Drilled Shaft Design and Construction

download Drilled Shaft Design and Construction

of 51

description

Drill shaft

Transcript of Drilled Shaft Design and Construction

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 1 of 51

    DRILLED SHAFT CONSTRUCTION

    West Tower Arthur Ravenel Jr. Bridge

    Photograph courtesy of Marvin Tallent, Palmetto Bridge Constructors

    Concrete Mix DesignConsiderations

    Dry Construction Method Wet Construction Method Casing ConstructionMethod

    Equipment Inspection and Testing

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 2 of 51

    CONCRETE MIX DESIGN CONSIDERATIONSSCDOT 712.03 - Class 4000DS (see SCDOT 701)

    AggregateType

    Min. CementContent(lbs/CY)

    Min.28 day

    f'c(psi)

    % Fine toCoarse

    AggregateRatio

    Max. W/CRatio

    Crushed 625 4000 40:60 0.44Stone 625 4000 39:61 0.43

    Type G or Type D w/ Type F Admixture Required Slump: 7-9 inches Nominal Coarse Aggregate: inch

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 3 of 51

    CONCRETE MIX DESIGN CONSIDERATIONSMassDOT LRFD Design Manual (2009)

    Section 3.2.3.2 6. The minimum clearance between reinforcing bars shall be 1-

    78 and is equal to 5 times the maximum coarse aggregate size (38) for both, the longitudinal bars as well as the spiral confinement reinforcement, to allow for better concrete consolidation during placement. Concrete mix design and workability shall be consistent for tremie or pump placement. In particular, the concrete slump should be 8 inches 1 inch for tremie or slurry construction and 7 inches 1 inch for all other conditions.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 4 of 51

    CONCRETE MIX DESIGN CONSIDERATIONS

    Figure 1. Concrete Flow Under Tremie Placement (Brown and

    Schindler, 2007).

    Figure 3. Restriction of Lateral Flow (Brown and Schindler, 2007).

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 5 of 51

    CONCRETE MIX DESIGN CONSIDERATIONS

    Figure 9-1. Free Fall Concrete Placement in a Dry Excavation (FHWA NHI-10-016).

    Figure 5. Effects of Loss of Workability during Concrete

    Placement (Brown and Schindler, 2007).

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 6 of 51

    CONCRETE MIX DESIGN CONSIDERATIONS

    Self Consolidating Concrete (SSC) Project for SCDOT (S&ME 2005).

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 7 of 51

    DRY METHOD (SCDOT 712.07)

    Less than 6 inches of water per hour

    Sides and Bottom Remain Stable(Engineer can order 4 hours wait period)

    Loose material & water can be satisfactorily removed

    Temporary casing can be used

    Photograph courtesy of GPE Inc.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 8 of 51

    UnstableCavingSoils

    Water table

    CohesiveSoils

    Unstable caving soilsprevent maintaining

    hole stability

    StableNon-CavingSoils

    CohesiveSoils

    Stable non-cavingsoils maintainhole stability

    STABLE vs. UNSTABLE SOILS

    Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 9 of 51

    WATER TABLE AT OR BELOW THE SHAFT TIP ELEVATION

    Generally, soils cave at thewater table preventing

    hole stability

    Water table

    StableNon-Caving

    Soils

    CohesiveSoils

    Water table belowshaft tip does not

    impact hole stability

    Water table

    Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 10 of 51

    DRY METHOD CONSTRUCTION PROCESS

    PlacePositionClean &InspectDrill

    Drill the shaft excavationClean shaft by removing the cuttings & seepage water

    Position the reinforcing cagePlace the concrete

    Competent,Non-CavingSoils

    Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 11 of 51

    DRY METHOD CONSTRUCTION PROCESS

    DRILL(SCDOT 712.10)

    Continuous Operation. No delays > 12 hrs.

    No entering non-cased excavations.

    Photographs courtesy of WPC Inc.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 12 of 51

    CLEAN & INSPECT

    DRY METHOD CONSTRUCTION PROCESS

    Photographs courtesy of WPC Inc.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 13 of 51

    EXCAVATION CLEANLINESS(SCDOT 712.14D)

    INSPECTION OF EXCAVATION (SCDOT 712.14)

    50% of Base has < inch of sedimentAND

    Maximum depth of sediment < 1 inches

    Need SCDOT Qualified Inspectors

    DRY METHOD CONSTRUCTION PROCESS

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 14 of 51

    POSITION(SCDOT 712.16)

    Spacers needed for 5 inch min. annulus.

    Spacer interval < 10 ft.

    DRY METHOD CONSTRUCTION PROCESS

    Photographs courtesy of WPC Inc.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 15 of 51

    PLACE (SCDOT 712.17) ASAP after reinforcement placement. Must be completed in 2 hours (unless

    approved). Tremie preferred. Tremie ID > 6 x Max.

    Aggregate Size AND > 10 inches. Tremie Embedment > 10 ft. Concrete flow: Positive pressure and

    continuous.

    DRY METHOD CONSTRUCTION PROCESS

    Photograph courtesy of WPC Inc.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 16 of 51

    PLACE (SCDOT 712.17)

    Freefall > 75 ft not permitted.

    Freefall Max. Aggregate Size inch, 7-9 inch slump.

    Freefall still needs chute. Must have tremie onsite.

    SCDOT can always order tremie.

    DRY METHOD CONSTRUCTION PROCESS

    Photograph courtesy of WPC Inc.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 17 of 51

    Less than 6inin one hour = Dry

    More than 6inin one hour = Wet

    SCDOT 712.08

    WET METHOD CONSTRUCTION PROCESSUSE WHEN A DRY EXCAVATION CANNOT BE MAINTAINED

    Figure courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 18 of 51

    WHEN THE SIDES AND BOTTOM OF THE HOLE CANNOT REMAIN

    STABLE

    WET METHOD CONSTRUCTION PROCESS

    WHEN LOOSE MATERIAL AND WATER CANNOT BE

    SATISFACTORILY REMOVEDFigures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 19 of 51

    PlacePositionCleanDrill

    Drill the shaft excavation

    Clean shaft by removing the cuttings & seepage water

    Place the concreteStabilize

    Position the reinforcing cage

    Stabilize the hole (Plain water, slurry)

    WET METHOD CONSTRUCTION PROCESS

    Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 20 of 51

    There are two forms of wet shaft construction:

    Static Process

    Circulation Process

    WET METHOD CONSTRUCTION PROCESS

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 21 of 51

    Drill down to the piezometric level

    Slurry introduced

    Drilling Completed

    Cuttings are lifted from the hole

    Piezometric level

    Drill down toPiezometriclevel

    Temporary surfacecasing installed(optional)

    Piezometric level

    Slurry addedto hole

    Slurry

    Hole drilled tocompletiondepth withslurry

    Slurry

    Piezometric levelPiezometric level

    Hole cleanedof slurry &cuttings

    Slurry

    WET METHOD: STATIC PROCESS

    Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 22 of 51

    Hole is drilled

    Slurry level maintained at the ground surface

    Cuttings and sand, is circulated to the surface, where it is cleaned and reintroduced down the hole.

    Piezometric level

    Hole drilled tocompletiondepth withslurry levelmaintained atground level

    SlurryProcessor

    SlurryProcessor

    Temporary surfacecasing install (optional)

    Piezometric level

    Slurry, with sand& cuttings isre-circulated forprocessing and reintroduced intohole.

    SlurryProcessor

    SlurryProcessor

    Piezometric level

    Hole cleaned

    SlurryProcessor

    SlurryProcessor

    WET METHOD: CIRCULATION PROCESS

    Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 23 of 51

    SLURRY(SCDOT 712.12)

    WET METHOD CONSTRUCTION PROCESS

    Photographs courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 24 of 51

    Natural mineral clays

    Bentonite, attapulgite and sepiolite

    Bentonite is the most common

    Attapulgite and sepiolite are typically used insaltwater environments

    Must be hydrated

    WET METHOD CONSTRUCTION PROCESSTYPES OF SLURRY

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 25 of 51

    Best ApplicationMineral Polymer

    Cohesionless Cohesive &Argillaceous Rock

    Mixability Difficult - Must be Hydrated Easy

    Mix Water Sensitivity SaltwaterSensitive Yes/No

    "Caking" Ability Best OK

    Suspension Ability Best OK

    WET METHOD CONSTRUCTION PROCESSSLURRY COMPARISONS

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 26 of 51

    Control tests are used to maintain proper slurrycondition. Tests are conducted for:

    Density- the slurry weight

    Viscosity- flow: consistency

    pH- acidity: alkalinity

    Sand Content

    WET METHOD CONSTRUCTION PROCESSCONTROLLING SLURRY

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 27 of 51

    SCDOT 712.12 MINERAL SLURRY ACCEPTABLE RANGES

    Property(Units)

    ValueRange @Introduction

    ValueRange @Concreting

    Test Method

    Density (pcf) 64.3 69.1* 64.3 75.0 Density BalanceViscosity(sec/qt)

    28-45 28-45 Marsh Cone

    pH 8-11 8-11pH paperpH meter

    * Add 2 pcf in saltwater ** Sand

    WET METHOD CONSTRUCTION PROCESSCONTROLLING SLURRY

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 28 of 51

    Proper Dosage and Solids Content for Proper Flowability and Cake Properties

    Thorough Mixing / Adequate Time for Hydration (Bentonite / Polymers)

    Maintenance of Head in Borehole

    Maintenance of pH, Hardness, Salts

    Minimize Pressures from Tools

    WET METHOD CONSTRUCTION PROCESSCONTROLLING SLURRY FOR BOREHOLE STABILITY

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 29 of 51

    Fails to properly suspend and facilitate theremoval of sediments and cuttings

    Does not control caving

    Does not control swelling of soils

    Hinders slurry displacement during concreteplacement

    Leads to a dirty hole

    WET METHOD CONSTRUCTION PROCESSIMPROPER SLURRY CONTROL

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 30 of 51

    WET METHOD CONSTRUCTION PROCESSDIRTY HOLE

    Figures courtesy of FHWA IF-99-025 Drilled Shafts: Construction Procedures and Design Methods.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 31 of 51

    Poor Slurry Job Excellent Slurry Job

    WET METHOD CONSTRUCTION PROCESSSLURRY EXAMPLES

    Photographs courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 32 of 51

    Where an open hole cannot be maintained.

    Where soil or rockdeformation will occur.

    Where constructing shafts below the water table or caving overburden.

    SCDOT 712.09 & 712.11

    SCDOT Types: Construction (712.11B) & Temporary (712.11C)

    CASING CONSTRUCTION METHOD

    Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 33 of 51

    Smooth, clean, watertight, w/ample strength

    Oversized must be approved by SCDOT.

    Temporary: Fresh concrete > 5 ft above hydrostatic pressure.

    SCDOT 712.11

    Construction: Installed as one continuous unit.

    Welds are only approved connection.

    CASING CONSTRUCTION METHOD

    Photograph courtesy of WPC Inc.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 34 of 51

    1. The Designer shall consider the intended method of construction (temporary or permanent casing, slurry drilling, etc.) and the resulting impact on the stiffness and resistance of the shaft.

    4. When a drilled shaft is constructed with a permanent casing, the skin friction along the permanently cased portion of the shaft should be neglected.

    MassDOT LRFD Design Manual (2009)Section 3.2.3.2

    CASING CONSTRUCTION METHOD

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 35 of 51

    Not Permitted by SCDOT

    (see 712.11C)

    CASING CONSTRUCTION METHODTELESCOPING CASING

    Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 36 of 51

    CASING METHOD: CONSTRUCTION PROCESS

    PlacePositionCleanDrill

    Drill the shaft excavation

    Clean shaft by removing the cuttings & seepage water

    CasePosition the reinforcing cage

    Install casing through caving soils and seal

    Caving SoilsFigures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 37 of 51

    CASING CONSTRUCTION METHODCONSTRUCTION (a.k.a. PERMANENT) CASING EXAMPLES

    Figures courtesy of FHWA IF-99-025 Drilled Shafts: Construction Procedures and Design Methods.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 38 of 51

    CASING CONSTRUCTION METHODCONSTRUCTION (a.k.a. PERMANENT) CASING EXAMPLES

    Figures courtesy of FHWA IF-99-025 Drilled Shafts: Construction Procedures and Design Methods.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 39 of 51

    FULL-DEPTH CASING PROCESS

    Installation of Casing

    Competent Soil

    Caving Soil

    Competent Soil

    Casing

    VibratoryDriver

    Competent Soil

    Caving Soil

    Competent Soil

    Casing

    VibratoryDriver

    Water Table

    Installation of Casing

    Drilling ahead ofcasing

    Competent Soil

    Caving Soil

    Competent Soil

    Competent Soil

    Caving Soil

    Competent Soil

    Water Table

    Drilling ahead of casing

    Remove casing Competent Soil

    Caving Soil

    Competent Soil

    Casing

    VibratoryDriver

    Water Table

    Remove casing

    Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

    Figure 1. Concrete Flow Under Tremie Placement.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 40 of 51

    CASING CONSTRUCTION METHODTEMPORARY CASING REMOVAL

    (a) Prior to lifting casingFigure 9-4. Concrete Pressure Head Requirement during Casing Extraction

    (FHWA NHI-10-016).

    (b) As Casing is Lifted.

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 41 of 51

    DRILLED SHAFT EQUIPMENT TERMINOLOGY

    Kelly

    Table

    Crane

    Power Unit

    Tool

    Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 42 of 51

    Single Flight

    Double Flight

    Double Cut

    Triple Cut

    Earth augers are generallyused in sands and cohesive

    materials.

    DRILLED SHAFT EQUIPMENTEARTH AUGERS

    Photographs courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 43 of 51

    Tapered Geometry

    Rock augers are generally used in soft to

    hard rock formations.

    Conical (Bullet)Carbide Teeth

    DRILLED SHAFT EQUIPMENTROCK AUGERS

    Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 44 of 51

    This is typical of rock bits designed for drilling in hard to very hard rock.

    ReplaceableRoller Bits

    Circulating bit

    DRILLED SHAFT EQUIPMENTROCK BITS

    Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 45 of 51

    GougingTeeth

    RippingTeeth

    Side Cutting Teeth

    DRILLED SHAFT EQUIPMENTDRILLING BUCKET

    Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 46 of 51

    This is typical of a cleanout (muck) bucket used to

    cleanout the cuttings and sediments from

    the bottom of the shaft.

    6-51

    DRILLED SHAFT EQUIPMENTCLEANOUT (MUCK) BUCKET

    Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 47 of 51

    DEEP FOUNDATION DESIGNGEOMATERIAL PROPERTIES NEEDED

    Table 13-1. Geomaterial Properties Required for Drained and Undrained Axial Resistances (FHWA NHI-10-016).

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 48 of 51

    DEEP FOUNDATION DESIGNAXIAL CAPACITY

    Where:Qtotal = Ultimate Pile CapacityQskin = Skin Friction (i.e. Side) CapacityQtip = Tip (i.e. Toe) Capacity

    Qtotal = Qskin + Qtip

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 49 of 51

    Qskin = fsAskinWhere:

    fs = Unit Skin FrictionAskin = Pile Skin Area

    Qtoe = qpAtoeWhere:

    qp = Unit End BearingAtoe = Pile Toe (i.e. Tip) Area

    DEEP FOUNDATION DESIGNAXIAL CAPACITY

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 50 of 51

    DEEP FOUNDATION DESIGNGENERALIZED LOAD TRANSFER BEHAVIOR

    Figure 13-1(FHWA NHI-10-016).

    Qskin = RsQtoe = Rb

  • Revised 9/2012

    14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction

    Slide 51 of 51

    REFERENCES SCDOT Standard Specifications for Highway

    Construction (2000). SCDOT Foundation Certification Program Notes. FHWA IF-99-025 Drilled Shafts: Construction

    Procedures and Design Methods. FHWA NHI-10-016 Drilled Shafts: Construction

    Procedures and LRFD Design Methods NHI Course 132070 - Drilled Shaft Foundation

    Inspection.