Team Transport & Logistics Safe Work Method Statements Booklet
Draft+Risk+Assessment+Method+Statements
-
Upload
tamilchelvam-murogayah -
Category
Documents
-
view
214 -
download
0
Transcript of Draft+Risk+Assessment+Method+Statements
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
1/11
Risk Assessment Method Statement Documents
April 2007
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
2/11
Safe Work Method Statement
Principal Contractor
PP Contract Services
82 Beveridge Way
Newton Aycliffe
Co. Durham
DL5 4LD
Telephone 08450 742950
Mobile 07814 009689
Plumbing / Electrical Sub-contractor details
??????????????????????????????
???????????????
????????????????
SAFETY NOTES
a) All PP Contract Services personnel will work within the Clients site safety
procedures.
b) All PP Contract Services personnel will wear the PPE safety equipment as
required for construction sites at all times.
c) Principal contractors representative and First aider on site ?????????? (Mob:)
d) All PP Contract Services personnel to be made aware of site regulations and
notices by Mr Alan Boyle site General Manager.
Work to be undertakenRemoval of steel cladded and block work wall in the works area.
Method Statement
1. Make the area safe with the provision and erection of portable fencing on both
sides of the wall. Also suitable and sufficient warning notices will be
displayed in the working area. (Risk Rating 1)
2. All electrical installation wiring and control boxes are to be made safe by a
qualified electrical contractor prior to the operation commencing (Risk Rating
4)
3. Work at height of up to 7 meters will be required during the removal operation
and this will be carried out from a suitable Sky Lift. This will be situated onfirm level ground in a safe area within the segregated work area. All personnel
using this equipment have been formally trained in its safe use and the Sky
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
3/11
4. Lift will be inspected prior to its use on a daily basis with these inspections
recorded. The lift will also have undergone the statutory inspections requiredwith the latest inspection report available on site at all times. Where necessary
fall arrest equipment will be provided and worn by PP Contract Services
personnel who have been trained in its safe use (Risk Rating 4)
5. Where possible bolts and fixings and block work will be removed using hand
tools. If this is not possible 110 volt tools will be used. There will be no 230
volt tools used by the main contractor whilst performing the removal
operation. (Risk Rating 2)
6. The steel cladding will be manually handled when removed and lowered down
in the Sky Lift once removed. Every possible safety measure will be
employed to prevent an item falling. No item will be allowed to fall at any
time during the demolition work. The steel cladding will be stacked and storedoutside the work area on a regular basis to allow for proper disposal by
CLIENTS staff. (Risk rating 3)
7. The block work debris from the lower part of the wall will be transferred to
another area of the site and used as in-fill for another project. Once transferred
to the other area the in-fill will be securely fenced to prevent CLIENTS
personnel from having access to the area. (Risk Rating 2)
8. Following removal of the wall all debris such as bolts and fixings are to be
cleared from the area portable fencing and tools belonging to PP Contract
Services personnel to be removed from the area and securely stored. (Risk
Rating 1)
Upon completion of the work a final inspection will be carried out by A. Boyle & PP
Contract Services and if satisfactory the area will then be returned to Clients
RISK RATING 5 Fatality
4 Major injury to several persons
3 Major injury to one person
2 Minor Injury
1 Trivial
All PP Contract Services staff to be acquainted with Clients Site Safety Procedures
and be provided with adequate site safety equipment. Specific Site Regulations to be
given to PP Contract Services personnel on attending site. Safety footwear, high
visibility clothing and head protection is to be worn at all times whilst on site
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
4/11
Safe Work Method Statement
Principal Contractor Details
PP Contract Services
82 Beveridge Way
Newton Aycliffe
Co. Durham
DL5 4LD
Telephone 08450 742950
Mobile 07814 009689
Electrical Sub-contractor details
??????????????????????????????
???????????????
????????????????
Gas Sub-contractor details
????????????????
??????????????
???????????????
????????????????
SAFETY NOTES
a) All PP Contract Services personnel will work within the Clients site safety
procedures.
b) All PP Contract Services personnel will wear the PPE safety equipment as
required for construction sites at all times.
c) Principal contractors representative and First aider on site ?????????? (Mob:)
d) All PP Contract Services personnel to be made aware of site regulations and
notices by Mr Alan Boyle site General Manager.
Work to be undertaken
Removal of steel cladded and block work and timber office in the works area to allow
fitting of new roller shutter door. Also removal of gas fired industrial heater and
repair of hole in the roof
Method Statement
1. Make the area safe with the provision and erection of portable fencing on bothsides of the work area (internally and externally). Also suitable and sufficient
warning notices will be displayed in the working area. (Risk Rating 1)
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
5/11
2. All electrical installation wiring and control boxes are to be made safe by a
qualified electrical contractor prior to the operation commencing (Risk Rating4)
3. All gas supply pipes and fittings to be disconnected and made safe by a
registered gas engineer prior to the operation commencing (Risk Rating 4)
4. Strip out front window and cladding. Work at height of up to 4 meters will be
required during the removal operation and this will be carried out from a
suitable Sky Lift. This will be situated on firm level ground in a safe area
within the segregated work area. All personnel using this equipment have been
formally trained in its safe use and the Sky Lift will be inspected prior to its
use on a daily basis with these inspections recorded. The lift will also have
undergone the statutory inspections required with the latest inspection report
available on site at all times. Where necessary fall arrest equipment will beprovided and worn by PP Contract Services personnel who have been trained
in its safe use (Risk Rating 4)
5. Strip out timber / plaster board office. The timber framed office will be
demolished using a 7 tonne tracked machine. The area will be cordoned off to
prevent access and the building demolished. The debris will then be
transferred to a suitable waste receptacle and disposed of by a reputable waste
disposal contractor (Risk Rating 2)
6. Remove gas fired industrial heater using vehicle mounted lifting equipment
and slings and deposit on the rear of the large goods vehicle to allow disposal
of the heater. All employees tasked with attaching slings will do so from the
operating area of the Sky Lift. No ladders will be used during this operation.
Where possible the heater fixing rods will be removed by hand but where this
is not possible they will be removed using a steel hack saw. During this
operation it may be necessary to use a petrol stihl saw. If this is the case the
petrol oil fuel will be stored in an area away from the main operation and
during operation of this equipment the following PPE will be worn at all times
face mask, goggles, gloves, boots and flameproof trousers. If necessary a fire
watcher will be designated to ensure that the operation does not cause a fire in
the work area and surrounding areas. This operation will only be carried out
when the weight of the heater has been taken by the slings and the vehicle
mounted crane used in the removal operation. The gas fired heater has beensold and will be transported directly to the purchasers site removing the need
for safe storage. Personnel used in this operation will be familiar with the
equipment being used and trained in its safe operation. (Risk rating 3)
7. Once removed the industrial gas heater will leave a hole in the roof
approximately 12 inches in diameter in the roof which will need to be made
good. The roofing material at the site is believed to be asbestos cement and
special care much be taken to ensure that the roofing material is not moved
excessively or broken. Work at height of up to 7 meters will be required
during the removal operation and this will be carried out from a suitable Sky
Lift. This will be situated on firm level ground in a safe area within the
segregated work area. All personnel using this equipment have been formallytrained in its safe use and the Sky Lift will be inspected prior to its use on a
daily basis with these inspections recorded. The lift will also have undergone
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
6/11
the statutory inspections required with the latest inspection report available on
site at all times. Where necessary fall arrest equipment will be provided andworn by PP Contract Services personnel who have been trained in its safe use
(Risk Rating 4)
8. The area where the cladding has been removed will be made good to allow the
installation of a new roller shutter door. During this operation it may be
necessary to use a petrol stihl saw. If this is the case the petrol oil fuel will be
stored in an area away from the main operation and during operation of this
equipment the following PPE will be worn at all times face mask, goggles,
gloves, boots and flameproof trousers. If necessary a fire watcher will be
designated to ensure that the operation does not cause a fire in the work area
and surrounding areas. All work involved in mounting the fixing points for theroller shutter door will be carried out from the Sky Lift and again no ladders
will be used in this operation. The shutter door will be lifted into place again
using vehicle mounted lifting equipment and slings. Personnel used in this
operation will be familiar with the equipment being used and trained in its safe
operation. (Risk rating 3)
9. All electrical connections relating to the new roller shutter door will be
connected by a qualified electrical contractor and checked to ensure correct
operation (Risk rating 3)
10. Following removal of all debris such as bolts and fixings are to be cleared
from the area portable fencing and tools belonging to PP Contract Services
personnel to be removed from the area and securely stored. (Risk Rating 1)
Should the operation take longer than one working day the site must not be left
unattended unless it has been adequately secured against intruders and all equipment
and machinery used in PP Contract Services operations has been isolated to prevent
use by unauthorised visitors to the site.
Upon completion of the work a final inspection will be carried out by A. Boyle & PP
Contract Services and if satisfactory the area will then be returned to Clients
RISK RATING 5 Fatality4 Major injury to several persons
3 Major injury to one person
2 Minor Injury
1 Trivial
All PP Contract Services staff to be acquainted with Clients Site Safety Procedures
and be provided with adequate site safety equipment. Specific Site Regulations to be
given to PP Contract Services personnel on attending site. Safety footwear, high
visibility clothing and head protection is to be worn at all times whilst on site
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
7/11
Safe Work Method Statement
Principal Contractor
PP Contract Services
82 Beveridge Way
Newton Aycliffe
Co. Durham
DL5 4LD
Telephone 08450 742950
Mobile 07814 009689
SAFETY NOTES
a) All PP Contract Services personnel will work within the Clients site safety
procedures.
b) All PP Contract Services personnel will wear the PPE safety equipment as
required for construction sites at all times.
c) Principal contractors representative and First aider on site ?????????? (Mob:)
d) All PP Contract Services personnel to be made aware of site regulations and
notices by Mr Alan Boyle site General Manager.
Work to be undertaken
Disassemble modify and move steel racks within the works area and re-root main
water pipe.
Method Statement
1. Make the area safe with the provision and erection of portable fencing on both
sides of the wall. Also suitable and sufficient warning notices will be
displayed in the working area. (Risk Rating 1)
2. Work at height of up to 4 meters will be required during the removal operationand this will be carried out from a suitable Sky Lift. This will be situated on
firm level ground in a safe area within the segregated work area. All personnel
using this equipment have been formally trained in its safe use and the Sky
Lift will be inspected prior to its use on a daily basis with these inspections
recorded. The lift will also have undergone the statutory inspections required
with the latest inspection report available on site at all times. Where necessary
fall arrest equipment will be provided and worn by PP Contract Services
personnel who have been trained in its safe use (Risk Rating 4)
3. The securing bolts and bracing spars will be removed from the racking and it
will be slung using vehicle mounted lifting equipment and slings. The racking
will be laid down to allow he modifications to be carried out prior to itrelocation in another area of the works. All employees tasked with attaching
slings will do so from the operating area of the Sky Lift. No ladders will be
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
8/11
used during this operation. Personnel used in this operation will be familiar
with the equipment being used and trained in its safe operation. (Risk rating3)
4. During the modification operation it will be necessary to use a petrol stihl saw.
The petrol oil fuel will be stored in an area away from the main operation and
during operation of this equipment the following PPE will be worn at all times
face mask, goggles, gloves, boots and flameproof trousers. A fire watcher will
be designated to ensure that the operation does not cause a fire in the work
area and surrounding areas.
5. Once modified the racking will be reassembled in another area of the works.
There is a possibility of the racking becoming unstable prior to it being
securely fixed in its new location and special care must be taken by anyone in
the area where the racks are to be located6. The main water pipe is to be relocated to an area where it is protected from
potential damage from the equipment CLIENTS operate on site. It is also to be
located away from any electrical installations and wiring.
Should the operation take longer than one working day the site must not be left
unattended unless it has been adequately secured against intruders and all equipment
and machinery used in PP Contract Services operations has been isolated to prevent
use by unauthorised visitors to the site.
Upon completion of the work a final inspection will be carried out by A. Boyle & PP
Contract Services and if satisfactory the area will then be returned to Clients
RISK RATING 5 Fatality
4 Major injury to several persons
3 Major injury to one person
2 Minor Injury
1 Trivial
All PP Contract Services staff to be acquainted with Clients Site Safety Procedures
and be provided with adequate site safety equipment. Specific Site Regulations to begiven to PP Contract Services personnel on attending site. Safety footwear, high
visibility clothing and head protection is to be worn at all times whilst on site
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
9/11
Safe Work Method Statement
Principal Contractor
PP Contract Services
82 Beveridge Way
Newton Aycliffe
Co. Durham
DL5 4LD
Telephone 08450 742950
Mobile 07814 009689
Electrical Sub-contractor details????????????????
??????????????
???????????????
????????????????
SAFETY NOTES
a) All PP Contract Services personnel will work within the Clients site safety
procedures.
b) All PP Contract Services personnel will wear the PPE safety equipment as
required for construction sites at all times.
c) Principal contractors representative and First aider on site ????????? (Mob:)
d) All PP Contract Services personnel to be made aware of site regulations and
notices by Mr Alan Boyle site General Manager.
Work to be undertaken
Remove 6 post sockets from the area. Also remove all foreign cables or potential
obstructions. Shutter off area and fill with approximately 148 tonnes of in fill andapply mesh and concrete with approximately 21.4 cubic meters of concrete. Power
float if necessary.
Method Statement
1. Make the area safe with the provision and erection of portable fencing on both
sides of the wall. Also suitable and sufficient warning notices will be
displayed in the working area. (Risk Rating 1)
2. All electrical installation wiring and control boxes are to be removed by a
qualified electrical contractor prior to the operation commencing (Risk Rating
4)
3. Ensure safe traffic routes are designated and clearly identified to ensuresuitable segregation between vehicles delivering the concrete and in-fill and
human visitors to the site (Risk Rating 1)
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
10/11
4. A 7 tonne tracked machine with attached concrete pecker will be used to allowthe removal of the 6 post sockets. When this equipment is being used it will be
noisy in the surrounding areas so hearing protection must be worn by anyone
in close proximity to the operation. There is also the potential of high velocity
particles being ejected from the work area any one in close proximity should
wear eye protection and all non essential operatives should be moved from the
area.. The equipment can only be operated by trained and authorised members
of PP Contract Services personnel and must be securely isolated at all times
when not in use. (Risk Rating 3)
5. Once the area has been suitably prepared concrete shuttering will be installed
to allow the void to be filled with approximately 148 tonnes of in-fill material.
This material will be deposited as close to the work area as possible and thentransferred to the void using the 7 tonne tracked vehicle. Any delivery vehicle
on site must be strictly controlled and must not be allowed to reverse on site
or deposit all or part of a load unless under the direct supervision of a member
of PP Contract Services personnel who will act as a banks man. Reinforcing
mesh will be put in at various levels throughout the void to ensure a sound
construction f the finished floor area. This will be lifted either manually or by
the 7 tonne tracked vehicle and suitable slings. When the in-fill reaches an
adequate depth it will be rolled using a 1.25 H/D roller. If this is the case the
petrol oil fuel will be stored in an area away from the main operation. The use
of the roller or striker will ensure that there are no unseen weaknesses or
voiClients in the finished concreted area. A striker plate may be used instead
of the roller which again has the potential to operate at a high noise level all
operatives will wear suitable personal protective equipment. (Risk Rating 3)
6. Once the void has been filed and adequately prepared approximately 21.4
cubic meters of liquid concrete will be used to completely fill the void. When
this has been done a hydraulic poker will be used to vibrate any air pockets
within the concrete to the surface ensuring a good quality construction and
finish to the new floor area. The area will be fenced off to prevent access at all
times during the curing period. (Risk Rating 1)
7. Following a minimum 10 day curing period the shuttering will be removed
using the 7 tonne tracked vehicle and manual handling with any defectsidentified in the new flooring area dressed and made good. . (Risk Rating 1)
As the operation will take longer than one working day the site must not be left
unattended unless it has been adequately secured against intruders and all equipment
and machinery used in PP Contract Services operations has been isolated to prevent
use by unauthorised visitors to the site.
-
7/28/2019 Draft+Risk+Assessment+Method+Statements
11/11
Upon completion of the work a final inspection will be carried out by A. Boyle & PPContract Services and if satisfactory the area will then be returned to Clients
RISK RATING 5 Fatality
4 Major injury to several persons
3 Major injury to one person
2 Minor Injury
1 Trivial
All PP Contract Services staff to be acquainted with Clients Site Safety Procedures
and be provided with adequate site safety equipment. Specific Site Regulations to begiven to PP Contract Services personnel on attending site. Safety footwear, high
visibility clothing and head protection is to be worn at all times whilst on site