm water away from the building liner connection and providing additional drainage.
PUMP HOUSE LEAK CORRECTIVE ACTION
E & E Solutions, LLC
![Page 14: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/14.jpg)
PERIMETER ANCHOR TRENCH §Storm water was also found to
be building up within the perimeter anchor trench . § Flaws in the primary liner
within the trench were believed to be a source of water to the secondary collection system. §Road at perimeter of site
prevents drainage away from lined area.
E & E Solutions, LLC
![Page 15: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/15.jpg)
Recommended Cover - Primary -Secondary Liner connection at perimeter.
E & E Solutions, LLC
![Page 16: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/16.jpg)
A rain flap and toe drain was installed over the perimeter welds to prevent storm water from collecting over the perimeter anchor trench.
PREVENT STORM WATER ACCUMILATION IN THE COVER
E & E Solutions, LLC
![Page 17: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/17.jpg)
OTHER CONSIDERATIONS
§Pump houses should be set sufficiently away from liner system so liner does not need to be connected to the building. Standard side slope riser pumping system may be preferred. §Provide space between landfill liner system and
perimeter road to allow storm water to be drained away from landfill.
E & E Solutions, LLC
![Page 18: DSWMA 2016 FINAL COVER CONSTRUCTION - …...Final cover was completed in three phases. Phase I of closure was completed in 1997 & 1998 closed 6.59 acres. Phase II was completed in](https://reader033.fdocuments.in/reader033/viewer/2022050111/5f490c2af224251d6b6201ad/html5/thumbnails/18.jpg)
ANY QUESTIONS?
Blaine Litteral - 616.566.4609 [email protected] Engineering & Environmental Solutions, LLC www.goEESolutions.com