Drilled Shaft Design and Construction
-
Upload
lingamkumar -
Category
Documents
-
view
21 -
download
0
description
Transcript of Drilled Shaft Design and Construction
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 1 of 51
DRILLED SHAFT CONSTRUCTION
West Tower Arthur Ravenel Jr. Bridge
Photograph courtesy of Marvin Tallent, Palmetto Bridge Constructors
Concrete Mix DesignConsiderations
Dry Construction Method Wet Construction Method Casing ConstructionMethod
Equipment Inspection and Testing
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 2 of 51
CONCRETE MIX DESIGN CONSIDERATIONSSCDOT 712.03 - Class 4000DS (see SCDOT 701)
AggregateType
Min. CementContent(lbs/CY)
Min.28 day
f'c(psi)
% Fine toCoarse
AggregateRatio
Max. W/CRatio
Crushed 625 4000 40:60 0.44Stone 625 4000 39:61 0.43
Type G or Type D w/ Type F Admixture Required Slump: 7-9 inches Nominal Coarse Aggregate: inch
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 3 of 51
CONCRETE MIX DESIGN CONSIDERATIONSMassDOT LRFD Design Manual (2009)
Section 3.2.3.2 6. The minimum clearance between reinforcing bars shall be 1-
78 and is equal to 5 times the maximum coarse aggregate size (38) for both, the longitudinal bars as well as the spiral confinement reinforcement, to allow for better concrete consolidation during placement. Concrete mix design and workability shall be consistent for tremie or pump placement. In particular, the concrete slump should be 8 inches 1 inch for tremie or slurry construction and 7 inches 1 inch for all other conditions.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 4 of 51
CONCRETE MIX DESIGN CONSIDERATIONS
Figure 1. Concrete Flow Under Tremie Placement (Brown and
Schindler, 2007).
Figure 3. Restriction of Lateral Flow (Brown and Schindler, 2007).
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 5 of 51
CONCRETE MIX DESIGN CONSIDERATIONS
Figure 9-1. Free Fall Concrete Placement in a Dry Excavation (FHWA NHI-10-016).
Figure 5. Effects of Loss of Workability during Concrete
Placement (Brown and Schindler, 2007).
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 6 of 51
CONCRETE MIX DESIGN CONSIDERATIONS
Self Consolidating Concrete (SSC) Project for SCDOT (S&ME 2005).
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 7 of 51
DRY METHOD (SCDOT 712.07)
Less than 6 inches of water per hour
Sides and Bottom Remain Stable(Engineer can order 4 hours wait period)
Loose material & water can be satisfactorily removed
Temporary casing can be used
Photograph courtesy of GPE Inc.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 8 of 51
UnstableCavingSoils
Water table
CohesiveSoils
Unstable caving soilsprevent maintaining
hole stability
StableNon-CavingSoils
CohesiveSoils
Stable non-cavingsoils maintainhole stability
STABLE vs. UNSTABLE SOILS
Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 9 of 51
WATER TABLE AT OR BELOW THE SHAFT TIP ELEVATION
Generally, soils cave at thewater table preventing
hole stability
Water table
StableNon-Caving
Soils
CohesiveSoils
Water table belowshaft tip does not
impact hole stability
Water table
Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 10 of 51
DRY METHOD CONSTRUCTION PROCESS
PlacePositionClean &InspectDrill
Drill the shaft excavationClean shaft by removing the cuttings & seepage water
Position the reinforcing cagePlace the concrete
Competent,Non-CavingSoils
Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 11 of 51
DRY METHOD CONSTRUCTION PROCESS
DRILL(SCDOT 712.10)
Continuous Operation. No delays > 12 hrs.
No entering non-cased excavations.
Photographs courtesy of WPC Inc.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 12 of 51
CLEAN & INSPECT
DRY METHOD CONSTRUCTION PROCESS
Photographs courtesy of WPC Inc.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 13 of 51
EXCAVATION CLEANLINESS(SCDOT 712.14D)
INSPECTION OF EXCAVATION (SCDOT 712.14)
50% of Base has < inch of sedimentAND
Maximum depth of sediment < 1 inches
Need SCDOT Qualified Inspectors
DRY METHOD CONSTRUCTION PROCESS
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 14 of 51
POSITION(SCDOT 712.16)
Spacers needed for 5 inch min. annulus.
Spacer interval < 10 ft.
DRY METHOD CONSTRUCTION PROCESS
Photographs courtesy of WPC Inc.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 15 of 51
PLACE (SCDOT 712.17) ASAP after reinforcement placement. Must be completed in 2 hours (unless
approved). Tremie preferred. Tremie ID > 6 x Max.
Aggregate Size AND > 10 inches. Tremie Embedment > 10 ft. Concrete flow: Positive pressure and
continuous.
DRY METHOD CONSTRUCTION PROCESS
Photograph courtesy of WPC Inc.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 16 of 51
PLACE (SCDOT 712.17)
Freefall > 75 ft not permitted.
Freefall Max. Aggregate Size inch, 7-9 inch slump.
Freefall still needs chute. Must have tremie onsite.
SCDOT can always order tremie.
DRY METHOD CONSTRUCTION PROCESS
Photograph courtesy of WPC Inc.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 17 of 51
Less than 6inin one hour = Dry
More than 6inin one hour = Wet
SCDOT 712.08
WET METHOD CONSTRUCTION PROCESSUSE WHEN A DRY EXCAVATION CANNOT BE MAINTAINED
Figure courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 18 of 51
WHEN THE SIDES AND BOTTOM OF THE HOLE CANNOT REMAIN
STABLE
WET METHOD CONSTRUCTION PROCESS
WHEN LOOSE MATERIAL AND WATER CANNOT BE
SATISFACTORILY REMOVEDFigures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 19 of 51
PlacePositionCleanDrill
Drill the shaft excavation
Clean shaft by removing the cuttings & seepage water
Place the concreteStabilize
Position the reinforcing cage
Stabilize the hole (Plain water, slurry)
WET METHOD CONSTRUCTION PROCESS
Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 20 of 51
There are two forms of wet shaft construction:
Static Process
Circulation Process
WET METHOD CONSTRUCTION PROCESS
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 21 of 51
Drill down to the piezometric level
Slurry introduced
Drilling Completed
Cuttings are lifted from the hole
Piezometric level
Drill down toPiezometriclevel
Temporary surfacecasing installed(optional)
Piezometric level
Slurry addedto hole
Slurry
Hole drilled tocompletiondepth withslurry
Slurry
Piezometric levelPiezometric level
Hole cleanedof slurry &cuttings
Slurry
WET METHOD: STATIC PROCESS
Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 22 of 51
Hole is drilled
Slurry level maintained at the ground surface
Cuttings and sand, is circulated to the surface, where it is cleaned and reintroduced down the hole.
Piezometric level
Hole drilled tocompletiondepth withslurry levelmaintained atground level
SlurryProcessor
SlurryProcessor
Temporary surfacecasing install (optional)
Piezometric level
Slurry, with sand& cuttings isre-circulated forprocessing and reintroduced intohole.
SlurryProcessor
SlurryProcessor
Piezometric level
Hole cleaned
SlurryProcessor
SlurryProcessor
WET METHOD: CIRCULATION PROCESS
Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 23 of 51
SLURRY(SCDOT 712.12)
WET METHOD CONSTRUCTION PROCESS
Photographs courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 24 of 51
Natural mineral clays
Bentonite, attapulgite and sepiolite
Bentonite is the most common
Attapulgite and sepiolite are typically used insaltwater environments
Must be hydrated
WET METHOD CONSTRUCTION PROCESSTYPES OF SLURRY
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 25 of 51
Best ApplicationMineral Polymer
Cohesionless Cohesive &Argillaceous Rock
Mixability Difficult - Must be Hydrated Easy
Mix Water Sensitivity SaltwaterSensitive Yes/No
"Caking" Ability Best OK
Suspension Ability Best OK
WET METHOD CONSTRUCTION PROCESSSLURRY COMPARISONS
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 26 of 51
Control tests are used to maintain proper slurrycondition. Tests are conducted for:
Density- the slurry weight
Viscosity- flow: consistency
pH- acidity: alkalinity
Sand Content
WET METHOD CONSTRUCTION PROCESSCONTROLLING SLURRY
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 27 of 51
SCDOT 712.12 MINERAL SLURRY ACCEPTABLE RANGES
Property(Units)
ValueRange @Introduction
ValueRange @Concreting
Test Method
Density (pcf) 64.3 69.1* 64.3 75.0 Density BalanceViscosity(sec/qt)
28-45 28-45 Marsh Cone
pH 8-11 8-11pH paperpH meter
* Add 2 pcf in saltwater ** Sand
WET METHOD CONSTRUCTION PROCESSCONTROLLING SLURRY
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 28 of 51
Proper Dosage and Solids Content for Proper Flowability and Cake Properties
Thorough Mixing / Adequate Time for Hydration (Bentonite / Polymers)
Maintenance of Head in Borehole
Maintenance of pH, Hardness, Salts
Minimize Pressures from Tools
WET METHOD CONSTRUCTION PROCESSCONTROLLING SLURRY FOR BOREHOLE STABILITY
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 29 of 51
Fails to properly suspend and facilitate theremoval of sediments and cuttings
Does not control caving
Does not control swelling of soils
Hinders slurry displacement during concreteplacement
Leads to a dirty hole
WET METHOD CONSTRUCTION PROCESSIMPROPER SLURRY CONTROL
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 30 of 51
WET METHOD CONSTRUCTION PROCESSDIRTY HOLE
Figures courtesy of FHWA IF-99-025 Drilled Shafts: Construction Procedures and Design Methods.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 31 of 51
Poor Slurry Job Excellent Slurry Job
WET METHOD CONSTRUCTION PROCESSSLURRY EXAMPLES
Photographs courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 32 of 51
Where an open hole cannot be maintained.
Where soil or rockdeformation will occur.
Where constructing shafts below the water table or caving overburden.
SCDOT 712.09 & 712.11
SCDOT Types: Construction (712.11B) & Temporary (712.11C)
CASING CONSTRUCTION METHOD
Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 33 of 51
Smooth, clean, watertight, w/ample strength
Oversized must be approved by SCDOT.
Temporary: Fresh concrete > 5 ft above hydrostatic pressure.
SCDOT 712.11
Construction: Installed as one continuous unit.
Welds are only approved connection.
CASING CONSTRUCTION METHOD
Photograph courtesy of WPC Inc.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 34 of 51
1. The Designer shall consider the intended method of construction (temporary or permanent casing, slurry drilling, etc.) and the resulting impact on the stiffness and resistance of the shaft.
4. When a drilled shaft is constructed with a permanent casing, the skin friction along the permanently cased portion of the shaft should be neglected.
MassDOT LRFD Design Manual (2009)Section 3.2.3.2
CASING CONSTRUCTION METHOD
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 35 of 51
Not Permitted by SCDOT
(see 712.11C)
CASING CONSTRUCTION METHODTELESCOPING CASING
Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 36 of 51
CASING METHOD: CONSTRUCTION PROCESS
PlacePositionCleanDrill
Drill the shaft excavation
Clean shaft by removing the cuttings & seepage water
CasePosition the reinforcing cage
Install casing through caving soils and seal
Caving SoilsFigures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 37 of 51
CASING CONSTRUCTION METHODCONSTRUCTION (a.k.a. PERMANENT) CASING EXAMPLES
Figures courtesy of FHWA IF-99-025 Drilled Shafts: Construction Procedures and Design Methods.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 38 of 51
CASING CONSTRUCTION METHODCONSTRUCTION (a.k.a. PERMANENT) CASING EXAMPLES
Figures courtesy of FHWA IF-99-025 Drilled Shafts: Construction Procedures and Design Methods.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 39 of 51
FULL-DEPTH CASING PROCESS
Installation of Casing
Competent Soil
Caving Soil
Competent Soil
Casing
VibratoryDriver
Competent Soil
Caving Soil
Competent Soil
Casing
VibratoryDriver
Water Table
Installation of Casing
Drilling ahead ofcasing
Competent Soil
Caving Soil
Competent Soil
Competent Soil
Caving Soil
Competent Soil
Water Table
Drilling ahead of casing
Remove casing Competent Soil
Caving Soil
Competent Soil
Casing
VibratoryDriver
Water Table
Remove casing
Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
Figure 1. Concrete Flow Under Tremie Placement.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 40 of 51
CASING CONSTRUCTION METHODTEMPORARY CASING REMOVAL
(a) Prior to lifting casingFigure 9-4. Concrete Pressure Head Requirement during Casing Extraction
(FHWA NHI-10-016).
(b) As Casing is Lifted.
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 41 of 51
DRILLED SHAFT EQUIPMENT TERMINOLOGY
Kelly
Table
Crane
Power Unit
Tool
Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 42 of 51
Single Flight
Double Flight
Double Cut
Triple Cut
Earth augers are generallyused in sands and cohesive
materials.
DRILLED SHAFT EQUIPMENTEARTH AUGERS
Photographs courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 43 of 51
Tapered Geometry
Rock augers are generally used in soft to
hard rock formations.
Conical (Bullet)Carbide Teeth
DRILLED SHAFT EQUIPMENTROCK AUGERS
Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 44 of 51
This is typical of rock bits designed for drilling in hard to very hard rock.
ReplaceableRoller Bits
Circulating bit
DRILLED SHAFT EQUIPMENTROCK BITS
Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 45 of 51
GougingTeeth
RippingTeeth
Side Cutting Teeth
DRILLED SHAFT EQUIPMENTDRILLING BUCKET
Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 46 of 51
This is typical of a cleanout (muck) bucket used to
cleanout the cuttings and sediments from
the bottom of the shaft.
6-51
DRILLED SHAFT EQUIPMENTCLEANOUT (MUCK) BUCKET
Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 47 of 51
DEEP FOUNDATION DESIGNGEOMATERIAL PROPERTIES NEEDED
Table 13-1. Geomaterial Properties Required for Drained and Undrained Axial Resistances (FHWA NHI-10-016).
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 48 of 51
DEEP FOUNDATION DESIGNAXIAL CAPACITY
Where:Qtotal = Ultimate Pile CapacityQskin = Skin Friction (i.e. Side) CapacityQtip = Tip (i.e. Toe) Capacity
Qtotal = Qskin + Qtip
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 49 of 51
Qskin = fsAskinWhere:
fs = Unit Skin FrictionAskin = Pile Skin Area
Qtoe = qpAtoeWhere:
qp = Unit End BearingAtoe = Pile Toe (i.e. Tip) Area
DEEP FOUNDATION DESIGNAXIAL CAPACITY
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 50 of 51
DEEP FOUNDATION DESIGNGENERALIZED LOAD TRANSFER BEHAVIOR
Figure 13-1(FHWA NHI-10-016).
Qskin = RsQtoe = Rb
-
Revised 9/2012
14.528 DRILLED DEEP FOUNDATIONSDrilled Shafts Design and Construction
Slide 51 of 51
REFERENCES SCDOT Standard Specifications for Highway
Construction (2000). SCDOT Foundation Certification Program Notes. FHWA IF-99-025 Drilled Shafts: Construction
Procedures and Design Methods. FHWA NHI-10-016 Drilled Shafts: Construction
Procedures and LRFD Design Methods NHI Course 132070 - Drilled Shaft Foundation
Inspection.